MEASURING QUANTITIES, PRICING & COST ANALYSIS




                      ● Mat Naim bin Abdullah @ Mohd Asmoni
                      ● Diploma QS (UTM), BSc. QS (Glasgow
                          Caledonian University), M.Eng. Construction
                          (UTM), PhD Facilities Management (UTM)
                      ●   matnaim@utm.my
                      ●   amn871969@yahoo.com
                      ●   C04-308
                      ●   019-7573760




         www.utm.my              innovative ● entrepreneurial ● global   1
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Assumption No. 1:        Total land area = 10m x 10m




                                   Project Title: Construction and completion of
                                   guard house
                                   Owner: Panicsonic Sdn Bhd
                                   Architect: A to Z Sdn Bhd
                                   Drawing Title: Ground beam and foundation plan
                                   -------------------------------------------------------------------------
                                   Drawn by: Sheila
                                   Checked by: Aaron




            www.utm.my            innovative ● entrepreneurial ● global                                        2
MEASURING QUANTITIES, PRICING & COST ANALYSIS




         www.utm.my       innovative ● entrepreneurial ● global   3
MEASURING QUANTITIES, PRICING & COST ANALYSIS

                      Construction Method

 1.    Preliminaries (Initial site works) - % of total cost
 2.    Site clearance and earthwork
 3.    Foundation construction (E.g. Piling and footing)
 4.    Work below lowest floor finish
 5.    Frame
 6.    Staircase
 7.    Upper Floor
 8.    Roof
 9.    Wall and partition
 10.   Door and window
 11.   Finishes
 12.   Sundries (Built-in furniture)
 13.   Building services (M&E, ICT etc)
 14.   External works (Water reticulation, landscape etc)



              www.utm.my                  innovative ● entrepreneurial ● global   4
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

1) Site clearance

1.1) Clear the site including grubbing of Area of the site:
     trees, shrubs and demolish any       10 x 10 = 100m2
     existing structure and cart away
     and dump to the specified
     location.

      10.00
      10.00
     ----------
     100.00          100 m2
     ----------




                    www.utm.my                  innovative ● entrepreneurial ● global   5
MEASURING QUANTITIES, PRICING & COST ANALYSIS




         www.utm.my       innovative ● entrepreneurial ● global   6
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.1) Piling including all related works   Area of the building:
                                          Length = 3048 + 3048 = 6096
        6.10                              Width = 3048 + 3048 = 6096
        6.10
     ----------
      37.21         37 m2
     ----------




                    www.utm.my                 innovative ● entrepreneurial ● global   7
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.2) Excavation for pile cap            Size of pile cap = 1219 x 1219
                                        Depth of excavation:
     9/1.22                                1524 + 50 (lean concrete) = 1574
        1.22
        1.57
     ----------
      21.03        21 m3
     ----------



                                              Excavation and Lean concrete as base
                                                               for pile cap




                    www.utm.my               innovative ● entrepreneurial ● global   8
MEASURING QUANTITIES, PRICING & COST ANALYSIS




         www.utm.my       innovative ● entrepreneurial ● global   9
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation
2.3) Reinforced concrete Grade 30 for   Size of pile cap:
     pile cap                           Length = 1219
                                        Width = 1219
    9/1.22                              Thickness = 305
       1.22
       0.31
    ----------
       4.15       4 m3
    ----------



                                                     Concrete for pile cap




                   www.utm.my                 innovative ● entrepreneurial ● global   10
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation
2.4) 50mm thick lean concrete Grade     Size of pile cap:
     15 for pile cap                    Length = 1219
                                        Width = 1219
   9 / 1.22
       1.22
       0.05
    ----------
       0.67       1 m3
    ----------



                                               Excavation and Lean concrete as base
                                                                for pile cap




                   www.utm.my                 innovative ● entrepreneurial ● global   11
MEASURING QUANTITIES, PRICING & COST ANALYSIS




         www.utm.my       innovative ● entrepreneurial ● global   12
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.5) Formwork for pile cap              Size of pile cap:
                                        Length = 1219
 9 / 4 /1.22                            Width = 1219
        0.31                            Thickness = 305
     ----------
       13.62             14 m2          9/2/1.22
     ----------                              0.31 6.81

                                        9/2/1.50
                                             0.31 8.37
                                                 15.18 15m2



              Formwork for pile cap


                          www.utm.my          innovative ● entrepreneurial ● global   13
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation
2.6) Reinforcement bar Y12 for pile cap   Length:
                                            a                    c
 9/2/ 12/ 1.53
       ----------                                      b

       330.48m x 0.89 kg/m = 294.13kg     = a + b + c – cover
       ----------                         = 305 + 1219 + 305 – 6(50)
                            = 294 kg      = 1829 – 300
                                          = 1529

                                          No. of bars:
                                          = (b/100) + 1
                                          = ((1219 – 2(50)cover )/100 )+1
                                          = 12 nos.



                   www.utm.my                   innovative ● entrepreneurial ● global   14
MEASURING QUANTITIES, PRICING & COST ANALYSIS




                      @100 c/c




         www.utm.my              innovative ● entrepreneurial ● global   15
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF                                Taker off :              Checked by:
3.1) Column stump                       Size of column stump:
3.1.1) Reinforced concrete Grade 30     Length = 229
       for column stump                 Width = 229
                                        Height = 1524 – 305 thickness of pile
    9/0.23                                         cap – (351/2) Half of beam’s
       0.23                                        thickness
       1.04                                      = 1043.50
    ----------
       0.50       1 m3
    ----------




                   www.utm.my                 innovative ● entrepreneurial ● global   16
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.1) Column stump                       Size of column stump:
3.1.2) Formwork for column stump        Length = 229
                                        Width = 229
  9/4/0.23                              Height = 1524 – 305 thickness of pile
        1.04                                       cap – (351/2) Half of beam’s
     ----------                                    thickness
       8.61       9 m2                           = 1043.50
     ----------




                   www.utm.my                innovative ● entrepreneurial ● global   17
MEASURING QUANTITIES, PRICING & COST ANALYSIS




                Height of column stump

                         @100 c/c




         www.utm.my                      innovative ● entrepreneurial ● global   18
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.1) Column stump                       Length = a + half beam’s thickness –
3.1.3) Reinforcement bar Y12 for        cover + 2 laps
       column stump                          lap



  9/4/2.97
     ----------                                    a

     106.92m x 0.89kg/m = 95.16kg
     ----------                                        lap
                           95kg
                                        = 1524 + (351/2) – 50 + (660x2)
                                        = 2969.50




                   www.utm.my                innovative ● entrepreneurial ● global   19
MEASURING QUANTITIES, PRICING & COST ANALYSIS
                      General Notes




         www.utm.my                   innovative ● entrepreneurial ● global   20
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.1) Column stump                       Length of link: (length of CS– 2cover) x
3.1.4) R6 link in for column stump      4 +hook            Hook


  9/6/0.62
     ----------
      33.48m x 0.22kg/m = 7.36kg        =(229-100)+(229-100)+(229-100)+(229-
     ----------                         100)+100=616
                           7kg
                                        No. of link:
                                        Height of column stump = 1043.50
                                        =(1043.50/229)+1
                                        = 6 nos.




                   www.utm.my                innovative ● entrepreneurial ● global   21
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Size of ground beam:
3.2.1) Excavation for ground beam       Length=3048+3048=6096
                                        Width = 229
  2/3/6.10                              Thickness = 351
       0.23
       0.35
     ----------
       2.95m3
     ----------
                           3m3


                                               Excavation for ground beam



                   www.utm.my                innovative ● entrepreneurial ● global   22
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                          Size of ground beam:
3.2.2) Reinforced concrete Grade 30 for   Length=3048+3048=6096
        ground beam                       Width = 229
                                          Thickness = 351
  2/3/6.10
       0.23
       0.35
     ----------
       2.95m3              3m3
     ----------



                                                  RC for ground beam


                   www.utm.my                 innovative ● entrepreneurial ● global   23
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Size of ground beam:
3.2.3) 50mm thick lean concrete Grade   Length=3048+3048=6096
        15 for ground beam              Width = 229
                                        Thickness = 351
  2/3/6.10
       0.23
       0.05
     ----------
       0.42m3             1 m3
     ----------



                                                 RC for ground beam


                   www.utm.my                innovative ● entrepreneurial ● global   24
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Assumption No. 1:        Total land area = 10m x 10m




                                   Project Title: Construction and completion of
                                   guard house
                                   Owner: Panicsonic Sdn Bhd
                                   Architect: A to Z Sdn Bhd
                                   Drawing Title: Ground beam and foundation plan
                                   -------------------------------------------------------------------------
                                   Drawn by: Sheila
                                   Checked by: Aaron




            www.utm.my            innovative ● entrepreneurial ● global                                        25
MEASURING QUANTITIES, PRICING & COST ANALYSIS




                Height of column stump

                         @100 c/c




         www.utm.my                      innovative ● entrepreneurial ● global   26
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Size of ground beam:
3.2.4) Formwork for ground beam         Length=3048+3048=6096
                                        Width = 229
                                        Thickness = 351
2/3/2/6.10
       0.35
     ----------
      25.62       26m2
     ----------



                                                 Installation of reinforcement bar and
                                                           formwork for ground beam




                   www.utm.my                innovative ● entrepreneurial ● global       27
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Length = (length–2cover)+(2bend-
3.2.5) Reinforcement bar Y10 for        2cover)
       ground beam                      =(6096-(2x50))+(2x351)-(4x50)
                                        = 6498
2/3/4/6.50
     ----------
    156.00m x 0.62kg/m = 96.72kg
     ----------
                          97kg




                   www.utm.my                innovative ● entrepreneurial ● global   28
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.2) Ground beam                        Length of stirrup:
3.2.6) R6 stirrup for ground beam                            Hook


2/3/28/0.86
      ----------                        =(229-100)+(351-100)+(229-100)+(351-
     144.48m x 0.22kg/m = 31.79kg       100)+100
      ----------                        =860
                          32kg
                                        No. of stirrup:
                                        Length of grd beam= 6096
                                        =(6096/229)+1
                                        = 28 nos.




                   www.utm.my                innovative ● entrepreneurial ● global   29
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.3) Ground slab                                     Area of slab including apron = length x width
3.3.1) Excavation for ground slab                    Depth of excavation = 500mm

       7.30
       7.30                                                             BRC A8
                                                                                          150mm thick
                                                                                          concrete slab
       0.50
      ----------
      26.65m3               27 m3
      ----------                                                                                  50mm thick
                                                                                                     sand

                                                                                                 300mm thick
                                                                                                   hardcore



                                                                             DPM




                                                     6096 + 1200 (apron) = 7296


      Installation of formwork,Damp Proof Membrane
         (DPM) and BRC wire mesh for ground slab



                               www.utm.my                     innovative ● entrepreneurial ● global            30
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                        Area of slab = length x width
3.3.2) Reinforced concrete G30 in       Depth of excavation = 500mm
       ground slab
                                                                      150mm thick
                                                        BRC A8
                                                                      concrete slab
       7.30
       7.30
       0.15                                                                   50mm thick

      ----------                                                                 sand


       7.99m3                                                                300mm thick
                                                                               hardcore

      ----------   8 m3
                                                            DPM




                   www.utm.my                innovative ● entrepreneurial ● global         31
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                        Area of slab = length x width
3.3.3) Formwork for ground slab         Depth of excavation = 500mm

     4/7.30                                            BRC A8
                                                                     150mm thick
                                                                     concrete slab
       0.15
      ----------
       4.38m2                                                                50mm thick

      ----------                                                                sand


                           4 m2                                             300mm thick
                                                                              hardcore



                                                           DPM




                   www.utm.my                innovative ● entrepreneurial ● global        32
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of
Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                          Area of slab including apron
3.3.4) BRC A8 for ground slab             Depth of excavation = 500mm
                                                                       150mm thick
                                                         BRC A8
                                                                       concrete slab

       7.30
       7.30
      ----------                                                               50mm thick
                                                                                  sand
      53.29m2                                                                 300mm thick
      ----------                                                                hardcore


                           53 m2                             DPM



                                          Length = 6096 + 1200 = 7296



                   www.utm.my                  innovative ● entrepreneurial ● global        33
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of
Guard House for Panicsonic Sdn Bhd
3) WBLFF
3.3) Ground slab                          Area of slab = length x width
3.3.5) DPM for ground slab                Depth of excavation = 500mm
                                                                        150mm thick
                                                          BRC A8
                             53 m2                                      concrete slab




                                                                                50mm thick
                                                                                   sand

                                                                               300mm thick
                                                                                 hardcore



                                                              DPM




                   www.utm.my                  innovative ● entrepreneurial ● global         34
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                         Area of slab = length x width
3.3.6) 50mm sand blinding for ground     Depth of excavation = 500mm
       slab
                                                                         150mm thick
                                                          BRC A8
                   53 m2                                                 concrete slab




                                                                                 50mm thick
                                                                                    sand

                                                                                300mm thick
                                                                                  hardcore



                                                              DPM




                   www.utm.my                 innovative ● entrepreneurial ● global           35
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.3) Ground slab                        Area of slab = length x width
3.3.7) Hardcore for ground slab         Depth of excavation = 500mm

       7.30                                             BRC A8
                                                                      150mm thick
                                                                      concrete slab
       7.30
       0.30
      ----------                                                              50mm thick

      15.99m3                                                                    sand


      ----------                                                             300mm thick
                                                                               hardcore

                           16 m3
                                                            DPM




                   www.utm.my                innovative ● entrepreneurial ● global         36
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF
3.4) Half round glazeware perimeter     Area of slab = length x width
      drain size 150mm diameter         Depth of excavation = 500mm

    4/7.30                                              BRC A8
                                                                      150mm thick
                                                                      concrete slab
      ----------
     29.20m
      ----------                                                              50mm thick

                           29 m                                                  sand

                                                                             300mm thick
                                                                               hardcore



                                                            DPM




                   www.utm.my                innovative ● entrepreneurial ● global         37
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME                                Taker off :                       Checked by:
4.1) Column                             Size of column:
4.1.1) Reinforced concrete Grade 30     Length = 229
       for column                       Width = 229
                                        Height = Height of the wall
    9/0.23                                       = 3000mm
       0.23
       3.00
    ----------
       1.43       1 m3
    ----------



                                                Installation of reinforcement bar and
                                                             formwork for column



                   www.utm.my                 innovative ● entrepreneurial ● global     38
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.1) Column                             Size of column:
4.1.2) Formwork for column              Length = 229
                                        Width = 229
  9/4/0.23                              Height = 3000
        3.00
     ----------
      24.84       25 m2
     ----------




                   www.utm.my                innovative ● entrepreneurial ● global   39
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.1) Column                             Length = height of column + half of roof
4.1.3) Reinforcement bar Y12 for        beam + 1 lap + bend
       column
                                                 bend


  9/4/4.50
     ----------                                  Height of wall
    162.00m x 0.89kg/m = 144.18kg
     ----------
                          144kg
                                                  lap




                                        = 3000+ (0.5x351) + 660 + 660
                                        = 4495.5


                   www.utm.my                innovative ● entrepreneurial ● global   40
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.1) Column                             Length of link: (length of CS– 2cover) x
4.1.4) R6 link in for column            4 +hook
                                                          Hook

  9/14/0.82
     ----------
    103.32m x 0.22kg/m = 22.73kg        =(229-50)+(229-50)+(229-50)+(229-
     ----------                         50)+100=816
                          23kg
                                        No. of link:
                                        Height of column = 3000
                                        =(3000/229)+1
                                        = 14 nos.



                    www.utm.my               innovative ● entrepreneurial ● global   41
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.2) Roof beam                            Size of roof beam:
4.2.1) Reinforced concrete Grade 30 for   Length=3048+3048=6096
        roof beam                         Width = 229
                                          Thickness = 351
  2/3/6.10
       0.23
       0.35
     ----------
       2.95m3
     ----------
                            3m3




                   www.utm.my                 innovative ● entrepreneurial ● global   42
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.2) Roof beam                          Size of roof beam:
4.2.2) Formwork for roof beam           Length=3048+3048=6096
                                        Width = 229                        Side

                                        Thickness = 351
  2/3/6.10                                                             Soffit
       0.93
     ----------
      34.04       34m2
     ----------




                                        = 351 + 229 + 351
                                        = 931
                   www.utm.my                 innovative ● entrepreneurial ● global   43
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
4.2) Roof beam                          Length = (length–2cover)+(2bend-
4.2.3) Reinforcement bar Y10 for roof   2cover)
       beam                             =(6096-(2x50))+(2x351)-(4x50)
                                        = 6498
2/3/4/6.50
     ----------
    156.00m x 0.62kg/m = 96.72kg
     ----------
                          97kg




                   www.utm.my                innovative ● entrepreneurial ● global   44
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME
3.2) Roof beam                          Length of stirrup:
3.2.5) R6 stirrup for roof beam                              Hook


2/3/28/1.06
      ----------                        =(229-50)+(351-50)+(229-50)+(351-
     178.08m x 0.22kg/m = 39.18kg       50)+100
      ----------                        =1060
                          39kg
                                        No. of stirrup:
                                        Length of beam= 6096
                                        =(6096/229)+1
                                        = 28 nos.




                   www.utm.my                innovative ● entrepreneurial ● global   45
MEASURING QUANTITIES, PRICING & COST ANALYSIS


Assumption No. 1:        Total land area = 10m x 10m




                                   Project Title: Construction and completion of
                                   guard house
                                   Owner: Panicsonic Sdn Bhd
                                   Architect: A to Z Sdn Bhd
                                   Drawing Title: Ground beam and foundation plan
                                   -------------------------------------------------------------------------
                                   Drawn by: Sheila
                                   Checked by: Aaron




            www.utm.my            innovative ● entrepreneurial ● global                                        46
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

5) ROOF                                      = area of roof
                                             =axbx2               a                          3m
5.1) Steel roof trusses and corrugated
      aluminium steel roof covering

2/8.50                                       a = 42482 + 30002
   5.20
  ----------                                                      Front and rear elevation
  88.40m2               88 m2                a = 5200
  ----------
                                             b = 6096 +
                                                  1200 +                     b
                                                  1200
                                             b = 8496


                                                                  Right and left elevation

                         www.utm.my                innovative ● entrepreneurial ● global          47
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

6) DOOR and WINDOW                            Door can be
                                              measured either     a                          3m
6.1) Single leaf panel door size 2100 x 900   in m2 or
      including frame and painting            number. If
                                              enumerated then
  2/2.10                                      need to state
     0.90                                     type and size
  ----------                                                      Front and rear elevation
     3.78           4 m2     or 2 nos
  ----------

                                                                             b



                                                                  Right and left elevation

                           www.utm.my              innovative ● entrepreneurial ● global          48
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

6) DOOR and WINDOW                           Window can be
                                             measured either      a                          3m
6.2) Adjustable louvres window 1200 x 600    in m2 or
      including frame , painting and glass   number. If
                                             enumerated then
                                             need to state
2/6/1.20                                     type and size
     0.60                                                         Front and rear elevation
  ----------
     8.64           8.64 m2   or 12 nos
  ----------
                                                                             b



                                                                  Right and left elevation

                         www.utm.my                innovative ● entrepreneurial ● global          49
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

7) WALL AND PARTITION
                                                                  a                          3m
7.1) Half brickwall in comon brick

 4/ 6.10
    3.00 73.20

Less opening (e.g. door and window)                               Front and rear elevation

 2/2.10
   0.90    3.78 (door)
                              61 m2                                          b
2/6/1.20
    0.60    8.64 (window)
                                                    Brickwall
           60.78

                                                                  Right and left elevation

                         www.utm.my                innovative ● entrepreneurial ● global          50
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

8) FINISHES                                  Area of plastering
                                             and panting =        a                          3m
8.1) Wall - Plastering and painting          Area of wall x 2
 2/ 61m2           122 m2                    Area of ceiling =
                                             area of slab
8.2) Floor Finishes – cement render                               Front and rear elevation

                   53 m2

                                                                             b
8.3) Ceiling       53 m2


                                                      Brickwall

                                                                  Right and left elevation

                           www.utm.my              innovative ● entrepreneurial ● global          51
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

9) SUNDRIES                                  Assumption.
9.1) Built-in counter size 1800mm x 900mm    1 no of counter for frontdesk.
      x 725mm(h).


     1
                           1 no.




                        www.utm.my                 innovative ● entrepreneurial ● global   52
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities                                Unit     Quantity     Rate          Amount
1. Site Clearance
1. 1 Clear the site including grubbing of trees,
     shrubs and demolish any existing              M2              100          2.40         240.00
     structure and cart away and dump to
     the specified location.
1.    Site Clearance                                                                         240.00
2.    Foundation
2.1   Piling works
2.2   Excavation for pile cap < 2m deep            M3               21       39.50           829.50
2.3   Reinforced concrete G30                      M3                4      286.30         1,145.20
2.4   Lean concrete G15                            M3                1      194.50           194.50
2.5   Sawn formwork                                M2               14       29.60           414.40
2.6   Reinforcement bar Y12                        Kg              294        3.00           882.00
2.    Foundation                                                                           3,465.60

                           www.utm.my                     innovative ● entrepreneurial ● global   53
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities                          Unit      Quantity     Rate        Amount
3. WBLFF
3.1 Column Stump
3.1.1 Reinforced Concrete G30                M3                 1     297.10            297.10
3.1.2 Sawn formwork                          M2                 9      29.80            268.20
3.1.3 Reinforcement bar Y12                  Kg                95       3.00            285.00
3.1.4 Reinforcement bar R6                   Kg                 7       3.00             21.00
                                             Total                                      871.30
3.2 Ground beam
3.2.1 Excavation for ground beam < 1m deep   M3                 3      20.80             62.40
3.2.2 Reinforced concrete G30                M3                 3     293.50            880.50
3.2.3 Lean concrete G15                      M3                 1     201.70            201.70
3.2.4 Sawn formwork                          M2                26      29.60            769.60
3.2.5 Reinforcement bar Y12                  Kg                97       3.00              291
3.2.6 Reinforcement bar R6                   Kg                32       3.00                96
                                             Total                                   2,301.20

                        www.utm.my                   innovative ● entrepreneurial ● global   54
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities                           Unit       Quantity     Rate         Amount
3. WBLFF
3.3 Ground slab
3.2.1 Excavation for ground slab < 1m deep    M3                 27       20.80          561.60
3.2.2 Reinforced concrete G30                 M3                  8      293.50        2,348.00
3.2.3 Sawn formwork                           M2                  4       29.60          118.40
3.2.4 BRC A8                                  M2                 53       23.10        1,224.30
3.2.5 DPM                                     M2                 53       12.90          683.70
3.2.6 Sand blinding                           M2                 53        2.60          137.80
3.2.7 Hardcore                                M3                 16       51.80          828.80
                                              Total                                   5,902.60

3.4 Perimeter Drain
    Half round glazeware 150mm dia.           M                  29       11.30          327.70


3.   WBLFF                                                                            9,402.80


                         www.utm.my                   innovative ● entrepreneurial ● global   55
MEASURING QUANTITIES, PRICING & COST ANALYSIS
Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities                          Unit      Quantity     Rate        Amount
4. Frame
4.1 Column
4.1.1 Reinforced Concrete G30                M3                1      297.10            297.10
4.1.2 Sawn formwork                          M2               25       29.80            745.00
4.1.3 Reinforcement bar Y12                  Kg              144        3.00            432.00
4.1.4 Reinforcement bar R6                   Kg               23        3.00             69.00
                                             Total                                    1,543.10

4.2 Roof Beam
4.2.1 Reinforced Concrete G30                M3                 3     297.10            891.30
4.2.2 Sawn formwork to sides & soffit        M2                34      29.80          1,013.20
4.2.3 Reinforcement bar Y10                  Kg                97       3.00            291.00
4.2.4 Reinforcement bar R6                   Kg                39       3.00            117.00
                                             Total                                    2,312.50
4.   Frame                                                                           3,855.60


                         www.utm.my                  innovative ● entrepreneurial ● global   56
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities                          Unit     Quantity     Rate        Amount
5. Roof and covering
5. 1 Steel roof trusses and corrugated
     aluminium steel roof covering           M2               88      133.30       11,730.40


5.   Roof and covering                                                             11,730.40

6. Door and Window
6.1 Single leaf panel door size 2100 x 900
    including frame and painting             No                2      250.00           500.00
6.2 Adjustable louvres window 1200 x 600
    including frame , painting and glass     No               12      120.00         1,440.00


6.   Door and window                                                                 1,940.00

                         www.utm.my                 innovative ● entrepreneurial ● global   57
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Bills of Quantities                           Unit     Quantity     Rate        Amount
7. Wall and partition
7. 1 Half brickwall in common brick           M2               61       39.00         2,379.00
7.    Wall and partition                                                              2,379.00

8.    Finishes
8.1   Wall finishes – plastering & painting   M2              122       17.70         2,159.40
8.2   Floor finishes – cement rendering       M2               53       10.60           561.80
8.3   Ceiling – gypsum plaster board          M2               53       17.70           938.10
8.    Finishes                                                                        3,659.30
9. Sundries
9. 1 Built-in counter size 1800mm x 900mm     No.               1    1500.00          1,500.00
     x 725mm(h).



                           www.utm.my                innovative ● entrepreneurial ● global   58
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd
Summary of Bills of Quantities                                                 Amount (RM)
1. Site clearing                                                                    240.00
2. Foundation                                                                      3,271.1
3. WBLFF                                                                          9,402.80
4. Frame                                                                          3,855.60
5. Roof and covering                                                             11,730.40
6. Door and window                                                                1,940.00
7. Wall and partition                                                             2,379.00
8. Finishes                                                                       3,659.30
9. Sundries                                                                       1,500.00
Subtotal #1                                                                        37,978.20
10. Building services (5%)                                                          1,898.91
11. External works (3%)                                                             1,139.35
Subtotal #2                                                                        41,016.46
12. Preliminaries (3%)                                                              1,230.49
Total                                                                              42,246.95


                          www.utm.my                  innovative ● entrepreneurial ● global    59
MEASURING QUANTITIES, PRICING & COST ANALYSIS

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd      GFA = 37m2
Building Cost Analysis                                                          Cost/GFA = 1,136.00
Summary                           Amount (RM)    Amount (RM)        Actual %    Normal %    Explanation:
1.  Site Clearing                      240.00    -under Prelim              -           -
2.  Foundation                        3,271.1        3,280.00            8%
                                                                                 10 -20%
3.  WBLFF                            9,402.80        9,400.00           21%
4.  Frame                            3,855.60        3,860.00            9%        5-10%
5.  Roof and covering               11,730.40       11,730.00           27%       20-25%
6.  Door and window                  1,940.00        1,940.00            5%        5-10%
7.  Wall and partition               2,379.00        2,400.00            6%        5-10%
8.  Finishes                         3,659.30        3,660.00            9%        6-15%
9.  Sundries                         1,500.00        1,500.00            4%         1-5%
Subtotal #1                          37,978.20
10.     Building services (5%)        1,898.91       1,900.00            5%       10-25%
11.     External works (5%)           1,139.35       1,140.00            3%         3-7%
Subtotal #2                          41,016.46
12.     Preliminaries (5%)            1,230.49       1,230.00            3%         3-7%
Total                                42,246.95      42,040.00            100




                                 www.utm.my                      innovative ● entrepreneurial ● global     60

More Related Content

What's hot

Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2Azizan Supardi
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slideseenyeeyong
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Anne Allan
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compileTimun Loh
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of QuantityArissa Loh
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Anne Allan
 
ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA FormKai Yun Pang
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
ECA Workshop - Presentation
ECA Workshop - PresentationECA Workshop - Presentation
ECA Workshop - PresentationKai Yun Pang
 
Eca presentation
Eca presentationEca presentation
Eca presentationwendyteosy
 

What's hot (20)

Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2
 
ECA Presentation slide
ECA Presentation slideECA Presentation slide
ECA Presentation slide
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
ibs 304
ibs 304ibs 304
ibs 304
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Final Bills of Quantity
Final Bills of QuantityFinal Bills of Quantity
Final Bills of Quantity
 
Spun pile
Spun pileSpun pile
Spun pile
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
 
ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA Form
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
SMM2 Explained
SMM2 ExplainedSMM2 Explained
SMM2 Explained
 
ECA presentation
ECA presentationECA presentation
ECA presentation
 
ECA Workshop - Presentation
ECA Workshop - PresentationECA Workshop - Presentation
ECA Workshop - Presentation
 
Earthwork support
Earthwork supportEarthwork support
Earthwork support
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
ECA form
ECA formECA form
ECA form
 
Eca presentation
Eca presentationEca presentation
Eca presentation
 

Viewers also liked

Construction Estimating
Construction EstimatingConstruction Estimating
Construction Estimatingmauinick
 
Taylor: Estimating uncertainty for continental scale measurements.
Taylor:  Estimating uncertainty for continental scale measurements.Taylor:  Estimating uncertainty for continental scale measurements.
Taylor: Estimating uncertainty for continental scale measurements.questRCN
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Lee Pei Gie
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimatingalanchong88
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & CostingGanesh Murugan
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimatingAli Juma Albahrani
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costsmairemic
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methodsSimarpreet Singh
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 

Viewers also liked (17)

Construction Estimating
Construction EstimatingConstruction Estimating
Construction Estimating
 
Taylor: Estimating uncertainty for continental scale measurements.
Taylor:  Estimating uncertainty for continental scale measurements.Taylor:  Estimating uncertainty for continental scale measurements.
Taylor: Estimating uncertainty for continental scale measurements.
 
Estimating
EstimatingEstimating
Estimating
 
Tender Presentation ( Estimating )
Tender Presentation ( Estimating )Tender Presentation ( Estimating )
Tender Presentation ( Estimating )
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimating
 
Cost Estimation
Cost EstimationCost Estimation
Cost Estimation
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & Costing
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Project Estimating
Project EstimatingProject Estimating
Project Estimating
 
The estimating process
The estimating processThe estimating process
The estimating process
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Estimation
EstimationEstimation
Estimation
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 

Similar to Sgp4813 measurement of quantities

hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxZakaria156221
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxZakaria156221
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptxssuser2ec079
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxZiyad Zaidi
 
internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdfPAYALINAMDAR
 
The Glass House V3 The Economics of Glass in Ark Mode
The Glass House V3 The Economics of Glass in Ark ModeThe Glass House V3 The Economics of Glass in Ark Mode
The Glass House V3 The Economics of Glass in Ark ModeBrij Consulting, LLC
 
SYED MUHAMMED ANWAR
SYED MUHAMMED ANWARSYED MUHAMMED ANWAR
SYED MUHAMMED ANWARsyed manwar
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...Shabaz Khan
 
Analysis of Geodesic dome structure
Analysis of Geodesic dome structureAnalysis of Geodesic dome structure
Analysis of Geodesic dome structureIRJET Journal
 
internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteSrikanthReddy345872
 

Similar to Sgp4813 measurement of quantities (20)

hochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptxhochPPT thesis statement master civil engineering.pptx
hochPPT thesis statement master civil engineering.pptx
 
Présentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptxPrésentation master thesesis in civil department pptx
Présentation master thesesis in civil department pptx
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Prima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptxPrima Vera Final Project PPT.pptx
Prima Vera Final Project PPT.pptx
 
swati structure.ipt
swati structure.iptswati structure.ipt
swati structure.ipt
 
internship review .pdf
internship review .pdfinternship review .pdf
internship review .pdf
 
The Glass House V3 The Economics of Glass in Ark Mode
The Glass House V3 The Economics of Glass in Ark ModeThe Glass House V3 The Economics of Glass in Ark Mode
The Glass House V3 The Economics of Glass in Ark Mode
 
SYED MUHAMMED ANWAR
SYED MUHAMMED ANWARSYED MUHAMMED ANWAR
SYED MUHAMMED ANWAR
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
Flexible pavement
Flexible pavement  Flexible pavement
Flexible pavement
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
A COMPARATIVE STUDY ON PRECAST CONSTRUCTION AND CONVENTIONAL CONSTRUCTION FOR...
 
Analysis of Geodesic dome structure
Analysis of Geodesic dome structureAnalysis of Geodesic dome structure
Analysis of Geodesic dome structure
 
internship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering instituteinternship ppt.pptx civil engineering institute
internship ppt.pptx civil engineering institute
 

Recently uploaded

The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...ssuserf63bd7
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Associazione Digital Days
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifeBhavana Pujan Kendra
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamArik Fletcher
 

Recently uploaded (20)

The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
Horngren’s Financial & Managerial Accounting, 7th edition by Miller-Nobles so...
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in Life
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management Team
 

Sgp4813 measurement of quantities

  • 1. MEASURING QUANTITIES, PRICING & COST ANALYSIS ● Mat Naim bin Abdullah @ Mohd Asmoni ● Diploma QS (UTM), BSc. QS (Glasgow Caledonian University), M.Eng. Construction (UTM), PhD Facilities Management (UTM) ● matnaim@utm.my ● amn871969@yahoo.com ● C04-308 ● 019-7573760 www.utm.my innovative ● entrepreneurial ● global 1
  • 2. MEASURING QUANTITIES, PRICING & COST ANALYSIS Assumption No. 1: Total land area = 10m x 10m Project Title: Construction and completion of guard house Owner: Panicsonic Sdn Bhd Architect: A to Z Sdn Bhd Drawing Title: Ground beam and foundation plan ------------------------------------------------------------------------- Drawn by: Sheila Checked by: Aaron www.utm.my innovative ● entrepreneurial ● global 2
  • 3. MEASURING QUANTITIES, PRICING & COST ANALYSIS www.utm.my innovative ● entrepreneurial ● global 3
  • 4. MEASURING QUANTITIES, PRICING & COST ANALYSIS Construction Method 1. Preliminaries (Initial site works) - % of total cost 2. Site clearance and earthwork 3. Foundation construction (E.g. Piling and footing) 4. Work below lowest floor finish 5. Frame 6. Staircase 7. Upper Floor 8. Roof 9. Wall and partition 10. Door and window 11. Finishes 12. Sundries (Built-in furniture) 13. Building services (M&E, ICT etc) 14. External works (Water reticulation, landscape etc) www.utm.my innovative ● entrepreneurial ● global 4
  • 5. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 1) Site clearance 1.1) Clear the site including grubbing of Area of the site: trees, shrubs and demolish any 10 x 10 = 100m2 existing structure and cart away and dump to the specified location. 10.00 10.00 ---------- 100.00 100 m2 ---------- www.utm.my innovative ● entrepreneurial ● global 5
  • 6. MEASURING QUANTITIES, PRICING & COST ANALYSIS www.utm.my innovative ● entrepreneurial ● global 6
  • 7. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.1) Piling including all related works Area of the building: Length = 3048 + 3048 = 6096 6.10 Width = 3048 + 3048 = 6096 6.10 ---------- 37.21 37 m2 ---------- www.utm.my innovative ● entrepreneurial ● global 7
  • 8. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.2) Excavation for pile cap Size of pile cap = 1219 x 1219 Depth of excavation: 9/1.22 1524 + 50 (lean concrete) = 1574 1.22 1.57 ---------- 21.03 21 m3 ---------- Excavation and Lean concrete as base for pile cap www.utm.my innovative ● entrepreneurial ● global 8
  • 9. MEASURING QUANTITIES, PRICING & COST ANALYSIS www.utm.my innovative ● entrepreneurial ● global 9
  • 10. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.3) Reinforced concrete Grade 30 for Size of pile cap: pile cap Length = 1219 Width = 1219 9/1.22 Thickness = 305 1.22 0.31 ---------- 4.15 4 m3 ---------- Concrete for pile cap www.utm.my innovative ● entrepreneurial ● global 10
  • 11. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.4) 50mm thick lean concrete Grade Size of pile cap: 15 for pile cap Length = 1219 Width = 1219 9 / 1.22 1.22 0.05 ---------- 0.67 1 m3 ---------- Excavation and Lean concrete as base for pile cap www.utm.my innovative ● entrepreneurial ● global 11
  • 12. MEASURING QUANTITIES, PRICING & COST ANALYSIS www.utm.my innovative ● entrepreneurial ● global 12
  • 13. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.5) Formwork for pile cap Size of pile cap: Length = 1219 9 / 4 /1.22 Width = 1219 0.31 Thickness = 305 ---------- 13.62 14 m2 9/2/1.22 ---------- 0.31 6.81 9/2/1.50 0.31 8.37 15.18 15m2 Formwork for pile cap www.utm.my innovative ● entrepreneurial ● global 13
  • 14. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 2) Foundation 2.6) Reinforcement bar Y12 for pile cap Length: a c 9/2/ 12/ 1.53 ---------- b 330.48m x 0.89 kg/m = 294.13kg = a + b + c – cover ---------- = 305 + 1219 + 305 – 6(50) = 294 kg = 1829 – 300 = 1529 No. of bars: = (b/100) + 1 = ((1219 – 2(50)cover )/100 )+1 = 12 nos. www.utm.my innovative ● entrepreneurial ● global 14
  • 15. MEASURING QUANTITIES, PRICING & COST ANALYSIS @100 c/c www.utm.my innovative ● entrepreneurial ● global 15
  • 16. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF Taker off : Checked by: 3.1) Column stump Size of column stump: 3.1.1) Reinforced concrete Grade 30 Length = 229 for column stump Width = 229 Height = 1524 – 305 thickness of pile 9/0.23 cap – (351/2) Half of beam’s 0.23 thickness 1.04 = 1043.50 ---------- 0.50 1 m3 ---------- www.utm.my innovative ● entrepreneurial ● global 16
  • 17. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.1) Column stump Size of column stump: 3.1.2) Formwork for column stump Length = 229 Width = 229 9/4/0.23 Height = 1524 – 305 thickness of pile 1.04 cap – (351/2) Half of beam’s ---------- thickness 8.61 9 m2 = 1043.50 ---------- www.utm.my innovative ● entrepreneurial ● global 17
  • 18. MEASURING QUANTITIES, PRICING & COST ANALYSIS Height of column stump @100 c/c www.utm.my innovative ● entrepreneurial ● global 18
  • 19. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.1) Column stump Length = a + half beam’s thickness – 3.1.3) Reinforcement bar Y12 for cover + 2 laps column stump lap 9/4/2.97 ---------- a 106.92m x 0.89kg/m = 95.16kg ---------- lap 95kg = 1524 + (351/2) – 50 + (660x2) = 2969.50 www.utm.my innovative ● entrepreneurial ● global 19
  • 20. MEASURING QUANTITIES, PRICING & COST ANALYSIS General Notes www.utm.my innovative ● entrepreneurial ● global 20
  • 21. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.1) Column stump Length of link: (length of CS– 2cover) x 3.1.4) R6 link in for column stump 4 +hook Hook 9/6/0.62 ---------- 33.48m x 0.22kg/m = 7.36kg =(229-100)+(229-100)+(229-100)+(229- ---------- 100)+100=616 7kg No. of link: Height of column stump = 1043.50 =(1043.50/229)+1 = 6 nos. www.utm.my innovative ● entrepreneurial ● global 21
  • 22. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Size of ground beam: 3.2.1) Excavation for ground beam Length=3048+3048=6096 Width = 229 2/3/6.10 Thickness = 351 0.23 0.35 ---------- 2.95m3 ---------- 3m3 Excavation for ground beam www.utm.my innovative ● entrepreneurial ● global 22
  • 23. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Size of ground beam: 3.2.2) Reinforced concrete Grade 30 for Length=3048+3048=6096 ground beam Width = 229 Thickness = 351 2/3/6.10 0.23 0.35 ---------- 2.95m3 3m3 ---------- RC for ground beam www.utm.my innovative ● entrepreneurial ● global 23
  • 24. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Size of ground beam: 3.2.3) 50mm thick lean concrete Grade Length=3048+3048=6096 15 for ground beam Width = 229 Thickness = 351 2/3/6.10 0.23 0.05 ---------- 0.42m3 1 m3 ---------- RC for ground beam www.utm.my innovative ● entrepreneurial ● global 24
  • 25. MEASURING QUANTITIES, PRICING & COST ANALYSIS Assumption No. 1: Total land area = 10m x 10m Project Title: Construction and completion of guard house Owner: Panicsonic Sdn Bhd Architect: A to Z Sdn Bhd Drawing Title: Ground beam and foundation plan ------------------------------------------------------------------------- Drawn by: Sheila Checked by: Aaron www.utm.my innovative ● entrepreneurial ● global 25
  • 26. MEASURING QUANTITIES, PRICING & COST ANALYSIS Height of column stump @100 c/c www.utm.my innovative ● entrepreneurial ● global 26
  • 27. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Size of ground beam: 3.2.4) Formwork for ground beam Length=3048+3048=6096 Width = 229 Thickness = 351 2/3/2/6.10 0.35 ---------- 25.62 26m2 ---------- Installation of reinforcement bar and formwork for ground beam www.utm.my innovative ● entrepreneurial ● global 27
  • 28. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Length = (length–2cover)+(2bend- 3.2.5) Reinforcement bar Y10 for 2cover) ground beam =(6096-(2x50))+(2x351)-(4x50) = 6498 2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ---------- 97kg www.utm.my innovative ● entrepreneurial ● global 28
  • 29. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.2) Ground beam Length of stirrup: 3.2.6) R6 stirrup for ground beam Hook 2/3/28/0.86 ---------- =(229-100)+(351-100)+(229-100)+(351- 144.48m x 0.22kg/m = 31.79kg 100)+100 ---------- =860 32kg No. of stirrup: Length of grd beam= 6096 =(6096/229)+1 = 28 nos. www.utm.my innovative ● entrepreneurial ● global 29
  • 30. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab including apron = length x width 3.3.1) Excavation for ground slab Depth of excavation = 500mm 7.30 7.30 BRC A8 150mm thick concrete slab 0.50 ---------- 26.65m3 27 m3 ---------- 50mm thick sand 300mm thick hardcore DPM 6096 + 1200 (apron) = 7296 Installation of formwork,Damp Proof Membrane (DPM) and BRC wire mesh for ground slab www.utm.my innovative ● entrepreneurial ● global 30
  • 31. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.2) Reinforced concrete G30 in Depth of excavation = 500mm ground slab 150mm thick BRC A8 concrete slab 7.30 7.30 0.15 50mm thick ---------- sand 7.99m3 300mm thick hardcore ---------- 8 m3 DPM www.utm.my innovative ● entrepreneurial ● global 31
  • 32. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.3) Formwork for ground slab Depth of excavation = 500mm 4/7.30 BRC A8 150mm thick concrete slab 0.15 ---------- 4.38m2 50mm thick ---------- sand 4 m2 300mm thick hardcore DPM www.utm.my innovative ● entrepreneurial ● global 32
  • 33. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab including apron 3.3.4) BRC A8 for ground slab Depth of excavation = 500mm 150mm thick BRC A8 concrete slab 7.30 7.30 ---------- 50mm thick sand 53.29m2 300mm thick ---------- hardcore 53 m2 DPM Length = 6096 + 1200 = 7296 www.utm.my innovative ● entrepreneurial ● global 33
  • 34. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.5) DPM for ground slab Depth of excavation = 500mm 150mm thick BRC A8 53 m2 concrete slab 50mm thick sand 300mm thick hardcore DPM www.utm.my innovative ● entrepreneurial ● global 34
  • 35. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.6) 50mm sand blinding for ground Depth of excavation = 500mm slab 150mm thick BRC A8 53 m2 concrete slab 50mm thick sand 300mm thick hardcore DPM www.utm.my innovative ● entrepreneurial ● global 35
  • 36. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.3) Ground slab Area of slab = length x width 3.3.7) Hardcore for ground slab Depth of excavation = 500mm 7.30 BRC A8 150mm thick concrete slab 7.30 0.30 ---------- 50mm thick 15.99m3 sand ---------- 300mm thick hardcore 16 m3 DPM www.utm.my innovative ● entrepreneurial ● global 36
  • 37. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 3) WBLFF 3.4) Half round glazeware perimeter Area of slab = length x width drain size 150mm diameter Depth of excavation = 500mm 4/7.30 BRC A8 150mm thick concrete slab ---------- 29.20m ---------- 50mm thick 29 m sand 300mm thick hardcore DPM www.utm.my innovative ● entrepreneurial ● global 37
  • 38. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME Taker off : Checked by: 4.1) Column Size of column: 4.1.1) Reinforced concrete Grade 30 Length = 229 for column Width = 229 Height = Height of the wall 9/0.23 = 3000mm 0.23 3.00 ---------- 1.43 1 m3 ---------- Installation of reinforcement bar and formwork for column www.utm.my innovative ● entrepreneurial ● global 38
  • 39. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.1) Column Size of column: 4.1.2) Formwork for column Length = 229 Width = 229 9/4/0.23 Height = 3000 3.00 ---------- 24.84 25 m2 ---------- www.utm.my innovative ● entrepreneurial ● global 39
  • 40. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.1) Column Length = height of column + half of roof 4.1.3) Reinforcement bar Y12 for beam + 1 lap + bend column bend 9/4/4.50 ---------- Height of wall 162.00m x 0.89kg/m = 144.18kg ---------- 144kg lap = 3000+ (0.5x351) + 660 + 660 = 4495.5 www.utm.my innovative ● entrepreneurial ● global 40
  • 41. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.1) Column Length of link: (length of CS– 2cover) x 4.1.4) R6 link in for column 4 +hook Hook 9/14/0.82 ---------- 103.32m x 0.22kg/m = 22.73kg =(229-50)+(229-50)+(229-50)+(229- ---------- 50)+100=816 23kg No. of link: Height of column = 3000 =(3000/229)+1 = 14 nos. www.utm.my innovative ● entrepreneurial ● global 41
  • 42. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.2) Roof beam Size of roof beam: 4.2.1) Reinforced concrete Grade 30 for Length=3048+3048=6096 roof beam Width = 229 Thickness = 351 2/3/6.10 0.23 0.35 ---------- 2.95m3 ---------- 3m3 www.utm.my innovative ● entrepreneurial ● global 42
  • 43. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.2) Roof beam Size of roof beam: 4.2.2) Formwork for roof beam Length=3048+3048=6096 Width = 229 Side Thickness = 351 2/3/6.10 Soffit 0.93 ---------- 34.04 34m2 ---------- = 351 + 229 + 351 = 931 www.utm.my innovative ● entrepreneurial ● global 43
  • 44. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 4.2) Roof beam Length = (length–2cover)+(2bend- 4.2.3) Reinforcement bar Y10 for roof 2cover) beam =(6096-(2x50))+(2x351)-(4x50) = 6498 2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ---------- 97kg www.utm.my innovative ● entrepreneurial ● global 44
  • 45. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 4) FRAME 3.2) Roof beam Length of stirrup: 3.2.5) R6 stirrup for roof beam Hook 2/3/28/1.06 ---------- =(229-50)+(351-50)+(229-50)+(351- 178.08m x 0.22kg/m = 39.18kg 50)+100 ---------- =1060 39kg No. of stirrup: Length of beam= 6096 =(6096/229)+1 = 28 nos. www.utm.my innovative ● entrepreneurial ● global 45
  • 46. MEASURING QUANTITIES, PRICING & COST ANALYSIS Assumption No. 1: Total land area = 10m x 10m Project Title: Construction and completion of guard house Owner: Panicsonic Sdn Bhd Architect: A to Z Sdn Bhd Drawing Title: Ground beam and foundation plan ------------------------------------------------------------------------- Drawn by: Sheila Checked by: Aaron www.utm.my innovative ● entrepreneurial ● global 46
  • 47. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 5) ROOF = area of roof =axbx2 a 3m 5.1) Steel roof trusses and corrugated aluminium steel roof covering 2/8.50 a = 42482 + 30002 5.20 ---------- Front and rear elevation 88.40m2 88 m2 a = 5200 ---------- b = 6096 + 1200 + b 1200 b = 8496 Right and left elevation www.utm.my innovative ● entrepreneurial ● global 47
  • 48. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 6) DOOR and WINDOW Door can be measured either a 3m 6.1) Single leaf panel door size 2100 x 900 in m2 or including frame and painting number. If enumerated then 2/2.10 need to state 0.90 type and size ---------- Front and rear elevation 3.78 4 m2 or 2 nos ---------- b Right and left elevation www.utm.my innovative ● entrepreneurial ● global 48
  • 49. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 6) DOOR and WINDOW Window can be measured either a 3m 6.2) Adjustable louvres window 1200 x 600 in m2 or including frame , painting and glass number. If enumerated then need to state 2/6/1.20 type and size 0.60 Front and rear elevation ---------- 8.64 8.64 m2 or 12 nos ---------- b Right and left elevation www.utm.my innovative ● entrepreneurial ● global 49
  • 50. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 7) WALL AND PARTITION a 3m 7.1) Half brickwall in comon brick 4/ 6.10 3.00 73.20 Less opening (e.g. door and window) Front and rear elevation 2/2.10 0.90 3.78 (door) 61 m2 b 2/6/1.20 0.60 8.64 (window) Brickwall 60.78 Right and left elevation www.utm.my innovative ● entrepreneurial ● global 50
  • 51. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 8) FINISHES Area of plastering and panting = a 3m 8.1) Wall - Plastering and painting Area of wall x 2 2/ 61m2 122 m2 Area of ceiling = area of slab 8.2) Floor Finishes – cement render Front and rear elevation 53 m2 b 8.3) Ceiling 53 m2 Brickwall Right and left elevation www.utm.my innovative ● entrepreneurial ● global 51
  • 52. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd 9) SUNDRIES Assumption. 9.1) Built-in counter size 1800mm x 900mm 1 no of counter for frontdesk. x 725mm(h). 1 1 no. www.utm.my innovative ● entrepreneurial ● global 52
  • 53. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd Bills of Quantities Unit Quantity Rate Amount 1. Site Clearance 1. 1 Clear the site including grubbing of trees, shrubs and demolish any existing M2 100 2.40 240.00 structure and cart away and dump to the specified location. 1. Site Clearance 240.00 2. Foundation 2.1 Piling works 2.2 Excavation for pile cap < 2m deep M3 21 39.50 829.50 2.3 Reinforced concrete G30 M3 4 286.30 1,145.20 2.4 Lean concrete G15 M3 1 194.50 194.50 2.5 Sawn formwork M2 14 29.60 414.40 2.6 Reinforcement bar Y12 Kg 294 3.00 882.00 2. Foundation 3,465.60 www.utm.my innovative ● entrepreneurial ● global 53
  • 54. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd Bills of Quantities Unit Quantity Rate Amount 3. WBLFF 3.1 Column Stump 3.1.1 Reinforced Concrete G30 M3 1 297.10 297.10 3.1.2 Sawn formwork M2 9 29.80 268.20 3.1.3 Reinforcement bar Y12 Kg 95 3.00 285.00 3.1.4 Reinforcement bar R6 Kg 7 3.00 21.00 Total 871.30 3.2 Ground beam 3.2.1 Excavation for ground beam < 1m deep M3 3 20.80 62.40 3.2.2 Reinforced concrete G30 M3 3 293.50 880.50 3.2.3 Lean concrete G15 M3 1 201.70 201.70 3.2.4 Sawn formwork M2 26 29.60 769.60 3.2.5 Reinforcement bar Y12 Kg 97 3.00 291 3.2.6 Reinforcement bar R6 Kg 32 3.00 96 Total 2,301.20 www.utm.my innovative ● entrepreneurial ● global 54
  • 55. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd Bills of Quantities Unit Quantity Rate Amount 3. WBLFF 3.3 Ground slab 3.2.1 Excavation for ground slab < 1m deep M3 27 20.80 561.60 3.2.2 Reinforced concrete G30 M3 8 293.50 2,348.00 3.2.3 Sawn formwork M2 4 29.60 118.40 3.2.4 BRC A8 M2 53 23.10 1,224.30 3.2.5 DPM M2 53 12.90 683.70 3.2.6 Sand blinding M2 53 2.60 137.80 3.2.7 Hardcore M3 16 51.80 828.80 Total 5,902.60 3.4 Perimeter Drain Half round glazeware 150mm dia. M 29 11.30 327.70 3. WBLFF 9,402.80 www.utm.my innovative ● entrepreneurial ● global 55
  • 56. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd Bills of Quantities Unit Quantity Rate Amount 4. Frame 4.1 Column 4.1.1 Reinforced Concrete G30 M3 1 297.10 297.10 4.1.2 Sawn formwork M2 25 29.80 745.00 4.1.3 Reinforcement bar Y12 Kg 144 3.00 432.00 4.1.4 Reinforcement bar R6 Kg 23 3.00 69.00 Total 1,543.10 4.2 Roof Beam 4.2.1 Reinforced Concrete G30 M3 3 297.10 891.30 4.2.2 Sawn formwork to sides & soffit M2 34 29.80 1,013.20 4.2.3 Reinforcement bar Y10 Kg 97 3.00 291.00 4.2.4 Reinforcement bar R6 Kg 39 3.00 117.00 Total 2,312.50 4. Frame 3,855.60 www.utm.my innovative ● entrepreneurial ● global 56
  • 57. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd Bills of Quantities Unit Quantity Rate Amount 5. Roof and covering 5. 1 Steel roof trusses and corrugated aluminium steel roof covering M2 88 133.30 11,730.40 5. Roof and covering 11,730.40 6. Door and Window 6.1 Single leaf panel door size 2100 x 900 including frame and painting No 2 250.00 500.00 6.2 Adjustable louvres window 1200 x 600 including frame , painting and glass No 12 120.00 1,440.00 6. Door and window 1,940.00 www.utm.my innovative ● entrepreneurial ● global 57
  • 58. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd Bills of Quantities Unit Quantity Rate Amount 7. Wall and partition 7. 1 Half brickwall in common brick M2 61 39.00 2,379.00 7. Wall and partition 2,379.00 8. Finishes 8.1 Wall finishes – plastering & painting M2 122 17.70 2,159.40 8.2 Floor finishes – cement rendering M2 53 10.60 561.80 8.3 Ceiling – gypsum plaster board M2 53 17.70 938.10 8. Finishes 3,659.30 9. Sundries 9. 1 Built-in counter size 1800mm x 900mm No. 1 1500.00 1,500.00 x 725mm(h). www.utm.my innovative ● entrepreneurial ● global 58
  • 59. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd Summary of Bills of Quantities Amount (RM) 1. Site clearing 240.00 2. Foundation 3,271.1 3. WBLFF 9,402.80 4. Frame 3,855.60 5. Roof and covering 11,730.40 6. Door and window 1,940.00 7. Wall and partition 2,379.00 8. Finishes 3,659.30 9. Sundries 1,500.00 Subtotal #1 37,978.20 10. Building services (5%) 1,898.91 11. External works (3%) 1,139.35 Subtotal #2 41,016.46 12. Preliminaries (3%) 1,230.49 Total 42,246.95 www.utm.my innovative ● entrepreneurial ● global 59
  • 60. MEASURING QUANTITIES, PRICING & COST ANALYSIS Project: Construction and completion of Guard House for Panicsonic Sdn Bhd GFA = 37m2 Building Cost Analysis Cost/GFA = 1,136.00 Summary Amount (RM) Amount (RM) Actual % Normal % Explanation: 1. Site Clearing 240.00 -under Prelim - - 2. Foundation 3,271.1 3,280.00 8% 10 -20% 3. WBLFF 9,402.80 9,400.00 21% 4. Frame 3,855.60 3,860.00 9% 5-10% 5. Roof and covering 11,730.40 11,730.00 27% 20-25% 6. Door and window 1,940.00 1,940.00 5% 5-10% 7. Wall and partition 2,379.00 2,400.00 6% 5-10% 8. Finishes 3,659.30 3,660.00 9% 6-15% 9. Sundries 1,500.00 1,500.00 4% 1-5% Subtotal #1 37,978.20 10. Building services (5%) 1,898.91 1,900.00 5% 10-25% 11. External works (5%) 1,139.35 1,140.00 3% 3-7% Subtotal #2 41,016.46 12. Preliminaries (5%) 1,230.49 1,230.00 3% 3-7% Total 42,246.95 42,040.00 100 www.utm.my innovative ● entrepreneurial ● global 60