SlideShare a Scribd company logo
1 of 22
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Define Activities
PMPChapter 6 –
Project Schedule Management
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule management
Overview
Define activity Process definition
Define Activity: ITTO
What is Decomposition?
What is Rolling wave planning?
What is Activity list?
What is Activity Attributes?
Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Schedule Management processes
Plan Schedule
management
Define Activities Sequence Activities
Estimate Activity
Duration
Develop Schedule Control Schedule
P P P
MCP P
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Define Activities -> Overview
CRM Project
Initiation
Project charter
Feasibility Study
Business Case
Stakeholder List
Project Kick-off
Study
Business
Requirement
Document
Reporting
Requirements
System
Requirements
PMP
Vendor selection
Integration
Requirements
Design & Build
System Design
High level Design
Low level Design
System Build
Sales Module
Marketing
Modules
Engagement
Social
Collaboration
VOC Dashboards
Test
System Testing
Integration
Testing
User Acceptance
Testing
Security Testing
Performance
Testing
Operate
Training
Go-live
Handover
Training
Contract Closure
Project closure
Training
Identify
Participants
Prepare Training
Presentation
Schedule Training
Arrange Training
Facility
Setup Training
environment
Conduct Training
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Identifying & documenting specific actions to be
performed to produce project deliverables.
Break work packages into activities that provide a basis for estimating,
scheduling, executing, monitoring & controlling the project work.
Define Activities -> Definition
Identifying &
Documenting
Specific
Actions
Produce
Project
Deliverables
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Define activities -> ITTO
Expert Judgment
Decomposition
Meetings
Rolling Wave planning
Project Management
plan
Enterprise
environmental factors
Organizational
process assets
Activity list
Activity attributes
Milestone list
Change Request
PMP Updates
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
PMP EEF OPA
Define activities -> Input
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management plan
Following plans & baseline will provide key inputs:
Define Activities -> Input -> PMP
Schedule Management plan:
•Prescribed level of details necessary to manage
the work.
•Guideline to define activities (e.g., max duration)
Scope baseline:
Project scope
statement:
WBS: WBS dictionary
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Organizational culture &
structure.
published Commercial
information.
Project Management
Information System
(PMIS)
Define Activities -> Input->EEF
Enterprise
environmental factors
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Lessons learned
about activity list.
Templates with
standard activity
list.
policies,
procedures, and
guidelines
Activity list from
Historical project
data.
Define Activities -> Input-> OPA
Organizational
process assets
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert Judgment Decomposition Meetings
Rolling Wave
planning
Define Activities -> Tools & Techniques
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Decomposition
Dividing & subdividing project scope & deliverables in smaller & more manageable parts.
Activities represent efforts needed to complete work package.
Best done by teams rather than individuals
Define Activities -> T&T -> Decomposition
------> Activity List
Identify Participants
Prepare Training
Presentation
Schedule a Training
Arrange Training Facility
Setup Training environment
Conduct Training
Training
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
An iterative planning technique in which:
work to be accomplished in near term is
planned in details.
while work in future is planned at a higher
level.
Define Activities -> T&T -> Rolling wave planning
Jan Feb Mar Apr May Jun Jul Aug Sep
Rolling Wave
planning
Planning Package:- Work
packages can be decomposed
further when sufficient
information is available.
Form of Progressive
Elaboration
CRM Project
Initiation
Project charter
Feasibility Study
Business Case
Stakeholder List
Study
Business
Requirement
Document
Reporting
Requirements
System
Requirements
Vendor selection
Integration
Requirements
Design & Build
System Design
High level
Design
Low level
Design
System Build
Build module1
Build Module2
Build Module3
Integration
Build
Reports Build
Test Operate
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Meetings
Meetings are useful tool for planning, especially while using decomposition technique
Participants may include, anyone with responsibility for schedule planning &/or execution
Who's the best person to define activities: Person responsible to execute them.
Define Activities -> T&T -> Expert Judgment
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Define Activities -> Outputs
Activity list Activity attributes Milestone list
Change Request PMP Updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Result of decomposition technique applied to the work packages of the WBS.
Rolling wave planning - activities list may be updated periodically
Unique activity id, WBS reference, Label & description of each activity.
Activity ID WBS Id Name
501 W50 Identify Participants
502 W50 Prepare Training Presentation
503 W50 Schedule Training
504 W50 Arrange Training Facility
505 W50 Setup Training environment
506 W50 Conduct Training
Define Activities -> Outputs -> Activity List
Activity list
Helps in accurate
estimation
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Activity
attributes
Activity attributes are details related to the activities in the activity list
These attributes will be
updated as we progress in
the process of schedule
creation
• Resource
requirements
• Geographic area or
place
• Predecessor activities
• Successor activities
• Logical relationships
• Imposed dates
• Assumptions
• Person responsible
Information available during the initial stages of scheduling:
Activity identifier (ID) WBS ID Activity label or name
Define Activities -> Outputs ->Activity Attributes
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Milestone list
A milestone is a significant point in the project.
A milestone list identifies all project milestones
Used for setting schedule goals & monitoring progress.
Define Activities -> Outputs ->Milestone List
Zero duration task with no. resources
Milestone may be mandatory (contractual), or just for planning(guidance).
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Change Request
If progressive elaboration is used, then after the initial iteration of the plan, new activities
will be identified & added in further iterations.
Activities will be added to the activity list through a change request.
Define Activities -> Outputs -> Change Request
CRM Project
Initiation
Project charter
Feasibility Study
Business Case
Stakeholder List
Study
Business
Requirement
Document
Reporting
Requirements
System
Requirements
Vendor selection
Integration
Requirements
Design & Build
System Design
High level
Design
Low level
Design
System Build
Build module1
Build Module2
Build Module3
Integration
Build
Reports Build
Test
System Testing
Integration Testing
User Acceptance
Testing
Security Testing
Performance
Testing
Operate
Training
Go-live
Handover Training
Contract Closure
Project closure
Jan Feb Mar Apr May Jun Jul Aug Sep
New activities
will be added
after Change
Request.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
PMP Updates
Baseline may be change due to addition of new activities to the activity list.
Define Activities -> Outputs -> PMP Updates
Schedule baseline Cost baseline
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Defining activities by Decomposing work package
Define activity Process definition
Define Activity: ITTO
What is decomposition?
What is rolling wave planning?
What is Activity list?
What is Activity Attributes?
Define Activities -> Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Don’t wait for the perfect moment. Take the moment and
make it perfect.

More Related Content

What's hot

Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality managementAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2Anand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage QualityAnand Bobade
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledgeAnand Bobade
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 

What's hot (20)

Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
project management
project managementproject management
project management
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management Overview
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
chap 4.4 Manage knowledge
chap 4.4 Manage knowledgechap 4.4 Manage knowledge
chap 4.4 Manage knowledge
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 

Similar to Chap 6.2 Define Activity

Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersAnand Bobade
 
Chap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderChap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderAnand Bobade
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
 

Similar to Chap 6.2 Define Activity (20)

Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholdersChap 13.1 Identify stakeholders
Chap 13.1 Identify stakeholders
 
Chap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholderChap 13.3 Manage stakeholder
Chap 13.3 Manage stakeholder
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 

More from Anand Bobade (9)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 

Recently uploaded

Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdffillmonipdc
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skillskristinalimarenko7
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 

Recently uploaded (20)

Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdf
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skills
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 

Chap 6.2 Define Activity

  • 1. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Define Activities PMPChapter 6 – Project Schedule Management
  • 2. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule management Overview Define activity Process definition Define Activity: ITTO What is Decomposition? What is Rolling wave planning? What is Activity list? What is Activity Attributes? Review
  • 3. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Schedule Management processes Plan Schedule management Define Activities Sequence Activities Estimate Activity Duration Develop Schedule Control Schedule P P P MCP P
  • 4. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Define Activities -> Overview CRM Project Initiation Project charter Feasibility Study Business Case Stakeholder List Project Kick-off Study Business Requirement Document Reporting Requirements System Requirements PMP Vendor selection Integration Requirements Design & Build System Design High level Design Low level Design System Build Sales Module Marketing Modules Engagement Social Collaboration VOC Dashboards Test System Testing Integration Testing User Acceptance Testing Security Testing Performance Testing Operate Training Go-live Handover Training Contract Closure Project closure Training Identify Participants Prepare Training Presentation Schedule Training Arrange Training Facility Setup Training environment Conduct Training
  • 5. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Identifying & documenting specific actions to be performed to produce project deliverables. Break work packages into activities that provide a basis for estimating, scheduling, executing, monitoring & controlling the project work. Define Activities -> Definition Identifying & Documenting Specific Actions Produce Project Deliverables
  • 6. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Define activities -> ITTO Expert Judgment Decomposition Meetings Rolling Wave planning Project Management plan Enterprise environmental factors Organizational process assets Activity list Activity attributes Milestone list Change Request PMP Updates Inputs Tools & Techniques Outputs
  • 7. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) PMP EEF OPA Define activities -> Input
  • 8. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management plan Following plans & baseline will provide key inputs: Define Activities -> Input -> PMP Schedule Management plan: •Prescribed level of details necessary to manage the work. •Guideline to define activities (e.g., max duration) Scope baseline: Project scope statement: WBS: WBS dictionary
  • 9. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Organizational culture & structure. published Commercial information. Project Management Information System (PMIS) Define Activities -> Input->EEF Enterprise environmental factors
  • 10. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Lessons learned about activity list. Templates with standard activity list. policies, procedures, and guidelines Activity list from Historical project data. Define Activities -> Input-> OPA Organizational process assets
  • 11. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Expert Judgment Decomposition Meetings Rolling Wave planning Define Activities -> Tools & Techniques
  • 12. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Decomposition Dividing & subdividing project scope & deliverables in smaller & more manageable parts. Activities represent efforts needed to complete work package. Best done by teams rather than individuals Define Activities -> T&T -> Decomposition ------> Activity List Identify Participants Prepare Training Presentation Schedule a Training Arrange Training Facility Setup Training environment Conduct Training Training
  • 13. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) An iterative planning technique in which: work to be accomplished in near term is planned in details. while work in future is planned at a higher level. Define Activities -> T&T -> Rolling wave planning Jan Feb Mar Apr May Jun Jul Aug Sep Rolling Wave planning Planning Package:- Work packages can be decomposed further when sufficient information is available. Form of Progressive Elaboration CRM Project Initiation Project charter Feasibility Study Business Case Stakeholder List Study Business Requirement Document Reporting Requirements System Requirements Vendor selection Integration Requirements Design & Build System Design High level Design Low level Design System Build Build module1 Build Module2 Build Module3 Integration Build Reports Build Test Operate
  • 14. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Meetings Meetings are useful tool for planning, especially while using decomposition technique Participants may include, anyone with responsibility for schedule planning &/or execution Who's the best person to define activities: Person responsible to execute them. Define Activities -> T&T -> Expert Judgment
  • 15. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Define Activities -> Outputs Activity list Activity attributes Milestone list Change Request PMP Updates
  • 16. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Result of decomposition technique applied to the work packages of the WBS. Rolling wave planning - activities list may be updated periodically Unique activity id, WBS reference, Label & description of each activity. Activity ID WBS Id Name 501 W50 Identify Participants 502 W50 Prepare Training Presentation 503 W50 Schedule Training 504 W50 Arrange Training Facility 505 W50 Setup Training environment 506 W50 Conduct Training Define Activities -> Outputs -> Activity List Activity list Helps in accurate estimation
  • 17. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Activity attributes Activity attributes are details related to the activities in the activity list These attributes will be updated as we progress in the process of schedule creation • Resource requirements • Geographic area or place • Predecessor activities • Successor activities • Logical relationships • Imposed dates • Assumptions • Person responsible Information available during the initial stages of scheduling: Activity identifier (ID) WBS ID Activity label or name Define Activities -> Outputs ->Activity Attributes
  • 18. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Milestone list A milestone is a significant point in the project. A milestone list identifies all project milestones Used for setting schedule goals & monitoring progress. Define Activities -> Outputs ->Milestone List Zero duration task with no. resources Milestone may be mandatory (contractual), or just for planning(guidance).
  • 19. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Change Request If progressive elaboration is used, then after the initial iteration of the plan, new activities will be identified & added in further iterations. Activities will be added to the activity list through a change request. Define Activities -> Outputs -> Change Request CRM Project Initiation Project charter Feasibility Study Business Case Stakeholder List Study Business Requirement Document Reporting Requirements System Requirements Vendor selection Integration Requirements Design & Build System Design High level Design Low level Design System Build Build module1 Build Module2 Build Module3 Integration Build Reports Build Test System Testing Integration Testing User Acceptance Testing Security Testing Performance Testing Operate Training Go-live Handover Training Contract Closure Project closure Jan Feb Mar Apr May Jun Jul Aug Sep New activities will be added after Change Request.
  • 20. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) PMP Updates Baseline may be change due to addition of new activities to the activity list. Define Activities -> Outputs -> PMP Updates Schedule baseline Cost baseline
  • 21. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Defining activities by Decomposing work package Define activity Process definition Define Activity: ITTO What is decomposition? What is rolling wave planning? What is Activity list? What is Activity Attributes? Define Activities -> Review
  • 22. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Don’t wait for the perfect moment. Take the moment and make it perfect.