By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
PMP:
Key Exam Concepts Series - Formulas
Crystal Clear understanding of key PMP concepts are
essential to pass the PMP exam. These slide will help you to:
• Visually learn key concepts
• Get deep understand with real world examples
• Sample Questions
Three point
estimation
Earned value
management
Forecasting
PV, FV, NPV,
EMV etc
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Definitions
Three point estimation:
• Accuracy improved by considering estimation uncertainty and
risk using three estimates to define an approximate range for an
activity’s cost.
Earned value management:
• It combines SCOPE, SCHEDULE, & RESOURCE measurements to
assess project performance and progress.
• It integrates the scope ,cost & schedule baselines, to form the
performance baseline
Forecasting:
• Forecasting is the process of predicting future project
performance based the current performance to date.
Miscellaneous formulas:
• Present value, Net Present value, Future value, EMV
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Three point estimation
Three point
estimation
Project schedule is the most important task which
depends on the activity estimation done by team.
Correctness of schedule heavily depends on the
accuracy of the duration of all project activities.
There are three basic techniques most widely used to
estimate activity duration and build the schedule.
Analogous Estimating
Parametric Estimating
Three Point Estimates
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Three point estimation
Weighted
average
• = (O + M + P) / 3Triangular Distribution
• = (O + 4M + P) / 6Beta Distribution or PERT
Accuracy improves by considering estimation uncertainty and risk
using three estimates to define an approximate range for an
activity’s cost.
Optimistic (O): Based on analysis of the best-case
scenario.
Most likely (M) : Based on realistic effort assessment
for required work & any predicted expenses (or ML)
Pessimistic (P). Based on analysis of the worst-case
scenario.
Three point
estimation
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Earned Value Management
It combines SCOPE, SCHEDULE, & RESOURCE
measurements to assess project performance and
progress.
It integrates the scope ,cost & schedule baselines, to
form the performance baseline
• It is authorized budget planned for work to be accomplished. Also known
as Budgeted Cost of Work Scheduled (BCWS). Total of PV (PMB or BAC).
Planned Value
(PV)
• It is actual amount of money spent to date. Also known as Actual Cost of
Work Performed (ACWP)
Actual cost
(AC)
• It is amount of money earned from completed work in a given time.
Earned Value is also known as Budgeted Cost of Work Performed
(BCWP).
Earned value
(EV)
Earned value
management
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Earned Value Management -> Earn Value (EV)
Earned value Calculation based on the Percentage completion
Schedule
Planned Value
(PV)
Percentage
Complete
Actual Cost
(AC)
Earn Value
(EV)
Task1 10,000 50% 6,000 ?
• Only 50% of work completed
• EV = 50% of PV
• EV = 50% of 10,000 = 5,000
Earn
Value
(EV)
Earned value
management
Schedule
Planned Value
(PV)
Percentage
Complete
Actual Cost
(AC)
Earn Value
(EV)
Task1 10,000 100% 9,000 ??
Task2 8,000 75% 6,000 ??
• EV = (100% of 10,000) + (75% of 8,000)
• EV = 10,000 + 6,000 = 16,000
Earn
Value
(EV)
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
• SV is a measure of schedule performance on a project.
• EVM & SV are best used with CPM scheduling & risk manag.
Schedule
variance (CV)
• It measure of cost performance on a project
• It indicates relationship of performance to costs spent
Cost variance
(CV)
• SPI is a measure of progress achieved compared to progress
planned on a project
Schedule
performance
index (SPI)
• CPI is a measure of the value of work completed compared
to the actual cost or progress made on the project.
Cost
performance
index (CPI)
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
• SPI = EV/PV
Schedule
performance
index
• CPI = EV/AC
Cost performance
index
Day1 Day2 Day3 Day4 Day5 Day6 Day7
Planned Budget (PV) 1,000 3,000 5,000 7,000 9,000 11,000 12,000
Actual Cost (AC) 1,100 3,300 6,600 9,900
Earned Value (EV) 1,000 2,000 3,000 4,000
PV: 7,000
BAC: 12,000
AC: 9,900
EV: 4,000
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Cost Variance
Schedule Variance
• SV = EV –PV
Schedule
variance
• CV= EV − ACCost variance
Note: All values are
cumulative
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
Planned
Value (PV)
Earned Value
(EV)
Actual Cost
(AC)
SV =
EV –PV
CV=
EV − AC
SPI =
EV/PV
CPI =
EV/AC
1000 800 1200 -200 -400 0.8 0.67
1500 1200 1800 -300 -600 0.8 0.67
• SV = EV –PVSchedule variance
• SPI = EV/PVSchedule performance index
• CV= EV − ACCost variance
• CPI = EV/ACCost performance index
Indexes
CPI
SPI
> 1
Under budget
Ahead of schedule
< 1
Over Budget
Behind schedule
= 1
On Budget
(planned cost)
On Schedule
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
Indexes
CPI
SPI
> 1
You are earning
more than the
spending. In other
words, you are
under budget.
More work has
been completed
than the planned
work. In other
words, you are
ahead of schedule.
< 1
You are earning
less than the
spending. In other
words, you’re over
budget
Less work is
completed than
the planned work.
In other words,
you are behind
schedule.
= 1
Earning &
spending are
equal. Or
proceeding exactly
as per planned
budget spending
On Schedule
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
EVM -> Variance & Performance Index
• Slowdown
with spending
to try to reach
optimal level
• Try to move
to optimal
otherwise re-
baseline.
• Continue as it
is
• Spend more
to catch up
Under Budget
but behind
schedule
Optimal –
Under Budget
& ahead of
Schedule
Over Budget
but ahead of
schedule
Worst case:
Over Budget
& behind
schedule
CPI >1
[Ahead of
Schedule]
CPI < 1
CPI >1
[Behind
Schedule]
CPI < 1
SPI < 1 [Under Budget] SPI >1
SPI < 1 [Over Budget] SPI >1
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting
Forecasting is used to come up with a future performance or
result of the project.
It gives project sponsors/management an early visibility on
of what may go wrong and help take preventive decision.
Forecasting
Estimate at
Completion (EAC)
Estimate to
Complete (ETC)
To Complete
Performance Index
(TCPI)
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate at Completion (EAC):
Estimate at
Completion
As the project progresses, forecast for estimate at completion
(EAC) may develop based on project performance.
If BAC is no longer viable, forecasted EAC should be considered.
EAC involves making projections of conditions & events in the
project’s future based on current performance & other
knowledge.
Forecasts are generated, updated, and reissued based on work
performance data.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate at Completion (EAC):
Budgeted Rate:
• Absorb the Variance (originally planed budgeted
rate)
Current Progress:
• Take the ongoing project trend (CPI & SPI or only
CPI)
Erroneous scenario:
• Re-estimate the remaining portion
Estimate at
Completion
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate at Completion (EAC):
• EAC = AC + (BAC –EV)
Based on Budgeted
rate
• EAC = AC + (BAC –EV)/CPI = BAC / CPIBased on CPI.
• EAC = AC + [(BAC –EV) / (CPI ×SPI)]Based on SPI & CPI
• EAC = AC + Bottom up estimateErroneous scenario:
EV=2K
AC=3.3K
BAC=12K
ETC=BAC-CV
EAC=AC+ETC
Estimate at
Completion
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Estimate to Complete
ETC tell you, how much money you need to complete
the task at hand.
ETC = BAC - EV
VAC (Variance at completion) shows whether project is
forecasted to finish under or over budget
VAC = BAC – EAC
VAC % = VAC / BAC
Estimate to
Complete
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
TCPI is the measure of the CP that is required to be
achieved in order to meet a specified management goal
Ratio of cost to finish outstanding work to remaining
budget.
TCPI
calculation
Same Budget Use BAC
Revised Budget
Use Forecasted
EAC
If BAC is no longer viable, forecasted EAC should be approved, use in
the TCPI calculation.
TCPI
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
PV: 6,000
BAC: 12,000
AC: 9,000
EV: 4,500
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Day1 Day2 Day3 Day4 Day5 Day6
Planned Budget (PV) Actual Cost (AC) Earned Value (EV)
Fund Remaining
= BAC-AC
= 3,000
Work Remaining
= BAC-EV
= 7,500
Case1: Same Budget
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
PV: 6,000
BAC: 12,000
AC: 9,000
EV: 4,500
-
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Day1 Day2 Day3 Day4 Day5 Day6
Planned Budget (PV) Actual Cost (AC) Earned Value (EV)
Fund Remaining
= EAC-AC
= 9,000
Work Remaining
= BAC-EV
= 7,500
EAC: 18,000
18,000
Case 2: Revised Budget
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
TCPI (based on the BAC):
(BAC –EV)
-----------------------------------------------------------------------------------------------------------
(BAC –AC)
TCPI (based on the EAC):
(BAC –EV)
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
(EAC –AC)
Work Remaining
----------------------
Fund Remaining
To-complete performance
index (TCPI) =
Case1 : TCPI
• (12,000-4,500)/(12,000-9,000)
• 7,500/3,000
• 2.5
Case2: TCPI
• (12,000-4,500)/(18,000-9,000)
• 7,500/9,000
• .83
TCPI
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> TCPI
• Project is in a comfortable position.If TCPI < 1
• Project have to perform with better cost performance than
the past cost performance.If TCPI > 1
• Project can continue with the same cost performance.if TCPI = 1
TCPI
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Forecasting -> Variance Analysis
An important aspect of project cost control includes determining the cause and
degree of variance relative to the cost baseline and deciding whether corrective or
preventive action is required.
Variance analysis is used in EVM for determining cause, impact, and corrective
actions
Cost (CV = EV –AC) Schedule (SV = EV –PV) VAC = BAC –EAC
Compare cost performance over time, schedule activities or work packages
overrunning and under running the budget, and estimated funds needed to
complete work in progress.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formulas
Miscellaneous
Formulas
Net present value (NPV):
• The total present value (PV) of a time series of
cash flows.
• It is a standard method for using the time value
of money to appraise long-term projects
Profit = Revenue – Costs
Profit Margin = Profit / Revenue
Evaluating efficiency of investment. Bigger
ROI is better.
ROI = (Gain – cost) / Gain
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formulas
Miscellaneous
Formulas
Internal Rate of Return:
• Interest rate received for an investment
consisting of payments and income that
occur at regular periods
Payback Period:
• The time it takes to recover your
investment in the project before you
start accumulating profit.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formula’s
Money
Value as of Today (PV) Future value (FV)
Money – value depends on time
• Receiving AED 100 today has different meaning than
receiving it after 1 year.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formula’s -> Future Value
• Present Value (PV) =
1,000
• Years : 2 years
• Interest: 5% (0.05)
• Future Value (FV) = ??
The future value ( FV )
• It refers to a method of calculating how much present value (PV)
of an asset or cash will be worth at a specific time in the future
FV = PV (1 + R)^N
• FV: Future value
• PV: Present value
• N: time of years
• R: Interest rate
PV=100, R=5%, N=1
• = 100 (1 + 0.05)^1 )
• = 100 * (1.05^1)
• = 100 * 1.05
• = 105
Above example
• = 1,000 (1 + 0.05)^2 )
• = 1,000 * (1.05^2)
• = 1,000 * 1.1025
• = 1,102.5
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Miscellaneous Formula’s -> Present Value
Present Value:
• The value of an expected income(as of date of valuation)
• PV <= FV because money has interest-earning potential
• To calculate PV discount FV by interest rate
•Present Value (PV) = ?? •Years : 2 years
•Interest: 4% (0.05)
•Future Value (FV) = 1,000
PV = FV/ (1 + R)^N
• PV: Present value
• FV: Future value
• N: time of years
• R: Interest rate
Above example, what is PV??
• PV = 1,000 / (1 + 0.04)^2 )
• PV = 1,000 / (1.04^2)
• PV = 1,000 / 1.0816
• PV = 924
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Additional Free Resources
Visit Slide Share website & you will find other Knowledge area presentation… Please share!!

More Related Content

What's hot

Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides SlideTeam
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control QualityAnand Bobade
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Project Management
Project ManagementProject Management
Project Managementajithsrc
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI ApproachZaur Ahmadov, PMP
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CycleAnand Bobade
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2Anand Bobade
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaEdureka!
 

What's hot (20)

PMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 QuestionsPMP Exam Preparation - 200 Questions
PMP Exam Preparation - 200 Questions
 
Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides Project Closure Activities In Project Management PowerPoint Presentation Slides
Project Closure Activities In Project Management PowerPoint Presentation Slides
 
Chap 8.3 Control Quality
Chap 8.3  Control QualityChap 8.3  Control Quality
Chap 8.3 Control Quality
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Project Management
Project ManagementProject Management
Project Management
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Project Management - PMI Approach
Project Management - PMI ApproachProject Management - PMI Approach
Project Management - PMI Approach
 
Project managment ppt
Project managment pptProject managment ppt
Project managment ppt
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Project management
Project managementProject management
Project management
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Pmbok6 to 7 transformation
Pmbok6 to 7 transformationPmbok6 to 7 transformation
Pmbok6 to 7 transformation
 
2_Project Scope Management
2_Project Scope Management2_Project Scope Management
2_Project Scope Management
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
Pmp chap 11 - project risk management - Part 2
Pmp   chap 11 - project risk management - Part 2Pmp   chap 11 - project risk management - Part 2
Pmp chap 11 - project risk management - Part 2
 
Project Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | EdurekaProject Time Management | Project Schedule Management | Edureka
Project Time Management | Project Schedule Management | Edureka
 

Viewers also liked

PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasksAnand Bobade
 
PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5Anand Bobade
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartAnand Bobade
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementAnand Bobade
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...TURKI , PMP
 
PMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPRPMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPRAnand Bobade
 
PMP Flash Card
PMP Flash CardPMP Flash Card
PMP Flash Cardasim78
 
PMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VSPMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VSAnand Bobade
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionRicardo Viana Vargas
 
PMP Chap 12 - Project Procurement Management Details - Part 1
PMP   Chap 12 - Project Procurement Management Details - Part 1PMP   Chap 12 - Project Procurement Management Details - Part 1
PMP Chap 12 - Project Procurement Management Details - Part 1Anand Bobade
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2Anand Bobade
 
PMBOK 5th Edition Mind map
PMBOK 5th Edition Mind mapPMBOK 5th Edition Mind map
PMBOK 5th Edition Mind mapAlex Ashton
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsAnand Bobade
 
PMP Application form
PMP Application formPMP Application form
PMP Application formAnand Bobade
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementAnand Bobade
 
Dr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring QuotesDr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring QuotesAnand Bobade
 

Viewers also liked (20)

PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasks
 
PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes Chart
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource management
 
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
Free PMP notes,Free PMP Study Material,Free PMP Chapter wise notes,PMP Exam N...
 
PMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPRPMP Key Exam Concepts WPD, WPI & WPR
PMP Key Exam Concepts WPD, WPI & WPR
 
PMP Flash Card
PMP Flash CardPMP Flash Card
PMP Flash Card
 
PMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VSPMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VS
 
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified VersionPMBOK® Guide 5th edition Processes Flow in English - Simplified Version
PMBOK® Guide 5th edition Processes Flow in English - Simplified Version
 
PMP Chap 12 - Project Procurement Management Details - Part 1
PMP   Chap 12 - Project Procurement Management Details - Part 1PMP   Chap 12 - Project Procurement Management Details - Part 1
PMP Chap 12 - Project Procurement Management Details - Part 1
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 
PMP Chap 12 - Project Procurement Management Details - Part2
PMP   Chap 12 - Project Procurement Management Details - Part2PMP   Chap 12 - Project Procurement Management Details - Part2
PMP Chap 12 - Project Procurement Management Details - Part2
 
PMBOK 5th Edition Mind map
PMBOK 5th Edition Mind mapPMBOK 5th Edition Mind map
PMBOK 5th Edition Mind map
 
PMP Exam Changes
PMP Exam ChangesPMP Exam Changes
PMP Exam Changes
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management details
 
PMP Application form
PMP Application formPMP Application form
PMP Application form
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality Management
 
Dr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring QuotesDr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring Quotes
 

Similar to PMP Key Exam Concepts - Formulas

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptAsBali1
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureJohn Carter
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_managementSayed Ahmed
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)Nita Cristian
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 

Similar to PMP Key Exam Concepts - Formulas (20)

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Module 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.pptModule 06 Adv PM Budget Mgmt.ppt
Module 06 Adv PM Budget Mgmt.ppt
 
Module 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.pptModule 06 Adv Project Manager Budget Mgmt.ppt
Module 06 Adv Project Manager Budget Mgmt.ppt
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)projectcostcontrol-130625012804-phpapp02 (1)
projectcostcontrol-130625012804-phpapp02 (1)
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 

More from Anand Bobade

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 

More from Anand Bobade (20)

Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 

Recently uploaded

Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 

Recently uploaded (20)

Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 

PMP Key Exam Concepts - Formulas

  • 1. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) PMP: Key Exam Concepts Series - Formulas Crystal Clear understanding of key PMP concepts are essential to pass the PMP exam. These slide will help you to: • Visually learn key concepts • Get deep understand with real world examples • Sample Questions Three point estimation Earned value management Forecasting PV, FV, NPV, EMV etc
  • 2. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Definitions Three point estimation: • Accuracy improved by considering estimation uncertainty and risk using three estimates to define an approximate range for an activity’s cost. Earned value management: • It combines SCOPE, SCHEDULE, & RESOURCE measurements to assess project performance and progress. • It integrates the scope ,cost & schedule baselines, to form the performance baseline Forecasting: • Forecasting is the process of predicting future project performance based the current performance to date. Miscellaneous formulas: • Present value, Net Present value, Future value, EMV
  • 3. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Three point estimation Three point estimation Project schedule is the most important task which depends on the activity estimation done by team. Correctness of schedule heavily depends on the accuracy of the duration of all project activities. There are three basic techniques most widely used to estimate activity duration and build the schedule. Analogous Estimating Parametric Estimating Three Point Estimates
  • 4. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Three point estimation Weighted average • = (O + M + P) / 3Triangular Distribution • = (O + 4M + P) / 6Beta Distribution or PERT Accuracy improves by considering estimation uncertainty and risk using three estimates to define an approximate range for an activity’s cost. Optimistic (O): Based on analysis of the best-case scenario. Most likely (M) : Based on realistic effort assessment for required work & any predicted expenses (or ML) Pessimistic (P). Based on analysis of the worst-case scenario. Three point estimation
  • 5. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Earned Value Management It combines SCOPE, SCHEDULE, & RESOURCE measurements to assess project performance and progress. It integrates the scope ,cost & schedule baselines, to form the performance baseline • It is authorized budget planned for work to be accomplished. Also known as Budgeted Cost of Work Scheduled (BCWS). Total of PV (PMB or BAC). Planned Value (PV) • It is actual amount of money spent to date. Also known as Actual Cost of Work Performed (ACWP) Actual cost (AC) • It is amount of money earned from completed work in a given time. Earned Value is also known as Budgeted Cost of Work Performed (BCWP). Earned value (EV) Earned value management
  • 6. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Earned Value Management -> Earn Value (EV) Earned value Calculation based on the Percentage completion Schedule Planned Value (PV) Percentage Complete Actual Cost (AC) Earn Value (EV) Task1 10,000 50% 6,000 ? • Only 50% of work completed • EV = 50% of PV • EV = 50% of 10,000 = 5,000 Earn Value (EV) Earned value management Schedule Planned Value (PV) Percentage Complete Actual Cost (AC) Earn Value (EV) Task1 10,000 100% 9,000 ?? Task2 8,000 75% 6,000 ?? • EV = (100% of 10,000) + (75% of 8,000) • EV = 10,000 + 6,000 = 16,000 Earn Value (EV)
  • 7. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index • SV is a measure of schedule performance on a project. • EVM & SV are best used with CPM scheduling & risk manag. Schedule variance (CV) • It measure of cost performance on a project • It indicates relationship of performance to costs spent Cost variance (CV) • SPI is a measure of progress achieved compared to progress planned on a project Schedule performance index (SPI) • CPI is a measure of the value of work completed compared to the actual cost or progress made on the project. Cost performance index (CPI)
  • 8. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index • SPI = EV/PV Schedule performance index • CPI = EV/AC Cost performance index Day1 Day2 Day3 Day4 Day5 Day6 Day7 Planned Budget (PV) 1,000 3,000 5,000 7,000 9,000 11,000 12,000 Actual Cost (AC) 1,100 3,300 6,600 9,900 Earned Value (EV) 1,000 2,000 3,000 4,000 PV: 7,000 BAC: 12,000 AC: 9,900 EV: 4,000 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Cost Variance Schedule Variance • SV = EV –PV Schedule variance • CV= EV − ACCost variance Note: All values are cumulative
  • 9. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index Planned Value (PV) Earned Value (EV) Actual Cost (AC) SV = EV –PV CV= EV − AC SPI = EV/PV CPI = EV/AC 1000 800 1200 -200 -400 0.8 0.67 1500 1200 1800 -300 -600 0.8 0.67 • SV = EV –PVSchedule variance • SPI = EV/PVSchedule performance index • CV= EV − ACCost variance • CPI = EV/ACCost performance index Indexes CPI SPI > 1 Under budget Ahead of schedule < 1 Over Budget Behind schedule = 1 On Budget (planned cost) On Schedule
  • 10. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index Indexes CPI SPI > 1 You are earning more than the spending. In other words, you are under budget. More work has been completed than the planned work. In other words, you are ahead of schedule. < 1 You are earning less than the spending. In other words, you’re over budget Less work is completed than the planned work. In other words, you are behind schedule. = 1 Earning & spending are equal. Or proceeding exactly as per planned budget spending On Schedule
  • 11. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) EVM -> Variance & Performance Index • Slowdown with spending to try to reach optimal level • Try to move to optimal otherwise re- baseline. • Continue as it is • Spend more to catch up Under Budget but behind schedule Optimal – Under Budget & ahead of Schedule Over Budget but ahead of schedule Worst case: Over Budget & behind schedule CPI >1 [Ahead of Schedule] CPI < 1 CPI >1 [Behind Schedule] CPI < 1 SPI < 1 [Under Budget] SPI >1 SPI < 1 [Over Budget] SPI >1
  • 12. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting Forecasting is used to come up with a future performance or result of the project. It gives project sponsors/management an early visibility on of what may go wrong and help take preventive decision. Forecasting Estimate at Completion (EAC) Estimate to Complete (ETC) To Complete Performance Index (TCPI)
  • 13. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate at Completion (EAC): Estimate at Completion As the project progresses, forecast for estimate at completion (EAC) may develop based on project performance. If BAC is no longer viable, forecasted EAC should be considered. EAC involves making projections of conditions & events in the project’s future based on current performance & other knowledge. Forecasts are generated, updated, and reissued based on work performance data.
  • 14. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate at Completion (EAC): Budgeted Rate: • Absorb the Variance (originally planed budgeted rate) Current Progress: • Take the ongoing project trend (CPI & SPI or only CPI) Erroneous scenario: • Re-estimate the remaining portion Estimate at Completion
  • 15. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate at Completion (EAC): • EAC = AC + (BAC –EV) Based on Budgeted rate • EAC = AC + (BAC –EV)/CPI = BAC / CPIBased on CPI. • EAC = AC + [(BAC –EV) / (CPI ×SPI)]Based on SPI & CPI • EAC = AC + Bottom up estimateErroneous scenario: EV=2K AC=3.3K BAC=12K ETC=BAC-CV EAC=AC+ETC Estimate at Completion
  • 16. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Estimate to Complete ETC tell you, how much money you need to complete the task at hand. ETC = BAC - EV VAC (Variance at completion) shows whether project is forecasted to finish under or over budget VAC = BAC – EAC VAC % = VAC / BAC Estimate to Complete
  • 17. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI TCPI is the measure of the CP that is required to be achieved in order to meet a specified management goal Ratio of cost to finish outstanding work to remaining budget. TCPI calculation Same Budget Use BAC Revised Budget Use Forecasted EAC If BAC is no longer viable, forecasted EAC should be approved, use in the TCPI calculation. TCPI
  • 18. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI PV: 6,000 BAC: 12,000 AC: 9,000 EV: 4,500 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Day1 Day2 Day3 Day4 Day5 Day6 Planned Budget (PV) Actual Cost (AC) Earned Value (EV) Fund Remaining = BAC-AC = 3,000 Work Remaining = BAC-EV = 7,500 Case1: Same Budget
  • 19. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI PV: 6,000 BAC: 12,000 AC: 9,000 EV: 4,500 - 2,000 4,000 6,000 8,000 10,000 12,000 14,000 Day1 Day2 Day3 Day4 Day5 Day6 Planned Budget (PV) Actual Cost (AC) Earned Value (EV) Fund Remaining = EAC-AC = 9,000 Work Remaining = BAC-EV = 7,500 EAC: 18,000 18,000 Case 2: Revised Budget
  • 20. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI TCPI (based on the BAC): (BAC –EV) ----------------------------------------------------------------------------------------------------------- (BAC –AC) TCPI (based on the EAC): (BAC –EV) ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- (EAC –AC) Work Remaining ---------------------- Fund Remaining To-complete performance index (TCPI) = Case1 : TCPI • (12,000-4,500)/(12,000-9,000) • 7,500/3,000 • 2.5 Case2: TCPI • (12,000-4,500)/(18,000-9,000) • 7,500/9,000 • .83 TCPI
  • 21. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> TCPI • Project is in a comfortable position.If TCPI < 1 • Project have to perform with better cost performance than the past cost performance.If TCPI > 1 • Project can continue with the same cost performance.if TCPI = 1 TCPI
  • 22. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Forecasting -> Variance Analysis An important aspect of project cost control includes determining the cause and degree of variance relative to the cost baseline and deciding whether corrective or preventive action is required. Variance analysis is used in EVM for determining cause, impact, and corrective actions Cost (CV = EV –AC) Schedule (SV = EV –PV) VAC = BAC –EAC Compare cost performance over time, schedule activities or work packages overrunning and under running the budget, and estimated funds needed to complete work in progress.
  • 23. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formulas Miscellaneous Formulas Net present value (NPV): • The total present value (PV) of a time series of cash flows. • It is a standard method for using the time value of money to appraise long-term projects Profit = Revenue – Costs Profit Margin = Profit / Revenue Evaluating efficiency of investment. Bigger ROI is better. ROI = (Gain – cost) / Gain
  • 24. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formulas Miscellaneous Formulas Internal Rate of Return: • Interest rate received for an investment consisting of payments and income that occur at regular periods Payback Period: • The time it takes to recover your investment in the project before you start accumulating profit.
  • 25. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formula’s Money Value as of Today (PV) Future value (FV) Money – value depends on time • Receiving AED 100 today has different meaning than receiving it after 1 year.
  • 26. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formula’s -> Future Value • Present Value (PV) = 1,000 • Years : 2 years • Interest: 5% (0.05) • Future Value (FV) = ?? The future value ( FV ) • It refers to a method of calculating how much present value (PV) of an asset or cash will be worth at a specific time in the future FV = PV (1 + R)^N • FV: Future value • PV: Present value • N: time of years • R: Interest rate PV=100, R=5%, N=1 • = 100 (1 + 0.05)^1 ) • = 100 * (1.05^1) • = 100 * 1.05 • = 105 Above example • = 1,000 (1 + 0.05)^2 ) • = 1,000 * (1.05^2) • = 1,000 * 1.1025 • = 1,102.5
  • 27. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Miscellaneous Formula’s -> Present Value Present Value: • The value of an expected income(as of date of valuation) • PV <= FV because money has interest-earning potential • To calculate PV discount FV by interest rate •Present Value (PV) = ?? •Years : 2 years •Interest: 4% (0.05) •Future Value (FV) = 1,000 PV = FV/ (1 + R)^N • PV: Present value • FV: Future value • N: time of years • R: Interest rate Above example, what is PV?? • PV = 1,000 / (1 + 0.04)^2 ) • PV = 1,000 / (1.04^2) • PV = 1,000 / 1.0816 • PV = 924
  • 28. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Additional Free Resources Visit Slide Share website & you will find other Knowledge area presentation… Please share!!