SlideShare a Scribd company logo
1 of 16
Download to read offline
30 St Mary Axe, London
                                Norman Foster




Assignment 2: Construction and

Management Plan

Course: Construction Technology 4

ARBE4100

Prepared by: Alyssa Turner

Student Number: 3037715

Lecturer: Marcus Jefferies

Date: Friday 5th June

                                          1|Page
Executive Summary
The aim of this report is to analyse the technical and management issues associated with
the construction of a high rise building. The report takes a case study approach in regards to
Fosters and Normans’ St Mary Axe and how a similar building could be constructed in
Newcastle CBD.

The report will outline issues such as building services within the high rise structure,
specifications for the cladding system in regards to legal documents, legal issues and the
how they comply with the BCA and Procurement Methods.

This report follows on from Assignment 1 of the structural and cost analysis of a high rise
building in the Newcastle CBD area. The report also takes 30 St Mary Axe as a case study
building and investigates the construction and management techniques in the high rise
building.




                                                                                    2|Page
Contents
1. Introduction                                           Page 4

2. Building Services                                      Page 5
        2.1 Service Details                               Page 5
        2.1.1 Ventilation                                 Page 5
        2.1.2 Plumbing                                    Page 6
        2.1.3 Lighting System                             Page 6
        2.1.4 Electric Supply                             Page 7
        2.1.5 Air Conditioning                            Page 7
        2.1.6 Lift System                                 Page 7

3. External Cladding System                               Page 8
        3.1 Overview of the Facade                        Page 8

4. Specification of the Cladding System                   Page 9
       4.1 Building Description                           Page 9
       4.1.1 Design Life                                  Page 10
       4.1.2 Structural Capability                        Page 10
       4.1.3 Water Penetration                            Page 10
       4.1.4 Acoustic Performance                         Page 10
       4.1.5 Fire/Smoke Separation                        Page 11
       4.1.6 Glazing                                      Page 11

5. Legal Issues                                           Page 11
        5.1 Requirements for BCA                          Page 11
        5.1.1 Type of Construction Required               Page 12
        5.1.2 General Floor Area and Volume Limitations   Page 12
        5.1.3 Separation by Fire Wall                     Page 12
        5.1.4 Separation of Lift Shaft                    Page 12
        5.1.5 Number of Lift Shafts                       Page 13
        5.2 Fire Regulations                              Page 13
        5.2.1 When Fire Isolated exits are Required       Page 13
        5.2.2 Sprinklers                                  Page 13
        5.2.3 Fire Control Centre                         Page 13

Conclusion                                                Page 14

Resources                                                 Page 15

Appendix                                                  Page 16



                                                                    3|Page
1. Introduction
“30 St Mary Axe, better known as the Gherkin because is floor plan resembled a sliced
pickle, is located in the heart of London’s insurance district. It was originally the site of the
Baltic Exchange since 1903 but was obliterated in April 1992 by the IRA. The site went
under many discussions on what was to be done with it including restoring the Baltic
Exchange and the proposal of an 84 storey Millennium Tower. In 1997 insurance giants
Swiss Re acquired the site and commissioned Foster and Partners to design the building.

London’s first environmentally sustainable tall building stands 180m high and consists of 40
storeys. The building consumes about half the energy of most skyscrapers this size. The
building gradually widens at each floor plan until it reaches the 16 th where it then diminishes
until it reaches its apex. This distinctive form responds to the constraints of the site: the
building appears more slender than a rectangular block of equivalent size; reflections are
reduced and transparency is improved; (Foster+Parnters.com). The sliming of the building at
ground floor maximises the public space at ground level. It helps maintain pedestrian
comfort at street level as the profile reduces the amount of wind deflected to the ground
compared with a rectilinear tower of similar size.” (Turner, 2009)

                                                                                        4|Page
2. Building Services
This section provides a detailed study of the service in St Mary Axe, providing an example of
how services could be integrated into a high rise building in Newcastle CBD.

2.1 Service Details
St Mary Axe building utilities are located around a circular central core (London
Architecture). This allows for uninterrupted floor space for tenants and the ability to
maximise daylight from every side of the building.


Fire Lift

Passenger Lift                                                              Service Riser

Toilets                                                                     Stairs

Fire Lift                                                                   Good Lift

                                                                            Space for Higher Level Lifts

                                                                            Electrical and Data Cable Duct

                                                                            Stairs

                                                                            Service Duct (water, sewer, waste)




                 Fig 2.1 Level 18 floor plan – Services shown in blue (Fedun)

2.1.1 Ventilation
30 St Mary Axe is designed to
maximise daylight and natural
ventilation so that it uses half the
energy typically required by an
office block (Glass Works). Gaps in
each floor create six shafts that
serve as a natural ventilation
system for the entire building
(Wikipedia). A double glazing
effect, which insulates the office
space inside is caused by air being
sandwiched between two layers
of glazing. These shafts pull warm      Fig 2.1.1 Image showing atrium which allows ventilation
                                        throughout the levels (Perfect Buildings)
                                                                                            5|Page
air out of the building during the summer and warm the building in the winter using passive
solar gain. Blinds located within the cavity of the ventilated double skin facade intercept
solar gain before it enters the office environment; intercepted heat can then be reclaimed
or rejected depending on the requirement for heating or cooling (Swiss Re). The ventilation
system is decentralised which enables occupants to supply and control mechanical
ventilation on a floor by floor basis.

Windows in the facade of the wedges, which open automatically, allow for fresh air to be
drawn into the building. As a result the building uses 50% less energy that a typical prestige
air-conditioned office building (Swiss Re).

2.1.2 Plumbing
The building uses an electric heat-tracing system which provides “energy-efficient hot water
temperature maintenance, frost protection and snow melting” (Process Heat).

Over 1000 metres of Raychem HWAT-M self-regulation heating cable has been installed.
This particular type of electric heat tracing system provides instant hot water throughout
the building without any re-circulation plumbing. This allows for “greater energy efficiency,
lower maintenance and significant installation time/cost savings over traditional re-
circulation systems (Process Heat).

2.1.3 Lighting System




 Fig 2.1.3 Image showing light              Fig 2.1.3i Model showing the
 penetration into the building (Perfect     twisting floor plates with cut outs
 Building)                                  (Munro)


The lightwells allow daylight to penetrate the building to a further distance inside the
building then they would have had the floor gone all the way to the perimeter, helping to
improve the internal environment. Although these lightwells reduce the need for artificial
lighting some is still required.

The building has also been equipped with motion and light level sensors to prevent
unnecessary lighting (Glass Works).




                                                                                     6|Page
2.1.4 Electrical Supply
The building uses primary fuel is gas as it is one of the cleanest available.

2.1.5 Air Conditioning
Air conditioning system consists of “assumed 4 – pipe fan coil system in conjunction with
ventilated facade” and “closed circuit evaporative cooling towers” for heat rejection (Great
Buildings Online).

2.1.6 Lift System
St Mary Axe consists of 23 lifts including; 16 passenger lifts (6 high rise, 5 mid rise and 5 low
rise) 2 good lifts, 2 fire fighters lifts, 2 shuttle lifts for the top floor and 1 car park lift. The
lifts can carry a maximum of 378 people at any one time reaching speeds of 6 metres a
second.

Majority of buildings will have
extensive lift equipment on the
roof of the building. However
seen as a bard had been planned
for the 40th floor this was not
possible. The architects dealt with
this by having the main lift only
reach the 34th floor, and then
having a push-from-below lift to
the 39th floor (Wikipedia, 2009).




                                          Fig 2.1.6 Elevators (Fedun)




                                                                                           7|Page
3. External Cladding System
3.1 Overview of the Facade
The building’s exterior cladding systems consists of full glazed, double-skinned facade
comprising approximately of 5,500 flat triangular and diamond shaped glass
panels.(Profinder). These metal and glass prefabricated panels are fixed to the diagrid.




Fig 3.1 Cladding under construction (Munro)

The elements of the facade consist of:
    Operable glass screen
    Perforated aluminium louvers (internal sun-screen)
    A column casing of aluminium
    Facade frame of extruded aluminium

The glazing to the office areas consist of a double-glazed outer layer and a single-glazed
inner screen. Sandwiched in between is a central ventilated cavity which reduces heating
and cooling requirements. Its performance can be turned to maximise benefits that the
prevailing internal and external environment might have to offer. The solar-control blinds
intercept solar gain before it enters the office environment.




                                                                                    8|Page
Double glazed aluminium framed facade



                          Ventilated cavity



 Internal sunscreen of perforated louvers



                              Inner screen


                                                    Fig 3.2 Section of the Facade (Munro)


The glazing in the lightwells consist of double-glazed panels which can be opened to allow
fresh air in, while solar gain is effectively reduced through the use of grey-tinted glass with a
high performance coating.

Despite the overall curvilinear shape of the building there is only one piece of curved glass
which is the lens at the top of the building.




   4. Specification for the Cladding
   System
The following section details the specification of the cladding system if 30 St Mary axe was
to be built in Newcastle CBD paying particular attention to Australian Standards.

4.1 Building Description
30 St Mary Axe consists of a circular plan that widens as it rises from the ground and then
tapers towards its apex. A typical floor plan has a six-leafed plan around a circular service
core with triangle shaped voids acting as light wells. The cladding consists of a “double-skin
energy efficient facade made of glass, with aluminium profiles and a steel frame” (Case
Study Landmark building). 24,000 square metres of glass arranged in diamond-shaped panes
is used to clad the building.




                                                                                       9|Page
4.1.1 Design Life
The external cladding is to be designed and constructed to withstand the severe exposure
for a realistic tine period. The external cladding system is to be designed to meet BCA
performance provisions listed in BCA Volume 2 – BCA 2007, Section P2.1 Structural stability
and resistance to actions

The external cladding should have a minimum of:

       - 30 year serviceable life, within reasonable schedule maintenance

       - 50 year design life for structural integrity, this is inclusive of brackets, framings and
       fixings

4.1.2 Structural Capability
AS 1170.0:2002 Structural Design Actions – General Principles refers to loads in which the
building must be able to withstand from. These include loads either generated from the
structure or from the environment.

Dead Loads – are the loads generated from the building itself. Refer to AS 1170.1:2002
Structural Design Actions – Earthquake actions in Australia.

Wind Loads – Due to the shape of the building vortices, which can generate strong gusts at
the base of the building, have been reduced. The shape also helps deflect string winds
around the building therefore causing less stress on the external cladding. The design for
wind loads should meet AS 1170.2:2002 Structural Design Actions – Wind Actions.

Earthquake loads – In 1989 an earthquake hitting Newcastle, reaching 5.5 on the Richter
scale, destroyed and damaged many buildings. As Newcastle is located in an area which can
suffer from earth disturbance the building is to be designed to meet AS 1170.4:2007
Structural Design Actions – Earthquake actions in Australia.

Ground Water – Due to Newcastle’s CBD location being only a few meters above sea level
precautions are to be taken in regards to flooding. The building shall be designed to meet AS
1170.1:2002 Structural Design Actions – Permanent, imposed & other actions.

4.1.3 Water Penetration
The external cladding system is to be designed to resist water penetration from heavy rain,
windy conditions and during window cleaning. The cladding standards are to meet AS
4420.5:1996 Windows – Methods to test. Water penetration resistance test.

4.1.4 Acoustic Performance
The external cladding is required to protect the occupants from external noises entering the
building and to help maintain a good acoustic atmosphere internally. The acoustic
performance design is to me AS 1055.1-1997 Acoustic – Description and Measurements of
Environmental Noise – General Procedures.


                                                                                      10 | P a g e
4.1.5 Fire/Smoke Separation
With relation to fire separation inside the building there are various issues which need to be
addressed. Fire/Smoke Separation regulations are to meet AS 4284: 1995 Testing of Building
Facades as well as BCA Parts C2 Compartmentation and Separation, C2.6 Vertical separation
of openings in external walls and C3 Protection of Openings.

4.1.6 Glazing
Majority of the cladding system of St Mary Axe consists of glazing. Glazing to the first 38
levels of the building are to be aluminium framed, while the domed structure on the top is
to be frameless glass.

The glass used for the external cladding is to be produced and installed with good
characterises in subject to wind loading, human impact, safety, security and the UV
elimination.

Glazing to be used for the cladding is SolarplusR Low E Twin-Glaze unit by G.James. It is
chosen for its superior thermal performance. Glass is to be clear in colour and grey glass for
the atrium and dome.

Glazing is to meet the following standards:

AS 1170.4:1993 Minimum design loads on structures – Earthquake loads

AS 1288 Glass in buildings – Selection and Installation

AS 2047 – 1999 Windows in buildings – Selection and Installation

As 4420.0 – 1996 Windows – Methods of test – General introduction and list of methods

AS/NZS 1170.1:2002 Structural Design Actions – Permanent, imposed and other actions

AS/NZS 1170.2:2002 Structural Design Actions – Wind actions

ISO 9000 Quality management and quality assurance standards




   5. Legal Issues
5.1 Requirement for BCA
Buildings within Australia must be built in accordance with regulations as set out in the BCA.
In the following section a case study approach has been taken in regards to requirements of
the BCA in the case of Foster and Partners 30 St Mary Axe building.




                                                                                   11 | P a g e
5.1.1 Type of Construction Required
Part C1.1 of the BCA sets the minimum type of fire resisting construction. The Case study
building (and any high rise building to be built in Newcastle) has 4 or more rises in a class 5
therefore the type of construction is A.

5.1.2 General Floor Area & Volume Limitations
Part C2.2 of the BCA states that the fire compartment or atrium must not exceed
8000m2/48000m2, unless sprinkled with a smoke exhaust system. See section 6.2.2 for
details.

5.1.3 Separation by Fire Wall
Part C2.7 of the BCA states that fire walls must be constructed so that they meet the
specified levels of fire protection.

5.1.4 Separation of Lift Shaft
Part C2.10 of the BCA requires lift shafts to be separated from the building and in an
enclosed shaft. All emergency lifts must be contained within a fire-resisting shaft having a
FRL of no less then 120/120/120. The floor plan below highlights the service lifts indicating
that there are masonry walls constructed around the lift shaft. Therefore complies with BCA
requirements.


                                                        Image indicating lift shafts with a
                                                        masonry wall




5.1.5 Number of Lift Shafts
Part D1.2 of the BCA requires buildings over the height of 25 metres to require at least two
exists from each story. As indicated in the above image St Mary Axe has the required
minimum number of fire exits provided for each level and therefore complies with BCA
requirements.

                                                                                       12 | P a g e
5.2 Fire Regulations
The spiral lightwell arrangement allows for a fire
escape strategy based on a variation of phased
evacuation. The building is divided into fire safety
zones at every sixth then second floor. This allows
for the evacuation of one area at a time as opposed
to the whole building at once. A system of smoke
curtains form smoke reservoirs in the lightwells.
Natural ventilation is used for smoke clearance for
the lightwells. (Mace) This eliminated the spread of
smoke through the lightwells from lower floors.

5.2.1 When Fire-isolated Exits are
required
Part D1.1 of the BCA requires every ‘required’ fire
exit to be fire isolated. As shown in figure fire stairs
appear to be constructed from masonry to comply
with BCA standards.
                                                           Fig 5.2 Division of building into fire
5.2.2 Sprinklers                                           compartments

Part E1.5 of the BCA requires sprinklers to be installed in a building which has a height of
more then25 metres. In the case study of St Mary Axe a sprinkler system has been used.
Lightwell based floors are protected by sprinklers on the overhanging soffits above (Mace).
The sprinkler system also includes an array of window sprinklers on levels 2 and 3. However
there is no sprinkler system in the dome. These were omitted on aesthetic and practical
grounds. “Instead the mechanical ventilation system needed for environmental purposes
has been upgraded to serve as a temperature and smoke control system” (Mace).

5.2.3 Fire Control Centre
Part E1.8 of the BCA states that buildings over a height of 25 metres, requires a fire control
centre facility. The installed fire alarm system includes “automatic smoke/heat detection,
manual call points, sprinkler flow switch activation, auto dial-up facility to London fire
brigade, two-way fire fighter’s system and a central fire command centre” (Great Buildings
Online).




                                                                                        13 | P a g e
Conclusion
This report has investigated the technical and management issues associated with the
construction of a high rise building taking a case study approach with Forster and Partners’
30 St Mary Axe building in London, UK.

As demonstrated in this example, the design and construction of a high rise building is very
complex and involved process. In regards to the Vision 2020 and Newcastle City Centre LED
2008, 30 St Mary Axe could realistic meet these requirements.

As we move towards design buildings which are more environmentally friendly we are able
to take the example of 30 St Mary axe and design a building which can meet the
requirements of the clients without compromising the environment.




                                                                                  14 | P a g e
Resources
Munro, Dominic; “Swiss Re’s Building, London” retrieved 04/04/09
http://www.sbi.se/uploaded/dokument/files/Art_Swiss%20Re%C2%B4s%20Building,%20Lo
ndon.pdf

Buchanan, Peter; “The Tower, An Anachronism Awaiting Rebirth?” retrieved 04/04/09
http://www.gsd.harvard.edu/research/publications/hdm/back/26_Buchanan.pdf

Emporis.com; “30 St Mary Axe” retrieved 10/04/09

Architecture Week.com; “Swiss Re Tower by Foster & Partners” retrieved 06/04/09

Freiberger, Marianne; “Perfect buildings: the maths of modern architecture” retrieved
04/04/09

Swiss Re; “Sustainability at 30 St Mary Axe” retrieved 06/04/09

Absolute Astronomy; “30 St Mary Axe” retrieved 06/04/09

MRMCA; “Case Study 001 – 30 St Mary Axe, London” retrieved 06/04/09 www.rlsd.com

The Institution of Structural Engineers; “30 St Mary Axe, London” retrieved 10/04/09

ICON Magazine Online; “30 St Mary Axe” (September 2004) retrieved 10/04/09

Processheat; “Case Study: 30 St Mary Axe (Swiss Re Building)” (2007) retrieved 23/06/09
http://www.processheat.ltd.uk/clients/case-study1.html

Fedun, Bill; “30 St Mary Axe” retrieved 20/05/09

www.hilsommoran.com; “Spotlight Projects – 30 St Mary Axe” retrieved 20/05/2009

Building Code of Australia “Class 2 to 9 Buildings – Volume One/Two” (2008)

www.londonarchitecture.co.uk; “30 St Mary Axe” retrieved 12/06/2009

www.wikepedia.com; “30 St Mary Axe” retrieved 12/06/2009




                                                                                15 | P a g e
Appendix
The following has been taken from Dominic Munro’s report titled Swiss Re’s Building,
London
Height to top of dome:                              179.8 m
Height to highest occupied floor level:             167.1 m
Number of floors above ground:                      40
Number of basement levels:                          single basement across whole site
Largest floor external diameter (lvl 17):           56.15 m
Site area:                                          0.57 hectares (1.4 acres)
Net accommodations areas:
➤ Office                                            46,450 m2
➤ Retail                                            1,400 m2
Office floor-floor:                                  4.15 m
Gross superstructure floor area (incl. lightwells): 74,300 m2
Tower Structural Steelwork
Total weight of steel (from Arup Xsteel model):     8,358 tonnes
of which:
➤ 29% is in the diagrid
➤ 24% core columns
➤ 47% beams.
Total number of primary steel pieces:               8 348
Total length:                                       54.56 km
Diagrid column sizes:
➤ Ground – level2:                                  508mm f, 40mm thick
➤ Level 36–38:                                      273mm f, 12.5mm thick
Hoop design tension at level 2:                     7 116 kN
Perimeter column maximum design load:               15,460 kN
Core column maximum design load:                    33,266 kN
Foundations
750mm diameter straight-shafted piles into London Clay
Number of piles:                                    333
Total length of piles:                              9 km
Total design capacity:                              117,000 Tonnes
Credits
Client: Swiss Re
Project Manager: RWG Associates
Architect: Foster and Partners
Structural Engineer: Arup
Building Services Engineer: Hilson Moran Partnership
Cost consultant: Gardiner & Theobold
Fire Engineering: Arup Fire
Main Contractor: Skanska
Structural Steel sub-contractor:
Victor Buyck – Hollandia


                                                                                16 | P a g e

More Related Content

What's hot

Hearst Tower
Hearst TowerHearst Tower
Hearst Towermisschand
 
High-Rise Iconic Buildings
High-Rise Iconic BuildingsHigh-Rise Iconic Buildings
High-Rise Iconic BuildingsDania Abdel-aziz
 
Unite'd habitation, Le corbusier.
Unite'd habitation, Le corbusier.Unite'd habitation, Le corbusier.
Unite'd habitation, Le corbusier.Mayur Waghulde
 
Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...
Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...
Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...Rohit Arora
 
JEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSIS
JEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSISJEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSIS
JEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSISSOUKTIK BHATTACHERJEE
 
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...Anurag Mathur
 
The Edge,Smart Building
The Edge,Smart BuildingThe Edge,Smart Building
The Edge,Smart BuildingDivleen Narula
 
Case Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban AreasCase Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban AreasSustainable Performance Institute
 
Case study cummunity. center presentation
Case study cummunity. center presentationCase study cummunity. center presentation
Case study cummunity. center presentationSispap1
 
LESS IS MORE(MIES VAN DER ROHE)
LESS IS MORE(MIES VAN DER ROHE)LESS IS MORE(MIES VAN DER ROHE)
LESS IS MORE(MIES VAN DER ROHE)Aashna Arora
 
MIXED USE DESIGN -BASICS
MIXED USE DESIGN -BASICSMIXED USE DESIGN -BASICS
MIXED USE DESIGN -BASICSJayashreeIyer14
 
The Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyThe Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyDinesh Kumar
 

What's hot (20)

Norman Foster
Norman FosterNorman Foster
Norman Foster
 
Hearst Tower
Hearst TowerHearst Tower
Hearst Tower
 
High-Rise Iconic Buildings
High-Rise Iconic BuildingsHigh-Rise Iconic Buildings
High-Rise Iconic Buildings
 
Shard tower
Shard towerShard tower
Shard tower
 
Sears tower
Sears towerSears tower
Sears tower
 
Unite'd habitation, Le corbusier.
Unite'd habitation, Le corbusier.Unite'd habitation, Le corbusier.
Unite'd habitation, Le corbusier.
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...
Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...
Hi- tech Architecture and its pioneering architects, Norman Foster , Richard ...
 
JEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSIS
JEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSISJEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSIS
JEWEL CHANGI AIRPORT , SINGAPORE | STRUCTURAL ANALYSIS
 
Kimbell art museum
Kimbell art museumKimbell art museum
Kimbell art museum
 
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
KOHINOOR SQUARE (High Rise Mixed use building) - Mumbai Case Study By Anurag ...
 
The Edge,Smart Building
The Edge,Smart BuildingThe Edge,Smart Building
The Edge,Smart Building
 
Case Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban AreasCase Study: Sustainable Mixed-Use Development in Historic Urban Areas
Case Study: Sustainable Mixed-Use Development in Historic Urban Areas
 
Turning torso
Turning torsoTurning torso
Turning torso
 
(Norman foster)
(Norman foster)(Norman foster)
(Norman foster)
 
Case study cummunity. center presentation
Case study cummunity. center presentationCase study cummunity. center presentation
Case study cummunity. center presentation
 
norman foster
norman fosternorman foster
norman foster
 
LESS IS MORE(MIES VAN DER ROHE)
LESS IS MORE(MIES VAN DER ROHE)LESS IS MORE(MIES VAN DER ROHE)
LESS IS MORE(MIES VAN DER ROHE)
 
MIXED USE DESIGN -BASICS
MIXED USE DESIGN -BASICSMIXED USE DESIGN -BASICS
MIXED USE DESIGN -BASICS
 
The Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case StudyThe Shard, Skyscraper - Architectural Case Study
The Shard, Skyscraper - Architectural Case Study
 

Similar to Swiss re building london

Ae4 Final Report
Ae4 Final ReportAe4 Final Report
Ae4 Final ReportRyan Brown
 
Seminar on capital gate building
Seminar on capital gate buildingSeminar on capital gate building
Seminar on capital gate buildingNayan Rao
 
Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15Arafat Akash
 
Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.Rohit Arora
 
Detail behind the proposal
Detail behind the proposalDetail behind the proposal
Detail behind the proposallauracarcano2
 
curtain wall -skin of building
 curtain wall -skin of building curtain wall -skin of building
curtain wall -skin of buildingabidha karthu
 
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...SimScale
 
IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...
IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...
IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...IRJET Journal
 
Lighting protection of an office building
Lighting protection of an office buildingLighting protection of an office building
Lighting protection of an office buildingfreelay
 
Low Energy Office Proposal
Low Energy Office Proposal Low Energy Office Proposal
Low Energy Office Proposal robatherton
 
DYNAMIC/ DA VINCI/ROTATING TOWER,DUBAI
DYNAMIC/ DA VINCI/ROTATING TOWER,DUBAIDYNAMIC/ DA VINCI/ROTATING TOWER,DUBAI
DYNAMIC/ DA VINCI/ROTATING TOWER,DUBAIpadamatikona swapnika
 
ARC401 report
ARC401 reportARC401 report
ARC401 report2gueso06
 
A new facade concept for an existing office building
A new facade concept for an existing office buildingA new facade concept for an existing office building
A new facade concept for an existing office buildingMardi Rahardjo
 
Green Studio Handbook - Part 4
Green Studio Handbook - Part 4Green Studio Handbook - Part 4
Green Studio Handbook - Part 4Galala University
 
Designing and optimising a glass curtain wall facade
Designing and optimising a glass curtain wall facadeDesigning and optimising a glass curtain wall facade
Designing and optimising a glass curtain wall facadeReshma Philip
 
ICWES15 - Improving the Thermal Performance of Framed Window Systems. Presen...
ICWES15 - Improving the Thermal Performance of Framed Window Systems.  Presen...ICWES15 - Improving the Thermal Performance of Framed Window Systems.  Presen...
ICWES15 - Improving the Thermal Performance of Framed Window Systems. Presen...Engineers Australia
 

Similar to Swiss re building london (20)

Ae4 Final Report
Ae4 Final ReportAe4 Final Report
Ae4 Final Report
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
burj khalifa
burj khalifaburj khalifa
burj khalifa
 
Seminar on capital gate building
Seminar on capital gate buildingSeminar on capital gate building
Seminar on capital gate building
 
Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15Case study on Leadenhall Building KUET BECM 2k15
Case study on Leadenhall Building KUET BECM 2k15
 
Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.Burj khalifa , its engineering as well as architectural features and facts.
Burj khalifa , its engineering as well as architectural features and facts.
 
Detail behind the proposal
Detail behind the proposalDetail behind the proposal
Detail behind the proposal
 
curtain wall -skin of building
 curtain wall -skin of building curtain wall -skin of building
curtain wall -skin of building
 
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...
 
IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...
IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...
IRJET- Ultra Light Weight Concrete – A New Boon to the Field of Construction:...
 
Lighting protection of an office building
Lighting protection of an office buildingLighting protection of an office building
Lighting protection of an office building
 
FH433_FinalReportPDF
FH433_FinalReportPDFFH433_FinalReportPDF
FH433_FinalReportPDF
 
Low Energy Office Proposal
Low Energy Office Proposal Low Energy Office Proposal
Low Energy Office Proposal
 
DYNAMIC/ DA VINCI/ROTATING TOWER,DUBAI
DYNAMIC/ DA VINCI/ROTATING TOWER,DUBAIDYNAMIC/ DA VINCI/ROTATING TOWER,DUBAI
DYNAMIC/ DA VINCI/ROTATING TOWER,DUBAI
 
Presentation1
Presentation1Presentation1
Presentation1
 
ARC401 report
ARC401 reportARC401 report
ARC401 report
 
A new facade concept for an existing office building
A new facade concept for an existing office buildingA new facade concept for an existing office building
A new facade concept for an existing office building
 
Green Studio Handbook - Part 4
Green Studio Handbook - Part 4Green Studio Handbook - Part 4
Green Studio Handbook - Part 4
 
Designing and optimising a glass curtain wall facade
Designing and optimising a glass curtain wall facadeDesigning and optimising a glass curtain wall facade
Designing and optimising a glass curtain wall facade
 
ICWES15 - Improving the Thermal Performance of Framed Window Systems. Presen...
ICWES15 - Improving the Thermal Performance of Framed Window Systems.  Presen...ICWES15 - Improving the Thermal Performance of Framed Window Systems.  Presen...
ICWES15 - Improving the Thermal Performance of Framed Window Systems. Presen...
 

Recently uploaded

Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfhans926745
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Scriptwesley chun
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 

Recently uploaded (20)

Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 

Swiss re building london

  • 1. 30 St Mary Axe, London Norman Foster Assignment 2: Construction and Management Plan Course: Construction Technology 4 ARBE4100 Prepared by: Alyssa Turner Student Number: 3037715 Lecturer: Marcus Jefferies Date: Friday 5th June 1|Page
  • 2. Executive Summary The aim of this report is to analyse the technical and management issues associated with the construction of a high rise building. The report takes a case study approach in regards to Fosters and Normans’ St Mary Axe and how a similar building could be constructed in Newcastle CBD. The report will outline issues such as building services within the high rise structure, specifications for the cladding system in regards to legal documents, legal issues and the how they comply with the BCA and Procurement Methods. This report follows on from Assignment 1 of the structural and cost analysis of a high rise building in the Newcastle CBD area. The report also takes 30 St Mary Axe as a case study building and investigates the construction and management techniques in the high rise building. 2|Page
  • 3. Contents 1. Introduction Page 4 2. Building Services Page 5 2.1 Service Details Page 5 2.1.1 Ventilation Page 5 2.1.2 Plumbing Page 6 2.1.3 Lighting System Page 6 2.1.4 Electric Supply Page 7 2.1.5 Air Conditioning Page 7 2.1.6 Lift System Page 7 3. External Cladding System Page 8 3.1 Overview of the Facade Page 8 4. Specification of the Cladding System Page 9 4.1 Building Description Page 9 4.1.1 Design Life Page 10 4.1.2 Structural Capability Page 10 4.1.3 Water Penetration Page 10 4.1.4 Acoustic Performance Page 10 4.1.5 Fire/Smoke Separation Page 11 4.1.6 Glazing Page 11 5. Legal Issues Page 11 5.1 Requirements for BCA Page 11 5.1.1 Type of Construction Required Page 12 5.1.2 General Floor Area and Volume Limitations Page 12 5.1.3 Separation by Fire Wall Page 12 5.1.4 Separation of Lift Shaft Page 12 5.1.5 Number of Lift Shafts Page 13 5.2 Fire Regulations Page 13 5.2.1 When Fire Isolated exits are Required Page 13 5.2.2 Sprinklers Page 13 5.2.3 Fire Control Centre Page 13 Conclusion Page 14 Resources Page 15 Appendix Page 16 3|Page
  • 4. 1. Introduction “30 St Mary Axe, better known as the Gherkin because is floor plan resembled a sliced pickle, is located in the heart of London’s insurance district. It was originally the site of the Baltic Exchange since 1903 but was obliterated in April 1992 by the IRA. The site went under many discussions on what was to be done with it including restoring the Baltic Exchange and the proposal of an 84 storey Millennium Tower. In 1997 insurance giants Swiss Re acquired the site and commissioned Foster and Partners to design the building. London’s first environmentally sustainable tall building stands 180m high and consists of 40 storeys. The building consumes about half the energy of most skyscrapers this size. The building gradually widens at each floor plan until it reaches the 16 th where it then diminishes until it reaches its apex. This distinctive form responds to the constraints of the site: the building appears more slender than a rectangular block of equivalent size; reflections are reduced and transparency is improved; (Foster+Parnters.com). The sliming of the building at ground floor maximises the public space at ground level. It helps maintain pedestrian comfort at street level as the profile reduces the amount of wind deflected to the ground compared with a rectilinear tower of similar size.” (Turner, 2009) 4|Page
  • 5. 2. Building Services This section provides a detailed study of the service in St Mary Axe, providing an example of how services could be integrated into a high rise building in Newcastle CBD. 2.1 Service Details St Mary Axe building utilities are located around a circular central core (London Architecture). This allows for uninterrupted floor space for tenants and the ability to maximise daylight from every side of the building. Fire Lift Passenger Lift Service Riser Toilets Stairs Fire Lift Good Lift Space for Higher Level Lifts Electrical and Data Cable Duct Stairs Service Duct (water, sewer, waste) Fig 2.1 Level 18 floor plan – Services shown in blue (Fedun) 2.1.1 Ventilation 30 St Mary Axe is designed to maximise daylight and natural ventilation so that it uses half the energy typically required by an office block (Glass Works). Gaps in each floor create six shafts that serve as a natural ventilation system for the entire building (Wikipedia). A double glazing effect, which insulates the office space inside is caused by air being sandwiched between two layers of glazing. These shafts pull warm Fig 2.1.1 Image showing atrium which allows ventilation throughout the levels (Perfect Buildings) 5|Page
  • 6. air out of the building during the summer and warm the building in the winter using passive solar gain. Blinds located within the cavity of the ventilated double skin facade intercept solar gain before it enters the office environment; intercepted heat can then be reclaimed or rejected depending on the requirement for heating or cooling (Swiss Re). The ventilation system is decentralised which enables occupants to supply and control mechanical ventilation on a floor by floor basis. Windows in the facade of the wedges, which open automatically, allow for fresh air to be drawn into the building. As a result the building uses 50% less energy that a typical prestige air-conditioned office building (Swiss Re). 2.1.2 Plumbing The building uses an electric heat-tracing system which provides “energy-efficient hot water temperature maintenance, frost protection and snow melting” (Process Heat). Over 1000 metres of Raychem HWAT-M self-regulation heating cable has been installed. This particular type of electric heat tracing system provides instant hot water throughout the building without any re-circulation plumbing. This allows for “greater energy efficiency, lower maintenance and significant installation time/cost savings over traditional re- circulation systems (Process Heat). 2.1.3 Lighting System Fig 2.1.3 Image showing light Fig 2.1.3i Model showing the penetration into the building (Perfect twisting floor plates with cut outs Building) (Munro) The lightwells allow daylight to penetrate the building to a further distance inside the building then they would have had the floor gone all the way to the perimeter, helping to improve the internal environment. Although these lightwells reduce the need for artificial lighting some is still required. The building has also been equipped with motion and light level sensors to prevent unnecessary lighting (Glass Works). 6|Page
  • 7. 2.1.4 Electrical Supply The building uses primary fuel is gas as it is one of the cleanest available. 2.1.5 Air Conditioning Air conditioning system consists of “assumed 4 – pipe fan coil system in conjunction with ventilated facade” and “closed circuit evaporative cooling towers” for heat rejection (Great Buildings Online). 2.1.6 Lift System St Mary Axe consists of 23 lifts including; 16 passenger lifts (6 high rise, 5 mid rise and 5 low rise) 2 good lifts, 2 fire fighters lifts, 2 shuttle lifts for the top floor and 1 car park lift. The lifts can carry a maximum of 378 people at any one time reaching speeds of 6 metres a second. Majority of buildings will have extensive lift equipment on the roof of the building. However seen as a bard had been planned for the 40th floor this was not possible. The architects dealt with this by having the main lift only reach the 34th floor, and then having a push-from-below lift to the 39th floor (Wikipedia, 2009). Fig 2.1.6 Elevators (Fedun) 7|Page
  • 8. 3. External Cladding System 3.1 Overview of the Facade The building’s exterior cladding systems consists of full glazed, double-skinned facade comprising approximately of 5,500 flat triangular and diamond shaped glass panels.(Profinder). These metal and glass prefabricated panels are fixed to the diagrid. Fig 3.1 Cladding under construction (Munro) The elements of the facade consist of:  Operable glass screen  Perforated aluminium louvers (internal sun-screen)  A column casing of aluminium  Facade frame of extruded aluminium The glazing to the office areas consist of a double-glazed outer layer and a single-glazed inner screen. Sandwiched in between is a central ventilated cavity which reduces heating and cooling requirements. Its performance can be turned to maximise benefits that the prevailing internal and external environment might have to offer. The solar-control blinds intercept solar gain before it enters the office environment. 8|Page
  • 9. Double glazed aluminium framed facade Ventilated cavity Internal sunscreen of perforated louvers Inner screen Fig 3.2 Section of the Facade (Munro) The glazing in the lightwells consist of double-glazed panels which can be opened to allow fresh air in, while solar gain is effectively reduced through the use of grey-tinted glass with a high performance coating. Despite the overall curvilinear shape of the building there is only one piece of curved glass which is the lens at the top of the building. 4. Specification for the Cladding System The following section details the specification of the cladding system if 30 St Mary axe was to be built in Newcastle CBD paying particular attention to Australian Standards. 4.1 Building Description 30 St Mary Axe consists of a circular plan that widens as it rises from the ground and then tapers towards its apex. A typical floor plan has a six-leafed plan around a circular service core with triangle shaped voids acting as light wells. The cladding consists of a “double-skin energy efficient facade made of glass, with aluminium profiles and a steel frame” (Case Study Landmark building). 24,000 square metres of glass arranged in diamond-shaped panes is used to clad the building. 9|Page
  • 10. 4.1.1 Design Life The external cladding is to be designed and constructed to withstand the severe exposure for a realistic tine period. The external cladding system is to be designed to meet BCA performance provisions listed in BCA Volume 2 – BCA 2007, Section P2.1 Structural stability and resistance to actions The external cladding should have a minimum of: - 30 year serviceable life, within reasonable schedule maintenance - 50 year design life for structural integrity, this is inclusive of brackets, framings and fixings 4.1.2 Structural Capability AS 1170.0:2002 Structural Design Actions – General Principles refers to loads in which the building must be able to withstand from. These include loads either generated from the structure or from the environment. Dead Loads – are the loads generated from the building itself. Refer to AS 1170.1:2002 Structural Design Actions – Earthquake actions in Australia. Wind Loads – Due to the shape of the building vortices, which can generate strong gusts at the base of the building, have been reduced. The shape also helps deflect string winds around the building therefore causing less stress on the external cladding. The design for wind loads should meet AS 1170.2:2002 Structural Design Actions – Wind Actions. Earthquake loads – In 1989 an earthquake hitting Newcastle, reaching 5.5 on the Richter scale, destroyed and damaged many buildings. As Newcastle is located in an area which can suffer from earth disturbance the building is to be designed to meet AS 1170.4:2007 Structural Design Actions – Earthquake actions in Australia. Ground Water – Due to Newcastle’s CBD location being only a few meters above sea level precautions are to be taken in regards to flooding. The building shall be designed to meet AS 1170.1:2002 Structural Design Actions – Permanent, imposed & other actions. 4.1.3 Water Penetration The external cladding system is to be designed to resist water penetration from heavy rain, windy conditions and during window cleaning. The cladding standards are to meet AS 4420.5:1996 Windows – Methods to test. Water penetration resistance test. 4.1.4 Acoustic Performance The external cladding is required to protect the occupants from external noises entering the building and to help maintain a good acoustic atmosphere internally. The acoustic performance design is to me AS 1055.1-1997 Acoustic – Description and Measurements of Environmental Noise – General Procedures. 10 | P a g e
  • 11. 4.1.5 Fire/Smoke Separation With relation to fire separation inside the building there are various issues which need to be addressed. Fire/Smoke Separation regulations are to meet AS 4284: 1995 Testing of Building Facades as well as BCA Parts C2 Compartmentation and Separation, C2.6 Vertical separation of openings in external walls and C3 Protection of Openings. 4.1.6 Glazing Majority of the cladding system of St Mary Axe consists of glazing. Glazing to the first 38 levels of the building are to be aluminium framed, while the domed structure on the top is to be frameless glass. The glass used for the external cladding is to be produced and installed with good characterises in subject to wind loading, human impact, safety, security and the UV elimination. Glazing to be used for the cladding is SolarplusR Low E Twin-Glaze unit by G.James. It is chosen for its superior thermal performance. Glass is to be clear in colour and grey glass for the atrium and dome. Glazing is to meet the following standards: AS 1170.4:1993 Minimum design loads on structures – Earthquake loads AS 1288 Glass in buildings – Selection and Installation AS 2047 – 1999 Windows in buildings – Selection and Installation As 4420.0 – 1996 Windows – Methods of test – General introduction and list of methods AS/NZS 1170.1:2002 Structural Design Actions – Permanent, imposed and other actions AS/NZS 1170.2:2002 Structural Design Actions – Wind actions ISO 9000 Quality management and quality assurance standards 5. Legal Issues 5.1 Requirement for BCA Buildings within Australia must be built in accordance with regulations as set out in the BCA. In the following section a case study approach has been taken in regards to requirements of the BCA in the case of Foster and Partners 30 St Mary Axe building. 11 | P a g e
  • 12. 5.1.1 Type of Construction Required Part C1.1 of the BCA sets the minimum type of fire resisting construction. The Case study building (and any high rise building to be built in Newcastle) has 4 or more rises in a class 5 therefore the type of construction is A. 5.1.2 General Floor Area & Volume Limitations Part C2.2 of the BCA states that the fire compartment or atrium must not exceed 8000m2/48000m2, unless sprinkled with a smoke exhaust system. See section 6.2.2 for details. 5.1.3 Separation by Fire Wall Part C2.7 of the BCA states that fire walls must be constructed so that they meet the specified levels of fire protection. 5.1.4 Separation of Lift Shaft Part C2.10 of the BCA requires lift shafts to be separated from the building and in an enclosed shaft. All emergency lifts must be contained within a fire-resisting shaft having a FRL of no less then 120/120/120. The floor plan below highlights the service lifts indicating that there are masonry walls constructed around the lift shaft. Therefore complies with BCA requirements. Image indicating lift shafts with a masonry wall 5.1.5 Number of Lift Shafts Part D1.2 of the BCA requires buildings over the height of 25 metres to require at least two exists from each story. As indicated in the above image St Mary Axe has the required minimum number of fire exits provided for each level and therefore complies with BCA requirements. 12 | P a g e
  • 13. 5.2 Fire Regulations The spiral lightwell arrangement allows for a fire escape strategy based on a variation of phased evacuation. The building is divided into fire safety zones at every sixth then second floor. This allows for the evacuation of one area at a time as opposed to the whole building at once. A system of smoke curtains form smoke reservoirs in the lightwells. Natural ventilation is used for smoke clearance for the lightwells. (Mace) This eliminated the spread of smoke through the lightwells from lower floors. 5.2.1 When Fire-isolated Exits are required Part D1.1 of the BCA requires every ‘required’ fire exit to be fire isolated. As shown in figure fire stairs appear to be constructed from masonry to comply with BCA standards. Fig 5.2 Division of building into fire 5.2.2 Sprinklers compartments Part E1.5 of the BCA requires sprinklers to be installed in a building which has a height of more then25 metres. In the case study of St Mary Axe a sprinkler system has been used. Lightwell based floors are protected by sprinklers on the overhanging soffits above (Mace). The sprinkler system also includes an array of window sprinklers on levels 2 and 3. However there is no sprinkler system in the dome. These were omitted on aesthetic and practical grounds. “Instead the mechanical ventilation system needed for environmental purposes has been upgraded to serve as a temperature and smoke control system” (Mace). 5.2.3 Fire Control Centre Part E1.8 of the BCA states that buildings over a height of 25 metres, requires a fire control centre facility. The installed fire alarm system includes “automatic smoke/heat detection, manual call points, sprinkler flow switch activation, auto dial-up facility to London fire brigade, two-way fire fighter’s system and a central fire command centre” (Great Buildings Online). 13 | P a g e
  • 14. Conclusion This report has investigated the technical and management issues associated with the construction of a high rise building taking a case study approach with Forster and Partners’ 30 St Mary Axe building in London, UK. As demonstrated in this example, the design and construction of a high rise building is very complex and involved process. In regards to the Vision 2020 and Newcastle City Centre LED 2008, 30 St Mary Axe could realistic meet these requirements. As we move towards design buildings which are more environmentally friendly we are able to take the example of 30 St Mary axe and design a building which can meet the requirements of the clients without compromising the environment. 14 | P a g e
  • 15. Resources Munro, Dominic; “Swiss Re’s Building, London” retrieved 04/04/09 http://www.sbi.se/uploaded/dokument/files/Art_Swiss%20Re%C2%B4s%20Building,%20Lo ndon.pdf Buchanan, Peter; “The Tower, An Anachronism Awaiting Rebirth?” retrieved 04/04/09 http://www.gsd.harvard.edu/research/publications/hdm/back/26_Buchanan.pdf Emporis.com; “30 St Mary Axe” retrieved 10/04/09 Architecture Week.com; “Swiss Re Tower by Foster & Partners” retrieved 06/04/09 Freiberger, Marianne; “Perfect buildings: the maths of modern architecture” retrieved 04/04/09 Swiss Re; “Sustainability at 30 St Mary Axe” retrieved 06/04/09 Absolute Astronomy; “30 St Mary Axe” retrieved 06/04/09 MRMCA; “Case Study 001 – 30 St Mary Axe, London” retrieved 06/04/09 www.rlsd.com The Institution of Structural Engineers; “30 St Mary Axe, London” retrieved 10/04/09 ICON Magazine Online; “30 St Mary Axe” (September 2004) retrieved 10/04/09 Processheat; “Case Study: 30 St Mary Axe (Swiss Re Building)” (2007) retrieved 23/06/09 http://www.processheat.ltd.uk/clients/case-study1.html Fedun, Bill; “30 St Mary Axe” retrieved 20/05/09 www.hilsommoran.com; “Spotlight Projects – 30 St Mary Axe” retrieved 20/05/2009 Building Code of Australia “Class 2 to 9 Buildings – Volume One/Two” (2008) www.londonarchitecture.co.uk; “30 St Mary Axe” retrieved 12/06/2009 www.wikepedia.com; “30 St Mary Axe” retrieved 12/06/2009 15 | P a g e
  • 16. Appendix The following has been taken from Dominic Munro’s report titled Swiss Re’s Building, London Height to top of dome: 179.8 m Height to highest occupied floor level: 167.1 m Number of floors above ground: 40 Number of basement levels: single basement across whole site Largest floor external diameter (lvl 17): 56.15 m Site area: 0.57 hectares (1.4 acres) Net accommodations areas: ➤ Office 46,450 m2 ➤ Retail 1,400 m2 Office floor-floor: 4.15 m Gross superstructure floor area (incl. lightwells): 74,300 m2 Tower Structural Steelwork Total weight of steel (from Arup Xsteel model): 8,358 tonnes of which: ➤ 29% is in the diagrid ➤ 24% core columns ➤ 47% beams. Total number of primary steel pieces: 8 348 Total length: 54.56 km Diagrid column sizes: ➤ Ground – level2: 508mm f, 40mm thick ➤ Level 36–38: 273mm f, 12.5mm thick Hoop design tension at level 2: 7 116 kN Perimeter column maximum design load: 15,460 kN Core column maximum design load: 33,266 kN Foundations 750mm diameter straight-shafted piles into London Clay Number of piles: 333 Total length of piles: 9 km Total design capacity: 117,000 Tonnes Credits Client: Swiss Re Project Manager: RWG Associates Architect: Foster and Partners Structural Engineer: Arup Building Services Engineer: Hilson Moran Partnership Cost consultant: Gardiner & Theobold Fire Engineering: Arup Fire Main Contractor: Skanska Structural Steel sub-contractor: Victor Buyck – Hollandia 16 | P a g e