Time is and Asset
Delay is a Cost
Applying qualitative and quantitative analysis
for competitive advantage
Andy Carmichael PHD FBCS
@andycarmich ac@openxprocess.com
Twitter: #lascot16
@andycarmich
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
2
Who is
going
to win?
• Tempo from the
Italian for time
• An essential
element of
strategy in chess
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
3
Who is
going to
win the
dogfight?
• Max speed? (level-climb-dive)
• Max altitude?
• Manoeuvrability? (agility)
• Pilot training
• Cockpit visibility
• Power-steering
References: Wikipedia, www.warbirddepot.com, Chet Richards, “Certain to Win”, OODA diagram drawn by Patrick Edwin Moran
John Boyd
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
4
Time is key to strategy in…
• Chess
• Warfare (Sun Tsu, Clauswitz,
Von Moltke, John Boyd)
– See Chet Richards, Stephen Bungay
•Business
We borrow
time…
We buy
time…
We invest
time…
We save
time…
We waste
time…
We spend
time…
Time “is” Money?
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
5
Time “is” Money?
Time (t) influences Value (V)
𝐷𝑒𝑙𝑎𝑦 𝐶𝑜𝑠𝑡 = −
𝜕𝑉
𝜕𝑡
Δ𝑡
“Cost of Delay” (CoD)
A Cost –
e.g. measured in
dollars
A rate of change
in value
e.g. measured in
dollars per week
or “Urgency”
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
6
Essential Kanban Condensed: The Glossary
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
7
Cost of Delay is a decision-aid
• Context:
• choosing the next “feature” / “experiment” to implement
(Product)?
• Choosing which product to fund / postpone (Portfolio)?
• Why?
• to maximise realised business benefit
• How?
• By estimating (forecasting) future cash (or value) flows and the
time delay before the benefits will occur
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
9
Context:
Portfolio level is where
decisions are made about
investing/disinvesting in
different products
Product level is where
decisions are made about
how to maximize the
value delivered by that
product
Portfolio
Product
Team
Personal
WEEKS/
DAYS
DAYS/
HOURS
MONTHS/
WEEKS
YEARS/
QUARTERS
Products - Goals
Strategic Direction
Options - Value
Product Management
Stories - Delivery
Day to day Leadership
Tasks - Focus
Individual Professionalism
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
10
How to approach Cost of Delay?
quantitatively? qualitatively?or
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
11
Value flow from a new development – “adoption”
Cost of
development
Increasing then
decreasing
profits/savings
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
12
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
13
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
14
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
15
The “Last Responsible Moment”
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
16
-100.0
0.0
100.0
200.0
300.0
400.0
500.0
600.0
0 20 40 60 80 100
CumulativeValue$(K)
Time in weeks
No delay
10-week delay
20-week delay
Cost of 10 week delay
Linear benefits profile (e.g. Staff-Saving feature)
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
17
0510
0
100
200
300
400
500
0 20 40 60 80 100
Urgency$(K)perweek
DelayCost$(K)
Length of Delay (weeks)
Approximately
linear Delay Cost
Approximately
constant “Urgency”
Linear benefits: Delay Cost & Urgency Profiles
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
18
DelayCost($)
Urgency($perweek)
Delay Cost and Urgency Profiles
General Delay Cost and Urgency Profiles
Low delay
impact before
this point
Low delay
impact after
this point
Roughly constant
urgency over this
period
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
19
WSJF with constant urgency (apply the formula)
prioritise highest urgency/duration
• Value realised by implementing
item 1 then item 2:
𝑉1 + 𝑉2 − 𝑈1 𝐷1 − 𝑈2(𝐷1 + 𝐷2)
• Difference in value by doing item 1 first,
compared to doing item 2 first
𝑈1
𝐷1
−
𝑈2
𝐷2
𝐷1 𝐷2
WSJF: Favours
urgent short jobs
12 wks
4 wks
$8pw
$3pw
D2
Urgency(CoD)
Time (weeks)
$96
$48
D1
U2
U1
D2
Urgency(CoD)
Time (weeks)
$112
$12
D1
U2
U1
Total Delay
Cost=$144
Total Delay
Cost=$140
Total Delay Cost
“wisjif”
or “CD3”
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
20
What is “Duration” in the WSJF formula
• Customer Lead Time?
• System Lead Time?
• Touch Time?
• Lead Time does not represent how long the team is “blocked” by a
different item
• In some circumstances* Touch Time (for which an estimate of effort is
a reasonable proxy) should be used
* where items are released on completion, rather than waiting for batch releases
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
21
How to approach Cost of Delay?
quantitatively? qualitatively?or
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
22
Value isn’t just increased profit…
• Protecting loss of profits
• Increased turnover
• Increased learning
• Reduced risk
• Cost saving
• New market option
• Cover competitors’ moves
• Staff retention
• Process improvement
• etc…
How would you put
a monetary value
on each of these?
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
23
Qualitative Approaches
to ordering work by Cost of Delay
1. Gut feel / HIPPO
2. SAFe
3. Delay Cost Profiles
4. Category Radar Plots
5. Hybrid approaches and combination with probabilistic forecasting
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
24
The SAFe formula for WSJF
• All quantities estimated on a 1-20 (sic) “Fibonacci” scale
• This is a qualitative rather than quantitative method
• The danger of this approach is the use of spurious numbers!
• As a qualitative method it may help people talk to each other about value…
Couldn’t they do that without playing cards?
𝑊𝑆𝐽𝐹 =
𝐶𝑜𝑠𝑡 𝑜𝑓 𝐷𝑒𝑙𝑎𝑦
𝑆𝑡𝑜𝑟𝑦 𝑃𝑜𝑖𝑛𝑡𝑠
No.
It doesn’t!
𝐶𝑜𝑠𝑡 𝑜𝑓 𝐷𝑒𝑙𝑎𝑦 = (𝑇𝑎𝑛𝑔𝑖𝑏𝑙𝑒 𝐵𝑒𝑛𝑒𝑓𝑖𝑡 + 𝑇𝑖𝑚𝑒 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙𝑖𝑡𝑦 + 𝐼𝑛𝑡𝑎𝑛𝑔𝑖𝑏𝑙𝑒 𝐵𝑒𝑛𝑒𝑓𝑖𝑡)
No.
It doesn’t!
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
25
Delay Cost Profiles
• Expedite: Very high urgency – no end point in sight
• Fixed Date: One off impact on fixed date
• Standard: Medium urgency; tails off (or cuts off) as value is lost
• Intangible: Low urgency, may be followed by high urgency
DelayCost($)
Delay (time)
Intangible
DelayCost($)
Delay (time)
Standard
DelayCost($)
Delay (time)
Fixed Date
DelayCost($)
Delay (time)
Expedite
We can define different
“Classes of Service” for
these archetypes
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
27
Category Radar Plots
• Context specific dimensions of
risk and value
• Dimensions…
• must be Ordinal
• not necessarily Interval/Ratio
• and not just Nominal
Source: David J Anderson http://www.slideshare.net/ScrumTrek/david-anderson-enterprise-service-planning-kanban
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
28
How urgent is it to start this item?
• the ordering of work items (WSJF: Urgency / LT)
• Choosing the class of service that is appropriate
for the work item
• Policies for more value, less risk
• Ensuring some intangible items are
always in play (interruptible if unexpected /
irrefutable demand)
• Pay attention to the “last responsible
moment” for starting a work item
(say, 85% probability point)
Source: @lki_dja
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
29
Know the context…
• Chaotic (high risk, uncertain)
domains are not susceptible to
quantitative analysis
• Obvious domains don’t require it
• Complicated domains are most
suitable to quantitative analysis
• Complex domains may benefit
from a qualitative or hybrid
approach
By Snowded (Own work) [CC BY-SA 3.0 (http://creativecommons.org/
licenses/by-sa/3.0)], via Wikimedia Commons
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
32Visit leankanban.com/guide for free download.
©2016ANDYCARMICHAELALLRIGHTSRESERVEDLEANAGILESCOTLAND2016
33
Questions and
Discussion

More Related Content

Similar to Time is an asset. delay is a cost.

Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...Association for Project Management
 
LKCE16 - Irrefutable Demand by Andy Carmichael
LKCE16 - Irrefutable Demand by Andy CarmichaelLKCE16 - Irrefutable Demand by Andy Carmichael
LKCE16 - Irrefutable Demand by Andy CarmichaelLean Kanban Central Europe
 
Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...
Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...
Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...Andy Carmichael
 
Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...
Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...
Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...LeanKanbanIndia
 
Data Science in Retail-as-a-Service (RaaS)
Data Science in Retail-as-a-Service (RaaS)Data Science in Retail-as-a-Service (RaaS)
Data Science in Retail-as-a-Service (RaaS)zhiking
 
The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...
The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...
The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...Monica Beckwith
 
Insights and Energy for Leaders in Crisis Time Webinar - Episode 7
Insights and Energy for Leaders in Crisis Time Webinar - Episode 7Insights and Energy for Leaders in Crisis Time Webinar - Episode 7
Insights and Energy for Leaders in Crisis Time Webinar - Episode 7Greatness Coaching
 
Deep Learning vs. Cheap Learning
Deep Learning vs. Cheap LearningDeep Learning vs. Cheap Learning
Deep Learning vs. Cheap LearningMapR Technologies
 
Rapid Threat Model Prototyping methodology
Rapid Threat Model Prototyping methodologyRapid Threat Model Prototyping methodology
Rapid Threat Model Prototyping methodologyGeoffrey Hill
 
Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0Steven Quenzel
 
The Keys to Digital Transformation
The Keys to Digital TransformationThe Keys to Digital Transformation
The Keys to Digital TransformationMapR Technologies
 
Anomaly Detection: How to find what you didn’t know to look for
Anomaly Detection: How to find what you didn’t know to look forAnomaly Detection: How to find what you didn’t know to look for
Anomaly Detection: How to find what you didn’t know to look forTed Dunning
 
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on AutomationGot 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on AutomationCAPINC
 
MoSCoW Rules: A quantitative expose
MoSCoW Rules: A quantitative exposeMoSCoW Rules: A quantitative expose
MoSCoW Rules: A quantitative exposeEsteban340583
 
Abbott Excellence Award - Achieving Dec 2016
Abbott Excellence Award - Achieving Dec 2016Abbott Excellence Award - Achieving Dec 2016
Abbott Excellence Award - Achieving Dec 2016sandeep ray
 
Portfolio management 101
Portfolio management 101Portfolio management 101
Portfolio management 101SmartOrg
 
Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...
Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...
Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...Theresa Zeidler-Shonat, ASA
 
ROI of the Cloud_vFinal
ROI of the Cloud_vFinalROI of the Cloud_vFinal
ROI of the Cloud_vFinalMatthew Conner
 

Similar to Time is an asset. delay is a cost. (20)

Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
Integrated Cost and Schedule Risk Analysis (ICSRA), Demystified webinar, 14 N...
 
LKCE16 - Irrefutable Demand by Andy Carmichael
LKCE16 - Irrefutable Demand by Andy CarmichaelLKCE16 - Irrefutable Demand by Andy Carmichael
LKCE16 - Irrefutable Demand by Andy Carmichael
 
Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...
Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...
Portfolio management: Balancing Irrefutable Demand with Cost of Delay #agilec...
 
Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...
Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...
Lean Kanban India 2016 | “The Surprising Effectiveness of Limiting WIP: What ...
 
Data Science in Retail-as-a-Service (RaaS)
Data Science in Retail-as-a-Service (RaaS)Data Science in Retail-as-a-Service (RaaS)
Data Science in Retail-as-a-Service (RaaS)
 
The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...
The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...
The Performance Engineer's Guide To (OpenJDK) HotSpot Garbage Collection - Th...
 
Insights and Energy for Leaders in Crisis Time Webinar - Episode 7
Insights and Energy for Leaders in Crisis Time Webinar - Episode 7Insights and Energy for Leaders in Crisis Time Webinar - Episode 7
Insights and Energy for Leaders in Crisis Time Webinar - Episode 7
 
Deep Learning vs. Cheap Learning
Deep Learning vs. Cheap LearningDeep Learning vs. Cheap Learning
Deep Learning vs. Cheap Learning
 
Rapid Threat Model Prototyping methodology
Rapid Threat Model Prototyping methodologyRapid Threat Model Prototyping methodology
Rapid Threat Model Prototyping methodology
 
Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0Final Presentation from Chester Group Rev 0
Final Presentation from Chester Group Rev 0
 
The Keys to Digital Transformation
The Keys to Digital TransformationThe Keys to Digital Transformation
The Keys to Digital Transformation
 
Anomaly Detection: How to find what you didn’t know to look for
Anomaly Detection: How to find what you didn’t know to look forAnomaly Detection: How to find what you didn’t know to look for
Anomaly Detection: How to find what you didn’t know to look for
 
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on AutomationGot 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
Got 99 Projects But Profit Ain't One? - CAPINC Presentation on Automation
 
MoSCoW Rules: A quantitative expose
MoSCoW Rules: A quantitative exposeMoSCoW Rules: A quantitative expose
MoSCoW Rules: A quantitative expose
 
Abbott Excellence Award - Achieving Dec 2016
Abbott Excellence Award - Achieving Dec 2016Abbott Excellence Award - Achieving Dec 2016
Abbott Excellence Award - Achieving Dec 2016
 
Portfolio management 101
Portfolio management 101Portfolio management 101
Portfolio management 101
 
The DEBS Grand Challenge 2018
The DEBS Grand Challenge 2018The DEBS Grand Challenge 2018
The DEBS Grand Challenge 2018
 
Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...
Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...
Asa wisconsin chapter april 2015 meeting presentation: residual values for ma...
 
ROI of the Cloud_vFinal
ROI of the Cloud_vFinalROI of the Cloud_vFinal
ROI of the Cloud_vFinal
 
Roi of-ux-dublin
Roi of-ux-dublinRoi of-ux-dublin
Roi of-ux-dublin
 

More from Andy Carmichael

What everyone needs to know about flow (lkce19)
What everyone needs to know about flow (lkce19)What everyone needs to know about flow (lkce19)
What everyone needs to know about flow (lkce19)Andy Carmichael
 
Feedback and cadence #agilecam 2018
Feedback and cadence #agilecam 2018Feedback and cadence #agilecam 2018
Feedback and cadence #agilecam 2018Andy Carmichael
 
Cadence workshop canvas a2
Cadence workshop canvas a2Cadence workshop canvas a2
Cadence workshop canvas a2Andy Carmichael
 
Feedback and cadence: how to improve improvement
Feedback and cadence: how to improve improvementFeedback and cadence: how to improve improvement
Feedback and cadence: how to improve improvementAndy Carmichael
 
Optics of Kanban (llkd18)
Optics of Kanban (llkd18)Optics of Kanban (llkd18)
Optics of Kanban (llkd18)Andy Carmichael
 
Whole Organisation Kanban (WOK)
Whole Organisation Kanban (WOK)Whole Organisation Kanban (WOK)
Whole Organisation Kanban (WOK)Andy Carmichael
 
Are you using Kanban? The Acid Test
Are you using Kanban? The Acid TestAre you using Kanban? The Acid Test
Are you using Kanban? The Acid TestAndy Carmichael
 
Exploring flow metrics in kanban systems
Exploring flow metrics in kanban systemsExploring flow metrics in kanban systems
Exploring flow metrics in kanban systemsAndy Carmichael
 
Cross-department Kanban Systems - 3 dimensions of scaling #llkd15
Cross-department Kanban Systems - 3 dimensions of scaling #llkd15Cross-department Kanban Systems - 3 dimensions of scaling #llkd15
Cross-department Kanban Systems - 3 dimensions of scaling #llkd15Andy Carmichael
 
Improving software development at scale - promise and pitfalls #llkd14
Improving software development at scale - promise and pitfalls #llkd14Improving software development at scale - promise and pitfalls #llkd14
Improving software development at scale - promise and pitfalls #llkd14Andy Carmichael
 
Improving software development at scale llkd14
Improving software development at scale llkd14Improving software development at scale llkd14
Improving software development at scale llkd14Andy Carmichael
 
Shortest possible definition of Kanban lkuk13
Shortest possible definition of Kanban lkuk13Shortest possible definition of Kanban lkuk13
Shortest possible definition of Kanban lkuk13Andy Carmichael
 

More from Andy Carmichael (12)

What everyone needs to know about flow (lkce19)
What everyone needs to know about flow (lkce19)What everyone needs to know about flow (lkce19)
What everyone needs to know about flow (lkce19)
 
Feedback and cadence #agilecam 2018
Feedback and cadence #agilecam 2018Feedback and cadence #agilecam 2018
Feedback and cadence #agilecam 2018
 
Cadence workshop canvas a2
Cadence workshop canvas a2Cadence workshop canvas a2
Cadence workshop canvas a2
 
Feedback and cadence: how to improve improvement
Feedback and cadence: how to improve improvementFeedback and cadence: how to improve improvement
Feedback and cadence: how to improve improvement
 
Optics of Kanban (llkd18)
Optics of Kanban (llkd18)Optics of Kanban (llkd18)
Optics of Kanban (llkd18)
 
Whole Organisation Kanban (WOK)
Whole Organisation Kanban (WOK)Whole Organisation Kanban (WOK)
Whole Organisation Kanban (WOK)
 
Are you using Kanban? The Acid Test
Are you using Kanban? The Acid TestAre you using Kanban? The Acid Test
Are you using Kanban? The Acid Test
 
Exploring flow metrics in kanban systems
Exploring flow metrics in kanban systemsExploring flow metrics in kanban systems
Exploring flow metrics in kanban systems
 
Cross-department Kanban Systems - 3 dimensions of scaling #llkd15
Cross-department Kanban Systems - 3 dimensions of scaling #llkd15Cross-department Kanban Systems - 3 dimensions of scaling #llkd15
Cross-department Kanban Systems - 3 dimensions of scaling #llkd15
 
Improving software development at scale - promise and pitfalls #llkd14
Improving software development at scale - promise and pitfalls #llkd14Improving software development at scale - promise and pitfalls #llkd14
Improving software development at scale - promise and pitfalls #llkd14
 
Improving software development at scale llkd14
Improving software development at scale llkd14Improving software development at scale llkd14
Improving software development at scale llkd14
 
Shortest possible definition of Kanban lkuk13
Shortest possible definition of Kanban lkuk13Shortest possible definition of Kanban lkuk13
Shortest possible definition of Kanban lkuk13
 

Recently uploaded

Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisCIToolkit
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentCIToolkit
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfcoolsnoopy1
 
Management 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing TeamsManagement 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing Teamsshakkardaddy
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBusiness of Software Conference
 
Management 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic ManagementManagement 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic Managementshakkardaddy
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Nagarjuna Reddy Aturi
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsCIToolkit
 
Leveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementLeveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...dsnow9802
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONsivani14565220
 
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Conny Dethloff
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingCIToolkit
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationPMIUKChapter
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Designshakkardaddy
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project ManagementCIToolkit
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesMassimo Canducci
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsCIToolkit
 

Recently uploaded (20)

Exploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram AnalysisExploring Variable Relationships with Scatter Diagram Analysis
Exploring Variable Relationships with Scatter Diagram Analysis
 
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light AssessmentFrom Red to Green: Enhancing Decision-Making with Traffic Light Assessment
From Red to Green: Enhancing Decision-Making with Traffic Light Assessment
 
Operations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdfOperations Management -- Sustainability and Supply Chain Management.pdf
Operations Management -- Sustainability and Supply Chain Management.pdf
 
Management 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing TeamsManagement 11th Edition - Chapter 13 - Managing Teams
Management 11th Edition - Chapter 13 - Managing Teams
 
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & EngineeringBoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
BoSUSA23 | Chris Spiek & Justin Dickow | Autobooks Product & Engineering
 
Management 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic ManagementManagement 11th Edition - Chapter 9 - Strategic Management
Management 11th Edition - Chapter 9 - Strategic Management
 
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
Advancing Enterprise Risk Management Practices- A Strategic Framework by Naga...
 
The Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data InsightsThe Role of Histograms in Exploring Data Insights
The Role of Histograms in Exploring Data Insights
 
Leveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous ImprovementLeveraging Gap Analysis for Continuous Improvement
Leveraging Gap Analysis for Continuous Improvement
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
Hajra Karrim: Transformative Leadership Driving Innovation and Efficiency in ...
 
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATIONHOTEL MANAGEMENT SYSTEM PPT PRESENTATION
HOTEL MANAGEMENT SYSTEM PPT PRESENTATION
 
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
Better SAFe than sorry - Why scaled agile frameworks do not necessarily impro...
 
Adapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-MakingAdapting to Change: Using PEST Analysis for Better Decision-Making
Adapting to Change: Using PEST Analysis for Better Decision-Making
 
Overview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentationOverview PMI Infinity - UK Chapter presentation
Overview PMI Infinity - UK Chapter presentation
 
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational DesignManagement 11th Edition - Chapter 11 - Adaptive Organizational Design
Management 11th Edition - Chapter 11 - Adaptive Organizational Design
 
The Final Activity in Project Management
The Final Activity in Project ManagementThe Final Activity in Project Management
The Final Activity in Project Management
 
How Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human ResourcesHow Technologies will change the relationship with Human Resources
How Technologies will change the relationship with Human Resources
 
The Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data SetsThe Role of Box Plots in Comparing Multiple Data Sets
The Role of Box Plots in Comparing Multiple Data Sets
 

Time is an asset. delay is a cost.