SlideShare a Scribd company logo
1 of 6
Download to read offline
VICTORIA: FIRM PLEADS GUILTY OVER UNLICENSED DOGMAN’S FALL
22 March 2010
A sheet metal engineering company and its director have pleaded guilty in the Indus-
trial Magistrates Court on Wednesday for failing to provide a safe working environment
- plant & systems of work, and information, instruction, training & supervision.
The case stemmed from a 2 February 2009 incident, where an unlicensed dogman fell
from height.
The Wodonga company’s employee acted as a dogman on a platform being raised by a
mobile tractor crane at an excessive height when he fell to the ground.
He was later transported to a hospital by ambulance, where he underwent surgery to


                                                                                                          LIFTING MATTERS
pin his right leg which was extensively damaged. He also suffered injury to his ribs and
wounds to his right thigh and left elbow.
It was later found the crane did not have a safety hook, and was not maintained prop-
erly.
                                                                                                          Published in the interest of promoting safety in the crane industry
Aside from the dogman, it was also found that the operator of the crane at the time of
the incident did not have a licence to undertake the work.
The company and its director knew crane operators need to be licensed, and that their
employees did not possess such licence. They had decided to get employees trained
after the job was complete as it would then be able to afford it.                                         Sharing an d Learnin g
Magistrate John Martin Murphy did not impose a fine when he determined the case on
March 3. However, he ordered the firm and its director costs of $1,354.52 and
$865.96, respectively.                         http://www. Safetyculture.com.au/news/index.php/page/6/

GOOD AUSTRALIAN HUMOUR
An Aussie truckie walks into an outback cafe' with a full-grown emu behind him. The waitress asks
them for their orders.
The truckie says, 'A hamburger, chips and a coke,' and turns to the emu, 'What's yours?' 'I'll have
the same,' says the emu.
A short time later the waitress returns with the order 'That will be $9.40 please,' and he reaches into
his pocket and pulls out the exact change for payment..
The next day, the man and the emu come again and he says, 'A hamburger, chips and a coke.' The
emu says, 'I'll have the same.' Again the truckie reaches into his pocket and pays with exact change.
This becomes routine until the two enter again. 'The usual?' asks the waitress. 'No, it's Friday night,
so I'll have a steak, baked potato and a salad,' says the man. 'Same,' says the emu. Shortly the
waitress brings the order and says, 'That will be $32.62.'
Once again the man pulls the exact change out of his pocket and places it on the table. The waitress
cannot hold back her curiosity any longer. 'Excuse me, mate, how do you manage to always come
up with the exact change in your pocket every time?'
'Well, love' says the truckie, 'a few years ago, I was cleaning out the back shed, and found an old
lamp. When I rubbed it, a Genie appeared and offered
me two wishes. My first wish was that if I ever had to
pay for anything, I would just put my hand in my pocket
and the right amount of money would always be there.'
'That's brilliant!' says the waitress. 'Most people would
ask for a million dollars or something, but you'll always
be as rich as you want for as long as you live!'
'That's right. Whether it's a gallon of milk or a Rolls
Royce, the exact money is always there,' says the man.
The waitress asks, 'What's with the bloody emu?'
The truckie sighs, pauses, and answers, 'My second                                                                                                         APRIL 2010
wish was for a tall bird with a big arse and long legs,
who agrees with everything I say.'

12   LIFTING MATTERS April 2010                                                                                                                         LIFTING MATTERS April 2010   1
EDITORIAL                                                                                                    WORKING AT HEIGHTS INNOVATIONS
Safety is everybody‟s business in the construction world because the consequences of failure can
                                                                                                             This photo was taken in London last year show-
be catastrophic, as demonstrated by the major crane accidents that kill dozens of people every year.         ing a specially constructed tower bolted to one of
In this light, it is critically important to study near-misses—accidents that never happen because           the vertical pillars of the building. A single ladder-
trained and concerned persons are on the scene, a serious safety program is in place or just, plain          beam mounted on top served as a jib/gantry for
dumb luck saved the day.                                                                                     use as a fall arrest system for the riggers to
Safety experts say the relationship between the number of accidents and incidents is shaped like a           unload steel from delivery trucks.
pyramid, with major accidents at the top, minor accidents in the widening middle and incidents, ob-          An inertia reel of sorts was attached to the end of
servations and near-misses at the broad bottom. The incidents at the bottom, like the crane crack            the ladder-beam and hooked onto the workers
that caused no injuries or damage, are a good opportunity to study the safety program of a company           harnesses to prevent them hitting the ground
or project to see if it has all the elements and processes needed to prevent a major accident.               should they fall from the back of the truck.
All near-misses have the potential for much more serious consequences, and, as a result, compa-              A concern would be if the worker was to fall from
nies should have an effective program of managing near-misses. Construction is a diverse industry,           the far end of the trailer. The pendulum effect of
so programs will vary with the kind of work performed, but risk experts suggest there are eight ele-         the arc of the „swing‟ would not arrest his fall in
ments in an effective near-miss process: 1) identifying an incident as a near-miss; 2) having a re-          time unless of course the trailer was to
                                                                                                             move as required.                               RDP
porting and disclosure structure; 3) prioritizing incidents according to potential severity; 4) distribut-
ing the information to those people analysing the causes; 5) identifying the direct and root causes of
the near-miss; 6) finding solutions for each identified cause; 7) disseminating the solutions to those       BOGGED—110 TONNE TADANO
who will execute them; and 8) tracking solutions to make sure they are executed.                             15 March 2010
                                                                                                             A 110T Tadano mobile crane became bogged in saturated
Few firms are happy to air details about the kinds and causes of near-misses on their projects, but
                                                                                                             sand in Darwin, NT after heavy rain over the weekend.
there is a greater public good in doing so. Just as companies learn from the best practices of others,
there is an even greater learning experience in hearing about and understanding the causes of                After leaving the site on the way back to the depot, the
events that could have been catastrophic. Measuring and analysing such events can pay great divi-            operator unfortunately strayed just a little too far off the
dends and are the main building block of a zero-accident safety culture.                                     very narrow bitumen road, with the undesired result of
                                                                                                             becoming bogged in what looked to all intense and
Your opinion and any queries or wishes you may have are extremely important to us! Let us know               purposes to be a fairly stable road surface.
what's on your mind. Please send your contributions to ricky@universalcranes.com or contact us
                                                                                                             Crane drivers should always be aware that during severe
by phone on +61 7 3907 5800.                                                            (RDP)                weather conditions, the shoulders of secondary roads
                                                                                                             will become unstable due to the run-off from the fin-
IN THIS ISSUE                                           ON THE COVER                                         ished road surface.
                                                                                                                                                                   RDP
Editorial                                          02
Emergency action plans                             03
                                                                                                             LIGHTNING STRIKE ON TOWER
Crane collapses onto traffic                       03                                                        CRANE IN PERTH
Safe loading of EWP’s on tilt tray trucks          04                                                        23 March 2010

CFME report on Worsley crane collapse              04                                                        A dramatic photo taken recently during an
Safety Alert: Mobile crane stability               05                                                        electrical storm in Perth, WA where a tower
                                                                                                             crane on the North side of the Swan River
Who trained him then?                              06
                                                                                                             received a direct hit from a bolt of lightning.
100T Crawler crane tip-over                        07
Crane backstop fell during erection                08                                                         Photo submitted by geoff.beaton@kjv.com.au     RDP
Light vehicle under rear dumper                    09
Ketchikan boom truck tips over with worker         09                                                        WORKING UNDER LOADS
Safety Alert: Fatality by unsecured truck load     10                                                        A photo taken in Brisbane recently showing workers attaching a
Working at heights innovations                     11   A Universal Cranes VOLVO FH16 with an                prop to a precast concrete element while being directly under a
                                                        8 line trailer transporting one of our               suspended load. This is unfortunately seen on sites around Aus-
Bogged 110T Tadano                                 11
                                                        Liebherr LTM 1300 (300t All Terrain                  tralia all to often.
Lightning strike on tower crane in Perth           11
                                                        Crane) from the Wind Farms in South                  The National Code of Practise for pre-cast, tilt-up and concrete
Working under loads                                11
                                                        Australia back to the Brisbane depot.                elements in Building Construction 2008 clearly discourages the
Victoria: firms pleads guilty                      12                                                        fixing of props to smaller concrete elements, unless the element
Good Australian humour                             12                                                        is in an almost vertical position and resting on the ground.
                                                                                                                                                                          RDP
2   LIFTING MATTERS April 2010                                                                                                                                                  LIFTING MATTERS April 2010   11
Emergency Action Plans
                                                                                                 “Should construction workers be faced with an accident that results in a need to call for help from
                                                                                                 the emergency services, then the following is an easy to follow Emergency Action Plan;
                                                                                                 Without placing yourself or others in harm‟s way, check for any further Danger.
                                                                                                 Remove the danger from the casualty or remove the casualty from the danger.
                                                                                                 Alert the emergency services personnel by ringing Triple Zero and asking for ambulance attendance
                                                                                                 and advice;
                                                                                                   The ambulance service will ask for specific details such as the incident‟s exact location and
                                                                                                     what happened. Leave the telephone line open for the emergency services personnel to con-
                                                                                                     tact you for updates;
                                                                                                   Do a head count, have someone in authority cross check the sign in/attendance book with the
                                                                                                     physical count of each worker;
                                                                                                   Any crisis needs leadership. Gently, but confidently, delegate important tasks to those willing
                                                                                                     to help. Give people a key job. Ask someone to direct the emergency vehicles; ask another to
                                                                                                     alert the first aid officer and another to help carry vital equipment;
                                                                                                   Have another person accurately write down the casualty‟s name, the times that the emergency
                                                                                                     happened and roughly what happened. Keep a record for your company and hand a copy to
                                                                                                     the paramedics;
                                                                                                   A job debrief is an important learning tool. If you think that someone isn‟t coping well after an
                                                                                                     emergency, let your supervisor know so that additional counselling can be offered if needed.
                                                                                                 Look at your Emergency Action Plans and practice them regularly.
                                                                                                 Practice makes perfect.
                                                                                                 Remember, Stay Healthy, Stay Safe…!”
                                                                                                 Yours sincerely,




                                                                                                 Baf Kuka.
                                                                                                 (baf.kuka@firstaidsafetytraining.com.au)

                                                                                                 CRANE COLLAPSES ONTO TRAFFIC
                                                                                                 26 March 2010
                                                                                                 A construction crane has collapsed in the
                                                                                                 Siberian city of Krasnoyarsk, smashing into
                                                                                                 nearby traffic. Six people were hurt in the
                                                                                                 accident, two of whom sustained serious
                                                                                                 injuries.
                                                                                                 The accident occurred in the late after-
                                                                                                 noon. The high-rise crane snapped at its
                                                                                                 foundation and fell onto the adjacent high-
                                                                                                 way, burying nine passenger cars and stall-
                                                                                                 ing all traffic. The plunging crane landed
                                                                                                 only a meter away from a nearby bus stop.
                                                                                                 Rescuers worked at the site through the
                                                                                                 night to remove the metal debris and un-
                                                                                                 block traffic.
                                                                                                                                 http://rt.com/Top_News/2010-03-26/krasnoyarsk-crane-collpases-traffic.html
                      http://www.buildsafeuae.com/DesktopDefault.aspx?tabindex=4269&tabid=3053
10   LIFTING MATTERS April 2010                                                                                                                                         LIFTING MATTERS April 2010       3
www.worksafe.qld.gov.au             LIGHT VEHICLE UNDER REAR DUMPER
    SAFETY ALERT                                                                                                                                           The parking of cars on
                                                                                                                                                           mining sites in Australia
                                                                                                                                                           needs to be done with
                                                                                                                                                           extreme care when
                                                                                                                                                           there are monster
                                                                                                                                                           trucks like this running
                    Workplace Health and Safety Queensland                                                                                                 around.
Safe loading of elevated work                                                                                                                              Of note is that the
                                                                                                                                                           dumper is also licensed
platforms on tilt tray trucks                                                                                                                              to travel on the road.
Purpose
The purpose of this alert is to inform persons of                                                                                                                 http://www.miningmayhem.com/2010/04/light-vehicle-under-rear-dumper.html
the risk of injury when loading and unloading ele-
vating work platforms (EWPs) onto and off tilt tray                                                                    Ronald Reagan
trucks.                                                                                                               How do you tell a communist? Well, it's someone who reads Marx and Lenin. And how do you tell an
                                                                                                                      anti-Communist? It's someone who understands Marx and Lenin.

                                                                                                                      Ketchikan boom truck tips over with worker in bucket
                                                               Photograph 2: EWP in travel position as specified by
                                                                                                                      28 March 2010
                                                           Actions required to minimise the risk of injury
                                                           For the safe loading of EWP‟s, the following is to         The worker was in a bucket at the end of
                                                           be ensured:                                                a truck's extended boom when the truck
                                                           • The EWP is loaded and unloaded according to              tipped over Friday. The worker suffered a
                                                           the EWP manufacturer‟s instructions.                       bloody nose and sore ribs.
                                                           • Always winch the unmanned EWP on/off the tilt
                                                           tray unless the manufacturer‟s instructions allow it       The worker and another utility employee
                                                           to be driven.                                              were on Tongass Avenue, the street that
                                                           • Use the winch if the tray surface or EWP’s tyres         runs along Ketchikan's waterfront, with the
                                                           are slippery or if the slope of the tray is too steep      truck parked on the ocean side. The
                                                           for the EWP.                                               boom was stretched above the road to
      Photograph 1: Loading an EWP onto a tilt tray truck. • Truck must be on firm level ground with no side          work on power lines across the street. The
Background                                                 slope. The winch may not stop the EWP from                 second employee was on the ground.
A recent incident occurred in Queensland when              falling off the tray if loading with a side slope in
                                                                                                                      Ketchikan Police Department Officer
an EWP slipped down the tray of a tilt tray truck.         slippery conditions.
                                                                                                                      Charlie Johnson witnessed the accident as he drove slowly north with traffic.
The operator was located in the basket and drove • The truck is suitable to transport the EWP in the
the EWP up the tilted tray to load it onto the truck travel (stowed) position as determined by the                    "I saw the tires on the left side start coming up off the ground, so I just stopped because I
for transportation. Photograph 1 shows an EWP              EWP manufacturer. The tray or trailer should be            knew that didn't look right," Johnson said. "He didn't have his downriggers out on the truck
being loaded onto a tilt tray. The truck tray used         long enough for the boom and basket in the travel          for the lateral support. I guess it put too much of a load on the suspension and took the
for transporting the EWP was too short to enable           (stowed) position. The mass of the EWP is to be            whole truck over."
the EWP to be placed in the transport (stowed)             within the capacity of the winch, truck and/or
                                                           trailer.                                                   The bucket struck about six feet from the base of a utility pole. The truck fell toward its pas-
position without the basket overhanging the tray.
Photograph 2 shows a view of the EWP with the              • The operators of EWP’s are provided with oper-           senger-side wheels with its bottom at a 45-degree angle. The boom remained stretched
basket overhanging the tray. To prevent overhang ating instructions and must be adequately trained                    above the street.
the basket was rotated under the boom                      for its operation. This is especially critical in rela-    The worker in the bucket stood up right away, Johnson said, and told the officer he was
(“crowded” position) as shown in Photograph 3.             tion to loading and unloading EWP‟s onto and off           fine. "He had a bloody nose and some banged-up ribs," Johnson said. "He was attended to
When the basket was placed in the crowded posi- tilt trays.                                                           by EMS."
tion and lowered onto the tilted tray, the braked          • The EWP is transported in compliance with De-
wheels nearer to the basket lifted off the tray. The partment of Transport and Main Roads require-                    Portions of the bottom of the bucket were broken but the rest of bucket appeared to be
remaining wheels in contact with the tray were not ments.                                                             intact. "It was really slow and it just slowly tipped over," Johnson said. "There was force, but it
fitted with brakes. The winch cable was not at-            In addition the following factors should be                wasn't really fast."
tached to the EWP, thus allowing it to roll down           considered:                                                Mike Kline, manger of the utility electric division, told the Ketchikan Daily News he was hesi-
the slope of the tray. This movement caused the            • Transport EWP’s on a drop deck trailer (low              tant to comment on any details and that the position of the downriggers was a detail in-
basket of the EWP to strike the ground. The op-            loader) rather than a tilt tray truck.                     vestigators will review. He would not identify the workers.
erator was crushed between the basket‟s handrail • Use of the winch by another person at the same
and the ground, inflicting serious bodily injuries.        time that the EWP is driven up or down the slope           The incident shut down Tongass Avenue for two hours.
                                                           of the tray, (see Photograph 4).                                                          http://www.adn.com/2010/03/28/1203019/ketchikan-boom-truck-tips-over.html

4   LIFTING MATTERS April 2010                                                                                                                                                                  LIFTING MATTERS April 2010          9
Photograph 4: EWP being driven up tilt tray with winch
                                                                                                      cable attached and operated simultaneously.

                                     Photograph 3: EWP in crowded position on levelled tilt   Legislative requirements
                                                                                              The Workplace Health and Safety Act 1995
                                 • If placing the basket onto the tray is recom-              imposes health and safety obligations on all per-
                                 mended by the manufacturer, level the tilt tray              sons conducting a business or undertaking
                                 prior to placing the basket onto the tray.                   whether as employer, self-employed person, de-
                                 • Use the ground controls when placing the bas-              signers, manufacturers, suppliers, installers and
                                 ket onto the tray.                                           owners of plant and workers.
                                 Routine maintenance                                          The information contained in this alert is designed
                                 A competent person should be engaged to carry                to help persons meet their obligations regarding
                                 out inspections of all critical components at least          the management of risks associated with loading
                                 annually or as prescribed by the manufacturer.               and unloading EWPs for transportation purposes.
                                 This includes but not limited to the inspection of           More information
                                 the winch, winch cable, chains, tie down points              Further information is available from
                                 and EWP brakes. A record of the above activities             www.worksafe.qld.gov.au or by calling the
                                 should be maintained to provide a history of the             Workplace Health and Safety Infoline on
                                 plant.                                                       1300 369 915.

                                 John D. Rockefeller, Jr.
                                 If you want to succeed you should strike out on new paths rather than travel the worn paths of ac-
                                 cepted success.
                                 David Russell
                                 The hardest thing in life to learn is which bridge to cross and which to burn.
                                 Robert Orben
                                 Illegal aliens have always been a problem in the United States. Ask any Indian.

                                 CFMEU says the Worsley crane collapse was due
                                 to mechanical failure
                                 15 January 2010

                                 THE CONSTRUCTION, Forestry, Mining and Energy Union (CFMEU)
                                 have reported the tower crane collapse at BHP’s Worsley Alumina
                                 Refinery project, WA, was due to mechanical failure.
                                 According to CFMEU, mechanical failure in the jib during commission-
                                 ing caused the boom structure of the tower crane to collapse on 13
                                 January, damaging a number of amenities sheds and another crane.
                                 Some workers escaped harm narrowly and without injury.
                                 The incident is said to have occurred during load testing on the John
                                 Holland construction project, with the crane subcontracted from NSW-
                                 based, Marrs Crane Hire.
                                                 http://www.constructioncontractor.com.au/article/A-spate-of-crane-collapses-in-WA/509383.aspx

8   LIFTING MATTERS April 2010                                                                                   LIFTING MATTERS April 2010            5
SAFETY ALERT NO. 11                                                                                                  crane can be sustained by the ground or any other means of support. AS2550.1—2002 Cranes,
                                                                                                                     hoists and winches — Safe use — General requirements, Section 4.2 deals specifically with this re-
WORKPLACE STANDARDS TASMANIA                                                                                         quirement

MOBILE CRANE GROUND STABILITY
                                                                                                                    operators of mobile cranes must be trained and aware of the requirement to ensure that ground
                                                                                                                     stability has been deemed to be satisfactory prior to commencing to set up the crane
Details                                                                                                             the set up area and any installed or prepared pads must be clearly marked and identifiable
On 9 November 2009 a serious near miss involving a 100 tonne mobile crane occurred on a busy con-                 clear communication channels between all parties engaged to erect precast concrete panels is para-
struction site. There was potential for multiple fatalities. The crane was being used to lift and position
                                                                                                                   mount.
precast concrete panels. The ground beneath one of the crane outriggers collapsed while the crane
                                                                                                                 When using cranes to lift precast concrete panels, a detailed erection procedure and checklist that
was lifting a 4 ton panel. The loss of ground stability resulted in the crane outrigger sinking approxi-
mately half a metre. Fortunately, the quick placement of extra timbers under the outrigger arm pre-              conforms or surpasses AS3850—2003 Tilt up concrete construction must be in place. A free checklist is
vented further ground collapse and the panel was able to be lowered without further incident.                    available from the Work Safe Victoria Website. Go to www.worksafe.vic.gov.au and search for
                                                                                                                 “checklist for onsite erection of concrete panels”.
                                                                        Contributing Factors
                                                                                                                 If you would like further information contact Workplace
    The larger timbers that                                             An investigation into this incident
                                                   Marking paint later                                           Standards Tasmania on:
  were used for the bottom                        used to identify pads revealed a number of factors which
     layer of the packing                                               have contributed to the cause:           Telephone: 1300 366 322 (inside Tasmania) or (03)
     Note the outrigger is                                                                                       6233 7657 (outside Tasmania)
     shown set up on the                                                • Change of cranes: Cranes which
     correct pad location                                               had previously been used at the site
                                                                        were not available for use. This re-     Who trained him then?
                                                                        sulted in a different crane company
                                                                                                                 These two were spotted with their truck mounted
                                                                        being engaged by a sub contractor.
                                                                                                                 alloy tower, almost breaking every rule of safe working
                                                                        Importantly the replacement crane
                                                                        had a different size outrigger foot-     in the book.
                                                                                                                                     http://www.vertikal.net/fileadmin/journals/
                                                                        print.                                                             ca/2010/ca_2010_3_p56-57.pdf
                                                                        • Suitability of the ground and
                                                                        prepared outrigger pads: An as-          100T CRAWLER CRANE TIP-OVER
  Area of previous
   ground collapse                                                      sessment of the ground stability
                                                                                                                 19th April 2010
                                                 Soft fill was obscured (hard stand capability) had taken
                                                    by surface soil     place and pads had been prepared for     Summary of Incident
                                                                        the previous cranes. However the         An operator was instructed to refuel a 100 tonne
                                                                        pads did not fit the footprint for the   Manitowoc crawler crane in preparation for mobili-
replacement crane.                                                                                               sation to a site.
• Communication of the suitability of the ground: The crane driver was told that the ground                      The crane had recently been demobilised from
was suitable and based his assessment on being told that previously same size cranes had set up in               another site and had been parked in a corner of
the same area. The sub contracting company communicated to the replacement crane company that                    the yard awaiting remobilisation, facing away from
other large cranes had been in use in the area but did not communicate that pads had been installed.             the exit route.
• Identification of outrigger pads: The installed pads were not easily identifiable and were ob-                 The tracks were retracted and there was 29 tonne
scured by surface dirt and loose gravel. As per the photograph, they were later identified with ground           of counter weight attached.
marking paint.
                                                                                                                 While attempting to manoeuvre the crane into a
• Inadequate outrigger support timbers: The timbers used by the crane set up crew under the
                                                                                                                 position to be able to track toward the fuel bowser,
out riggers were inadequate in spreading the load. Subsequently larger timbers were used as shown in             the operator not being able to see where he
the photograph.                                                                                                  wanted to go, disengaged the slew ring lock pin
• Failure to adequately reassess risk: No new risk assessment took place after new plant was                     and began to slew around. The crane immediately
introduced to the worksite as required by the Workplace Health and Safety Regulations 1998. Post                 tipped over backwards onto the counterweights.
the incident, a resubmitted Job Safety Analysis was provided by the cranage company. This document               There were no injuries and very minor damage. The recovery was done immediately using a 50
included the need to check ground stability.                                                                     tonne Kobelco crawler crane.
Recommendations
                                                                                                                 Actions taken to prevent reoccurrence
In order to reduce the risk of possible injury or death from a crane rollover as a result of ground col-
lapse:                                                                                                           1. Toolbox talks with all employees
 a risk assessment must be conducted prior to the use of any mobile crane which includes a formal               2. All crane operators have been reminded of the standing rule in the yard that no movement of any
   assessment of the ground stability. Importantly a new risk assessment must coincide with any                     high risk plant is to be undertaken without the guidance of a spotter.
   change in the plant (crane)                                                                                   Stability is one of the most important factors relating to any crane. Failure to maintain stability is one
 from the risk assessment process, a competent person must ensure that the loads imposed by the                 of the key factors associated with serious crane incidents.
                                                                                                                                                                                                                    RDP

6   LIFTING MATTERS April 2010                                                                                                                                                          LIFTING MATTERS April 2010     7

More Related Content

Viewers also liked

Asbestos New Guide Lucion
Asbestos New Guide LucionAsbestos New Guide Lucion
Asbestos New Guide LucionAlan Bassett
 
HMG Response To One Death Is Too Many March 2010
HMG Response To One Death Is Too Many   March 2010HMG Response To One Death Is Too Many   March 2010
HMG Response To One Death Is Too Many March 2010Alan Bassett
 
Which Customers are You Building the Right Product For PCA9
Which Customers are You Building the Right Product For PCA9Which Customers are You Building the Right Product For PCA9
Which Customers are You Building the Right Product For PCA9Paul Teich
 
The end of injection education
The end of injection educationThe end of injection education
The end of injection educationBrightwave Group
 
Slayter on planning quant design for flc projects - may 2011
Slayter   on planning quant design for flc projects - may 2011Slayter   on planning quant design for flc projects - may 2011
Slayter on planning quant design for flc projects - may 2011Elspeth Slayter
 
Mercurial はオフラインの海を越える
Mercurial はオフラインの海を越えるMercurial はオフラインの海を越える
Mercurial はオフラインの海を越えるzetamatta
 
OSvパンフレット v3
OSvパンフレット v3OSvパンフレット v3
OSvパンフレット v3Takuya ASADA
 
Quarter square log cabin tutorial
Quarter square log cabin tutorialQuarter square log cabin tutorial
Quarter square log cabin tutorialLaura Rieben
 
kasina: Costs of Compensation - Sales & National Accounts 2009
kasina: Costs of Compensation - Sales & National Accounts 2009kasina: Costs of Compensation - Sales & National Accounts 2009
kasina: Costs of Compensation - Sales & National Accounts 2009kasina
 
Made to measure: Trends in personalised digital learning
Made to measure: Trends in personalised digital learning Made to measure: Trends in personalised digital learning
Made to measure: Trends in personalised digital learning Brightwave Group
 
Ideavirus Readand Share
Ideavirus Readand ShareIdeavirus Readand Share
Ideavirus Readand ShareManuel Fal
 
Permutation and combination
Permutation and combinationPermutation and combination
Permutation and combinationmanishkanwar
 
February 3rd meeting summary
February 3rd meeting summaryFebruary 3rd meeting summary
February 3rd meeting summaryAlan Bassett
 
Lord Young\'s Review
Lord Young\'s ReviewLord Young\'s Review
Lord Young\'s ReviewAlan Bassett
 
Mud In Stock...Discontinued Items
Mud In Stock...Discontinued ItemsMud In Stock...Discontinued Items
Mud In Stock...Discontinued Itemscnunnally
 
Work from height event 26.09.13 chester le street
Work from height event 26.09.13 chester le streetWork from height event 26.09.13 chester le street
Work from height event 26.09.13 chester le streetAlan Bassett
 

Viewers also liked (18)

Open sourcelibrary
Open sourcelibraryOpen sourcelibrary
Open sourcelibrary
 
Asbestos New Guide Lucion
Asbestos New Guide LucionAsbestos New Guide Lucion
Asbestos New Guide Lucion
 
HMG Response To One Death Is Too Many March 2010
HMG Response To One Death Is Too Many   March 2010HMG Response To One Death Is Too Many   March 2010
HMG Response To One Death Is Too Many March 2010
 
Which Customers are You Building the Right Product For PCA9
Which Customers are You Building the Right Product For PCA9Which Customers are You Building the Right Product For PCA9
Which Customers are You Building the Right Product For PCA9
 
The end of injection education
The end of injection educationThe end of injection education
The end of injection education
 
Slayter on planning quant design for flc projects - may 2011
Slayter   on planning quant design for flc projects - may 2011Slayter   on planning quant design for flc projects - may 2011
Slayter on planning quant design for flc projects - may 2011
 
Mercurial はオフラインの海を越える
Mercurial はオフラインの海を越えるMercurial はオフラインの海を越える
Mercurial はオフラインの海を越える
 
NESHEP Handbook
NESHEP HandbookNESHEP Handbook
NESHEP Handbook
 
OSvパンフレット v3
OSvパンフレット v3OSvパンフレット v3
OSvパンフレット v3
 
Quarter square log cabin tutorial
Quarter square log cabin tutorialQuarter square log cabin tutorial
Quarter square log cabin tutorial
 
kasina: Costs of Compensation - Sales & National Accounts 2009
kasina: Costs of Compensation - Sales & National Accounts 2009kasina: Costs of Compensation - Sales & National Accounts 2009
kasina: Costs of Compensation - Sales & National Accounts 2009
 
Made to measure: Trends in personalised digital learning
Made to measure: Trends in personalised digital learning Made to measure: Trends in personalised digital learning
Made to measure: Trends in personalised digital learning
 
Ideavirus Readand Share
Ideavirus Readand ShareIdeavirus Readand Share
Ideavirus Readand Share
 
Permutation and combination
Permutation and combinationPermutation and combination
Permutation and combination
 
February 3rd meeting summary
February 3rd meeting summaryFebruary 3rd meeting summary
February 3rd meeting summary
 
Lord Young\'s Review
Lord Young\'s ReviewLord Young\'s Review
Lord Young\'s Review
 
Mud In Stock...Discontinued Items
Mud In Stock...Discontinued ItemsMud In Stock...Discontinued Items
Mud In Stock...Discontinued Items
 
Work from height event 26.09.13 chester le street
Work from height event 26.09.13 chester le streetWork from height event 26.09.13 chester le street
Work from height event 26.09.13 chester le street
 

More from Alan Bassett

TOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibrationTOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibrationAlan Bassett
 
SAFETY ALERT | crane incident
SAFETY ALERT | crane incidentSAFETY ALERT | crane incident
SAFETY ALERT | crane incidentAlan Bassett
 
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2Alan Bassett
 
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalitiesSAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalitiesAlan Bassett
 
TOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air qualityTOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air qualityAlan Bassett
 
TOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen EnrichmentTOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen EnrichmentAlan Bassett
 
Safety alert 112 first aid
Safety alert 112 first aidSafety alert 112 first aid
Safety alert 112 first aidAlan Bassett
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsAlan Bassett
 
TOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlersTOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlersAlan Bassett
 
TOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at HeightTOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at HeightAlan Bassett
 
Ju t lifting bulletin
Ju t lifting bulletinJu t lifting bulletin
Ju t lifting bulletinAlan Bassett
 
02. point of work risk assessments
02. point of work risk assessments02. point of work risk assessments
02. point of work risk assessmentsAlan Bassett
 
45. 12 tips to a safe christmas
45. 12 tips to a safe christmas45. 12 tips to a safe christmas
45. 12 tips to a safe christmasAlan Bassett
 
Processed like-any-other-criminal
Processed like-any-other-criminalProcessed like-any-other-criminal
Processed like-any-other-criminalAlan Bassett
 
Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016Alan Bassett
 
Safety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuriesSafety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuriesAlan Bassett
 
Toolbox talk jewellery
Toolbox talk jewelleryToolbox talk jewellery
Toolbox talk jewelleryAlan Bassett
 
40. work at height scaffold
40. work at height scaffold40. work at height scaffold
40. work at height scaffoldAlan Bassett
 
Grinder injury bos 17 10 16
Grinder injury bos 17 10 16Grinder injury bos 17 10 16
Grinder injury bos 17 10 16Alan Bassett
 

More from Alan Bassett (20)

TOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibrationTOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibration
 
SAFETY ALERT | crane incident
SAFETY ALERT | crane incidentSAFETY ALERT | crane incident
SAFETY ALERT | crane incident
 
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
 
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalitiesSAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
 
TOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air qualityTOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air quality
 
TOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen EnrichmentTOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen Enrichment
 
Safety alert 112 first aid
Safety alert 112 first aidSafety alert 112 first aid
Safety alert 112 first aid
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operations
 
TOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlersTOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlers
 
TOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at HeightTOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at Height
 
Ju t lifting bulletin
Ju t lifting bulletinJu t lifting bulletin
Ju t lifting bulletin
 
02. point of work risk assessments
02. point of work risk assessments02. point of work risk assessments
02. point of work risk assessments
 
45. 12 tips to a safe christmas
45. 12 tips to a safe christmas45. 12 tips to a safe christmas
45. 12 tips to a safe christmas
 
Processed like-any-other-criminal
Processed like-any-other-criminalProcessed like-any-other-criminal
Processed like-any-other-criminal
 
Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016
 
41. line of fire
41. line of fire41. line of fire
41. line of fire
 
Safety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuriesSafety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuries
 
Toolbox talk jewellery
Toolbox talk jewelleryToolbox talk jewellery
Toolbox talk jewellery
 
40. work at height scaffold
40. work at height scaffold40. work at height scaffold
40. work at height scaffold
 
Grinder injury bos 17 10 16
Grinder injury bos 17 10 16Grinder injury bos 17 10 16
Grinder injury bos 17 10 16
 

Lifting Matters Issue 13 April 2010

  • 1. VICTORIA: FIRM PLEADS GUILTY OVER UNLICENSED DOGMAN’S FALL 22 March 2010 A sheet metal engineering company and its director have pleaded guilty in the Indus- trial Magistrates Court on Wednesday for failing to provide a safe working environment - plant & systems of work, and information, instruction, training & supervision. The case stemmed from a 2 February 2009 incident, where an unlicensed dogman fell from height. The Wodonga company’s employee acted as a dogman on a platform being raised by a mobile tractor crane at an excessive height when he fell to the ground. He was later transported to a hospital by ambulance, where he underwent surgery to LIFTING MATTERS pin his right leg which was extensively damaged. He also suffered injury to his ribs and wounds to his right thigh and left elbow. It was later found the crane did not have a safety hook, and was not maintained prop- erly. Published in the interest of promoting safety in the crane industry Aside from the dogman, it was also found that the operator of the crane at the time of the incident did not have a licence to undertake the work. The company and its director knew crane operators need to be licensed, and that their employees did not possess such licence. They had decided to get employees trained after the job was complete as it would then be able to afford it. Sharing an d Learnin g Magistrate John Martin Murphy did not impose a fine when he determined the case on March 3. However, he ordered the firm and its director costs of $1,354.52 and $865.96, respectively. http://www. Safetyculture.com.au/news/index.php/page/6/ GOOD AUSTRALIAN HUMOUR An Aussie truckie walks into an outback cafe' with a full-grown emu behind him. The waitress asks them for their orders. The truckie says, 'A hamburger, chips and a coke,' and turns to the emu, 'What's yours?' 'I'll have the same,' says the emu. A short time later the waitress returns with the order 'That will be $9.40 please,' and he reaches into his pocket and pulls out the exact change for payment.. The next day, the man and the emu come again and he says, 'A hamburger, chips and a coke.' The emu says, 'I'll have the same.' Again the truckie reaches into his pocket and pays with exact change. This becomes routine until the two enter again. 'The usual?' asks the waitress. 'No, it's Friday night, so I'll have a steak, baked potato and a salad,' says the man. 'Same,' says the emu. Shortly the waitress brings the order and says, 'That will be $32.62.' Once again the man pulls the exact change out of his pocket and places it on the table. The waitress cannot hold back her curiosity any longer. 'Excuse me, mate, how do you manage to always come up with the exact change in your pocket every time?' 'Well, love' says the truckie, 'a few years ago, I was cleaning out the back shed, and found an old lamp. When I rubbed it, a Genie appeared and offered me two wishes. My first wish was that if I ever had to pay for anything, I would just put my hand in my pocket and the right amount of money would always be there.' 'That's brilliant!' says the waitress. 'Most people would ask for a million dollars or something, but you'll always be as rich as you want for as long as you live!' 'That's right. Whether it's a gallon of milk or a Rolls Royce, the exact money is always there,' says the man. The waitress asks, 'What's with the bloody emu?' The truckie sighs, pauses, and answers, 'My second APRIL 2010 wish was for a tall bird with a big arse and long legs, who agrees with everything I say.' 12 LIFTING MATTERS April 2010 LIFTING MATTERS April 2010 1
  • 2. EDITORIAL WORKING AT HEIGHTS INNOVATIONS Safety is everybody‟s business in the construction world because the consequences of failure can This photo was taken in London last year show- be catastrophic, as demonstrated by the major crane accidents that kill dozens of people every year. ing a specially constructed tower bolted to one of In this light, it is critically important to study near-misses—accidents that never happen because the vertical pillars of the building. A single ladder- trained and concerned persons are on the scene, a serious safety program is in place or just, plain beam mounted on top served as a jib/gantry for dumb luck saved the day. use as a fall arrest system for the riggers to Safety experts say the relationship between the number of accidents and incidents is shaped like a unload steel from delivery trucks. pyramid, with major accidents at the top, minor accidents in the widening middle and incidents, ob- An inertia reel of sorts was attached to the end of servations and near-misses at the broad bottom. The incidents at the bottom, like the crane crack the ladder-beam and hooked onto the workers that caused no injuries or damage, are a good opportunity to study the safety program of a company harnesses to prevent them hitting the ground or project to see if it has all the elements and processes needed to prevent a major accident. should they fall from the back of the truck. All near-misses have the potential for much more serious consequences, and, as a result, compa- A concern would be if the worker was to fall from nies should have an effective program of managing near-misses. Construction is a diverse industry, the far end of the trailer. The pendulum effect of so programs will vary with the kind of work performed, but risk experts suggest there are eight ele- the arc of the „swing‟ would not arrest his fall in ments in an effective near-miss process: 1) identifying an incident as a near-miss; 2) having a re- time unless of course the trailer was to move as required. RDP porting and disclosure structure; 3) prioritizing incidents according to potential severity; 4) distribut- ing the information to those people analysing the causes; 5) identifying the direct and root causes of the near-miss; 6) finding solutions for each identified cause; 7) disseminating the solutions to those BOGGED—110 TONNE TADANO who will execute them; and 8) tracking solutions to make sure they are executed. 15 March 2010 A 110T Tadano mobile crane became bogged in saturated Few firms are happy to air details about the kinds and causes of near-misses on their projects, but sand in Darwin, NT after heavy rain over the weekend. there is a greater public good in doing so. Just as companies learn from the best practices of others, there is an even greater learning experience in hearing about and understanding the causes of After leaving the site on the way back to the depot, the events that could have been catastrophic. Measuring and analysing such events can pay great divi- operator unfortunately strayed just a little too far off the dends and are the main building block of a zero-accident safety culture. very narrow bitumen road, with the undesired result of becoming bogged in what looked to all intense and Your opinion and any queries or wishes you may have are extremely important to us! Let us know purposes to be a fairly stable road surface. what's on your mind. Please send your contributions to ricky@universalcranes.com or contact us Crane drivers should always be aware that during severe by phone on +61 7 3907 5800. (RDP) weather conditions, the shoulders of secondary roads will become unstable due to the run-off from the fin- IN THIS ISSUE ON THE COVER ished road surface. RDP Editorial 02 Emergency action plans 03 LIGHTNING STRIKE ON TOWER Crane collapses onto traffic 03 CRANE IN PERTH Safe loading of EWP’s on tilt tray trucks 04 23 March 2010 CFME report on Worsley crane collapse 04 A dramatic photo taken recently during an Safety Alert: Mobile crane stability 05 electrical storm in Perth, WA where a tower crane on the North side of the Swan River Who trained him then? 06 received a direct hit from a bolt of lightning. 100T Crawler crane tip-over 07 Crane backstop fell during erection 08 Photo submitted by geoff.beaton@kjv.com.au RDP Light vehicle under rear dumper 09 Ketchikan boom truck tips over with worker 09 WORKING UNDER LOADS Safety Alert: Fatality by unsecured truck load 10 A photo taken in Brisbane recently showing workers attaching a Working at heights innovations 11 A Universal Cranes VOLVO FH16 with an prop to a precast concrete element while being directly under a 8 line trailer transporting one of our suspended load. This is unfortunately seen on sites around Aus- Bogged 110T Tadano 11 Liebherr LTM 1300 (300t All Terrain tralia all to often. Lightning strike on tower crane in Perth 11 Crane) from the Wind Farms in South The National Code of Practise for pre-cast, tilt-up and concrete Working under loads 11 Australia back to the Brisbane depot. elements in Building Construction 2008 clearly discourages the Victoria: firms pleads guilty 12 fixing of props to smaller concrete elements, unless the element Good Australian humour 12 is in an almost vertical position and resting on the ground. RDP 2 LIFTING MATTERS April 2010 LIFTING MATTERS April 2010 11
  • 3. Emergency Action Plans “Should construction workers be faced with an accident that results in a need to call for help from the emergency services, then the following is an easy to follow Emergency Action Plan; Without placing yourself or others in harm‟s way, check for any further Danger. Remove the danger from the casualty or remove the casualty from the danger. Alert the emergency services personnel by ringing Triple Zero and asking for ambulance attendance and advice;  The ambulance service will ask for specific details such as the incident‟s exact location and what happened. Leave the telephone line open for the emergency services personnel to con- tact you for updates;  Do a head count, have someone in authority cross check the sign in/attendance book with the physical count of each worker;  Any crisis needs leadership. Gently, but confidently, delegate important tasks to those willing to help. Give people a key job. Ask someone to direct the emergency vehicles; ask another to alert the first aid officer and another to help carry vital equipment;  Have another person accurately write down the casualty‟s name, the times that the emergency happened and roughly what happened. Keep a record for your company and hand a copy to the paramedics;  A job debrief is an important learning tool. If you think that someone isn‟t coping well after an emergency, let your supervisor know so that additional counselling can be offered if needed. Look at your Emergency Action Plans and practice them regularly. Practice makes perfect. Remember, Stay Healthy, Stay Safe…!” Yours sincerely, Baf Kuka. (baf.kuka@firstaidsafetytraining.com.au) CRANE COLLAPSES ONTO TRAFFIC 26 March 2010 A construction crane has collapsed in the Siberian city of Krasnoyarsk, smashing into nearby traffic. Six people were hurt in the accident, two of whom sustained serious injuries. The accident occurred in the late after- noon. The high-rise crane snapped at its foundation and fell onto the adjacent high- way, burying nine passenger cars and stall- ing all traffic. The plunging crane landed only a meter away from a nearby bus stop. Rescuers worked at the site through the night to remove the metal debris and un- block traffic. http://rt.com/Top_News/2010-03-26/krasnoyarsk-crane-collpases-traffic.html http://www.buildsafeuae.com/DesktopDefault.aspx?tabindex=4269&tabid=3053 10 LIFTING MATTERS April 2010 LIFTING MATTERS April 2010 3
  • 4. www.worksafe.qld.gov.au LIGHT VEHICLE UNDER REAR DUMPER SAFETY ALERT The parking of cars on mining sites in Australia needs to be done with extreme care when there are monster trucks like this running Workplace Health and Safety Queensland around. Safe loading of elevated work Of note is that the dumper is also licensed platforms on tilt tray trucks to travel on the road. Purpose The purpose of this alert is to inform persons of http://www.miningmayhem.com/2010/04/light-vehicle-under-rear-dumper.html the risk of injury when loading and unloading ele- vating work platforms (EWPs) onto and off tilt tray Ronald Reagan trucks. How do you tell a communist? Well, it's someone who reads Marx and Lenin. And how do you tell an anti-Communist? It's someone who understands Marx and Lenin. Ketchikan boom truck tips over with worker in bucket Photograph 2: EWP in travel position as specified by 28 March 2010 Actions required to minimise the risk of injury For the safe loading of EWP‟s, the following is to The worker was in a bucket at the end of be ensured: a truck's extended boom when the truck • The EWP is loaded and unloaded according to tipped over Friday. The worker suffered a the EWP manufacturer‟s instructions. bloody nose and sore ribs. • Always winch the unmanned EWP on/off the tilt tray unless the manufacturer‟s instructions allow it The worker and another utility employee to be driven. were on Tongass Avenue, the street that • Use the winch if the tray surface or EWP’s tyres runs along Ketchikan's waterfront, with the are slippery or if the slope of the tray is too steep truck parked on the ocean side. The for the EWP. boom was stretched above the road to Photograph 1: Loading an EWP onto a tilt tray truck. • Truck must be on firm level ground with no side work on power lines across the street. The Background slope. The winch may not stop the EWP from second employee was on the ground. A recent incident occurred in Queensland when falling off the tray if loading with a side slope in Ketchikan Police Department Officer an EWP slipped down the tray of a tilt tray truck. slippery conditions. Charlie Johnson witnessed the accident as he drove slowly north with traffic. The operator was located in the basket and drove • The truck is suitable to transport the EWP in the the EWP up the tilted tray to load it onto the truck travel (stowed) position as determined by the "I saw the tires on the left side start coming up off the ground, so I just stopped because I for transportation. Photograph 1 shows an EWP EWP manufacturer. The tray or trailer should be knew that didn't look right," Johnson said. "He didn't have his downriggers out on the truck being loaded onto a tilt tray. The truck tray used long enough for the boom and basket in the travel for the lateral support. I guess it put too much of a load on the suspension and took the for transporting the EWP was too short to enable (stowed) position. The mass of the EWP is to be whole truck over." the EWP to be placed in the transport (stowed) within the capacity of the winch, truck and/or trailer. The bucket struck about six feet from the base of a utility pole. The truck fell toward its pas- position without the basket overhanging the tray. Photograph 2 shows a view of the EWP with the • The operators of EWP’s are provided with oper- senger-side wheels with its bottom at a 45-degree angle. The boom remained stretched basket overhanging the tray. To prevent overhang ating instructions and must be adequately trained above the street. the basket was rotated under the boom for its operation. This is especially critical in rela- The worker in the bucket stood up right away, Johnson said, and told the officer he was (“crowded” position) as shown in Photograph 3. tion to loading and unloading EWP‟s onto and off fine. "He had a bloody nose and some banged-up ribs," Johnson said. "He was attended to When the basket was placed in the crowded posi- tilt trays. by EMS." tion and lowered onto the tilted tray, the braked • The EWP is transported in compliance with De- wheels nearer to the basket lifted off the tray. The partment of Transport and Main Roads require- Portions of the bottom of the bucket were broken but the rest of bucket appeared to be remaining wheels in contact with the tray were not ments. intact. "It was really slow and it just slowly tipped over," Johnson said. "There was force, but it fitted with brakes. The winch cable was not at- In addition the following factors should be wasn't really fast." tached to the EWP, thus allowing it to roll down considered: Mike Kline, manger of the utility electric division, told the Ketchikan Daily News he was hesi- the slope of the tray. This movement caused the • Transport EWP’s on a drop deck trailer (low tant to comment on any details and that the position of the downriggers was a detail in- basket of the EWP to strike the ground. The op- loader) rather than a tilt tray truck. vestigators will review. He would not identify the workers. erator was crushed between the basket‟s handrail • Use of the winch by another person at the same and the ground, inflicting serious bodily injuries. time that the EWP is driven up or down the slope The incident shut down Tongass Avenue for two hours. of the tray, (see Photograph 4). http://www.adn.com/2010/03/28/1203019/ketchikan-boom-truck-tips-over.html 4 LIFTING MATTERS April 2010 LIFTING MATTERS April 2010 9
  • 5. Photograph 4: EWP being driven up tilt tray with winch cable attached and operated simultaneously. Photograph 3: EWP in crowded position on levelled tilt Legislative requirements The Workplace Health and Safety Act 1995 • If placing the basket onto the tray is recom- imposes health and safety obligations on all per- mended by the manufacturer, level the tilt tray sons conducting a business or undertaking prior to placing the basket onto the tray. whether as employer, self-employed person, de- • Use the ground controls when placing the bas- signers, manufacturers, suppliers, installers and ket onto the tray. owners of plant and workers. Routine maintenance The information contained in this alert is designed A competent person should be engaged to carry to help persons meet their obligations regarding out inspections of all critical components at least the management of risks associated with loading annually or as prescribed by the manufacturer. and unloading EWPs for transportation purposes. This includes but not limited to the inspection of More information the winch, winch cable, chains, tie down points Further information is available from and EWP brakes. A record of the above activities www.worksafe.qld.gov.au or by calling the should be maintained to provide a history of the Workplace Health and Safety Infoline on plant. 1300 369 915. John D. Rockefeller, Jr. If you want to succeed you should strike out on new paths rather than travel the worn paths of ac- cepted success. David Russell The hardest thing in life to learn is which bridge to cross and which to burn. Robert Orben Illegal aliens have always been a problem in the United States. Ask any Indian. CFMEU says the Worsley crane collapse was due to mechanical failure 15 January 2010 THE CONSTRUCTION, Forestry, Mining and Energy Union (CFMEU) have reported the tower crane collapse at BHP’s Worsley Alumina Refinery project, WA, was due to mechanical failure. According to CFMEU, mechanical failure in the jib during commission- ing caused the boom structure of the tower crane to collapse on 13 January, damaging a number of amenities sheds and another crane. Some workers escaped harm narrowly and without injury. The incident is said to have occurred during load testing on the John Holland construction project, with the crane subcontracted from NSW- based, Marrs Crane Hire. http://www.constructioncontractor.com.au/article/A-spate-of-crane-collapses-in-WA/509383.aspx 8 LIFTING MATTERS April 2010 LIFTING MATTERS April 2010 5
  • 6. SAFETY ALERT NO. 11 crane can be sustained by the ground or any other means of support. AS2550.1—2002 Cranes, hoists and winches — Safe use — General requirements, Section 4.2 deals specifically with this re- WORKPLACE STANDARDS TASMANIA quirement MOBILE CRANE GROUND STABILITY  operators of mobile cranes must be trained and aware of the requirement to ensure that ground stability has been deemed to be satisfactory prior to commencing to set up the crane Details  the set up area and any installed or prepared pads must be clearly marked and identifiable On 9 November 2009 a serious near miss involving a 100 tonne mobile crane occurred on a busy con-  clear communication channels between all parties engaged to erect precast concrete panels is para- struction site. There was potential for multiple fatalities. The crane was being used to lift and position mount. precast concrete panels. The ground beneath one of the crane outriggers collapsed while the crane When using cranes to lift precast concrete panels, a detailed erection procedure and checklist that was lifting a 4 ton panel. The loss of ground stability resulted in the crane outrigger sinking approxi- mately half a metre. Fortunately, the quick placement of extra timbers under the outrigger arm pre- conforms or surpasses AS3850—2003 Tilt up concrete construction must be in place. A free checklist is vented further ground collapse and the panel was able to be lowered without further incident. available from the Work Safe Victoria Website. Go to www.worksafe.vic.gov.au and search for “checklist for onsite erection of concrete panels”. Contributing Factors If you would like further information contact Workplace The larger timbers that An investigation into this incident Marking paint later Standards Tasmania on: were used for the bottom used to identify pads revealed a number of factors which layer of the packing have contributed to the cause: Telephone: 1300 366 322 (inside Tasmania) or (03) Note the outrigger is 6233 7657 (outside Tasmania) shown set up on the • Change of cranes: Cranes which correct pad location had previously been used at the site were not available for use. This re- Who trained him then? sulted in a different crane company These two were spotted with their truck mounted being engaged by a sub contractor. alloy tower, almost breaking every rule of safe working Importantly the replacement crane had a different size outrigger foot- in the book. http://www.vertikal.net/fileadmin/journals/ print. ca/2010/ca_2010_3_p56-57.pdf • Suitability of the ground and prepared outrigger pads: An as- 100T CRAWLER CRANE TIP-OVER Area of previous ground collapse sessment of the ground stability 19th April 2010 Soft fill was obscured (hard stand capability) had taken by surface soil place and pads had been prepared for Summary of Incident the previous cranes. However the An operator was instructed to refuel a 100 tonne pads did not fit the footprint for the Manitowoc crawler crane in preparation for mobili- replacement crane. sation to a site. • Communication of the suitability of the ground: The crane driver was told that the ground The crane had recently been demobilised from was suitable and based his assessment on being told that previously same size cranes had set up in another site and had been parked in a corner of the same area. The sub contracting company communicated to the replacement crane company that the yard awaiting remobilisation, facing away from other large cranes had been in use in the area but did not communicate that pads had been installed. the exit route. • Identification of outrigger pads: The installed pads were not easily identifiable and were ob- The tracks were retracted and there was 29 tonne scured by surface dirt and loose gravel. As per the photograph, they were later identified with ground of counter weight attached. marking paint. While attempting to manoeuvre the crane into a • Inadequate outrigger support timbers: The timbers used by the crane set up crew under the position to be able to track toward the fuel bowser, out riggers were inadequate in spreading the load. Subsequently larger timbers were used as shown in the operator not being able to see where he the photograph. wanted to go, disengaged the slew ring lock pin • Failure to adequately reassess risk: No new risk assessment took place after new plant was and began to slew around. The crane immediately introduced to the worksite as required by the Workplace Health and Safety Regulations 1998. Post tipped over backwards onto the counterweights. the incident, a resubmitted Job Safety Analysis was provided by the cranage company. This document There were no injuries and very minor damage. The recovery was done immediately using a 50 included the need to check ground stability. tonne Kobelco crawler crane. Recommendations Actions taken to prevent reoccurrence In order to reduce the risk of possible injury or death from a crane rollover as a result of ground col- lapse: 1. Toolbox talks with all employees  a risk assessment must be conducted prior to the use of any mobile crane which includes a formal 2. All crane operators have been reminded of the standing rule in the yard that no movement of any assessment of the ground stability. Importantly a new risk assessment must coincide with any high risk plant is to be undertaken without the guidance of a spotter. change in the plant (crane) Stability is one of the most important factors relating to any crane. Failure to maintain stability is one  from the risk assessment process, a competent person must ensure that the loads imposed by the of the key factors associated with serious crane incidents. RDP 6 LIFTING MATTERS April 2010 LIFTING MATTERS April 2010 7