SETTING OUT OF BUILDING
BUILDING TECHNOLOGY AND MATERIALS III
TERM I
2
The operations carried out once the site is handed over
• Clearing the site
• Setting out the building
• Establishing a datum level
3
What is setting out ?
It is the process of developing the physical positions of corners and walls of a
building, and it’s done by transferring dimensions from the layout plan (also called
as setting out plan, demarcation plan) to the ground. The setting out clearly defines
the outline of the excavations and the centre line of the walls, so that the
construction can be carried out according to the plan.
When is setting out done ?
• when building a new house
• when renovating an already existing one, especially an extension.
The process of Setting out is done by a contractor, and overseen by the lead project
consultant engineer, architect or any other qualified member of the project team.
Function of setting out
• To establish the position of the trench and wall of the house as well as the
position of corners and rooms.
4
METHODS OF SETTING OUT
1. Peg or rope method (commonly used).
2. Dumpy Level (Best for big construction projects)
5
ITEMS REQUIRED IN SETTING OUT.
• Timber, 75mm by 50mm or any
appropriate size.
• Round poles/ timber to act as pegs or
steel for hard ground.
• Nylon threads (Manila rope).
• Ordinary nails inch and 2 inch.
• White chalk or lime.
• Clear hose pipe for determining
horizontal levels.
• Sledge hammer.
• Measuring tape
• Builder’s square
6
DATUM LEVEL
A point which serves as a reference or base for the measurement of other quantities
Where there are no benchmarks on or near the
site, a suitable datum must be established. A
site datum or temporary benchmark could be a
post set in concrete or a concrete plinth set up
on site.
7
PROCESS OF SETTING OUT.
• Setting out is done on the principle of whole to part. According to this principle
the largest possible rectangle of the building is found and set out. The rectangle
is further partitioned into small parts (internal rooms).
• The first thing we need to establish is a parallel/ reference/ base line, to which
all other lines can be related. This can be taken along an existing building close
to the proposed new structure/ boundary wall if existing/ kerb line etc.
8
9
PROCESS OF SETTING OUT
STEP 1: SETTING OUT THE BUILDING LINE
Two square offset lines are set from the kerb to the position of the building line. The
length of the line is greater than the width of the proposed building.
Pegs are positioned at these points and a ranging line is fixed to these, giving a
position of the building line .
10
STEP 2: SETTING OUT FRONTAGE LINE/ BASE LINE
After taking the dimensions from the drawing, the frontage line is set out. This can be
either on building line or behind it.
The first corner peg (A) will be positioned from dimensions given on the drawing which
relates to site features such as distance from kerb, gate post, boundary wall etc.
Eg: the point A is positioned a distance of (D) from the boundary.
Following the position of first peg, the second peg (B) is positioned after carefully
measuring the width along the frontage line.
The nail is knocked into each peg to determine the exact position of the corner.
11
STEP 3: SETTING OUT OF FIRST RIGHT ANGLE TO THE FRONTAGE LINE
Attach the taut line to the nail on the corner peg which will be extended well beyond the length of the
wall to be set out.
Adjust the line carefully to cross the frontage line at 90 degree by using a builder’s square or the
3:4:5 method.
When the line is correct, knock the peg with nail at the distance greater than the length of the wall.
12
RIGHT ANGLE TRINAGLE USED IN SETTING OUT
One of the most important procedure used in setting out is the process of ensuring that all
right angle corners are properly aligned. One of the simplest ways is to use the method
known as 3:4:5 triangle method.
PROCEDURE:
1. A peg with a nail is fixed exactly at 3m from
the corner peg on the fixed line.
2. A measuring tape is the hooked to the nail on
the corner peg and another tape is hooked to
the nail of the peg on the front line.
3. Both the tapes are pulled towards the end wall
and with distance of 4m showing on one tape
and 5m on the other tape. Where they cross
third peg will be fixed.
4. This will establish a line at 90 degree to the
front line.
13
STEP 4: SETTING OUT OF SECOND RIGHT ANGLE TO THE FRONTAGE
LINE
Measure the same length from the frontage line and set point D.
Check the ranging lines before proceeding.
14
STEP 5: SETTING OUT
OF FINAL BACK LINE
Measure the dimensions of
the building side wall from
the outer peg of the frontage
line and set pegs parallel to
the wall lines.
Attach ranging lines to the
pegs to establish the back
wall line.
Pegs can be positioned at G
and H, but this is not
essential.
15
STEP 6: CHECKING THE
BUILDING SETTING OUT
The setting out will be confirmed if
all measurements are correct and the
diagonals measure exactly the same.
Measure the dimensions from A to G
and B to H. these should be same if
the building has been set perfectly.
If there is some difference in the
measurement, adjust the back pegs
as per dimensions. The frontage line
should not be altered.
16
STEP 7: SET UP PROFILES AND ATTACH RANGING LINES
When the building has been set out and proved by checking the diagonals, profiles can be erected to
enable the corner points to be easily located after the trenches have been excavated.
The ranging lines attached to the pegs are extended by holding the line to pass over the peg to the
profile.
The wall position is then clearly marked on the profile.
17
POSITIONING OF PROFILE
The profiles are positioned well away from the proposed excavations to allow an adequate
working space. This is even more important when the excavations is to be carried out by a
mechanical means.
18
SETTING PROFILE LEVELS
While setting up profiles, it is essential that they are as level as possible. This avoids
inaccuracies when re measuring the walls and diagonals before commencing work.
The profile is most conveniently levelled to the DPC level of the proposed building.
19
BONING RODS
A boning rod is a simple device used to quickly position levelling pegs. It consist of two
pieces of timber nailed together at right angles. Boing rod can be used to transfer levels
between the two known points.
20
MARKING THE POSITION OF FOUNDATION TRENCH
Before excavation begins, the position of the foundation trench is marked on the ground.
The original corner pegs can be then removed. The foundation line is then marked using
lime or a spray paint.
21
22
THANK YOU
NEXT TOPIC
SOIL TYPES AND ITS BEHAVIOUR

More Related Content

What's hot

Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructureguasiya
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildingsAshar Gill
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGVISHNU VIJAYAN
 
Chapter 1 introduction of building construction
Chapter 1 introduction of building constructionChapter 1 introduction of building construction
Chapter 1 introduction of building constructionKHUSHBU SHAH
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
Scaffolding, underepinning and shoring
Scaffolding, underepinning and shoringScaffolding, underepinning and shoring
Scaffolding, underepinning and shoringlaxman singh
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated StructuresBoopathi Raja
 

What's hot (20)

Setting out 12042018
Setting out 12042018Setting out 12042018
Setting out 12042018
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Building Components
Building ComponentsBuilding Components
Building Components
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Foundation ppt
Foundation pptFoundation ppt
Foundation ppt
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Formwork
FormworkFormwork
Formwork
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Levelling
LevellingLevelling
Levelling
 
Earthwork
EarthworkEarthwork
Earthwork
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
 
TYPES OF Foundation
TYPES OF FoundationTYPES OF Foundation
TYPES OF Foundation
 
Chapter 1 introduction of building construction
Chapter 1 introduction of building constructionChapter 1 introduction of building construction
Chapter 1 introduction of building construction
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Scaffolding, underepinning and shoring
Scaffolding, underepinning and shoringScaffolding, underepinning and shoring
Scaffolding, underepinning and shoring
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 

Viewers also liked

CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADGLA University
 
building material
building materialbuilding material
building materialnicocarlos
 
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS LOUIS WAYNE
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Dexter Ng
 
Building materials elements of civil engineering
Building materials elements of civil engineeringBuilding materials elements of civil engineering
Building materials elements of civil engineeringPriyank Bhimani
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materialsAkash Patel
 
Green Building Construction in India
Green Building Construction in IndiaGreen Building Construction in India
Green Building Construction in Indiaintellobuild
 
Scaffolding Power Point
Scaffolding Power PointScaffolding Power Point
Scaffolding Power PointAshlow
 
Construction Materials
Construction MaterialsConstruction Materials
Construction Materialsrocioyana
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materialsGAURAV. H .TANDON
 

Viewers also liked (20)

CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Mortars and Plasters
Mortars and PlastersMortars and Plasters
Mortars and Plasters
 
Glass
GlassGlass
Glass
 
Non Ferrous Metal
Non Ferrous MetalNon Ferrous Metal
Non Ferrous Metal
 
Plastic
PlasticPlastic
Plastic
 
building material
building materialbuilding material
building material
 
Scaffolding Technique
Scaffolding TechniqueScaffolding Technique
Scaffolding Technique
 
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS CIVIL ENGINEERING  CONSTRUCTIONS MATERIALS
CIVIL ENGINEERING CONSTRUCTIONS MATERIALS
 
Timber-II
Timber-IITimber-II
Timber-II
 
Insulating material
Insulating materialInsulating material
Insulating material
 
Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1 Final BUILDING CONSTRUCTION 1
Final BUILDING CONSTRUCTION 1
 
Building materials elements of civil engineering
Building materials elements of civil engineeringBuilding materials elements of civil engineering
Building materials elements of civil engineering
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materials
 
Green Building Construction in India
Green Building Construction in IndiaGreen Building Construction in India
Green Building Construction in India
 
Scaffolds ppt construction
Scaffolds ppt constructionScaffolds ppt construction
Scaffolds ppt construction
 
Scaffolding Power Point
Scaffolding Power PointScaffolding Power Point
Scaffolding Power Point
 
Construction Materials
Construction MaterialsConstruction Materials
Construction Materials
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Building construction materials
Building construction materialsBuilding construction materials
Building construction materials
 

Similar to Setting out of building

Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting outLuke D'Arcy
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting outLuke D'Arcy
 
Setting out of Building
Setting out of BuildingSetting out of Building
Setting out of BuildingPhurba Tamang
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptxGabrielBentil1
 
SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2Nhatz Marticio
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveysEst
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level Luke D'Arcy
 
Tutor brickwork below ground level
Tutor brickwork below ground levelTutor brickwork below ground level
Tutor brickwork below ground levelLuke D'Arcy
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insituLingWei11
 
BuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 StepsBuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 StepsBrian Corder
 
Plinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protectionPlinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protectionAkshayKamble94
 
procedures-for-mivan-formwork
procedures-for-mivan-formworkprocedures-for-mivan-formwork
procedures-for-mivan-formworkAmrish Tyagi
 
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfJunaidMughal34
 
Construction Survey
Construction SurveyConstruction Survey
Construction Surveyhalmifaizol
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01Rajesh Rajguru
 

Similar to Setting out of building (20)

Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Setting out of Building
Setting out of BuildingSetting out of Building
Setting out of Building
 
Integrated project.pptx
Integrated project.pptxIntegrated project.pptx
Integrated project.pptx
 
Apply set out work.pdf
Apply set out work.pdfApply set out work.pdf
Apply set out work.pdf
 
SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2SLK Carpentry 9 Quarter 2
SLK Carpentry 9 Quarter 2
 
S2 8 construction surveys
S2 8 construction surveysS2 8 construction surveys
S2 8 construction surveys
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level
 
Tutor brickwork below ground level
Tutor brickwork below ground levelTutor brickwork below ground level
Tutor brickwork below ground level
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
How to install False Ceiling?
How to install False Ceiling?How to install False Ceiling?
How to install False Ceiling?
 
BuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 StepsBuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
BuildBlock Insulating Concrete Form (ICF) Construction in 22 Steps
 
Plinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protectionPlinth beam work procedure - checklist, protection
Plinth beam work procedure - checklist, protection
 
procedures-for-mivan-formwork
procedures-for-mivan-formworkprocedures-for-mivan-formwork
procedures-for-mivan-formwork
 
CE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdfCE Lec Slides, Setting out.pdf
CE Lec Slides, Setting out.pdf
 
Deck marking
Deck markingDeck marking
Deck marking
 
Construction Survey
Construction SurveyConstruction Survey
Construction Survey
 
Bcs day-two-exam
Bcs day-two-examBcs day-two-exam
Bcs day-two-exam
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01
 
Deck marking
Deck markingDeck marking
Deck marking
 

Recently uploaded

原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一diploma 1
 
韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作7tz4rjpd
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024CristobalHeraud
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryWilliamVickery6
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一Fi L
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degreeyuu sss
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改yuu sss
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证nhjeo1gg
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfneelspinoy
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
Mookuthi is an artisanal nose ornament brand based in Madras.
Mookuthi is an artisanal nose ornament brand based in Madras.Mookuthi is an artisanal nose ornament brand based in Madras.
Mookuthi is an artisanal nose ornament brand based in Madras.Mookuthi
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfAayushChavan5
 
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...Rishabh Aryan
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Servicejennyeacort
 

Recently uploaded (20)

原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
 
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
办理(USYD毕业证书)澳洲悉尼大学毕业证成绩单原版一比一
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
Design Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William VickeryDesign Portfolio - 2024 - William Vickery
Design Portfolio - 2024 - William Vickery
 
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
办理学位证(TheAuckland证书)新西兰奥克兰大学毕业证成绩单原版一比一
 
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
专业一比一美国亚利桑那大学毕业证成绩单pdf电子版制作修改#真实工艺展示#真实防伪#diploma#degree
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdf
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
 
Mookuthi is an artisanal nose ornament brand based in Madras.
Mookuthi is an artisanal nose ornament brand based in Madras.Mookuthi is an artisanal nose ornament brand based in Madras.
Mookuthi is an artisanal nose ornament brand based in Madras.
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdf
 
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
 

Setting out of building

  • 1. SETTING OUT OF BUILDING BUILDING TECHNOLOGY AND MATERIALS III TERM I
  • 2. 2 The operations carried out once the site is handed over • Clearing the site • Setting out the building • Establishing a datum level
  • 3. 3 What is setting out ? It is the process of developing the physical positions of corners and walls of a building, and it’s done by transferring dimensions from the layout plan (also called as setting out plan, demarcation plan) to the ground. The setting out clearly defines the outline of the excavations and the centre line of the walls, so that the construction can be carried out according to the plan. When is setting out done ? • when building a new house • when renovating an already existing one, especially an extension. The process of Setting out is done by a contractor, and overseen by the lead project consultant engineer, architect or any other qualified member of the project team. Function of setting out • To establish the position of the trench and wall of the house as well as the position of corners and rooms.
  • 4. 4 METHODS OF SETTING OUT 1. Peg or rope method (commonly used). 2. Dumpy Level (Best for big construction projects)
  • 5. 5 ITEMS REQUIRED IN SETTING OUT. • Timber, 75mm by 50mm or any appropriate size. • Round poles/ timber to act as pegs or steel for hard ground. • Nylon threads (Manila rope). • Ordinary nails inch and 2 inch. • White chalk or lime. • Clear hose pipe for determining horizontal levels. • Sledge hammer. • Measuring tape • Builder’s square
  • 6. 6 DATUM LEVEL A point which serves as a reference or base for the measurement of other quantities Where there are no benchmarks on or near the site, a suitable datum must be established. A site datum or temporary benchmark could be a post set in concrete or a concrete plinth set up on site.
  • 7. 7 PROCESS OF SETTING OUT. • Setting out is done on the principle of whole to part. According to this principle the largest possible rectangle of the building is found and set out. The rectangle is further partitioned into small parts (internal rooms). • The first thing we need to establish is a parallel/ reference/ base line, to which all other lines can be related. This can be taken along an existing building close to the proposed new structure/ boundary wall if existing/ kerb line etc.
  • 8. 8
  • 9. 9 PROCESS OF SETTING OUT STEP 1: SETTING OUT THE BUILDING LINE Two square offset lines are set from the kerb to the position of the building line. The length of the line is greater than the width of the proposed building. Pegs are positioned at these points and a ranging line is fixed to these, giving a position of the building line .
  • 10. 10 STEP 2: SETTING OUT FRONTAGE LINE/ BASE LINE After taking the dimensions from the drawing, the frontage line is set out. This can be either on building line or behind it. The first corner peg (A) will be positioned from dimensions given on the drawing which relates to site features such as distance from kerb, gate post, boundary wall etc. Eg: the point A is positioned a distance of (D) from the boundary. Following the position of first peg, the second peg (B) is positioned after carefully measuring the width along the frontage line. The nail is knocked into each peg to determine the exact position of the corner.
  • 11. 11 STEP 3: SETTING OUT OF FIRST RIGHT ANGLE TO THE FRONTAGE LINE Attach the taut line to the nail on the corner peg which will be extended well beyond the length of the wall to be set out. Adjust the line carefully to cross the frontage line at 90 degree by using a builder’s square or the 3:4:5 method. When the line is correct, knock the peg with nail at the distance greater than the length of the wall.
  • 12. 12 RIGHT ANGLE TRINAGLE USED IN SETTING OUT One of the most important procedure used in setting out is the process of ensuring that all right angle corners are properly aligned. One of the simplest ways is to use the method known as 3:4:5 triangle method. PROCEDURE: 1. A peg with a nail is fixed exactly at 3m from the corner peg on the fixed line. 2. A measuring tape is the hooked to the nail on the corner peg and another tape is hooked to the nail of the peg on the front line. 3. Both the tapes are pulled towards the end wall and with distance of 4m showing on one tape and 5m on the other tape. Where they cross third peg will be fixed. 4. This will establish a line at 90 degree to the front line.
  • 13. 13 STEP 4: SETTING OUT OF SECOND RIGHT ANGLE TO THE FRONTAGE LINE Measure the same length from the frontage line and set point D. Check the ranging lines before proceeding.
  • 14. 14 STEP 5: SETTING OUT OF FINAL BACK LINE Measure the dimensions of the building side wall from the outer peg of the frontage line and set pegs parallel to the wall lines. Attach ranging lines to the pegs to establish the back wall line. Pegs can be positioned at G and H, but this is not essential.
  • 15. 15 STEP 6: CHECKING THE BUILDING SETTING OUT The setting out will be confirmed if all measurements are correct and the diagonals measure exactly the same. Measure the dimensions from A to G and B to H. these should be same if the building has been set perfectly. If there is some difference in the measurement, adjust the back pegs as per dimensions. The frontage line should not be altered.
  • 16. 16 STEP 7: SET UP PROFILES AND ATTACH RANGING LINES When the building has been set out and proved by checking the diagonals, profiles can be erected to enable the corner points to be easily located after the trenches have been excavated. The ranging lines attached to the pegs are extended by holding the line to pass over the peg to the profile. The wall position is then clearly marked on the profile.
  • 17. 17 POSITIONING OF PROFILE The profiles are positioned well away from the proposed excavations to allow an adequate working space. This is even more important when the excavations is to be carried out by a mechanical means.
  • 18. 18 SETTING PROFILE LEVELS While setting up profiles, it is essential that they are as level as possible. This avoids inaccuracies when re measuring the walls and diagonals before commencing work. The profile is most conveniently levelled to the DPC level of the proposed building.
  • 19. 19 BONING RODS A boning rod is a simple device used to quickly position levelling pegs. It consist of two pieces of timber nailed together at right angles. Boing rod can be used to transfer levels between the two known points.
  • 20. 20 MARKING THE POSITION OF FOUNDATION TRENCH Before excavation begins, the position of the foundation trench is marked on the ground. The original corner pegs can be then removed. The foundation line is then marked using lime or a spray paint.
  • 21. 21
  • 22. 22 THANK YOU NEXT TOPIC SOIL TYPES AND ITS BEHAVIOUR