SlideShare a Scribd company logo
1 of 45
Download to read offline
Premier Oil (Vietnam) B.V.
INDEPENDENT PROJECT RISKS ASSESSMENT
BLOCK 12W GREENFIELD DEVELOPMENT
CHIM SAO & DUA PROSPECTS
Analyses and Presentation by Angus Macleod MAPM – Head Planning & Risk Management
PRESENTATION TO BLOCK 12W STAKEHOLDERS
SCHEDULE / COST RISKS ASSOCIATED WITH
PROJECT DEVELOPMENT & EXECUTION to 1st OIL
LEGAL NOTE : the material contained in this presentation is PROPRIETARY and CONFIDENTIAL and remains at all times the
INTELLECTUAL PROPERTY of PREMIER OIL (Vietnam) B.V>
Block 12W Field Schematic
1. Introduction (Basis of Report)
2. Purpose
3. Methodology
4. Risk Inputs
• Qualitative – Risk Registers / Cost Profiles
• Quantative – 3 point duration estimates / Class 2 Estimate
• Risk Analysis / Outputs
• Quantative – Schedule : Monte-Carlo Simulation in Pertmaster
• Quantative – Cost : Monte-Carlo Simulation in @RISK
• Risk Responses, Monitoring & Control
• What if…………
• Consultant Conclusions
• Schedule / Cost Risk Appendices
• Continuous Value Improvement Process
Contents of Report
Defined Project Risk Management an integral part of the Project Management Process
Introduction (Basis of Report)
Defined Project Risk Management Process as below
Introduction (Basis of Report contd....)
Identified some key components for Project Risk Management sucess
Introduction (Basis of Report)
contd......
Identified some key elements to obtain Schedule/Cost risk parameters and implement the
results for PSC and Project Management Decision Making
Introduction (Basis of Report) contd.......
Identified Project Risk Management Process as a Six Stage Cycle
Introduction (Basis of Report) contd ....
Identified the relationships between 6 stage Project Risk Management Process
Introduction (Basis of Report) contd ......
Total Schedule / Cost Effect (+ / -) of Risk
Purposes of this Report
• Provide historical basis for schedule/cost risk identification /mitigation
• Map the process of Risk Management used to optimise risk mitigations
• Illustrate consolidated risks that pertain to Execution of the Project
• Identify risks as threats / opportunities to optimise schedule/cost to 1st
Oil
• Illustrate the effective use of qualitative and Quantative methodologies used to
optimise risk mitigation
• Provide a basis for PSC decision-making processes with regard to
• Critical Path(s) to 1st
Oil ( based on probabilistic analyses)
• Mitigation of Schedule/Cost “sensitivities”
• Criticality of Project Sanction to achieve zero deferred production
• Initiate a “Continuous Value Improvement” Process
Purpose of Risk Report
Risk Process Methodology
General
Consolidate Risks and Collect p10,p50,p90 estimates
Developed a flowchart to map the Risk Process & Methodologies used
and consequences
LEGEND
Methodology 1 – Qualitative Risk Analysis
Utilised Project Risk Register with “Boston Square Matrix ” technique to model
Qualitative Risk Probability / Impact
Methodology 2 – Quantative Risk Analysis
Used Project Risk Register, Boston Square Matrix & p50,p10,p90 range of Activity
durations to run “Monte Carlo” simulations in Pertmaster (Schedule) and @RISK (Cost)
Risk Outputs- Deterministic (P50) Schedule – Page 1 of 3
RAN a DETERMINISTIC SCHEDULE in Primavera P6 and tested it in Pertmaster using equal distribution of P50 durations
and confirmed a DETERMINISTIC (unrisked) 1st
OIL DATE OF 25th
May 2010
Original Planned
Project Sanctiom
1st Jul 08
LLI
(pre-FID)
PO's Placed
(Cost Risk)
OPS LLI (pre-FID)
PO's
(Cost Risk)
Risk Outputs- Deterministic (P50) Schedule Page 2 of 3
(cont’d) DETERMINISTIC SCHEDULE in Primavera P6 and tested it in Pertmaster using equal distribution of P50 durations
and confirmed a DETERMINISTIC (unrisked) 1st
OIL DATE OF 25th
May 2010
LLI
(pre-FID)
PO's Placed
(Cost Risk)
Risk Outputs- Deterministic (P50) Schedule Page 3 0f 3)
(cont’d) DETERMINISTIC SCHEDULE in Primavera P6 and tested it in Pertmaster using equal distribution of P50 durations
and confirmed a DETERMINISTIC (unrisked) 1st
OIL DATE OF 25th
May 2010
Un-risked,
Deterministic
First Oil Date
Cost Risk
pre-FID
Contract
Award
CA Cost /
Schedule
Risk
Risk Outputs- Deterministic Distrubtion (P50) Schedule
DETERMINISTIC SCHEDULE in Primavera P6 RAN IN PERTMASTER using equal distribution of P50 durations and
confirmed a DETERMINISTIC (unrisked) 1st
OIL DATE OF 25th
May 2010
RAN a PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical
Path Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers
Quantative Risk Analysis – Probabilistic Schedule
- Critical Path Report – Page 1 of 5
Project
Sanction
July 08
RAN a PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical
Path Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers
Quantative Risk Analysis – Probabilistic Schedule
- Critical Path Report – Page 2 of 5
RAN PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path
Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers
Quantative Risk Analysis – Probabilistic Schedule
- Critical Path Report – Page 3 of 5
RAN PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path
Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers
Quantative Risk Analysis – Probabilistic Schedule
- Critical Path Report – Page 4 of 5
RAN PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path
Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers
Quantative Risk Analysis – Probabilistic Schedule
- Critical Path Report – Page 5 of 5
15 Oct 2009- 28 Feb 2010
P50 Marine Installation
Weather Window
P50 First Oil
28 May 2010
Risk Outputs “Base Case” Probabilistic Schedule Finish Dates
Extrapolated p10, p50, p90 Probabilistic Finish Dates from PROBABLISTIC SCHEDULE ANALYSIS based on Monte-Carlo
simulation of 3 point duration estimates – and produced 1st
Pass range of 1st
Oil dates
P10 1st Oil Date = 25th
May 2010
P50 1st
Oil Date = 7th July 2010
P90 1st
Oil Date = 26th
Aug 2010
1st Pass p10 p50 p90 “Base
Case”
Probabilistic Dates to 1st
Oil
Risk Outputs - Tornado Graph – Schedule Sensitivity Index
“Base Case”
RAN Monte-Carlo Simulations in PERTMASTER and produced TORNADO GRAPHS depicting SCHEDULE SENSITIVITY
INDEX – (Top Ten Schedule Sensitivities)
Turner & Townsend–ran DETERMINISTIC SCHEDULE SCENARIOS in Primavera P6 to model the BEST CASE schedule
scenarios under theoretical “what-if” conditions to identify threats to 1st
OIL DATE OF 25th
May 2010
If Project Sanction Delayed by 2
Months then deterministic “best
case” is 1st
Oil delayed by
4 months (deferred production)
What-if….Deterministic Schedule Scenario if Sanction (FID) Delay
RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction
delayed 2 months and P50 net result 1st
OIL DATE slips to Dec 2010
What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay
(Page 1 of 4)
Jacket &
Topsides LF
delayed until
Q2 2010
RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction
delayed 2 months and P50 net result 1st
OIL DATE slips to Dec 2010
Contigency :
Template drilling
$200k USD
cost trade-off to
maintain drilling
schedule
What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay
(Page 2 of 4)
RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction
delayed 2 months and P50 net result 1st
OIL DATE slips to Dec 2010
FPSO Contract Award
Schedule “frozen”
pending delayed FID
What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay
(Page 3 of 4)
RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction
delayed 2 months and P50 net result 1st
OIL DATE slips to Dec 2010
All Jacket &
Topsides heavy
lifts slip to
post-monsoon
2010
Most Likely “Sanction Delay Case”
1st
Oil Date slips 5 months to 24th
Oct 10
What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay
(Page 4 of 4)
Oct 09 - Feb 10
Weather Window
Risk Outputs – Quantative – Probabilistic Schedule Finish Dates
Extrapolated p10, p50, p90 Probabilistic Finish Dates from PROBABLISTIC SCHEDULE ANALYSIS based on Monte-Carlo
simulation of 3 point duration estimates – and produced new range of 1st
Oil dates
“Sanction Delay Case “ Probabilistic Dates to 1st
Oil
P90 1st
Oil Date = 6th
Dec 2010
P50 1st
Oil Date = 4th
Nov 2010
P10 1st Oil Date 5th
Oct 2010
Used the following Class 2 Estimate to run Cost Probability Simulations in @RISK
Input to @Risk Class II Cost Estimate Scenario
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 1
CBS -Extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost
Profiles (using values probabilistic around the base case costs)
CBS -extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost
Profiles (using values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 2
CBS-extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost
Profiles (using values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 3
CBS –extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost
Profiles (using values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 4
CBS –extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost
Profiles (using values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 5
CBS –extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost
Profiles (using values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 6
CBS - extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost
Profiles (using values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 7
CBS -extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of Probabilistic Cost Profiles (using
values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 8
CALCULATED based on Monte-Carlo simulation of Class 2 Cost Estimate a range of Probabilistic Cost Profiles (using
values probabilistic around the base case costs)
Quantative – Cost Risk Outputs on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK - Page 9
Based on Spearman's Rank Correlation simulation of cost centre sensitivity (relative Coefficient values) of Class 2 “Total
Project Value”
Quantative – Cost Risk Sensitivity on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK
Calculated Cumulative Ascending Cost Distribution Curve based on values inherent in
Class 2 “Total Project Value” Cost Estimate
Cost Distribution of “Total Project Value” on Class II Estimate
using Monte-Carlo Simulation in Palisade @RISK
Template Drilling Costs (if EPCI miss 2009-2010 weather
window)
• Risk Analysis / Outputs :
• Schedule : Monte-Carlo Simulation in PERTMASTER ( “Base Case” assumes
Sanction July 08”)
• P10 = 25th
May 2010 (originally the P50 Deterministic Case)
• P50 = 7th
July 2010
• P90 = 26th
August 2010
• Schedule : Monte-Carlo Simulation PERTMASTER (“Sanction Delay Case”
assumes Sep 08”)
• P10 = 5th Oct 2010
• P50 = 4th
Nov 2010
• P90 = 6th
Dec 2010
Chima Sao Field Development
“Best Case” and “Sanction Delay Case”
pe-mitagated (Determinstic) post-mitigated (Probablistic)
Cost / Schedule Analytics to acheive Optimal 1st Oil Date
using Oracle Primavera Risk Analysis and Palisade @RISK
Statistical Results of Cost / Schedule Risk Analyitics
Conclusions of this Report :
The original Deterministic Schedule is “aggressive but achievable” provided no slippage
occurs in Approvals Process and Project Sanction is not delayed beyond July 2008
• EPCI LL Procurement manageable with a schedule benefit and slight cost risk
ahead of Project Sanction
• Much effort has gone into ensuring that “team effort” at 2 x risk workshops
contributed to refinement both of quality, content and appropriate detail of Risk
Registers
• A “face-to-face” knowledge management process was adopted to refine accuracy
of schedule 3 point activity duration estimates – this proved a valuable exercise
and encouraged risk “ownership”
• Using a structured Risk Assessment Process and latest risk analysis methodologies
applied to state of the art Risk Analysis software the consultant was able to :
• Link Qualitative Risk Registers to Level 2 Schedule activities
• Run probabilistic algorithms on Quantative 3 point duration estimates and
Class 2 Estimate
CONCLUSIONS

More Related Content

Similar to POVO_CSRA_FDP_FINAL.pdf 2 Compressed-compressed.pdf

Lachit Deka_Project Controls_London Conference
Lachit Deka_Project Controls_London ConferenceLachit Deka_Project Controls_London Conference
Lachit Deka_Project Controls_London ConferenceLachit Deka
 
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk AnalysisJavier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk AnalysisJ. García - Verdugo
 
[Alghumgham]2011SPEpowerpoint
[Alghumgham]2011SPEpowerpoint[Alghumgham]2011SPEpowerpoint
[Alghumgham]2011SPEpowerpointEssam Alghumgham
 
Wet x dry completion with risk
Wet x dry completion with riskWet x dry completion with risk
Wet x dry completion with riskGláucio Bastos
 
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...angusmacleod22
 
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...ANGUSMACLEOD21
 
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsxCAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsxANGUS MACLEOD
 
Am website presentation (a) september 2016
Am website presentation (a)   september 2016Am website presentation (a)   september 2016
Am website presentation (a) september 2016anteromidstream
 
Company website presentation october 2016
Company website presentation   october 2016Company website presentation   october 2016
Company website presentation october 2016AnteroResources
 
How Material Science Helps Operators with End of Warranty Inspections
How Material Science Helps Operators with End of Warranty InspectionsHow Material Science Helps Operators with End of Warranty Inspections
How Material Science Helps Operators with End of Warranty InspectionsSentient Science
 
Am website presentation september 2016
Am website presentation   september 2016Am website presentation   september 2016
Am website presentation september 2016anteromidstream
 
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...Association for Project Management
 
Regulating Oil and Gas Production Emissions
Regulating Oil and Gas Production EmissionsRegulating Oil and Gas Production Emissions
Regulating Oil and Gas Production EmissionsBret Gallo
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
FWP 2017 l Pierre PEYSSON, WPD Offshore France
FWP 2017 l Pierre PEYSSON, WPD Offshore FranceFWP 2017 l Pierre PEYSSON, WPD Offshore France
FWP 2017 l Pierre PEYSSON, WPD Offshore FranceBluesign
 
Am website presentation (a) june 2016
Am website presentation (a)   june 2016Am website presentation (a)   june 2016
Am website presentation (a) june 2016anteromidstream
 
Am website presentation (b) june 2016
Am website presentation (b)   june 2016Am website presentation (b)   june 2016
Am website presentation (b) june 2016anteromidstream
 
Am website presentation (c) june 2016
Am website presentation (c)   june 2016Am website presentation (c)   june 2016
Am website presentation (c) june 2016anteromidstream
 

Similar to POVO_CSRA_FDP_FINAL.pdf 2 Compressed-compressed.pdf (20)

Lachit Deka_Project Controls_London Conference
Lachit Deka_Project Controls_London ConferenceLachit Deka_Project Controls_London Conference
Lachit Deka_Project Controls_London Conference
 
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk AnalysisJavier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Risk Analysis
 
[Alghumgham]2011SPEpowerpoint
[Alghumgham]2011SPEpowerpoint[Alghumgham]2011SPEpowerpoint
[Alghumgham]2011SPEpowerpoint
 
Wet x dry completion with risk
Wet x dry completion with riskWet x dry completion with risk
Wet x dry completion with risk
 
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
LKG COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LO...
 
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
COMBINED VALUE ASSURANCE PRESENTATION OF CAPITAL PROJECTS BY FRONT-END LOADIN...
 
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsxCAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
CAPITAL ENERGY PROJECTS VALUE ASSURANCE via FRONT END LOADING copy.ppsx
 
Am website presentation (a) september 2016
Am website presentation (a)   september 2016Am website presentation (a)   september 2016
Am website presentation (a) september 2016
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Company website presentation october 2016
Company website presentation   october 2016Company website presentation   october 2016
Company website presentation october 2016
 
How Material Science Helps Operators with End of Warranty Inspections
How Material Science Helps Operators with End of Warranty InspectionsHow Material Science Helps Operators with End of Warranty Inspections
How Material Science Helps Operators with End of Warranty Inspections
 
Ahmed Reedy CVf
Ahmed Reedy CVfAhmed Reedy CVf
Ahmed Reedy CVf
 
Am website presentation september 2016
Am website presentation   september 2016Am website presentation   september 2016
Am website presentation september 2016
 
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
Practical project risk assessment, presented by Simon White, 10th Oct 2016, A...
 
Regulating Oil and Gas Production Emissions
Regulating Oil and Gas Production EmissionsRegulating Oil and Gas Production Emissions
Regulating Oil and Gas Production Emissions
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
FWP 2017 l Pierre PEYSSON, WPD Offshore France
FWP 2017 l Pierre PEYSSON, WPD Offshore FranceFWP 2017 l Pierre PEYSSON, WPD Offshore France
FWP 2017 l Pierre PEYSSON, WPD Offshore France
 
Am website presentation (a) june 2016
Am website presentation (a)   june 2016Am website presentation (a)   june 2016
Am website presentation (a) june 2016
 
Am website presentation (b) june 2016
Am website presentation (b)   june 2016Am website presentation (b)   june 2016
Am website presentation (b) june 2016
 
Am website presentation (c) june 2016
Am website presentation (c)   june 2016Am website presentation (c)   june 2016
Am website presentation (c) june 2016
 

Recently uploaded

Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital AgeCredit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital AgeBoston Institute of Analytics
 
Bios of leading Astrologers & Researchers
Bios of leading Astrologers & ResearchersBios of leading Astrologers & Researchers
Bios of leading Astrologers & Researchersdarmandersingh4580
 
MATERI MANAJEMEN OF PENYAKIT TETANUS.ppt
MATERI  MANAJEMEN OF PENYAKIT TETANUS.pptMATERI  MANAJEMEN OF PENYAKIT TETANUS.ppt
MATERI MANAJEMEN OF PENYAKIT TETANUS.pptRachmaGhifari
 
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样jk0tkvfv
 
一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样
一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样
一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样yhavx
 
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...Klinik kandungan
 
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...ssuserf63bd7
 
obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di Ban...
obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di  Ban...obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di  Ban...
obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di Ban...siskavia95
 
RESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptx
RESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptxRESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptx
RESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptxronsairoathenadugay
 
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...Klinik Aborsi
 
社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token PredictionNABLAS株式会社
 
Fuel Efficiency Forecast: Predictive Analytics for a Greener Automotive Future
Fuel Efficiency Forecast: Predictive Analytics for a Greener Automotive FutureFuel Efficiency Forecast: Predictive Analytics for a Greener Automotive Future
Fuel Efficiency Forecast: Predictive Analytics for a Greener Automotive FutureBoston Institute of Analytics
 
Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...
Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...
Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...Obat Aborsi 088980685493 Jual Obat Aborsi
 
Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024patrickdtherriault
 
How to Transform Clinical Trial Management with Advanced Data Analytics
How to Transform Clinical Trial Management with Advanced Data AnalyticsHow to Transform Clinical Trial Management with Advanced Data Analytics
How to Transform Clinical Trial Management with Advanced Data AnalyticsBrainSell Technologies
 
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...mikehavy0
 
Seven tools of quality control.slideshare
Seven tools of quality control.slideshareSeven tools of quality control.slideshare
Seven tools of quality control.slideshareraiaryan448
 
Audience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptxAudience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptxStephen266013
 
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证acoha1
 

Recently uploaded (20)

Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital AgeCredit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
 
Bios of leading Astrologers & Researchers
Bios of leading Astrologers & ResearchersBios of leading Astrologers & Researchers
Bios of leading Astrologers & Researchers
 
MATERI MANAJEMEN OF PENYAKIT TETANUS.ppt
MATERI  MANAJEMEN OF PENYAKIT TETANUS.pptMATERI  MANAJEMEN OF PENYAKIT TETANUS.ppt
MATERI MANAJEMEN OF PENYAKIT TETANUS.ppt
 
Abortion pills in Riyadh Saudi Arabia (+966572737505 buy cytotec
Abortion pills in Riyadh Saudi Arabia (+966572737505 buy cytotecAbortion pills in Riyadh Saudi Arabia (+966572737505 buy cytotec
Abortion pills in Riyadh Saudi Arabia (+966572737505 buy cytotec
 
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
 
一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样
一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样
一比一原版(Monash毕业证书)莫纳什大学毕业证原件一模一样
 
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
Jual obat aborsi Bandung ( 085657271886 ) Cytote pil telat bulan penggugur ka...
 
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
Statistics Informed Decisions Using Data 5th edition by Michael Sullivan solu...
 
obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di Ban...
obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di  Ban...obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di  Ban...
obat aborsi Banjarmasin wa 082135199655 jual obat aborsi cytotec asli di Ban...
 
RESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptx
RESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptxRESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptx
RESEARCH-FINAL-DEFENSE-PPT-TEMPLATE.pptx
 
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
Jual Obat Aborsi Bandung (Asli No.1) Wa 082134680322 Klinik Obat Penggugur Ka...
 
社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction
 
Fuel Efficiency Forecast: Predictive Analytics for a Greener Automotive Future
Fuel Efficiency Forecast: Predictive Analytics for a Greener Automotive FutureFuel Efficiency Forecast: Predictive Analytics for a Greener Automotive Future
Fuel Efficiency Forecast: Predictive Analytics for a Greener Automotive Future
 
Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...
Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...
Jual Obat Aborsi Lhokseumawe ( Asli No.1 ) 088980685493 Obat Penggugur Kandun...
 
Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024
 
How to Transform Clinical Trial Management with Advanced Data Analytics
How to Transform Clinical Trial Management with Advanced Data AnalyticsHow to Transform Clinical Trial Management with Advanced Data Analytics
How to Transform Clinical Trial Management with Advanced Data Analytics
 
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
Abortion Clinic in Kempton Park +27791653574 WhatsApp Abortion Clinic Service...
 
Seven tools of quality control.slideshare
Seven tools of quality control.slideshareSeven tools of quality control.slideshare
Seven tools of quality control.slideshare
 
Audience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptxAudience Researchndfhcvnfgvgbhujhgfv.pptx
Audience Researchndfhcvnfgvgbhujhgfv.pptx
 
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
如何办理(WashU毕业证书)圣路易斯华盛顿大学毕业证成绩单本科硕士学位证留信学历认证
 

POVO_CSRA_FDP_FINAL.pdf 2 Compressed-compressed.pdf

  • 1. Premier Oil (Vietnam) B.V. INDEPENDENT PROJECT RISKS ASSESSMENT BLOCK 12W GREENFIELD DEVELOPMENT CHIM SAO & DUA PROSPECTS Analyses and Presentation by Angus Macleod MAPM – Head Planning & Risk Management PRESENTATION TO BLOCK 12W STAKEHOLDERS SCHEDULE / COST RISKS ASSOCIATED WITH PROJECT DEVELOPMENT & EXECUTION to 1st OIL LEGAL NOTE : the material contained in this presentation is PROPRIETARY and CONFIDENTIAL and remains at all times the INTELLECTUAL PROPERTY of PREMIER OIL (Vietnam) B.V>
  • 2. Block 12W Field Schematic
  • 3. 1. Introduction (Basis of Report) 2. Purpose 3. Methodology 4. Risk Inputs • Qualitative – Risk Registers / Cost Profiles • Quantative – 3 point duration estimates / Class 2 Estimate • Risk Analysis / Outputs • Quantative – Schedule : Monte-Carlo Simulation in Pertmaster • Quantative – Cost : Monte-Carlo Simulation in @RISK • Risk Responses, Monitoring & Control • What if………… • Consultant Conclusions • Schedule / Cost Risk Appendices • Continuous Value Improvement Process Contents of Report
  • 4. Defined Project Risk Management an integral part of the Project Management Process Introduction (Basis of Report)
  • 5. Defined Project Risk Management Process as below Introduction (Basis of Report contd....)
  • 6. Identified some key components for Project Risk Management sucess Introduction (Basis of Report) contd......
  • 7. Identified some key elements to obtain Schedule/Cost risk parameters and implement the results for PSC and Project Management Decision Making Introduction (Basis of Report) contd.......
  • 8. Identified Project Risk Management Process as a Six Stage Cycle Introduction (Basis of Report) contd ....
  • 9. Identified the relationships between 6 stage Project Risk Management Process Introduction (Basis of Report) contd ...... Total Schedule / Cost Effect (+ / -) of Risk
  • 10. Purposes of this Report • Provide historical basis for schedule/cost risk identification /mitigation • Map the process of Risk Management used to optimise risk mitigations • Illustrate consolidated risks that pertain to Execution of the Project • Identify risks as threats / opportunities to optimise schedule/cost to 1st Oil • Illustrate the effective use of qualitative and Quantative methodologies used to optimise risk mitigation • Provide a basis for PSC decision-making processes with regard to • Critical Path(s) to 1st Oil ( based on probabilistic analyses) • Mitigation of Schedule/Cost “sensitivities” • Criticality of Project Sanction to achieve zero deferred production • Initiate a “Continuous Value Improvement” Process Purpose of Risk Report
  • 11. Risk Process Methodology General Consolidate Risks and Collect p10,p50,p90 estimates Developed a flowchart to map the Risk Process & Methodologies used
  • 12. and consequences LEGEND Methodology 1 – Qualitative Risk Analysis Utilised Project Risk Register with “Boston Square Matrix ” technique to model Qualitative Risk Probability / Impact
  • 13. Methodology 2 – Quantative Risk Analysis Used Project Risk Register, Boston Square Matrix & p50,p10,p90 range of Activity durations to run “Monte Carlo” simulations in Pertmaster (Schedule) and @RISK (Cost)
  • 14. Risk Outputs- Deterministic (P50) Schedule – Page 1 of 3 RAN a DETERMINISTIC SCHEDULE in Primavera P6 and tested it in Pertmaster using equal distribution of P50 durations and confirmed a DETERMINISTIC (unrisked) 1st OIL DATE OF 25th May 2010 Original Planned Project Sanctiom 1st Jul 08 LLI (pre-FID) PO's Placed (Cost Risk) OPS LLI (pre-FID) PO's (Cost Risk)
  • 15. Risk Outputs- Deterministic (P50) Schedule Page 2 of 3 (cont’d) DETERMINISTIC SCHEDULE in Primavera P6 and tested it in Pertmaster using equal distribution of P50 durations and confirmed a DETERMINISTIC (unrisked) 1st OIL DATE OF 25th May 2010 LLI (pre-FID) PO's Placed (Cost Risk)
  • 16. Risk Outputs- Deterministic (P50) Schedule Page 3 0f 3) (cont’d) DETERMINISTIC SCHEDULE in Primavera P6 and tested it in Pertmaster using equal distribution of P50 durations and confirmed a DETERMINISTIC (unrisked) 1st OIL DATE OF 25th May 2010 Un-risked, Deterministic First Oil Date Cost Risk pre-FID Contract Award CA Cost / Schedule Risk
  • 17. Risk Outputs- Deterministic Distrubtion (P50) Schedule DETERMINISTIC SCHEDULE in Primavera P6 RAN IN PERTMASTER using equal distribution of P50 durations and confirmed a DETERMINISTIC (unrisked) 1st OIL DATE OF 25th May 2010
  • 18. RAN a PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers Quantative Risk Analysis – Probabilistic Schedule - Critical Path Report – Page 1 of 5 Project Sanction July 08
  • 19. RAN a PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers Quantative Risk Analysis – Probabilistic Schedule - Critical Path Report – Page 2 of 5
  • 20. RAN PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers Quantative Risk Analysis – Probabilistic Schedule - Critical Path Report – Page 3 of 5
  • 21. RAN PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers Quantative Risk Analysis – Probabilistic Schedule - Critical Path Report – Page 4 of 5
  • 22. RAN PROBABLISTIC SCHEDULE with Monte-Carlo Simulations in PERTMASTER using original Deterministic Critical Path Schedule + collected 3 point estimates + Post-Mitigated Qualative Risk Registers Quantative Risk Analysis – Probabilistic Schedule - Critical Path Report – Page 5 of 5 15 Oct 2009- 28 Feb 2010 P50 Marine Installation Weather Window P50 First Oil 28 May 2010
  • 23. Risk Outputs “Base Case” Probabilistic Schedule Finish Dates Extrapolated p10, p50, p90 Probabilistic Finish Dates from PROBABLISTIC SCHEDULE ANALYSIS based on Monte-Carlo simulation of 3 point duration estimates – and produced 1st Pass range of 1st Oil dates P10 1st Oil Date = 25th May 2010 P50 1st Oil Date = 7th July 2010 P90 1st Oil Date = 26th Aug 2010 1st Pass p10 p50 p90 “Base Case” Probabilistic Dates to 1st Oil
  • 24. Risk Outputs - Tornado Graph – Schedule Sensitivity Index “Base Case” RAN Monte-Carlo Simulations in PERTMASTER and produced TORNADO GRAPHS depicting SCHEDULE SENSITIVITY INDEX – (Top Ten Schedule Sensitivities)
  • 25. Turner & Townsend–ran DETERMINISTIC SCHEDULE SCENARIOS in Primavera P6 to model the BEST CASE schedule scenarios under theoretical “what-if” conditions to identify threats to 1st OIL DATE OF 25th May 2010 If Project Sanction Delayed by 2 Months then deterministic “best case” is 1st Oil delayed by 4 months (deferred production) What-if….Deterministic Schedule Scenario if Sanction (FID) Delay
  • 26. RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction delayed 2 months and P50 net result 1st OIL DATE slips to Dec 2010 What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay (Page 1 of 4) Jacket & Topsides LF delayed until Q2 2010
  • 27. RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction delayed 2 months and P50 net result 1st OIL DATE slips to Dec 2010 Contigency : Template drilling $200k USD cost trade-off to maintain drilling schedule What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay (Page 2 of 4)
  • 28. RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction delayed 2 months and P50 net result 1st OIL DATE slips to Dec 2010 FPSO Contract Award Schedule “frozen” pending delayed FID What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay (Page 3 of 4)
  • 29. RAN PROBABLISTIC SCHEDULE SCENARIO in PERTMASTER to model the P50 CASE schedule if Project Sanction delayed 2 months and P50 net result 1st OIL DATE slips to Dec 2010 All Jacket & Topsides heavy lifts slip to post-monsoon 2010 Most Likely “Sanction Delay Case” 1st Oil Date slips 5 months to 24th Oct 10 What-if Scenario ….Probabilistic Schedule (P50) if Sanction Delay (Page 4 of 4) Oct 09 - Feb 10 Weather Window
  • 30. Risk Outputs – Quantative – Probabilistic Schedule Finish Dates Extrapolated p10, p50, p90 Probabilistic Finish Dates from PROBABLISTIC SCHEDULE ANALYSIS based on Monte-Carlo simulation of 3 point duration estimates – and produced new range of 1st Oil dates “Sanction Delay Case “ Probabilistic Dates to 1st Oil P90 1st Oil Date = 6th Dec 2010 P50 1st Oil Date = 4th Nov 2010 P10 1st Oil Date 5th Oct 2010
  • 31. Used the following Class 2 Estimate to run Cost Probability Simulations in @RISK Input to @Risk Class II Cost Estimate Scenario
  • 32. Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 1 CBS -Extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost Profiles (using values probabilistic around the base case costs)
  • 33. CBS -extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 2
  • 34. CBS-extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 3
  • 35. CBS –extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 4
  • 36. CBS –extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 5
  • 37. CBS –extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 6
  • 38. CBS - extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of p10, p50, p90 Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 7
  • 39. CBS -extrapolated based on Monte-Carlo simulation of Class 2 Cost Estimate a range of Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 8
  • 40. CALCULATED based on Monte-Carlo simulation of Class 2 Cost Estimate a range of Probabilistic Cost Profiles (using values probabilistic around the base case costs) Quantative – Cost Risk Outputs on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK - Page 9
  • 41. Based on Spearman's Rank Correlation simulation of cost centre sensitivity (relative Coefficient values) of Class 2 “Total Project Value” Quantative – Cost Risk Sensitivity on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK
  • 42. Calculated Cumulative Ascending Cost Distribution Curve based on values inherent in Class 2 “Total Project Value” Cost Estimate Cost Distribution of “Total Project Value” on Class II Estimate using Monte-Carlo Simulation in Palisade @RISK
  • 43. Template Drilling Costs (if EPCI miss 2009-2010 weather window)
  • 44. • Risk Analysis / Outputs : • Schedule : Monte-Carlo Simulation in PERTMASTER ( “Base Case” assumes Sanction July 08”) • P10 = 25th May 2010 (originally the P50 Deterministic Case) • P50 = 7th July 2010 • P90 = 26th August 2010 • Schedule : Monte-Carlo Simulation PERTMASTER (“Sanction Delay Case” assumes Sep 08”) • P10 = 5th Oct 2010 • P50 = 4th Nov 2010 • P90 = 6th Dec 2010 Chima Sao Field Development “Best Case” and “Sanction Delay Case” pe-mitagated (Determinstic) post-mitigated (Probablistic) Cost / Schedule Analytics to acheive Optimal 1st Oil Date using Oracle Primavera Risk Analysis and Palisade @RISK Statistical Results of Cost / Schedule Risk Analyitics
  • 45. Conclusions of this Report : The original Deterministic Schedule is “aggressive but achievable” provided no slippage occurs in Approvals Process and Project Sanction is not delayed beyond July 2008 • EPCI LL Procurement manageable with a schedule benefit and slight cost risk ahead of Project Sanction • Much effort has gone into ensuring that “team effort” at 2 x risk workshops contributed to refinement both of quality, content and appropriate detail of Risk Registers • A “face-to-face” knowledge management process was adopted to refine accuracy of schedule 3 point activity duration estimates – this proved a valuable exercise and encouraged risk “ownership” • Using a structured Risk Assessment Process and latest risk analysis methodologies applied to state of the art Risk Analysis software the consultant was able to : • Link Qualitative Risk Registers to Level 2 Schedule activities • Run probabilistic algorithms on Quantative 3 point duration estimates and Class 2 Estimate CONCLUSIONS