SlideShare a Scribd company logo
1 of 37
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Estimate Activity
Duration
PMPChapter 6 –
Project Schedule Management
SIXTH EDITION
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Duration
Overview
Estimate Activity Duration Definition
Important terms
Estimate Activity Duration : ITTO
Estimation techniques – Analogues, Parametric, 3P
Duration estimate & basis of estimation
Review
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Schedule Management processes
Plan Schedule
management
Define Activities Sequence Activities
Estimate Activity
Duration
Develop Schedule Control Schedule
P P P
MCP P
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration-> Introduction
SME Technical Lead
Solution Architect Quality expert
Estimation is joint activity, respective experts has to
estimate their work. PM is responsible to aggregation.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Resources Advances in technology
Staff Motivation Law of diminishing returns
Estimate Activity Duration-> Key factors than influences estimation:
Key factors than influences estimation:
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration-> Key factors than influences estimation:
The number of resources
•Increasing the number of resources to twice does not always
reduce the time by half.
•It may increase extra duration due to risk.
Advances in technology
•Plays an important role in estimating duration.
•Ex: Road construction work can be expedited by procuring fully
automated machines.
•This may impact duration, cost and resource needs
Staff Motivation
•Aware of the Student Syndrome or procrastination.
•When resources start working at last possible moment before the
deadline, Parkinson’s Law come in effect.
•Parkinson’s Law - Work expands to fill time available for its
completion
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Law of diminishing
returns
Refer to a point at which, benefits gained is less than the amount of efforts and/or
money invested.
When one factor, e.g., resource is increased, & all other factors remain fixed, you may get
increased output.
However, A point will eventually be reached at which additions of that factor start to
yield diminishing output.
Estimate Activity Duration-> Key factors than influences estimation:
1
2
3
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Example: Painting a house
Estimate Activity Duration-> Important Terms
• 20 daysEfforts
• 10 days
• With 2 resources
Duration
• 15 days
• Includes (2 weekends & 1 day holiday by resources)
Elapsed Time
Day1 Day2 Day3 Day4 Day5 Day6 Day7 Day8 Day9 Day10 Day11 Day12 Day13 Day14 Day15
Work Started
1-Jan (Sunday)
Work completed
15-Jan (Sunday)
Weekend Weekend
Resource on
Holiday
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimating number of work periods needed to complete each
activity with estimated resources.
It is a major input to Develop Schedule process.
Activity
Estimate Activity Duration -> Definition
Estimating
Work Periods per
activity
With estimated
resources
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration -> ITTO
Expert Judgments
Analogous Estimates
Parametric Estimates
Three point estimates
Bottom up estimates
Data analysis
Decision making
Meetings
Project Management
plan
Project Documents
Enterprise
environmental factors
Organizational process
assets
Duration Estimates
Basis of estimates
Project documents
updates
Inputs Tools & Techniques Outputs
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration -> Input
Project Management
plan
Project Documents
Enterprise
environmental factors
Organizational process
assets
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Management plan
Following PMP subsidiary plans & baselines can be used as input:
Estimate Activity Duration -> Input -> PMP
Schedule Management
plan
Scope baseline
Scope baseline -> Project Scope statement:
• Project scope statement provides description of the
• Project scope, Major deliverables, Assumptions & Constraints
• Expect senior expert to work on the technical design due to requirements complexity.
• Impact on estimation: Longer estimate; multiple resource may not be able to reduce
estimate proportionally.
Assumption
• Requirement has to be implemented before 1-Aug, due to government legislation.
• Impact on estimation: Multiple resource may be added to shorten the duration of
activity.
Constraint
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project Documents
Following Project Documents can be used as input:
Activity list
Activity
attributes
Assumption
log
Resource
breakdown st.
Resource
Requirements
Risk Register
Resource
Calendar
Milestone list
Lessons
Register Reg.
Project team
assignments
Estimate Activity Duration -> Input -> Project documents
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Activity list:
• A list of all activities under each work package.
Activity ID WBS Id Name Description
501 W50 Compare Furniture brands
502 W50 Find showrooms
503 W50 Get Quotes
504 W50 Compare Quotes
Estimate Activity Duration -> Input -> Project documents ->Activity List
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Activity attributes:
• Additional details of activities, which are useful for estimation.
Predecessor
activities
Successor
activities
Logical
relationships
Leads and lags
Resource
requirements
Imposed
dates
Constraints Assumptions
Person
responsible
Geographic
area or place
Calendar
Estimate Activity Duration->Input->Activity Attributes
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Resource Requirements:
• The types and quantities of resources required for each activity in a work package.
• Aggregated to determine resource estimation for each work package.
Estimate Activity Dur.->Inputs-> Resource Requirement
Activity
ID
WBS
Id
Name Resource Type Quantity
601 W51 Unit Testing Developer 5
602 W51 System Testing Test Analyst 10
603 W51 Performance Testing Sr. Performance Test
Analyst
2
604 W51 Security testing Security expert 2
Resource Type Resource Quantity
Total Resources for
Work Package
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Resource Calendars:
• Identifies working days & shifts when each resource is available.
• Details about how long resource will be available.
• Other details – Skill, Skill levels, location etc
Estimate Activity Duration->Input->Resource Calendar
•Resource may be material, human resources, equipment etcRemember:
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Risk Register:
• Concerns with results of Risk analysis & response planning.
• List of Risks related to estimations & resources.
Estimate Activity Duration->Input->Risk Register
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Resource Breakdown Structure:
• Hierarchical representation of resources by category or type.
• Used for searching Resources.
Construction Project
Labor
Managers
Manager1
Manager2
Workers
Worker1
Worker2
Worker3
Material
Building
Office setup
Equipment
Desktop
Laptop
Printer
Projector
Supplies
Printer
Cartridges
Papers
Stationary
Estimate Activity Duration->Inputs-> RBS
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Enterprise
environmental factors
Duration
estimating
databases & other
reference data.
Productivity
metrics.
Published
commercial
information.
Location of team
members.
Estimate Activity Duration -> Input -> EEF
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Organizational
process assets
Historical
duration
information.
Project
calendars.
Scheduling
methodology.
Lessons
learned.
Estimate Activity Duration -> Input -> OPA
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration ->Tools & Techniques
Expert Judgments
Analogous
Estimates
Parametric
Estimates
Three point
estimates
Bottom up
estimates
Data analysis Decision making Meetings
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Expert
Judgement
All estimations should be done by Experts. Expert can be internal or external.
Complex project need many experts.
General schedule
development
Management and
control
Expertise in
estimating
Estimate Activity Duration -> T&T -> Expert Judgement
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Analogues
estimation
Estimate duration of activity using historical data from a similar activity or a project.
Uses historical information, expert judgment.
Think “analogy” – something similar
Relatively quick and low cost
It is gross value estimation approach.
Parameters used:
Duration Budget Size Weight Complexity
Estimate Activity Duration -> T&T -> Analogues estimation
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Parametric
estimation
Algorithm is used to calculate duration based on historical data & project parameters.
Uses statistical relationship between historical data & other parameters.
• Accuracy of historical data.
• Sophistication & scalability of model.
• Quantifiable parameters
Accuracy is
based on:
Estimate Activity Duration -> T&T -> Parametric estimation
Railroad Project Highway Project
E.g., Construction
estimation
software
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Bottom up
estimates
Estimate the duration of each activity
Then aggregate the estimates for the different level of components as per WBS
Advantage • It is accurate
Disadvantage • It is time-consuming.
Estimate Activity Duration ->Tools & Techniques-> Bottom up estimate
Sum up the durations
of each activity for
each work package,
Sum up the subtotals
for each work
package,
Rolling up the levels of
the WBS until you get
estimate for entire
project.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Three point
estimation
Estimate duration by applying an average of optimistic, pessimistic & most likely
estimates.
This is also called as PERT techniques (Program Evaluation and Review Technique).
• = (O + M + P) / 3Triangular Distribution
• = (O + 4M + P) / 6
Beta Distribution
(Weighted average)
Estimate Activity Duration->T&T->Three point estimation
What's efforts required for activity1:
Most likely = 12 hours (Regular prog.)
Optimistic = 10 hours (coding guru)
Pessimistic = 16 hours (New prog.)
Estimation Discussion meeting
• = 10+12+16 / 3
• = 12.66 hours
Triangular
• = [10 + (4X12) +
16] / 6
• = 12.33 hours
Beta
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data analysis
Following Data analysis techniques will be used:
Reserve Analysis:
• To determine the amount of
contingency and management
reserve needed for the project
Alternative analysis:
• Used to compare various levels of
resource capability or skills;
• different tools(manual vs.
automated); and make, rent, or buy
decisions regarding the resources
Estimate Activity Duration -> T&T -> Data analysis
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Data analysis
Reserve
Analysis
Contingency reserves are used in schedule to account schedule uncertainty.
PM has to use reserve to protect baseline & constantly reduce or eliminate it.
Quantitative analysis like Monte Carlo can be used to identify reserves.
Estimate Activity Duration -> T&T -> Data analysis
Reserve can be @
Activity level
Work package
level
Can be fixed
amount
Can be % of the
estimates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Decision
making
Voting
Estimate Activity Duration ->T&T -> Decision making
How it works?
Closed fist
indicates no
support
Five fingers open
indicates full
support
if less than 3 fingers are
opened, then the objection
is discussed until everyone
has 3 or more fingers open
Fist of five (or fist to five) voting in agile:
• technique used by agile software development teams to
poll team members & achieve consensus.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Meetings
In agile, sprint or iteration meetings is used to discuss the prioritized product backlog
Done on day 1, & attended by product owner, Scrum team & PM/Scum Master
Stories are broken into tasks, which are estimated & checked against team capacity
Estimate Activity Duration ->T&T -> Meetings
Results in Sprint backlog Assumptions Constraints Risks Dependencies
Decision &
actions
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration -> Output
Duration
Estimates
Basis of
estimates
Project
documents
updates
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Duration
Estimates
Estimate Activity Duration->Output->Duration estimates
• It is important to properly communicate
estimates.
• Estimates should be given in range.
• State the confidence level in estimates.
Communicating
estimate:
Sr. No Activity Duration
1 Requirement Gathering 30 days
2 Development 90 days
3 System Testing 15 days
4 User acceptance Testing 20 days
5 Performance Testing 5 days
6 Handover 5 days
7 Project closure 5 days
These are estimated duration, which are likely number of time periods required to
complete the activities.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Basis of
estimates
known constraints, project risk which influence estimates
Documentation of how the duration estimates were developed
Indication of range of estimates (ex: +/-10%),
Confidence level of the final estimate
Estimate Activity Duration -> Output
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Project
Documents
Following Project Documents may get updated.
Estimate Activity Duration -> Output -> Project document updates
Activity
attributes
Assumption log
Lessons
Learned Reg.
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)
Estimate Activity Duration->Review
Overview
Estimate Activity Duration Definition
Important terms
Estimate Activity Duration : ITTO
Estimation techniques - Analogues, Parametric, 3P
Duration estimate & basis of estimation
PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)

More Related Content

What's hot

Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scopeAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewAnand Bobade
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2Anand Bobade
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsAhmed Alageed
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Scheduleshofiulalom
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 

What's hot (20)

Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes GroupsProject / Program / Portfolio Management and Processes Groups
Project / Program / Portfolio Management and Processes Groups
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 

Similar to Chap 6.4 Estimate Activity Duration

PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2Anand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define ActivityAnand Bobade
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scopeAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirementsAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control ScopeAnand Bobade
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewAnand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementAnand Bobade
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 

Similar to Chap 6.4 Estimate Activity Duration (20)

PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 5.3 define scope
Chap 5.3 define scopeChap 5.3 define scope
Chap 5.3 define scope
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 4.1- Develop Project Charter
Chap 4.1- Develop Project CharterChap 4.1- Develop Project Charter
Chap 4.1- Develop Project Charter
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management Overview
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 5.1 Plan Scope Management
Chap 5.1 Plan Scope ManagementChap 5.1 Plan Scope Management
Chap 5.1 Plan Scope Management
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 

More from Anand Bobade (11)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 

Recently uploaded

CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 

Recently uploaded (20)

Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 

Chap 6.4 Estimate Activity Duration

  • 1. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Estimate Activity Duration PMPChapter 6 – Project Schedule Management SIXTH EDITION
  • 2. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Duration Overview Estimate Activity Duration Definition Important terms Estimate Activity Duration : ITTO Estimation techniques – Analogues, Parametric, 3P Duration estimate & basis of estimation Review
  • 3. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Schedule Management processes Plan Schedule management Define Activities Sequence Activities Estimate Activity Duration Develop Schedule Control Schedule P P P MCP P
  • 4. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration-> Introduction SME Technical Lead Solution Architect Quality expert Estimation is joint activity, respective experts has to estimate their work. PM is responsible to aggregation.
  • 5. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Resources Advances in technology Staff Motivation Law of diminishing returns Estimate Activity Duration-> Key factors than influences estimation: Key factors than influences estimation:
  • 6. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration-> Key factors than influences estimation: The number of resources •Increasing the number of resources to twice does not always reduce the time by half. •It may increase extra duration due to risk. Advances in technology •Plays an important role in estimating duration. •Ex: Road construction work can be expedited by procuring fully automated machines. •This may impact duration, cost and resource needs Staff Motivation •Aware of the Student Syndrome or procrastination. •When resources start working at last possible moment before the deadline, Parkinson’s Law come in effect. •Parkinson’s Law - Work expands to fill time available for its completion
  • 7. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Law of diminishing returns Refer to a point at which, benefits gained is less than the amount of efforts and/or money invested. When one factor, e.g., resource is increased, & all other factors remain fixed, you may get increased output. However, A point will eventually be reached at which additions of that factor start to yield diminishing output. Estimate Activity Duration-> Key factors than influences estimation: 1 2 3
  • 8. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Example: Painting a house Estimate Activity Duration-> Important Terms • 20 daysEfforts • 10 days • With 2 resources Duration • 15 days • Includes (2 weekends & 1 day holiday by resources) Elapsed Time Day1 Day2 Day3 Day4 Day5 Day6 Day7 Day8 Day9 Day10 Day11 Day12 Day13 Day14 Day15 Work Started 1-Jan (Sunday) Work completed 15-Jan (Sunday) Weekend Weekend Resource on Holiday
  • 9. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimating number of work periods needed to complete each activity with estimated resources. It is a major input to Develop Schedule process. Activity Estimate Activity Duration -> Definition Estimating Work Periods per activity With estimated resources
  • 10. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration -> ITTO Expert Judgments Analogous Estimates Parametric Estimates Three point estimates Bottom up estimates Data analysis Decision making Meetings Project Management plan Project Documents Enterprise environmental factors Organizational process assets Duration Estimates Basis of estimates Project documents updates Inputs Tools & Techniques Outputs
  • 11. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration -> Input Project Management plan Project Documents Enterprise environmental factors Organizational process assets
  • 12. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Management plan Following PMP subsidiary plans & baselines can be used as input: Estimate Activity Duration -> Input -> PMP Schedule Management plan Scope baseline Scope baseline -> Project Scope statement: • Project scope statement provides description of the • Project scope, Major deliverables, Assumptions & Constraints • Expect senior expert to work on the technical design due to requirements complexity. • Impact on estimation: Longer estimate; multiple resource may not be able to reduce estimate proportionally. Assumption • Requirement has to be implemented before 1-Aug, due to government legislation. • Impact on estimation: Multiple resource may be added to shorten the duration of activity. Constraint
  • 13. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Documents Following Project Documents can be used as input: Activity list Activity attributes Assumption log Resource breakdown st. Resource Requirements Risk Register Resource Calendar Milestone list Lessons Register Reg. Project team assignments Estimate Activity Duration -> Input -> Project documents
  • 14. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Activity list: • A list of all activities under each work package. Activity ID WBS Id Name Description 501 W50 Compare Furniture brands 502 W50 Find showrooms 503 W50 Get Quotes 504 W50 Compare Quotes Estimate Activity Duration -> Input -> Project documents ->Activity List
  • 15. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Activity attributes: • Additional details of activities, which are useful for estimation. Predecessor activities Successor activities Logical relationships Leads and lags Resource requirements Imposed dates Constraints Assumptions Person responsible Geographic area or place Calendar Estimate Activity Duration->Input->Activity Attributes
  • 16. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Resource Requirements: • The types and quantities of resources required for each activity in a work package. • Aggregated to determine resource estimation for each work package. Estimate Activity Dur.->Inputs-> Resource Requirement Activity ID WBS Id Name Resource Type Quantity 601 W51 Unit Testing Developer 5 602 W51 System Testing Test Analyst 10 603 W51 Performance Testing Sr. Performance Test Analyst 2 604 W51 Security testing Security expert 2 Resource Type Resource Quantity Total Resources for Work Package
  • 17. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Resource Calendars: • Identifies working days & shifts when each resource is available. • Details about how long resource will be available. • Other details – Skill, Skill levels, location etc Estimate Activity Duration->Input->Resource Calendar •Resource may be material, human resources, equipment etcRemember:
  • 18. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Risk Register: • Concerns with results of Risk analysis & response planning. • List of Risks related to estimations & resources. Estimate Activity Duration->Input->Risk Register
  • 19. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Resource Breakdown Structure: • Hierarchical representation of resources by category or type. • Used for searching Resources. Construction Project Labor Managers Manager1 Manager2 Workers Worker1 Worker2 Worker3 Material Building Office setup Equipment Desktop Laptop Printer Projector Supplies Printer Cartridges Papers Stationary Estimate Activity Duration->Inputs-> RBS
  • 20. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Enterprise environmental factors Duration estimating databases & other reference data. Productivity metrics. Published commercial information. Location of team members. Estimate Activity Duration -> Input -> EEF
  • 21. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Organizational process assets Historical duration information. Project calendars. Scheduling methodology. Lessons learned. Estimate Activity Duration -> Input -> OPA
  • 22. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration ->Tools & Techniques Expert Judgments Analogous Estimates Parametric Estimates Three point estimates Bottom up estimates Data analysis Decision making Meetings
  • 23. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Expert Judgement All estimations should be done by Experts. Expert can be internal or external. Complex project need many experts. General schedule development Management and control Expertise in estimating Estimate Activity Duration -> T&T -> Expert Judgement
  • 24. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Analogues estimation Estimate duration of activity using historical data from a similar activity or a project. Uses historical information, expert judgment. Think “analogy” – something similar Relatively quick and low cost It is gross value estimation approach. Parameters used: Duration Budget Size Weight Complexity Estimate Activity Duration -> T&T -> Analogues estimation
  • 25. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Parametric estimation Algorithm is used to calculate duration based on historical data & project parameters. Uses statistical relationship between historical data & other parameters. • Accuracy of historical data. • Sophistication & scalability of model. • Quantifiable parameters Accuracy is based on: Estimate Activity Duration -> T&T -> Parametric estimation Railroad Project Highway Project E.g., Construction estimation software
  • 26. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Bottom up estimates Estimate the duration of each activity Then aggregate the estimates for the different level of components as per WBS Advantage • It is accurate Disadvantage • It is time-consuming. Estimate Activity Duration ->Tools & Techniques-> Bottom up estimate Sum up the durations of each activity for each work package, Sum up the subtotals for each work package, Rolling up the levels of the WBS until you get estimate for entire project.
  • 27. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Three point estimation Estimate duration by applying an average of optimistic, pessimistic & most likely estimates. This is also called as PERT techniques (Program Evaluation and Review Technique). • = (O + M + P) / 3Triangular Distribution • = (O + 4M + P) / 6 Beta Distribution (Weighted average) Estimate Activity Duration->T&T->Three point estimation What's efforts required for activity1: Most likely = 12 hours (Regular prog.) Optimistic = 10 hours (coding guru) Pessimistic = 16 hours (New prog.) Estimation Discussion meeting • = 10+12+16 / 3 • = 12.66 hours Triangular • = [10 + (4X12) + 16] / 6 • = 12.33 hours Beta
  • 28. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data analysis Following Data analysis techniques will be used: Reserve Analysis: • To determine the amount of contingency and management reserve needed for the project Alternative analysis: • Used to compare various levels of resource capability or skills; • different tools(manual vs. automated); and make, rent, or buy decisions regarding the resources Estimate Activity Duration -> T&T -> Data analysis
  • 29. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Data analysis Reserve Analysis Contingency reserves are used in schedule to account schedule uncertainty. PM has to use reserve to protect baseline & constantly reduce or eliminate it. Quantitative analysis like Monte Carlo can be used to identify reserves. Estimate Activity Duration -> T&T -> Data analysis Reserve can be @ Activity level Work package level Can be fixed amount Can be % of the estimates
  • 30. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Decision making Voting Estimate Activity Duration ->T&T -> Decision making How it works? Closed fist indicates no support Five fingers open indicates full support if less than 3 fingers are opened, then the objection is discussed until everyone has 3 or more fingers open Fist of five (or fist to five) voting in agile: • technique used by agile software development teams to poll team members & achieve consensus.
  • 31. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Meetings In agile, sprint or iteration meetings is used to discuss the prioritized product backlog Done on day 1, & attended by product owner, Scrum team & PM/Scum Master Stories are broken into tasks, which are estimated & checked against team capacity Estimate Activity Duration ->T&T -> Meetings Results in Sprint backlog Assumptions Constraints Risks Dependencies Decision & actions
  • 32. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration -> Output Duration Estimates Basis of estimates Project documents updates
  • 33. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Duration Estimates Estimate Activity Duration->Output->Duration estimates • It is important to properly communicate estimates. • Estimates should be given in range. • State the confidence level in estimates. Communicating estimate: Sr. No Activity Duration 1 Requirement Gathering 30 days 2 Development 90 days 3 System Testing 15 days 4 User acceptance Testing 20 days 5 Performance Testing 5 days 6 Handover 5 days 7 Project closure 5 days These are estimated duration, which are likely number of time periods required to complete the activities.
  • 34. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Basis of estimates known constraints, project risk which influence estimates Documentation of how the duration estimates were developed Indication of range of estimates (ex: +/-10%), Confidence level of the final estimate Estimate Activity Duration -> Output
  • 35. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Project Documents Following Project Documents may get updated. Estimate Activity Duration -> Output -> Project document updates Activity attributes Assumption log Lessons Learned Reg.
  • 36. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com) Estimate Activity Duration->Review Overview Estimate Activity Duration Definition Important terms Estimate Activity Duration : ITTO Estimation techniques - Analogues, Parametric, 3P Duration estimate & basis of estimation
  • 37. PMBOK 6 - All rights reserved; By: Anand Bobade (nmbobade@gmail.com)