Chapter 6 :
Project Time Management
(Part 1)
Plan Schedule
management
Define
Activities
Sequence
Activities
Estimate
Activity
resource
Estimate
Activity
Duration
Develop
Schedule
Control
Schedule
Planning
Monitoring &
Controlling
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
L : Lesson
Introduction
Time Management Processes
Processes in details:
Review of all processes
Exam Essentials & Tips
Self Assessment
Additional Resources
P1 P2 P3 P4 P5 P6 P7
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management-> Introduction
Provide scheduling framework.
Develop a schedule.
Finalize deliverable delivery dates.
Prepare base for budgeting.
Control project schedule.
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.1 Plan Schedule management:
The process of establishing policies, procedures, &
documentation for planning, developing, managing,
executing, & controlling the project schedule
6.2 Define Activities:
The process of identifying and documenting the
specific actions to be performed to produce the project
deliverables.
6.3 Sequence Activities:
The process of identifying and documenting
relationships among the project activities.
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.4: Estimate Activity resource:
Estimating the type and quantities of material, human resources,
equipment, or supplies required to perform each activity
6:5 Estimate Activity Duration:
Estimating the number of work periods needed to complete
individual activities with estimated resources
6:6 Develop Schedule:
Analysing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model
6.7 Control Schedule:
Monitoring the status of project activities to update project
progress and manage changes to the schedule baseline to achieve
the plan.
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule management
Plan Schedule Management Definition
Plan Schedule management : ITTO
What is Analytical Techniques?
What is inside Schedule Management plan?
Data flow diagram
Review
Guidelines for exam questions
Self Assessment
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
Planning Developing Managing
Executing Controlling
Establishing policies, procedures & documentation for
planning, developing, managing, executing &
controlling project schedule.
Provide guidance & direction on how the project
schedule will be managed.
Establishing
6.1 Plan Schedule management -> Definition
Project Schedule
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management
Inputs (4)
• Project
management plan
• Project charter
• Enterprise
environmental
factors
• Organizational
process assets
Tools &
Techniques (3)
• Expert judgment
• Analytical
Technique
• Meetings
Outputs (1)
• Schedule
Management plan
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Input
PMP Project
Charter
EEF OPA
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Input
PMP
PMP contains the information about project
execution and control.
Other Subsidiary plans.
Scope baseline – Project scope statement, WBS,
WBS dictionary.
Other information – scheduling cost, risk &
communication related decisions.
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Input
Project
Charter
Summary Milestone Schedule.
Project approval requirements.
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Input -> EEF
EEF
Organizational culture & structure.
Resource availability & skills.
Published commercial data - resource productivity.
Scheduling tool.
Organizational work authorization systems.
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management-> Tools & Techniques
Expert Judgment
Analytical
Techniques
Meetings
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Manag.->T&T->Expert Judgment
Expert Judgment
Can suggest scheduling methods & solutions.
Expertise in project execution in the organization (one who
already executed project). Historical information.
E.g., Technology Lead worked on various software project in the
organization.
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Manag.->T&T->Analytical Techniques
Analytical
Techniques
Choosing option for estimating, optimizing &
controlling schedule.
Scheduling
Methodology
Scheduling
techniques
Resource
optimizing
techniques
Schedule
performance
review
Resource Levelling: balance
demand for resources with
supply.
Resource Smoothing: Adjusts
schedule activities.
Crashing: Shorten duration by
adding resources.
Fast tracking: Activities done in
sequence are performed in
parallel
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Manag.->T&T->Analytical Techniques
Schedule MP - Details the way to fast track or crash the project.
Organization Policies & procedure may influence selection of
scheduling techniques.
Analytical
Techniques Rolling wave planning
Leads & Lags
Alternative Analysis
Methods for reviewing schedule performance
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Manag.->T&T->Meetings
Meetings
Project team may attend meetings.
Project
Manager
Technical
Leads
Selected team
members
Functional
Managers
Any one with estimation & scheduling related
responsibilities should attend meetings.
Discuss & agree
how Resource
optimizing
techniques
Discuss & agree
on Scheduling
Methodology,
Scheduling
techniques
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Output->SMP
Schedule
Management
plan
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Output
Schedule
Management
plan
Establishes criteria & activities for developing,
monitoring & controlling project schedule.
Project Schedule Model Development & maintenance (Gantt
chart).
Level of accuracy (High level or detailed)
Unit of measure (Hours, days or weeks)
Schedule Control thresholds ( E.g., what is acceptable delay )
Rules of Performance measurement.
Scheduling/estimating techniques to be used on Project.
Process descriptions.
Reporting formats (Performance reports, variance reports etc)
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Output
Schedule
Management
plan
• Predicted vs actuals
• Earned value management (EVM)
rules.
• Physical measurement rules.
Rules of
performance
measurement:
• Rules for establishing percentage
complete.
• Rules for Control accounts.
• Earned value measurement
techniques (Baselines, fixed-
formula, % complete, etc.)
Ex: Schedule
management
plan may
specify:
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Data Flow Diagram
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.1 Plan Schedule Management -> Review
Why schedule Management is important?
What is schedule management plan?
What are the components of schedule
management plan?
What is use of analytical technics?
6.1 I T&T O
By: Nemanand Bobade (nmbobade@gmail.com)
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
6.1 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities
Define activity Process definition
Define Activity: ITTO
What is Decomposition?
What is Rolling wave planning?
Data flow diagram
Review
Guidelines for exam questions
Self Assessment
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.1 Plan Schedule management:
The process of establishing policies, procedures, &
documentation for planning, developing, managing,
executing, & controlling the project schedule
6.2 Define Activities:
The process of identifying and documenting the
specific actions to be performed to produce the project
deliverables.
6.3 Sequence Activities:
The process of identifying and documenting
relationships among the project activities.
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.4: Estimate Activity resource:
Estimating the type and quantities of material, human resources,
equipment, or supplies required to perform each activity
6:5 Estimate Activity Duration:
Estimating the number of work periods needed to complete
individual activities with estimated resources
6:6 Develop Schedule:
Analysing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model
6.7 Control Schedule:
Monitoring the status of project activities to update project
progress and manage changes to the schedule baseline to achieve
the plan.
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Introduction
Consider Project to construct 50 KM water Pipeline in difficult terrain.
It is huge task & will involve lot of planning & coordination.
How do we execute this?
Start identifying all activities of each work package in WBS.
Also, think about the key milestones.
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Definition
Identifying &
Documenting
Specific
Actions
Produce
Identifying & documenting specific actions to be
performed to produce project deliverables.
Break work packages into activities that provide a basis
for estimating, scheduling, executing, monitoring &
controlling the project work.
Project
Deliverables
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> ITTO
Inputs
• Schedule
management plan
• Scope baseline
• Enterprise
environmental
factors
• Organizational
process assets
Tools &
Techniques
• Rolling wave
planning
• Expert judgment
Outputs
• Activity list
• Activity attributes
• Milestone list
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Input
Schedule Manag.
plan
Scope Baseline EEF OPA
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Input -> SMP
Schedule Manag.
plan
Prescribed level of details necessary to manage the
work.
Guideline to define activities (e.g., max duration)
Organizational Policies & procedure.
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Input -> Scope Baseline
Scope Baseline
Project scope statement:
• Scope, major deliverables.
• Assumptions & constraints.
WBS: List of all work packages. This is the
key input. Activities under each work
package will be identified & listed.
WBS dictionary: Detailed deliverable &
scheduling information about each WBS.
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Input->EEF
EEF
Organizational culture & structure.
published Commercial information.
Project Management Information System (PMIS)
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Input-> OPA
OPA
Lessons learned about activity list.
Templates with standard activity list.
Activity list from Historical project data.
Activity related policies, procedures & guidelines
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Tools & Techniques
Decomposition Rolling Wave
planning
Expert Judgment
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Tools & Techniques->Decomposition
Decomposition
Technique used for dividing & subdividing project scope &
deliverables in smaller & more manageable parts.
Activities represent efforts needed to complete work package.
It define final output as activities rather than deliverables.
Oil & Gas Pipeline
Project
Project
Management
Project Plan
Scope
Budget
Procurement
Metal
Equipment
Resources
Build pipeline
Foundation
work
Equipment
erection
Pipe joining
Sensor
installations
------> Activity List
Mark the layout
Get the Machines
Dig the area
Level the area
Prepare foundation
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> T & T -> Rolling wave planning
Rolling Wave
planning
An iterative planning technique in which:
work to be accomplished in
near term is planned in
details.
while work in future is
planned at a higher level.
Form of
Progressive
Elaboration
Planning packages can be created when detailed
information is not available.
6.2 I T&T O
CRM Project
Initiation
Project charter
Feasibility Study
Business Case
Stakeholder List
Study
Business
Requirement
Document
Reporting
Requirements
System
Requirements
Vendor
selection
Integration
Requirements
Design & Build
System Design
High level
Design
Low level Design
System Build
Build module1
Build Module2
Build Module3
Integration Build
Reports Build
Test
System Testing
Integration
Testing
User
Acceptance
Testing
Security Testing
Performance
Testing
Operate
Training
Go-live
Handover
Training
Contract Closure
Project closure
Work packages can
be decomposed
further when
sufficient
information is
available.
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> T & T -> Rolling wave planning
CRM Project
Initiation
Project charter
Feasibility Study
Business Case
Stakeholder List
Study
Business
Requirement
Document
Reporting
Requirements
System
Requirements
Vendor selection
Integration
Requirements
Design & Build
System Design
High level Design
Low level Design
System Build
Build module1
Build Module2
Build Module3
Integration Build
Reports Build
Test
System Testing
Integration
Testing
User Acceptance
Testing
Security Testing
Performance
Testing
Operate
Training
Go-live
Handover
Training
Contract Closure
Project closure
Jan
Feb
March Apr
May
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities->Tools & Techniques->Expert Judgment
Expert Judgment
Person experienced & skilled in developing detailed
• Project scope statement
• WBS
Who's should define activities:
• Person responsible to execute them.
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Outputs
Activity list
Activity
attributes
Milestone list
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Outputs -> Activity List
Activity list
A list of activities that will be performed on project.
Every work package in the WBS is detailed to create activity list.
It is a list with unique id, WBS reference & description of each activity.
Complete activity list helps in accurate estimation & project schedule.
Activity ID WBS Id Name Description
501 W50 Mark the layout
502 W50 Get the Machines
503 W50 Dig the area
504 W50 Level the area
505 W50 Prepare foundation
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Outputs ->Activity Attributes
Activity
attributes
When Completed, they may include following attributes:
Information available during the initial stages of the project:
Activity identifier (ID) WBS ID Activity label or name
Activity description Predecessor activities Successor activities
Logical relationships
Resource
requirements
Imposed dates
Assumptions Person responsible
Geographic area or
place
Provide more information such as predecessors, successors,
logical relationships, resource requirements etc for each
identified activity.
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Outputs ->Milestone List
Milestone list
A milestone is a significant point in the project.
Used for setting schedule goals & monitoring
progress.
May be mandatory (contractual), or just for guidance.
Zero duration task with no. resources
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Data Flow Diagram
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.2 Define Activities -> Review
Defining activities by Decomposing work
package
Scope baseline is the main input
What is decomposition?
What is rolling wave planning?
What is Activity list?
What is Activity Attributes?
6.2 I T&T O
By: Nemanand Bobade (nmbobade@gmail.com)
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
6.2 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities
Sequence activity Process definition
Sequence Activity: ITTO
Why to determine Activity dependencies?
What is PDM?
What is logical Relationship between activities?
Data flow diagram
Review
Guidelines for exam questions
Self Assessment
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.1 Plan Schedule management:
The process of establishing policies, procedures, &
documentation for planning, developing, managing,
executing, & controlling the project schedule
6.2 Define Activities:
The process of identifying and documenting the
specific actions to be performed to produce the project
deliverables.
6.3 Sequence Activities:
The process of identifying and documenting
relationships among the project activities.
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.4: Estimate Activity resource:
Estimating the type and quantities of material, human resources,
equipment, or supplies required to perform each activity
6:5 Estimate Activity Duration:
Estimating the number of work periods needed to complete
individual activities with estimated resources
6:6 Develop Schedule:
Analysing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model
6.7 Control Schedule:
Monitoring the status of project activities to update project
progress and manage changes to the schedule baseline to achieve
the plan.
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->Introduction
Consider same example about constructing pipeline.
We will need to sequence activities . How?
Identify relationship between activities.
Create the logical relationship.
Execute them in same order.
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->Definition
The process of identifying & documenting relationships
among project activities.
Project
Activities
Identifying &
Documenting
Relationship
Defines logical sequence of work to obtain greatest
efficiency within project constraints.
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities
Inputs
• Schedule
management plan
• Activity list
• Activity attributes
• Milestone list
• Project scope
statement
• EEF
• OPA
Tools &
Techniques
• Precedence
diagramming
method (PDM)
• Dependency
determination
• Leads and lags
Outputs
• Project schedule
network diagrams
• Project documents
updates
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Input
Schedule
Management plan
Activity list Activity Attributes Milestone list
Project Scope
statement
EEF OPA
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Input
Identifies scheduling method & tools to be used for
project, which will guide on sequencing activities.
All schedule activities required which are to be
sequenced. Dependencies & constraints can influence
sequencing.
Describes necessary sequence of events or defined
predecessor & successor activities.
It will have schedule date for specific milestone, which
may influence the way activities are sequenced.
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Input
Scope statement contains product scope description
that may effect activity sequencing. Deliverables,
constraints, assumption also may effect sequencing
Govt. or Industry standards, PIMS, scheduling tool,
Work authorization system
Scheduling methodology, activity planning related
policies, procedures guidelines.
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Tools & Techniques
Dependency
determination
Precedence
diagramming
method (PDM)
Leads and lags
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->T&T->Dependency Determination
Dependency
determination
Types:
Mandatory
dependency
Discretionary
dependency
External
dependency
Internal
dependency
Determine how one activity is dependent of another
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->T&T->Dependency Determination
Dependency
determination
Requirements
Documentation
Client Approval
• Legally or contractually required
• Inherent in the nature of work
Mandatory
dependency
(Hard logic)
Lay Building Foundation Construct Floor
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->T&T->Dependency Determination
Dependency
determination
Develop Module A Develop Module C
• There could be more than one way to
define the sequence between 2 activities.
• Based on best practices.
• Defined by project team (Flexible)
Discretionary
dependency
(Preferred or
preferential or
soft logic)
6.3 I T&T O
Develop Module A Develop Module B
If above sequence of module development was decided by
project team; you can always change it to below sequence, if
required.
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->T&T->Dependency Determination
Dependency
determination
Delivery of Equipment Start work
Vendor team on boarding Start work
• Relationships between project and non-
project activities
• Activities are done by external people.
• Outside project control.
External
dependencies
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->T&T->Dependency Determination
Dependency
determination
Develop System by
coding team
Test System by software
testing team
build house by
Contruction team
Paint & decorate house by
interior design team
• Precedency relationship defined between
two activities.
• Done by internal team member.
• Inside project teams control.
Internal
dependencies
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Tools & Techniques -> PDM
Precedence
diagramming
method (PDM)
Method of constructing a project schedule network
diagram, to represent activities & connects them
with arrows that show dependencies.
Activities are represented by boxes.
Arrows shows relationships between activities.
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Tools & Techniques -> PDM
How to develop schedule network diagram.
Activity Activity Description Duration (days) Predecessor
A Collect Requirement 50 -
B System Design 25 A
C Build Module 1 40 B
D Build Module 2 50 C
E Build Module 3 10 B
F Build Module 4 15 E
G Build Module 5 30 B
H System Testing 25 D,F,G
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Tools & Techniques -> PDM
Collect
Requirements
(A - 50days)
Start
System
Design
(B - 20d)
Build module 1
(C - 40 day)
Build module 2
(D - 50 day)
Build
module 3
(E - 10 day)
Build module 5
(G - 30 day)
Testing
(H-25 days)
Build
module 4
(F - 15 day)
End
Acti
vity
Activity
Description
Duratio
n (days)
Predece
ssor
A Collect
Requirement
50 -
B System Design 25 A
C Build Module 1 40 B
D Build Module 2 50 C
E Build Module 3 10 B
F Build Module 4 15 E
G Build Module 5 30 B
H System Testing 25 D,F,G
• = A->B->C->D->H =
50+20+40+50+25 = 185Path1
• = A->B->E->F->H = 50+20+10+15+25
= 120Path2
• = A->B->G->H = 50+20+30+25 = 125Path3
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Tools & Techniques -> PDM
Logical Relationships
Precedence
diagramming
method (PDM)
• Task B can not start until Task
A finishes
Finish to start
- FS
• Task B can not start until Task
A starts
Start to Start
- SS
• Task B can finish until Task A
finishes
Finish to
Finish - FF
• Task B can not finish until
Task A starts
Start to Finish
- SF
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Tools & Techniques -> PDM
Wash a Car Dry a Car
Mix Concrete
Prepare
Concrete floor
• Drying the car can not start until Car is washedFS
• Concrete flooring cant not be started until you start mixing
concrete
SS
Precedence
diagramming
method (PDM)
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Tools & Techniques -> PDM
Match in progress
Broadcasting
Shift Finish
for Guard1
Shift start for
Guard2
• Broadcasting of a match cannot finish until the match is
finished
FF
• start of the new shift of the security guard signal the finish
shift of the current security guard
SF
Precedence
diagramming
method (PDM)
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> T&T -> Leads & Lags
Business Requirement
(BRS)
System Requirement
(SRS)
Sign Contract
Team On-
board
Lead
1 week
Lag
3 week
Lead: It is amount of time where
successor activity can be advanced w.r.t.
predecessor activity.
Lag: It is amount of time whereby a
successor activity will be delayed w.r.t. a
predecessor activity.
Leads & lags
6.3 I T&T O
Business Requirement
(BRS – 4 weeks)
System Requirement
(SRS – 4 weeks)
W1 W2 W3 W4 W5 W6 W7 W8 W1 W2 W3 W4 W5 W6 W7 W8
Sign Contract
Team On-
board
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> T&T -> Leads & Lags
Coding (6 week)
Peer Review (3 week)
FS : Lead –
2 week
Coding (6 week)
Peer Review (3 week)
SS : Lag –
3 week
Coding (6 week)
Peer Review (3 week)
FF : Lag –
3 week
Both gives same
output in terms
of schedule
This is more
appropriate as
Coding finish
means coding &
Peer review has to
finish.
Leads & lags
Lead is often represented as negative value for Lag in scheduling software
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Output
Project Schedule
Network diagram
Project
Documents update
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->Output->Proj. Schedule ND
It is a graphical representation of logical relationship
between activities.
Shows dependencies among schedule activities.
Project Schedule
Network diagram
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->Output->Proj. Schedule ND
Schedule Network template:
Will be generated once all activities are sequenced &
relationship/dependencies are set.
Templates can be used from similar projects.
Developed by accumulating lessons learned.
Used for entire project or portion of a project.
Project Schedule
Network diagram
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Output->Project Doc. updates
Project
Documents
update
• New activities identified during
sequencingActivity lists
• New attribute identified
• Change in attributes of older
activities
Activity
attributes
• Risk identified due to dependenciesRisk register
• Any change in scheduling process
Schedule
management
plan
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities->Output->Data Flow Diagram
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.3 Sequence Activities -> Review
Why sequencing is important?
Why are different types of activity
dependencies?
What is PDM?
What are different logical Relationship?
What is Project schedule network
diagram?
6.3 I T&T O
By: Nemanand Bobade (nmbobade@gmail.com)
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
6.3 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resource
Estimate Activity resource Process definition
Estimate Activity resource: ITTO
Why is Alternative Analysis?
What is Bottom up estimation?
What is resource breakdown structure?
Data flow diagram
Review
Guidelines for exam questions
Self Assessment
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.1 Plan Schedule management:
The process of establishing policies, procedures, &
documentation for planning, developing, managing,
executing, & controlling the project schedule
6.2 Define Activities:
The process of identifying and documenting the
specific actions to be performed to produce the project
deliverables.
6.3 Sequence Activities:
The process of identifying and documenting
relationships among the project activities.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6. Project Time Management
6.4: Estimate Activity resource:
Estimating the type and quantities of material, human resources,
equipment, or supplies required to perform each activity
6:5 Estimate Activity Duration:
Estimating the number of work periods needed to complete
individual activities with estimated resources
6:6 Develop Schedule:
Analysing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model
6.7 Control Schedule:
Monitoring the status of project activities to update project
progress and manage changes to the schedule baseline to achieve
the plan.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4: Estimate Activity resource -> Introduction
Human resources Material
Equipment Supplies
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
Estimating type & quantities of material, human
resources, equipment or supplies required to perform
each activity.
Type &
Quantities
Material
Human resources
Equipment
Supplies
Estimating
Project
Activities
Perform
Develop more accurate cost and duration estimates.
6.4: Estimate Activity resource -> Definition
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4: Estimate Activity resource -> Key Factors
Complexity Resource Skills
Resource
availability
History of
performing similar
task
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources
Inputs
• Schedule
management plan
• Activity list
• Activity attributes
• Resource calendars
• Risk register
• Activity cost
estimates
• EEF
• OPA
Tools &
Techniques
• Expert judgment
• Alternative analysis
• Published
estimating data
• Bottom-up
estimating
• Project
management
software
Outputs
• Activity resource
requirements
• Resource
breakdown
structure
• Project documents
updates
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Resources -> Input
Schedule
Management
Plan
Activity list
Activity
Attributes
Resource
Calendars
Risk Register
Activity Cost
estimates
EEF OPA
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Resources -> Input->SMP
Schedule
Management
plan
It identifies scheduling method & tools to be used
for the project, which will guide how to estimate
activity resources.
Project Schedule Model Development
Level of accuracy
Unit of measure (Hour, Day etc)
Control thresholds
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Resources -> Input-> Activity List
Activity list
A list of all schedule activities to estimate activity
resources.
Activity ID WBS Id Name Description
501 W50 Compare Furniture brands
502 W50 Find showrooms
503 W50 Get Quotes
504 W50 Compare Quotes
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Resources -> Input-> Activity Attributes
Activity
attributes
Activity description Predecessor activities Successor activities
Logical relationships
Resource
requirements
Imposed dates
Assumptions Person responsible
Geographic area or
place
Provide more information such as predecessors, successors, logical
relationships, resource requirements etc for each identified activity.
Attributes are updated during schedule creations, when completed
they may include following attributes:
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Resources -> Input-> Resource Calendar
Identifies working days & shifts on which each
specific resource is available.
Details about when & how long identified project
resource will be availableResource
Calendars
• Resource may be material, human resources, equipment etcRemember:
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->Input->Risk Register
Risk events may impact resource selection and
availability.
Risks related to activity sequencing, dependencies.
It may lead to alternative analysis.
Risk
Register
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->Input->Activity Cost Estimates
Activity Cost
Estimates
Provides probable costs required to complete
activities / project work. (summary or detail)
Resource & cost estimation is cyclic process.
Cost constraints may lead to selection of certain
type of resources.
Estimate Cost
(Project Cost Manag.)
Estimate Activity
resources-Resource type / Quantity; make or
buy / Manual or automated can be
decided based on cost constraints.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Resources -> Input->OPA
OPA
Staffing related Policies and procedures.
Procurement (rental and purchase) related Policies
and procedures.
Historical information – types/quantities of
resources used for similar work on previous projects.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Resources -> Input->EEF
EEF
Resource
location availability and skills.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources -> Tools & Techniques
Expert
Judgement
Alternative
Analysis
Published
Estimating data
Bottom up
estimates
Project
Management
Software
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
Mr. Expert
6.4 Estimate Activity resources -> T&T -> Expert Judgment
Expert
Judgement
Can help in choosing right resource.
Identify activity resource requirement.
Can perform or contribute in estimating &
alternative analysis.
Specialized knowledge in resource planning &
estimating can provide such expertise.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->T&T->Alternative Analysis
Any group or person with specialized knowledge in resource
planning and estimating can provide such expertise
Alternative
Analysis
Many schedule activities have alternative methods
of accomplishment
Various levels of
resource capability
or skills.
Different size or
type of machines.
Different tools
(hand versus
automated)
Make- rent-or-buy
decisions regarding
the resource.
Analyses
focus on:
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->T&T->Alternative Analysis
Any group or person with specialized knowledge in resource
planning and estimating can provide such expertise
2
Example: Road construction work - Expert helping PM
identifying resource requirements through alternative analysis
Build Manually
• Advantage: Less cost
• Disadvantage: More
human resources & Slow
delivery.
Use machines
• Advantages: Faster
delivery & Less human
resources.
• Disadvantages: More
cost, Resource
capabilities, Machines
availability etc
Alternative
Analysis
1
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->T&T-> Alternative Analysis
Alternative
Analysis
Example: Cost, Quality & Risk
• Manual work may cost less as cheap human
resources are available but may need more time
to complete project.
Cost
• Machine developed road will give better quality
hence maintenance cost will be less. Also,
delivery will be faster.
Quality:
• Machines may not be available. Bringing
machines to the location may not be possible.
Human resource to operate may not be available.
Risk:
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->T&T->Published est. data
Any group or person with specialized knowledge in resource
planning and estimating can provide such expertise
Rates
Unit
Cost
Labour
trade
Material
Equipm
-ent
Published
Estimating
Data
Production rates & unit costs of resources, material, and
equipment.
Data from different countries and geographical locations.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->T&T-> Bottom up estimate
Bottom up
Estimate
Estimating resources or cost by aggregating
estimates of lower-level components of WBS.
Activities are broken into smaller activities which can
be estimated.
There resource needs are estimated.
Resources are assigned to each activity.
These estimates are aggregated into a total quantity
of resources.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->T&T-> PM Software
Any group or person with specialized knowledge in resource
planning and estimating can provide such expertise
Project
Management
Software
Optimizing Resource utilization
Resource breakdown
structure
Resource availability
Resource rate
Resource calendar
Project Management Software has capability to:
Plan, organize & manage the
resource pools.
Develop resource estimates
Can automatically resolve scheduling conflicts.
Can help perform workload analysis.
Can help optimize resource utilization.
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources -> Outputs
Activity resource
requirements
Resource
breakdown
structure
Project Documents
update
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity Res.->Outputs->Activity Resource Req
Activity
Resource
Requirements
The types and quantities of resources required for
each activity in a work package.
Aggregated to determine the estimated resources
for each work package and each work period.
Resource
Type/ Activity
Resource
Quantity/
Activity
Resource for
Work Package
6.4 I T&T O
Activity ID WBS Id Name Resource Type Quantity
601 W51 Unit Testing Developer 5
602 W51 System Testing Test Analyst 10
603 W51 Performance Testing Sr. Performance
Test Analyst
2
604 W51 Security testing Security expert 2
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources -> Outputs-> RBS
Resource
Breakdown
Structure
Hierarchical representation of resources by category and type.
RBS is useful for organizing & reporting project schedule data
with resource utilization information.
Construction Project
Labor
Managers
Manager1
Manager2
Workers
Worker1
Worker2
Worker3
Material
Building
Office
setup
Equipment
Desktop
Laptop
Printer
Projector
Supplies
Printer
Cartridges
Papers
Stationary
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources->Outputs->Proj. doc. update
Project
Documents
update
• Activities identified during process
Activity
lists
• Attribute for new activities
• Change in attributes of older activities
Activity
attributes
• Resource related Risk
Risk
register
• Update Project & recourse calendar
Resource
Calendars
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources -> Data Flow Diagram
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
6.4 Estimate Activity resources -> Review
Why to estimate activity resources?
What is Alternative Analysis?
What is published estimation data?
What is Bottom up estimation?
What is resource breakdown structure?
What is PMIS?
6.4 I T&T O
By: Nemanand Bobade (nmbobade@gmail.com)
Learn Project Management & prepare for PMP exam:
• Learn visually
• Detailed coverage of all PMP concepts
• Sample Questions
6.4 I T&T O
By: Anand Bobade (nmbobade@gmail.com)
To Learn Project Management Contact Anand Bobade (055 5932004)
•nmbobade@gmail.com
•https://ae.linkedin.com/in/anandbobade
•http://www.slideshare.net/anandbobade
•Conduct Online training, Corporate Training, evening & weekend workshops.
Free learning resources
By: Anand Bobade (nmbobade@gmail.com)
Questions -1
In which of the following project phases is the project schedule developed?
A. Conceptual
B. Planning
C. Implementation
D. Design
B. Planning
- Refer Process and Knowledge area mapping on Page 61, PMBOK 5
By: Anand Bobade (nmbobade@gmail.com)
Questions -2
The process of establishing the policies, procedures and documentation for planning,
developing, managing, executing and controlling the project schedule is known as
A. Plan Schedule Management
B. Control Schedule
C. Develop Schedule
D. Sequence Activities
A. Plan Schedule Management
See Plan Schedule Management definition on Page 141, PMBOK 5
By: Anand Bobade (nmbobade@gmail.com)
Questions -1
When sequencing project activities in the schedule, all the following are true
EXCEPT—
A. There may be scheduled dates for specific milestones
B. Every activity is connected to at least one predecessor and at
least one successor
C. Lead or lag time may be required
D. Necessary sequencing of events may be described by the
activity attributes
B - Every activity is connected to at least one predecessor and at least one successor
The sequence activity process involves identifying and documenting relationships among the project
activities. However, the last activity or milestone are not connected to at least one successor. [Planning]
PMI®, PMBOK® Guide, 2013, 156
By: Anand Bobade (nmbobade@gmail.com)
Questions -2
The risk register may need to be updated as an output of which following process:
A. Define activities
B. Sequence activities
C. Estimate activity resources
D. Control schedule
B - Sequence activities
The risk register may require updates in both the sequence activities and develop schedule
processes. In the sequence activity process, the activity lists and activity attributes may need
updates as well. [Planning]
By: Anand Bobade (nmbobade@gmail.com)
Questions -1
The inputs used in the Define Activities process includes below except
A. Scope baseline
B. Schedule Management plan
C. OPA
D. Milestone list
D - See Figure 6-1, Page 143, PMBOK 5
By: Anand Bobade (nmbobade@gmail.com)
Questions -2
Which of the following is tool & techniques of Define Activities process
A. Rolling wave planning
B. Analytical tools
C. Meeting
D. Scheduling techniques
A
By: Anand Bobade (nmbobade@gmail.com)
Questions -1
You are in the early stages of a project to manufacture disposable medical devices. You need a
number of engineers including ones with specialties in mechanical, environmental, and systems
engineering. In the early stages of this project, your resource pool includes a large number of
both junior and senior engineers in the various specialty areas. However, as the project
progresses
A. Fewer systems engineers will be needed
B. The resource pool can be limited to those people who are knowledgeable
about the project
C. To complete the project on time, you will continue to require access to a
large number of engineers in their specialty areas
D. You will only need junior level engineers as the senior level people can be
used early in the project to mentor and train them
B - The resource pool can be limited to those people who are knowledgeable about the project
Resource calendars are an input to the estimate activity resource process and to the estimate activity durations process.
They are used to estimate resource use. Early in a project, the resource pool might include people at different levels of
expertise in large numbers, but as the project progresses, the resource pool then can be limited to those people who are
knowledgeable about the project because of their work on it. [Planning] - PMBOK® Guide, 2013, 163, 167–168
By: Anand Bobade (nmbobade@gmail.com)
Questions -2
You are managing a project that will use a virtual team with team members on three different
continents. Your company is looking to use the virtual team to provide a lower cost product by
using resources in countries that have a favorable exchange rate to that of your country. To assist
in this process as you estimate resource requirements, it is helpful to consider
A. Bottom-up estimating
B. Published estimating data
C. Analogous estimating
D. Reserve analysis
B - Published estimating data
In estimating activity resources, published estimating data is a tool and technique that is used as many
companies routinely publish updated production rates and unit costs of resources. This includes labor
trades, material, and equipment for different countries and geographic locations in these countries.
[Planning] - PMBOK® Guide, 2013, 164

More Related Content

What's hot

Project scope management
Project scope managementProject scope management
Project scope managementJody R Flower
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CycleAnand Bobade
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Project scope management
Project scope managementProject scope management
Project scope managementAnit Roy
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementAnand Bobade
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHICJonathan Donado
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 
Project Management
Project ManagementProject Management
Project ManagementMark Roman
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 

What's hot (20)

Project scope management
Project scope managementProject scope management
Project scope management
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
Project scope management
Project scope managementProject scope management
Project scope management
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality Management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 
Project Management
Project ManagementProject Management
Project Management
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 

Similar to PMP Chap 6 - Project Time management - Part1

PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementAnand Bobade
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material Abdel Rahman okasha
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planAnand Bobade
 
Project management slide - Introduction
Project management slide - IntroductionProject management slide - Introduction
Project management slide - IntroductionAlbert Poghosyan
 

Similar to PMP Chap 6 - Project Time management - Part1 (20)

PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
Chap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule ManagementChap 6.1 Plan Schedule Management
Chap 6.1 Plan Schedule Management
 
PMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time managementPMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time management
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
Project management slide - Introduction
Project management slide - IntroductionProject management slide - Introduction
Project management slide - Introduction
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 

More from Anand Bobade (20)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 

Recently uploaded

How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesMassimo Canducci
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisCIToolkit
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsCIToolkit
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsCIToolkit
 
Yokoten: Enhancing Performance through Best Practice Sharing
Yokoten: Enhancing Performance through Best Practice SharingYokoten: Enhancing Performance through Best Practice Sharing
Yokoten: Enhancing Performance through Best Practice SharingCIToolkit
 
Mastering Management Insights from First Break All the Rules.pptx
Mastering Management Insights from First Break All the Rules.pptxMastering Management Insights from First Break All the Rules.pptx
Mastering Management Insights from First Break All the Rules.pptxAS Design & AST.
 
Leveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementLeveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementCIToolkit
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsCIToolkit
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationPMIUKChapter
 
Critical thinking categorical syllogism pptx
Critical thinking categorical syllogism pptxCritical thinking categorical syllogism pptx
Critical thinking categorical syllogism pptxcalinagavris17
 
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...dsnow9802
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfcoolsnoopy1
 
Flowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of FlowchartsFlowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of FlowchartsCIToolkit
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBusiness of Software Conference
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Designshakkardaddy
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingCIToolkit
 

Recently uploaded (16)

How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human Resources
 
Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram Analysis
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data Insights
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data Sets
 
Yokoten: Enhancing Performance through Best Practice Sharing
Yokoten: Enhancing Performance through Best Practice SharingYokoten: Enhancing Performance through Best Practice Sharing
Yokoten: Enhancing Performance through Best Practice Sharing
 
Mastering Management Insights from First Break All the Rules.pptx
Mastering Management Insights from First Break All the Rules.pptxMastering Management Insights from First Break All the Rules.pptx
Mastering Management Insights from First Break All the Rules.pptx
 
Leveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementLeveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous Improvement
 
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and ThoughtsMind Mapping: A Visual Approach to Organize Ideas and Thoughts
Mind Mapping: A Visual Approach to Organize Ideas and Thoughts
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentation
 
Critical thinking categorical syllogism pptx
Critical thinking categorical syllogism pptxCritical thinking categorical syllogism pptx
Critical thinking categorical syllogism pptx
 
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdf
 
Flowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of FlowchartsFlowcharting: The Three Common Types of Flowcharts
Flowcharting: The Three Common Types of Flowcharts
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-Making
 

PMP Chap 6 - Project Time management - Part1

  • 1. By: Nemanand Bobade (nmbobade@gmail.com) Chapter 6 : Project Time Management (Part 1) Plan Schedule management Define Activities Sequence Activities Estimate Activity resource Estimate Activity Duration Develop Schedule Control Schedule Planning Monitoring & Controlling Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions
  • 2. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management L : Lesson Introduction Time Management Processes Processes in details: Review of all processes Exam Essentials & Tips Self Assessment Additional Resources P1 P2 P3 P4 P5 P6 P7
  • 3. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management-> Introduction Provide scheduling framework. Develop a schedule. Finalize deliverable delivery dates. Prepare base for budgeting. Control project schedule.
  • 4. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.1 Plan Schedule management: The process of establishing policies, procedures, & documentation for planning, developing, managing, executing, & controlling the project schedule 6.2 Define Activities: The process of identifying and documenting the specific actions to be performed to produce the project deliverables. 6.3 Sequence Activities: The process of identifying and documenting relationships among the project activities.
  • 5. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.4: Estimate Activity resource: Estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity 6:5 Estimate Activity Duration: Estimating the number of work periods needed to complete individual activities with estimated resources 6:6 Develop Schedule: Analysing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model 6.7 Control Schedule: Monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
  • 6. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule management Plan Schedule Management Definition Plan Schedule management : ITTO What is Analytical Techniques? What is inside Schedule Management plan? Data flow diagram Review Guidelines for exam questions Self Assessment 6.1 I T&T O
  • 7. By: Anand Bobade (nmbobade@gmail.com) Planning Developing Managing Executing Controlling Establishing policies, procedures & documentation for planning, developing, managing, executing & controlling project schedule. Provide guidance & direction on how the project schedule will be managed. Establishing 6.1 Plan Schedule management -> Definition Project Schedule 6.1 I T&T O
  • 8. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management Inputs (4) • Project management plan • Project charter • Enterprise environmental factors • Organizational process assets Tools & Techniques (3) • Expert judgment • Analytical Technique • Meetings Outputs (1) • Schedule Management plan 6.1 I T&T O
  • 9. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Input PMP Project Charter EEF OPA 6.1 I T&T O
  • 10. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Input PMP PMP contains the information about project execution and control. Other Subsidiary plans. Scope baseline – Project scope statement, WBS, WBS dictionary. Other information – scheduling cost, risk & communication related decisions. 6.1 I T&T O
  • 11. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Input Project Charter Summary Milestone Schedule. Project approval requirements. 6.1 I T&T O
  • 12. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Input -> EEF EEF Organizational culture & structure. Resource availability & skills. Published commercial data - resource productivity. Scheduling tool. Organizational work authorization systems. 6.1 I T&T O
  • 13. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management-> Tools & Techniques Expert Judgment Analytical Techniques Meetings 6.1 I T&T O
  • 14. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Manag.->T&T->Expert Judgment Expert Judgment Can suggest scheduling methods & solutions. Expertise in project execution in the organization (one who already executed project). Historical information. E.g., Technology Lead worked on various software project in the organization. 6.1 I T&T O
  • 15. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Manag.->T&T->Analytical Techniques Analytical Techniques Choosing option for estimating, optimizing & controlling schedule. Scheduling Methodology Scheduling techniques Resource optimizing techniques Schedule performance review Resource Levelling: balance demand for resources with supply. Resource Smoothing: Adjusts schedule activities. Crashing: Shorten duration by adding resources. Fast tracking: Activities done in sequence are performed in parallel 6.1 I T&T O
  • 16. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Manag.->T&T->Analytical Techniques Schedule MP - Details the way to fast track or crash the project. Organization Policies & procedure may influence selection of scheduling techniques. Analytical Techniques Rolling wave planning Leads & Lags Alternative Analysis Methods for reviewing schedule performance 6.1 I T&T O
  • 17. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Manag.->T&T->Meetings Meetings Project team may attend meetings. Project Manager Technical Leads Selected team members Functional Managers Any one with estimation & scheduling related responsibilities should attend meetings. Discuss & agree how Resource optimizing techniques Discuss & agree on Scheduling Methodology, Scheduling techniques 6.1 I T&T O
  • 18. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Output->SMP Schedule Management plan 6.1 I T&T O
  • 19. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Output Schedule Management plan Establishes criteria & activities for developing, monitoring & controlling project schedule. Project Schedule Model Development & maintenance (Gantt chart). Level of accuracy (High level or detailed) Unit of measure (Hours, days or weeks) Schedule Control thresholds ( E.g., what is acceptable delay ) Rules of Performance measurement. Scheduling/estimating techniques to be used on Project. Process descriptions. Reporting formats (Performance reports, variance reports etc) 6.1 I T&T O
  • 20. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Output Schedule Management plan • Predicted vs actuals • Earned value management (EVM) rules. • Physical measurement rules. Rules of performance measurement: • Rules for establishing percentage complete. • Rules for Control accounts. • Earned value measurement techniques (Baselines, fixed- formula, % complete, etc.) Ex: Schedule management plan may specify: 6.1 I T&T O
  • 21. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Data Flow Diagram 6.1 I T&T O
  • 22. By: Anand Bobade (nmbobade@gmail.com) 6.1 Plan Schedule Management -> Review Why schedule Management is important? What is schedule management plan? What are the components of schedule management plan? What is use of analytical technics? 6.1 I T&T O
  • 23. By: Nemanand Bobade (nmbobade@gmail.com) Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions 6.1 I T&T O
  • 24. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities Define activity Process definition Define Activity: ITTO What is Decomposition? What is Rolling wave planning? Data flow diagram Review Guidelines for exam questions Self Assessment 6.2 I T&T O
  • 25. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.1 Plan Schedule management: The process of establishing policies, procedures, & documentation for planning, developing, managing, executing, & controlling the project schedule 6.2 Define Activities: The process of identifying and documenting the specific actions to be performed to produce the project deliverables. 6.3 Sequence Activities: The process of identifying and documenting relationships among the project activities.
  • 26. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.4: Estimate Activity resource: Estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity 6:5 Estimate Activity Duration: Estimating the number of work periods needed to complete individual activities with estimated resources 6:6 Develop Schedule: Analysing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model 6.7 Control Schedule: Monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan.
  • 27. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Introduction Consider Project to construct 50 KM water Pipeline in difficult terrain. It is huge task & will involve lot of planning & coordination. How do we execute this? Start identifying all activities of each work package in WBS. Also, think about the key milestones. 6.2 I T&T O
  • 28. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Definition Identifying & Documenting Specific Actions Produce Identifying & documenting specific actions to be performed to produce project deliverables. Break work packages into activities that provide a basis for estimating, scheduling, executing, monitoring & controlling the project work. Project Deliverables 6.2 I T&T O
  • 29. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> ITTO Inputs • Schedule management plan • Scope baseline • Enterprise environmental factors • Organizational process assets Tools & Techniques • Rolling wave planning • Expert judgment Outputs • Activity list • Activity attributes • Milestone list 6.2 I T&T O
  • 30. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Input Schedule Manag. plan Scope Baseline EEF OPA 6.2 I T&T O
  • 31. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Input -> SMP Schedule Manag. plan Prescribed level of details necessary to manage the work. Guideline to define activities (e.g., max duration) Organizational Policies & procedure. 6.2 I T&T O
  • 32. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Input -> Scope Baseline Scope Baseline Project scope statement: • Scope, major deliverables. • Assumptions & constraints. WBS: List of all work packages. This is the key input. Activities under each work package will be identified & listed. WBS dictionary: Detailed deliverable & scheduling information about each WBS. 6.2 I T&T O
  • 33. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Input->EEF EEF Organizational culture & structure. published Commercial information. Project Management Information System (PMIS) 6.2 I T&T O
  • 34. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Input-> OPA OPA Lessons learned about activity list. Templates with standard activity list. Activity list from Historical project data. Activity related policies, procedures & guidelines 6.2 I T&T O
  • 35. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Tools & Techniques Decomposition Rolling Wave planning Expert Judgment 6.2 I T&T O
  • 36. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Tools & Techniques->Decomposition Decomposition Technique used for dividing & subdividing project scope & deliverables in smaller & more manageable parts. Activities represent efforts needed to complete work package. It define final output as activities rather than deliverables. Oil & Gas Pipeline Project Project Management Project Plan Scope Budget Procurement Metal Equipment Resources Build pipeline Foundation work Equipment erection Pipe joining Sensor installations ------> Activity List Mark the layout Get the Machines Dig the area Level the area Prepare foundation 6.2 I T&T O
  • 37. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> T & T -> Rolling wave planning Rolling Wave planning An iterative planning technique in which: work to be accomplished in near term is planned in details. while work in future is planned at a higher level. Form of Progressive Elaboration Planning packages can be created when detailed information is not available. 6.2 I T&T O CRM Project Initiation Project charter Feasibility Study Business Case Stakeholder List Study Business Requirement Document Reporting Requirements System Requirements Vendor selection Integration Requirements Design & Build System Design High level Design Low level Design System Build Build module1 Build Module2 Build Module3 Integration Build Reports Build Test System Testing Integration Testing User Acceptance Testing Security Testing Performance Testing Operate Training Go-live Handover Training Contract Closure Project closure Work packages can be decomposed further when sufficient information is available.
  • 38. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> T & T -> Rolling wave planning CRM Project Initiation Project charter Feasibility Study Business Case Stakeholder List Study Business Requirement Document Reporting Requirements System Requirements Vendor selection Integration Requirements Design & Build System Design High level Design Low level Design System Build Build module1 Build Module2 Build Module3 Integration Build Reports Build Test System Testing Integration Testing User Acceptance Testing Security Testing Performance Testing Operate Training Go-live Handover Training Contract Closure Project closure Jan Feb March Apr May 6.2 I T&T O
  • 39. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities->Tools & Techniques->Expert Judgment Expert Judgment Person experienced & skilled in developing detailed • Project scope statement • WBS Who's should define activities: • Person responsible to execute them. 6.2 I T&T O
  • 40. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Outputs Activity list Activity attributes Milestone list 6.2 I T&T O
  • 41. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Outputs -> Activity List Activity list A list of activities that will be performed on project. Every work package in the WBS is detailed to create activity list. It is a list with unique id, WBS reference & description of each activity. Complete activity list helps in accurate estimation & project schedule. Activity ID WBS Id Name Description 501 W50 Mark the layout 502 W50 Get the Machines 503 W50 Dig the area 504 W50 Level the area 505 W50 Prepare foundation 6.2 I T&T O
  • 42. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Outputs ->Activity Attributes Activity attributes When Completed, they may include following attributes: Information available during the initial stages of the project: Activity identifier (ID) WBS ID Activity label or name Activity description Predecessor activities Successor activities Logical relationships Resource requirements Imposed dates Assumptions Person responsible Geographic area or place Provide more information such as predecessors, successors, logical relationships, resource requirements etc for each identified activity. 6.2 I T&T O
  • 43. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Outputs ->Milestone List Milestone list A milestone is a significant point in the project. Used for setting schedule goals & monitoring progress. May be mandatory (contractual), or just for guidance. Zero duration task with no. resources 6.2 I T&T O
  • 44. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Data Flow Diagram 6.2 I T&T O
  • 45. By: Anand Bobade (nmbobade@gmail.com) 6.2 Define Activities -> Review Defining activities by Decomposing work package Scope baseline is the main input What is decomposition? What is rolling wave planning? What is Activity list? What is Activity Attributes? 6.2 I T&T O
  • 46. By: Nemanand Bobade (nmbobade@gmail.com) Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions 6.2 I T&T O
  • 47. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities Sequence activity Process definition Sequence Activity: ITTO Why to determine Activity dependencies? What is PDM? What is logical Relationship between activities? Data flow diagram Review Guidelines for exam questions Self Assessment 6.3 I T&T O
  • 48. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.1 Plan Schedule management: The process of establishing policies, procedures, & documentation for planning, developing, managing, executing, & controlling the project schedule 6.2 Define Activities: The process of identifying and documenting the specific actions to be performed to produce the project deliverables. 6.3 Sequence Activities: The process of identifying and documenting relationships among the project activities. 6.3 I T&T O
  • 49. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.4: Estimate Activity resource: Estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity 6:5 Estimate Activity Duration: Estimating the number of work periods needed to complete individual activities with estimated resources 6:6 Develop Schedule: Analysing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model 6.7 Control Schedule: Monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. 6.3 I T&T O
  • 50. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->Introduction Consider same example about constructing pipeline. We will need to sequence activities . How? Identify relationship between activities. Create the logical relationship. Execute them in same order. 6.3 I T&T O
  • 51. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->Definition The process of identifying & documenting relationships among project activities. Project Activities Identifying & Documenting Relationship Defines logical sequence of work to obtain greatest efficiency within project constraints. 6.3 I T&T O
  • 52. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities Inputs • Schedule management plan • Activity list • Activity attributes • Milestone list • Project scope statement • EEF • OPA Tools & Techniques • Precedence diagramming method (PDM) • Dependency determination • Leads and lags Outputs • Project schedule network diagrams • Project documents updates 6.3 I T&T O
  • 53. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Input Schedule Management plan Activity list Activity Attributes Milestone list Project Scope statement EEF OPA 6.3 I T&T O
  • 54. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Input Identifies scheduling method & tools to be used for project, which will guide on sequencing activities. All schedule activities required which are to be sequenced. Dependencies & constraints can influence sequencing. Describes necessary sequence of events or defined predecessor & successor activities. It will have schedule date for specific milestone, which may influence the way activities are sequenced. 6.3 I T&T O
  • 55. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Input Scope statement contains product scope description that may effect activity sequencing. Deliverables, constraints, assumption also may effect sequencing Govt. or Industry standards, PIMS, scheduling tool, Work authorization system Scheduling methodology, activity planning related policies, procedures guidelines. 6.3 I T&T O
  • 56. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Tools & Techniques Dependency determination Precedence diagramming method (PDM) Leads and lags 6.3 I T&T O
  • 57. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->T&T->Dependency Determination Dependency determination Types: Mandatory dependency Discretionary dependency External dependency Internal dependency Determine how one activity is dependent of another 6.3 I T&T O
  • 58. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->T&T->Dependency Determination Dependency determination Requirements Documentation Client Approval • Legally or contractually required • Inherent in the nature of work Mandatory dependency (Hard logic) Lay Building Foundation Construct Floor 6.3 I T&T O
  • 59. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->T&T->Dependency Determination Dependency determination Develop Module A Develop Module C • There could be more than one way to define the sequence between 2 activities. • Based on best practices. • Defined by project team (Flexible) Discretionary dependency (Preferred or preferential or soft logic) 6.3 I T&T O Develop Module A Develop Module B If above sequence of module development was decided by project team; you can always change it to below sequence, if required.
  • 60. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->T&T->Dependency Determination Dependency determination Delivery of Equipment Start work Vendor team on boarding Start work • Relationships between project and non- project activities • Activities are done by external people. • Outside project control. External dependencies 6.3 I T&T O
  • 61. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->T&T->Dependency Determination Dependency determination Develop System by coding team Test System by software testing team build house by Contruction team Paint & decorate house by interior design team • Precedency relationship defined between two activities. • Done by internal team member. • Inside project teams control. Internal dependencies 6.3 I T&T O
  • 62. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Tools & Techniques -> PDM Precedence diagramming method (PDM) Method of constructing a project schedule network diagram, to represent activities & connects them with arrows that show dependencies. Activities are represented by boxes. Arrows shows relationships between activities. 6.3 I T&T O
  • 63. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Tools & Techniques -> PDM How to develop schedule network diagram. Activity Activity Description Duration (days) Predecessor A Collect Requirement 50 - B System Design 25 A C Build Module 1 40 B D Build Module 2 50 C E Build Module 3 10 B F Build Module 4 15 E G Build Module 5 30 B H System Testing 25 D,F,G 6.3 I T&T O
  • 64. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Tools & Techniques -> PDM Collect Requirements (A - 50days) Start System Design (B - 20d) Build module 1 (C - 40 day) Build module 2 (D - 50 day) Build module 3 (E - 10 day) Build module 5 (G - 30 day) Testing (H-25 days) Build module 4 (F - 15 day) End Acti vity Activity Description Duratio n (days) Predece ssor A Collect Requirement 50 - B System Design 25 A C Build Module 1 40 B D Build Module 2 50 C E Build Module 3 10 B F Build Module 4 15 E G Build Module 5 30 B H System Testing 25 D,F,G • = A->B->C->D->H = 50+20+40+50+25 = 185Path1 • = A->B->E->F->H = 50+20+10+15+25 = 120Path2 • = A->B->G->H = 50+20+30+25 = 125Path3 6.3 I T&T O
  • 65. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Tools & Techniques -> PDM Logical Relationships Precedence diagramming method (PDM) • Task B can not start until Task A finishes Finish to start - FS • Task B can not start until Task A starts Start to Start - SS • Task B can finish until Task A finishes Finish to Finish - FF • Task B can not finish until Task A starts Start to Finish - SF 6.3 I T&T O
  • 66. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Tools & Techniques -> PDM Wash a Car Dry a Car Mix Concrete Prepare Concrete floor • Drying the car can not start until Car is washedFS • Concrete flooring cant not be started until you start mixing concrete SS Precedence diagramming method (PDM) 6.3 I T&T O
  • 67. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Tools & Techniques -> PDM Match in progress Broadcasting Shift Finish for Guard1 Shift start for Guard2 • Broadcasting of a match cannot finish until the match is finished FF • start of the new shift of the security guard signal the finish shift of the current security guard SF Precedence diagramming method (PDM) 6.3 I T&T O
  • 68. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> T&T -> Leads & Lags Business Requirement (BRS) System Requirement (SRS) Sign Contract Team On- board Lead 1 week Lag 3 week Lead: It is amount of time where successor activity can be advanced w.r.t. predecessor activity. Lag: It is amount of time whereby a successor activity will be delayed w.r.t. a predecessor activity. Leads & lags 6.3 I T&T O Business Requirement (BRS – 4 weeks) System Requirement (SRS – 4 weeks) W1 W2 W3 W4 W5 W6 W7 W8 W1 W2 W3 W4 W5 W6 W7 W8 Sign Contract Team On- board
  • 69. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> T&T -> Leads & Lags Coding (6 week) Peer Review (3 week) FS : Lead – 2 week Coding (6 week) Peer Review (3 week) SS : Lag – 3 week Coding (6 week) Peer Review (3 week) FF : Lag – 3 week Both gives same output in terms of schedule This is more appropriate as Coding finish means coding & Peer review has to finish. Leads & lags Lead is often represented as negative value for Lag in scheduling software 6.3 I T&T O
  • 70. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Output Project Schedule Network diagram Project Documents update 6.3 I T&T O
  • 71. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->Output->Proj. Schedule ND It is a graphical representation of logical relationship between activities. Shows dependencies among schedule activities. Project Schedule Network diagram 6.3 I T&T O
  • 72. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->Output->Proj. Schedule ND Schedule Network template: Will be generated once all activities are sequenced & relationship/dependencies are set. Templates can be used from similar projects. Developed by accumulating lessons learned. Used for entire project or portion of a project. Project Schedule Network diagram 6.3 I T&T O
  • 73. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Output->Project Doc. updates Project Documents update • New activities identified during sequencingActivity lists • New attribute identified • Change in attributes of older activities Activity attributes • Risk identified due to dependenciesRisk register • Any change in scheduling process Schedule management plan 6.3 I T&T O
  • 74. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities->Output->Data Flow Diagram 6.3 I T&T O
  • 75. By: Anand Bobade (nmbobade@gmail.com) 6.3 Sequence Activities -> Review Why sequencing is important? Why are different types of activity dependencies? What is PDM? What are different logical Relationship? What is Project schedule network diagram? 6.3 I T&T O
  • 76. By: Nemanand Bobade (nmbobade@gmail.com) Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions 6.3 I T&T O
  • 77. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resource Estimate Activity resource Process definition Estimate Activity resource: ITTO Why is Alternative Analysis? What is Bottom up estimation? What is resource breakdown structure? Data flow diagram Review Guidelines for exam questions Self Assessment 6.4 I T&T O
  • 78. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.1 Plan Schedule management: The process of establishing policies, procedures, & documentation for planning, developing, managing, executing, & controlling the project schedule 6.2 Define Activities: The process of identifying and documenting the specific actions to be performed to produce the project deliverables. 6.3 Sequence Activities: The process of identifying and documenting relationships among the project activities. 6.4 I T&T O
  • 79. By: Anand Bobade (nmbobade@gmail.com) 6. Project Time Management 6.4: Estimate Activity resource: Estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity 6:5 Estimate Activity Duration: Estimating the number of work periods needed to complete individual activities with estimated resources 6:6 Develop Schedule: Analysing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model 6.7 Control Schedule: Monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. 6.4 I T&T O
  • 80. By: Anand Bobade (nmbobade@gmail.com) 6.4: Estimate Activity resource -> Introduction Human resources Material Equipment Supplies 6.4 I T&T O
  • 81. By: Anand Bobade (nmbobade@gmail.com) Estimating type & quantities of material, human resources, equipment or supplies required to perform each activity. Type & Quantities Material Human resources Equipment Supplies Estimating Project Activities Perform Develop more accurate cost and duration estimates. 6.4: Estimate Activity resource -> Definition 6.4 I T&T O
  • 82. By: Anand Bobade (nmbobade@gmail.com) 6.4: Estimate Activity resource -> Key Factors Complexity Resource Skills Resource availability History of performing similar task 6.4 I T&T O
  • 83. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources Inputs • Schedule management plan • Activity list • Activity attributes • Resource calendars • Risk register • Activity cost estimates • EEF • OPA Tools & Techniques • Expert judgment • Alternative analysis • Published estimating data • Bottom-up estimating • Project management software Outputs • Activity resource requirements • Resource breakdown structure • Project documents updates 6.4 I T&T O
  • 84. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Resources -> Input Schedule Management Plan Activity list Activity Attributes Resource Calendars Risk Register Activity Cost estimates EEF OPA 6.4 I T&T O
  • 85. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Resources -> Input->SMP Schedule Management plan It identifies scheduling method & tools to be used for the project, which will guide how to estimate activity resources. Project Schedule Model Development Level of accuracy Unit of measure (Hour, Day etc) Control thresholds 6.4 I T&T O
  • 86. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Resources -> Input-> Activity List Activity list A list of all schedule activities to estimate activity resources. Activity ID WBS Id Name Description 501 W50 Compare Furniture brands 502 W50 Find showrooms 503 W50 Get Quotes 504 W50 Compare Quotes 6.4 I T&T O
  • 87. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Resources -> Input-> Activity Attributes Activity attributes Activity description Predecessor activities Successor activities Logical relationships Resource requirements Imposed dates Assumptions Person responsible Geographic area or place Provide more information such as predecessors, successors, logical relationships, resource requirements etc for each identified activity. Attributes are updated during schedule creations, when completed they may include following attributes: 6.4 I T&T O
  • 88. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Resources -> Input-> Resource Calendar Identifies working days & shifts on which each specific resource is available. Details about when & how long identified project resource will be availableResource Calendars • Resource may be material, human resources, equipment etcRemember: 6.4 I T&T O
  • 89. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->Input->Risk Register Risk events may impact resource selection and availability. Risks related to activity sequencing, dependencies. It may lead to alternative analysis. Risk Register 6.4 I T&T O
  • 90. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->Input->Activity Cost Estimates Activity Cost Estimates Provides probable costs required to complete activities / project work. (summary or detail) Resource & cost estimation is cyclic process. Cost constraints may lead to selection of certain type of resources. Estimate Cost (Project Cost Manag.) Estimate Activity resources-Resource type / Quantity; make or buy / Manual or automated can be decided based on cost constraints. 6.4 I T&T O
  • 91. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Resources -> Input->OPA OPA Staffing related Policies and procedures. Procurement (rental and purchase) related Policies and procedures. Historical information – types/quantities of resources used for similar work on previous projects. 6.4 I T&T O
  • 92. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Resources -> Input->EEF EEF Resource location availability and skills. 6.4 I T&T O
  • 93. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources -> Tools & Techniques Expert Judgement Alternative Analysis Published Estimating data Bottom up estimates Project Management Software 6.4 I T&T O
  • 94. By: Anand Bobade (nmbobade@gmail.com) Mr. Expert 6.4 Estimate Activity resources -> T&T -> Expert Judgment Expert Judgement Can help in choosing right resource. Identify activity resource requirement. Can perform or contribute in estimating & alternative analysis. Specialized knowledge in resource planning & estimating can provide such expertise. 6.4 I T&T O
  • 95. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->T&T->Alternative Analysis Any group or person with specialized knowledge in resource planning and estimating can provide such expertise Alternative Analysis Many schedule activities have alternative methods of accomplishment Various levels of resource capability or skills. Different size or type of machines. Different tools (hand versus automated) Make- rent-or-buy decisions regarding the resource. Analyses focus on: 6.4 I T&T O
  • 96. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->T&T->Alternative Analysis Any group or person with specialized knowledge in resource planning and estimating can provide such expertise 2 Example: Road construction work - Expert helping PM identifying resource requirements through alternative analysis Build Manually • Advantage: Less cost • Disadvantage: More human resources & Slow delivery. Use machines • Advantages: Faster delivery & Less human resources. • Disadvantages: More cost, Resource capabilities, Machines availability etc Alternative Analysis 1 6.4 I T&T O
  • 97. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->T&T-> Alternative Analysis Alternative Analysis Example: Cost, Quality & Risk • Manual work may cost less as cheap human resources are available but may need more time to complete project. Cost • Machine developed road will give better quality hence maintenance cost will be less. Also, delivery will be faster. Quality: • Machines may not be available. Bringing machines to the location may not be possible. Human resource to operate may not be available. Risk: 6.4 I T&T O
  • 98. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->T&T->Published est. data Any group or person with specialized knowledge in resource planning and estimating can provide such expertise Rates Unit Cost Labour trade Material Equipm -ent Published Estimating Data Production rates & unit costs of resources, material, and equipment. Data from different countries and geographical locations. 6.4 I T&T O
  • 99. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->T&T-> Bottom up estimate Bottom up Estimate Estimating resources or cost by aggregating estimates of lower-level components of WBS. Activities are broken into smaller activities which can be estimated. There resource needs are estimated. Resources are assigned to each activity. These estimates are aggregated into a total quantity of resources. 6.4 I T&T O
  • 100. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->T&T-> PM Software Any group or person with specialized knowledge in resource planning and estimating can provide such expertise Project Management Software Optimizing Resource utilization Resource breakdown structure Resource availability Resource rate Resource calendar Project Management Software has capability to: Plan, organize & manage the resource pools. Develop resource estimates Can automatically resolve scheduling conflicts. Can help perform workload analysis. Can help optimize resource utilization. 6.4 I T&T O
  • 101. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources -> Outputs Activity resource requirements Resource breakdown structure Project Documents update 6.4 I T&T O
  • 102. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity Res.->Outputs->Activity Resource Req Activity Resource Requirements The types and quantities of resources required for each activity in a work package. Aggregated to determine the estimated resources for each work package and each work period. Resource Type/ Activity Resource Quantity/ Activity Resource for Work Package 6.4 I T&T O Activity ID WBS Id Name Resource Type Quantity 601 W51 Unit Testing Developer 5 602 W51 System Testing Test Analyst 10 603 W51 Performance Testing Sr. Performance Test Analyst 2 604 W51 Security testing Security expert 2
  • 103. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources -> Outputs-> RBS Resource Breakdown Structure Hierarchical representation of resources by category and type. RBS is useful for organizing & reporting project schedule data with resource utilization information. Construction Project Labor Managers Manager1 Manager2 Workers Worker1 Worker2 Worker3 Material Building Office setup Equipment Desktop Laptop Printer Projector Supplies Printer Cartridges Papers Stationary 6.4 I T&T O
  • 104. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources->Outputs->Proj. doc. update Project Documents update • Activities identified during process Activity lists • Attribute for new activities • Change in attributes of older activities Activity attributes • Resource related Risk Risk register • Update Project & recourse calendar Resource Calendars 6.4 I T&T O
  • 105. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources -> Data Flow Diagram 6.4 I T&T O
  • 106. By: Anand Bobade (nmbobade@gmail.com) 6.4 Estimate Activity resources -> Review Why to estimate activity resources? What is Alternative Analysis? What is published estimation data? What is Bottom up estimation? What is resource breakdown structure? What is PMIS? 6.4 I T&T O
  • 107. By: Nemanand Bobade (nmbobade@gmail.com) Learn Project Management & prepare for PMP exam: • Learn visually • Detailed coverage of all PMP concepts • Sample Questions 6.4 I T&T O
  • 108. By: Anand Bobade (nmbobade@gmail.com) To Learn Project Management Contact Anand Bobade (055 5932004) •nmbobade@gmail.com •https://ae.linkedin.com/in/anandbobade •http://www.slideshare.net/anandbobade •Conduct Online training, Corporate Training, evening & weekend workshops. Free learning resources
  • 109. By: Anand Bobade (nmbobade@gmail.com) Questions -1 In which of the following project phases is the project schedule developed? A. Conceptual B. Planning C. Implementation D. Design B. Planning - Refer Process and Knowledge area mapping on Page 61, PMBOK 5
  • 110. By: Anand Bobade (nmbobade@gmail.com) Questions -2 The process of establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule is known as A. Plan Schedule Management B. Control Schedule C. Develop Schedule D. Sequence Activities A. Plan Schedule Management See Plan Schedule Management definition on Page 141, PMBOK 5
  • 111. By: Anand Bobade (nmbobade@gmail.com) Questions -1 When sequencing project activities in the schedule, all the following are true EXCEPT— A. There may be scheduled dates for specific milestones B. Every activity is connected to at least one predecessor and at least one successor C. Lead or lag time may be required D. Necessary sequencing of events may be described by the activity attributes B - Every activity is connected to at least one predecessor and at least one successor The sequence activity process involves identifying and documenting relationships among the project activities. However, the last activity or milestone are not connected to at least one successor. [Planning] PMI®, PMBOK® Guide, 2013, 156
  • 112. By: Anand Bobade (nmbobade@gmail.com) Questions -2 The risk register may need to be updated as an output of which following process: A. Define activities B. Sequence activities C. Estimate activity resources D. Control schedule B - Sequence activities The risk register may require updates in both the sequence activities and develop schedule processes. In the sequence activity process, the activity lists and activity attributes may need updates as well. [Planning]
  • 113. By: Anand Bobade (nmbobade@gmail.com) Questions -1 The inputs used in the Define Activities process includes below except A. Scope baseline B. Schedule Management plan C. OPA D. Milestone list D - See Figure 6-1, Page 143, PMBOK 5
  • 114. By: Anand Bobade (nmbobade@gmail.com) Questions -2 Which of the following is tool & techniques of Define Activities process A. Rolling wave planning B. Analytical tools C. Meeting D. Scheduling techniques A
  • 115. By: Anand Bobade (nmbobade@gmail.com) Questions -1 You are in the early stages of a project to manufacture disposable medical devices. You need a number of engineers including ones with specialties in mechanical, environmental, and systems engineering. In the early stages of this project, your resource pool includes a large number of both junior and senior engineers in the various specialty areas. However, as the project progresses A. Fewer systems engineers will be needed B. The resource pool can be limited to those people who are knowledgeable about the project C. To complete the project on time, you will continue to require access to a large number of engineers in their specialty areas D. You will only need junior level engineers as the senior level people can be used early in the project to mentor and train them B - The resource pool can be limited to those people who are knowledgeable about the project Resource calendars are an input to the estimate activity resource process and to the estimate activity durations process. They are used to estimate resource use. Early in a project, the resource pool might include people at different levels of expertise in large numbers, but as the project progresses, the resource pool then can be limited to those people who are knowledgeable about the project because of their work on it. [Planning] - PMBOK® Guide, 2013, 163, 167–168
  • 116. By: Anand Bobade (nmbobade@gmail.com) Questions -2 You are managing a project that will use a virtual team with team members on three different continents. Your company is looking to use the virtual team to provide a lower cost product by using resources in countries that have a favorable exchange rate to that of your country. To assist in this process as you estimate resource requirements, it is helpful to consider A. Bottom-up estimating B. Published estimating data C. Analogous estimating D. Reserve analysis B - Published estimating data In estimating activity resources, published estimating data is a tool and technique that is used as many companies routinely publish updated production rates and unit costs of resources. This includes labor trades, material, and equipment for different countries and geographic locations in these countries. [Planning] - PMBOK® Guide, 2013, 164

Editor's Notes

  1. Discrete Efforts: An activity that can be planned and measured and that yields a specific output.  Apportioned Efforts: An activity where an effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts.
  2. http://www.izenbridge.com/blog/what-is-lead-lag/
  3. Discrete Efforts: An activity that can be planned and measured and that yields a specific output.  Apportioned Efforts: An activity where an effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts.
  4. Quantitative assessments of the probable costs required to complete project work. Presented in summary form or in detail. Including all resources Direct labour, materials, equipment, services, facilities, information technology, Special categories :cost of financing (including interest charges), Inflation allowance, exchange rates, Cost contingency reserve. Indirect costs, (if they) can be included at the activity level or at higher levels.