PRE-COMMISSIONING &
      COMMISSIONING

             A discussion on
             Pre-commissioning /
             Commissioning &
             Start Up of Projects




1
Contents

       Objective
       Common work at process plant at pipe
        line
       Definition of Mechanical Completion
       Pre-Commissioning Definition and
        Procedure

2
Contents(Continued)

       Activities (Piping & vessels, Mechanical,
        Electrical, Instrumentation, Operations)
       Check Sheets
       Punch Listing
       Completion Activities



3
Objectives


       Start-up and hand-over of the completed

        plant to the Client.

       To support client in operation of plant



                               .
4
COMMISSIONING
                                    & START-UP




MECHANICAL
COMPLETION
                                                    SYSTEM /   OPERATION
Inclusive of                        PLANT
                    COMMISSIONING                   PACKAGE    STAFF
Pre-commissioning                   START-UP
                                                    HANDOVER   TRAINING
Activities




                                                                           5
Commissioning Works
                       At Process Plants
        PIPING / VESSEL                                       ELECT / INSTRUM
•Flushing/Blowing                                      •Preliminary Check
•Chemical Cleaning                                     •Calibration
•Reinstatement                                         •Circuitry Check
•Gross leak with N2                                    •Continuity Check
•Drying                                                •Loop Test
•Inerting                                              • Energization (Power Up)
•Hydrocarbon In                                        •Performance Tests

                                MANAGEMENT
                          •Systems Breakdown
                          •Preparation of Procedures
                          •Loop Folder
                          •Circuit Folder
                          •Test Packs
                                                            CONTROL SYSTEM
    ROTATING EQUIPMENT                                 •SCADA / PCS SAT
•Alignment                                             •Fire & Gas System
•Belt Tensioning                                       •Safety Shutdown Sys.
•Motor Run in Test                                     •Alarm Set-Up & Test
•Vibration Test                                        •Simulation Test

                                                                                   6
Commissioning Works
                  At Pipe Lines
      PRECOMMISSIONING       SPECIALIZED PIPELINE CLEANING
•Cleaning                    •Dewaxing
•Flooding                    •Descaling
•Hydro testing               •De-oiling
•Dewatering & Drying         •Pit cleaning
•Flushing                    •Chemical cleaning
•Nitrogen Inserting          •Combined cleaning methods




     ASSOCIATED SERVICES           PIPELINE INSPECTION
•Temporary pipeline repair   •Geometry inspection
•On-site supervision         •Metal loss inspection
•Cathodic protection         •Crack detection
•Hot tapping & stoppling     •Leak detection and location
•Flow assurance Etc.         •Profile monitoring and mapping

                                                               7
Definition of Mechanical Completion
        & Construction Completion

       Mechanical Completion: A series of
        activities that MUST be completed prior to
        the commencement of Commissioning and
        Start-up of a Utility System or Main Process
        Unit.
       Mechanical Completion ALSO includes
        ALL pre-commissioning activities.

8
Pre-Commissioning Overview

       Process: Confirmation of Loops
        according to P& ID’s
       Vessels: Internal Inspection & Box up
       Piping: Hydro testing, reinstatement &
        verification of main gaskets.
       Stationary Equipment: Tightening and
        Final Box Up.
       Rotary Equipment: Leveling, Rotation,
9       Alignment & lubrications
Pre-Commissioning Activities –
                    Piping & Vessels

        Field checks as per isometrics and P&ID’s

        Verification of hydro testing

        Verification of flushing , blowing & drying

        Internal inspection of equipment as
         required

10
Pre-Commissioning Activities –
           Piping & Vessels(Continued)

        Verification of Internals
        Re-instatement of all flanges, control
         value, orifices, Psv’s and steam traps.
        Verification of blinds / spades installation
         and / or removal
        Box up: Pre-commissioned and closed



11
Pre-Commissioning Activities –
     Mechanical Discipline

        Verification of coupling and belt
         alignment

        Pumps / compressor checks

        Bearing lubrications

        Inspection / checking of filters & strainers

12
Pre-Commissioning Activities –
     Electrical Discipline

      MCC & UPS installation
      Field electrical installation
       – Cable Meggering (Continuity)
       – Termination of wiring; end devices
         to JB’s & MCC
       – Termination & Glanding according
         to area classification.

13
Pre-Commissioning Activities –
     Electrical Discipline(Continued)


        Motor installation

         –   Resistance maggering

         –   Rotation confirmation

         –   No load test run

14
Pre-Commissioning Activities -
                Instrumentation

        Instrument installation checks
        PSV calibration
        Calibration of transmitters and switches
        Loop checking of device end to PLC
        Function testing of PLC & ESD systems


15
Pre-Commissioning Check Sheets

        Vessel & Piping Check Sheets

        Mechanical Check Sheets

        Electrical Check Sheets

        Instrumentation Check Sheets


16      Operation / Process Check Sheets
Punch Listing

        Punch Lists are created and sorted as per disciplines
          – Piping and Vessels
          – Mechanical
          – Electrical
          – Instrumentation
          – Operations
        Punch Lists are categorized on a priority basis
          – Category “A”; MUST be completed prior to
             Commissioning
          – Category “B”; MUST be completed prior to Start-up
          – Category “C”; Signifies end of job
        Construction Contractor MUST have a coordinated
         management plan of Punch Listing including categorizing
         of punch list items
17
Completion Activities

        Flushing Blowing Certificates
        Box Up Certificate
        Mechanical Completion Certificate for
         each Utility and Process Unit
        Handover Certificate


18
COMMISSIONING

        Definition

        Utility Description

        Commissioning Activities

        Check Sheets

        Commissioning / Start Up Procedure
19
Systems Description

     Commissioning of The Following Systems
      Air Compression System

        MCC & Plant Lighting System
        UPS, PLC & Plant ESD System
        Fire Water System
        Fire & Gas Detection System


20
Systems Description

        Instrument Air Package
        Inert Gas Package
        Fuel Gas System
        Closed Drain & Waste Water Systems
        Condensate Transfer System
        Process Units; Reactor

21
Commissioning Check Sheets

        Commissioning check sheets are given in
         the Commissioning Protocol.




22
START-UP OF PROCESS UNITS

        Utilities in Service
        Introduction of Raw material (Vacuum Residue
         Feed)
        Introduction of Process Air & Steam
        Production of required grades of products
        Maintaining required proportion of off gases as
         per specs
        Achievement of required steam temperature
        Obtaining steam temperature compatible to
         system steam temperature.

23
Issues for Discussion.


        Less re-work SS304, 304L

        Carbon filter back flow

        Go for the standard packages

        15 KM pipeline

24
THANK YOU



25

More Related Content

What's hot

Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installationswan saiful arini
 
Hot Tapping Requirement
Hot Tapping RequirementHot Tapping Requirement
Hot Tapping Requirementwael el ariny
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
 
Simple Piping design
Simple Piping designSimple Piping design
Simple Piping designMusa Sabri
 
Asme viii Div. 1 presentation rev.0
Asme viii Div. 1  presentation   rev.0Asme viii Div. 1  presentation   rev.0
Asme viii Div. 1 presentation rev.0Mohammad Mahrous
 
what is process piping
what is process pipingwhat is process piping
what is process pipingVarun Patel
 
Process piping fundamentals, codes and standards module 1
Process piping fundamentals, codes and standards    module 1Process piping fundamentals, codes and standards    module 1
Process piping fundamentals, codes and standards module 1BHARAT BELLAD
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdfmoumo1
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2Jithu John
 
Floating head heat exchanger - Maintainance
Floating head heat exchanger - MaintainanceFloating head heat exchanger - Maintainance
Floating head heat exchanger - MaintainanceAbhishek Srivastav
 
Piping handbook
Piping handbookPiping handbook
Piping handbookpdmsguy
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overviewAshifuddinAli
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxhesham ismail
 

What's hot (20)

Commissioning of Offshore Installations
Commissioning of Offshore InstallationsCommissioning of Offshore Installations
Commissioning of Offshore Installations
 
Hot Tapping Requirement
Hot Tapping RequirementHot Tapping Requirement
Hot Tapping Requirement
 
Asme b31,pressure piping code
Asme b31,pressure piping codeAsme b31,pressure piping code
Asme b31,pressure piping code
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
Piping ppt1
Piping ppt1Piping ppt1
Piping ppt1
 
Simple Piping design
Simple Piping designSimple Piping design
Simple Piping design
 
Asme viii Div. 1 presentation rev.0
Asme viii Div. 1  presentation   rev.0Asme viii Div. 1  presentation   rev.0
Asme viii Div. 1 presentation rev.0
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Process piping fundamentals, codes and standards module 1
Process piping fundamentals, codes and standards    module 1Process piping fundamentals, codes and standards    module 1
Process piping fundamentals, codes and standards module 1
 
Piping Design ppt.pdf
Piping Design ppt.pdfPiping Design ppt.pdf
Piping Design ppt.pdf
 
Process Plant design fundementals
Process Plant design fundementalsProcess Plant design fundementals
Process Plant design fundementals
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf269831351-PIPING-Q-C-AG-UG.pdf
269831351-PIPING-Q-C-AG-UG.pdf
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2
 
Floating head heat exchanger - Maintainance
Floating head heat exchanger - MaintainanceFloating head heat exchanger - Maintainance
Floating head heat exchanger - Maintainance
 
Piping handbook
Piping handbookPiping handbook
Piping handbook
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
 
Presentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptxPresentation API 570 -510-653.pptx
Presentation API 570 -510-653.pptx
 
HAZARDS-Pneumatic Test(1)
HAZARDS-Pneumatic Test(1)HAZARDS-Pneumatic Test(1)
HAZARDS-Pneumatic Test(1)
 
Pipeline repair techniques
Pipeline repair techniquesPipeline repair techniques
Pipeline repair techniques
 

Viewers also liked

Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processingmubarak2009
 
Petrolium and gas processing
Petrolium and gas processingPetrolium and gas processing
Petrolium and gas processingwaseemakhtar120
 
Hydrocarbon preeti bhatt
Hydrocarbon preeti bhattHydrocarbon preeti bhatt
Hydrocarbon preeti bhattkapde1970
 
Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Fingrid Oyj
 
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies ProfilesHp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies Profilesabakshi2011
 
Power Point On Hydrocarbon
Power Point On HydrocarbonPower Point On Hydrocarbon
Power Point On HydrocarbonSamiran Ghosh
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical CompletionsAndy Lang
 
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enE nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enVugar Ali
 

Viewers also liked (11)

Oil And Gas Processing
Oil And Gas ProcessingOil And Gas Processing
Oil And Gas Processing
 
Petrolium and gas processing
Petrolium and gas processingPetrolium and gas processing
Petrolium and gas processing
 
Hydrocarbon preeti bhatt
Hydrocarbon preeti bhattHydrocarbon preeti bhatt
Hydrocarbon preeti bhatt
 
Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät Commissioning Plan Robert Thelander, Svenska kraftnät
Commissioning Plan Robert Thelander, Svenska kraftnät
 
Hydrocarbons
HydrocarbonsHydrocarbons
Hydrocarbons
 
Hydrocarbons
HydrocarbonsHydrocarbons
Hydrocarbons
 
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies ProfilesHp 2011 Rph Refining Hydrocarbon Technologies Profiles
Hp 2011 Rph Refining Hydrocarbon Technologies Profiles
 
Power Point On Hydrocarbon
Power Point On HydrocarbonPower Point On Hydrocarbon
Power Point On Hydrocarbon
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
The Future of Leadership Development
The Future of Leadership DevelopmentThe Future of Leadership Development
The Future of Leadership Development
 
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-enE nodeb commissioning guide(v100r005c00 04)(pdf)-en
E nodeb commissioning guide(v100r005c00 04)(pdf)-en
 

Similar to Commissioning & Interface With Engineering

Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningsakol kai
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineJOBY Joby.Stephan
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineerankur sood
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineerankur sood
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEdamian Filip
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & ToubroJAIPRAKASH PATIL
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdfAnithaSyam
 
POWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.pptPOWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.pptPOOJAOHRI2
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply systemceutics1315
 

Similar to Commissioning & Interface With Engineering (20)

Mind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioningMind map the_9_key_elements_video_05_pre-commissioning
Mind map the_9_key_elements_video_05_pre-commissioning
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
Ankur Sood-Instrument engineer
Ankur Sood-Instrument engineerAnkur Sood-Instrument engineer
Ankur Sood-Instrument engineer
 
OMV Muzaffar CV
OMV Muzaffar CVOMV Muzaffar CV
OMV Muzaffar CV
 
updated_ashishmalhotra
updated_ashishmalhotraupdated_ashishmalhotra
updated_ashishmalhotra
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIE
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & Toubro
 
Brij mohan cv
Brij mohan  cvBrij mohan  cv
Brij mohan cv
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdf
 
ELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIANELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIAN
 
ELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIANELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIAN
 
POWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.pptPOWER TRANSFORMER UDAIPUR 29022012.ppt
POWER TRANSFORMER UDAIPUR 29022012.ppt
 
Aamir C.V (1)
Aamir C.V (1)Aamir C.V (1)
Aamir C.V (1)
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply system
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply system
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply system
 

Commissioning & Interface With Engineering

  • 1. PRE-COMMISSIONING & COMMISSIONING A discussion on Pre-commissioning / Commissioning & Start Up of Projects 1
  • 2. Contents  Objective  Common work at process plant at pipe line  Definition of Mechanical Completion  Pre-Commissioning Definition and Procedure 2
  • 3. Contents(Continued)  Activities (Piping & vessels, Mechanical, Electrical, Instrumentation, Operations)  Check Sheets  Punch Listing  Completion Activities 3
  • 4. Objectives  Start-up and hand-over of the completed plant to the Client.  To support client in operation of plant . 4
  • 5. COMMISSIONING & START-UP MECHANICAL COMPLETION SYSTEM / OPERATION Inclusive of PLANT COMMISSIONING PACKAGE STAFF Pre-commissioning START-UP HANDOVER TRAINING Activities 5
  • 6. Commissioning Works At Process Plants PIPING / VESSEL ELECT / INSTRUM •Flushing/Blowing •Preliminary Check •Chemical Cleaning •Calibration •Reinstatement •Circuitry Check •Gross leak with N2 •Continuity Check •Drying •Loop Test •Inerting • Energization (Power Up) •Hydrocarbon In •Performance Tests MANAGEMENT •Systems Breakdown •Preparation of Procedures •Loop Folder •Circuit Folder •Test Packs CONTROL SYSTEM ROTATING EQUIPMENT •SCADA / PCS SAT •Alignment •Fire & Gas System •Belt Tensioning •Safety Shutdown Sys. •Motor Run in Test •Alarm Set-Up & Test •Vibration Test •Simulation Test 6
  • 7. Commissioning Works At Pipe Lines PRECOMMISSIONING SPECIALIZED PIPELINE CLEANING •Cleaning •Dewaxing •Flooding •Descaling •Hydro testing •De-oiling •Dewatering & Drying •Pit cleaning •Flushing •Chemical cleaning •Nitrogen Inserting •Combined cleaning methods ASSOCIATED SERVICES PIPELINE INSPECTION •Temporary pipeline repair •Geometry inspection •On-site supervision •Metal loss inspection •Cathodic protection •Crack detection •Hot tapping & stoppling •Leak detection and location •Flow assurance Etc. •Profile monitoring and mapping 7
  • 8. Definition of Mechanical Completion & Construction Completion  Mechanical Completion: A series of activities that MUST be completed prior to the commencement of Commissioning and Start-up of a Utility System or Main Process Unit.  Mechanical Completion ALSO includes ALL pre-commissioning activities. 8
  • 9. Pre-Commissioning Overview  Process: Confirmation of Loops according to P& ID’s  Vessels: Internal Inspection & Box up  Piping: Hydro testing, reinstatement & verification of main gaskets.  Stationary Equipment: Tightening and Final Box Up.  Rotary Equipment: Leveling, Rotation, 9 Alignment & lubrications
  • 10. Pre-Commissioning Activities – Piping & Vessels  Field checks as per isometrics and P&ID’s  Verification of hydro testing  Verification of flushing , blowing & drying  Internal inspection of equipment as required 10
  • 11. Pre-Commissioning Activities – Piping & Vessels(Continued)  Verification of Internals  Re-instatement of all flanges, control value, orifices, Psv’s and steam traps.  Verification of blinds / spades installation and / or removal  Box up: Pre-commissioned and closed 11
  • 12. Pre-Commissioning Activities – Mechanical Discipline  Verification of coupling and belt alignment  Pumps / compressor checks  Bearing lubrications  Inspection / checking of filters & strainers 12
  • 13. Pre-Commissioning Activities – Electrical Discipline  MCC & UPS installation  Field electrical installation – Cable Meggering (Continuity) – Termination of wiring; end devices to JB’s & MCC – Termination & Glanding according to area classification. 13
  • 14. Pre-Commissioning Activities – Electrical Discipline(Continued)  Motor installation – Resistance maggering – Rotation confirmation – No load test run 14
  • 15. Pre-Commissioning Activities - Instrumentation  Instrument installation checks  PSV calibration  Calibration of transmitters and switches  Loop checking of device end to PLC  Function testing of PLC & ESD systems 15
  • 16. Pre-Commissioning Check Sheets  Vessel & Piping Check Sheets  Mechanical Check Sheets  Electrical Check Sheets  Instrumentation Check Sheets 16  Operation / Process Check Sheets
  • 17. Punch Listing  Punch Lists are created and sorted as per disciplines – Piping and Vessels – Mechanical – Electrical – Instrumentation – Operations  Punch Lists are categorized on a priority basis – Category “A”; MUST be completed prior to Commissioning – Category “B”; MUST be completed prior to Start-up – Category “C”; Signifies end of job  Construction Contractor MUST have a coordinated management plan of Punch Listing including categorizing of punch list items 17
  • 18. Completion Activities  Flushing Blowing Certificates  Box Up Certificate  Mechanical Completion Certificate for each Utility and Process Unit  Handover Certificate 18
  • 19. COMMISSIONING  Definition  Utility Description  Commissioning Activities  Check Sheets  Commissioning / Start Up Procedure 19
  • 20. Systems Description Commissioning of The Following Systems  Air Compression System  MCC & Plant Lighting System  UPS, PLC & Plant ESD System  Fire Water System  Fire & Gas Detection System 20
  • 21. Systems Description  Instrument Air Package  Inert Gas Package  Fuel Gas System  Closed Drain & Waste Water Systems  Condensate Transfer System  Process Units; Reactor 21
  • 22. Commissioning Check Sheets  Commissioning check sheets are given in the Commissioning Protocol. 22
  • 23. START-UP OF PROCESS UNITS  Utilities in Service  Introduction of Raw material (Vacuum Residue Feed)  Introduction of Process Air & Steam  Production of required grades of products  Maintaining required proportion of off gases as per specs  Achievement of required steam temperature  Obtaining steam temperature compatible to system steam temperature. 23
  • 24. Issues for Discussion.  Less re-work SS304, 304L  Carbon filter back flow  Go for the standard packages  15 KM pipeline 24