Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Project Challenge: A Guide to Conducting Integrated Baseline Reviews
1. A Guide to
Conducting Integrated
Baseline Reviews
Project Challenge Expo 2016
Breda Ryan
Ewan Glen
2. Introduction to the APM
Planning, Monitoring and Control SIG
• The Planning, Monitoring and Control SIG was formed in 2012
by combining the Planning and Earned Value SIGs. We are
bound by a common vision to identify best practice and to
share it with the membership of APM, and beyond.
• pmcsig@apm.org.uk
• Stand 140
3. Introduction to the IBR Guide
• Launched on the 16th
June 2016.
• The guidance in this document supports both the client and
supplier teams with all stages of the process from planning it,
delivering it, and then closing out the actions.
• We are fortunate to be joined by two of the guide’s authors:
• Ewan Glen of BMT Hi-Q Sigma; and
• Breda Ryan of Jacobs.
• pmcsig@apm.org.uk
4. Agenda
Introduction
Origins of the Guide
Who may benefit from an IBR?
Who should use an IBR?
The purpose of an IBR
The benefits of an IBR
IBR Vs Audit
The IBR Process
Using supporting information
Application lessons
Questions
Close
5. Origins of the Guide
Defence focussed guide
-Developed by Defence Earned
Value Management Interest
Group (DEVMIG),
•comprising MoD and key
industry organisations
Task to update and refresh
guide taken on by PMC SIG
•Aim to make the guidance
applicable to all sectors
Guide available via
APM, free to members
6. Integrated Baseline Review – Who?
Who may benefit from an IBR?
ProjectDuration
Project Cost
High
complexity
& risk
Low
complexity
& risk
Low
complexity
& risk
High
complexity
& risk
Low
complexity
& risk
High
complexity
& risk
Low
complexity
& risk
Historically seen as
applicable to
projects of greater
complexity, risk, cost
and duration
BUT
The intent of the
review is applicable
to all projects
(Including where
EVM is not being
applied)
7. Integrated Baseline Review – Who?
Applicability across Projects, Programmes and the
Portfolio
The portfolio benefits
from the improvements
delivered by the process
The portfolio benefits
from the improvements
delivered by the process
Projects
Programmes
Can be broadened to
projects making up the
programme (with review
of programme layer)
Can be broadened to
projects making up the
programme (with review
of programme layer)
IBRs have typically
focussed on projects
IBRs have typically
focussed on projects
Portfolio
8. The Purpose of an IBR
An IBR aims to find out if a project’s Performance
Measurement Baseline can be delivered, given the
project constraints
It checks if the project team understand the risks
inherent in the baseline and the control processes
to be used to deliver the scope
An IBR gives the PMO a standard approach to
identifying baseline risks to successful delivery
9. IBR Vs Audit
An IBR is not an audit
An audit looks for compliance to set standards
and procedures
An IBR checks for 3 key things
– That the baseline is robust
– That the whole process works
– That you are in control of your project
10. Who should use IBRs & why?
Applies to clients and contractors in any
sector on any size project or programme
Clients – check that their projects with
multiple supplier inputs and interfaces still
allow for full scope delivery
Contractors/Suppliers - check if the contract
baseline is robust, scheduled, resourced
and costed appropriately to make the
expected profit
12. When to conduct an IBR
IBRs are usually initiated by the client post contract
award or as a result of a significant change
Suppliers are generally obligated to conduct an IBR and
this is typically within 3 months post contract award
Suppliers may also conduct their own IBRs to verify their
own delivery capability and risk exposure
Some clients run annual or bi-annual IBRs to to
check the robustness of, and risk exposure to,
their overall capital investment programme
baseline
17. Application Lessons
Get buy-in and commitment from
key stakeholders in the client and
supplier organisation
Understand team behaviours and
dynamics. Expect scale from resistance to
cooperation
Document the follow-up actions and check
they are completed
Be prepared for the impact of the sponsor’s
decisions. Projects may be stopped or team
re-staffed
18. Application Lessons
Good planning supports a good
review
Before the review, train the team
conducting the review and consider
training the team under review
Don’t be afraid to arrange discussions with
senior managers involved in the project to
understand their views
A well constructed in-brief allows the review
team to decide what it should and should
not focus upon