SlideShare a Scribd company logo
1 of 55
By: Anand Bobade (nmbobade@gmail.com)
Chapter 7 –
Project Cost Management
PMP
Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved.
Control Cost
SIXTH EDITION
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost Definition
Control Cost : ITTO
What is EVM?
What is cost & schedule performance index?
What is forecasting?
What is TCPI?
Data flow diagram
Review
7.4 Control Cost
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Cost Management processes
Plan Cost
management
Estimate Cost
Determine Budget Control Cost
PP
MCP
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
7.4 Control Cost ->Introduction
0
200
400
600
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Thousands
Planned Actuals
Frequency of
measurement
Activity cost
WBS
components
(Control
accounts)
Total project
cost
Don’t include unapproved change cost
Influence factor affecting cost baselines
Manage changes & cost overrunMeasure
Monitor
Control
Report
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost ->Introduction
•The factors that create changes to baselineInfluencing
•All change requests are acted on in a timely mannerEnsuring
•The actual changes when and as they occurManaging
•That cost expenditures do not exceed the authorized funding
by period, WBS ,activity, in total
Ensuring
•Cost performance to isolate and understand variancesMonitoring
•Work performance against funds expendedMonitoring
•Unapproved changes reported or resource usage;Preventing
•Appropriate stakeholders of all approved changes and
associated cost;
Informing
•Expected cost overruns within acceptable limitsBringing
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Monitoring the status of the project to update the project costs & managing
changes to the cost baseline.
Provides the means to recognize variance from the plan
in order to take corrective action and minimize risk.
7.4 Control Cost ->Definition
Monitoring Project
status
Update project
Cost
Manage cost
baseline changes
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
7.4 Control Cost -> ITTO
Expert Judgment
Data Analysis
To-Complete Performance
Index (TCPI)
PMIS
Project Management
Plan
Project Documents
Project Funding
Requirements
WPD
OPA
Work Performance
Information
Cost Forecasts
Change Requests
PMP updates
Project doc. updates
Inputs Tools & Techniques Outputs
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Project Management
Plan
Project Documents
Project Funding
Requirements
Work Performance
data
OPA
Control Cost -> Input
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Project
Management Plan
Cost Management Plan
• Define how project costs will be planned, structured, and
controlled.
• Define how each Cost Management Process is executed.
• Specify preferred method or techniques to be used.
Cost baseline
• It is an approved time phased budget.
Performance measurement baseline:
• Used in earned value analysis
• It takes the three constraints scope, schedule and cost
and combines them to create a baseline.
• It is compared with Actual results (CPI & CV)
Control Cost ->Input->Project Management Plan
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Project Documents
Lessons learned register
• May updated to see if there are any procedures done by the
project team that improve cost control.
Control Cost ->Input->Project Documents
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
WPD
The data include the actual costs that have authorized, incurred, invoiced and
paid for activities/milestone completed on the project.
Control Cost >Input->Work performance data
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
OPA
Existing cost policies, procedures, and guidelines (e.g., invoicing
process)
Financial controls procedures.
Historical information and lessons learned (e.g., past cost escalation
issues)
Financial databases (Old project finance details)
Control Cost ->Input->OPA
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> Tools & Techniques
Expert Judgment Data Analysis
To-Complete
Performance Index
PMIS
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Data Analysis
Control Cost -> T&T -> Data analysis
Earned value
management
Forecasting Variance Analysis:
Trend Analysis Reserve analysis
Following data analysis techniques can be used:
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Earned value
management
Control Cost -> T&T -> Data analysis -> EVM
It combines SCOPE, SCHEDULE, & RESOURCE measurements to assess project
performance and progress.
It integrates the scope ,cost & schedule baselines, to form the performance baseline
• It is authorized budget planned for work to be
accomplished.
Planned
Value (PV)
• Realized cost incurred for the work performed on an
activity during a specific time period.
Actual cost
(AC)
• A measure of work performed expressed in terms of
the budget authorized.
Earned
value (EV)
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> EVM
Earned value Calculation based on the Percentage completion
Schedule Planned Value (PV)
Percentage
Complete
Actual Cost (AC)
Earn Value
(EV)
Day1 10,000 100% 10,000
Day2 10,000 80% 10,000
10,000
8,000
18,000
•100% of work completed
•EV = 100% of 10,000
•EV = 10,000
Day1
•Only 80% of work completed
•EV = 80% of 10,000
•EV = 8,000
Day2
•EV = EV of Day1 + EV of Day2
•EV = 10,000 + 8,000
•EV = 18,000
Combined
EV
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> EVM
EV Calculation based on planned vs actual work done.
Schedule
Planned
Work
Planned
Value (PV)
Actual
work
Actual Cost
(AC)
Earn Value
(EV)
Day1 10 computer 10,000 9 computers 10,000
Day2 10 computer 10,000 10 computers 10,000
Plan : Install 10 computers each day costing 10,00 per day.
10,000
9,000
•Only 9 computer installed on Day1
•Hence, EV of spending 10,000 is only 9,000
Day1
•10 computer installed on Day 2
•Hence, EV of spending 10,000 is 10,000
Day2
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> EVM
Task/Days Day1 Day2 Day3 Day4 Day5 Day6 Day7
Setup Setup
Installation 10 comp 10 comp 10 comp 10 comp 10 comp
Training & Handover Handover
Project : Install 50 computers for school Lab.
• Assumption:
• Resource cost is 1000/day. One resource first & last day.
• Two resources during execution (Day 2 to Day6)
Planned cost(Cumulative) 1,000 3,000 5,000 7,000 9,000 11,000 12,000
Planned cost 1,000 2,000 2,000 2,000 2,000 2,000 1,000
We could not get resource with 1,000/per day, hence hired resource with 1100 per day
Actual cost (Cumulative) 1,100 3,300 5,500 7,700
Actual cost 1,100 2,200 2,200 2,200
Earn Value 1,000 1,600 1,600 1,600
Earn Value (Cumulative) 1,000 2,600 4,200 5,800
Only 8 computer
installed on each day,
so 80% earn value
8 / 10 8 / 10 8 / 10
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> EVM
PV: 7,000
BAC: 12,000
AC: 7,700
EV: 5,800
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Day1 Day2 Day3 Day4 Day5 Day6 Day7
Cost Variance
Schedule Variance
Hints about Formula:
Always start with “EV”
Variance uses “-”
Index uses “/”
Only AC is used for Cost
•SPI = EV/PVSchedule performance index
•CPI = EV/ACCost performance index
•SV = EV –PVSchedule variance
•CV= EV − ACCost variance
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> EVM
•= 5,800 –7,000 = -1,200Schedule variance ( SV = EV – PV)
•= 5,800− 7,700 = -1,900Cost variance (CV = EV − AC)
•= 5,800 / 7,000 = 0.82Schedule performance Index (SPI = EV / PV)
•= 5,800 / 7,700 = 0.75Cost performance Index (CPI = EV / AC)
Indexes
CPI
SPI
> 1
Under
budget
Ahead of
schedule
< 1
Over
Budget
Behind
schedule
= 1
On Budget
(planned
cost)
On
Schedule
Project is over budget &
behind Schedule
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> EVM
•Slowdown with
spending to try
to reach
optimal level
•Try to move to
optimal
otherwise re-
baseline.
•Continue as it is•Spend more to
catch up
Under Budget
but behind
schedule
Optimal –
Under Budget
& ahead of
Schedule
Over Budget
but ahead of
schedule
Worst case:
Over Budget &
behind
schedule
CPI >1
[Ahead of
Schedule]
CPI < 1
CPI >1
[Behind
Schedule]
CPI < 1
SPI < 1 [Under Budget] SPI >1
SPI < 1 [Over Budget] SPI >1
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> EVM
• SV is a measure of schedule performance on a
project.
Schedule
variance (SV)
• It measure of cost performance on a project.
• It indicates relationship of performance to costs
spent.
Cost variance
(CV)
• SPI is a measure of progress achieved compared to
progress planned.
Schedule
performance
index (SPI)
• CPI is a measure of value of work completed
compared to actual cost.
Cost
performance
index (CPI)
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
A) The project is ahead of schedule and on budget
B) The project is on schedule and below budget
C) The EAC is incorrect
D) The project is behind schedule and on budget
Answer : The project is behind schedule because as PV is 110,000 & EV is only
90,000. We are 20,000 behind schedule.
We are on budget because both our Actual Cost and Earned Value are 90,000. Hence
answer is D) The project is behind schedule and on budget
Your earned value analysis shows the following values. Which of the following
is true?
- PV = 110,000,
- AC = 90,000
- EV = 90,000,
- BAC = 200,000
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
Task Duration Planned
Value
Actual Jan Feb Mar Apr May Jun
Analysis 20 1,000 1,400
Design 40 2,000 1,000
Development 60 10,000 4,000
Testing 10 2,000 -
Go-live 10 1,000 -
closure 0 - -
Below graph shows the Project schedule & current performance of the IT project managed by Anand. What is the current SPI of
the project.
A: -1
B: 0.58
C: 1.21
D: 1
100%
75%
50%
A: SPI>1 & CPI>1
B: SPI<1 & CPI<1
C: SPI>1 & CPI<1
D: SPI<1 & CPI>1
Other possible options:
A: Project is performing good
B: Project is performing bad
C: Slowdown with spending to try to reach optimal level
D: Spend more to catch up
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
Calculate PV of completed or in progress activities
•= Activity1(PV)+ Activity2(PV)+ Activity3(PV)
•= 1,000+2,000+10,000
•= 13,000
Calculate EV of completed or in progress activities
•= Activity1(PV * % complete)+ Activity2(PV * % complete)+ Activity3(PV * %
complete)
•= (1,000* 100%) + (2,000 * 75%) + (10,000 * 50%)
•= 1,000+1,500+5,000
•= 7,500
SPI = EV / PV
•= 7,500 /13,000
•= 0.5769
•(SPI <1 means project is behind schedule)
Answer- B: 0.58
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
Exercise: Calculate CPI?
Calculate AC of completed or in progress activities
•= Activity1(AC)+ Activity2(AC)+ Activity3(AC)
•= 1,400+1,000+4,000
•= 6,400
Calculate EV of completed or in progress activities
•= Activity1(PV * % complete)+ Activity2(PV * % complete)+ Activity3(PV * % complete)
•= (1,000* 100%) + (2,000 * 75%) + (10,000 * 50%)
•= 1,000+1,500+5,000
•= 7,500
CPI = EV / AC
•= 7,500 /6,400
•= 1.17
CPI >1 means project under budget.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
Control Cost -> T&T -> Data analysis -> Forecasting
Prediction of conditions & events in project's future based on information & knowledge
available during forecast.
ETC - Estimate to complete:
• Expected cost to finish all remaining project work.
EAC - Estimate at completion:
• Expected total cost of completing all work expressed as
“sum of actual cost to date” & “estimate to complete”.
• Forecasted estimate for total cost of the Project.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
Control Cost -> T&T -> Data analysis -> Forecasting
ETC - Estimate
to complete
EAC - Estimate
at completion
Remaining
Cost
Total Cost
at end
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
Control Cost -> T&T -> Data analysis -> Forecasting
EAC - Estimate at
completion
ETC - Estimate to
complete
The information is derived from:
Project's past performance
Information that could impact project in future
Expected future performance
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting Consider forecasted EAC, If BAC is no longer viable.
EAC involves projections of project’s future based on current
performance.
Key input is work performance data.
EAC - Estimate at completion
• Expected total cost of completing all work expressed as “sum of
actual cost to date” & “estimate to complete”.
Control Cost -> T&T -> Data analysis -> Forecasting
Total Cost
at end
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
EAC - Estimate at completion
• Expected total cost of completing all work expressed as “sum of
actual cost to date” & “estimate to complete”.
Control Cost -> T&T -> Data analysis -> Forecasting
Total Cost
at end
EAC based on Budgeted Rate:
•Absorb the Variance (originally planed budgeted rate)
EAC based on Current Progress:
•Take the ongoing project trend (CPI & SPI or only CPI)
EAC - Erroneous scenario:
•Re-estimate the remaining portion
•Original estimates were fundamentally flowed.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
EAC - Estimate at completion
• Expected total cost of completing all work expressed as “sum of
actual cost to date” & “estimate to complete”.
Control Cost -> T&T -> Data analysis -> Forecasting
Total Cost
at end
• EAC = AC + (BAC –EV)
Based on Budgeted
rate
• EAC = BAC / CPIBased on CPI.
• EAC = AC + [(BAC –EV) / (CPI ×SPI)]Based on SPI & CPI
• EAC = AC + re-estimateErroneous scenario:
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> Forecasting
There are many ways to calculate EAC based on project progress.
Questions about the EAC will always contain some information about the current “health” (or
progression) of the project. There are certain keywords that you can look for to pick correct formula.
• EAC = AC + (BAC –EV)
• Current variances are
thought to be
atypical in the future.
• Note: atypical means
unusual or abnormal.
EAC based on Budgeted
Rate:
• EAC = BAC / CPI
• No variances from
the BAC have
occurred or
• Progress expected to
continue at the same
rate of spending.
•This is most often
required on the exam.
EAC based on Current
Cost Progress
• EAC=AC+ BAC –EV
• Current variances
are thought to be
typical in the future.
EAC based on Current
cost & schedule
Progress
• EAC = AC+ETC
• Original estimate was
fundamentally
flawed or conditions
have changed and
invalidated original
estimating
assumptions.
EAC - Erroneous
scenario:
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> Forecasting -> Example
Task Duration Planned
Value
Actual Jan Feb Mar Apr May Jun
Initial infrastructure 1 month 1 million 1 ml
Pillar 1 & slab 2 months 2 million 2 ml
Pillar 2 & slab 2 months 2 million .25 ml
Pillar 3 & slab 2 months 2 million -
Pillar 4 & slab 2 months 2 million -
Pillar 5 & slab 2 months 2 million -
Finalize & handover 1 month 1 million
Bridge construction project.
100%
100%
25%
Bridge construction Project: Duration : 12 months, Cost of the Project: 10,000,000
Current status at end of month 3.5: The pillar was collapsed & hence progress was slowed.
Actual cost: 3,250,000
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
EAC based on Budgeted Rate:
•EAC = AC + (BAC –EV)
Bridge construction Project:
•Duration : 12 months
•Cost of the Project: 10,000,000
•Current status at end of month 3:
•The pillar was collapsed & hence progress was
slowed.
•Work completed: only 20% of complete project
•Actual cost: 3,000,000
BAC = 10,000,000
AC = 3,000,000
EV = 20% of 10,,000,000 = 2,000,000
(0nly 20% work done)
EAC = AC + (BAC – EV)
EAC = 3,000,000 + (10,000,000 – 2,000,000) = 11,000,000
EAC = 11 Million
Considering this as rare incident. Project will continues
progressing as originally planned, then it will need 11
Million to complete.
Control Cost -> T&T -> Data analysis -> Forecasting -> Example
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> Forecasting -> Example
EAC based on Current Progress (Based on CPI):
EAC = BAC / CPI
Bridge construction Project:
• Duration : 12 months
• Cost of the Project: 10,000,000
• Current status at end of month 6:
• Work completed: only 40% of complete
project
• Actual cost: 6,000,000
BAC = 10,000,000
AC = 6,000,000
EV = 40% of 10,000,000 = 4,000,000
(0nly 40% work done)
CPI = EV / AC = 4,000,000 / 6,000,000 = 0.66
EAC = BAC/CPI = 10,000,000/0.66 = 15,151,515
EAC = 15,151,515
If project continues to progress CPI 0.66 until end,
you have to spend 15.15 Million to complete the
project.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> Forecasting -> Example
EAC based on Current Progress (Based on CPI & SPI):
EAC = AC + [(BAC –EV) / (CPI ×SPI)]
Bridge construction Project:
Duration : 12 months
Cost of the Project: 10,000,000
Current status at end of month 6:
Work completed: only 40% of complete project
Actual cost: 6,000,000
BAC = 10,000,000 & AC = 6,000,000
PV = 50% of 10,000,000 = 5,000,000
(six months completed)
EV = 40% of 10,000,000 = 4,000,000
(0nly 40% work done)
CPI = EV / AC = 4,000,000 / 6,000,000 = 0.66
SPI = EV / PV = 4,000,000 / 5,000,000 = 0.8
EAC = 6,000,000 + [ (10,000,000–4,000,000)/
(0.66 * 0.8) ]
EAC = 6,000,000 + [6,000,000 / 0.528 ] = 17,363,636
If project continues with similar CPI & SPI, you have
to spend 17.36 Million to complete project.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> Data analysis -> Forecasting -> Example
Bridge construction Project:
Duration : 12 months, Cost of the Project: 10,000,000
Current status at end of month 6: Work completed: only 55% of complete project.
Actual cost: 5,000,000
EAC based on Budgeted Rate:
•EAC = AC + (BAC –EV)
•BAC = 10,000,000
•AC = 5,000,000
•EV = 55%10,000,000 = 5,500,000
•EAC = 5,000,000 + ( 10,000,000 –
5,500,000)
•EAC = 5,000,000 + 4,500,000
•EAC = 9,500,000
EAC based on Current Progress
(Based on CPI):
•EAC = BAC / CPI
•BAC = 10,000,000
•AC = 5,000,000
•EV= 55%10,000,000
•EV =5,500,000
•CPI = EV / AC
•CPI = 5,500,000 / 5,000,00= 1.1
•EAC = 10,000,000 / 1.1
•EAC = 9,090,909
EAC based on Current Progress
(Based on CPI & SPI):
•EAC = AC + [(BAC –EV) / (CPI
×SPI)]
•PV = 50% of 10,000,000 =
5,000,000 (six months
completed)
•EV & CPI calculation is same.
•SPI = EV / PV
•SPI = 5,500,000 / 5,000,000 = 1.1
•EAC = 5,000,000 + [(10,000,000 –
5,500,000) / (1.1 * 1.1)]
•EAC = 5,000,000 +( 4,500,000 /
1.21)
•EAC = 5,000,000 + 3,719,008.26
•EAC = 8,719,008.26
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
You presenting project status to Steering committee at the end of first Quarter in
one year project. The project is progressing as planned and you expect no major
problems in the foreseeable future.
Your PMIS is showing following data:
BAC = 500,000, SPI = 1.1, CPI = 1.05, EV = 173,000, AC = 164,761.
What you should report about EAC in the meeting?
A) 491,761
B) 454,545
C) 189,761
D) 476,190
Answer: Highlighted information indicates there were no variances after atypical
situation & expect to continue at same rate.
Hence, we will use second formula EAC= BAC/CPI =500,00/1.05 = 476,190; Hence,
answer is D) 476,190
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
Task Duration Planned
Value
Actual Jan Feb Mar Apr May Jun
Analysis 20 1,000 1,400
Design 40 2,000 2,000
Development 60 10,000 -
Testing 10 2,000 -
Go-live 10 1,000 -
closure 0 - -
Below schedule depicts the CRM Project schedule managed by Project managed Anand. As of today first two activities should
have been 100% completed and third 50%. However PM reported 100% completion of first two, and remaining activities are not
yet started. Assuming projects future performance will be at budgeted rate, what will be the projects EAC (Estimate at
completion)?
100%
100%
A: 3,400
B: 16,000
C: 16,400
D: 3,000
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
Even though project is not performing as expected, we expect project to performed at the planned rate
(budgeted rate). The formula used in this scenario is EAC = AC + (BAC – EV)
Calculate Actual Cost (AC) of completed or in progress activities.
• = Activity1(AC)+ Activity2(AC) = 1,400+2,000 = 3,400
Calculate BAC (Total of all the activities)
• BAC = 1,000 + 2,000 + 10,000 + 2,000 + 1,000 = 16,000
Calculate EV of completed or in progress activities
• = Activity1(PV * % complete)+ Activity2(PV * % complete)
• = (1,000* 100%) + (2,000 * 100%) = 1,000+2,000 = 3,000
EAC=AC+(BAC-EV)
• =3,400 + (16,000 – 3,000) = 3,400 + 13,000 = 16,400
Answer – C: 16,400
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
Control Cost -> T&T -> Data analysis -> Forecasting
Total Cost
at end
EAC - Estimate at completion (Re-estimate)
• EAC = AC + ETC (or Re-estimate)
Software Project:
• Project is to implement CRM Software for
government department for 5,000,000.
• To date project has spent 1,100,000.
• However, during execution, it was noticed
that present cost estimation were
fundamentally flawed & need to re-
calculate budget for remaining part of the
project.
You discuss with your team & re-estimate
the cost of the remaining work.
Your new estimates: Design = 1,000,000,
Development=3,000,000,
testing=1,500,500
Re-estimated cost = Design +
Development + testing
Re-estimated cost = 1,000,000 +
3,000,000 + 1,500,500 = 5,500,500
EAC = AC + Re-estimate
EAC = 1,100,000 + 5,500,500 = 6,500,500
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
Control Cost -> T&T -> Data analysis -> Forecasting
ETC - Estimate to complete
•ETC = EAC- AC or (Re-estimate remaining work)
Cost to
complete House construction Project:
• You have a construction project to be
completed in 12 months with cost of
1,000,000.
• Six months passed & project have spent
600,000.
• In meeting PM reported that only 40% of
work is completed & project is expected to
perform with same cost performance.
• Management is interested to know what is
Estimate to complete?
BAC = 1,000,000, AC = 600,000
PV= 50% of 1,000,000 = 500,000
(six months completed)
EV= 40% of 1,000,000 = 400,000
(0nly 40% work done)
CPI= EV / AC = 400,000 / 600,000 =
0.66
EAC = BAC/CPI = 1,000,000/0.66 =
1,515,151
ETC = EAC- AC
ETC = 1,515,151 – 600,000
ETC = 915, 151
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> EVM -> Exercise
Your Team Lead, who was leading the estimation team, tells you that he had missed several
key project components in estimation. So, his original cost estimations were completely
wrong. At the end of this meeting, he assured to provide new estimate in 2 days. Based on
the new estimates, your PMIS shows below:
BAC: 5,000,000. AC= 1,100,000, CPI = 1.05, SPI = 1.05, EV = 1,000,000.
How much project will cost, if the new estimate to complete that you received from your
Team Lead is 5,500,500?
A) 5,500,500
B) 6,500,500
C) 6,600,500
D) 6,100,000
Answer: Highlighted information indicates there were fundamental flows in the estimates.
Hence, we will use fourth formula EAC= AC + ETC = 1,100,000 +5,500,500 = 6,600,500;
Hence, answer is C) 6,600,500
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Forecasting
Control Cost -> T&T -> Data analysis -> Forecasting
VAC (Variance at completion)
• Projection of budget difference between BAC & EAC.
VAC shows whether project is forecasted to finish under or
over budget.
VAC = BAC – EAC
VAC % = EAC / BAC
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
TCPI
TCPI
calculation
Same Budget Use BAC
Revised
Budget
Use Forecasted
EAC
TCPI is measure of Cost Performance that is required to be achieved in order to meet a specified
management goal.
Ratio of “work remaining”, to “funds remaining”.
Control Cost -> T&T -> To Complete Performance Index (TCPI)
If BAC is no longer viable, then forecasted EAC should be approved to use in the
TCPI calculation.
Work Remaining
----------------------
Fund Remaining
( BAC – EV )
----------------
( BAC – AC )
( BAC – EV )
----------------
( EAC – AC )
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> TCPI -> Example
300,000
BAC:600,000
315,000
270,000
-
100,000
200,000
300,000
400,000
500,000
600,000
700,000
Month1 Month2 Month3 Month4 Month5 Month6
Planned Budget (PV) Actual Cost (AC) Earned Value (EV)
Fund Remaining
= BAC-AC
= 600,000-315,000
= 285,000
Work Remaining
= BAC-EV
= 600,000-270,000
= 330,000
Case1: Same
Budget
Project with current status BAC=600,000 PV=300,000 AC=315,000 EV=270,000
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> TCPI -> Example
TCPI (based on BAC)
Work Remaining = BAC-EV = 600,000-
270,000 = 330,000
Fund Remaining = BAC-AC = 600,000-
315,000 = 285,000
TCPI = Work Remaining / Fund Remaining
= 330,000 / 285,000
= 1.15
You have to get output of 1.15 AED of every
1 AED spent.
•Project is in a comfortable position.
If TCPI
< 1
•Project have to perform with better
cost performance than past.
If TCPI
> 1
•Project can continue with same cost
performance.
if TCPI
= 1
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> TCPI -> Example
300,000
BAC:600,000
315,000
270,000
-
100,000
200,000
300,000
400,000
500,000
600,000
700,000
Month1 Month2 Month3 Month4 Month5 Month6
Planned Budget (PV) Actual Cost (AC) Earned Value (EV)
Fund Remaining
= EAC-AC
= 650,000-315,000
= 335,000
Work Remaining
= BAC-EV
= 600,000-270,000
= 330,000
Case1: Revised
Budget
Project with current status BAC=600,000 PV=300,000 AC=315,000 EV=270,000
EAC = 650,000
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> T&T -> TCPI -> Example
TCPI (based on BAC)
Work Remaining = BAC-EV = 600,000-270,000 =
330,000
Fund Remaining = BAC-AC = 600,000-315,000 =
285,000
TCPI = Work Remaining / Fund Remaining
= 330,000 / 285,000
= 1.15
You have to get output of 1.15 AED of every 1 AED
spent.
TCPI (Based on EAC)
Work Remaining = BAC-EV = 600,000-270,000 =
330,000
Fund Remaining = EAC-AC = 650,000-315,000 =
335,000
TCPI = Work Remaining / Fund Remaining
= 330,000/335,000
=0.98
You have to get output of 0.98 AED of every 1 AED
spent.
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
PMIS
Control Cost ->T&T-> Project Management Information System (PMIS)
Calculate earn value
Display graphical trends & calculate SPI & CPI
Show variances
Forecast a range of possible final project results
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> Output
Work Performance
Information
Cost Forecasts Change Requests
PMP updates Project doc. updates
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
Control Cost -> Data flow diagram
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .
How to control cost?
What is EVM?
What is cost & schedule variance?
What is cost & schedule performance index?
What is forecasting?
What is TCPI?
What do you mean by Performance review?
Control Cost -> Review
By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .

More Related Content

What's hot

What's hot (20)

Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management OverviewChap 6.0 Schedule Management Overview
Chap 6.0 Schedule Management Overview
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBS
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
Chap 8.1 Plan quality management
Chap 8.1 Plan quality managementChap 8.1 Plan quality management
Chap 8.1 Plan quality management
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 5.2 Collect requirements
Chap 5.2 Collect requirementsChap 5.2 Collect requirements
Chap 5.2 Collect requirements
 
Chap 6.2 Define Activity
Chap 6.2 Define ActivityChap 6.2 Define Activity
Chap 6.2 Define Activity
 
Chap 8.0 Quality Management Overview
Chap 8.0 Quality Management OverviewChap 8.0 Quality Management Overview
Chap 8.0 Quality Management Overview
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Chap 5.6 Control Scope
Chap 5.6 Control ScopeChap 5.6 Control Scope
Chap 5.6 Control Scope
 
PMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management OverviewPMP Chap 5.0 Scope Management Overview
PMP Chap 5.0 Scope Management Overview
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 8.2 Manage Quality
Chap 8.2 Manage QualityChap 8.2 Manage Quality
Chap 8.2 Manage Quality
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 

Similar to Chap 7.4 Control Cost

L06 cost management
L06 cost managementL06 cost management
L06 cost management
Asa Chan
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
ejlp12
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Serdar Temiz
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
eidalin95
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
Nita Cristian
 

Similar to Chap 7.4 Control Cost (20)

PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
6- PMP Training - Cost Management
6- PMP Training - Cost Management6- PMP Training - Cost Management
6- PMP Training - Cost Management
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Earned value
Earned valueEarned value
Earned value
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Evm power point january 2017
Evm power point  january 2017Evm power point  january 2017
Evm power point january 2017
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
ROI of Machine Learning In IoT
ROI of Machine Learning In IoTROI of Machine Learning In IoT
ROI of Machine Learning In IoT
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
Anand Bobade
 

More from Anand Bobade (18)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 
Chap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity DurationChap 6.4 Estimate Activity Duration
Chap 6.4 Estimate Activity Duration
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
Chap 5.5 validate scope
Chap 5.5 validate scopeChap 5.5 validate scope
Chap 5.5 validate scope
 

Recently uploaded

Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
Nimot Muili
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 

Recently uploaded (15)

Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 

Chap 7.4 Control Cost

  • 1. By: Anand Bobade (nmbobade@gmail.com) Chapter 7 – Project Cost Management PMP Trainer: Anand BobadePMBOK 6th Edition, 2019, All rights reserved. Control Cost SIXTH EDITION
  • 2. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost Definition Control Cost : ITTO What is EVM? What is cost & schedule performance index? What is forecasting? What is TCPI? Data flow diagram Review 7.4 Control Cost
  • 3. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Cost Management processes Plan Cost management Estimate Cost Determine Budget Control Cost PP MCP
  • 4. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . 7.4 Control Cost ->Introduction 0 200 400 600 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Thousands Planned Actuals Frequency of measurement Activity cost WBS components (Control accounts) Total project cost Don’t include unapproved change cost Influence factor affecting cost baselines Manage changes & cost overrunMeasure Monitor Control Report
  • 5. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost ->Introduction •The factors that create changes to baselineInfluencing •All change requests are acted on in a timely mannerEnsuring •The actual changes when and as they occurManaging •That cost expenditures do not exceed the authorized funding by period, WBS ,activity, in total Ensuring •Cost performance to isolate and understand variancesMonitoring •Work performance against funds expendedMonitoring •Unapproved changes reported or resource usage;Preventing •Appropriate stakeholders of all approved changes and associated cost; Informing •Expected cost overruns within acceptable limitsBringing
  • 6. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Monitoring the status of the project to update the project costs & managing changes to the cost baseline. Provides the means to recognize variance from the plan in order to take corrective action and minimize risk. 7.4 Control Cost ->Definition Monitoring Project status Update project Cost Manage cost baseline changes
  • 7. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . 7.4 Control Cost -> ITTO Expert Judgment Data Analysis To-Complete Performance Index (TCPI) PMIS Project Management Plan Project Documents Project Funding Requirements WPD OPA Work Performance Information Cost Forecasts Change Requests PMP updates Project doc. updates Inputs Tools & Techniques Outputs
  • 8. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Project Management Plan Project Documents Project Funding Requirements Work Performance data OPA Control Cost -> Input
  • 9. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Project Management Plan Cost Management Plan • Define how project costs will be planned, structured, and controlled. • Define how each Cost Management Process is executed. • Specify preferred method or techniques to be used. Cost baseline • It is an approved time phased budget. Performance measurement baseline: • Used in earned value analysis • It takes the three constraints scope, schedule and cost and combines them to create a baseline. • It is compared with Actual results (CPI & CV) Control Cost ->Input->Project Management Plan
  • 10. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Project Documents Lessons learned register • May updated to see if there are any procedures done by the project team that improve cost control. Control Cost ->Input->Project Documents
  • 11. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . WPD The data include the actual costs that have authorized, incurred, invoiced and paid for activities/milestone completed on the project. Control Cost >Input->Work performance data
  • 12. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . OPA Existing cost policies, procedures, and guidelines (e.g., invoicing process) Financial controls procedures. Historical information and lessons learned (e.g., past cost escalation issues) Financial databases (Old project finance details) Control Cost ->Input->OPA
  • 13. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> Tools & Techniques Expert Judgment Data Analysis To-Complete Performance Index PMIS
  • 14. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Data Analysis Control Cost -> T&T -> Data analysis Earned value management Forecasting Variance Analysis: Trend Analysis Reserve analysis Following data analysis techniques can be used:
  • 15. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Earned value management Control Cost -> T&T -> Data analysis -> EVM It combines SCOPE, SCHEDULE, & RESOURCE measurements to assess project performance and progress. It integrates the scope ,cost & schedule baselines, to form the performance baseline • It is authorized budget planned for work to be accomplished. Planned Value (PV) • Realized cost incurred for the work performed on an activity during a specific time period. Actual cost (AC) • A measure of work performed expressed in terms of the budget authorized. Earned value (EV)
  • 16. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> EVM Earned value Calculation based on the Percentage completion Schedule Planned Value (PV) Percentage Complete Actual Cost (AC) Earn Value (EV) Day1 10,000 100% 10,000 Day2 10,000 80% 10,000 10,000 8,000 18,000 •100% of work completed •EV = 100% of 10,000 •EV = 10,000 Day1 •Only 80% of work completed •EV = 80% of 10,000 •EV = 8,000 Day2 •EV = EV of Day1 + EV of Day2 •EV = 10,000 + 8,000 •EV = 18,000 Combined EV
  • 17. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> EVM EV Calculation based on planned vs actual work done. Schedule Planned Work Planned Value (PV) Actual work Actual Cost (AC) Earn Value (EV) Day1 10 computer 10,000 9 computers 10,000 Day2 10 computer 10,000 10 computers 10,000 Plan : Install 10 computers each day costing 10,00 per day. 10,000 9,000 •Only 9 computer installed on Day1 •Hence, EV of spending 10,000 is only 9,000 Day1 •10 computer installed on Day 2 •Hence, EV of spending 10,000 is 10,000 Day2
  • 18. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> EVM Task/Days Day1 Day2 Day3 Day4 Day5 Day6 Day7 Setup Setup Installation 10 comp 10 comp 10 comp 10 comp 10 comp Training & Handover Handover Project : Install 50 computers for school Lab. • Assumption: • Resource cost is 1000/day. One resource first & last day. • Two resources during execution (Day 2 to Day6) Planned cost(Cumulative) 1,000 3,000 5,000 7,000 9,000 11,000 12,000 Planned cost 1,000 2,000 2,000 2,000 2,000 2,000 1,000 We could not get resource with 1,000/per day, hence hired resource with 1100 per day Actual cost (Cumulative) 1,100 3,300 5,500 7,700 Actual cost 1,100 2,200 2,200 2,200 Earn Value 1,000 1,600 1,600 1,600 Earn Value (Cumulative) 1,000 2,600 4,200 5,800 Only 8 computer installed on each day, so 80% earn value 8 / 10 8 / 10 8 / 10
  • 19. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> EVM PV: 7,000 BAC: 12,000 AC: 7,700 EV: 5,800 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Day1 Day2 Day3 Day4 Day5 Day6 Day7 Cost Variance Schedule Variance Hints about Formula: Always start with “EV” Variance uses “-” Index uses “/” Only AC is used for Cost •SPI = EV/PVSchedule performance index •CPI = EV/ACCost performance index •SV = EV –PVSchedule variance •CV= EV − ACCost variance
  • 20. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> EVM •= 5,800 –7,000 = -1,200Schedule variance ( SV = EV – PV) •= 5,800− 7,700 = -1,900Cost variance (CV = EV − AC) •= 5,800 / 7,000 = 0.82Schedule performance Index (SPI = EV / PV) •= 5,800 / 7,700 = 0.75Cost performance Index (CPI = EV / AC) Indexes CPI SPI > 1 Under budget Ahead of schedule < 1 Over Budget Behind schedule = 1 On Budget (planned cost) On Schedule Project is over budget & behind Schedule
  • 21. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> EVM •Slowdown with spending to try to reach optimal level •Try to move to optimal otherwise re- baseline. •Continue as it is•Spend more to catch up Under Budget but behind schedule Optimal – Under Budget & ahead of Schedule Over Budget but ahead of schedule Worst case: Over Budget & behind schedule CPI >1 [Ahead of Schedule] CPI < 1 CPI >1 [Behind Schedule] CPI < 1 SPI < 1 [Under Budget] SPI >1 SPI < 1 [Over Budget] SPI >1
  • 22. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> EVM • SV is a measure of schedule performance on a project. Schedule variance (SV) • It measure of cost performance on a project. • It indicates relationship of performance to costs spent. Cost variance (CV) • SPI is a measure of progress achieved compared to progress planned. Schedule performance index (SPI) • CPI is a measure of value of work completed compared to actual cost. Cost performance index (CPI)
  • 23. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise A) The project is ahead of schedule and on budget B) The project is on schedule and below budget C) The EAC is incorrect D) The project is behind schedule and on budget Answer : The project is behind schedule because as PV is 110,000 & EV is only 90,000. We are 20,000 behind schedule. We are on budget because both our Actual Cost and Earned Value are 90,000. Hence answer is D) The project is behind schedule and on budget Your earned value analysis shows the following values. Which of the following is true? - PV = 110,000, - AC = 90,000 - EV = 90,000, - BAC = 200,000
  • 24. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise Task Duration Planned Value Actual Jan Feb Mar Apr May Jun Analysis 20 1,000 1,400 Design 40 2,000 1,000 Development 60 10,000 4,000 Testing 10 2,000 - Go-live 10 1,000 - closure 0 - - Below graph shows the Project schedule & current performance of the IT project managed by Anand. What is the current SPI of the project. A: -1 B: 0.58 C: 1.21 D: 1 100% 75% 50% A: SPI>1 & CPI>1 B: SPI<1 & CPI<1 C: SPI>1 & CPI<1 D: SPI<1 & CPI>1 Other possible options: A: Project is performing good B: Project is performing bad C: Slowdown with spending to try to reach optimal level D: Spend more to catch up
  • 25. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise Calculate PV of completed or in progress activities •= Activity1(PV)+ Activity2(PV)+ Activity3(PV) •= 1,000+2,000+10,000 •= 13,000 Calculate EV of completed or in progress activities •= Activity1(PV * % complete)+ Activity2(PV * % complete)+ Activity3(PV * % complete) •= (1,000* 100%) + (2,000 * 75%) + (10,000 * 50%) •= 1,000+1,500+5,000 •= 7,500 SPI = EV / PV •= 7,500 /13,000 •= 0.5769 •(SPI <1 means project is behind schedule) Answer- B: 0.58
  • 26. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise Exercise: Calculate CPI? Calculate AC of completed or in progress activities •= Activity1(AC)+ Activity2(AC)+ Activity3(AC) •= 1,400+1,000+4,000 •= 6,400 Calculate EV of completed or in progress activities •= Activity1(PV * % complete)+ Activity2(PV * % complete)+ Activity3(PV * % complete) •= (1,000* 100%) + (2,000 * 75%) + (10,000 * 50%) •= 1,000+1,500+5,000 •= 7,500 CPI = EV / AC •= 7,500 /6,400 •= 1.17 CPI >1 means project under budget.
  • 27. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting Control Cost -> T&T -> Data analysis -> Forecasting Prediction of conditions & events in project's future based on information & knowledge available during forecast. ETC - Estimate to complete: • Expected cost to finish all remaining project work. EAC - Estimate at completion: • Expected total cost of completing all work expressed as “sum of actual cost to date” & “estimate to complete”. • Forecasted estimate for total cost of the Project.
  • 28. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting Control Cost -> T&T -> Data analysis -> Forecasting ETC - Estimate to complete EAC - Estimate at completion Remaining Cost Total Cost at end
  • 29. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting Control Cost -> T&T -> Data analysis -> Forecasting EAC - Estimate at completion ETC - Estimate to complete The information is derived from: Project's past performance Information that could impact project in future Expected future performance
  • 30. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting Consider forecasted EAC, If BAC is no longer viable. EAC involves projections of project’s future based on current performance. Key input is work performance data. EAC - Estimate at completion • Expected total cost of completing all work expressed as “sum of actual cost to date” & “estimate to complete”. Control Cost -> T&T -> Data analysis -> Forecasting Total Cost at end
  • 31. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting EAC - Estimate at completion • Expected total cost of completing all work expressed as “sum of actual cost to date” & “estimate to complete”. Control Cost -> T&T -> Data analysis -> Forecasting Total Cost at end EAC based on Budgeted Rate: •Absorb the Variance (originally planed budgeted rate) EAC based on Current Progress: •Take the ongoing project trend (CPI & SPI or only CPI) EAC - Erroneous scenario: •Re-estimate the remaining portion •Original estimates were fundamentally flowed.
  • 32. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting EAC - Estimate at completion • Expected total cost of completing all work expressed as “sum of actual cost to date” & “estimate to complete”. Control Cost -> T&T -> Data analysis -> Forecasting Total Cost at end • EAC = AC + (BAC –EV) Based on Budgeted rate • EAC = BAC / CPIBased on CPI. • EAC = AC + [(BAC –EV) / (CPI ×SPI)]Based on SPI & CPI • EAC = AC + re-estimateErroneous scenario:
  • 33. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> Forecasting There are many ways to calculate EAC based on project progress. Questions about the EAC will always contain some information about the current “health” (or progression) of the project. There are certain keywords that you can look for to pick correct formula. • EAC = AC + (BAC –EV) • Current variances are thought to be atypical in the future. • Note: atypical means unusual or abnormal. EAC based on Budgeted Rate: • EAC = BAC / CPI • No variances from the BAC have occurred or • Progress expected to continue at the same rate of spending. •This is most often required on the exam. EAC based on Current Cost Progress • EAC=AC+ BAC –EV • Current variances are thought to be typical in the future. EAC based on Current cost & schedule Progress • EAC = AC+ETC • Original estimate was fundamentally flawed or conditions have changed and invalidated original estimating assumptions. EAC - Erroneous scenario:
  • 34. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> Forecasting -> Example Task Duration Planned Value Actual Jan Feb Mar Apr May Jun Initial infrastructure 1 month 1 million 1 ml Pillar 1 & slab 2 months 2 million 2 ml Pillar 2 & slab 2 months 2 million .25 ml Pillar 3 & slab 2 months 2 million - Pillar 4 & slab 2 months 2 million - Pillar 5 & slab 2 months 2 million - Finalize & handover 1 month 1 million Bridge construction project. 100% 100% 25% Bridge construction Project: Duration : 12 months, Cost of the Project: 10,000,000 Current status at end of month 3.5: The pillar was collapsed & hence progress was slowed. Actual cost: 3,250,000
  • 35. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . EAC based on Budgeted Rate: •EAC = AC + (BAC –EV) Bridge construction Project: •Duration : 12 months •Cost of the Project: 10,000,000 •Current status at end of month 3: •The pillar was collapsed & hence progress was slowed. •Work completed: only 20% of complete project •Actual cost: 3,000,000 BAC = 10,000,000 AC = 3,000,000 EV = 20% of 10,,000,000 = 2,000,000 (0nly 20% work done) EAC = AC + (BAC – EV) EAC = 3,000,000 + (10,000,000 – 2,000,000) = 11,000,000 EAC = 11 Million Considering this as rare incident. Project will continues progressing as originally planned, then it will need 11 Million to complete. Control Cost -> T&T -> Data analysis -> Forecasting -> Example
  • 36. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> Forecasting -> Example EAC based on Current Progress (Based on CPI): EAC = BAC / CPI Bridge construction Project: • Duration : 12 months • Cost of the Project: 10,000,000 • Current status at end of month 6: • Work completed: only 40% of complete project • Actual cost: 6,000,000 BAC = 10,000,000 AC = 6,000,000 EV = 40% of 10,000,000 = 4,000,000 (0nly 40% work done) CPI = EV / AC = 4,000,000 / 6,000,000 = 0.66 EAC = BAC/CPI = 10,000,000/0.66 = 15,151,515 EAC = 15,151,515 If project continues to progress CPI 0.66 until end, you have to spend 15.15 Million to complete the project.
  • 37. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> Forecasting -> Example EAC based on Current Progress (Based on CPI & SPI): EAC = AC + [(BAC –EV) / (CPI ×SPI)] Bridge construction Project: Duration : 12 months Cost of the Project: 10,000,000 Current status at end of month 6: Work completed: only 40% of complete project Actual cost: 6,000,000 BAC = 10,000,000 & AC = 6,000,000 PV = 50% of 10,000,000 = 5,000,000 (six months completed) EV = 40% of 10,000,000 = 4,000,000 (0nly 40% work done) CPI = EV / AC = 4,000,000 / 6,000,000 = 0.66 SPI = EV / PV = 4,000,000 / 5,000,000 = 0.8 EAC = 6,000,000 + [ (10,000,000–4,000,000)/ (0.66 * 0.8) ] EAC = 6,000,000 + [6,000,000 / 0.528 ] = 17,363,636 If project continues with similar CPI & SPI, you have to spend 17.36 Million to complete project.
  • 38. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> Data analysis -> Forecasting -> Example Bridge construction Project: Duration : 12 months, Cost of the Project: 10,000,000 Current status at end of month 6: Work completed: only 55% of complete project. Actual cost: 5,000,000 EAC based on Budgeted Rate: •EAC = AC + (BAC –EV) •BAC = 10,000,000 •AC = 5,000,000 •EV = 55%10,000,000 = 5,500,000 •EAC = 5,000,000 + ( 10,000,000 – 5,500,000) •EAC = 5,000,000 + 4,500,000 •EAC = 9,500,000 EAC based on Current Progress (Based on CPI): •EAC = BAC / CPI •BAC = 10,000,000 •AC = 5,000,000 •EV= 55%10,000,000 •EV =5,500,000 •CPI = EV / AC •CPI = 5,500,000 / 5,000,00= 1.1 •EAC = 10,000,000 / 1.1 •EAC = 9,090,909 EAC based on Current Progress (Based on CPI & SPI): •EAC = AC + [(BAC –EV) / (CPI ×SPI)] •PV = 50% of 10,000,000 = 5,000,000 (six months completed) •EV & CPI calculation is same. •SPI = EV / PV •SPI = 5,500,000 / 5,000,000 = 1.1 •EAC = 5,000,000 + [(10,000,000 – 5,500,000) / (1.1 * 1.1)] •EAC = 5,000,000 +( 4,500,000 / 1.21) •EAC = 5,000,000 + 3,719,008.26 •EAC = 8,719,008.26
  • 39. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise You presenting project status to Steering committee at the end of first Quarter in one year project. The project is progressing as planned and you expect no major problems in the foreseeable future. Your PMIS is showing following data: BAC = 500,000, SPI = 1.1, CPI = 1.05, EV = 173,000, AC = 164,761. What you should report about EAC in the meeting? A) 491,761 B) 454,545 C) 189,761 D) 476,190 Answer: Highlighted information indicates there were no variances after atypical situation & expect to continue at same rate. Hence, we will use second formula EAC= BAC/CPI =500,00/1.05 = 476,190; Hence, answer is D) 476,190
  • 40. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise Task Duration Planned Value Actual Jan Feb Mar Apr May Jun Analysis 20 1,000 1,400 Design 40 2,000 2,000 Development 60 10,000 - Testing 10 2,000 - Go-live 10 1,000 - closure 0 - - Below schedule depicts the CRM Project schedule managed by Project managed Anand. As of today first two activities should have been 100% completed and third 50%. However PM reported 100% completion of first two, and remaining activities are not yet started. Assuming projects future performance will be at budgeted rate, what will be the projects EAC (Estimate at completion)? 100% 100% A: 3,400 B: 16,000 C: 16,400 D: 3,000
  • 41. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise Even though project is not performing as expected, we expect project to performed at the planned rate (budgeted rate). The formula used in this scenario is EAC = AC + (BAC – EV) Calculate Actual Cost (AC) of completed or in progress activities. • = Activity1(AC)+ Activity2(AC) = 1,400+2,000 = 3,400 Calculate BAC (Total of all the activities) • BAC = 1,000 + 2,000 + 10,000 + 2,000 + 1,000 = 16,000 Calculate EV of completed or in progress activities • = Activity1(PV * % complete)+ Activity2(PV * % complete) • = (1,000* 100%) + (2,000 * 100%) = 1,000+2,000 = 3,000 EAC=AC+(BAC-EV) • =3,400 + (16,000 – 3,000) = 3,400 + 13,000 = 16,400 Answer – C: 16,400
  • 42. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting Control Cost -> T&T -> Data analysis -> Forecasting Total Cost at end EAC - Estimate at completion (Re-estimate) • EAC = AC + ETC (or Re-estimate) Software Project: • Project is to implement CRM Software for government department for 5,000,000. • To date project has spent 1,100,000. • However, during execution, it was noticed that present cost estimation were fundamentally flawed & need to re- calculate budget for remaining part of the project. You discuss with your team & re-estimate the cost of the remaining work. Your new estimates: Design = 1,000,000, Development=3,000,000, testing=1,500,500 Re-estimated cost = Design + Development + testing Re-estimated cost = 1,000,000 + 3,000,000 + 1,500,500 = 5,500,500 EAC = AC + Re-estimate EAC = 1,100,000 + 5,500,500 = 6,500,500
  • 43. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting Control Cost -> T&T -> Data analysis -> Forecasting ETC - Estimate to complete •ETC = EAC- AC or (Re-estimate remaining work) Cost to complete House construction Project: • You have a construction project to be completed in 12 months with cost of 1,000,000. • Six months passed & project have spent 600,000. • In meeting PM reported that only 40% of work is completed & project is expected to perform with same cost performance. • Management is interested to know what is Estimate to complete? BAC = 1,000,000, AC = 600,000 PV= 50% of 1,000,000 = 500,000 (six months completed) EV= 40% of 1,000,000 = 400,000 (0nly 40% work done) CPI= EV / AC = 400,000 / 600,000 = 0.66 EAC = BAC/CPI = 1,000,000/0.66 = 1,515,151 ETC = EAC- AC ETC = 1,515,151 – 600,000 ETC = 915, 151
  • 44. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> EVM -> Exercise Your Team Lead, who was leading the estimation team, tells you that he had missed several key project components in estimation. So, his original cost estimations were completely wrong. At the end of this meeting, he assured to provide new estimate in 2 days. Based on the new estimates, your PMIS shows below: BAC: 5,000,000. AC= 1,100,000, CPI = 1.05, SPI = 1.05, EV = 1,000,000. How much project will cost, if the new estimate to complete that you received from your Team Lead is 5,500,500? A) 5,500,500 B) 6,500,500 C) 6,600,500 D) 6,100,000 Answer: Highlighted information indicates there were fundamental flows in the estimates. Hence, we will use fourth formula EAC= AC + ETC = 1,100,000 +5,500,500 = 6,600,500; Hence, answer is C) 6,600,500
  • 45. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Forecasting Control Cost -> T&T -> Data analysis -> Forecasting VAC (Variance at completion) • Projection of budget difference between BAC & EAC. VAC shows whether project is forecasted to finish under or over budget. VAC = BAC – EAC VAC % = EAC / BAC
  • 46. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . TCPI TCPI calculation Same Budget Use BAC Revised Budget Use Forecasted EAC TCPI is measure of Cost Performance that is required to be achieved in order to meet a specified management goal. Ratio of “work remaining”, to “funds remaining”. Control Cost -> T&T -> To Complete Performance Index (TCPI) If BAC is no longer viable, then forecasted EAC should be approved to use in the TCPI calculation. Work Remaining ---------------------- Fund Remaining ( BAC – EV ) ---------------- ( BAC – AC ) ( BAC – EV ) ---------------- ( EAC – AC )
  • 47. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> TCPI -> Example 300,000 BAC:600,000 315,000 270,000 - 100,000 200,000 300,000 400,000 500,000 600,000 700,000 Month1 Month2 Month3 Month4 Month5 Month6 Planned Budget (PV) Actual Cost (AC) Earned Value (EV) Fund Remaining = BAC-AC = 600,000-315,000 = 285,000 Work Remaining = BAC-EV = 600,000-270,000 = 330,000 Case1: Same Budget Project with current status BAC=600,000 PV=300,000 AC=315,000 EV=270,000
  • 48. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> TCPI -> Example TCPI (based on BAC) Work Remaining = BAC-EV = 600,000- 270,000 = 330,000 Fund Remaining = BAC-AC = 600,000- 315,000 = 285,000 TCPI = Work Remaining / Fund Remaining = 330,000 / 285,000 = 1.15 You have to get output of 1.15 AED of every 1 AED spent. •Project is in a comfortable position. If TCPI < 1 •Project have to perform with better cost performance than past. If TCPI > 1 •Project can continue with same cost performance. if TCPI = 1
  • 49. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> TCPI -> Example 300,000 BAC:600,000 315,000 270,000 - 100,000 200,000 300,000 400,000 500,000 600,000 700,000 Month1 Month2 Month3 Month4 Month5 Month6 Planned Budget (PV) Actual Cost (AC) Earned Value (EV) Fund Remaining = EAC-AC = 650,000-315,000 = 335,000 Work Remaining = BAC-EV = 600,000-270,000 = 330,000 Case1: Revised Budget Project with current status BAC=600,000 PV=300,000 AC=315,000 EV=270,000 EAC = 650,000
  • 50. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> T&T -> TCPI -> Example TCPI (based on BAC) Work Remaining = BAC-EV = 600,000-270,000 = 330,000 Fund Remaining = BAC-AC = 600,000-315,000 = 285,000 TCPI = Work Remaining / Fund Remaining = 330,000 / 285,000 = 1.15 You have to get output of 1.15 AED of every 1 AED spent. TCPI (Based on EAC) Work Remaining = BAC-EV = 600,000-270,000 = 330,000 Fund Remaining = EAC-AC = 650,000-315,000 = 335,000 TCPI = Work Remaining / Fund Remaining = 330,000/335,000 =0.98 You have to get output of 0.98 AED of every 1 AED spent.
  • 51. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . PMIS Control Cost ->T&T-> Project Management Information System (PMIS) Calculate earn value Display graphical trends & calculate SPI & CPI Show variances Forecast a range of possible final project results
  • 52. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> Output Work Performance Information Cost Forecasts Change Requests PMP updates Project doc. updates
  • 53. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . Control Cost -> Data flow diagram
  • 54. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved . How to control cost? What is EVM? What is cost & schedule variance? What is cost & schedule performance index? What is forecasting? What is TCPI? What do you mean by Performance review? Control Cost -> Review
  • 55. By: Anand Bobade (nmbobade@gmail.com)PMBOK 6edition @ All rights reserved .