Estimation Games Pascal Van Cauwenberghe Nayima
Consultant.  Project Manager.  Games Maker. His Blog: blog.nayima.be NAYIMA We make play work
Estimate the height of the highest place in Belgium In meters or feet
# 1: Always give a range Never give them a number
# 1: Numbers are for factsRanges are for estimates I estimate “Between 650 and 700m” Or “Between 0 et 4000m” I know it’s 694m (2092 ft)
Estimation exercise One result per table Choose one of three collaboration techniques If you can’t choose, let the Post-It choose for you RED Post-It Estimate as a group, come to consensus GREEN Post-It Divide the work among you YELLOW Post-it First estimate individually Then combine the estimates as a group
Estimation exercise 1 Surface temperature of the sun (in degrees C) Latitude of Shanghai (in degrees) Surface area of Asia (in km2) Birth date of Alexander The Great (year) Dollars in circulation in the US in 2004 (in $) Volume of the Great American lakes (in litres) Global revenue of “Titanic” (in $) Length of the Pacific coastline (Ca, Or, Wa) (in km) Number of books published in USA, 1776 to 2004 Weight of the largest whale (in tonnes) Time’s up! 10min This quiz is from “Software Estimation” by Steve McConnell (Microsoft Press) (C) 2006 Steve McConnell. Used with permission
An estimation joke An engineer, a mathematician and an accountant are sitting at the bar The barman asks: “What’s 68+73 ?” Engineer: 141 Mathematician: 68 + 73 = 73 + 68 Accountant: Usually it’s 141, but what do you want to do with the number?
Why estimate? What is the expected error margin?
#2 Always ask what the estimate will be used for
What have you committed to? Based on what information?
Cone of uncertainty 400% 25% Watch out: this is the best possible case!
#3 Estimation != Commitment Getting an estimate wrong doesn’t hurt
Estimating money (individually) How much money is there in this room? Counting only cash dollars Re-do the estimation, but this time Count the number of people: N Count how much money you have on you: M Estimate how much money the average person holds, based on M: M1-M2 Compute the amount: N * M1 – N * M2
What can you count? Number of stakeholders Number of goals Number of events Number of business processes Number of high-level user stories Number of detailed user stories Number of screens ....
#4 First try to measure, count and computeEstimate only when necessary
Estimating money (in group) Estimate as one group per table Combine individual estimations into a group estimate Planning Poker style: announce estimates, low/high estimators explain, again Take min and max for a range that covers all estimates Take average of min and max for a range that covers much of the estimates ...
Aggregate estimates Independent estimators For example, by playing Planning Poker Independent estimation methods For example, by combining: Comparison with previous project Expert estimation Counting high level stories
#5 Aggregate independent estimates “Wisdom of the Crowds”
The law of large numbers (or: statistics is on our side, for once) If we estimate with an error of x% The estimate of each scope item will have an error of x% But... Some items will be over-estimated, others under-estimated (maybe....) => The error on the total estimate is < x%
The law of 15 Have about 15-20 same-sized elements at each planning horizon Program, Project, Release, Iteration Enough for the law of large numbers to have an effect But not too many, easy to manage
#6 Use the law of large numbers Decompose  Just enough, just in time
Sprint CommitmentSprint Burndown
Release Burndown
Velocity Chart
Re-estimation and calibration First estimation: Relative estimate (1 point, 2 points, ...) Calibrate with previous projects (16-22 points per iteration) Re-estimate during the project Check if relative sizes are ok Re-calibrate with measured velocity
Ensure consistency of relative estimates Build in internal consistency Demonstrated in “XP Game” Analyse large errors in retrospectives Some variance is normal Keep a library of representative reference stories Estimate relative to references Add stories that were mis-estimated!
Velocity of the first project Take a similar, finished project Estimate relatively in Story points: N points We know it took M mandays Decide how many mandays per iteration: K Velocity = +/- K * N/M points/iteration Attention: M is complete cost No “Twilight Zone” or “Murky Zone”!
#7 Calibrate your estimates with real velocity data Project data >  Company data >  Industry data
Evil Estimation Games “Guess the number I’ve got in my head!” “An awesome team like you can do better than that!” “This time it’ll go so much faster, because we learned so much from the previous project!” “This project will be very different!” “If we just work a bit harder, we’ll increase velocity” “I could code this in half the time!” “If we lower the estimate, the project will be done faster” (this actually works in some circumstances...)
Q: Why are there so many pointy haired-bosses? A: because there are so many Dilberts
#8 Never negotiate estimates Always question the reasoning and assumptions behind estimates
#9 Never negotiate commitments
#10 Solve problems together Make assumptions explicit Question assumptions Offer options
The Options exercise Estimate of the project: 5-6 months Conference in 3 months We need to make a great impression on prospects I want to show all our functionality Which assumptions are we making? What options can you offer?
Roadmap OR Kanban? Our dilemma: Product manager needs to publish a credible long term roadmap for customers, partners and integrators Development team  has flow-based process without estimation, planning or velocity tracking We can’t have both, can we? Yes we can!
Roadmap AND Kanban Roadmap with customer goals, not features Product Manager estimates value of achieving each goal => priorities of roadmap Product Manager determines budget per goal Quick feasibility check by team Each release, PM and team find a way to achieve release goals within release budget Watch flow, ensure release goals are met
Summary Ranges for estimates. Numbers for facts. Always ask what the estimate will be used for Estimation is not Commitment Measure, count, compute before estimating Aggregate independent estimates Use the law of large numbers (large ~= 15) Calibrate estimates with measured velocity Never negotiate estimates Never negotiate commitments Solve problems together
Estimation exercise 2 Surface temperature of the sun (in degrees C) Latitude of Shanghai (in degrees) Surface area of Asia (in km2) Birth date of Alexander The Great (year) Dollars in circulation in the US in 2004 (in $) Volume of the Great American lakes (in litres) Global revenue of “Titanic” (in $) Length of the Pacific coastline (Ca, Or, Wa) (in km) Number of books published in USA, 1776 to 2004 Weight of the largest whale (in tonnes) Time’s up! 6 min This quiz is from “Software Estimation” by Steve McConnell (Microsoft Press) (C) 2006 Steve McConnell. Used with permission
Answers Sun: 6000° C Shanghai: 31 degrees North Asian area: 44,390,000 km² Alexander was born in 356 BC Dollars in circulation: $719.9 billion Great Lakes: 6.8x10^23 litres Titanic: 1.835 billion $ Pacific Coast: 1293 kilometres Published books: 22 million Whale: 170 tonnes This quiz is from “Software Estimation” by Steve McConnell (Microsoft Press) (C) 2006 Steve McConnell. Used with permission
And the winner is? Life is like a box of tasty  Belgian chocolates!
Software Estimation – Steve McConnell presentation 42 |
Session Retro Thank You! for your Gift of Feedback 
Merci Thank You

More Related Content

What's hot

Agile effort estimation
Agile effort estimation Agile effort estimation
Agile effort estimation Elad Sofer
 
Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)David Anderson
 
Planning Poker estimating technique
Planning Poker estimating techniquePlanning Poker estimating technique
Planning Poker estimating techniqueSuhail Jamaldeen
 
Org Topologies at Scrum Day Europe 2022, Amsterdam
Org Topologies at Scrum Day Europe 2022, AmsterdamOrg Topologies at Scrum Day Europe 2022, Amsterdam
Org Topologies at Scrum Day Europe 2022, AmsterdamAlexey Krivitsky
 
Scrum - Requirements and User Stories
Scrum - Requirements and User StoriesScrum - Requirements and User Stories
Scrum - Requirements and User StoriesUpekha Vandebona
 
Agile stories, estimating and planning
Agile stories, estimating and planningAgile stories, estimating and planning
Agile stories, estimating and planningDimitri Ponomareff
 
Agile Performance Metrics
Agile Performance MetricsAgile Performance Metrics
Agile Performance MetricsACM
 
Introduction to Agile Estimation & Planning
Introduction to Agile Estimation & PlanningIntroduction to Agile Estimation & Planning
Introduction to Agile Estimation & PlanningAmaad Qureshi
 
Estimating Story Points in Agile - MAGIC Approach
Estimating Story Points in Agile - MAGIC ApproachEstimating Story Points in Agile - MAGIC Approach
Estimating Story Points in Agile - MAGIC ApproachMarraju Bollapragada V
 
Estimation techniques for Scrum Teams
Estimation techniques for Scrum TeamsEstimation techniques for Scrum Teams
Estimation techniques for Scrum TeamsJesus Mendez
 
Heart of Agile: What is Agile?
Heart of Agile: What is Agile?Heart of Agile: What is Agile?
Heart of Agile: What is Agile?Agile Tour Beirut
 
Story Points Estimation And Planning Poker
Story Points Estimation And Planning PokerStory Points Estimation And Planning Poker
Story Points Estimation And Planning PokerDaniel Toader
 
A New Introduction to Jira & Agile Product Management
A New Introduction to Jira & Agile Product ManagementA New Introduction to Jira & Agile Product Management
A New Introduction to Jira & Agile Product ManagementDan Chuparkoff
 

What's hot (20)

Agile Estimation Techniques
Agile Estimation TechniquesAgile Estimation Techniques
Agile Estimation Techniques
 
Agile effort estimation
Agile effort estimation Agile effort estimation
Agile effort estimation
 
Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)Kanban's 3 Agendas (London Lean Kanban Day)
Kanban's 3 Agendas (London Lean Kanban Day)
 
Planning Poker estimating technique
Planning Poker estimating techniquePlanning Poker estimating technique
Planning Poker estimating technique
 
Planning Poker
Planning PokerPlanning Poker
Planning Poker
 
Org Topologies at Scrum Day Europe 2022, Amsterdam
Org Topologies at Scrum Day Europe 2022, AmsterdamOrg Topologies at Scrum Day Europe 2022, Amsterdam
Org Topologies at Scrum Day Europe 2022, Amsterdam
 
Scrum - Requirements and User Stories
Scrum - Requirements and User StoriesScrum - Requirements and User Stories
Scrum - Requirements and User Stories
 
Agile stories, estimating and planning
Agile stories, estimating and planningAgile stories, estimating and planning
Agile stories, estimating and planning
 
Agile Performance Metrics
Agile Performance MetricsAgile Performance Metrics
Agile Performance Metrics
 
Introduction to Agile Estimation & Planning
Introduction to Agile Estimation & PlanningIntroduction to Agile Estimation & Planning
Introduction to Agile Estimation & Planning
 
Agile estimation
Agile estimationAgile estimation
Agile estimation
 
Agile Mindset Shifting: Agile For All
Agile Mindset Shifting: Agile For AllAgile Mindset Shifting: Agile For All
Agile Mindset Shifting: Agile For All
 
Estimating Story Points in Agile - MAGIC Approach
Estimating Story Points in Agile - MAGIC ApproachEstimating Story Points in Agile - MAGIC Approach
Estimating Story Points in Agile - MAGIC Approach
 
Estimation techniques for Scrum Teams
Estimation techniques for Scrum TeamsEstimation techniques for Scrum Teams
Estimation techniques for Scrum Teams
 
Estimation and Release Planning in Scrum
Estimation and Release Planning in ScrumEstimation and Release Planning in Scrum
Estimation and Release Planning in Scrum
 
User Stories
User StoriesUser Stories
User Stories
 
Agile Team structure-roles
Agile Team structure-rolesAgile Team structure-roles
Agile Team structure-roles
 
Heart of Agile: What is Agile?
Heart of Agile: What is Agile?Heart of Agile: What is Agile?
Heart of Agile: What is Agile?
 
Story Points Estimation And Planning Poker
Story Points Estimation And Planning PokerStory Points Estimation And Planning Poker
Story Points Estimation And Planning Poker
 
A New Introduction to Jira & Agile Product Management
A New Introduction to Jira & Agile Product ManagementA New Introduction to Jira & Agile Product Management
A New Introduction to Jira & Agile Product Management
 

Similar to Agile 2010 Estimation Games

Estimation Games – Pascal Van Cauwenberghe
Estimation Games – Pascal Van CauwenbergheEstimation Games – Pascal Van Cauwenberghe
Estimation Games – Pascal Van CauwenbergheAgile Tour Beirut
 
Software estimation is crap
Software estimation is crapSoftware estimation is crap
Software estimation is crapIan Garrison
 
Ryan Ripley - The #NoEstimatesMovement
Ryan Ripley - The #NoEstimatesMovementRyan Ripley - The #NoEstimatesMovement
Ryan Ripley - The #NoEstimatesMovementProjectCon
 
Estimating IT projects - VU Amsterdam
Estimating IT projects - VU AmsterdamEstimating IT projects - VU Amsterdam
Estimating IT projects - VU AmsterdamFrank Vogelezang
 
What are the odds of making that number risk analysis with crystal ball - O...
What are the odds of making that number   risk analysis with crystal ball - O...What are the odds of making that number   risk analysis with crystal ball - O...
What are the odds of making that number risk analysis with crystal ball - O...p6academy
 
Introduction To Agile Estimating and Planning
Introduction To Agile Estimating and PlanningIntroduction To Agile Estimating and Planning
Introduction To Agile Estimating and PlanningKane Mar
 
The Art Of Estimation
The Art Of EstimationThe Art Of Estimation
The Art Of Estimationcodeburns
 
Magically predictable software delivery ralf westphal
Magically predictable software delivery   ralf westphalMagically predictable software delivery   ralf westphal
Magically predictable software delivery ralf westphalRenald Wittwer
 
Risk And Relevance 20080414ppt
Risk And Relevance 20080414pptRisk And Relevance 20080414ppt
Risk And Relevance 20080414pptgregoryg
 
Risk And Relevance 20080414ppt
Risk And Relevance 20080414pptRisk And Relevance 20080414ppt
Risk And Relevance 20080414pptgregoryg
 
Iwsm2014 why cant people estimate (dan galorath)
Iwsm2014   why cant people estimate (dan galorath)Iwsm2014   why cant people estimate (dan galorath)
Iwsm2014 why cant people estimate (dan galorath)Nesma
 
Data visualization tools & techniques - 1
Data visualization tools & techniques - 1Data visualization tools & techniques - 1
Data visualization tools & techniques - 1Korivi Sravan Kumar
 
Measurement in a Continuous World - Jim Highsmith
Measurement in a Continuous World - Jim HighsmithMeasurement in a Continuous World - Jim Highsmith
Measurement in a Continuous World - Jim HighsmithThoughtworks
 
2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrf2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrfJohnnie Fox
 
Agile Estimating & Planning by Amaad Qureshi
Agile Estimating & Planning by Amaad QureshiAgile Estimating & Planning by Amaad Qureshi
Agile Estimating & Planning by Amaad QureshiAmaad Qureshi
 
Three baseline metrics & what they can tell you about your team.
Three baseline metrics & what they can tell you about your team.Three baseline metrics & what they can tell you about your team.
Three baseline metrics & what they can tell you about your team.Mike Burns
 
Outcome Over Output - And why should we care?
Outcome Over Output - And why should we care?Outcome Over Output - And why should we care?
Outcome Over Output - And why should we care?Scrum Australia Pty Ltd
 

Similar to Agile 2010 Estimation Games (20)

Scrum Coach : Estimation
Scrum Coach : EstimationScrum Coach : Estimation
Scrum Coach : Estimation
 
Estimation Games – Pascal Van Cauwenberghe
Estimation Games – Pascal Van CauwenbergheEstimation Games – Pascal Van Cauwenberghe
Estimation Games – Pascal Van Cauwenberghe
 
Software estimation is crap
Software estimation is crapSoftware estimation is crap
Software estimation is crap
 
Ryan Ripley - The #NoEstimatesMovement
Ryan Ripley - The #NoEstimatesMovementRyan Ripley - The #NoEstimatesMovement
Ryan Ripley - The #NoEstimatesMovement
 
Estimating IT projects - VU Amsterdam
Estimating IT projects - VU AmsterdamEstimating IT projects - VU Amsterdam
Estimating IT projects - VU Amsterdam
 
What are the odds of making that number risk analysis with crystal ball - O...
What are the odds of making that number   risk analysis with crystal ball - O...What are the odds of making that number   risk analysis with crystal ball - O...
What are the odds of making that number risk analysis with crystal ball - O...
 
Introduction To Agile Estimating and Planning
Introduction To Agile Estimating and PlanningIntroduction To Agile Estimating and Planning
Introduction To Agile Estimating and Planning
 
The Art Of Estimation
The Art Of EstimationThe Art Of Estimation
The Art Of Estimation
 
Magically predictable software delivery ralf westphal
Magically predictable software delivery   ralf westphalMagically predictable software delivery   ralf westphal
Magically predictable software delivery ralf westphal
 
Risk And Relevance 20080414ppt
Risk And Relevance 20080414pptRisk And Relevance 20080414ppt
Risk And Relevance 20080414ppt
 
Risk And Relevance 20080414ppt
Risk And Relevance 20080414pptRisk And Relevance 20080414ppt
Risk And Relevance 20080414ppt
 
Iwsm2014 why cant people estimate (dan galorath)
Iwsm2014   why cant people estimate (dan galorath)Iwsm2014   why cant people estimate (dan galorath)
Iwsm2014 why cant people estimate (dan galorath)
 
Data visualization tools & techniques - 1
Data visualization tools & techniques - 1Data visualization tools & techniques - 1
Data visualization tools & techniques - 1
 
Measurement in a Continuous World - Jim Highsmith
Measurement in a Continuous World - Jim HighsmithMeasurement in a Continuous World - Jim Highsmith
Measurement in a Continuous World - Jim Highsmith
 
2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrf2015 drupalcampcebu estimation_jrf
2015 drupalcampcebu estimation_jrf
 
The art of estimation
The art of estimationThe art of estimation
The art of estimation
 
Agile Estimating & Planning by Amaad Qureshi
Agile Estimating & Planning by Amaad QureshiAgile Estimating & Planning by Amaad Qureshi
Agile Estimating & Planning by Amaad Qureshi
 
Three baseline metrics & what they can tell you about your team.
Three baseline metrics & what they can tell you about your team.Three baseline metrics & what they can tell you about your team.
Three baseline metrics & what they can tell you about your team.
 
Outcome Over Output - And why should we care?
Outcome Over Output - And why should we care?Outcome Over Output - And why should we care?
Outcome Over Output - And why should we care?
 
Agile Business Value
Agile Business ValueAgile Business Value
Agile Business Value
 

More from AgileCoach.net

Vous pouvez ignorerr les controleurs de gestion
Vous pouvez ignorerr les controleurs de gestionVous pouvez ignorerr les controleurs de gestion
Vous pouvez ignorerr les controleurs de gestionAgileCoach.net
 
Keynote agile grenoble 2013
Keynote agile grenoble 2013Keynote agile grenoble 2013
Keynote agile grenoble 2013AgileCoach.net
 
Real Options Agile Tour Brussels 2013
Real Options Agile Tour Brussels 2013Real Options Agile Tour Brussels 2013
Real Options Agile Tour Brussels 2013AgileCoach.net
 
Real Options Lean Kanban France 2013
Real Options Lean Kanban France 2013Real Options Lean Kanban France 2013
Real Options Lean Kanban France 2013AgileCoach.net
 
Real Options: How and When (not) to take Decisions
Real Options: How and When (not) to take DecisionsReal Options: How and When (not) to take Decisions
Real Options: How and When (not) to take DecisionsAgileCoach.net
 
Real Options - Agile France 2013
Real Options - Agile France 2013Real Options - Agile France 2013
Real Options - Agile France 2013AgileCoach.net
 
Devoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisions
Devoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisionsDevoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisions
Devoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisionsAgileCoach.net
 
Chouette! Encore un bug! Agile Tour 2012
Chouette! Encore un bug! Agile Tour 2012Chouette! Encore un bug! Agile Tour 2012
Chouette! Encore un bug! Agile Tour 2012AgileCoach.net
 
Chouette! Encore un bug!
Chouette! Encore un bug!Chouette! Encore un bug!
Chouette! Encore un bug!AgileCoach.net
 
Les Bases des Méthodes Lean/Agile
Les Bases des Méthodes Lean/AgileLes Bases des Méthodes Lean/Agile
Les Bases des Méthodes Lean/AgileAgileCoach.net
 
Conflict Resolution Diagram Tutorial - French
Conflict Resolution Diagram Tutorial - FrenchConflict Resolution Diagram Tutorial - French
Conflict Resolution Diagram Tutorial - FrenchAgileCoach.net
 
Agreeing on business value
Agreeing on business valueAgreeing on business value
Agreeing on business valueAgileCoach.net
 
Lean out your backlog - Lean and Kanban Belgium 2010
Lean out your backlog - Lean and Kanban Belgium 2010Lean out your backlog - Lean and Kanban Belgium 2010
Lean out your backlog - Lean and Kanban Belgium 2010AgileCoach.net
 
Conflict resolution diagram tutorial
Conflict resolution diagram tutorialConflict resolution diagram tutorial
Conflict resolution diagram tutorialAgileCoach.net
 
Business value by systems thinking
Business value by systems thinkingBusiness value by systems thinking
Business value by systems thinkingAgileCoach.net
 

More from AgileCoach.net (16)

Vous pouvez ignorerr les controleurs de gestion
Vous pouvez ignorerr les controleurs de gestionVous pouvez ignorerr les controleurs de gestion
Vous pouvez ignorerr les controleurs de gestion
 
Keynote agile grenoble 2013
Keynote agile grenoble 2013Keynote agile grenoble 2013
Keynote agile grenoble 2013
 
Real Options Agile Tour Brussels 2013
Real Options Agile Tour Brussels 2013Real Options Agile Tour Brussels 2013
Real Options Agile Tour Brussels 2013
 
Real Options Lean Kanban France 2013
Real Options Lean Kanban France 2013Real Options Lean Kanban France 2013
Real Options Lean Kanban France 2013
 
Real Options: How and When (not) to take Decisions
Real Options: How and When (not) to take DecisionsReal Options: How and When (not) to take Decisions
Real Options: How and When (not) to take Decisions
 
Real Options - Agile France 2013
Real Options - Agile France 2013Real Options - Agile France 2013
Real Options - Agile France 2013
 
Devoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisions
Devoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisionsDevoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisions
Devoxx fr 2013 Real Options - Comment et Quand (ne pas) prendre des décisions
 
Chouette! Encore un bug! Agile Tour 2012
Chouette! Encore un bug! Agile Tour 2012Chouette! Encore un bug! Agile Tour 2012
Chouette! Encore un bug! Agile Tour 2012
 
Great! another bug
Great! another bugGreat! another bug
Great! another bug
 
Chouette! Encore un bug!
Chouette! Encore un bug!Chouette! Encore un bug!
Chouette! Encore un bug!
 
Les Bases des Méthodes Lean/Agile
Les Bases des Méthodes Lean/AgileLes Bases des Méthodes Lean/Agile
Les Bases des Méthodes Lean/Agile
 
Conflict Resolution Diagram Tutorial - French
Conflict Resolution Diagram Tutorial - FrenchConflict Resolution Diagram Tutorial - French
Conflict Resolution Diagram Tutorial - French
 
Agreeing on business value
Agreeing on business valueAgreeing on business value
Agreeing on business value
 
Lean out your backlog - Lean and Kanban Belgium 2010
Lean out your backlog - Lean and Kanban Belgium 2010Lean out your backlog - Lean and Kanban Belgium 2010
Lean out your backlog - Lean and Kanban Belgium 2010
 
Conflict resolution diagram tutorial
Conflict resolution diagram tutorialConflict resolution diagram tutorial
Conflict resolution diagram tutorial
 
Business value by systems thinking
Business value by systems thinkingBusiness value by systems thinking
Business value by systems thinking
 

Recently uploaded

Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 

Recently uploaded (20)

Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 

Agile 2010 Estimation Games

  • 1. Estimation Games Pascal Van Cauwenberghe Nayima
  • 2. Consultant. Project Manager. Games Maker. His Blog: blog.nayima.be NAYIMA We make play work
  • 3. Estimate the height of the highest place in Belgium In meters or feet
  • 4. # 1: Always give a range Never give them a number
  • 5. # 1: Numbers are for factsRanges are for estimates I estimate “Between 650 and 700m” Or “Between 0 et 4000m” I know it’s 694m (2092 ft)
  • 6. Estimation exercise One result per table Choose one of three collaboration techniques If you can’t choose, let the Post-It choose for you RED Post-It Estimate as a group, come to consensus GREEN Post-It Divide the work among you YELLOW Post-it First estimate individually Then combine the estimates as a group
  • 7. Estimation exercise 1 Surface temperature of the sun (in degrees C) Latitude of Shanghai (in degrees) Surface area of Asia (in km2) Birth date of Alexander The Great (year) Dollars in circulation in the US in 2004 (in $) Volume of the Great American lakes (in litres) Global revenue of “Titanic” (in $) Length of the Pacific coastline (Ca, Or, Wa) (in km) Number of books published in USA, 1776 to 2004 Weight of the largest whale (in tonnes) Time’s up! 10min This quiz is from “Software Estimation” by Steve McConnell (Microsoft Press) (C) 2006 Steve McConnell. Used with permission
  • 8. An estimation joke An engineer, a mathematician and an accountant are sitting at the bar The barman asks: “What’s 68+73 ?” Engineer: 141 Mathematician: 68 + 73 = 73 + 68 Accountant: Usually it’s 141, but what do you want to do with the number?
  • 9. Why estimate? What is the expected error margin?
  • 10. #2 Always ask what the estimate will be used for
  • 11. What have you committed to? Based on what information?
  • 12. Cone of uncertainty 400% 25% Watch out: this is the best possible case!
  • 13. #3 Estimation != Commitment Getting an estimate wrong doesn’t hurt
  • 14. Estimating money (individually) How much money is there in this room? Counting only cash dollars Re-do the estimation, but this time Count the number of people: N Count how much money you have on you: M Estimate how much money the average person holds, based on M: M1-M2 Compute the amount: N * M1 – N * M2
  • 15. What can you count? Number of stakeholders Number of goals Number of events Number of business processes Number of high-level user stories Number of detailed user stories Number of screens ....
  • 16. #4 First try to measure, count and computeEstimate only when necessary
  • 17. Estimating money (in group) Estimate as one group per table Combine individual estimations into a group estimate Planning Poker style: announce estimates, low/high estimators explain, again Take min and max for a range that covers all estimates Take average of min and max for a range that covers much of the estimates ...
  • 18. Aggregate estimates Independent estimators For example, by playing Planning Poker Independent estimation methods For example, by combining: Comparison with previous project Expert estimation Counting high level stories
  • 19. #5 Aggregate independent estimates “Wisdom of the Crowds”
  • 20. The law of large numbers (or: statistics is on our side, for once) If we estimate with an error of x% The estimate of each scope item will have an error of x% But... Some items will be over-estimated, others under-estimated (maybe....) => The error on the total estimate is < x%
  • 21. The law of 15 Have about 15-20 same-sized elements at each planning horizon Program, Project, Release, Iteration Enough for the law of large numbers to have an effect But not too many, easy to manage
  • 22. #6 Use the law of large numbers Decompose Just enough, just in time
  • 26. Re-estimation and calibration First estimation: Relative estimate (1 point, 2 points, ...) Calibrate with previous projects (16-22 points per iteration) Re-estimate during the project Check if relative sizes are ok Re-calibrate with measured velocity
  • 27. Ensure consistency of relative estimates Build in internal consistency Demonstrated in “XP Game” Analyse large errors in retrospectives Some variance is normal Keep a library of representative reference stories Estimate relative to references Add stories that were mis-estimated!
  • 28. Velocity of the first project Take a similar, finished project Estimate relatively in Story points: N points We know it took M mandays Decide how many mandays per iteration: K Velocity = +/- K * N/M points/iteration Attention: M is complete cost No “Twilight Zone” or “Murky Zone”!
  • 29. #7 Calibrate your estimates with real velocity data Project data > Company data > Industry data
  • 30. Evil Estimation Games “Guess the number I’ve got in my head!” “An awesome team like you can do better than that!” “This time it’ll go so much faster, because we learned so much from the previous project!” “This project will be very different!” “If we just work a bit harder, we’ll increase velocity” “I could code this in half the time!” “If we lower the estimate, the project will be done faster” (this actually works in some circumstances...)
  • 31. Q: Why are there so many pointy haired-bosses? A: because there are so many Dilberts
  • 32. #8 Never negotiate estimates Always question the reasoning and assumptions behind estimates
  • 33. #9 Never negotiate commitments
  • 34. #10 Solve problems together Make assumptions explicit Question assumptions Offer options
  • 35. The Options exercise Estimate of the project: 5-6 months Conference in 3 months We need to make a great impression on prospects I want to show all our functionality Which assumptions are we making? What options can you offer?
  • 36. Roadmap OR Kanban? Our dilemma: Product manager needs to publish a credible long term roadmap for customers, partners and integrators Development team has flow-based process without estimation, planning or velocity tracking We can’t have both, can we? Yes we can!
  • 37. Roadmap AND Kanban Roadmap with customer goals, not features Product Manager estimates value of achieving each goal => priorities of roadmap Product Manager determines budget per goal Quick feasibility check by team Each release, PM and team find a way to achieve release goals within release budget Watch flow, ensure release goals are met
  • 38. Summary Ranges for estimates. Numbers for facts. Always ask what the estimate will be used for Estimation is not Commitment Measure, count, compute before estimating Aggregate independent estimates Use the law of large numbers (large ~= 15) Calibrate estimates with measured velocity Never negotiate estimates Never negotiate commitments Solve problems together
  • 39. Estimation exercise 2 Surface temperature of the sun (in degrees C) Latitude of Shanghai (in degrees) Surface area of Asia (in km2) Birth date of Alexander The Great (year) Dollars in circulation in the US in 2004 (in $) Volume of the Great American lakes (in litres) Global revenue of “Titanic” (in $) Length of the Pacific coastline (Ca, Or, Wa) (in km) Number of books published in USA, 1776 to 2004 Weight of the largest whale (in tonnes) Time’s up! 6 min This quiz is from “Software Estimation” by Steve McConnell (Microsoft Press) (C) 2006 Steve McConnell. Used with permission
  • 40. Answers Sun: 6000° C Shanghai: 31 degrees North Asian area: 44,390,000 km² Alexander was born in 356 BC Dollars in circulation: $719.9 billion Great Lakes: 6.8x10^23 litres Titanic: 1.835 billion $ Pacific Coast: 1293 kilometres Published books: 22 million Whale: 170 tonnes This quiz is from “Software Estimation” by Steve McConnell (Microsoft Press) (C) 2006 Steve McConnell. Used with permission
  • 41. And the winner is? Life is like a box of tasty Belgian chocolates!
  • 42. Software Estimation – Steve McConnell presentation 42 |
  • 43. Session Retro Thank You! for your Gift of Feedback 
  • 44.
  • 46. If you want to know more www.agilecoach.net www.nayima.be blog.nayima.be

Editor's Notes

  1. Portia and Pascal introduce themselves by sharing a bit about their background.
  2. TODO create CRD
  3. We are constantly striving to improve. Give your Gift of Feedback by completing a session retrospective.Everyone take a sheet of paper. Split it into 4 quadrants.In the top left quadrant, note down all the things that went well.In the top right quadrant, note down all the things that went wrong.In the bottom left quadrant, note down your puzzles such as outstanding questions you have as a result of the attending the session.In the bottom right quadrant, note down your lessons learned.