PROJECT SCHEDULE
In project management, a schedule is a listing of a project milestone
activities, and deliverables, usually intended start and finish dates.
In many industries such as engineering and construction the
development and maintenance of project schedule is a responsibility
of a full time schedule or team of schedulers depending on the size
of the project.
TERMINOLOGIES IN PROJECT SCHEDULING
MILESTONE: A milestone is a significant event that normally has no duration
It often takes several activities and a lot of work to complete a milestone
They’re useful tools for setting schedule goals and monitoring progress
Examples include obtaining customer sign-off on key documents or
completion of specific products
Milestones should be:
Specific Measurable Assignable Realistic Time-framed
BASIC STEPS TAKEN IN PROJECT
MANAGEMENT
•Define Activities – identifying the specific actions to be performed to produce
the project deliverables
•Sequencing Activities – identifying and documenting relationships among the
project activities.
•Estimate Activity Resources – estimating the type and quantities of material,
people, equipment, or supplies required to perform each activity.
•Estimate Activity Duration – approximating the number of work periods
needed to complete individual activities with estimated resources.
BASIC STEPS TAKEN IN PROJECT
MANAGEMENT -continue
•Develop Schedule – analyzing activity sequences, durations,
resource requirements, and schedule constraints to create the
project schedule.
•Control Schedule – monitoring the status of the project to update
project progress and managing changes to the schedule baseline
TECHNIQUE USED PROJECT SCHEDULING
 Before a project schedule can be created the schedule maker.
It should have a WORK BREAKDOWN STRUCTURE (WBS) an effort
estimate for each task and resource list with available resource.
WORK BREAKDOWN STRUCTURE
Dividing complex projects to simpler and manageable tasks is the
process identified as WORK BREAKDOWN STRUCTURE (WBS).
Usually, the project managers use this method for simplifying the
project execution. In WBS, much larger tasks are broken-down to
manageable chunks of work. These chunks can be easily supervised
and estimated.
Further sub dividing can be said as Decomposition.
WORK BREAKDOWN
STRUCTURE(CONTINUE)
In project management and systems engineering, is a deliverable
oriented decomposition of a project into smaller components.
A work breakdown structure element may be a product, data, a
service, or any combination. A WBS also provides the necessary
framework for detailed cost estimating and control along with
providing guidance for schedule development and control
EXAMPLE ON WBS
AIM OF WORK BREAKDOWN STRUCTURE
Giving visibility to important work efforts.
Giving visibility to risky work efforts.
Illustrate the correlation between the activities and deliverables.
Show clear ownership by task leaders.
METHODS FOR MAKING A PROJECT SCHEDULE
HEALTHY
• Schedule must be constantly updated.
• The EAC(Estimation At Completion) value must be equal base line
value.
•The remaining efforts must be approximately distributed among team
members(taking vacation into consideration).
SCHEDULING TOOLS OR TECHNIQUES
MOSTLY COMMONLY USED METHODS ARE:
1. GANTT CHART
2. NETWORK DIAGRAMS(PERT/CPM)
SCHEDULING TOOLS
Gantt chart
A bar chart that is a visual representation of the sequencing and
duration of activities on any given project.
Useful:
◦ Easy to read
◦ Give each team members overview of the project.
◦ Indicate clearly the status of each activity
◦ Can be drawn to show the budgets, equipment's usage
GANTT CHART
Gantt charts are used as a tool to monitor and control the project progress.
Developed in 1918 by H.L. Gantt
A Gantt chart is a graphical presentation that displays activities as follows:
◦ Time is measured on the horizontal axis. A horizontal bar is drawn proportionately to an
activity’ s expected completion time.
◦ Each activity is listed on the vertical axis.
In an earliest time Gantt chart each bar begins and ends at the earliest
start/finish the activity can take place.
APPLICATION OF GANTT CHART
oGantt chart can be used as a visual aid for tracking the progress of project
activities.
oAppropriate percentage of a bar is shaded to document the completed work.
oThe manager can easily see if the project is progressing on schedule (with
respect to the earliest possible completion times).
ADVANTAGES AND DISADVANTAGES OF
GANTT CHART
Advantages.
◦ Easy to construct
◦ Gives earliest completion date.
◦ Provides a schedule of earliest possible start and finish times of activities.
Disadvantages
◦ Gives only one possible schedule (earliest).
◦ Does not show whether the project is behind schedule.
◦ Does not demonstrate the effects of delays in any one activity on the start of
another activity, thus on the project completion time.
AN EXAMPLE OF GANTT CHART
NETWORK DIAGRAM
 Is a graphical depiction of project tasks and their inter-relationships.
 The distinguishing feature of a network diagram is that the ordering of
tasks is shown by connecting with its predecessor and successor tasks.
 Network diagramming is a critical path scheduling technique used for
controlling resources.
 Critical path scheduling
A Scheduling Technique whose order and duration of a sequence
of task activities directly affect the completion date of a project.
CRITICAL PATH METHOD(CPM)
CPM is a network diagramming technique used to predict total project
duration.
A critical path for a project is the series of activities that determines the
earliest time by which the project can be completed.
The critical path is the longest path through the network diagram and
has the least amount of slack or float.
Slack or float is the amount of time an activity can be delayed without
delaying a succeeding activity or the project finish date.
Reducing an activity’s completion time is called “crashing.”
AN EXAMPLE FOR CRITICAL PATH
METHOD
84
A
D
C
B
E
F G
I
H
Baja Burrito Restaurants –
Network presentation
L
O
J NM
K
P
PROGRAM EVALUATION REVIEW
TECHNIQUE (PERT)
One of the most difficult and most error prone activities when constructing
a Project Schedule is the determination of the TIME DURATION for each
task within a Work Breakdown Structure (WBS), specially when there is a
high degree of complexity and uncertainty about a task.
PERT is a technique used to calculate the Expected Time for a tasks.
PERT is a technique that uses Optimistic time (O), Pessimistic time (P) and
Realistic Time (R) estimates to calculate the EXPECTED TIME (ET) or a
particular task.
PROGRAM EVALUATION REVIEW TECHNIQUE
(PERT) -continue
PERT is a technique that uses Optimistic time (o), Pessimistic time (p)
and Realistic Time (r) estimates to calculate the EXPECTED TIME (ET) or a
particular task.
The Optimistic time (o) and Pessimistic time (p) reflects the minimum
and maximum possible periods of time for an activity to be completed.
The Realistic time (r) or the Most likely time , reflects the Project
manager’s “Best Guess” of the amount of time required for a task
completion.
PROGRAM EVALUATION REVIEW
TECHNIQUE (PERT) -continue
CALCULATING EXPECTED COMPLETION TIME (ET)
o + 4r + p
ET = -------------------
6
Because the expected Completion time should be closer to the realistic
time (r), it is typically weighed Four times more than the Optimistic time
(o) and the Pessimistic time (p). Once you add these values together , it
must be divided by 6 to determine the Expected Time for a task.
PROGRAM EVALUATION REVIEW
TECHNIQUE (PERT) -continue
oPERT Chart is consisted of TASKS and EVENTS.
oAn EVENT is called a Milestone, representing a point in time, such as the Start or
Completion of a Task.
oA circle or a Rectangle shape NODE is used to represent an EVENT.
oEvery PERT Chart has one Beginning and one End NODE that represents the Start
and Finish of a Project.
oThe Earliest and Latest Time is both Zero in Starting Event.
oA TASK also called Activity, is depicted by an ARROW Connecting Events.
oA Dashed Arrow represents a DUMMY TASK which is the dependency between
two events without requiring any resource.
PERT/CPM Network
◦ Activity-On-Nodes
◦ Activity-On-Arrows
ACTIVITY-ON-NODE:
Activity-On-Nodes each activity is represented by nod or a box.
PRECEDENCE DIAGRAMMING METHOD
The precedence diagramming method (PDM) is a way of
constructing a project network diagram that employs boxes or
rectangles (nodes) to represent the activities and connects them
with arrows that show the dependencies. Essentially, it is an AON
network logic diagram with time added.
To calculate project duration using a PDM, you identify the early
start and early finishes using a calculation known as forward pass. A
similar calculation, known as backward pass, is used to calculate the
critical path for the project with the float of each activity.
-continue
FORWARD PASS:
Forward pass is the calculation of the early start and early finish
dates for the uncompleted portions of all network activities.
BACKWARD PASS:
Backward pass is the calculation of late finish dates and late start
dates for the uncompleted portions of all network activities. It is
determined by working backwards through the network logic from
the project’s end date. The end date may be calculated in a forward
pass or set by the customer or sponsor.
DIFFERENT TASK DEPENDENCY
RELATIONSHIPS(ACTIVITY-ON-NODES)
Finish to Start
Activity A must be finished before Activity B can start
A B
Start to Start
A must start in order for B to start
A
B
Finish To Finish
A must be finished in order for B to finish
A
B
Combinations
Extending the gap of writing and typing, since durations are different
and since typing cannot finish until writing finished.
A B
ACTIVITY ON ARROW
The Arrow move from Label to Label, and you may use two labels
to relate a more detailed description of an activity on Spreadsheet.
Finish To Start
A B
Start To Start
A
B
Finish To Finish
A
B
Combination
A
B
PROJECT CONTROL
The PMBOK® defines Project Control
“A project management function that involves comparing actual performance with planned
performance and taking appropriate corrective action (or directing others to take this
action) that will yield the desired outcome in the project when significant differences exist.”
The project controls function is defined as:
Project controls are the data gathering, management and analytical processes used to
predict, understand and constructively influence the time and cost outcomes of a project
or program; through the communication of information in formats that assist effective
management and decision making.
PROJECT CONTROL CYCLE
PLAN
Specifications
Project Schedule
Project budget
Resource plan
Vendor contracts MONITOR
Record status
Report progress
Report cost
COMPARE
Actual status
against plan
-Schedule
-Cost
ACTION
Correct
deviations
from plan
RE-PLAN as
necessary
STEPS IN PROJECT CONTROL PROCESS
1 •Project Planning
2 •Project Execution
3 •Project Evaluation
PROJECT PLANNING
• Scope
• Schedule
• Cost
Nature of the Project Plan
• CPM
• PERTNetwork Analysis
• Known Cost
• Unknown CostEstimating Cost
• An important link between planning and control of performance
Preparing the Control
budget
PROJECT EXECUTION
Actual execution of project takes place
In the stage, data on actual cost, actual time and actual accomplishment are compared with
estimates.
Managers seeks three types of reports:
Trouble
Report
Progress
Report
Financial
Report
PROJECT EVALUATION
• Evaluation of Management and process of project
Evaluation of Performance
• When actual cost exceeds budgeted cost.
Cost Overruns
• To discover instances where “right” decision was not made.
Hindsight
• Whether the project achieved its objective. It might take many years to completely evaluate a
project. Unless action can be taken based on analysis there is no point in evaluating a project
Evaluation of Results
RISK MANAGEMENT
Risk is the chance or probability of something that may or may not occur; it is something
which can be quantified or calculated (using standard deviation). Whereas, Uncertainty is
something, which cannot be predicted with statistical confidence, normally due to
insufficient information.
A project manager has to consider different tasks, activities, and work to be accomplished
and consider risk associated with the actual outcome which would be differ from expected
outcome.
Models such as PEST or SLEPT analysis and other derivatives help to analyze different
types of risk e.g. social, legal, economic, political and technological risk.
Risk management processes can also help to identify those risks that are controllable and
uncontrollable

More Related Content

What's hot

Project management PPT
Project management  PPTProject management  PPT
Project management PPTRaj Sampat
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysisHarinadh Karimikonda
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt341741357
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project managementJared C. Powell
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk ManagementKaustubh Gupta
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 

What's hot (20)

Project management PPT
Project management  PPTProject management  PPT
Project management PPT
 
Project management & Network analysis
Project management & Network analysisProject management & Network analysis
Project management & Network analysis
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Estimating Cost & Time.ppt
Estimating Cost & Time.pptEstimating Cost & Time.ppt
Estimating Cost & Time.ppt
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Project planning
Project planning Project planning
Project planning
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 

Viewers also liked

Monte carlo simulation
Monte carlo simulationMonte carlo simulation
Monte carlo simulationRajesh Piryani
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project ManagementAyaz Shariff
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Introduction of software project management
Introduction of software project managementIntroduction of software project management
Introduction of software project managementREHMAT ULLAH
 
Software Project Managment
Software Project ManagmentSoftware Project Managment
Software Project ManagmentSaqib Naveed
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project ManagementRamesh Babu
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-schedulingsaurabhshertukde
 
Theory of estimation
Theory of estimationTheory of estimation
Theory of estimationTech_MX
 
Software Project Management ppt
Software Project Management pptSoftware Project Management ppt
Software Project Management pptAndreea Usatenco
 
Software project management
Software project managementSoftware project management
Software project managementR A Akerkar
 

Viewers also liked (13)

Monte carlo simulation
Monte carlo simulationMonte carlo simulation
Monte carlo simulation
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Introduction of software project management
Introduction of software project managementIntroduction of software project management
Introduction of software project management
 
Software Project Managment
Software Project ManagmentSoftware Project Managment
Software Project Managment
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Theory of estimation
Theory of estimationTheory of estimation
Theory of estimation
 
Software Project Management ppt
Software Project Management pptSoftware Project Management ppt
Software Project Management ppt
 
Software project management
Software project managementSoftware project management
Software project management
 
Project management
Project managementProject management
Project management
 

Similar to PROJECT SCHEDULE (20)

PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
project management -04.ppt
project management -04.pptproject management -04.ppt
project management -04.ppt
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
9a. SEPM LECTURE # 06 - PERT (1).pptx
9a.    SEPM LECTURE # 06 - PERT (1).pptx9a.    SEPM LECTURE # 06 - PERT (1).pptx
9a. SEPM LECTURE # 06 - PERT (1).pptx
 
Unit II.pptx
Unit II.pptxUnit II.pptx
Unit II.pptx
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Pert and gantt chart
Pert and gantt chartPert and gantt chart
Pert and gantt chart
 
Tools & Techniques.pptx
Tools & Techniques.pptxTools & Techniques.pptx
Tools & Techniques.pptx
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Control techniques
Control techniquesControl techniques
Control techniques
 

More from Ajeesh Mk

Indian Financial System
Indian Financial SystemIndian Financial System
Indian Financial SystemAjeesh Mk
 
International Finan
International FinanInternational Finan
International FinanAjeesh Mk
 
Transperancy international india (tii)
Transperancy international india (tii)Transperancy international india (tii)
Transperancy international india (tii)Ajeesh Mk
 
CHANDHUBHAI VIRANI- Owner of Balaji Wafer
CHANDHUBHAI VIRANI- Owner of Balaji WaferCHANDHUBHAI VIRANI- Owner of Balaji Wafer
CHANDHUBHAI VIRANI- Owner of Balaji WaferAjeesh Mk
 
WHISTLE-BLOWING
WHISTLE-BLOWINGWHISTLE-BLOWING
WHISTLE-BLOWINGAjeesh Mk
 
Globalisation
GlobalisationGlobalisation
GlobalisationAjeesh Mk
 
Major 8 MNC's from different sector (Brief)
Major 8 MNC's from different sector (Brief)Major 8 MNC's from different sector (Brief)
Major 8 MNC's from different sector (Brief)Ajeesh Mk
 
PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)
PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)
PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)Ajeesh Mk
 
CROSS BORDER M&A AND COPERATE RESTRUCTURING
CROSS BORDER M&A AND COPERATE RESTRUCTURINGCROSS BORDER M&A AND COPERATE RESTRUCTURING
CROSS BORDER M&A AND COPERATE RESTRUCTURINGAjeesh Mk
 
MANAGING RESISTANCE TO CHANGE
MANAGING RESISTANCE TO CHANGEMANAGING RESISTANCE TO CHANGE
MANAGING RESISTANCE TO CHANGEAjeesh Mk
 
COPYWRITING STYLES IN ADVERTISING (5)
COPYWRITING STYLES IN ADVERTISING (5)COPYWRITING STYLES IN ADVERTISING (5)
COPYWRITING STYLES IN ADVERTISING (5)Ajeesh Mk
 
PRIMARY MARKET
PRIMARY MARKETPRIMARY MARKET
PRIMARY MARKETAjeesh Mk
 
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENTWAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENTAjeesh Mk
 
STRUCTURAL IMPLEMENTATION
STRUCTURAL IMPLEMENTATIONSTRUCTURAL IMPLEMENTATION
STRUCTURAL IMPLEMENTATIONAjeesh Mk
 
Balance Of Payment
Balance Of Payment Balance Of Payment
Balance Of Payment Ajeesh Mk
 

More from Ajeesh Mk (15)

Indian Financial System
Indian Financial SystemIndian Financial System
Indian Financial System
 
International Finan
International FinanInternational Finan
International Finan
 
Transperancy international india (tii)
Transperancy international india (tii)Transperancy international india (tii)
Transperancy international india (tii)
 
CHANDHUBHAI VIRANI- Owner of Balaji Wafer
CHANDHUBHAI VIRANI- Owner of Balaji WaferCHANDHUBHAI VIRANI- Owner of Balaji Wafer
CHANDHUBHAI VIRANI- Owner of Balaji Wafer
 
WHISTLE-BLOWING
WHISTLE-BLOWINGWHISTLE-BLOWING
WHISTLE-BLOWING
 
Globalisation
GlobalisationGlobalisation
Globalisation
 
Major 8 MNC's from different sector (Brief)
Major 8 MNC's from different sector (Brief)Major 8 MNC's from different sector (Brief)
Major 8 MNC's from different sector (Brief)
 
PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)
PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)
PROJECT REPORT ON EMPLOYEE SATISFACTION (sample)
 
CROSS BORDER M&A AND COPERATE RESTRUCTURING
CROSS BORDER M&A AND COPERATE RESTRUCTURINGCROSS BORDER M&A AND COPERATE RESTRUCTURING
CROSS BORDER M&A AND COPERATE RESTRUCTURING
 
MANAGING RESISTANCE TO CHANGE
MANAGING RESISTANCE TO CHANGEMANAGING RESISTANCE TO CHANGE
MANAGING RESISTANCE TO CHANGE
 
COPYWRITING STYLES IN ADVERTISING (5)
COPYWRITING STYLES IN ADVERTISING (5)COPYWRITING STYLES IN ADVERTISING (5)
COPYWRITING STYLES IN ADVERTISING (5)
 
PRIMARY MARKET
PRIMARY MARKETPRIMARY MARKET
PRIMARY MARKET
 
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENTWAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
WAREHOUSING AND STORAGE IN SUPPLY CHAIN MANAGEMENT
 
STRUCTURAL IMPLEMENTATION
STRUCTURAL IMPLEMENTATIONSTRUCTURAL IMPLEMENTATION
STRUCTURAL IMPLEMENTATION
 
Balance Of Payment
Balance Of Payment Balance Of Payment
Balance Of Payment
 

Recently uploaded

Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinojohnmickonozaleda
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 

Recently uploaded (20)

Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipino
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 

PROJECT SCHEDULE

  • 1. Seminar presentationon PROJECT SCHEDULING GROUP MEMBERS: AJEESH MOOSAKUTTY (4) SABITH P (33) SRUTHI.K.R(45) SHAFEEK MA() NIDEESH()
  • 2. PROJECT SCHEDULE In project management, a schedule is a listing of a project milestone activities, and deliverables, usually intended start and finish dates. In many industries such as engineering and construction the development and maintenance of project schedule is a responsibility of a full time schedule or team of schedulers depending on the size of the project.
  • 3. TERMINOLOGIES IN PROJECT SCHEDULING MILESTONE: A milestone is a significant event that normally has no duration It often takes several activities and a lot of work to complete a milestone They’re useful tools for setting schedule goals and monitoring progress Examples include obtaining customer sign-off on key documents or completion of specific products Milestones should be: Specific Measurable Assignable Realistic Time-framed
  • 4. BASIC STEPS TAKEN IN PROJECT MANAGEMENT •Define Activities – identifying the specific actions to be performed to produce the project deliverables •Sequencing Activities – identifying and documenting relationships among the project activities. •Estimate Activity Resources – estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. •Estimate Activity Duration – approximating the number of work periods needed to complete individual activities with estimated resources.
  • 5. BASIC STEPS TAKEN IN PROJECT MANAGEMENT -continue •Develop Schedule – analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. •Control Schedule – monitoring the status of the project to update project progress and managing changes to the schedule baseline
  • 6. TECHNIQUE USED PROJECT SCHEDULING  Before a project schedule can be created the schedule maker. It should have a WORK BREAKDOWN STRUCTURE (WBS) an effort estimate for each task and resource list with available resource.
  • 7. WORK BREAKDOWN STRUCTURE Dividing complex projects to simpler and manageable tasks is the process identified as WORK BREAKDOWN STRUCTURE (WBS). Usually, the project managers use this method for simplifying the project execution. In WBS, much larger tasks are broken-down to manageable chunks of work. These chunks can be easily supervised and estimated. Further sub dividing can be said as Decomposition.
  • 8. WORK BREAKDOWN STRUCTURE(CONTINUE) In project management and systems engineering, is a deliverable oriented decomposition of a project into smaller components. A work breakdown structure element may be a product, data, a service, or any combination. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control
  • 10. AIM OF WORK BREAKDOWN STRUCTURE Giving visibility to important work efforts. Giving visibility to risky work efforts. Illustrate the correlation between the activities and deliverables. Show clear ownership by task leaders.
  • 11. METHODS FOR MAKING A PROJECT SCHEDULE HEALTHY • Schedule must be constantly updated. • The EAC(Estimation At Completion) value must be equal base line value. •The remaining efforts must be approximately distributed among team members(taking vacation into consideration).
  • 12. SCHEDULING TOOLS OR TECHNIQUES MOSTLY COMMONLY USED METHODS ARE: 1. GANTT CHART 2. NETWORK DIAGRAMS(PERT/CPM)
  • 13. SCHEDULING TOOLS Gantt chart A bar chart that is a visual representation of the sequencing and duration of activities on any given project. Useful: ◦ Easy to read ◦ Give each team members overview of the project. ◦ Indicate clearly the status of each activity ◦ Can be drawn to show the budgets, equipment's usage
  • 14. GANTT CHART Gantt charts are used as a tool to monitor and control the project progress. Developed in 1918 by H.L. Gantt A Gantt chart is a graphical presentation that displays activities as follows: ◦ Time is measured on the horizontal axis. A horizontal bar is drawn proportionately to an activity’ s expected completion time. ◦ Each activity is listed on the vertical axis. In an earliest time Gantt chart each bar begins and ends at the earliest start/finish the activity can take place.
  • 15. APPLICATION OF GANTT CHART oGantt chart can be used as a visual aid for tracking the progress of project activities. oAppropriate percentage of a bar is shaded to document the completed work. oThe manager can easily see if the project is progressing on schedule (with respect to the earliest possible completion times).
  • 16. ADVANTAGES AND DISADVANTAGES OF GANTT CHART Advantages. ◦ Easy to construct ◦ Gives earliest completion date. ◦ Provides a schedule of earliest possible start and finish times of activities. Disadvantages ◦ Gives only one possible schedule (earliest). ◦ Does not show whether the project is behind schedule. ◦ Does not demonstrate the effects of delays in any one activity on the start of another activity, thus on the project completion time.
  • 17. AN EXAMPLE OF GANTT CHART
  • 18. NETWORK DIAGRAM  Is a graphical depiction of project tasks and their inter-relationships.  The distinguishing feature of a network diagram is that the ordering of tasks is shown by connecting with its predecessor and successor tasks.  Network diagramming is a critical path scheduling technique used for controlling resources.  Critical path scheduling A Scheduling Technique whose order and duration of a sequence of task activities directly affect the completion date of a project.
  • 19. CRITICAL PATH METHOD(CPM) CPM is a network diagramming technique used to predict total project duration. A critical path for a project is the series of activities that determines the earliest time by which the project can be completed. The critical path is the longest path through the network diagram and has the least amount of slack or float. Slack or float is the amount of time an activity can be delayed without delaying a succeeding activity or the project finish date. Reducing an activity’s completion time is called “crashing.”
  • 20. AN EXAMPLE FOR CRITICAL PATH METHOD 84 A D C B E F G I H Baja Burrito Restaurants – Network presentation L O J NM K P
  • 21. PROGRAM EVALUATION REVIEW TECHNIQUE (PERT) One of the most difficult and most error prone activities when constructing a Project Schedule is the determination of the TIME DURATION for each task within a Work Breakdown Structure (WBS), specially when there is a high degree of complexity and uncertainty about a task. PERT is a technique used to calculate the Expected Time for a tasks. PERT is a technique that uses Optimistic time (O), Pessimistic time (P) and Realistic Time (R) estimates to calculate the EXPECTED TIME (ET) or a particular task.
  • 22. PROGRAM EVALUATION REVIEW TECHNIQUE (PERT) -continue PERT is a technique that uses Optimistic time (o), Pessimistic time (p) and Realistic Time (r) estimates to calculate the EXPECTED TIME (ET) or a particular task. The Optimistic time (o) and Pessimistic time (p) reflects the minimum and maximum possible periods of time for an activity to be completed. The Realistic time (r) or the Most likely time , reflects the Project manager’s “Best Guess” of the amount of time required for a task completion.
  • 23. PROGRAM EVALUATION REVIEW TECHNIQUE (PERT) -continue CALCULATING EXPECTED COMPLETION TIME (ET) o + 4r + p ET = ------------------- 6 Because the expected Completion time should be closer to the realistic time (r), it is typically weighed Four times more than the Optimistic time (o) and the Pessimistic time (p). Once you add these values together , it must be divided by 6 to determine the Expected Time for a task.
  • 24. PROGRAM EVALUATION REVIEW TECHNIQUE (PERT) -continue oPERT Chart is consisted of TASKS and EVENTS. oAn EVENT is called a Milestone, representing a point in time, such as the Start or Completion of a Task. oA circle or a Rectangle shape NODE is used to represent an EVENT. oEvery PERT Chart has one Beginning and one End NODE that represents the Start and Finish of a Project. oThe Earliest and Latest Time is both Zero in Starting Event. oA TASK also called Activity, is depicted by an ARROW Connecting Events. oA Dashed Arrow represents a DUMMY TASK which is the dependency between two events without requiring any resource.
  • 25. PERT/CPM Network ◦ Activity-On-Nodes ◦ Activity-On-Arrows ACTIVITY-ON-NODE: Activity-On-Nodes each activity is represented by nod or a box.
  • 26. PRECEDENCE DIAGRAMMING METHOD The precedence diagramming method (PDM) is a way of constructing a project network diagram that employs boxes or rectangles (nodes) to represent the activities and connects them with arrows that show the dependencies. Essentially, it is an AON network logic diagram with time added. To calculate project duration using a PDM, you identify the early start and early finishes using a calculation known as forward pass. A similar calculation, known as backward pass, is used to calculate the critical path for the project with the float of each activity.
  • 27. -continue FORWARD PASS: Forward pass is the calculation of the early start and early finish dates for the uncompleted portions of all network activities. BACKWARD PASS: Backward pass is the calculation of late finish dates and late start dates for the uncompleted portions of all network activities. It is determined by working backwards through the network logic from the project’s end date. The end date may be calculated in a forward pass or set by the customer or sponsor.
  • 29. Finish to Start Activity A must be finished before Activity B can start A B
  • 30. Start to Start A must start in order for B to start A B
  • 31. Finish To Finish A must be finished in order for B to finish A B
  • 32. Combinations Extending the gap of writing and typing, since durations are different and since typing cannot finish until writing finished. A B
  • 33. ACTIVITY ON ARROW The Arrow move from Label to Label, and you may use two labels to relate a more detailed description of an activity on Spreadsheet.
  • 38. PROJECT CONTROL The PMBOK® defines Project Control “A project management function that involves comparing actual performance with planned performance and taking appropriate corrective action (or directing others to take this action) that will yield the desired outcome in the project when significant differences exist.” The project controls function is defined as: Project controls are the data gathering, management and analytical processes used to predict, understand and constructively influence the time and cost outcomes of a project or program; through the communication of information in formats that assist effective management and decision making.
  • 39. PROJECT CONTROL CYCLE PLAN Specifications Project Schedule Project budget Resource plan Vendor contracts MONITOR Record status Report progress Report cost COMPARE Actual status against plan -Schedule -Cost ACTION Correct deviations from plan RE-PLAN as necessary
  • 40. STEPS IN PROJECT CONTROL PROCESS 1 •Project Planning 2 •Project Execution 3 •Project Evaluation
  • 41. PROJECT PLANNING • Scope • Schedule • Cost Nature of the Project Plan • CPM • PERTNetwork Analysis • Known Cost • Unknown CostEstimating Cost • An important link between planning and control of performance Preparing the Control budget
  • 42. PROJECT EXECUTION Actual execution of project takes place In the stage, data on actual cost, actual time and actual accomplishment are compared with estimates. Managers seeks three types of reports: Trouble Report Progress Report Financial Report
  • 43. PROJECT EVALUATION • Evaluation of Management and process of project Evaluation of Performance • When actual cost exceeds budgeted cost. Cost Overruns • To discover instances where “right” decision was not made. Hindsight • Whether the project achieved its objective. It might take many years to completely evaluate a project. Unless action can be taken based on analysis there is no point in evaluating a project Evaluation of Results
  • 44. RISK MANAGEMENT Risk is the chance or probability of something that may or may not occur; it is something which can be quantified or calculated (using standard deviation). Whereas, Uncertainty is something, which cannot be predicted with statistical confidence, normally due to insufficient information. A project manager has to consider different tasks, activities, and work to be accomplished and consider risk associated with the actual outcome which would be differ from expected outcome. Models such as PEST or SLEPT analysis and other derivatives help to analyze different types of risk e.g. social, legal, economic, political and technological risk. Risk management processes can also help to identify those risks that are controllable and uncontrollable