Project Management - CPM/PERT
Dr. M Varaprasada Rao
DEAN - ACADEMICS
GIET RAJAHMUNDRY
Dr. Varaprasada Rao GGSESTC 2
What exactly is a project?
PM 1 – A building supervisor is in-charge for construction of a retail
development in the centre of Rajahmundry. There are 26 retail units and
a super market in the complex. The main responsibilities are to co-
ordinate the work of the various contractors to ensure that the project is
completed to specification, within budget and on time.
PM 2 – Dr. Rao directing a team of research scientists. They are
running trials on a new analgesic drug on behalf of a pharmaceutical
company. It is the responsibility to design the experiments and make
sure that proper scientific and legal procedures are followed, so that the
results can be subjected to independent statistical analysis.
PM 3- The international aid agency which employs me is sending me to
New Delhi to organize the introduction of multimedia resources at a
teachers’ training college. My role is quite complex. I have to make sure
that appropriate resources are purchased- and in some cases developed
within the college. I also have to encourage the acceptance of these
resources by lecturers and students within the college.5/10/2016
Dr. Varaprasada Rao GGSESTC 3
Project is not defined by the type of outcome it is set up to achieve
PM 1 – A building supervisor is in-charge for construction of a retail
development in the centre of Rajahmundry. There are 26 retail units and
a super market in the complex. The main responsibilities are to co-
ordinate the work of the various contractors to ensure that the project is
completed to specification, within budget and on time.
PM 2 – Dr. Rao directing a team of research scientists. They are
running trials on a new analgesic drug on behalf of a pharmaceutical
company. It is the responsibility to design the experiments and make
sure that proper scientific and legal procedures are followed, so that the
results can be subjected to independent statistical analysis.
PM 3- The international aid agency which employs me is sending me to
New Delhi to organize the introduction of multimedia resources at a
teachers’ training college. My role is quite complex. I have to make sure
that appropriate resources are purchased- and in some cases developed
within the college. I also have to encourage the acceptance of these
resources by lecturers and students within the college.5/10/2016
Dr. Varaprasada Rao GGSESTC 4
Characteristic of a project
A project is an endeavour involving a connected sequence of
activities and a range of resources, which is designed to achieve
a specific outcome and which operates within a time frame,
cost and quality constraints and which is often used to
introduce change.
A unique, one-time operational activity or effort
Requires the completion of a large number of
interrelated activities
Established to achieve specific objective
Resources, such as time and/or money, are limited
Typically has its own management structure
Need leadership
Project
5/10/2016
Dr. Varaprasada Rao GGSESTC 5
Examples
– constructing houses, factories, shopping malls,
athletic stadiums or arenas
– developing military weapons systems, aircrafts,
new ships
– launching satellite systems
– constructing oil pipelines
– developing and implementing new computer
systems
– planning concert, football games, or basketball
tournaments
– introducing new products into market
5/10/2016
Dr. Varaprasada Rao GGSESTC 6
What is project management
• The application of a collection of tools and
techniques to direct the use of diverse resources
towards the accomplishment of a unique,
complex, one time task within time, cost and
quality constraints.
• Its origins lie in World War II, when the
military authorities used the techniques of
operational research to plan the optimum use
of resources.
• One of these techniques was the use of networks
to represent a system of related activities
5/10/2016
Dr. Varaprasada Rao GGSESTC 7
Project Management Process
• Project planning - Project scheduling - Project control
• Project team
– made up of individuals from various areas and departments within a
company
• Matrix organization
– a team structure with members from functional areas, depending on skills
required
• Project Manager
– most important member of project team
• Scope statement
– a document that provides an understanding, justification, and expected result
of a project
• Statement of work
– written description of objectives of a project
• Organizational Breakdown Structure
– a chart that shows which organizational units are responsible for work items
• Responsibility Assignment Matrix
– shows who is responsible for work in a project
5/10/2016
Dr. Varaprasada Rao GGSESTC 8
Work breakdown structure
• A method of breaking down a project into individual
elements ( components, subcomponents, activities and
tasks) in a hierarchical structure which can be scheduled
and cost
• It defines tasks that can be completed independently of
other tasks, facilitating resource allocation, assignment
of responsibilities and measurement and control of the
project
• It is foundation of project planning
• It is developed before identification of dependencies and
estimation of activity durations
• It can be used to identity the tasks in the CPM and PERT
5/10/2016
Dr. Varaprasada Rao GGSESTC 9
Work Breakdown Structure for Computer Order
Processing System Project
5/10/2016
Dr. Varaprasada Rao GGSESTC 10
Project Planning
• Resource Availability and/or Limits
– Due date, late penalties, early completion
incentives
– Budget
• Activity Information
– Identify all required activities
– Estimate the resources required (time) to complete
each activity
– Immediate predecessor(s) to each activity needed
to create interrelationships
5/10/2016
Dr. Varaprasada Rao GGSESTC 11
Project Scheduling and Control Techniques
Gantt Chart
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
5/10/2016
Dr. Varaprasada Rao GGSESTC 12
Graph or bar chart with a bar for each project activity that shows
passage of time
Provides visual display of project schedule
Gantt Chart
5/10/2016
Dr. Varaprasada Rao GGSESTC 13
History of CPM/PERT
• Critical Path Method (CPM)
– E I Du Pont de Nemours & Co. (1957) for construction of new
chemical plant and maintenance shut-down
– Deterministic task times
– Activity-on-node network construction
– Repetitive nature of jobs
• Project Evaluation and Review Technique (PERT)
– U S Navy (1958) for the POLARIS missile program
– Multiple task time estimates (probabilistic nature)
– Activity-on-arrow network construction
– Non-repetitive jobs (R & D work)
5/10/2016
Dr. Varaprasada Rao GGSESTC 14
• Event
– Signals the beginning or ending of an activity
– Designates a point in time
– Represented by a circle (node)
• Network
– Shows the sequential relationships among activities using nodes
and arrows
Activity-on-node (AON)
nodes represent activities, and arrows show precedence
relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points in
time
Project Network
5/10/2016
Dr. Varaprasada Rao GGSESTC 15
Project Network
• Network analysis is the general name given to certain specific
techniques which can be used for the planning, management and
control of projects
• Use of nodes and arrows
Arrows  An arrow leads from tail to head directionally
– Indicate ACTIVITY, a time consuming effort that is required to perform a
part of the work.
Nodes  A node is represented by a circle
- Indicate EVENT, a point in time where one or more activities start and/or
finish.
• Activity
– A task or a certain amount of work required in the project
– Requires time to complete
– Represented by an arrow
• Dummy Activity
– Indicates only precedence relationships
– Does not require any time of effort
5/10/2016
5/10/2016 Dr. Varaprasada Rao GGSESTC 16
5/10/2016 Dr. Varaprasada Rao GGSESTC 17
5/10/2016 Dr. Varaprasada Rao GGSESTC 18
5/10/2016 Dr. Varaprasada Rao GGSESTC 19
5/10/2016 Dr. Varaprasada Rao GGSESTC 20
5/10/2016 Dr. Varaprasada Rao GGSESTC 21
5/10/2016 Dr. Varaprasada Rao GGSESTC 22
5/10/2016 Dr. Varaprasada Rao GGSESTC 23
Dr. Varaprasada Rao GGSESTC 24
AOA Project Network for House
3
2 0
1
3
1 1
1
1 2 4 6 7
3
5
Lay
foundation
Design house
and obtain
financing
Order and
receive
materials
Dummy
Finish
work
Select
carpet
Select
paint
Build
house
AON Project Network for House
1
3
2
2
4
3
3
1 5
1
6
1
7
1Start
Design house and
obtain financing
Order and receive
materials
Select paint
Select carpet
Lay foundations Build house
Finish work
5/10/2016
Dr. Varaprasada Rao GGSESTC 25
Situations in network diagram
A
B
C
A must finish before either B or C can start
A
B
C both A and B must finish before C can start
D
C
B
A
both A and C must finish before either of B
or D can start
A
C
B
D
Dummy
A must finish before B can start
both A and C must finish before D can start
5/10/2016
Dr. Varaprasada Rao GGSESTC 26
Concurrent Activities
2 3
Lay foundation
Order material
(a) Incorrect precedence
relationship
(b) Correct precedence
relationship
3
42
Dummy
Lay
foundation
Order material
1
2 0
5/10/2016
Dr. Varaprasada Rao GGSESTC 27
Network example
Illustration of network analysis of a minor redesign of a product and
its associated packaging.
The key question is: How long will it take to complete this project ?
5/10/2016
Dr. Varaprasada Rao GGSESTC 28
For clarity, this list is kept to a minimum by specifying only
immediate relationships, that is relationships involving activities
that "occur near to each other in time".
5/10/2016
Dr. Varaprasada Rao GGSESTC 29
Questions to prepare activity network
• Is this a Start Activity?
• Is this a Finish Activity?
• What Activity Precedes this?
• What Activity Follows this?
• What Activity is Concurrent with this?
5/10/2016
Dr. Varaprasada Rao GGSESTC 30
CPM calculation
• Path
– A connected sequence of activities leading from
the starting event to the ending event
• Critical Path
– The longest path (time); determines the project
duration
• Critical Activities
– All of the activities that make up the critical path
5/10/2016
Dr. Varaprasada Rao GGSESTC 31
Forward Pass
• Earliest Start Time (ES)
– earliest time an activity can start
– ES = maximum EF of immediate predecessors
• Earliest finish time (EF)
– earliest time an activity can finish
– earliest start time plus activity time
EF= ES + t
Latest Start Time (LS)
Latest time an activity can start without delaying critical path
time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying
critical path time
LS = minimum LS of immediate predecessors
Backward Pass
5/10/2016
Dr. Varaprasada Rao GGSESTC 32
CPM analysis
• Draw the CPM network
• Analyze the paths through the network
• Determine the float for each activity
– Compute the activity’s float
float = LS - ES = LF - EF
– Float is the maximum amount of time that this activity can be
delay in its completion before it becomes a critical activity,
i.e., delays completion of the project
• Find the critical path is that the sequence of activities and events
where there is no “slack” i.e.. Zero slack
– Longest path through a network
• Find the project duration is minimum project completion time
5/10/2016
Dr. Varaprasada Rao GGSESTC 33
CPM Example:
• CPM Network
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
5/10/2016
Dr. Varaprasada Rao GGSESTC 34
CPM Example
• ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
5/10/2016
Dr. Varaprasada Rao GGSESTC 35
CPM Example
• ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
6 23
6 21
5/10/2016
Dr. Varaprasada Rao GGSESTC 36
CPM Example
• ES and EF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
Project’s EF = 33
5/10/2016
Dr. Varaprasada Rao GGSESTC 37
CPM Example
• LS and LF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
21 33
6 23
21 30
23 29
6 21
21 33
27 33
24 33
5/10/2016
Dr. Varaprasada Rao GGSESTC 38
CPM Example
• LS and LF Times
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21
21 33
6 23
21 30
23 29
6 21
4 10
0 8
7 12
12 21
21 33
27 33
8 21
10 27
24 33
9 24
5/10/2016
Dr. Varaprasada Rao GGSESTC 39
CPM Example
• Float
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17
h, 9
i, 6
j, 12
0 6
0 8
0 5
5 14
8 21 21 33
6 23
21 30
23 29
6 21
3 9
0 8
7 12
12 21
21 33
27 33
8 21
10 27
24 33
9 24
3 4
3
3
4
0
0
7
7
0
5/10/2016
Dr. Varaprasada Rao GGSESTC 40
CPM Example
• Critical Path
a, 6
f, 15
b, 8
c, 5
e, 9
d, 13
g, 17 h, 9
i, 6
j, 12
5/10/2016
Dr. Varaprasada Rao GGSESTC 41
PERT
• PERT is based on the assumption that an activity’s duration
follows a probability distribution instead of being a single value
• Three time estimates are required to compute the parameters of
an activity’s duration distribution:
– pessimistic time (tp ) - the time the activity would take if
things did not go well
– most likely time (tm ) - the consensus best estimate of the
activity’s duration
– optimistic time (to ) - the time the activity would take if things
did go well
Mean (expected time): te =
tp + 4 tm + to
6
Variance: Vt =2 =
tp - to
6
2
5/10/2016
Dr. Varaprasada Rao GGSESTC 42
PERT analysis
• Draw the network.
• Analyze the paths through the network and find the critical path.
• The length of the critical path is the mean of the project duration
probability distribution which is assumed to be normal
• The standard deviation of the project duration probability
distribution is computed by adding the variances of the critical
activities (all of the activities that make up the critical path) and
taking the square root of that sum
• Probability computations can now be made using the normal
distribution table.
5/10/2016
Dr. Varaprasada Rao GGSESTC 43
Probability computation
Determine probability that project is completed within specified time
Z =
x - 

where  = tp = project mean time
 = project standard mean time
x = (proposed ) specified time
5/10/2016
Dr. Varaprasada Rao GGSESTC 44
Normal Distribution of Project Time
 = tp Timex
Z
Probability
5/10/2016
Dr. Varaprasada Rao GGSESTC 45
PERT Example
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)
A -- 4 6 8
B -- 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
J D,H 2.5 2.75 4.5
K G,I 3 5 75/10/2016
Dr. Varaprasada Rao GGSESTC 46
PERT Example
A
D
C
B
F
E
G
I
H
K
J
PERT Network
5/10/2016
Dr. Varaprasada Rao GGSESTC 47
PERT Example
Activity Expected Time Variance
A 6 4/9
B 4 4/9
C 3 0
D 5 1/9
E 1 1/36
F 4 1/9
G 2 4/9
H 6 1/9
I 5 1
J 3 1/9
K 5 4/9
5/10/2016
Dr. Varaprasada Rao GGSESTC 48
PERT Example
Activity ES EF LS LF Slack
A 0 6 0 6 0 *critical
B 0 4 5 9 5
C 6 9 6 9 0 *
D 6 11 15 20 9
E 6 7 12 13 6
F 9 13 9 13 0 *
G 9 11 16 18 7
H 13 19 14 20 1
I 13 18 13 18 0 *
J 19 22 20 23 1
K 18 23 18 23 0 *
5/10/2016
Dr. Varaprasada Rao GGSESTC 49
PERT Example
Vpath = VA + VC + VF + VI + VK
= 4/9 + 0 + 1/9 + 1 + 4/9
= 2
path = 1.414
z = (24 - 23)/(24-23)/1.414 = .71
From the Standard Normal Distribution table:
P(z < .71) = .5 + .2612 = .7612
5/10/2016
PROJECT COST
Dr. Varaprasada Rao GGSESTC 51
Cost consideration in project
• Project managers may have the option or requirement to crash the
project, or accelerate the completion of the project.
• This is accomplished by reducing the length of the critical path(s).
• The length of the critical path is reduced by reducing the duration
of the activities on the critical path.
• If each activity requires the expenditure of an amount of money to
reduce its duration by one unit of time, then the project manager
selects the least cost critical activity, reduces it by one time unit,
and traces that change through the remainder of the network.
• As a result of a reduction in an activity’s time, a new critical path
may be created.
• When there is more than one critical path, each of the critical
paths must be reduced.
• If the length of the project needs to be reduced further, the
process is repeated.
5/10/2016
Dr. Varaprasada Rao GGSESTC 52
Project Crashing
• Crashing
– reducing project time by expending additional resources
• Crash time
– an amount of time an activity is reduced
• Crash cost
– cost of reducing activity time
• Goal
– reduce project duration at minimum cost
5/10/2016
Dr. Varaprasada Rao GGSESTC 53
Activity crashing
Activity time
Crashing activity
Crash
time
Crash
cost
Normal Activity
Normal
time
Normal
cost
Slope = crash cost per unit time
5/10/2016
Dr. Varaprasada Rao GGSESTC 54
Time-Cost Relationship
 Crashing costs increase as project duration decreases
 Indirect costs increase as project duration increases
 Reduce project length as long as crashing costs are less than
indirect costs
Time-Cost Tradeoff
time
Direct cost
Indirect
cost
Total project costMin total cost =
optimal project
time
5/10/2016
Dr. Varaprasada Rao GGSESTC 55
Project Crashing example
1
12
2
8
4
12
3
4 5
4
6
4
7
4
5/10/2016
Dr. Varaprasada Rao GGSESTC 56
Time Cost data
Activity Normal
time
Normal
cost Rs
Crash
time
Crash
cost Rs
Allowable
crash time
slope
1
2
3
4
5
6
7
12
8
4
12
4
4
4
3000
2000
4000
50000
500
500
1500
7
5
3
9
1
1
3
5000
3500
7000
71000
1100
1100
22000
5
3
1
3
3
3
1
400
500
3000
7000
200
200
7000
75000 110700
5/10/2016
Dr. Varaprasada Rao GGSESTC 57
1
12
2
8
3
4 5
4
6
4
7
4
R400
R500
R3000
R7000
R200
R200
R70012
4
Project duration = 36
From…..
To…..
1
7
2
8
3
4 5
4
6
4
7
4
R400
R500
R3000
R7000
R200
R200
R70012
4
Project
duration = 31
Additional cost = R2000
5/10/2016
Dr. Varaprasada Rao GGSESTC 58
Benefits of CPM/PERT
• Useful at many stages of project management
• Mathematically simple
• Give critical path and slack time
• Provide project documentation
• Useful in monitoring costs
•How long will the entire project take to be completed? What are the
risks involved?
•Which are the critical activities or tasks in the project which could
delay the entire project if they were not completed on time?
•Is the project on schedule, behind schedule or ahead of schedule?
•If the project has to be finished earlier than planned, what is the best
way to do this at the least cost?
CPM/PERT can answer the following important
questions:
5/10/2016
Dr. Varaprasada Rao GGSESTC 59
Limitations to CPM/PERT
• Clearly defined, independent and stable activities
• Specified precedence relationships
• Over emphasis on critical paths
• Deterministic CPM model
• Activity time estimates are subjective and depend on judgment
• PERT assumes a beta distribution for these time estimates, but
the actual distribution may be different
• PERT consistently underestimates the expected project
completion time due to alternate paths becoming critical
To overcome the limitation, Monte Carlo simulations can be
performed on the network to eliminate the optimistic bias
5/10/2016
Dr. Varaprasada Rao GGSESTC 60
Computer Software
for Project Management
• Microsoft Project (Microsoft Corp.)
• MacProject (Claris Corp.)
• PowerProject (ASTA Development Inc.)
• Primavera Project Planner (Primavera)
• Project Scheduler (Scitor Corp.)
• Project Workbench (ABT Corp.)
5/10/2016
Dr. Varaprasada Rao GGSESTC 61
Practice Example
A social project manager is faced with a project with the following
activities:
Activity Description Duration
Social work team to live in village 5w
Social research team to do survey 12w
Analyse results of survey 5w
Establish mother & child health program 14w
Establish rural credit programme 15w
Carry out immunization of under fives 4w
Draw network diagram and show the critical path.
Calculate project duration.5/10/2016
Dr. Varaprasada Rao GGSESTC 62
Practice problem
Activity Description Duration
1-2 Social work team to live in village 5w
1-3 Social research team to do survey 12w
3-4 Analyse results of survey 5w
2-4 Establish mother & child health program 14w
3-5 Establish rural credit programme 15w
4-5 Carry out immunization of under fives 4w
3
1
2
4
5
5/10/2016
Re-cap
Please try to understand various systems now
5/10/2016 Dr. Varaprasada Rao GGSESTC 63
ACTIVITY ON NODE
5/10/2016 64Dr. Varaprasada Rao GGSESTC
Dr. Varaprasada Rao GGSESTC
Step 1-Define the Project: Cables By ITD is bringing a new product on line to be
manufactured in their current facility in existing space. The owners have identified 11
activities and their precedence relationships. Develop an AON for the project.
Activity Description
Immediate
Predecessor
Duration
(weeks)
A Develop product specifications None 4
B Design manufacturing process A 6
C Source & purchase materials A 3
D Source & purchase tooling & equipment B 6
E Receive & install tooling & equipment D 14
F Receive materials C 5
G Pilot production run E & F 2
H Evaluate product design G 2
I Evaluate process performance G 3
J Write documentation report H & I 4
K Transition to manufacturing J 25/10/2016 65
Dr. Varaprasada Rao GGSESTC
Step 2- Diagram the Network for
Cables By ITD
5/10/2016 66
Dr. Varaprasada Rao GGSESTC
Step 3 (a)- Add Deterministic Time Estimates
and Connected Paths
5/10/2016 67
Dr. Varaprasada Rao GGSESTC
Step 3 (a) (Con’t): Calculate the
Project Completion Times
• The longest path (ABDEGIJK) limits the
project’s duration (project cannot finish in less
time than its longest path)
• ABDEGIJK is the project’s critical path
Paths Path duration
ABDEGHJK 40
ABDEGIJK 41
ACFGHJK 22
ACFGIJK 23
5/10/2016 68
ACTIVITY ON ARROW
5/10/2016 69Dr. Varaprasada Rao GGSESTC
5/10/2016 71Dr. Varaprasada Rao GGSESTC
5/10/2016 72Dr. Varaprasada Rao GGSESTC
5/10/2016 73Dr. Varaprasada Rao GGSESTC
PERT
Dr. Varaprasada Rao GGSESTC
Revisiting Cables By ITD Using Probabilistic Time
Estimates
Activity Description
Optimistic
time
Most likely
time
Pessimistic
time
A Develop product specifications 2 4 6
B Design manufacturing process 3 7 10
C Source & purchase materials 2 3 5
D Source & purchase tooling & equipment 4 7 9
E Receive & install tooling & equipment 12 16 20
F Receive materials 2 5 8
G Pilot production run 2 2 2
H Evaluate product design 2 3 4
I Evaluate process performance 2 3 5
J Write documentation report 2 4 6
K Transition to manufacturing 2 2 25/10/2016 74
Dr. Varaprasada Rao GGSESTC
Using Beta Probability Distribution to
Calculate Expected Time Durations
• A typical beta distribution is shown below, note that it has
definite end points
• The expected time for finishing each activity is a weighted
average
 
6
cpessimistilikelymost4optimistic
timeExp.

5/10/2016 75
Dr. Varaprasada Rao GGSESTC
Calculating Expected Task Times
Activity
Optimistic
time
Most likely
time
Pessimistic
time
Expected
time
A 2 4 6 4
B 3 7 10 6.83
C 2 3 5 3.17
D 4 7 9 6.83
E 12 16 20 16
F 2 5 8 5
G 2 2 2 2
H 2 3 4 3
I 2 3 5 3.17
J 2 4 6 4
K 2 2 2 2
 
6
4 cpessimistilikelymostoptimistic
timeExpected


5/10/2016 76
Dr. Varaprasada Rao GGSESTC
Network Diagram with Expected
Activity Times
5/10/2016 77
Dr. Varaprasada Rao GGSESTC
Estimated Path Durations through the
Network
• ABDEGIJK is the expected critical path &
the project has an expected duration of 44.83
weeks
Activities on paths Expected duration
ABDEGHJK 44.66
ABDEGIJK 44.83
ACFGHJK 23.17
ACFGIJK 23.34
5/10/2016 78
PROBABILITY IN PERT
5/10/2016 79Dr. Varaprasada Rao GGSESTC
Dr. Varaprasada Rao GGSESTC
Estimating the Probability of
Completion Dates
• Using probabilistic time estimates offers the advantage of predicting the
probability of project completion dates
• We have already calculated the expected time for each activity by making
three time estimates
• Now we need to calculate the variance for each activity
• The variance of the beta probability distribution is:
– where p=pessimistic activity time estimate
o=optimistic activity time estimate
2
2
6
op
σ 




 

5/10/2016 80
Dr. Varaprasada Rao GGSESTC
Project Activity Variance
Activity Optimistic Most Likely Pessimistic Variance
A 2 4 6 0.44
B 3 7 10 1.36
C 2 3 5 0.25
D 4 7 9 0.69
E 12 16 20 1.78
F 2 5 8 1.00
G 2 2 2 0.00
H 2 3 4 0.11
I 2 3 5 0.25
J 2 4 6 0.44
K 2 2 2 0.00
5/10/2016 81
Dr. Varaprasada Rao GGSESTC
Variances of Each Path through the
Network
Path
Number
Activities on
Path
Path Variance
(weeks)
1 A,B,D,E,G,H,J,k 4.82
2 A,B,D,E,G,I,J,K 4.96
3 A,C,F,G,H,J,K 2.24
4 A,C,F,G,I,J,K 2.38
5/10/2016 82
Dr. Varaprasada Rao GGSESTC
Calculating the Probability of Completing the
Project in Less Than a Specified Time
• When you know:
– The expected completion time
– Its variance
• You can calculate the probability of completing the project in “X”
weeks with the following formula:
Where DT = the specified completion date
EFPath = the expected completion time of the path





 


 2
Pσ
EFD
timestandardpath
timeexpectedpathtimespecified
z
PT
pathofvarianceσ 2
Path 
5/10/2016 83
Dr. Varaprasada Rao GGSESTC
Example: Calculating the probability of
finishing the project in 48 weeks
• Use the z values in Appendix B to determine probabilities
• e.g. probability for path 1 is
Path
Number
Activities on Path Path Variance
(weeks)
z-value Probability of
Completion
1 A,B,D,E,G,H,J,k 4.82 1.5216 0.9357
2 A,B,D,E,G,I,J,K 4.96 1.4215 0.9222
3 A,C,F,G,H,J,K 2.24 16.5898 1.000
4 A,C,F,G,I,J,K 2.38 15.9847 1.000
1.52
4.82
weeks44.66weeks48
z 




 

5/10/2016 84
Dr. Varaprasada Rao GGSESTC
Reducing Project Completion
Time
• Project completion times may need to be
shortened because:
– Different deadlines
– Penalty clauses
– Need to put resources on a new project
– Promised completion dates
• Reduced project completion time is
“crashing”
5/10/2016 85
Dr. Varaprasada Rao GGSESTC
Reducing Project Completion Time
–
• Crashing a project needs to balance
– Shorten a project duration
– Cost to shorten the project duration
• Crashing a project requires you to know
– Crash time of each activity
– Crash cost of each activity
Crash cost/duration = (crash cost-normal cost)/(normal time – crash time)
5/10/2016 86
Dr. Varaprasada Rao GGSESTC
Reducing the Time of a Project (crashing)
Activity Normal
Time (wk)
Normal
Cost
Crash
Time
Crash
Cost
Max. weeks
of reduction
Reduce cost
per week
A 4 8,000 3 11,000 1 3,000
B 6 30,000 5 35,000 1 5,000
C 3 6,000 3 6,000 0 0
D 6 24,000 4 28,000 2 2,000
E 14 60,000 12 72,000 2 6,000
F 5 5,000 4 6,500 1 1500
G 2 6,000 2 6,000 0 0
H 2 4,000 2 4,000 0 0
I 3 4,000 2 5,000 1 1,000
J 4 4,000 2 6,400 2 1,200
K 2 5,000 2 5,000 0 0
5/10/2016 87
Dr. Varaprasada Rao GGSESTC
Crashing Example: Suppose the Cables By ITD project
manager wants to reduce the new product project from 41
to 36 weeks.
• Crashing Costs are considered to be linear
• Look to crash activities on the critical path
• Crash the least expensive activities on the critical path first
(based on cost per week)
– Crash activity I from 3 weeks to 2 weeks 1000
– Crash activity J from 4 weeks to 2 weeks 2400
– Crash activity D from 6 weeks to 4 weeks 4000
– Recommend Crash Cost 7400
5/10/2016 88
A convenient analytical and visual technique of PERT and
CPM prove extremely valuable in assisting the managers in
managing the projects.
PERT stands for Project Evaluation and Review
Technique developed during 1950’s. The technique was
developed and used in conjunction with the planning and
designing of the Polaris missile project.
CPM stands for Critical Path Method which was
developed by DuPont Company and applied first to the
construction projects in the chemical industry.
Though both PERT and CPM techniques have similarity in terms of
concepts, the basic difference is; CPM has single time estimate and PERT
has three time estimates for activities and uses probability theory to find
the chance of reaching the scheduled time.
5/10/2016 89Dr. Varaprasada Rao GGSESTC
Project management generally consists of three phases.
Planning:
Planning involves setting the objectives of the project. Identifying
various activities to be performed and determining the requirement of
resources such as men, materials, machines, etc.
The cost and time for all the activities are estimated, and a network diagram is
developed showing sequential interrelationships (predecessor and successor)
between various activities during the planning stage.
Scheduling:
Based on the time estimates, the start and finish times for each
activity are worked out by applying forward and backward pass
techniques, critical path is identified, along with the slack and float for
the non-critical paths.
Controlling:
Controlling refers to analyzing and evaluating the actual
progress against the plan. Reallocation of resources, crashing and
review of projects with periodical reports are carried out.
5/10/2016 90Dr. Varaprasada Rao GGSESTC
COMPONENTS of PERT/CPM NETWORK
PERT / CPM networks contain two major components
i. Activities, and
ii. Events
Activity: An activity represents an action and consumption of
resources (time, money, energy) required to complete a portion of a
project. Activity is represented by an arrow, (Figure 8.1).
Event: An event (or node) will always occur at the beginning
and end of an activity. The event has no resources and is
represented by a circle. The ith event and jth event are the
tail event and head event respectively, (Figure 8.2).
5/10/2016 91Dr. Varaprasada Rao GGSESTC
Merge and Burst Events
One or more activities can start and end simultaneously at an
event (Figure 8.3 a, b).
Preceding and Succeeding Activities
Activities performed before given events are known as
preceding activities (Figure 8.4), and activities performed after
a given event are known as succeeding activities.
Activities A and B precede activities C and D
respectively.
5/10/2016 92Dr. Varaprasada Rao GGSESTC
Dummy Activity
An imaginary activity which does not consume any resource and
time is called a dummy activity. Dummy activities are simply
used to represent a connection between events in order to
maintain a logic in the network. It is represented by a dotted line
in a network, see Figure 8.5.
5/10/2016 93Dr. Varaprasada Rao GGSESTC
ERRORS TO BE AVOIDED IN CONSTRUCTING A
NETWORK
a. Two activities starting from a tail event
must not have a same end event. To ensure
this, it is absolutely necessary to introduce a
dummy activity, as shown in Figure 8.6.
b. Looping error should not be formed in a
network, as it represents performance of
activities repeatedly in a cyclic manner, as
shown below in Figure 8.7.
c. In a network, there should be only one
start event and one ending event as shown
below, in Figure 8.8.
d. The direction of arrows should
flow from left to right avoiding
mixing of direction as shown in
Figure 8.9.
5/10/2016 94Dr. Varaprasada Rao GGSESTC
RULES IN CONSTRUCTING A NETWORK
1. No single activity can be represented more than once in a network. The
length of an arrow has no significance.
2. The event numbered 1 is the start event and an event with highest number is
the end event. Before an activity can be undertaken, all activities preceding it
must be completed. That is, the activities must follow a logical sequence (or –
interrelationship) between activities.
3. In assigning numbers to events, there should not be any duplication of event
numbers in a network.
4. Dummy activities must be used only if it is necessary to reduce the complexity
of a network.
5. A network should have only one start event and one end event.
5/10/2016 95Dr. Varaprasada Rao GGSESTC
Some conventions of network diagram are shown in Figure 8.10
(a), (b), (c), (d) below:
5/10/2016 96Dr. Varaprasada Rao GGSESTC
PROCEDURE FOR NUMBERING THE EVENTS
USING FULKERSON'S RULE
Step1: Number the start or initial event as 1.
Step2: From event 1, strike off all outgoing activities. This would have
made one or more events as initial events (event which do not have
incoming activities). Number that event as 2.
Step3: Repeat step 2 for event 2, event 3 and till the end event. The end
event must have the highest number
Example 1:
Draw a network for a house construction project. The sequence of
activities with their predecessors are given in Table 8.1, below.
5/10/2016 97Dr. Varaprasada Rao GGSESTC
CRITICAL PATH ANALYSIS
The critical path for any network is the longest path through the entire
network.
Since all activities must be completed to complete the entire project,
the length of the critical path is also the shortest time allowable for
completion of the project.
Thus if the project is to be completed in that shortest time, all activities
on the critical path must be started as soon as possible.
These activities are called critical activities.
If the project has to be completed ahead of the schedule, then the time
required for at least one of the critical activity must be reduced.
Further, any delay in completing the critical activities will increase the
project duration.
5/10/2016 98Dr. Varaprasada Rao GGSESTC
The activity, which does not lie on the critical path, is called non-critical
activity.
These non-critical activities may have some slack time.
The slack is the amount of time by which the start of an activity may be
delayed without affecting the overall completion time of the project.
But a critical activity has no slack.
To reduce the overall project time, it would require more resources (at
extra cost) to reduce the time taken by the critical activities to complete.
5/10/2016 99Dr. Varaprasada Rao GGSESTC
Scheduling of Activities: Earliest Time (TE) and Latest
Time(TL)
Before the critical path in a network is determined, it is necessary to
find the earliest and latest time of each event to know the earliest
expected time (TE) at which the activities originating from the event
can be started and to know the latest allowable time (TL) at which
activities terminating at the event can be completed.
Forward Pass Computations (to calculate Earliest, Time TE)
Step 1: Begin from the start event and move towards the end event.
Step 2: Put TE = 0 for the start event.
Step 3: Go to the next event (i.e node 2) if there is an incoming activity for
event 2, add calculate TE of previous event (i.e event 1) and activity time.
Note: If there are more than one incoming activities, calculate TE for all incoming
activities and take the maximum value. This value is the TE for event 2.
Step 4: Repeat the same procedure from step 3 till the end event.
5/10/2016 100Dr. Varaprasada Rao GGSESTC
Backward Pass Computations (to calculate Latest Time TL)
Procedure :
Step 1: Begin from end event and move towards the start
event. Assume that the direction of arrows is reversed.
Step 2: Latest Time TL for the last event is the earliest
time. TE of the last event.
Step 3: Go to the next event, if there is an incoming activity, subtract
the value of TL of previous event from the activity duration time. The
arrived value is TL for that event. If there are more than one incoming
activities, take the minimum TE value.
Step 4: Repeat the same procedure from step 2 till the
start event.
5/10/2016 101Dr. Varaprasada Rao GGSESTC
DETERMINATION OF FLOAT AND SLACK TIMES
As discussed earlier, the non – critical activities have some slack
or float. The float of an activity is the amount of time available by
which it is possible to delay its completion time without
extending the overall project completion time.
tij = duration of activity
TE = earliest expected time
TL = latest allowable time
ESij = earliest start time of the activity
EFij = earliest finish time of the activity
LSij = latest start time of the activity
LFij = latest finish time of the activity
Total Float TFij: The total float of an activity is the difference between
the latest start time and the earliest start time of that activity.
TFij = LS ij – ESij ....................(1)
or
TFij = (TL – TE) – tij …………..(ii)
5/10/2016 102Dr. Varaprasada Rao GGSESTC
Free Float FFij: The time by which the completion of an activity can
be delayed from its earliest finish time without affecting the
earliest start time of the succeeding activity is called free float.
FF ij = (Ej – Ei) – tij
....................(3)
FFij = Total float – Head event
slackIndependent Float IFij: The amount of time by which the start of an
activity can be delayed without affecting the earliest start time of
any immediately following activities, assuming that the preceding
activity has finished at its latest finish time.
IF ij = (Ej – Li) – tij
....................(4)
IFij = Free float – Tail event slack
Where tail event slack = Li – Ei
The negative value of independent float is considered to be zero.
5/10/2016 103Dr. Varaprasada Rao GGSESTC
Critical Path:
After determining the earliest and the latest scheduled times for various
activities, the minimum time required to complete the project is
calculated. In a network, among various paths, the longest path which
determines the total time duration of the project is called the critical path.
The following conditions must be satisfied in locating the critical path of a
network.
An activity is said to be critical only if both the conditions are satisfied.
1. TL – TE = 0
2. TLj – tij – TEj = 0
Example :
A project schedule has the following characteristics as shown in Table
i. Construct PERT network.
ii. Compute TE and TL for
each activity.
iii. Find the critical path.
5/10/2016 104Dr. Varaprasada Rao GGSESTC
(i) From the data given in the problem, the activity network is
constructed as shown in Figure given below
5/10/2016 105Dr. Varaprasada Rao GGSESTC
(ii) To determine the critical path, compute the earliest time TE
and latest time TL for each of the activity of the project. The
calculations of TE and TL are as follows:,
To calculate TE for all activities
TE1 = 0
TE2 = TE1 + t1, 2 = 0 + 4 = 4
TE3 = TE1 + t1, 3 = 0 + 1 =1
TE4 = max (TE2 + t2, 4 and TE3 + t3, 4)
= max (4 + 1 and 1 + 1) = max (5, 2)
= 5 days
TE5 = TE3 + t3, 6 = 1 + 6 = 7
TE6 = TE5 + t5, 6 = 7 + 4 = 11
TE7 = TE5 + t5, 7 = 7 + 8 = 15
TE8 = max (TE6 + t6, 8 and TE7 + t7, 8)
= max (11 + 1 and 15 + 2) = max (12, 17)
= 17 days
TE9 = TE4 + t4, 9 = 5 + 5 = 10
TE10 = max (TE9 + t9, 10 and TE8 + t8, 10)
= max (10 + 7 and 17 + 5) = max (17, 22)
= 22 days
To calculate TL for all activities
TL10 = TE10 = 22
TL9 = TE10 – t9,10 = 22 – 7 = 15
TL8 = TE10 – t8, 10 = 22 – 5 = 17
TL7 = TE8 – t7, 8 = 17 – 2 = 15
TL6 = TE8 – t6, 8 = 17 – 1 = 16
TL5 = min (TE6 – t5, 6 and TE7 – t5, 7)
= min (16 – 4 and 15 –8) = min (12, 7)
= 7 days
TL4 = TL9 – t4, 9 = 15 – 5 =10
TL3 = min (TL4 – t3, 4 and TL5 – t3, 5 )
= min (10 – 1 and 7 – 6) = min (9, 1)
= 1 day
TL2 = TL4 – t2, 4 = 10 – 1 = 9
TL1 = Min (TL2 – t1, 2 and TL3 – t1, 3)
= Min (9 – 4 and 1 – 1) = 0
5/10/2016 106Dr. Varaprasada Rao GGSESTC
5/10/2016 107Dr. Varaprasada Rao GGSESTC
(iii) From the Table 8.6, we observe that the
activities 1 – 3, 3 – 5, 5 – 7,7 – 8 and 8 – 10 are
critical activities as their floats are zero.
5/10/2016 108Dr. Varaprasada Rao GGSESTC
PROJECT EVALUATION REVIEW TECHNIQUE, (PERT)
In the critical path method, the time estimates are assumed to be
known with certainty. In certain projects like research and
development, new product introductions, it is difficult to estimate
the time of various activities.
Hence PERT is used in such projects with a probabilistic method using three time
estimates for an activity, rather than a single estimate, as shown in Figure 8.22.
Optimistic time tO:
It is the shortest time taken to complete the
activity. It means that if everything goes well
then there is more chance of completing the
activity within this time.
Most likely time tm:
It is the normal time taken to complete an activity,
if the activity were frequently repeated under the
same conditions.
Pessimistic time tp:
It is the longest time that an activity would take to
complete. It is the worst time estimate that an
activity would take if unexpected problems are
faced.5/10/2016 109
Dr. Varaprasada Rao GGSESTC
Taking all these time estimates into consideration, the expected time
of an activity is arrived at.
The average or mean (ta) value of
the activity duration is given by,
The variance of the activity time
is calculated using the formula,
The probability of completing the project
within the scheduled time (Ts) or contracted
time may be obtained by using the standard
normal deviate where Te is the expected time
of project completion.
Probability for Project Duration
Probability of completing the project
within the scheduled time is,
5/10/2016 110Dr. Varaprasada Rao GGSESTC
An R & D project has a list of tasks to be performed whose time estimates are
given in the Table 8.11, as follows.
Example
a. Draw the project network.
b. Find the critical path.
c. Find the probability that the project is completed in 19 days. If the
probability is less than 20%, find the probability of completing it in 24
days.
5/10/2016 111Dr. Varaprasada Rao GGSESTC
Time expected for each activity is
calculated using the formula (5):
Similarly, the expected time is
calculated for all the activities.
The variance of activity time is
calculated using the formula (6).
Similarly, variances of all the activities
are calculated.
5/10/2016 112Dr. Varaprasada Rao GGSESTC
calculate the time earliest
(TE) and time Latest (TL)
for all the activities.
Construct a network diagram:
From the network diagram Figure 8.24, the critical path
is identified as
1-4, 4-6, 6-7, with a project duration of 22 days.
5/10/2016 113Dr. Varaprasada Rao GGSESTC
The probability of completing the project within 19 days is given by, P (Z< Z0)
To find Z0 ,
we know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) = 0.4099)
= 0.5 – 0.4099
= 0.0901
= 9.01% Thus, the probability of completing the R & D project in 19 days is 9.01%.
Since the probability of completing the project in 19 days is less than 20% As in question, we
find the probability of completing it in 24 days.
5/10/2016 114Dr. Varaprasada Rao GGSESTC
COST ANALYSIS
The two important components of any activity are the cost and time.
Cost is directly proportional to time and vice versa.
For example, in constructing a shopping complex, the expected time of completion can be
calculated using the time estimates of various activities. But if the construction has to be
finished earlier, it requires additional cost to complete the project. We need to arrive at a
time/cost trade-off between total cost of project and total time required to complete it.
Normal time:
Normal time is the time required to complete
the activity at normal conditions and cost.
Crash time:
Crash time is the shortest possible activity
time; crashing more than the normal time
will increase the direct cost.
Cost Slope
Cost slope is the increase in cost per unit of
time saved by crashing. A linear cost curve
is shown in Figure 8.27.
5/10/2016 115Dr. Varaprasada Rao GGSESTC
An activity takes 4 days to complete at a normal cost of Rs. 500.00. If it is
possible to complete the activity in 2 days with an additional cost of Rs.
700.00, what is the incremental cost of the activity?
Example
Incremental Cost or Cost Slope
It means, if one day is reduced we have to spend Rs. 100/- extra
per day.
Project Crashing
Procedure for crashing
Step1: Draw the network diagram and mark the Normal time and Crash time.
Step2: Calculate TE and TL for all the activities.
Step3: Find the critical path and other paths.
Step 4: Find the slope for all activities and rank them in ascending order.
5/10/2016 116Dr. Varaprasada Rao GGSESTC
Step 5: Establish a tabular column with required field.
Step 6: Select the lowest ranked activity; check whether it is a critical activity. If
so,crash the activity, else go to the next highest ranked activity.
Note: The critical path must remain critical while crashing.
Step 7: Calculate the total cost of project for each crashing
Step 8: Repeat Step 6 until all the activities in the critical path are fully
crashed.
Example
The following Table
8.13 gives the activities
of a construction
project and other data.
If the indirect cost is Rs. 20 per day, crash the activities to find the minimum
duration of the project and the project cost associated.
5/10/2016
117
Dr. Varaprasada Rao GGSESTC
From the data provided in the table, draw the network diagram (Figure 8.28)
and find the critical path.
Solution
From the diagram, we observe that the
critical path is 1-2-5 with project duration of
14 days
The cost slope for all activities and their rank
is calculated as shown in Table 8.14
5/10/2016 118Dr. Varaprasada Rao GGSESTC
The available paths of the network are listed down in Table 8.15
indicating the sequence of crashing (see Figure 8.29).
The sequence of crashing
and the total cost involved
is given in Table 8.16 Initial
direct cost = sum of all
normal costs given
= Rs. 490.00
5/10/2016 119Dr. Varaprasada Rao GGSESTC
It is not possible to crash more than 10 days, as all
the activities in the critical path are fully crashed.
Hence the minimum project duration is 10 days
with the total cost of Rs. 970.00.
Activity
Crashed
Project
Duration
Critical Path Direct Cost in (Rs.) Indirect
Cost in
(Rs.)
Total
Cost in
(Rs.)
- 14 1-2-5 490 14 x 20 =
280
770
1 – 2(2)
2 – 5(2)
2 – 4(1)
3 – 4(2)
10 1 – 2 – 5
1 – 3 – 4 – 5
1 – 2 – 4 – 5
490 + (2 x 15) + (2 x
100) + (1 x 10) + (2 x
20) = 770
10 x 20 =
200
970
5/10/2016 120Dr. Varaprasada Rao GGSESTC
Assignment
5/10/2016 121Dr. Varaprasada Rao GGSESTC
5/10/2016 122Dr. Varaprasada Rao GGSESTC
5/10/2016 123Dr. Varaprasada Rao GGSESTC
a. Draw the project network diagram.
b. Calculate the length and variance of the critical path.
c. What is the probability that the jobs on the critical path can be
completed in 41 days?
5/10/2016 124Dr. Varaprasada Rao GGSESTC
Dr. Varaprasada Rao GGSESTC 125
Dr. M Varaprasada Rao
Director.ggsestc@gmail.com
5/10/2016

More Related Content

What's hot

PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.pptPedadaSaikumar
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using PertVishnu RC Vijayan
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)El Moro
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSHafiz JUNAID
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method Mkaur01
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
time cost trade off
 time cost trade off time cost trade off
time cost trade offbriankirui9
 

What's hot (20)

PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Module-4:Introduction to engineering economy,Interest and time value of money...
Module-4:Introduction to engineering economy,Interest and time value of money...Module-4:Introduction to engineering economy,Interest and time value of money...
Module-4:Introduction to engineering economy,Interest and time value of money...
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 

Similar to Project Management - CPM/PERT Techniques

Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pertAbu Bashar
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Jags Jagdish
 
ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project ManagementPooja
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project SummaryMinhas Kamal
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material Abdel Rahman okasha
 
OM Session 15 and 16.pdf
OM Session 15 and 16.pdfOM Session 15 and 16.pdf
OM Session 15 and 16.pdfsrijitghoshal
 
Week 2 24 - 28 July 2023 (1).pptx
Week 2 24 - 28 July 2023 (1).pptxWeek 2 24 - 28 July 2023 (1).pptx
Week 2 24 - 28 July 2023 (1).pptxXuanQin3
 
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxPROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxwkyra78
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 

Similar to Project Management - CPM/PERT Techniques (20)

Project management - CPM & PERT
Project management   - CPM & PERTProject management   - CPM & PERT
Project management - CPM & PERT
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)Pert cpm-1226075768298180-8 (1)
Pert cpm-1226075768298180-8 (1)
 
ITFT - Project Management
ITFT - Project ManagementITFT - Project Management
ITFT - Project Management
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project Summary
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
SPM Unit-1 Final.pptx
SPM Unit-1 Final.pptxSPM Unit-1 Final.pptx
SPM Unit-1 Final.pptx
 
OM Session 15 and 16.pdf
OM Session 15 and 16.pdfOM Session 15 and 16.pdf
OM Session 15 and 16.pdf
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Week 2 24 - 28 July 2023 (1).pptx
Week 2 24 - 28 July 2023 (1).pptxWeek 2 24 - 28 July 2023 (1).pptx
Week 2 24 - 28 July 2023 (1).pptx
 
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docxPROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
PROJECT CHARTER TEMPLATE GENERAL PROJECT INFORMATIONProject Na.docx
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Project Management for PhD Research
Project Management for PhD ResearchProject Management for PhD Research
Project Management for PhD Research
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 

Recently uploaded

How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 

Recently uploaded (20)

How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 

Project Management - CPM/PERT Techniques

  • 1. Project Management - CPM/PERT Dr. M Varaprasada Rao DEAN - ACADEMICS GIET RAJAHMUNDRY
  • 2. Dr. Varaprasada Rao GGSESTC 2 What exactly is a project? PM 1 – A building supervisor is in-charge for construction of a retail development in the centre of Rajahmundry. There are 26 retail units and a super market in the complex. The main responsibilities are to co- ordinate the work of the various contractors to ensure that the project is completed to specification, within budget and on time. PM 2 – Dr. Rao directing a team of research scientists. They are running trials on a new analgesic drug on behalf of a pharmaceutical company. It is the responsibility to design the experiments and make sure that proper scientific and legal procedures are followed, so that the results can be subjected to independent statistical analysis. PM 3- The international aid agency which employs me is sending me to New Delhi to organize the introduction of multimedia resources at a teachers’ training college. My role is quite complex. I have to make sure that appropriate resources are purchased- and in some cases developed within the college. I also have to encourage the acceptance of these resources by lecturers and students within the college.5/10/2016
  • 3. Dr. Varaprasada Rao GGSESTC 3 Project is not defined by the type of outcome it is set up to achieve PM 1 – A building supervisor is in-charge for construction of a retail development in the centre of Rajahmundry. There are 26 retail units and a super market in the complex. The main responsibilities are to co- ordinate the work of the various contractors to ensure that the project is completed to specification, within budget and on time. PM 2 – Dr. Rao directing a team of research scientists. They are running trials on a new analgesic drug on behalf of a pharmaceutical company. It is the responsibility to design the experiments and make sure that proper scientific and legal procedures are followed, so that the results can be subjected to independent statistical analysis. PM 3- The international aid agency which employs me is sending me to New Delhi to organize the introduction of multimedia resources at a teachers’ training college. My role is quite complex. I have to make sure that appropriate resources are purchased- and in some cases developed within the college. I also have to encourage the acceptance of these resources by lecturers and students within the college.5/10/2016
  • 4. Dr. Varaprasada Rao GGSESTC 4 Characteristic of a project A project is an endeavour involving a connected sequence of activities and a range of resources, which is designed to achieve a specific outcome and which operates within a time frame, cost and quality constraints and which is often used to introduce change. A unique, one-time operational activity or effort Requires the completion of a large number of interrelated activities Established to achieve specific objective Resources, such as time and/or money, are limited Typically has its own management structure Need leadership Project 5/10/2016
  • 5. Dr. Varaprasada Rao GGSESTC 5 Examples – constructing houses, factories, shopping malls, athletic stadiums or arenas – developing military weapons systems, aircrafts, new ships – launching satellite systems – constructing oil pipelines – developing and implementing new computer systems – planning concert, football games, or basketball tournaments – introducing new products into market 5/10/2016
  • 6. Dr. Varaprasada Rao GGSESTC 6 What is project management • The application of a collection of tools and techniques to direct the use of diverse resources towards the accomplishment of a unique, complex, one time task within time, cost and quality constraints. • Its origins lie in World War II, when the military authorities used the techniques of operational research to plan the optimum use of resources. • One of these techniques was the use of networks to represent a system of related activities 5/10/2016
  • 7. Dr. Varaprasada Rao GGSESTC 7 Project Management Process • Project planning - Project scheduling - Project control • Project team – made up of individuals from various areas and departments within a company • Matrix organization – a team structure with members from functional areas, depending on skills required • Project Manager – most important member of project team • Scope statement – a document that provides an understanding, justification, and expected result of a project • Statement of work – written description of objectives of a project • Organizational Breakdown Structure – a chart that shows which organizational units are responsible for work items • Responsibility Assignment Matrix – shows who is responsible for work in a project 5/10/2016
  • 8. Dr. Varaprasada Rao GGSESTC 8 Work breakdown structure • A method of breaking down a project into individual elements ( components, subcomponents, activities and tasks) in a hierarchical structure which can be scheduled and cost • It defines tasks that can be completed independently of other tasks, facilitating resource allocation, assignment of responsibilities and measurement and control of the project • It is foundation of project planning • It is developed before identification of dependencies and estimation of activity durations • It can be used to identity the tasks in the CPM and PERT 5/10/2016
  • 9. Dr. Varaprasada Rao GGSESTC 9 Work Breakdown Structure for Computer Order Processing System Project 5/10/2016
  • 10. Dr. Varaprasada Rao GGSESTC 10 Project Planning • Resource Availability and/or Limits – Due date, late penalties, early completion incentives – Budget • Activity Information – Identify all required activities – Estimate the resources required (time) to complete each activity – Immediate predecessor(s) to each activity needed to create interrelationships 5/10/2016
  • 11. Dr. Varaprasada Rao GGSESTC 11 Project Scheduling and Control Techniques Gantt Chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) 5/10/2016
  • 12. Dr. Varaprasada Rao GGSESTC 12 Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule Gantt Chart 5/10/2016
  • 13. Dr. Varaprasada Rao GGSESTC 13 History of CPM/PERT • Critical Path Method (CPM) – E I Du Pont de Nemours & Co. (1957) for construction of new chemical plant and maintenance shut-down – Deterministic task times – Activity-on-node network construction – Repetitive nature of jobs • Project Evaluation and Review Technique (PERT) – U S Navy (1958) for the POLARIS missile program – Multiple task time estimates (probabilistic nature) – Activity-on-arrow network construction – Non-repetitive jobs (R & D work) 5/10/2016
  • 14. Dr. Varaprasada Rao GGSESTC 14 • Event – Signals the beginning or ending of an activity – Designates a point in time – Represented by a circle (node) • Network – Shows the sequential relationships among activities using nodes and arrows Activity-on-node (AON) nodes represent activities, and arrows show precedence relationships Activity-on-arrow (AOA) arrows represent activities and nodes are events for points in time Project Network 5/10/2016
  • 15. Dr. Varaprasada Rao GGSESTC 15 Project Network • Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects • Use of nodes and arrows Arrows  An arrow leads from tail to head directionally – Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes  A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish. • Activity – A task or a certain amount of work required in the project – Requires time to complete – Represented by an arrow • Dummy Activity – Indicates only precedence relationships – Does not require any time of effort 5/10/2016
  • 16. 5/10/2016 Dr. Varaprasada Rao GGSESTC 16
  • 17. 5/10/2016 Dr. Varaprasada Rao GGSESTC 17
  • 18. 5/10/2016 Dr. Varaprasada Rao GGSESTC 18
  • 19. 5/10/2016 Dr. Varaprasada Rao GGSESTC 19
  • 20. 5/10/2016 Dr. Varaprasada Rao GGSESTC 20
  • 21. 5/10/2016 Dr. Varaprasada Rao GGSESTC 21
  • 22. 5/10/2016 Dr. Varaprasada Rao GGSESTC 22
  • 23. 5/10/2016 Dr. Varaprasada Rao GGSESTC 23
  • 24. Dr. Varaprasada Rao GGSESTC 24 AOA Project Network for House 3 2 0 1 3 1 1 1 1 2 4 6 7 3 5 Lay foundation Design house and obtain financing Order and receive materials Dummy Finish work Select carpet Select paint Build house AON Project Network for House 1 3 2 2 4 3 3 1 5 1 6 1 7 1Start Design house and obtain financing Order and receive materials Select paint Select carpet Lay foundations Build house Finish work 5/10/2016
  • 25. Dr. Varaprasada Rao GGSESTC 25 Situations in network diagram A B C A must finish before either B or C can start A B C both A and B must finish before C can start D C B A both A and C must finish before either of B or D can start A C B D Dummy A must finish before B can start both A and C must finish before D can start 5/10/2016
  • 26. Dr. Varaprasada Rao GGSESTC 26 Concurrent Activities 2 3 Lay foundation Order material (a) Incorrect precedence relationship (b) Correct precedence relationship 3 42 Dummy Lay foundation Order material 1 2 0 5/10/2016
  • 27. Dr. Varaprasada Rao GGSESTC 27 Network example Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project ? 5/10/2016
  • 28. Dr. Varaprasada Rao GGSESTC 28 For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time". 5/10/2016
  • 29. Dr. Varaprasada Rao GGSESTC 29 Questions to prepare activity network • Is this a Start Activity? • Is this a Finish Activity? • What Activity Precedes this? • What Activity Follows this? • What Activity is Concurrent with this? 5/10/2016
  • 30. Dr. Varaprasada Rao GGSESTC 30 CPM calculation • Path – A connected sequence of activities leading from the starting event to the ending event • Critical Path – The longest path (time); determines the project duration • Critical Activities – All of the activities that make up the critical path 5/10/2016
  • 31. Dr. Varaprasada Rao GGSESTC 31 Forward Pass • Earliest Start Time (ES) – earliest time an activity can start – ES = maximum EF of immediate predecessors • Earliest finish time (EF) – earliest time an activity can finish – earliest start time plus activity time EF= ES + t Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors Backward Pass 5/10/2016
  • 32. Dr. Varaprasada Rao GGSESTC 32 CPM analysis • Draw the CPM network • Analyze the paths through the network • Determine the float for each activity – Compute the activity’s float float = LS - ES = LF - EF – Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project • Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack – Longest path through a network • Find the project duration is minimum project completion time 5/10/2016
  • 33. Dr. Varaprasada Rao GGSESTC 33 CPM Example: • CPM Network a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 5/10/2016
  • 34. Dr. Varaprasada Rao GGSESTC 34 CPM Example • ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5/10/2016
  • 35. Dr. Varaprasada Rao GGSESTC 35 CPM Example • ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 6 23 6 21 5/10/2016
  • 36. Dr. Varaprasada Rao GGSESTC 36 CPM Example • ES and EF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 Project’s EF = 33 5/10/2016
  • 37. Dr. Varaprasada Rao GGSESTC 37 CPM Example • LS and LF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 21 33 27 33 24 33 5/10/2016
  • 38. Dr. Varaprasada Rao GGSESTC 38 CPM Example • LS and LF Times a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 4 10 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 9 24 5/10/2016
  • 39. Dr. Varaprasada Rao GGSESTC 39 CPM Example • Float a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 3 9 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 9 24 3 4 3 3 4 0 0 7 7 0 5/10/2016
  • 40. Dr. Varaprasada Rao GGSESTC 40 CPM Example • Critical Path a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 5/10/2016
  • 41. Dr. Varaprasada Rao GGSESTC 41 PERT • PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value • Three time estimates are required to compute the parameters of an activity’s duration distribution: – pessimistic time (tp ) - the time the activity would take if things did not go well – most likely time (tm ) - the consensus best estimate of the activity’s duration – optimistic time (to ) - the time the activity would take if things did go well Mean (expected time): te = tp + 4 tm + to 6 Variance: Vt =2 = tp - to 6 2 5/10/2016
  • 42. Dr. Varaprasada Rao GGSESTC 42 PERT analysis • Draw the network. • Analyze the paths through the network and find the critical path. • The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal • The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum • Probability computations can now be made using the normal distribution table. 5/10/2016
  • 43. Dr. Varaprasada Rao GGSESTC 43 Probability computation Determine probability that project is completed within specified time Z = x -   where  = tp = project mean time  = project standard mean time x = (proposed ) specified time 5/10/2016
  • 44. Dr. Varaprasada Rao GGSESTC 44 Normal Distribution of Project Time  = tp Timex Z Probability 5/10/2016
  • 45. Dr. Varaprasada Rao GGSESTC 45 PERT Example Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8 B -- 1 4.5 5 C A 3 3 3 D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 75/10/2016
  • 46. Dr. Varaprasada Rao GGSESTC 46 PERT Example A D C B F E G I H K J PERT Network 5/10/2016
  • 47. Dr. Varaprasada Rao GGSESTC 47 PERT Example Activity Expected Time Variance A 6 4/9 B 4 4/9 C 3 0 D 5 1/9 E 1 1/36 F 4 1/9 G 2 4/9 H 6 1/9 I 5 1 J 3 1/9 K 5 4/9 5/10/2016
  • 48. Dr. Varaprasada Rao GGSESTC 48 PERT Example Activity ES EF LS LF Slack A 0 6 0 6 0 *critical B 0 4 5 9 5 C 6 9 6 9 0 * D 6 11 15 20 9 E 6 7 12 13 6 F 9 13 9 13 0 * G 9 11 16 18 7 H 13 19 14 20 1 I 13 18 13 18 0 * J 19 22 20 23 1 K 18 23 18 23 0 * 5/10/2016
  • 49. Dr. Varaprasada Rao GGSESTC 49 PERT Example Vpath = VA + VC + VF + VI + VK = 4/9 + 0 + 1/9 + 1 + 4/9 = 2 path = 1.414 z = (24 - 23)/(24-23)/1.414 = .71 From the Standard Normal Distribution table: P(z < .71) = .5 + .2612 = .7612 5/10/2016
  • 51. Dr. Varaprasada Rao GGSESTC 51 Cost consideration in project • Project managers may have the option or requirement to crash the project, or accelerate the completion of the project. • This is accomplished by reducing the length of the critical path(s). • The length of the critical path is reduced by reducing the duration of the activities on the critical path. • If each activity requires the expenditure of an amount of money to reduce its duration by one unit of time, then the project manager selects the least cost critical activity, reduces it by one time unit, and traces that change through the remainder of the network. • As a result of a reduction in an activity’s time, a new critical path may be created. • When there is more than one critical path, each of the critical paths must be reduced. • If the length of the project needs to be reduced further, the process is repeated. 5/10/2016
  • 52. Dr. Varaprasada Rao GGSESTC 52 Project Crashing • Crashing – reducing project time by expending additional resources • Crash time – an amount of time an activity is reduced • Crash cost – cost of reducing activity time • Goal – reduce project duration at minimum cost 5/10/2016
  • 53. Dr. Varaprasada Rao GGSESTC 53 Activity crashing Activity time Crashing activity Crash time Crash cost Normal Activity Normal time Normal cost Slope = crash cost per unit time 5/10/2016
  • 54. Dr. Varaprasada Rao GGSESTC 54 Time-Cost Relationship  Crashing costs increase as project duration decreases  Indirect costs increase as project duration increases  Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff time Direct cost Indirect cost Total project costMin total cost = optimal project time 5/10/2016
  • 55. Dr. Varaprasada Rao GGSESTC 55 Project Crashing example 1 12 2 8 4 12 3 4 5 4 6 4 7 4 5/10/2016
  • 56. Dr. Varaprasada Rao GGSESTC 56 Time Cost data Activity Normal time Normal cost Rs Crash time Crash cost Rs Allowable crash time slope 1 2 3 4 5 6 7 12 8 4 12 4 4 4 3000 2000 4000 50000 500 500 1500 7 5 3 9 1 1 3 5000 3500 7000 71000 1100 1100 22000 5 3 1 3 3 3 1 400 500 3000 7000 200 200 7000 75000 110700 5/10/2016
  • 57. Dr. Varaprasada Rao GGSESTC 57 1 12 2 8 3 4 5 4 6 4 7 4 R400 R500 R3000 R7000 R200 R200 R70012 4 Project duration = 36 From….. To….. 1 7 2 8 3 4 5 4 6 4 7 4 R400 R500 R3000 R7000 R200 R200 R70012 4 Project duration = 31 Additional cost = R2000 5/10/2016
  • 58. Dr. Varaprasada Rao GGSESTC 58 Benefits of CPM/PERT • Useful at many stages of project management • Mathematically simple • Give critical path and slack time • Provide project documentation • Useful in monitoring costs •How long will the entire project take to be completed? What are the risks involved? •Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? •Is the project on schedule, behind schedule or ahead of schedule? •If the project has to be finished earlier than planned, what is the best way to do this at the least cost? CPM/PERT can answer the following important questions: 5/10/2016
  • 59. Dr. Varaprasada Rao GGSESTC 59 Limitations to CPM/PERT • Clearly defined, independent and stable activities • Specified precedence relationships • Over emphasis on critical paths • Deterministic CPM model • Activity time estimates are subjective and depend on judgment • PERT assumes a beta distribution for these time estimates, but the actual distribution may be different • PERT consistently underestimates the expected project completion time due to alternate paths becoming critical To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias 5/10/2016
  • 60. Dr. Varaprasada Rao GGSESTC 60 Computer Software for Project Management • Microsoft Project (Microsoft Corp.) • MacProject (Claris Corp.) • PowerProject (ASTA Development Inc.) • Primavera Project Planner (Primavera) • Project Scheduler (Scitor Corp.) • Project Workbench (ABT Corp.) 5/10/2016
  • 61. Dr. Varaprasada Rao GGSESTC 61 Practice Example A social project manager is faced with a project with the following activities: Activity Description Duration Social work team to live in village 5w Social research team to do survey 12w Analyse results of survey 5w Establish mother & child health program 14w Establish rural credit programme 15w Carry out immunization of under fives 4w Draw network diagram and show the critical path. Calculate project duration.5/10/2016
  • 62. Dr. Varaprasada Rao GGSESTC 62 Practice problem Activity Description Duration 1-2 Social work team to live in village 5w 1-3 Social research team to do survey 12w 3-4 Analyse results of survey 5w 2-4 Establish mother & child health program 14w 3-5 Establish rural credit programme 15w 4-5 Carry out immunization of under fives 4w 3 1 2 4 5 5/10/2016
  • 63. Re-cap Please try to understand various systems now 5/10/2016 Dr. Varaprasada Rao GGSESTC 63
  • 64. ACTIVITY ON NODE 5/10/2016 64Dr. Varaprasada Rao GGSESTC
  • 65. Dr. Varaprasada Rao GGSESTC Step 1-Define the Project: Cables By ITD is bringing a new product on line to be manufactured in their current facility in existing space. The owners have identified 11 activities and their precedence relationships. Develop an AON for the project. Activity Description Immediate Predecessor Duration (weeks) A Develop product specifications None 4 B Design manufacturing process A 6 C Source & purchase materials A 3 D Source & purchase tooling & equipment B 6 E Receive & install tooling & equipment D 14 F Receive materials C 5 G Pilot production run E & F 2 H Evaluate product design G 2 I Evaluate process performance G 3 J Write documentation report H & I 4 K Transition to manufacturing J 25/10/2016 65
  • 66. Dr. Varaprasada Rao GGSESTC Step 2- Diagram the Network for Cables By ITD 5/10/2016 66
  • 67. Dr. Varaprasada Rao GGSESTC Step 3 (a)- Add Deterministic Time Estimates and Connected Paths 5/10/2016 67
  • 68. Dr. Varaprasada Rao GGSESTC Step 3 (a) (Con’t): Calculate the Project Completion Times • The longest path (ABDEGIJK) limits the project’s duration (project cannot finish in less time than its longest path) • ABDEGIJK is the project’s critical path Paths Path duration ABDEGHJK 40 ABDEGIJK 41 ACFGHJK 22 ACFGIJK 23 5/10/2016 68
  • 69. ACTIVITY ON ARROW 5/10/2016 69Dr. Varaprasada Rao GGSESTC
  • 70.
  • 73. 5/10/2016 73Dr. Varaprasada Rao GGSESTC PERT
  • 74. Dr. Varaprasada Rao GGSESTC Revisiting Cables By ITD Using Probabilistic Time Estimates Activity Description Optimistic time Most likely time Pessimistic time A Develop product specifications 2 4 6 B Design manufacturing process 3 7 10 C Source & purchase materials 2 3 5 D Source & purchase tooling & equipment 4 7 9 E Receive & install tooling & equipment 12 16 20 F Receive materials 2 5 8 G Pilot production run 2 2 2 H Evaluate product design 2 3 4 I Evaluate process performance 2 3 5 J Write documentation report 2 4 6 K Transition to manufacturing 2 2 25/10/2016 74
  • 75. Dr. Varaprasada Rao GGSESTC Using Beta Probability Distribution to Calculate Expected Time Durations • A typical beta distribution is shown below, note that it has definite end points • The expected time for finishing each activity is a weighted average   6 cpessimistilikelymost4optimistic timeExp.  5/10/2016 75
  • 76. Dr. Varaprasada Rao GGSESTC Calculating Expected Task Times Activity Optimistic time Most likely time Pessimistic time Expected time A 2 4 6 4 B 3 7 10 6.83 C 2 3 5 3.17 D 4 7 9 6.83 E 12 16 20 16 F 2 5 8 5 G 2 2 2 2 H 2 3 4 3 I 2 3 5 3.17 J 2 4 6 4 K 2 2 2 2   6 4 cpessimistilikelymostoptimistic timeExpected   5/10/2016 76
  • 77. Dr. Varaprasada Rao GGSESTC Network Diagram with Expected Activity Times 5/10/2016 77
  • 78. Dr. Varaprasada Rao GGSESTC Estimated Path Durations through the Network • ABDEGIJK is the expected critical path & the project has an expected duration of 44.83 weeks Activities on paths Expected duration ABDEGHJK 44.66 ABDEGIJK 44.83 ACFGHJK 23.17 ACFGIJK 23.34 5/10/2016 78
  • 79. PROBABILITY IN PERT 5/10/2016 79Dr. Varaprasada Rao GGSESTC
  • 80. Dr. Varaprasada Rao GGSESTC Estimating the Probability of Completion Dates • Using probabilistic time estimates offers the advantage of predicting the probability of project completion dates • We have already calculated the expected time for each activity by making three time estimates • Now we need to calculate the variance for each activity • The variance of the beta probability distribution is: – where p=pessimistic activity time estimate o=optimistic activity time estimate 2 2 6 op σ         5/10/2016 80
  • 81. Dr. Varaprasada Rao GGSESTC Project Activity Variance Activity Optimistic Most Likely Pessimistic Variance A 2 4 6 0.44 B 3 7 10 1.36 C 2 3 5 0.25 D 4 7 9 0.69 E 12 16 20 1.78 F 2 5 8 1.00 G 2 2 2 0.00 H 2 3 4 0.11 I 2 3 5 0.25 J 2 4 6 0.44 K 2 2 2 0.00 5/10/2016 81
  • 82. Dr. Varaprasada Rao GGSESTC Variances of Each Path through the Network Path Number Activities on Path Path Variance (weeks) 1 A,B,D,E,G,H,J,k 4.82 2 A,B,D,E,G,I,J,K 4.96 3 A,C,F,G,H,J,K 2.24 4 A,C,F,G,I,J,K 2.38 5/10/2016 82
  • 83. Dr. Varaprasada Rao GGSESTC Calculating the Probability of Completing the Project in Less Than a Specified Time • When you know: – The expected completion time – Its variance • You can calculate the probability of completing the project in “X” weeks with the following formula: Where DT = the specified completion date EFPath = the expected completion time of the path           2 Pσ EFD timestandardpath timeexpectedpathtimespecified z PT pathofvarianceσ 2 Path  5/10/2016 83
  • 84. Dr. Varaprasada Rao GGSESTC Example: Calculating the probability of finishing the project in 48 weeks • Use the z values in Appendix B to determine probabilities • e.g. probability for path 1 is Path Number Activities on Path Path Variance (weeks) z-value Probability of Completion 1 A,B,D,E,G,H,J,k 4.82 1.5216 0.9357 2 A,B,D,E,G,I,J,K 4.96 1.4215 0.9222 3 A,C,F,G,H,J,K 2.24 16.5898 1.000 4 A,C,F,G,I,J,K 2.38 15.9847 1.000 1.52 4.82 weeks44.66weeks48 z         5/10/2016 84
  • 85. Dr. Varaprasada Rao GGSESTC Reducing Project Completion Time • Project completion times may need to be shortened because: – Different deadlines – Penalty clauses – Need to put resources on a new project – Promised completion dates • Reduced project completion time is “crashing” 5/10/2016 85
  • 86. Dr. Varaprasada Rao GGSESTC Reducing Project Completion Time – • Crashing a project needs to balance – Shorten a project duration – Cost to shorten the project duration • Crashing a project requires you to know – Crash time of each activity – Crash cost of each activity Crash cost/duration = (crash cost-normal cost)/(normal time – crash time) 5/10/2016 86
  • 87. Dr. Varaprasada Rao GGSESTC Reducing the Time of a Project (crashing) Activity Normal Time (wk) Normal Cost Crash Time Crash Cost Max. weeks of reduction Reduce cost per week A 4 8,000 3 11,000 1 3,000 B 6 30,000 5 35,000 1 5,000 C 3 6,000 3 6,000 0 0 D 6 24,000 4 28,000 2 2,000 E 14 60,000 12 72,000 2 6,000 F 5 5,000 4 6,500 1 1500 G 2 6,000 2 6,000 0 0 H 2 4,000 2 4,000 0 0 I 3 4,000 2 5,000 1 1,000 J 4 4,000 2 6,400 2 1,200 K 2 5,000 2 5,000 0 0 5/10/2016 87
  • 88. Dr. Varaprasada Rao GGSESTC Crashing Example: Suppose the Cables By ITD project manager wants to reduce the new product project from 41 to 36 weeks. • Crashing Costs are considered to be linear • Look to crash activities on the critical path • Crash the least expensive activities on the critical path first (based on cost per week) – Crash activity I from 3 weeks to 2 weeks 1000 – Crash activity J from 4 weeks to 2 weeks 2400 – Crash activity D from 6 weeks to 4 weeks 4000 – Recommend Crash Cost 7400 5/10/2016 88
  • 89. A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects. PERT stands for Project Evaluation and Review Technique developed during 1950’s. The technique was developed and used in conjunction with the planning and designing of the Polaris missile project. CPM stands for Critical Path Method which was developed by DuPont Company and applied first to the construction projects in the chemical industry. Though both PERT and CPM techniques have similarity in terms of concepts, the basic difference is; CPM has single time estimate and PERT has three time estimates for activities and uses probability theory to find the chance of reaching the scheduled time. 5/10/2016 89Dr. Varaprasada Rao GGSESTC
  • 90. Project management generally consists of three phases. Planning: Planning involves setting the objectives of the project. Identifying various activities to be performed and determining the requirement of resources such as men, materials, machines, etc. The cost and time for all the activities are estimated, and a network diagram is developed showing sequential interrelationships (predecessor and successor) between various activities during the planning stage. Scheduling: Based on the time estimates, the start and finish times for each activity are worked out by applying forward and backward pass techniques, critical path is identified, along with the slack and float for the non-critical paths. Controlling: Controlling refers to analyzing and evaluating the actual progress against the plan. Reallocation of resources, crashing and review of projects with periodical reports are carried out. 5/10/2016 90Dr. Varaprasada Rao GGSESTC
  • 91. COMPONENTS of PERT/CPM NETWORK PERT / CPM networks contain two major components i. Activities, and ii. Events Activity: An activity represents an action and consumption of resources (time, money, energy) required to complete a portion of a project. Activity is represented by an arrow, (Figure 8.1). Event: An event (or node) will always occur at the beginning and end of an activity. The event has no resources and is represented by a circle. The ith event and jth event are the tail event and head event respectively, (Figure 8.2). 5/10/2016 91Dr. Varaprasada Rao GGSESTC
  • 92. Merge and Burst Events One or more activities can start and end simultaneously at an event (Figure 8.3 a, b). Preceding and Succeeding Activities Activities performed before given events are known as preceding activities (Figure 8.4), and activities performed after a given event are known as succeeding activities. Activities A and B precede activities C and D respectively. 5/10/2016 92Dr. Varaprasada Rao GGSESTC
  • 93. Dummy Activity An imaginary activity which does not consume any resource and time is called a dummy activity. Dummy activities are simply used to represent a connection between events in order to maintain a logic in the network. It is represented by a dotted line in a network, see Figure 8.5. 5/10/2016 93Dr. Varaprasada Rao GGSESTC
  • 94. ERRORS TO BE AVOIDED IN CONSTRUCTING A NETWORK a. Two activities starting from a tail event must not have a same end event. To ensure this, it is absolutely necessary to introduce a dummy activity, as shown in Figure 8.6. b. Looping error should not be formed in a network, as it represents performance of activities repeatedly in a cyclic manner, as shown below in Figure 8.7. c. In a network, there should be only one start event and one ending event as shown below, in Figure 8.8. d. The direction of arrows should flow from left to right avoiding mixing of direction as shown in Figure 8.9. 5/10/2016 94Dr. Varaprasada Rao GGSESTC
  • 95. RULES IN CONSTRUCTING A NETWORK 1. No single activity can be represented more than once in a network. The length of an arrow has no significance. 2. The event numbered 1 is the start event and an event with highest number is the end event. Before an activity can be undertaken, all activities preceding it must be completed. That is, the activities must follow a logical sequence (or – interrelationship) between activities. 3. In assigning numbers to events, there should not be any duplication of event numbers in a network. 4. Dummy activities must be used only if it is necessary to reduce the complexity of a network. 5. A network should have only one start event and one end event. 5/10/2016 95Dr. Varaprasada Rao GGSESTC
  • 96. Some conventions of network diagram are shown in Figure 8.10 (a), (b), (c), (d) below: 5/10/2016 96Dr. Varaprasada Rao GGSESTC
  • 97. PROCEDURE FOR NUMBERING THE EVENTS USING FULKERSON'S RULE Step1: Number the start or initial event as 1. Step2: From event 1, strike off all outgoing activities. This would have made one or more events as initial events (event which do not have incoming activities). Number that event as 2. Step3: Repeat step 2 for event 2, event 3 and till the end event. The end event must have the highest number Example 1: Draw a network for a house construction project. The sequence of activities with their predecessors are given in Table 8.1, below. 5/10/2016 97Dr. Varaprasada Rao GGSESTC
  • 98. CRITICAL PATH ANALYSIS The critical path for any network is the longest path through the entire network. Since all activities must be completed to complete the entire project, the length of the critical path is also the shortest time allowable for completion of the project. Thus if the project is to be completed in that shortest time, all activities on the critical path must be started as soon as possible. These activities are called critical activities. If the project has to be completed ahead of the schedule, then the time required for at least one of the critical activity must be reduced. Further, any delay in completing the critical activities will increase the project duration. 5/10/2016 98Dr. Varaprasada Rao GGSESTC
  • 99. The activity, which does not lie on the critical path, is called non-critical activity. These non-critical activities may have some slack time. The slack is the amount of time by which the start of an activity may be delayed without affecting the overall completion time of the project. But a critical activity has no slack. To reduce the overall project time, it would require more resources (at extra cost) to reduce the time taken by the critical activities to complete. 5/10/2016 99Dr. Varaprasada Rao GGSESTC
  • 100. Scheduling of Activities: Earliest Time (TE) and Latest Time(TL) Before the critical path in a network is determined, it is necessary to find the earliest and latest time of each event to know the earliest expected time (TE) at which the activities originating from the event can be started and to know the latest allowable time (TL) at which activities terminating at the event can be completed. Forward Pass Computations (to calculate Earliest, Time TE) Step 1: Begin from the start event and move towards the end event. Step 2: Put TE = 0 for the start event. Step 3: Go to the next event (i.e node 2) if there is an incoming activity for event 2, add calculate TE of previous event (i.e event 1) and activity time. Note: If there are more than one incoming activities, calculate TE for all incoming activities and take the maximum value. This value is the TE for event 2. Step 4: Repeat the same procedure from step 3 till the end event. 5/10/2016 100Dr. Varaprasada Rao GGSESTC
  • 101. Backward Pass Computations (to calculate Latest Time TL) Procedure : Step 1: Begin from end event and move towards the start event. Assume that the direction of arrows is reversed. Step 2: Latest Time TL for the last event is the earliest time. TE of the last event. Step 3: Go to the next event, if there is an incoming activity, subtract the value of TL of previous event from the activity duration time. The arrived value is TL for that event. If there are more than one incoming activities, take the minimum TE value. Step 4: Repeat the same procedure from step 2 till the start event. 5/10/2016 101Dr. Varaprasada Rao GGSESTC
  • 102. DETERMINATION OF FLOAT AND SLACK TIMES As discussed earlier, the non – critical activities have some slack or float. The float of an activity is the amount of time available by which it is possible to delay its completion time without extending the overall project completion time. tij = duration of activity TE = earliest expected time TL = latest allowable time ESij = earliest start time of the activity EFij = earliest finish time of the activity LSij = latest start time of the activity LFij = latest finish time of the activity Total Float TFij: The total float of an activity is the difference between the latest start time and the earliest start time of that activity. TFij = LS ij – ESij ....................(1) or TFij = (TL – TE) – tij …………..(ii) 5/10/2016 102Dr. Varaprasada Rao GGSESTC
  • 103. Free Float FFij: The time by which the completion of an activity can be delayed from its earliest finish time without affecting the earliest start time of the succeeding activity is called free float. FF ij = (Ej – Ei) – tij ....................(3) FFij = Total float – Head event slackIndependent Float IFij: The amount of time by which the start of an activity can be delayed without affecting the earliest start time of any immediately following activities, assuming that the preceding activity has finished at its latest finish time. IF ij = (Ej – Li) – tij ....................(4) IFij = Free float – Tail event slack Where tail event slack = Li – Ei The negative value of independent float is considered to be zero. 5/10/2016 103Dr. Varaprasada Rao GGSESTC
  • 104. Critical Path: After determining the earliest and the latest scheduled times for various activities, the minimum time required to complete the project is calculated. In a network, among various paths, the longest path which determines the total time duration of the project is called the critical path. The following conditions must be satisfied in locating the critical path of a network. An activity is said to be critical only if both the conditions are satisfied. 1. TL – TE = 0 2. TLj – tij – TEj = 0 Example : A project schedule has the following characteristics as shown in Table i. Construct PERT network. ii. Compute TE and TL for each activity. iii. Find the critical path. 5/10/2016 104Dr. Varaprasada Rao GGSESTC
  • 105. (i) From the data given in the problem, the activity network is constructed as shown in Figure given below 5/10/2016 105Dr. Varaprasada Rao GGSESTC
  • 106. (ii) To determine the critical path, compute the earliest time TE and latest time TL for each of the activity of the project. The calculations of TE and TL are as follows:, To calculate TE for all activities TE1 = 0 TE2 = TE1 + t1, 2 = 0 + 4 = 4 TE3 = TE1 + t1, 3 = 0 + 1 =1 TE4 = max (TE2 + t2, 4 and TE3 + t3, 4) = max (4 + 1 and 1 + 1) = max (5, 2) = 5 days TE5 = TE3 + t3, 6 = 1 + 6 = 7 TE6 = TE5 + t5, 6 = 7 + 4 = 11 TE7 = TE5 + t5, 7 = 7 + 8 = 15 TE8 = max (TE6 + t6, 8 and TE7 + t7, 8) = max (11 + 1 and 15 + 2) = max (12, 17) = 17 days TE9 = TE4 + t4, 9 = 5 + 5 = 10 TE10 = max (TE9 + t9, 10 and TE8 + t8, 10) = max (10 + 7 and 17 + 5) = max (17, 22) = 22 days To calculate TL for all activities TL10 = TE10 = 22 TL9 = TE10 – t9,10 = 22 – 7 = 15 TL8 = TE10 – t8, 10 = 22 – 5 = 17 TL7 = TE8 – t7, 8 = 17 – 2 = 15 TL6 = TE8 – t6, 8 = 17 – 1 = 16 TL5 = min (TE6 – t5, 6 and TE7 – t5, 7) = min (16 – 4 and 15 –8) = min (12, 7) = 7 days TL4 = TL9 – t4, 9 = 15 – 5 =10 TL3 = min (TL4 – t3, 4 and TL5 – t3, 5 ) = min (10 – 1 and 7 – 6) = min (9, 1) = 1 day TL2 = TL4 – t2, 4 = 10 – 1 = 9 TL1 = Min (TL2 – t1, 2 and TL3 – t1, 3) = Min (9 – 4 and 1 – 1) = 0 5/10/2016 106Dr. Varaprasada Rao GGSESTC
  • 108. (iii) From the Table 8.6, we observe that the activities 1 – 3, 3 – 5, 5 – 7,7 – 8 and 8 – 10 are critical activities as their floats are zero. 5/10/2016 108Dr. Varaprasada Rao GGSESTC
  • 109. PROJECT EVALUATION REVIEW TECHNIQUE, (PERT) In the critical path method, the time estimates are assumed to be known with certainty. In certain projects like research and development, new product introductions, it is difficult to estimate the time of various activities. Hence PERT is used in such projects with a probabilistic method using three time estimates for an activity, rather than a single estimate, as shown in Figure 8.22. Optimistic time tO: It is the shortest time taken to complete the activity. It means that if everything goes well then there is more chance of completing the activity within this time. Most likely time tm: It is the normal time taken to complete an activity, if the activity were frequently repeated under the same conditions. Pessimistic time tp: It is the longest time that an activity would take to complete. It is the worst time estimate that an activity would take if unexpected problems are faced.5/10/2016 109 Dr. Varaprasada Rao GGSESTC
  • 110. Taking all these time estimates into consideration, the expected time of an activity is arrived at. The average or mean (ta) value of the activity duration is given by, The variance of the activity time is calculated using the formula, The probability of completing the project within the scheduled time (Ts) or contracted time may be obtained by using the standard normal deviate where Te is the expected time of project completion. Probability for Project Duration Probability of completing the project within the scheduled time is, 5/10/2016 110Dr. Varaprasada Rao GGSESTC
  • 111. An R & D project has a list of tasks to be performed whose time estimates are given in the Table 8.11, as follows. Example a. Draw the project network. b. Find the critical path. c. Find the probability that the project is completed in 19 days. If the probability is less than 20%, find the probability of completing it in 24 days. 5/10/2016 111Dr. Varaprasada Rao GGSESTC
  • 112. Time expected for each activity is calculated using the formula (5): Similarly, the expected time is calculated for all the activities. The variance of activity time is calculated using the formula (6). Similarly, variances of all the activities are calculated. 5/10/2016 112Dr. Varaprasada Rao GGSESTC
  • 113. calculate the time earliest (TE) and time Latest (TL) for all the activities. Construct a network diagram: From the network diagram Figure 8.24, the critical path is identified as 1-4, 4-6, 6-7, with a project duration of 22 days. 5/10/2016 113Dr. Varaprasada Rao GGSESTC
  • 114. The probability of completing the project within 19 days is given by, P (Z< Z0) To find Z0 , we know, P (Z <Z Network Model 0) = 0.5 – z (1.3416) (from normal tables, z (1.3416) = 0.4099) = 0.5 – 0.4099 = 0.0901 = 9.01% Thus, the probability of completing the R & D project in 19 days is 9.01%. Since the probability of completing the project in 19 days is less than 20% As in question, we find the probability of completing it in 24 days. 5/10/2016 114Dr. Varaprasada Rao GGSESTC
  • 115. COST ANALYSIS The two important components of any activity are the cost and time. Cost is directly proportional to time and vice versa. For example, in constructing a shopping complex, the expected time of completion can be calculated using the time estimates of various activities. But if the construction has to be finished earlier, it requires additional cost to complete the project. We need to arrive at a time/cost trade-off between total cost of project and total time required to complete it. Normal time: Normal time is the time required to complete the activity at normal conditions and cost. Crash time: Crash time is the shortest possible activity time; crashing more than the normal time will increase the direct cost. Cost Slope Cost slope is the increase in cost per unit of time saved by crashing. A linear cost curve is shown in Figure 8.27. 5/10/2016 115Dr. Varaprasada Rao GGSESTC
  • 116. An activity takes 4 days to complete at a normal cost of Rs. 500.00. If it is possible to complete the activity in 2 days with an additional cost of Rs. 700.00, what is the incremental cost of the activity? Example Incremental Cost or Cost Slope It means, if one day is reduced we have to spend Rs. 100/- extra per day. Project Crashing Procedure for crashing Step1: Draw the network diagram and mark the Normal time and Crash time. Step2: Calculate TE and TL for all the activities. Step3: Find the critical path and other paths. Step 4: Find the slope for all activities and rank them in ascending order. 5/10/2016 116Dr. Varaprasada Rao GGSESTC
  • 117. Step 5: Establish a tabular column with required field. Step 6: Select the lowest ranked activity; check whether it is a critical activity. If so,crash the activity, else go to the next highest ranked activity. Note: The critical path must remain critical while crashing. Step 7: Calculate the total cost of project for each crashing Step 8: Repeat Step 6 until all the activities in the critical path are fully crashed. Example The following Table 8.13 gives the activities of a construction project and other data. If the indirect cost is Rs. 20 per day, crash the activities to find the minimum duration of the project and the project cost associated. 5/10/2016 117 Dr. Varaprasada Rao GGSESTC
  • 118. From the data provided in the table, draw the network diagram (Figure 8.28) and find the critical path. Solution From the diagram, we observe that the critical path is 1-2-5 with project duration of 14 days The cost slope for all activities and their rank is calculated as shown in Table 8.14 5/10/2016 118Dr. Varaprasada Rao GGSESTC
  • 119. The available paths of the network are listed down in Table 8.15 indicating the sequence of crashing (see Figure 8.29). The sequence of crashing and the total cost involved is given in Table 8.16 Initial direct cost = sum of all normal costs given = Rs. 490.00 5/10/2016 119Dr. Varaprasada Rao GGSESTC
  • 120. It is not possible to crash more than 10 days, as all the activities in the critical path are fully crashed. Hence the minimum project duration is 10 days with the total cost of Rs. 970.00. Activity Crashed Project Duration Critical Path Direct Cost in (Rs.) Indirect Cost in (Rs.) Total Cost in (Rs.) - 14 1-2-5 490 14 x 20 = 280 770 1 – 2(2) 2 – 5(2) 2 – 4(1) 3 – 4(2) 10 1 – 2 – 5 1 – 3 – 4 – 5 1 – 2 – 4 – 5 490 + (2 x 15) + (2 x 100) + (1 x 10) + (2 x 20) = 770 10 x 20 = 200 970 5/10/2016 120Dr. Varaprasada Rao GGSESTC
  • 124. a. Draw the project network diagram. b. Calculate the length and variance of the critical path. c. What is the probability that the jobs on the critical path can be completed in 41 days? 5/10/2016 124Dr. Varaprasada Rao GGSESTC
  • 125. Dr. Varaprasada Rao GGSESTC 125 Dr. M Varaprasada Rao Director.ggsestc@gmail.com 5/10/2016