1. A
SEMINAR ON
INDUSTRIAL TRAINING
AT
NTPC FARIDABAD
SUBMITTED BY :-
ANIL JADON
1204320011 (FINAL YR)
ELECTRICAL ENGG.
HEAD OF DEPARTMENT :
Dr. DEEPAK NAGARIA
HEAD, ELECTRICAL ENGG DEPTT.
2. INDEX
ABOUT THE COMPANY
INTRODUCTION OF NTPC FARIDABAD
WORKING OF POWER PLANT
FUEL USED
ELECTRICAL SYSTEM
DISTRIBUTION OF ELECTRICITY
CONTROL AND INSTRUMENTATION
ADVANTAGES AND PRECAUTION
CONCLUSION
3. ABOUT NTPC
• NTPC Limited is the largest thermal power generating company of India. A public
sector company, it was incorporated in the year 1975 to accelerate power development
in the country as a wholly owned company of the Government of India.
• NTPC's core business is generation and sale of electricity to state-owned power
distribution companies and State Electricity Boards in India.
• It is the largest power company in India with an electric power generating capacity of
43,803 MW.
4. NTPC FARIDABAD
The power plant is one of the GAS based power plant.
The NTPC F has an total installed capacity of 432 MW, 2*132 MW from GS
and 156 MW from ST .
The natural gas for the plant is taken from the IOCL .
All the turbines are of Russian Design.
Both turbine and boilers have been
supplied by BHEL.
It receive cooling water from Rampur
distributaries of Gurgaon canal.
The cost of power from NTPC FBD is
Rs 2.05/kWh.
5. ANTI-SALIENT FEATURES
Cost of Generation: Rs. 2.05 / Kwh
Mode of Operation: Base Load
Rated Output: 135 MVA for GTG & 191.6 MVA for STG
Rated Terminal Vol.: 10.5 KV for GTG & 15.75 KV FOR STG
Rated Speed: 3000 rpm
Type of Cooling: Air Cooled
Black start facility:3.5 MW Diesel Generator Set: 2000 rpm
1kw power = 1975kcal of fuel
6. OPERATION OF A POWER PLANT
Basic Principle
As per FARADAY’s Law-“Whenever the amount of magnetic flux linked with a circuit
changes, an EMF is produced in the circuit”.
Natural gas is pumped into the gas turbine , where it is mixed with air and burned,
converting its chemical energy into heat energy.
Burning natural gas produces a mixture of gases called the combustion gas.
The heat makes the combustion gas expand.
In the enclosed gas turbine, this causes a build-up of pressure.
The pressure drives the combustion gas over the blades of the gas turbine, causing it to spin,
converting some of the heat energy into mechanical energy.
A shaft connects the gas turbine to the gas turbine generator , so when the turbine spins, the
generator does too.
The generator uses an electromagnetic field to convert this mechanical energy into electrical
energy.
10. FUEL USED
Natural gas
Natural gas is an ideal fuel in gas turbine. It contains primarily Methane (CH4) other
gases are ethane (C2H6), Nitrogen (N2), Carbon dioxide (CO2) and Sulphur(S).
Naphtha
FGPP works on natural gas but if there is shortage of natural gas then plant is run on
Naphtha. Naphtha as compared to natural gas has less calorific value but there is no
alternate fuel other than Naphtha. It is cheaper than any other fuel and the amount of
flue gases that comesout of the Naphtha can also be sent out to boiler to boil the
water for manufacturing of steam for running the steam turbine.
11. SWITCHYARD
The switch yard is the place from where the electricity is send outside. We know that electrical energy
can’t be stored like cells, so what we generate should be consumed instantaneously. But as the load is not
constant, therefore we generate electricity according to need i.e. the generation depends upon load. It has
both outdoor and indoor equipments.
Outdoor Equipments
Bus Bar
Circuit Breaker
Lightening Arrester
Earth Switch
Capacitor Voltage Transformer
Wave Trap
PLCC
Current Transformer
Isolators
Potential Transformer
Indoor Equipments
Relays
Control Panels
ELECTICAL SYSTEM
12. OUTDOOR EQUIPMENTS
BUS BAR
There are three buses viz. two main buses
(bus 1 and bus 2) and one transfer bus.
The two main buses are further divided
into two sections thus giving us a
total of five buses.
CIRCUIT BREAKER
An electric power system needs some form of
switchgear in order to operate it safely & efficiently
under both normal and abnormal conditions. Circuit
breaker is an arrangement by which we can break
the circuit or flow of current.
At NTPC FBD uses SF6 CB and GAS CB.
13. CVT
The CVT is used for line voltage measurements
on loaded conditions. CVT is used for line voltage
measurements on loaded conditions.
In PT full line voltage and in
CVT reduced voltage is applied.
LA
Lightening Arrester
Air Break Earthling Switch
These are used to ground the circuit
and to discharge the CB when CB is in
off condition.
WAVE TRAP
14. PLCC
POWER LINE CARRIER COMMUNICATION
CT
These are used for stepping down AC current
from higher value to lower value for
measurement, protection and control.
ISOLATORS
TRANSFORMERS
15. CONTROL AND INSTRUMENTATION
The main functions of the C&I dept. at NTPC Faridabad are:
1. Measurement and display of various parameters.
2. To control the various parameters by Automatic feedback controlling which involves the
taking of decision based on inputs from measurements by the processor.
3. Protection of various equipments (pumps, generators etc.) and workers from hazards by
automatically tripping a cycle when hazardous conditions are reached.
4. Alarm generation in case of a mechanical or an electrical failure.
The Faridabad plant has outsourced its automaton to various companies on a Package Based
Deal.
17. ADVANTAGES
Advantages of using Natural Gas for Generating Electricity
Less Harmful than Coal or Oil
Easy Storage and Transport
Residential Use
Vehicle Fuel
Burns Cleaner
Instant energy
Precision in Kitchen
Industrial use
Abundant.
Safer
Versatile
Cheaper
Neater
Used to Produce Electricity
18. PRECAUTIONS
Normally, the natural gas is non toxic. However, if having high content of hydrogen
sulfide; the gas can harm people whom inhale the gas. It can irritate skin, eyes, the
respiratory tract and lung.
Fire and explosion. Natural gas can be flammable when it leaks and mixes with air,
cause fire at a right proportion of air and natural gas and there is a source of ignition or
a flame. It can cause explosion if it accumulates in a confined space such as in the
building where there is not enough ventilation.
19. CONCLUSION
On completion of my vocational training at NTPC Faridabad, I have come to know about
how the very necessity of our lives now a days i.e. how electricity is generated & what
all processes are needed to generate and run the plant on a 24x7 basis. NTPC Faridabad
is one the plants in India to be under highest load factor for the maximum duration of
time and that to operating at highest plant efficiencies. This plant is an example in terms
of working efficiency and management of resources to all other thermal plants in our
country. The operating of the NTPC as compared to the rest of country is the highest
with 95 % the highest since its inception. The training gave me an opportunity to clear
my concepts from practical point of view with the availability of machinery of diverse
ratings.