SlideShare a Scribd company logo
1 of 20
BOX
PUSHING
TECHNIQUE
CONVENTIONAL METHOD
Demerits
• Increased time for execution
• Interruption in traffic
• Cost factor was high
Open cut system
• Excavation
• Placing
• Covering
Visit www.seminarlinks.blogspot.com to download
NEED FOR THE ALTERNATIVE
• Present day Intensity of Traffic, both Rail & Road due to the
fast development, is very heavy it cannot the disturbed, for
construction of under bridges or Canal Crossings, drainage
etc by conventional i.e. open cut system.
• Box Pushing Technique is developed where in R.C.C. Boxes
in segments are cast out side and pushed through the heavy
embankments of Rail or Road by Jacking.
METHODOLOGY
• Excavation
• Casting of Thrust Bed
• Fabrication of Front and Rear shield
• Box Casting and placing
• Pushing-shifting-pushing operation
• Miscellaneous works
• Precautions
Excavation and casting of thrust bed
Open excavation is carried out for construction of Thrust bed
Thrust bed
• The Thrustbed and Thrust Beam and keys are designed in R.C.C. to
resist the required Thrust extorted by Jacking force and transfer it to
soil at bottom and sides.
• In cohesive soils even shallow piles are required to transfer the load.
• Provision for Jacking supports is made by providing suitable Pockets
in the bed to accommodate pin supports.
• On completion of Jacking the thrust bed is utilised as floor bed, and so
it is left in place.
Box Casting And Pushing
• The RCC Box is cast in segments
of convenient lengths of Total
pushing length.
• The Box section is designed as per
IRS / IRC codes of practice for
loading. Concrete grade normally
kept as M-35.
Front Cutting Shield & Rear Jacking Shield
• The First Segment of the precast box is provided with a specially
designed structure named as cutting shield which forms the front
working face with a cutting edge fabricated from 16 to 20 mm thick M.S.
Plates and housed on RCC Box section with suitable anchor bolts.
• Necessary strengthening is provided by stiffeners and face plates of Box
in front on completion of jacking the outer shell of the shield is cut and
removed
• The Rear Jacking shield is provided by anchoring steel plate on the
face of Bottom slab of RCC Box suitably designed to distribute the
jacking load uniformly on concrete area.
Fabrication of Front Shield
It is fabricated for cutting action and to provide support , to prevent caving in of soil.
Fabrication of Rear Shield
It is provided by anchoring steel plates on the face of bottom slab of
RCC box to suitably distribute the jacking load.
Intermediate Jacking Station
• As total length of Box is cast in Segments, each segment is
pushed turn by turn with necessary jacking force and so for this
necessary intermediate jacking stations are provided, with jacking
pockets in bed & walls.
Pushing Operation of the Box
• The purpose of pushing of Box is to form a horizontal opening below ground or
through embankments, can say a tunnel, by providing precast box units
underground or an embankment, without disturbing the overhead amenities, like
traffic & structures.
• To reduce the frictional resistance, a thin film of Grease and thick gauge plastic
sheet is provided between the top of the thrustbed & Bottom of the Box.
• This is done before casting of the Bottom slab of the box.
• A Glossy Epoxy layer is also provided to reduce friction on the top and prevent the
disturbance of the mass over box to least during progress of pushing
• Where mass of embankment is less or the soil is of poor quality, drag sheet
system is also considered for least resistance of friction and disturbance of mass
above box.
• Auxiliary beds are also provided for casting of the other segments with thin
film of grease and plastic and segments are then brought in alignment of
pushing as and when required as pushing progresses.
• With the progress of jacking, the front unit with shield penetrates into
the embankment and there after excavation within the shield is done
either manually or mechanically and the excavated stuff is transported
outside the working area.
• After the first segment advances to the end of the thrustbed, the second
segment is brought in alignment of the front Box & intermediate jacking
space is lift between the two.
• The progress of pushing is kept continuous and the system of side shifting of
remaining box segments from Auxiliary bed and bring in pushing alignment is
adopted till total length is pushed.
Hydraulic Equipment
• The entire Box Pushing system is matter of proper selection of Hydraulic
equipment, as tremendous driving force is required for pushing of medium to
large size of Boxes.
• So for this, Number of Jack units are provided in series for distribution of
pushing load evenly on the face of the concrete, and all Jacks are operated
simultaneously with a common power pack, which supplies uniform flow of
pressure through network of Hydraulic pipes of required pressure capacity,
commencing from front unit to rear unit. Jacking force is applied in sequence.
• This way pushing cycles are repeated till total pushing is completed.
Precautions
• Cutting edge of front shield is
fabricated with adequate
thickness of steel plate and the
front edges of the steel plate are
sharpened to facilitate
penetration into the soil.
• To prevent caving of earth
during excavation quantity of
earth shall be removed to barest
minimum duly following the slop
of cutting edge.
• Guide channels to be provided in the
thrust bed to guide the segments to
ensure straight alignment
• The level of the boxes should be
continuously checked.
• The Speed limit should be set to 20 km/h
at the site of construction
• The work should be stopped when a train
is passing over the work.
Conclusion
The entire system is purely technical, dependent on Hydraulic system, &
safest method of crossing underground / Embankment, without
disturbing overhead traffic / structures for R.U.B., Canal siphon and
other drainage crossings.
Visit www.seminarlinks.blogspot.com to download
Photo Gallery
Thank YouVisit www.seminarlinks.blogspot.com to download

More Related Content

What's hot

CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSreemajadwani
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFShankar Ramasamy
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundationsDar Hilal
 
Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concreteAglaia Connect
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION Ved Jangid
 
Construction of Road
Construction of RoadConstruction of Road
Construction of RoadAman Shakya
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Application of plate girders in steel construction
Application of plate girders in steel constructionApplication of plate girders in steel construction
Application of plate girders in steel constructionHaider Jafferi
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNeha Vivek
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)SSudhaVelan
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingAnkit Patel
 

What's hot (20)

CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Well foundation
Well foundationWell foundation
Well foundation
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
Design and construction of well foundations
Design and construction of well foundationsDesign and construction of well foundations
Design and construction of well foundations
 
Foundation ppt
Foundation pptFoundation ppt
Foundation ppt
 
Different types of pile
Different types of pile Different types of pile
Different types of pile
 
Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concrete
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
Construction of Road
Construction of RoadConstruction of Road
Construction of Road
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Application of plate girders in steel construction
Application of plate girders in steel constructionApplication of plate girders in steel construction
Application of plate girders in steel construction
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Limit state method
Limit state methodLimit state method
Limit state method
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 

Similar to Box Pushing Technique

Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxcharantinku6799
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxChinnuNinan
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionShyam Anandjiwala
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)ManviVarshney2
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxpateljatin15
 
Building construction
Building constructionBuilding construction
Building constructionnhmurad
 
RCC foundation methodology & process.pptx
RCC foundation methodology & process.pptxRCC foundation methodology & process.pptx
RCC foundation methodology & process.pptxJoydeepPaul54
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
R22 bunker storage of grains
R22 bunker storage of grainsR22 bunker storage of grains
R22 bunker storage of grainsMaya Sharma
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation dilip patidar
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptVaibhavSoni742163
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptHarshKumarEname
 

Similar to Box Pushing Technique (20)

Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptx
 
Module 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptxModule 1 - Jacking techniques.pptx
Module 1 - Jacking techniques.pptx
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant Construction
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Construction portfolio (manvi)
Construction portfolio (manvi)Construction portfolio (manvi)
Construction portfolio (manvi)
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Box Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptxBox Pushing Technology Presentation.pptx
Box Pushing Technology Presentation.pptx
 
Building construction
Building constructionBuilding construction
Building construction
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
RCC foundation methodology & process.pptx
RCC foundation methodology & process.pptxRCC foundation methodology & process.pptx
RCC foundation methodology & process.pptx
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
R22 bunker storage of grains
R22 bunker storage of grainsR22 bunker storage of grains
R22 bunker storage of grains
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Construction of well foundation
Construction of well foundation Construction of well foundation
Construction of well foundation
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 
MODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).pptMODULE 4 Special Concrete (1).ppt
MODULE 4 Special Concrete (1).ppt
 

More from Seminar Links

Artificial Intelligence (A.I.) in Schools (PPT)
Artificial Intelligence (A.I.) in Schools (PPT)Artificial Intelligence (A.I.) in Schools (PPT)
Artificial Intelligence (A.I.) in Schools (PPT)Seminar Links
 
Sustainable Materials Management (SMM)
Sustainable Materials Management (SMM)Sustainable Materials Management (SMM)
Sustainable Materials Management (SMM)Seminar Links
 
Are Top Grades Enough (PPT)
Are Top Grades Enough (PPT)Are Top Grades Enough (PPT)
Are Top Grades Enough (PPT)Seminar Links
 
AI and Youth Employment (PPT)
AI and Youth Employment (PPT)AI and Youth Employment (PPT)
AI and Youth Employment (PPT)Seminar Links
 
Environmental Impacts of COVID-19 Pandemic: PPT
Environmental Impacts of COVID-19 Pandemic: PPTEnvironmental Impacts of COVID-19 Pandemic: PPT
Environmental Impacts of COVID-19 Pandemic: PPTSeminar Links
 
20 Latest Computer Science Seminar Topics on Emerging Technologies
20 Latest Computer Science Seminar Topics on Emerging Technologies20 Latest Computer Science Seminar Topics on Emerging Technologies
20 Latest Computer Science Seminar Topics on Emerging TechnologiesSeminar Links
 
Claytronics | Programmable Matter | PPT
Claytronics | Programmable Matter | PPTClaytronics | Programmable Matter | PPT
Claytronics | Programmable Matter | PPTSeminar Links
 
Three-dimensional Holographic Projection Technology PPT | 2018
Three-dimensional Holographic Projection Technology PPT | 2018Three-dimensional Holographic Projection Technology PPT | 2018
Three-dimensional Holographic Projection Technology PPT | 2018Seminar Links
 
MicroLED : Latest Display Technology | PPT
MicroLED : Latest Display Technology | PPTMicroLED : Latest Display Technology | PPT
MicroLED : Latest Display Technology | PPTSeminar Links
 
Performance of 400 kV line insulators under pollution | PDF | DOC | PPT
Performance of 400 kV line insulators under pollution | PDF | DOC | PPTPerformance of 400 kV line insulators under pollution | PDF | DOC | PPT
Performance of 400 kV line insulators under pollution | PDF | DOC | PPTSeminar Links
 
Highest Largest Tallest Longest in India 2018
Highest Largest Tallest Longest in India 2018Highest Largest Tallest Longest in India 2018
Highest Largest Tallest Longest in India 2018Seminar Links
 
Atmospheric Vortex Engine (AVE)
Atmospheric Vortex Engine (AVE) Atmospheric Vortex Engine (AVE)
Atmospheric Vortex Engine (AVE) Seminar Links
 
Artificial photosynthesis PPT
Artificial photosynthesis PPTArtificial photosynthesis PPT
Artificial photosynthesis PPTSeminar Links
 
How to prevent WannaCry Ransomware
How to prevent WannaCry RansomwareHow to prevent WannaCry Ransomware
How to prevent WannaCry RansomwareSeminar Links
 
Babbitt material ppt
Babbitt material pptBabbitt material ppt
Babbitt material pptSeminar Links
 
Carbon Foam Military Applications
Carbon Foam Military ApplicationsCarbon Foam Military Applications
Carbon Foam Military ApplicationsSeminar Links
 
Future challenges in computer science
Future challenges in computer scienceFuture challenges in computer science
Future challenges in computer scienceSeminar Links
 

More from Seminar Links (20)

Artificial Intelligence (A.I.) in Schools (PPT)
Artificial Intelligence (A.I.) in Schools (PPT)Artificial Intelligence (A.I.) in Schools (PPT)
Artificial Intelligence (A.I.) in Schools (PPT)
 
Sustainable Materials Management (SMM)
Sustainable Materials Management (SMM)Sustainable Materials Management (SMM)
Sustainable Materials Management (SMM)
 
Are Top Grades Enough (PPT)
Are Top Grades Enough (PPT)Are Top Grades Enough (PPT)
Are Top Grades Enough (PPT)
 
AI and Youth Employment (PPT)
AI and Youth Employment (PPT)AI and Youth Employment (PPT)
AI and Youth Employment (PPT)
 
Environmental Impacts of COVID-19 Pandemic: PPT
Environmental Impacts of COVID-19 Pandemic: PPTEnvironmental Impacts of COVID-19 Pandemic: PPT
Environmental Impacts of COVID-19 Pandemic: PPT
 
20 Latest Computer Science Seminar Topics on Emerging Technologies
20 Latest Computer Science Seminar Topics on Emerging Technologies20 Latest Computer Science Seminar Topics on Emerging Technologies
20 Latest Computer Science Seminar Topics on Emerging Technologies
 
Claytronics | Programmable Matter | PPT
Claytronics | Programmable Matter | PPTClaytronics | Programmable Matter | PPT
Claytronics | Programmable Matter | PPT
 
Three-dimensional Holographic Projection Technology PPT | 2018
Three-dimensional Holographic Projection Technology PPT | 2018Three-dimensional Holographic Projection Technology PPT | 2018
Three-dimensional Holographic Projection Technology PPT | 2018
 
MicroLED : Latest Display Technology | PPT
MicroLED : Latest Display Technology | PPTMicroLED : Latest Display Technology | PPT
MicroLED : Latest Display Technology | PPT
 
Performance of 400 kV line insulators under pollution | PDF | DOC | PPT
Performance of 400 kV line insulators under pollution | PDF | DOC | PPTPerformance of 400 kV line insulators under pollution | PDF | DOC | PPT
Performance of 400 kV line insulators under pollution | PDF | DOC | PPT
 
Highest Largest Tallest Longest in India 2018
Highest Largest Tallest Longest in India 2018Highest Largest Tallest Longest in India 2018
Highest Largest Tallest Longest in India 2018
 
Atmospheric Vortex Engine (AVE)
Atmospheric Vortex Engine (AVE) Atmospheric Vortex Engine (AVE)
Atmospheric Vortex Engine (AVE)
 
Artificial photosynthesis PPT
Artificial photosynthesis PPTArtificial photosynthesis PPT
Artificial photosynthesis PPT
 
How to prevent WannaCry Ransomware
How to prevent WannaCry RansomwareHow to prevent WannaCry Ransomware
How to prevent WannaCry Ransomware
 
Dams PPT
Dams PPTDams PPT
Dams PPT
 
Bio mass Energy
Bio mass EnergyBio mass Energy
Bio mass Energy
 
Babbitt material ppt
Babbitt material pptBabbitt material ppt
Babbitt material ppt
 
Ceramic Bearing ppt
Ceramic Bearing pptCeramic Bearing ppt
Ceramic Bearing ppt
 
Carbon Foam Military Applications
Carbon Foam Military ApplicationsCarbon Foam Military Applications
Carbon Foam Military Applications
 
Future challenges in computer science
Future challenges in computer scienceFuture challenges in computer science
Future challenges in computer science
 

Recently uploaded

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

Box Pushing Technique

  • 2. CONVENTIONAL METHOD Demerits • Increased time for execution • Interruption in traffic • Cost factor was high Open cut system • Excavation • Placing • Covering Visit www.seminarlinks.blogspot.com to download
  • 3. NEED FOR THE ALTERNATIVE • Present day Intensity of Traffic, both Rail & Road due to the fast development, is very heavy it cannot the disturbed, for construction of under bridges or Canal Crossings, drainage etc by conventional i.e. open cut system. • Box Pushing Technique is developed where in R.C.C. Boxes in segments are cast out side and pushed through the heavy embankments of Rail or Road by Jacking.
  • 4. METHODOLOGY • Excavation • Casting of Thrust Bed • Fabrication of Front and Rear shield • Box Casting and placing • Pushing-shifting-pushing operation • Miscellaneous works • Precautions
  • 5. Excavation and casting of thrust bed Open excavation is carried out for construction of Thrust bed
  • 6. Thrust bed • The Thrustbed and Thrust Beam and keys are designed in R.C.C. to resist the required Thrust extorted by Jacking force and transfer it to soil at bottom and sides. • In cohesive soils even shallow piles are required to transfer the load. • Provision for Jacking supports is made by providing suitable Pockets in the bed to accommodate pin supports. • On completion of Jacking the thrust bed is utilised as floor bed, and so it is left in place.
  • 7. Box Casting And Pushing • The RCC Box is cast in segments of convenient lengths of Total pushing length. • The Box section is designed as per IRS / IRC codes of practice for loading. Concrete grade normally kept as M-35.
  • 8. Front Cutting Shield & Rear Jacking Shield • The First Segment of the precast box is provided with a specially designed structure named as cutting shield which forms the front working face with a cutting edge fabricated from 16 to 20 mm thick M.S. Plates and housed on RCC Box section with suitable anchor bolts. • Necessary strengthening is provided by stiffeners and face plates of Box in front on completion of jacking the outer shell of the shield is cut and removed • The Rear Jacking shield is provided by anchoring steel plate on the face of Bottom slab of RCC Box suitably designed to distribute the jacking load uniformly on concrete area.
  • 9. Fabrication of Front Shield It is fabricated for cutting action and to provide support , to prevent caving in of soil.
  • 10. Fabrication of Rear Shield It is provided by anchoring steel plates on the face of bottom slab of RCC box to suitably distribute the jacking load.
  • 11. Intermediate Jacking Station • As total length of Box is cast in Segments, each segment is pushed turn by turn with necessary jacking force and so for this necessary intermediate jacking stations are provided, with jacking pockets in bed & walls.
  • 12. Pushing Operation of the Box • The purpose of pushing of Box is to form a horizontal opening below ground or through embankments, can say a tunnel, by providing precast box units underground or an embankment, without disturbing the overhead amenities, like traffic & structures. • To reduce the frictional resistance, a thin film of Grease and thick gauge plastic sheet is provided between the top of the thrustbed & Bottom of the Box. • This is done before casting of the Bottom slab of the box. • A Glossy Epoxy layer is also provided to reduce friction on the top and prevent the disturbance of the mass over box to least during progress of pushing • Where mass of embankment is less or the soil is of poor quality, drag sheet system is also considered for least resistance of friction and disturbance of mass above box.
  • 13. • Auxiliary beds are also provided for casting of the other segments with thin film of grease and plastic and segments are then brought in alignment of pushing as and when required as pushing progresses. • With the progress of jacking, the front unit with shield penetrates into the embankment and there after excavation within the shield is done either manually or mechanically and the excavated stuff is transported outside the working area. • After the first segment advances to the end of the thrustbed, the second segment is brought in alignment of the front Box & intermediate jacking space is lift between the two. • The progress of pushing is kept continuous and the system of side shifting of remaining box segments from Auxiliary bed and bring in pushing alignment is adopted till total length is pushed.
  • 14. Hydraulic Equipment • The entire Box Pushing system is matter of proper selection of Hydraulic equipment, as tremendous driving force is required for pushing of medium to large size of Boxes. • So for this, Number of Jack units are provided in series for distribution of pushing load evenly on the face of the concrete, and all Jacks are operated simultaneously with a common power pack, which supplies uniform flow of pressure through network of Hydraulic pipes of required pressure capacity, commencing from front unit to rear unit. Jacking force is applied in sequence. • This way pushing cycles are repeated till total pushing is completed.
  • 15. Precautions • Cutting edge of front shield is fabricated with adequate thickness of steel plate and the front edges of the steel plate are sharpened to facilitate penetration into the soil. • To prevent caving of earth during excavation quantity of earth shall be removed to barest minimum duly following the slop of cutting edge. • Guide channels to be provided in the thrust bed to guide the segments to ensure straight alignment • The level of the boxes should be continuously checked. • The Speed limit should be set to 20 km/h at the site of construction • The work should be stopped when a train is passing over the work.
  • 16. Conclusion The entire system is purely technical, dependent on Hydraulic system, & safest method of crossing underground / Embankment, without disturbing overhead traffic / structures for R.U.B., Canal siphon and other drainage crossings. Visit www.seminarlinks.blogspot.com to download
  • 18.
  • 19.