SlideShare a Scribd company logo
1 of 28
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
PMP:
Key Exam Concepts Series
Crystal Clear understanding of key PMP concepts are
essential to pass the PMP exam. These slide will help you to:
• Visually learn key concepts
• Get deep understand with real world examples
• Sample Questions
Work Performance
Data
Work Performance
Information
Work Performance
Report
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Definitions
Work Performance Data:
• The raw observations & measurements identified
during activities performed to carry out the project
work.
Work Performance Information:
• The performance data collected from various
controlling processes, analyzed in context &
integrated based on relationships across areas.
Work Performance Report:
• The physical or electronic representation of WPI
compiled in project documents, intended to generate
decision or raise issues, actions or awareness
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
What is Work Performance Data (WPD)?
Work
Performance
Data
The raw observations & measurements identified
during activities performed to carry out the
project work.
It is the raw data of the project’s status.
e.g. actual cost, actual duration etc.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
How WPD is generated?
Work
Performance
Data
The compliance of requirements, non-conformities.
The number of change requests received, accepted
or rejected.
How many activities have been started, finished, &
status of current activities etc.
Cost parameter of project. E.g., work completed,
money spent to date, etc.
Testing & performance measurements. E.g.,
characteristics of product, quality metrics, number
of defects, rejection rate, etc.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
How WPD is generated?
Work
Performance
Data
Distribution of communications reports, feedback
on report, etc.
Risk status, new identified risks, effectiveness of
risk response plan, contingency or management
reserve utilization, risk impact on schedule, cost,
and scope.
Procurement related activities. E.g., quality
standards met by seller, seller’s performance, etc.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
How WPD is generated?
Work
Performance
Data
Executing PG ->
Direct and Manage
Project work
Work Performance
Data
Validate Scope Control Scope Control
Schedule
Control Cost Control Quality
Control
Communicatio
n
Control Risks Control
Stakeholder
Eng.
Control
Procurements
Monitoring &
Controlling PG
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Project team status meeting
WPD -> Example
No of activities started,
finished
Work completed,
money spent.
Number of defects found,
the rejection rate
Risk status; new risks,
effectiveness of risk
response plan
Control Schedule –
identify delay
Control Cost – Analyses
cost of completed work
vs money spent
Control Quality – analyse
data & control quality
Control Risks – analyse
risk data & re-
asses/control risks
Monitoring & Controlling PG
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDWhat is Work Performance Information (WPI)?
Work
Performance
Information
The performance data collected from various controlling
processes, analyzed in context and integrated based on
relationships across areas
PM analyze the work performance data. Compare
planned performance with actual performance
E.g, Planned vs actual cost, planned vs actual duration
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDHow WPI is generated?
Work
Performance
Information
Review project’s progress; e.g. status of
deliverables, whether deliverable is accepted, how
project scope is performing against scope baseline.
Compare planned schedule with actual schedule.
You will see the planned duration for an activity,
and the time taken by the activity to be completed,
etc
PM will compare planned cost with actual cost of
this activity; i.e. planned cost versus actual cost
spent. You will also review other parameters such
as cost variance, cost performance, etc
PM will analyze planned versus actual technical
performance, such as how many defects, tolerance
& threshold was allowed, and how much it actually
is, how much rework is required, etc
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDHow WPI is generated?
Work
Performance
Information
Find the status and progress information of the
project & check if it is communicated or not.
Compare how risks have occurred, efficiency of risk
response plan, how much contingency money has
been spent, and what is remaining reserve, etc.
Review the seller’s performance against agreed
terms.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Monitoring & Controlling PG-> Control Process
12.3 Control Procurement ->Input->WPDHow WPI is generated?
Work
Performance
Information
Validate Scope Control Scope Control
Schedule
Control Cost Control Quality
Control
Communication
Control Risks Control
Stakeholder Eng.
Control
Procurements
Monitoring & Controlling
PG-> Monitor & Control
Project work
Work Performance
Information
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Relation between WPD & WPI
• Executing PG ->Direct
& Manage process
• Generates WPD
• Monitor & Control PG -
> All Control process
• Generate WPI
•Monitoring & Controlling
PG-> Monitor & Control
Project work
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
WPI -> Example
Control Schedule – identify
delay & try controlling it
Control Cost – Analyses cost of
completed work against money
spent
Control Quality – analyse data
& control quality
Control Risks – analyse risk
data & re-asses/control risks
Compare, Assess, Document,
Forecast & Communicate
 SV, SPI
 CV, CPI
 Quality issues, corrective actions
 New risks, closed risk
User below T&T to initiate CR &
distribute reports:
 Expert Judgment
 Analytical Techniques
 PMIS &Meetings
Monitoring & Controlling PG ->
Control Processes
Monitoring & Controlling PG ->
Monitor & Control Project work
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDWhat is Work Performance Reports (WPR)?
Work
Performance
Reports
The physical or electronic representation of work performance
information compiled in project documents, intended to generate
decision or raise issues, actions or awareness
Are output of the Monitor & Control Project Work process, and
input to various managing and controlling processes.
Helps stakeholders with current status of the project and its
performance against the planned baselines.
If project is not progressing as planned, stakeholder may decide to
take any corrective action. E.g., extra funds or resources, or time
extension etc.
It can be given to stakeholders in a format desired by them and as
decided in the communication management plan.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDHow WPR is generated?
Work
Performance
Reports
Manage Project
Team
Manage
Communication
Perform
Integrated
Change Control
Control Risks Control
Procurement
Monitoring & Controlling PG->
Monitor & Control Project work
Monitoring & Controlling PGExecuting PG
Work Performance
Reports
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDFormat of WPR
Work
Performance
Reports
Performance Reports may be any combination of these
formats:
Burndown
Chart
S-Curve Bar Charts
Histograms Tables Run Charts.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
12.3 Control Procurement ->Input->WPDContent of WPR
Work
Performance
Reports
The content of the Performance Reports includes:
Percentage of the work completed
Balance work to be completed
Cost incurred
Balance of funds available
Balance of time available
Major risks that have occurred, or passed without occurring
Major remaining identified risks
Results of variance analysis: e.g. schedule variance and cost variance
Performance indexes: e.g. SPI , CPI
Forecasted fund required to complete the remaining work
Forecasted time required to complete the remaining work
Summary of major approved change requests.
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
WPR -> Example
Execute PG -> Manage
Communication:
Share Performance report to all
stakeholders through manage
communication process.
M & C PG -> Perform Integrated
Change Control:
Huge variance or major finding in
performance reports will warrant CR.
CCB
Monitoring & Controlling PG ->
Monitor & Control Project work
Stakeholders
Compare, Assess,
Document,
Forecast & Communicate
 SV, SPI
 CV, CPI
 Quality issues, corrective
actions
 New risks, closed risk
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewReview
Work performance data is a collection of raw information of the project’s status.
On the other hand, work performance information is a comparison of various
performances, like cost and schedule, etc.
Work performance data and work performance information are the basis for the
Performance Reports.
The Performance Reports are the reports given to project stakeholders to make them
aware of the current status and the forecasted progress of the project.
The Performance Reports show stakeholders how the project is going.
The forecast analysis of what they should expect if the project is allowed to keep
going in the same way, or what additional funds or resources may be required to
complete the project
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
1. Anand is working on CRM project for Dubai
Customs, even though you are using agile methods,
you realize you are preparing an extensive amount of
data and information. You regularly share data with
your project team. Your last team meeting focused on
the number of change requests and also the start and
finish dates of activities in your schedule. They are
examples of—
• A. Key performance indicators
• B. Work performance reports
• C. Work performance data
• D. Work performance information
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
2. The purpose of work performance data
in control communications is to present
results of comparative analysis to the—
• A. Performance measurement baseline
• B. Communications management plan
• C. Stakeholder management plan
• D. Deliverable status
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
3. Work performance information
includes all the following EXCEPT—
• A. Started deliverables
• B. Costs authorized and incurred
• C. Progress of deliverables
• D. Completed deliverables
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
4. Work performance information is an output
of which process?
• A. Manage risks
• B. Manage communications
• C. Control communications
• D. Report performance
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions
5. Assume you want to optimize the work
performance reports you will use to manage
communications. You should do so by—
• A. Determining the most appropriate choice of
communications media
• B. Setting different communications techniques for
different stakeholder groups
• B. Ensuring the information is consistent with regulations
and standards
• D. Ensuring comprehensiveness, accuracy, and availability
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions - Answers
1. c. Work performance data
• Work performance data are the raw observations and
measurements identified during activities performed to carry out
the work of the project. Other examples are the reported
percent of work physically completed, quality and technical
performance measures, number of defects, actual costs, and
actual durations. [Executing]
2. a. Performance measurement baseline
• Wok performance data are an input in control communications.
These data organize and summarize information gathered and
present the results of comparative analysis to the performance
measurement baseline. [Monitoring and Controlling]
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions - Answers
3. b. Costs authorized and incurred
• Work performance information is an output of validate scope.
It emphasizes deliverables—whether or not they have started,
their progress, and ones that have finished or have been
accepted. [Monitoring and Controlling]
4. c. Control communications
• Work performance information, an output of control
communications, organizes and summaries performance data
such as status and progress information on the project at the
level required by stakeholders. This information next is
communicated to the appropriate stakeholders. [Monitoring
and Controlling]
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
ReviewSample Questions - Answers
5. d. Ensuring comprehensiveness,
accuracy, and availability
• Work performance reports are an input to manage
communications. They are a collection of project
performance and status information used to facilitate
discussion and create communications. They should
be comprehensive, accurate, and available in a timely
way. [Executing]
By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com)
Additional Free Resources
Visit Slide Share website & you will find other Knowledge area presentation… Please share!!

More Related Content

What's hot

PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slidesmasilamani ramasamy
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementFred Wiersma
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2Anand Bobade
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1Anand Bobade
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityAnand Bobade
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Agus Suhanto
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 

What's hot (20)

PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Earned value management
Earned value managementEarned value management
Earned value management
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Chap 6.3 Sequence Activity
Chap 6.3 Sequence ActivityChap 6.3 Sequence Activity
Chap 6.3 Sequence Activity
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 

Viewers also liked

PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasAnand Bobade
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasksAnand Bobade
 
PMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VSPMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VSAnand Bobade
 
PMP Chap 12 - Project Procurement Management Details - Part 1
PMP   Chap 12 - Project Procurement Management Details - Part 1PMP   Chap 12 - Project Procurement Management Details - Part 1
PMP Chap 12 - Project Procurement Management Details - Part 1Anand Bobade
 
PMP Exam Changes
PMP Exam ChangesPMP Exam Changes
PMP Exam ChangesAnand Bobade
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 
PMP Application form
PMP Application formPMP Application form
PMP Application formAnand Bobade
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsAnand Bobade
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 
Dr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring QuotesDr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring QuotesAnand Bobade
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementAnand Bobade
 
PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5Anand Bobade
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CycleAnand Bobade
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartAnand Bobade
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2Anand Bobade
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementAnand Bobade
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2Anand Bobade
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 

Viewers also liked (20)

PMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - FormulasPMP Key Exam Concepts - Formulas
PMP Key Exam Concepts - Formulas
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasks
 
PMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VSPMP Key-exam-concepts-QA-QC-VS-VS
PMP Key-exam-concepts-QA-QC-VS-VS
 
PMP Chap 12 - Project Procurement Management Details - Part 1
PMP   Chap 12 - Project Procurement Management Details - Part 1PMP   Chap 12 - Project Procurement Management Details - Part 1
PMP Chap 12 - Project Procurement Management Details - Part 1
 
PMP Exam Changes
PMP Exam ChangesPMP Exam Changes
PMP Exam Changes
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
PMP Application form
PMP Application formPMP Application form
PMP Application form
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management details
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 
Dr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring QuotesDr. APJ Abdul Kalam's Inspiring Quotes
Dr. APJ Abdul Kalam's Inspiring Quotes
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource management
 
PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5PMBOK-5th ed: PMP- Flashcards Part1/5
PMBOK-5th ed: PMP- Flashcards Part1/5
 
PMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life CyclePMP Chap 2- Org. Influence and Project Life Cycle
PMP Chap 2- Org. Influence and Project Life Cycle
 
Knowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes ChartKnowledge Area and 47 Processes Chart
Knowledge Area and 47 Processes Chart
 
PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2PMP Chap4-Project Integration Management Details: Part-2
PMP Chap4-Project Integration Management Details: Part-2
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 
PMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality ManagementPMP Chap 8 - Project Quality Management
PMP Chap 8 - Project Quality Management
 
PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2PMP Chap 6 - Project Time management - Part2
PMP Chap 6 - Project Time management - Part2
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 

Similar to PMP Key Exam Concepts WPD, WPI & WPR

Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkAnand Bobade
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation TafseerKishan Solankimbaccepmp
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workAnand Bobade
 
'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014
'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014
'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014ColomboCampsCommunity
 
Gaurav Gupta Resume
Gaurav Gupta ResumeGaurav Gupta Resume
Gaurav Gupta ResumeGaurav Gupta
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor RisksAnand Bobade
 
Project Planning & Control Engineer
Project Planning & Control EngineerProject Planning & Control Engineer
Project Planning & Control EngineerMoshir Shabbir Moshir
 
Resume_Theresa_Lawson_2016_All
Resume_Theresa_Lawson_2016_AllResume_Theresa_Lawson_2016_All
Resume_Theresa_Lawson_2016_AllTheresa Lawson
 
Module 4 - IDP.pptx
Module 4 - IDP.pptxModule 4 - IDP.pptx
Module 4 - IDP.pptxRAJESH S
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...Glen Alleman
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
JIm Johnson Engineering Excellence
JIm Johnson Engineering ExcellenceJIm Johnson Engineering Excellence
JIm Johnson Engineering Excellencejijoh123
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.iFour Institute - Sustainable Learning
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlAnand Bobade
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason Uyder
 

Similar to PMP Key Exam Concepts WPD, WPI & WPR (20)

Chap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project WorkChap 4.5 Monitor and Control Project Work
Chap 4.5 Monitor and Control Project Work
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 
Chap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project workChap 4.3 Direct and Manage Project work
Chap 4.3 Direct and Manage Project work
 
'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014
'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014
'Metrics That Matter': Gabrielle Benefield @ Colombo Agile Con 2014
 
Gaurav Gupta Resume
Gaurav Gupta ResumeGaurav Gupta Resume
Gaurav Gupta Resume
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Chap 11.7 Monitor Risks
Chap 11.7 Monitor RisksChap 11.7 Monitor Risks
Chap 11.7 Monitor Risks
 
Project Planning & Control Engineer
Project Planning & Control EngineerProject Planning & Control Engineer
Project Planning & Control Engineer
 
Resume_Theresa_Lawson_2016_All
Resume_Theresa_Lawson_2016_AllResume_Theresa_Lawson_2016_All
Resume_Theresa_Lawson_2016_All
 
Module 4 - IDP.pptx
Module 4 - IDP.pptxModule 4 - IDP.pptx
Module 4 - IDP.pptx
 
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
 
Introduction to six sigma (www.gotoaims.com)
Introduction to six sigma (www.gotoaims.com)Introduction to six sigma (www.gotoaims.com)
Introduction to six sigma (www.gotoaims.com)
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
JIm Johnson Engineering Excellence
JIm Johnson Engineering ExcellenceJIm Johnson Engineering Excellence
JIm Johnson Engineering Excellence
 
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
Project management : Project Monitoring and Control by iFour Technolab Pvt. Ltd.
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Chap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change ControlChap 4.6 Perform Integrated Change Control
Chap 4.6 Perform Integrated Change Control
 
Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12Jason uyderv pmi 2 16 12
Jason uyderv pmi 2 16 12
 
6 Sigma
6 Sigma6 Sigma
6 Sigma
 

More from Anand Bobade

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control ProcurementAnand Bobade
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementAnand Bobade
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementAnand Bobade
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overviewAnand Bobade
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify RisksAnand Bobade
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationAnand Bobade
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage CommunicationAnand Bobade
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication ManagementAnand Bobade
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control ResourcesAnand Bobade
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage TeamAnand Bobade
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop TeamAnand Bobade
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire ResourcesAnand Bobade
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource ManagementAnand Bobade
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overviewAnand Bobade
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate CostAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewAnand Bobade
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define ScheduleAnand Bobade
 

More from Anand Bobade (20)

PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
Chap 12.3 Control Procurement
Chap 12.3 Control ProcurementChap 12.3 Control Procurement
Chap 12.3 Control Procurement
 
Chap 12.2 Conduct Procurement
Chap 12.2 Conduct ProcurementChap 12.2 Conduct Procurement
Chap 12.2 Conduct Procurement
 
Chap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement ManagementChap 12.1 Plan Procurement Management
Chap 12.1 Plan Procurement Management
 
Chap 12.0 Procurement Management overview
Chap 12.0   Procurement Management overviewChap 12.0   Procurement Management overview
Chap 12.0 Procurement Management overview
 
Chap 11.2 Identify Risks
Chap 11.2 Identify RisksChap 11.2 Identify Risks
Chap 11.2 Identify Risks
 
Chap 10.3 Monitor Communication
Chap 10.3 Monitor CommunicationChap 10.3 Monitor Communication
Chap 10.3 Monitor Communication
 
Chap 10.2 Manage Communication
Chap 10.2  Manage CommunicationChap 10.2  Manage Communication
Chap 10.2 Manage Communication
 
Chap 10.1 Plan Communication Management
Chap 10.1  Plan Communication ManagementChap 10.1  Plan Communication Management
Chap 10.1 Plan Communication Management
 
Chap 9.6 Control Resources
Chap 9.6  Control ResourcesChap 9.6  Control Resources
Chap 9.6 Control Resources
 
Chap 9.5 Manage Team
Chap 9.5  Manage TeamChap 9.5  Manage Team
Chap 9.5 Manage Team
 
Chap 9.4 Develop Team
Chap 9.4  Develop TeamChap 9.4  Develop Team
Chap 9.4 Develop Team
 
Chap 9.3 Acquire Resources
Chap 9.3   Acquire ResourcesChap 9.3   Acquire Resources
Chap 9.3 Acquire Resources
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
Chap 9.1 Pan Resource Management
Chap 9.1   Pan Resource ManagementChap 9.1   Pan Resource Management
Chap 9.1 Pan Resource Management
 
Chap 9.0 Project Resource Management overview
Chap 9.0   Project Resource Management overviewChap 9.0   Project Resource Management overview
Chap 9.0 Project Resource Management overview
 
Chap 7.2 Estimate Cost
Chap 7.2 Estimate CostChap 7.2 Estimate Cost
Chap 7.2 Estimate Cost
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
Chap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management OverviewChap 7.0 Project Cost Management Overview
Chap 7.0 Project Cost Management Overview
 
Chap 6.5 Define Schedule
Chap 6.5 Define ScheduleChap 6.5 Define Schedule
Chap 6.5 Define Schedule
 

Recently uploaded

Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 

Recently uploaded (20)

Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 

PMP Key Exam Concepts WPD, WPI & WPR

  • 1. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) PMP: Key Exam Concepts Series Crystal Clear understanding of key PMP concepts are essential to pass the PMP exam. These slide will help you to: • Visually learn key concepts • Get deep understand with real world examples • Sample Questions Work Performance Data Work Performance Information Work Performance Report
  • 2. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Definitions Work Performance Data: • The raw observations & measurements identified during activities performed to carry out the project work. Work Performance Information: • The performance data collected from various controlling processes, analyzed in context & integrated based on relationships across areas. Work Performance Report: • The physical or electronic representation of WPI compiled in project documents, intended to generate decision or raise issues, actions or awareness
  • 3. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) What is Work Performance Data (WPD)? Work Performance Data The raw observations & measurements identified during activities performed to carry out the project work. It is the raw data of the project’s status. e.g. actual cost, actual duration etc.
  • 4. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) How WPD is generated? Work Performance Data The compliance of requirements, non-conformities. The number of change requests received, accepted or rejected. How many activities have been started, finished, & status of current activities etc. Cost parameter of project. E.g., work completed, money spent to date, etc. Testing & performance measurements. E.g., characteristics of product, quality metrics, number of defects, rejection rate, etc.
  • 5. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) How WPD is generated? Work Performance Data Distribution of communications reports, feedback on report, etc. Risk status, new identified risks, effectiveness of risk response plan, contingency or management reserve utilization, risk impact on schedule, cost, and scope. Procurement related activities. E.g., quality standards met by seller, seller’s performance, etc.
  • 6. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) How WPD is generated? Work Performance Data Executing PG -> Direct and Manage Project work Work Performance Data Validate Scope Control Scope Control Schedule Control Cost Control Quality Control Communicatio n Control Risks Control Stakeholder Eng. Control Procurements Monitoring & Controlling PG
  • 7. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Project team status meeting WPD -> Example No of activities started, finished Work completed, money spent. Number of defects found, the rejection rate Risk status; new risks, effectiveness of risk response plan Control Schedule – identify delay Control Cost – Analyses cost of completed work vs money spent Control Quality – analyse data & control quality Control Risks – analyse risk data & re- asses/control risks Monitoring & Controlling PG
  • 8. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDWhat is Work Performance Information (WPI)? Work Performance Information The performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas PM analyze the work performance data. Compare planned performance with actual performance E.g, Planned vs actual cost, planned vs actual duration
  • 9. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDHow WPI is generated? Work Performance Information Review project’s progress; e.g. status of deliverables, whether deliverable is accepted, how project scope is performing against scope baseline. Compare planned schedule with actual schedule. You will see the planned duration for an activity, and the time taken by the activity to be completed, etc PM will compare planned cost with actual cost of this activity; i.e. planned cost versus actual cost spent. You will also review other parameters such as cost variance, cost performance, etc PM will analyze planned versus actual technical performance, such as how many defects, tolerance & threshold was allowed, and how much it actually is, how much rework is required, etc
  • 10. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDHow WPI is generated? Work Performance Information Find the status and progress information of the project & check if it is communicated or not. Compare how risks have occurred, efficiency of risk response plan, how much contingency money has been spent, and what is remaining reserve, etc. Review the seller’s performance against agreed terms.
  • 11. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Monitoring & Controlling PG-> Control Process 12.3 Control Procurement ->Input->WPDHow WPI is generated? Work Performance Information Validate Scope Control Scope Control Schedule Control Cost Control Quality Control Communication Control Risks Control Stakeholder Eng. Control Procurements Monitoring & Controlling PG-> Monitor & Control Project work Work Performance Information
  • 12. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Relation between WPD & WPI • Executing PG ->Direct & Manage process • Generates WPD • Monitor & Control PG - > All Control process • Generate WPI •Monitoring & Controlling PG-> Monitor & Control Project work
  • 13. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) WPI -> Example Control Schedule – identify delay & try controlling it Control Cost – Analyses cost of completed work against money spent Control Quality – analyse data & control quality Control Risks – analyse risk data & re-asses/control risks Compare, Assess, Document, Forecast & Communicate  SV, SPI  CV, CPI  Quality issues, corrective actions  New risks, closed risk User below T&T to initiate CR & distribute reports:  Expert Judgment  Analytical Techniques  PMIS &Meetings Monitoring & Controlling PG -> Control Processes Monitoring & Controlling PG -> Monitor & Control Project work
  • 14. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDWhat is Work Performance Reports (WPR)? Work Performance Reports The physical or electronic representation of work performance information compiled in project documents, intended to generate decision or raise issues, actions or awareness Are output of the Monitor & Control Project Work process, and input to various managing and controlling processes. Helps stakeholders with current status of the project and its performance against the planned baselines. If project is not progressing as planned, stakeholder may decide to take any corrective action. E.g., extra funds or resources, or time extension etc. It can be given to stakeholders in a format desired by them and as decided in the communication management plan.
  • 15. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDHow WPR is generated? Work Performance Reports Manage Project Team Manage Communication Perform Integrated Change Control Control Risks Control Procurement Monitoring & Controlling PG-> Monitor & Control Project work Monitoring & Controlling PGExecuting PG Work Performance Reports
  • 16. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDFormat of WPR Work Performance Reports Performance Reports may be any combination of these formats: Burndown Chart S-Curve Bar Charts Histograms Tables Run Charts.
  • 17. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) 12.3 Control Procurement ->Input->WPDContent of WPR Work Performance Reports The content of the Performance Reports includes: Percentage of the work completed Balance work to be completed Cost incurred Balance of funds available Balance of time available Major risks that have occurred, or passed without occurring Major remaining identified risks Results of variance analysis: e.g. schedule variance and cost variance Performance indexes: e.g. SPI , CPI Forecasted fund required to complete the remaining work Forecasted time required to complete the remaining work Summary of major approved change requests.
  • 18. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) WPR -> Example Execute PG -> Manage Communication: Share Performance report to all stakeholders through manage communication process. M & C PG -> Perform Integrated Change Control: Huge variance or major finding in performance reports will warrant CR. CCB Monitoring & Controlling PG -> Monitor & Control Project work Stakeholders Compare, Assess, Document, Forecast & Communicate  SV, SPI  CV, CPI  Quality issues, corrective actions  New risks, closed risk
  • 19. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewReview Work performance data is a collection of raw information of the project’s status. On the other hand, work performance information is a comparison of various performances, like cost and schedule, etc. Work performance data and work performance information are the basis for the Performance Reports. The Performance Reports are the reports given to project stakeholders to make them aware of the current status and the forecasted progress of the project. The Performance Reports show stakeholders how the project is going. The forecast analysis of what they should expect if the project is allowed to keep going in the same way, or what additional funds or resources may be required to complete the project
  • 20. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 1. Anand is working on CRM project for Dubai Customs, even though you are using agile methods, you realize you are preparing an extensive amount of data and information. You regularly share data with your project team. Your last team meeting focused on the number of change requests and also the start and finish dates of activities in your schedule. They are examples of— • A. Key performance indicators • B. Work performance reports • C. Work performance data • D. Work performance information
  • 21. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 2. The purpose of work performance data in control communications is to present results of comparative analysis to the— • A. Performance measurement baseline • B. Communications management plan • C. Stakeholder management plan • D. Deliverable status
  • 22. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 3. Work performance information includes all the following EXCEPT— • A. Started deliverables • B. Costs authorized and incurred • C. Progress of deliverables • D. Completed deliverables
  • 23. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 4. Work performance information is an output of which process? • A. Manage risks • B. Manage communications • C. Control communications • D. Report performance
  • 24. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions 5. Assume you want to optimize the work performance reports you will use to manage communications. You should do so by— • A. Determining the most appropriate choice of communications media • B. Setting different communications techniques for different stakeholder groups • B. Ensuring the information is consistent with regulations and standards • D. Ensuring comprehensiveness, accuracy, and availability
  • 25. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions - Answers 1. c. Work performance data • Work performance data are the raw observations and measurements identified during activities performed to carry out the work of the project. Other examples are the reported percent of work physically completed, quality and technical performance measures, number of defects, actual costs, and actual durations. [Executing] 2. a. Performance measurement baseline • Wok performance data are an input in control communications. These data organize and summarize information gathered and present the results of comparative analysis to the performance measurement baseline. [Monitoring and Controlling]
  • 26. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions - Answers 3. b. Costs authorized and incurred • Work performance information is an output of validate scope. It emphasizes deliverables—whether or not they have started, their progress, and ones that have finished or have been accepted. [Monitoring and Controlling] 4. c. Control communications • Work performance information, an output of control communications, organizes and summaries performance data such as status and progress information on the project at the level required by stakeholders. This information next is communicated to the appropriate stakeholders. [Monitoring and Controlling]
  • 27. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) ReviewSample Questions - Answers 5. d. Ensuring comprehensiveness, accuracy, and availability • Work performance reports are an input to manage communications. They are a collection of project performance and status information used to facilitate discussion and create communications. They should be comprehensive, accurate, and available in a timely way. [Executing]
  • 28. By: Anand Bobade; PMP, SCEA, MCP, CIW (nmbobade@gmail.com) Additional Free Resources Visit Slide Share website & you will find other Knowledge area presentation… Please share!!