SlideShare a Scribd company logo
1 of 71
Download to read offline
1
Project Cost Management
Chapter 7
2
Project Cost Management
Why do we need to manage our project cost ?
Sponsor Project manager
I need fund for the
project
You didn’t tell
before. I don’t have
now
No
money……No
3
Project Cost Management
Why do we need to manage our project cost ?
4
 Definitions
 7.1 Plan Cost Management
 7.2 Estimate Costs
 7.3 Determine Budget
 7.4 Control Costs
 Earned Value Management
KEY TERMS
Project Cost Management
5
Knowledge
Area
Process
Initiating Planning Executing
Monitoring &
Control
Closing
Cost
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
 7.4 Control
Costs
Enter phase/
Start project
Exit phase/
End project
Initiating
Processes
Closing
Processes
Planning
Processes
Executing
Processes
Monitoring &
Controlling Processes
Project Cost Management
6
7.1 Plan Cost Management—The process that establishes
the policies, procedures, and documentation for planning,
managing, expending, and controlling project costs.
7.2 Estimate Costs—The process of developing an
approximation of the monetary resources needed to
complete project activities.
7.3 Determine Budget—The process of aggregating the
estimated costs of individual activities or work
packages to establish an authorized cost baseline.
7.4 Control Costs—The process of monitoring the status of
the project to update the project costs and managing
changes to the cost baseline.
Definitions
7
 Profit = Revenue – Costs
 Direct costs are costs that can be directly related
to producing the deliverable of the project: Salaries, cost
of hardware & software purchased specifically for the
project
 Indirect costs are costs that are not directly related to
the deliverable of the project, but are indirectly related
to performing the project, e.g. cost of electricity,
Internet, rent and office supplies.
8
9
 Variable Costs: change with the amount of production
(cost of material).
 Fixed Costs: do not change with production (rent,
setup costs, … etc.).
BUS IS
Fixed cost
Variable
cost
Variable
cost
Variable
cost
10
 Contingency reserves:  Cost Baseline : the cost
impacts of the remaining risk ( known-unknown )
 Management reserves:  Cost Budget : extra fund
to cover unforeseen risk or changes to the project
( unknown-unknown )
11
• Cost Of Quality
Refers to the total cost of the conformance work and the
nonconformance work
12
**** Life Cycle Costing
• Costs over the entire life of the product.
• You plan the project to produce the product at a lower
level of quality and save $9,000.
• Project is completed. Maintenance costs are $100,000
over the product's life.
• Maintenance cost could be $20,000 if higher quality was
applied.
• Your $9,000 project "savings" cost the company $80,000.
13
• Level of precision. ( measure of exactness )
The degree to which activity cost estimates will be rounded
up or down (e.g., US$100.49 to US$100, or US$995.59 to
US$1,000).
based on the scope of the activities and magnitude of the
project.
• Level of accuracy. ( assessment of correctness )
The acceptable range (e.g., ―/+ 10%) used in determining
realistic activity cost estimates is specified, and may include
an amount for contingencies
14
**** Analogous Estimate ( Top Down )
• Use actual values of a similar in fact project.
• Is used in project initiation when no details.
• Quick, less costly but less accurate.
• Difficult for projects with uncertainty.
• ( Rough Order Of Magnitude ) Accuracy of estimate
- 50 % to + 75 % or -25 % to +75 %
**** Parametric Estimate ( Budgetary)
• Is used in project Planning when more details are available.
• ( Budgetary estimate ) Accuracy of estimate is
-10 % to +25 % or -25% to +25%
15
**** Bottom-Up Estimating
• Creating detailed estimates for each part of an activity (if
available) or work package (if activities are not defined).
• Accurate WBS is needed.
• Applied before project execution.
• ( Definitive estimate ) Accuracy of estimate is
-5 % to +10 % or -10 % to +10 %
• Takes time and more costly.
• Based on details
16
GANTT Chart tells the progress of each activity
17
Acronym Term Interpretation
PV Planed Value Authorized budget for work scheduled
EV Earned Value Budget cost for work done.
AC Actual Cost Actual cost incurred for the work accomplished.
BAC
Budget At
Completion
Budget for the total project effort.
EAC
Estimate At
Completion
Expectation of the total project to cost (a forecast).
ETC
Estimate To
Complete
How much more do we expect it to cost to finish the
project (a forecast) ?
VAC
Variance At
Completion
How much over or under budget do we expect to be at
the end of the project?
**** Earned Value Management
• EVM is a Project Performance Measurement technique that
integrates scope, time, & cost data.
CV ( Cost Variance )
 The difference between Earned Value and Actual Cost
 Negative value = Cost Overrun or over budget
 Positive value = on or under cost or under budget
 Are we under or over budget  1.0 or greater is good
EV = Earned Value
AC = Actual Costs
CV = EV – AC
18
SV ( Schedule Variance )
 The difference between Earned Value and Planned Value
 Negative value = behind schedule
 Positive value = on or ahead of schedule
 Are we ahead or behind schedule  1.0 or greater is good
EV = Earned Value
PV = Planned Value
SV = EV – PV
19
CPI - Cost Performance Index
 The ratio of Earned Value to Actual Cost
 Value < 1 = Cost over budget
 Value > 1 = Cost below budget
 How efficiently are we using our resources
 Ex: We are only getting about 89 cents out of every dollar we put
into the project – THIS IS BAD
EV = Earned Value
AC = Actual Costs
CPI = EV / AC
20
SPI - Schedule Performance Index
 The ratio of Earned Value to Planned Value
 Value < 1 = behind schedule
 Value > 1 = on or ahead of schedule
 How efficiently are we using time
 Ex: We are only progressing at about 83 percent of the rate
planned – THIS IS BAD
EV = Earned Value
PV = Planned Value
SPI = EV / PV
21
22
Estimate At Completion
Budget At Completion
Variance At
Completion
EAC – Estimate At Completion
 The ratio of Budget at Completion to Cost Performance Index
 This formula is used if no variances from the BAC
have occurred
 This formula is used if you will continue typically at the
same rate of spending ( same performance ).
Default way if exam mentioned nothing.
 Past performance will be typically in future.
EAC = BAC / CPI
32
EAC – Estimate At Completion
 This formula calculates actual costs to date + a new
estimate for the remaining work.
 It is used when the original estimate was fundamentally
flawed.
 It is used when your plan is no longer valid
EAC = AC+ ETC (bottom-up)
24
EAC – Estimate At Completion
 This formula calculates Actual Costs + Remaining Budget.
 It is used when current variances are thought to be atypical
of the future.
 It is used if you will follow plan.
 It accepts the actual project performance to date (whether
favorable or unfavorable)
EAC = AC+ (BAC ‫ـــ‬ EV)
25
EAC – Estimate At Completion
 ETC work will be performed at an efficiency rate that
considers both the cost and schedule performance.
 It is used when current variances are thought to be typical
of the future and when project schedule constraints will
influence the completion of the remaining effort.
 example, it might be used when the cumulative CPI is less
than one and a firm completion date must be met.
EAC = AC+
BAC - EV
CPI X SPI
26
To-Complete Performance Index (TCPI)
If CPI > 1
If CPI < 1
 This formula divides the work remaining to be done by the
money remaining to do it.
 It answers the question "In order to stay within budget, what
rate must we meet for the remaining work?"
 Greater than one is bad and less than 1 is good.
TCPI = BAC - EV
BAC - AC
TCPI = BAC - EV
EAC - AC
27
VAC -Variance at Completion
 The difference between the Budget at Completion and the
Estimate at Completion ratio.
 This is a variance formula.
 Ex : As of today will we be under or over budget at the end
of the project
VAC = BAC ‫ـــ‬ EAC
28
29
QUIZ
A project is estimated to cost $ 50,000 with a timeline of 50
days. After 25 days, the project manager finds that 50% of
the project is complete and Actual costs are $ 50,000. What
is the Cost Performance Index (CPI) ?
A. The CPI is 1
B. The CPI is 2
C. The CPI is 0.5
D. The CPI is 1.5
30
QUIZ
A project is estimated to cost $ 50,000 with a timeline of 50
days. After 25 days, the project manager finds that 50% of
the project is complete and Actual costs are $ 50,000. What
is the Cost Performance Index (CPI) ?
A. The CPI is 1
B. The CPI is 2
C. The CPI is 0.5
D. The CPI is 1.5
Answer : C
31
Task Progress Cost spent
Side 1 ||||||||||||||||||||||||||||||||||||||||100% $1,200
Side 2 ||||||||||||||||||||||||||||||||||||||||100% $1,000
Side 3 ||||||||||||||||||||||||||||||75% $750
Side 4 ||||||||||||||||||||50% $500
Side 5 0% $0
Side 6 0% $0
Question
You have a project to build a box. The box is six sided. Each side is to take
one day to build and is budgeted for $1000 per side. The sides are
planned to be completed one after the other. Today is the end of day
three.
• Using the following project status chart, calculate PV, EV, AC, BAC,
CV, CPI, SV, SPI, EAC, ETC, VAC.
32
Parameter Calculation Result
PV 1000 + 1000 + 1000 3000
EV (100% x 1000) + (100% x 1000) + (75% x 1000) + (50% x 1000) 3250
AC 1200 + 1000 + 750 + 500 3450
BAC 6 x 1000 6000
CV EV – AC = 3250 - 3450 -200
CPI EV / AC = 3250 / 3450 0.942
SV EV – PV = 3250 - 3000 250
SPI EV / PV = 3250/ 3000 1.08
EAC BAC / CPI = 6000 / 0.942 6369.42
ETC EAC – AC = 6369.42 - 3450 2919.42
VAC BAC – EAC = 6000 – 6369.42 -369.42
• Over budget, getting 0.94 dollar for every dollar we spent,
• Ahead schedule, progressing 108% of the rate planned,
• Probably will spend $6369.42 at the end (estimation),
• Need $2919.42 to complete,
• Over budget at the end for about $369.42 (estimation)
7.1- Plan Cost
Management
33
34
7.1- Plan Cost Management.
The process that establishes the policies, procedures, and
documentation for planning, managing, expending, and
controlling project costs.
35
7.1- Plan Cost Management INPUTS
36
1. Project
Management Plan
Scope Baseline
Schedule Baseline
2. Project Charter
3- EEF
4- OPA
7.1- Plan Cost Management T & T
1. Expert Judgment
1. Analytical Techniques
1. Meetings
7.1- Plan Cost Management OUTPUTS
37
CostManagementPlan • Units of Measure staff hours, staff days, meters, liters,
tons, kilometers
• Level of Precision (measure of exactness)
• Level of Accuracy (assessment of correctness)
• Control Accounts
• Control Thresholds (Percentage deviations from the
baseline plan.)
• Rules for Performance Measurement
Specify tracking methodologies
Earned value measurement techniques
Earned value management computation equations
• Reporting Formats (cost reports)
• Process Description
• Additional Details
7.2- Estimate Cost
38
39
7.2 Estimate Costs
The process of developing an approximation of the
monetary resources needed to complete project activities.
40
7.2- Estimate Cost INPUTS
41
1. Cost Management Plan
2. Human Resource Management Plan
3. Scope Baselines
Scope Statement / WBS /
WBS Dictionary
4. Project Schedule
5. Risk Register (Risk mitigation costs)
6. EEF
 Market Conditions
 Published Commercial Data
7- OPA
 Cost Estimating Policies
 Cost Estimating Templates
 Historical Information
 Lessons Learned
7.2- Estimate Cost T & T
42
1. Expert Judgment
2. Analogous Estimating (Top down)
3. Parametric Estimating
4. Bottom-up estimating
5. Three-point
Estimation
(Beta Distribution) Weighted Average (P+4M+O) / 6
(Triangular Distribution) ( P+M+O ) / 3
6. Reserve
Analysis
• Contingency Reserve ( Known Unknown ) by project
manager for activities
• Management Reserve ( Unknown Unknown ) by
management for whole project
7. Cost Of
Quality
• Cost Of Conformance
• Cost Of Non Conformance
8. PMIS
9. Group Decision making techniques: Unanimity, Majority (>50%),
Plurality, Dictatorship
10. Vendor Bid analysis
7.2- Estimate Cost Outputs
43
1. Activity Cost Estimates
2. Basis of Estimates
• how the cost estimate was derived
• Documentation of :
Assumptions
Known constraints
Range of possible estimates
3. Project Documents Updates
44
7.3- Determine Budget
45
7.3- Determine Budget
The process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost
baseline
46
7.3- Determine Budget INPUTS
47
1. Cost Management Plan
2. Scope Baseline
3. Activity Costs Estimates
4. Basis of Estimates
5. Project Schedule
6. Resource
Calendars
which resources are assigned to the project and
when they are assigned
7. Risk Register
8. Agreements
9. OPA
• Existing formal and informal cost budgeting-
related policies, procedures, and guidelines.
• Cost budgeting tools.
• Reporting methods.
7.3- Determine Budget T & T
48
1. Cost Aggregation
2. Reserve Analysis
3. Expert Judgment
4. Historical
Relationships
• Historical information used to develop the model.
• Parameters used in the model are readily quantifiable.
5. Funding
Limit
Reconciliation
When to supply the fund needed on time along with the
work being done
7.3- Determine Budget Outputs
49
1. Cost Baseline
the approved version of the time-phased project
budget
Known UnknownUnknown Unknown
This is the level of divisions to track measurement
7.3- Determine Budget Outputs
50
2. Project
Funding
Requirements
When I will provide fund supply to work being done
51
7.4- Control Cost
52
7.4- Control Cost.
The process of monitoring the status of the project to
update the project costs and managing changes to the cost
baseline
53
7.4- Control Cost INPUTS
54
1. Project Management
Plan
• Cost Baseline
• Cost Management Plan
2. Project Funding Requirements
3. Work Performance Data
4. OPA
1. Earned Value Management
2. Forecasting
3.To-Complete Performance Index
4. Performance Reviews
• Variance Analysis
• Trend Analysis
• Earned Value Performance
5. ReserveAnalysis
6. PMIS
7.4- Control Cost T & T
7.4- Control Cost Outputs
55
1. Work Performance Measurements
2. Budget Forecasts ( EAC / ETC )
3. Change Requests
4. Project Management Plan
Updates
• Cost baseline.
• Cost management plan.
5. OPA Updates
6. Project Document Updates • Cost estimates, and
• Basis of estimates.
56
Questions
l. One common way to compute estimate at completion
(EAC) is to take the budget at completion BAC
and:
• A. Divide by SPI.
• B. Multiply by SPI.
• C. Multiply by CPI.
• D. Divide by CPI.
• Answer : D
57
Questions
2. Estimate at completion (EAC) is a periodic evaluation of:
A. The cost of work completed.
B. The value of work performed.
C. The anticipated total cost at project completion.
D. What it will cost to finish the project.
• Answer : C
58
Questions
3. If earned value (EV) = 350, actual cost (AC) = 400, and
planned value (PV) = 325,
what is cost variance (CV)?
A. 350
B. -75
c. 400
D. -50
• Answer : D
59
Questions
4. Analogous estimating:
A. Uses bottom-up estimating techniques.
B. Is used most frequently during project executing.
C. Uses top-down estimating techniques.
D. Calculates estimates using actual detailed historical
costs.
• Answer : C
60
Questions
5. A cost performance index (CPI) of 0.89 means:
A. At this time, we expect the total project to cost 89
percent more than planned.
B. When the project is completed, we will have spent 89
percent more than planned.
C. The project is progressing at 89 percent of the rate
planned.
D. The project is getting 89 cents out of every dollar
invested.
• Answer : D
61
Questions
6. A schedule performance index (SPI) of 0.76 means:
A. You are over budget.
B. You are ahead of schedule.
C. You are progressing at 76 percent of the rate originally
planned.
D. You are progressing at 24 percent of the rate originally
planned.
• Answer : C
62
Questions
7. Which type of cost is team training?
A. Direct
B. NPV
C. Indirect
D. Fixed
• Answer : A
63
Questions
8. Project setup costs are an example of:
A. Variable costs.
B. Fixed costs.
C. Overhead costs.
D. Opportunity costs.
• Answer : B
64
Questions
9. The project manager is allocating overall cost estimates
to individual activities to establish a baseline for measuring
project performance. What process is this?
A. Cost Management
B. Estimate Costs
C. Determine Budget
D. Control Costs
• Answer : C
65
Questions
10. You provide a project cost estimate for the project to the
project sponsor. He is unhappy with the estimate, because
he thinks the price should be lower. He asks you to cut 15
percent off the project estimate. What should you do?
A. Start the project and constantly look for cost savings.
B. Tell all the team members to cut 15 percent from their
estimates.
C. Inform the sponsor of the activities to be cut.
D. Add additional resources with low hourly rates.
• Answer : C
66
11. Lucy is currently preparing a high-level cost estimate for
her project in the initiation phase. Given the limited detail
available to her, what would you expect the range of her
estimate to be and what would you call such an estimate?
A. -25 to +75 %, Rough Order of Magnitude.
B. -5 to +10 %, Narrow.
C. 25 to +25 %, Rough Order of Magnitude.
D. -1 to +1 %, Definitive.
Questions
67
11. Lucy is currently preparing a high-level cost estimate for
her project in the initiation phase. Given the limited detail
available to her, what would you expect the range of her
estimate to be and what would you call such an estimate?
A. -25 to +75 %, Rough Order of Magnitude.
B. -5 to +10 %, Narrow.
C. 25 to +25 %, Rough Order of Magnitude.
D. -1 to +1 %, Definitive.
Answer : A
Questions
68
12. The Cost Performance Baseline is a time-phased
budget and is used as a basis to measure, monitor, and
control overall cost performance of the project. It is usually
displayed in the form of:
A. Pie-chart
B. An inverted S curve.
C. A Z curve
D. An S-curve
Questions
69
12. The Cost Performance Baseline is a time-phased
budget and is used as a basis to measure, monitor, and
control overall cost performance of the project. It is usually
displayed in the form of:
A. Pie-chart
B. An inverted S curve.
C. A Z curve
D. An S-curve
Answer : D
Questions
70
13. Contingency Reserves are estimated costs to be used
at the discretion of the project manager to deal with:
A. Anticipated but not certain events.
B. Scope creep
C. Anticipated and certain events
D. Unanticipated events
Questions
71
13. Contingency Reserves are estimated costs to be used
at the discretion of the project manager to deal with:
A. Anticipated but not certain events.
B. Scope creep
C. Anticipated and certain events
D. Unanticipated events
Answer : A
Questions

More Related Content

What's hot

Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Managementpankajsh10
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management Ahmad Maharma, PMP,RMP
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Agus Suhanto
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementMohamed Loey
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management Yesica Adicondro
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Managementmovinghats
 
Project management and Success Criteria
Project management and Success Criteria Project management and Success Criteria
Project management and Success Criteria ujjwal Mania
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionJohn Khateeb
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Editionpankajsh10
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
Project management
Project managementProject management
Project managementJay Raval
 

What's hot (20)

Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
Pmbok 4th edition chapter 7 - Project Cost Management
Pmbok 4th edition   chapter 7 - Project Cost Management Pmbok 4th edition   chapter 7 - Project Cost Management
Pmbok 4th edition chapter 7 - Project Cost Management
 
Project management
Project managementProject management
Project management
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 
Project Resource Management - PMBOK6
Project Resource Management - PMBOK6Project Resource Management - PMBOK6
Project Resource Management - PMBOK6
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project management and Success Criteria
Project management and Success Criteria Project management and Success Criteria
Project management and Success Criteria
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 

Viewers also liked

Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesNishant Munjal
 

Viewers also liked (20)

Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
Pmp procurement chapter 12
Pmp procurement chapter 12Pmp procurement chapter 12
Pmp procurement chapter 12
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Quality Vs. Grade
Quality Vs. GradeQuality Vs. Grade
Quality Vs. Grade
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
4.contracting
4.contracting4.contracting
4.contracting
 
Project Monitoring and Controlling Processes
Project Monitoring and Controlling ProcessesProject Monitoring and Controlling Processes
Project Monitoring and Controlling Processes
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 

Similar to Pmp cost chapter 7

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 

Similar to Pmp cost chapter 7 (20)

Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Earned value management
Earned value managementEarned value management
Earned value management
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 

Recently uploaded

Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdffillmonipdc
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skillskristinalimarenko7
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 

Recently uploaded (20)

Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdf
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skills
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 

Pmp cost chapter 7

  • 2. 2 Project Cost Management Why do we need to manage our project cost ? Sponsor Project manager I need fund for the project You didn’t tell before. I don’t have now No money……No
  • 3. 3 Project Cost Management Why do we need to manage our project cost ?
  • 4. 4  Definitions  7.1 Plan Cost Management  7.2 Estimate Costs  7.3 Determine Budget  7.4 Control Costs  Earned Value Management KEY TERMS
  • 5. Project Cost Management 5 Knowledge Area Process Initiating Planning Executing Monitoring & Control Closing Cost 7.1 Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget  7.4 Control Costs Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Planning Processes Executing Processes Monitoring & Controlling Processes
  • 6. Project Cost Management 6 7.1 Plan Cost Management—The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. 7.2 Estimate Costs—The process of developing an approximation of the monetary resources needed to complete project activities. 7.3 Determine Budget—The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. 7.4 Control Costs—The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline.
  • 7. Definitions 7  Profit = Revenue – Costs  Direct costs are costs that can be directly related to producing the deliverable of the project: Salaries, cost of hardware & software purchased specifically for the project  Indirect costs are costs that are not directly related to the deliverable of the project, but are indirectly related to performing the project, e.g. cost of electricity, Internet, rent and office supplies.
  • 8. 8
  • 9. 9  Variable Costs: change with the amount of production (cost of material).  Fixed Costs: do not change with production (rent, setup costs, … etc.). BUS IS Fixed cost Variable cost Variable cost Variable cost
  • 10. 10  Contingency reserves:  Cost Baseline : the cost impacts of the remaining risk ( known-unknown )  Management reserves:  Cost Budget : extra fund to cover unforeseen risk or changes to the project ( unknown-unknown )
  • 11. 11 • Cost Of Quality Refers to the total cost of the conformance work and the nonconformance work
  • 12. 12 **** Life Cycle Costing • Costs over the entire life of the product. • You plan the project to produce the product at a lower level of quality and save $9,000. • Project is completed. Maintenance costs are $100,000 over the product's life. • Maintenance cost could be $20,000 if higher quality was applied. • Your $9,000 project "savings" cost the company $80,000.
  • 13. 13 • Level of precision. ( measure of exactness ) The degree to which activity cost estimates will be rounded up or down (e.g., US$100.49 to US$100, or US$995.59 to US$1,000). based on the scope of the activities and magnitude of the project. • Level of accuracy. ( assessment of correctness ) The acceptable range (e.g., ―/+ 10%) used in determining realistic activity cost estimates is specified, and may include an amount for contingencies
  • 14. 14 **** Analogous Estimate ( Top Down ) • Use actual values of a similar in fact project. • Is used in project initiation when no details. • Quick, less costly but less accurate. • Difficult for projects with uncertainty. • ( Rough Order Of Magnitude ) Accuracy of estimate - 50 % to + 75 % or -25 % to +75 % **** Parametric Estimate ( Budgetary) • Is used in project Planning when more details are available. • ( Budgetary estimate ) Accuracy of estimate is -10 % to +25 % or -25% to +25%
  • 15. 15 **** Bottom-Up Estimating • Creating detailed estimates for each part of an activity (if available) or work package (if activities are not defined). • Accurate WBS is needed. • Applied before project execution. • ( Definitive estimate ) Accuracy of estimate is -5 % to +10 % or -10 % to +10 % • Takes time and more costly. • Based on details
  • 16. 16 GANTT Chart tells the progress of each activity
  • 17. 17 Acronym Term Interpretation PV Planed Value Authorized budget for work scheduled EV Earned Value Budget cost for work done. AC Actual Cost Actual cost incurred for the work accomplished. BAC Budget At Completion Budget for the total project effort. EAC Estimate At Completion Expectation of the total project to cost (a forecast). ETC Estimate To Complete How much more do we expect it to cost to finish the project (a forecast) ? VAC Variance At Completion How much over or under budget do we expect to be at the end of the project? **** Earned Value Management • EVM is a Project Performance Measurement technique that integrates scope, time, & cost data.
  • 18. CV ( Cost Variance )  The difference between Earned Value and Actual Cost  Negative value = Cost Overrun or over budget  Positive value = on or under cost or under budget  Are we under or over budget  1.0 or greater is good EV = Earned Value AC = Actual Costs CV = EV – AC 18
  • 19. SV ( Schedule Variance )  The difference between Earned Value and Planned Value  Negative value = behind schedule  Positive value = on or ahead of schedule  Are we ahead or behind schedule  1.0 or greater is good EV = Earned Value PV = Planned Value SV = EV – PV 19
  • 20. CPI - Cost Performance Index  The ratio of Earned Value to Actual Cost  Value < 1 = Cost over budget  Value > 1 = Cost below budget  How efficiently are we using our resources  Ex: We are only getting about 89 cents out of every dollar we put into the project – THIS IS BAD EV = Earned Value AC = Actual Costs CPI = EV / AC 20
  • 21. SPI - Schedule Performance Index  The ratio of Earned Value to Planned Value  Value < 1 = behind schedule  Value > 1 = on or ahead of schedule  How efficiently are we using time  Ex: We are only progressing at about 83 percent of the rate planned – THIS IS BAD EV = Earned Value PV = Planned Value SPI = EV / PV 21
  • 22. 22 Estimate At Completion Budget At Completion Variance At Completion
  • 23. EAC – Estimate At Completion  The ratio of Budget at Completion to Cost Performance Index  This formula is used if no variances from the BAC have occurred  This formula is used if you will continue typically at the same rate of spending ( same performance ). Default way if exam mentioned nothing.  Past performance will be typically in future. EAC = BAC / CPI 32
  • 24. EAC – Estimate At Completion  This formula calculates actual costs to date + a new estimate for the remaining work.  It is used when the original estimate was fundamentally flawed.  It is used when your plan is no longer valid EAC = AC+ ETC (bottom-up) 24
  • 25. EAC – Estimate At Completion  This formula calculates Actual Costs + Remaining Budget.  It is used when current variances are thought to be atypical of the future.  It is used if you will follow plan.  It accepts the actual project performance to date (whether favorable or unfavorable) EAC = AC+ (BAC ‫ـــ‬ EV) 25
  • 26. EAC – Estimate At Completion  ETC work will be performed at an efficiency rate that considers both the cost and schedule performance.  It is used when current variances are thought to be typical of the future and when project schedule constraints will influence the completion of the remaining effort.  example, it might be used when the cumulative CPI is less than one and a firm completion date must be met. EAC = AC+ BAC - EV CPI X SPI 26
  • 27. To-Complete Performance Index (TCPI) If CPI > 1 If CPI < 1  This formula divides the work remaining to be done by the money remaining to do it.  It answers the question "In order to stay within budget, what rate must we meet for the remaining work?"  Greater than one is bad and less than 1 is good. TCPI = BAC - EV BAC - AC TCPI = BAC - EV EAC - AC 27
  • 28. VAC -Variance at Completion  The difference between the Budget at Completion and the Estimate at Completion ratio.  This is a variance formula.  Ex : As of today will we be under or over budget at the end of the project VAC = BAC ‫ـــ‬ EAC 28
  • 29. 29 QUIZ A project is estimated to cost $ 50,000 with a timeline of 50 days. After 25 days, the project manager finds that 50% of the project is complete and Actual costs are $ 50,000. What is the Cost Performance Index (CPI) ? A. The CPI is 1 B. The CPI is 2 C. The CPI is 0.5 D. The CPI is 1.5
  • 30. 30 QUIZ A project is estimated to cost $ 50,000 with a timeline of 50 days. After 25 days, the project manager finds that 50% of the project is complete and Actual costs are $ 50,000. What is the Cost Performance Index (CPI) ? A. The CPI is 1 B. The CPI is 2 C. The CPI is 0.5 D. The CPI is 1.5 Answer : C
  • 31. 31 Task Progress Cost spent Side 1 ||||||||||||||||||||||||||||||||||||||||100% $1,200 Side 2 ||||||||||||||||||||||||||||||||||||||||100% $1,000 Side 3 ||||||||||||||||||||||||||||||75% $750 Side 4 ||||||||||||||||||||50% $500 Side 5 0% $0 Side 6 0% $0 Question You have a project to build a box. The box is six sided. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planned to be completed one after the other. Today is the end of day three. • Using the following project status chart, calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC.
  • 32. 32 Parameter Calculation Result PV 1000 + 1000 + 1000 3000 EV (100% x 1000) + (100% x 1000) + (75% x 1000) + (50% x 1000) 3250 AC 1200 + 1000 + 750 + 500 3450 BAC 6 x 1000 6000 CV EV – AC = 3250 - 3450 -200 CPI EV / AC = 3250 / 3450 0.942 SV EV – PV = 3250 - 3000 250 SPI EV / PV = 3250/ 3000 1.08 EAC BAC / CPI = 6000 / 0.942 6369.42 ETC EAC – AC = 6369.42 - 3450 2919.42 VAC BAC – EAC = 6000 – 6369.42 -369.42 • Over budget, getting 0.94 dollar for every dollar we spent, • Ahead schedule, progressing 108% of the rate planned, • Probably will spend $6369.42 at the end (estimation), • Need $2919.42 to complete, • Over budget at the end for about $369.42 (estimation)
  • 34. 34 7.1- Plan Cost Management. The process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs.
  • 35. 35
  • 36. 7.1- Plan Cost Management INPUTS 36 1. Project Management Plan Scope Baseline Schedule Baseline 2. Project Charter 3- EEF 4- OPA 7.1- Plan Cost Management T & T 1. Expert Judgment 1. Analytical Techniques 1. Meetings
  • 37. 7.1- Plan Cost Management OUTPUTS 37 CostManagementPlan • Units of Measure staff hours, staff days, meters, liters, tons, kilometers • Level of Precision (measure of exactness) • Level of Accuracy (assessment of correctness) • Control Accounts • Control Thresholds (Percentage deviations from the baseline plan.) • Rules for Performance Measurement Specify tracking methodologies Earned value measurement techniques Earned value management computation equations • Reporting Formats (cost reports) • Process Description • Additional Details
  • 39. 39 7.2 Estimate Costs The process of developing an approximation of the monetary resources needed to complete project activities.
  • 40. 40
  • 41. 7.2- Estimate Cost INPUTS 41 1. Cost Management Plan 2. Human Resource Management Plan 3. Scope Baselines Scope Statement / WBS / WBS Dictionary 4. Project Schedule 5. Risk Register (Risk mitigation costs) 6. EEF  Market Conditions  Published Commercial Data 7- OPA  Cost Estimating Policies  Cost Estimating Templates  Historical Information  Lessons Learned
  • 42. 7.2- Estimate Cost T & T 42 1. Expert Judgment 2. Analogous Estimating (Top down) 3. Parametric Estimating 4. Bottom-up estimating 5. Three-point Estimation (Beta Distribution) Weighted Average (P+4M+O) / 6 (Triangular Distribution) ( P+M+O ) / 3 6. Reserve Analysis • Contingency Reserve ( Known Unknown ) by project manager for activities • Management Reserve ( Unknown Unknown ) by management for whole project 7. Cost Of Quality • Cost Of Conformance • Cost Of Non Conformance 8. PMIS 9. Group Decision making techniques: Unanimity, Majority (>50%), Plurality, Dictatorship 10. Vendor Bid analysis
  • 43. 7.2- Estimate Cost Outputs 43 1. Activity Cost Estimates 2. Basis of Estimates • how the cost estimate was derived • Documentation of : Assumptions Known constraints Range of possible estimates 3. Project Documents Updates
  • 45. 45 7.3- Determine Budget The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline
  • 46. 46
  • 47. 7.3- Determine Budget INPUTS 47 1. Cost Management Plan 2. Scope Baseline 3. Activity Costs Estimates 4. Basis of Estimates 5. Project Schedule 6. Resource Calendars which resources are assigned to the project and when they are assigned 7. Risk Register 8. Agreements 9. OPA • Existing formal and informal cost budgeting- related policies, procedures, and guidelines. • Cost budgeting tools. • Reporting methods.
  • 48. 7.3- Determine Budget T & T 48 1. Cost Aggregation 2. Reserve Analysis 3. Expert Judgment 4. Historical Relationships • Historical information used to develop the model. • Parameters used in the model are readily quantifiable. 5. Funding Limit Reconciliation When to supply the fund needed on time along with the work being done
  • 49. 7.3- Determine Budget Outputs 49 1. Cost Baseline the approved version of the time-phased project budget Known UnknownUnknown Unknown This is the level of divisions to track measurement
  • 50. 7.3- Determine Budget Outputs 50 2. Project Funding Requirements When I will provide fund supply to work being done
  • 52. 52 7.4- Control Cost. The process of monitoring the status of the project to update the project costs and managing changes to the cost baseline
  • 53. 53
  • 54. 7.4- Control Cost INPUTS 54 1. Project Management Plan • Cost Baseline • Cost Management Plan 2. Project Funding Requirements 3. Work Performance Data 4. OPA 1. Earned Value Management 2. Forecasting 3.To-Complete Performance Index 4. Performance Reviews • Variance Analysis • Trend Analysis • Earned Value Performance 5. ReserveAnalysis 6. PMIS 7.4- Control Cost T & T
  • 55. 7.4- Control Cost Outputs 55 1. Work Performance Measurements 2. Budget Forecasts ( EAC / ETC ) 3. Change Requests 4. Project Management Plan Updates • Cost baseline. • Cost management plan. 5. OPA Updates 6. Project Document Updates • Cost estimates, and • Basis of estimates.
  • 56. 56 Questions l. One common way to compute estimate at completion (EAC) is to take the budget at completion BAC and: • A. Divide by SPI. • B. Multiply by SPI. • C. Multiply by CPI. • D. Divide by CPI. • Answer : D
  • 57. 57 Questions 2. Estimate at completion (EAC) is a periodic evaluation of: A. The cost of work completed. B. The value of work performed. C. The anticipated total cost at project completion. D. What it will cost to finish the project. • Answer : C
  • 58. 58 Questions 3. If earned value (EV) = 350, actual cost (AC) = 400, and planned value (PV) = 325, what is cost variance (CV)? A. 350 B. -75 c. 400 D. -50 • Answer : D
  • 59. 59 Questions 4. Analogous estimating: A. Uses bottom-up estimating techniques. B. Is used most frequently during project executing. C. Uses top-down estimating techniques. D. Calculates estimates using actual detailed historical costs. • Answer : C
  • 60. 60 Questions 5. A cost performance index (CPI) of 0.89 means: A. At this time, we expect the total project to cost 89 percent more than planned. B. When the project is completed, we will have spent 89 percent more than planned. C. The project is progressing at 89 percent of the rate planned. D. The project is getting 89 cents out of every dollar invested. • Answer : D
  • 61. 61 Questions 6. A schedule performance index (SPI) of 0.76 means: A. You are over budget. B. You are ahead of schedule. C. You are progressing at 76 percent of the rate originally planned. D. You are progressing at 24 percent of the rate originally planned. • Answer : C
  • 62. 62 Questions 7. Which type of cost is team training? A. Direct B. NPV C. Indirect D. Fixed • Answer : A
  • 63. 63 Questions 8. Project setup costs are an example of: A. Variable costs. B. Fixed costs. C. Overhead costs. D. Opportunity costs. • Answer : B
  • 64. 64 Questions 9. The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this? A. Cost Management B. Estimate Costs C. Determine Budget D. Control Costs • Answer : C
  • 65. 65 Questions 10. You provide a project cost estimate for the project to the project sponsor. He is unhappy with the estimate, because he thinks the price should be lower. He asks you to cut 15 percent off the project estimate. What should you do? A. Start the project and constantly look for cost savings. B. Tell all the team members to cut 15 percent from their estimates. C. Inform the sponsor of the activities to be cut. D. Add additional resources with low hourly rates. • Answer : C
  • 66. 66 11. Lucy is currently preparing a high-level cost estimate for her project in the initiation phase. Given the limited detail available to her, what would you expect the range of her estimate to be and what would you call such an estimate? A. -25 to +75 %, Rough Order of Magnitude. B. -5 to +10 %, Narrow. C. 25 to +25 %, Rough Order of Magnitude. D. -1 to +1 %, Definitive. Questions
  • 67. 67 11. Lucy is currently preparing a high-level cost estimate for her project in the initiation phase. Given the limited detail available to her, what would you expect the range of her estimate to be and what would you call such an estimate? A. -25 to +75 %, Rough Order of Magnitude. B. -5 to +10 %, Narrow. C. 25 to +25 %, Rough Order of Magnitude. D. -1 to +1 %, Definitive. Answer : A Questions
  • 68. 68 12. The Cost Performance Baseline is a time-phased budget and is used as a basis to measure, monitor, and control overall cost performance of the project. It is usually displayed in the form of: A. Pie-chart B. An inverted S curve. C. A Z curve D. An S-curve Questions
  • 69. 69 12. The Cost Performance Baseline is a time-phased budget and is used as a basis to measure, monitor, and control overall cost performance of the project. It is usually displayed in the form of: A. Pie-chart B. An inverted S curve. C. A Z curve D. An S-curve Answer : D Questions
  • 70. 70 13. Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with: A. Anticipated but not certain events. B. Scope creep C. Anticipated and certain events D. Unanticipated events Questions
  • 71. 71 13. Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with: A. Anticipated but not certain events. B. Scope creep C. Anticipated and certain events D. Unanticipated events Answer : A Questions