SlideShare a Scribd company logo
1 of 20
RAMZI LABBAN

DR. SIMAAN M. ABOURIZK

MANAGER, COMPUTER MODELING
& SIMULATION
CCC
PHD CANDIDATE
UNIVERSITY OF ALBERTA

PROFESSOR
UNIVERSITY OF ALBERTA

MR. ZUHAIR HADDAD

DR. AMR EL-SERSY

VICE PRESIDENT, CORPORATE
AFFAIRS & CIO
CCC

GROUP MANAGER, LEARNING &
INNOVATION
CCC
Agenda
• Introduction
• Pipe Spool Fabrication Model
–
–
–
–
–

•
•
•
•
•

Background
Simulator Design and Development
Product Definitions
Process Definitions (Activity Flow, Resources)
Model Structure (Parameters Interface, DES Model, Outputs)

Potential Benefits
Future Work
Conclusions
Acknowledgements
Q&A
Introduction
• Pipe spool fabrication
– A major component of construction operations on
large industrial projects
– Relatively short term, complex construction process
– Riddled with uncertainty due to the intrinsic unique
nature of its outputs and the numerous factors
affecting its activities

• Important for all stakeholders to have a good grasp
of the performance of pipe fabrication shops and
their ability to meet the site pipe installation
schedules
Pipe Spool Fabrication Model
Background
• Activities in pipe fabrication shops include:
– Cut, bevel, fit-up, welding, QC inspection, post
weld heat treatment, non-destructive testing,
painting
• These activities are repeatedly performed by a
specific type of crew on pipe spools for a certain
duration
Pipe Spool Fabrication Model
Background
• Forecasting pipe spool fabrication activity
completion and optimizing resource allocation and
utilization are complicated by two main factors:
– very large number of spools
– diverse characteristics and resource requirements
for each spool
• A complex task well suited to computer modeling
and simulation
Pipe Spool Fabrication Model
Simulator Design and Development
• Abstraction of the real world situation into a
simulation model representing the operations of a
pipe spool fabrication shop:
– Product definitions
• Spool characteristics
• Joint characteristics

– Process definitions
• Activities and their flow
• Resources
Pipe Spool Fabrication Model
Product Definitions
• Spool and joint characteristics required for simulating
the fabrication activities were specified
Spool ID
Stauts
A140-A141-B92SL-15139D-S101
3
Weld #
2
4
5
A140-A141-B92SL-15139D-S102
3
A140-A141-B92SL-15139D-S103
3

Material
CS
Weld Type
SB
SB
SB
CS
CS

Paint Code
Surface Area Priority
6D
0.03
180
Weld Inch-Dia PWHT Req'd NDT Req'd
0.75
0
0
0.75
0
0
0.75
0
0
6D
0.01
180
6D
0.15
180

Two-level hierarchy for spools and their relevant joints
Pipe Spool Fabrication Model
Process Definitions
• Major pipe spool fabrication activities to be simulated and
their flow were identified:
 Cut
 Bevel
 Fit-up (& tack welding)
 Welding (auto and manual)
 QC inspection
 Post weld heat treatment (PWHT)
 Non-destructive testing (NDT)
 Painting
• For each activity, the type of resource (crew) required and its
relevant productivity were also identified
Pipe Spool Fabrication Model
Activity Flow
Pipe Spool Fabrication Model
Resources
• Each pipe fabrication activity is associated with a
resource type
• Each resource type is typically a crew composed of a
group of workers required to perform a specific task
Worker Worker Worker Worker Worker Worker Worker Worker Worker
Crew Type
Type 1 Type 2 Type 3 Type 4 Type 5 Type 6 Type 7 Type 8 Type 9
Cut
1
2
1
2
Bevel
1
Fit-up
2
2
1
4
Weld Size 1
1
1
Weld Size 2
2
2
PWHT
1
2
Painting
1
3
4

Typical crew compositions on a large industrial construction project
Pipe Spool Fabrication Model
Resources
• Workers available over the duration of the project
make up the required crews (resources) for the
fabrication activities
Worker
Type
1
2
3
5
6
7

1
21
85
80
37
90
92

2
23
90
82
38
95
99

3
25
95
85
40
100
112

Month
4
5
25
25
95 100
86 104
41
42
100 110
129 135

6
25
100
104
42
110
135

7
25
100
104
42
110
135

Typical worker availability over time on an industrial project

8
25
100
104
42
110
135
Pipe Spool Fabrication Model
Model Structure
Spool
Engineering
Data

Pipe
Fabrication
Schedule

Spool
Priority Lists

Crew
(Resource)
Database

Parameters Input Interface

Spool
Progress
Data
To-Date

DES Model

Simulation Outputs
Pipe Spool Fabrication Model
Parameters Interface
Pipe Spool Fabrication Model
DES Model

Pipe Fabrication Activity Flow

DES Model
Pipe Spool Fabrication Model
Outputs
• The simulator produces a comprehensive set of data
comprised of the artificial history of the simulated pipe
fabrication operations
• The result set contains a record of the activities performed on
the corresponding entities (spools or welds) utilizing the
required resources
Scenario #
1304152
1304152
1304152
1304152

Spool ID
Weld No
A140-A141-B92SL-15139D-S101
2
A140-A141-B92SL-15139D-S101
4
A140-A141-B92SL-15139D-S101
5
A140-A141-B92SL-15139D-S101

Activity Start Date and Time
Welding 03/04/2013 11:01
Welding 03/04/2013 11:01
Welding 03/03/2013 15:01
Painting
3/14/13 8:00

End Date and Time Resources
03/04/2013 11:23
1
03/04/2013 11:23
1
03/03/2013 15:23
1
3/16/13 10:00
1

• For each entity/activity/resource occurrence, the data
contains a start date and time, an end date and time, and a
number of resources utilized for the duration
Potential Benefits
• The model provides stakeholders and end users with a
tool to proactively perform low level resource planning
on pipe fabrication activities on large industrial
projects

• The model can be run during the different phases of a
project:
– Ahead of the project in predictive mode
– During execution to aid in optimization and forecasting
– Retrospectively for change impact assessment and/or
lessons-learned analysis
Future Work
• The pipe spool fabrication model described in this
paper is a first step at aiding in the management
of pipe spool fabrication operations
• Further development and enhancements to this
model include:
– A material constraint module
– A pipe installation simulation model covering pipe
spool construction activities until spools are installed
in place on site and given final release
Conclusions
• This paper presented a special purpose discrete event simulation
model for managing pipe spool fabrication operations in pipe
fabrication shops on industrial projects
• The simulation model helps stakeholders manage their activities
and perform low level resource planning for all shop pipe spool
fabrication activities
• The main benefits of the model are
– predictive analysis of fabrication resource requirements
– managing operations and forecasting resource and time
requirements during project execution
– Retrospective analysis
Acknowledgements
• The pipe fabrication model described in this paper was
developed and implemented at Consolidated Contractors
Group (CCC) to aid in estimating, planning and managing pipe
fabrication operations on large industrial construction
projects
Thank you!
Any questions?

More Related Content

What's hot

Flange management presentation
Flange management presentationFlange management presentation
Flange management presentationMohamed Gaafar
 
Regulation for cgd_technical_standard_071.8
Regulation for cgd_technical_standard_071.8Regulation for cgd_technical_standard_071.8
Regulation for cgd_technical_standard_071.8Nikhil Nangia
 
Piping handbook
Piping handbookPiping handbook
Piping handbookpdmsguy
 
pipefitting pressure-test
pipefitting pressure-testpipefitting pressure-test
pipefitting pressure-testIzzuwan Yusoff
 
Presentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ixPresentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ixmayank0738
 
Piping sample report
Piping sample reportPiping sample report
Piping sample reportram111eg
 
Piping training-course
Piping training-coursePiping training-course
Piping training-coursepdmsguy
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works Shaik Mohsin
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingAbhijeet Nagle
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Philippe Porta
 
B31.3 process piping course 02 metallic pipe & fitting selection
B31.3 process piping course   02 metallic pipe & fitting selectionB31.3 process piping course   02 metallic pipe & fitting selection
B31.3 process piping course 02 metallic pipe & fitting selectionAhmedhelal_Metito Helal
 
Codes and standards by madhur mahajan
Codes and standards by madhur mahajanCodes and standards by madhur mahajan
Codes and standards by madhur mahajanMadhur Mahajan
 
Saudi arabian-engineering-standards-saes-j-502
Saudi arabian-engineering-standards-saes-j-502Saudi arabian-engineering-standards-saes-j-502
Saudi arabian-engineering-standards-saes-j-502nadim khan
 
Wis5 welding defects 02
Wis5 welding defects 02Wis5 welding defects 02
Wis5 welding defects 02Thang Do Minh
 

What's hot (20)

Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
 
Regulation for cgd_technical_standard_071.8
Regulation for cgd_technical_standard_071.8Regulation for cgd_technical_standard_071.8
Regulation for cgd_technical_standard_071.8
 
Piping handbook
Piping handbookPiping handbook
Piping handbook
 
pipefitting pressure-test
pipefitting pressure-testpipefitting pressure-test
pipefitting pressure-test
 
Presentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ixPresentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ix
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 
Piping training-course
Piping training-coursePiping training-course
Piping training-course
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
 
Weekly excavation checklist
Weekly excavation checklistWeekly excavation checklist
Weekly excavation checklist
 
Method of statement piping works
Method of statement piping works Method of statement piping works
Method of statement piping works
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / Hydrotesting
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
WPS & WPQ
WPS & WPQWPS & WPQ
WPS & WPQ
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
 
B31.3 process piping course 02 metallic pipe & fitting selection
B31.3 process piping course   02 metallic pipe & fitting selectionB31.3 process piping course   02 metallic pipe & fitting selection
B31.3 process piping course 02 metallic pipe & fitting selection
 
Welding book
Welding bookWelding book
Welding book
 
Codes and standards by madhur mahajan
Codes and standards by madhur mahajanCodes and standards by madhur mahajan
Codes and standards by madhur mahajan
 
Saudi arabian-engineering-standards-saes-j-502
Saudi arabian-engineering-standards-saes-j-502Saudi arabian-engineering-standards-saes-j-502
Saudi arabian-engineering-standards-saes-j-502
 
Wis5 welding defects 02
Wis5 welding defects 02Wis5 welding defects 02
Wis5 welding defects 02
 

Viewers also liked

INSTRUCTION PIPELINING
INSTRUCTION PIPELININGINSTRUCTION PIPELINING
INSTRUCTION PIPELININGrubysistec
 
Pipe stress engineering
Pipe stress engineeringPipe stress engineering
Pipe stress engineeringRicardo Soares
 
U.S. Concrete Pipe Market. Analysis And Forecast to 2020
U.S. Concrete Pipe Market. Analysis And Forecast to 2020U.S. Concrete Pipe Market. Analysis And Forecast to 2020
U.S. Concrete Pipe Market. Analysis And Forecast to 2020IndexBox Marketing
 
Plumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto SoberanoPlumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto SoberanoEsOj Soberano
 
Engineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) WebinarEngineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) WebinarPiping Technology & Products, Inc.
 
The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...
The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...
The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...TWCA
 
Project-Based Learning
Project-Based LearningProject-Based Learning
Project-Based LearningJose Gigante
 
pipe line calculation
pipe line calculationpipe line calculation
pipe line calculationjatinar123
 

Viewers also liked (13)

Pipeline hydraulic calculation
Pipeline hydraulic calculationPipeline hydraulic calculation
Pipeline hydraulic calculation
 
Design, Application & Installation of Pipe Clamps Webinar
Design, Application & Installation of Pipe Clamps WebinarDesign, Application & Installation of Pipe Clamps Webinar
Design, Application & Installation of Pipe Clamps Webinar
 
INSTRUCTION PIPELINING
INSTRUCTION PIPELININGINSTRUCTION PIPELINING
INSTRUCTION PIPELINING
 
Pipe stress engineering
Pipe stress engineeringPipe stress engineering
Pipe stress engineering
 
U.S. Concrete Pipe Market. Analysis And Forecast to 2020
U.S. Concrete Pipe Market. Analysis And Forecast to 2020U.S. Concrete Pipe Market. Analysis And Forecast to 2020
U.S. Concrete Pipe Market. Analysis And Forecast to 2020
 
Plumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto SoberanoPlumbing presentation by Jose Anacleto Soberano
Plumbing presentation by Jose Anacleto Soberano
 
Engineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) WebinarEngineered Spring Supports (Practical, Hands-on Approach) Webinar
Engineered Spring Supports (Practical, Hands-on Approach) Webinar
 
The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...
The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...
The Dakota Access Pipeline: Lessons Learned from the Standing Rock Protests f...
 
Types of pipes
Types of pipesTypes of pipes
Types of pipes
 
Project-Based Learning
Project-Based LearningProject-Based Learning
Project-Based Learning
 
plumbing
plumbingplumbing
plumbing
 
Underwater Welding
Underwater WeldingUnderwater Welding
Underwater Welding
 
pipe line calculation
pipe line calculationpipe line calculation
pipe line calculation
 

Similar to I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model

Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanCCT International
 
Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)Antonio Delmo
 
Summary of previous projects
Summary of previous projectsSummary of previous projects
Summary of previous projectsHarun Hodžić
 
STAGE 1 PRESENTATION.pptx
STAGE 1 PRESENTATION.pptxSTAGE 1 PRESENTATION.pptx
STAGE 1 PRESENTATION.pptxVishalKotia1
 
Introduction to CAD/CAM
Introduction to CAD/CAMIntroduction to CAD/CAM
Introduction to CAD/CAMNafis Ahmad
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Chris Baichoo
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015Mach Cao Xuan
 
Employee Management Process (Engineering Model)
Employee Management Process (Engineering Model)Employee Management Process (Engineering Model)
Employee Management Process (Engineering Model)Dhyey Patel
 
Design Engineer (Mechanical) Valve Design, Manufacturing Industry
Design Engineer (Mechanical) Valve Design, Manufacturing IndustryDesign Engineer (Mechanical) Valve Design, Manufacturing Industry
Design Engineer (Mechanical) Valve Design, Manufacturing IndustryAmarjit Rajeshirke
 
Software engineering jwfiles 3
Software engineering jwfiles 3Software engineering jwfiles 3
Software engineering jwfiles 3Azhar Shaik
 
RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016Randall Tointon
 
Resume-travisllucas ME ATD
Resume-travisllucas ME ATDResume-travisllucas ME ATD
Resume-travisllucas ME ATDTravis Lucas
 
Mayank Kumar (Updated CV)
Mayank Kumar (Updated CV)Mayank Kumar (Updated CV)
Mayank Kumar (Updated CV)Mayank Sharma
 
Software Development Life Cycle
Software Development Life CycleSoftware Development Life Cycle
Software Development Life CycleAashima Wadhwa
 

Similar to I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model (20)

Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi LabbanFiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
Fiatech 2014 - Computer Simulation of Pipe Fabrication, Ramzi Labban
 
Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)Antonio R.Delmo updated resume Sept2016docx (1)
Antonio R.Delmo updated resume Sept2016docx (1)
 
Summary of previous projects
Summary of previous projectsSummary of previous projects
Summary of previous projects
 
Resume_Hariprasad
Resume_HariprasadResume_Hariprasad
Resume_Hariprasad
 
STAGE 1 PRESENTATION.pptx
STAGE 1 PRESENTATION.pptxSTAGE 1 PRESENTATION.pptx
STAGE 1 PRESENTATION.pptx
 
Introduction to CAD/CAM
Introduction to CAD/CAMIntroduction to CAD/CAM
Introduction to CAD/CAM
 
Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006Using lean to reduce prototype lead time 2006
Using lean to reduce prototype lead time 2006
 
Company Presentation 2015
Company Presentation 2015Company Presentation 2015
Company Presentation 2015
 
Employee Management Process (Engineering Model)
Employee Management Process (Engineering Model)Employee Management Process (Engineering Model)
Employee Management Process (Engineering Model)
 
Resume_AG
Resume_AGResume_AG
Resume_AG
 
Project Management
Project ManagementProject Management
Project Management
 
Design Engineer (Mechanical) Valve Design, Manufacturing Industry
Design Engineer (Mechanical) Valve Design, Manufacturing IndustryDesign Engineer (Mechanical) Valve Design, Manufacturing Industry
Design Engineer (Mechanical) Valve Design, Manufacturing Industry
 
CV- Piping Engineer (EPC)
CV- Piping  Engineer (EPC)CV- Piping  Engineer (EPC)
CV- Piping Engineer (EPC)
 
Software engineering jwfiles 3
Software engineering jwfiles 3Software engineering jwfiles 3
Software engineering jwfiles 3
 
RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016RESUME RANDALL V TOINTON 2016
RESUME RANDALL V TOINTON 2016
 
Resume-travisllucas ME ATD
Resume-travisllucas ME ATDResume-travisllucas ME ATD
Resume-travisllucas ME ATD
 
Resume
ResumeResume
Resume
 
Mayank Kumar (Updated CV)
Mayank Kumar (Updated CV)Mayank Kumar (Updated CV)
Mayank Kumar (Updated CV)
 
Resume-steer
Resume-steerResume-steer
Resume-steer
 
Software Development Life Cycle
Software Development Life CycleSoftware Development Life Cycle
Software Development Life Cycle
 

More from CCT International

BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? CCT International
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryCCT International
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction IndustryCCT International
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsCCT International
 
The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)CCT International
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastCCT International
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIMCCT International
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringCCT International
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?CCT International
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...CCT International
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeCCT International
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCCCT International
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...CCT International
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...CCT International
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementCCT International
 

More from CCT International (20)

BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together?
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 
BIM In Practice Seminar
BIM In Practice Seminar BIM In Practice Seminar
BIM In Practice Seminar
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
 
Adding Intelligence to AWP
Adding Intelligence to AWPAdding Intelligence to AWP
Adding Intelligence to AWP
 
BIM Based Project Controls
BIM Based Project ControlsBIM Based Project Controls
BIM Based Project Controls
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
 
The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIM
 
Contractors: Get BIM Ready!
Contractors: Get BIM Ready!Contractors: Get BIM Ready!
Contractors: Get BIM Ready!
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCC
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset Management
 

Recently uploaded

A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsNanddeep Nachan
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...apidays
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbuapidays
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...apidays
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusZilliz
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNavi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelDeepika Singh
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024The Digital Insurer
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 

Recently uploaded (20)

A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu SubbuApidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
Apidays Singapore 2024 - Modernizing Securities Finance by Madhu Subbu
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
Apidays Singapore 2024 - Scalable LLM APIs for AI and Generative AI Applicati...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNavi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Navi Mumbai Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 

I3M 2013 – EMSS Conference - Pipe Spool Fabrication Simulation Model

  • 1. RAMZI LABBAN DR. SIMAAN M. ABOURIZK MANAGER, COMPUTER MODELING & SIMULATION CCC PHD CANDIDATE UNIVERSITY OF ALBERTA PROFESSOR UNIVERSITY OF ALBERTA MR. ZUHAIR HADDAD DR. AMR EL-SERSY VICE PRESIDENT, CORPORATE AFFAIRS & CIO CCC GROUP MANAGER, LEARNING & INNOVATION CCC
  • 2. Agenda • Introduction • Pipe Spool Fabrication Model – – – – – • • • • • Background Simulator Design and Development Product Definitions Process Definitions (Activity Flow, Resources) Model Structure (Parameters Interface, DES Model, Outputs) Potential Benefits Future Work Conclusions Acknowledgements Q&A
  • 3. Introduction • Pipe spool fabrication – A major component of construction operations on large industrial projects – Relatively short term, complex construction process – Riddled with uncertainty due to the intrinsic unique nature of its outputs and the numerous factors affecting its activities • Important for all stakeholders to have a good grasp of the performance of pipe fabrication shops and their ability to meet the site pipe installation schedules
  • 4. Pipe Spool Fabrication Model Background • Activities in pipe fabrication shops include: – Cut, bevel, fit-up, welding, QC inspection, post weld heat treatment, non-destructive testing, painting • These activities are repeatedly performed by a specific type of crew on pipe spools for a certain duration
  • 5. Pipe Spool Fabrication Model Background • Forecasting pipe spool fabrication activity completion and optimizing resource allocation and utilization are complicated by two main factors: – very large number of spools – diverse characteristics and resource requirements for each spool • A complex task well suited to computer modeling and simulation
  • 6. Pipe Spool Fabrication Model Simulator Design and Development • Abstraction of the real world situation into a simulation model representing the operations of a pipe spool fabrication shop: – Product definitions • Spool characteristics • Joint characteristics – Process definitions • Activities and their flow • Resources
  • 7. Pipe Spool Fabrication Model Product Definitions • Spool and joint characteristics required for simulating the fabrication activities were specified Spool ID Stauts A140-A141-B92SL-15139D-S101 3 Weld # 2 4 5 A140-A141-B92SL-15139D-S102 3 A140-A141-B92SL-15139D-S103 3 Material CS Weld Type SB SB SB CS CS Paint Code Surface Area Priority 6D 0.03 180 Weld Inch-Dia PWHT Req'd NDT Req'd 0.75 0 0 0.75 0 0 0.75 0 0 6D 0.01 180 6D 0.15 180 Two-level hierarchy for spools and their relevant joints
  • 8. Pipe Spool Fabrication Model Process Definitions • Major pipe spool fabrication activities to be simulated and their flow were identified:  Cut  Bevel  Fit-up (& tack welding)  Welding (auto and manual)  QC inspection  Post weld heat treatment (PWHT)  Non-destructive testing (NDT)  Painting • For each activity, the type of resource (crew) required and its relevant productivity were also identified
  • 9. Pipe Spool Fabrication Model Activity Flow
  • 10. Pipe Spool Fabrication Model Resources • Each pipe fabrication activity is associated with a resource type • Each resource type is typically a crew composed of a group of workers required to perform a specific task Worker Worker Worker Worker Worker Worker Worker Worker Worker Crew Type Type 1 Type 2 Type 3 Type 4 Type 5 Type 6 Type 7 Type 8 Type 9 Cut 1 2 1 2 Bevel 1 Fit-up 2 2 1 4 Weld Size 1 1 1 Weld Size 2 2 2 PWHT 1 2 Painting 1 3 4 Typical crew compositions on a large industrial construction project
  • 11. Pipe Spool Fabrication Model Resources • Workers available over the duration of the project make up the required crews (resources) for the fabrication activities Worker Type 1 2 3 5 6 7 1 21 85 80 37 90 92 2 23 90 82 38 95 99 3 25 95 85 40 100 112 Month 4 5 25 25 95 100 86 104 41 42 100 110 129 135 6 25 100 104 42 110 135 7 25 100 104 42 110 135 Typical worker availability over time on an industrial project 8 25 100 104 42 110 135
  • 12. Pipe Spool Fabrication Model Model Structure Spool Engineering Data Pipe Fabrication Schedule Spool Priority Lists Crew (Resource) Database Parameters Input Interface Spool Progress Data To-Date DES Model Simulation Outputs
  • 13. Pipe Spool Fabrication Model Parameters Interface
  • 14. Pipe Spool Fabrication Model DES Model Pipe Fabrication Activity Flow DES Model
  • 15. Pipe Spool Fabrication Model Outputs • The simulator produces a comprehensive set of data comprised of the artificial history of the simulated pipe fabrication operations • The result set contains a record of the activities performed on the corresponding entities (spools or welds) utilizing the required resources Scenario # 1304152 1304152 1304152 1304152 Spool ID Weld No A140-A141-B92SL-15139D-S101 2 A140-A141-B92SL-15139D-S101 4 A140-A141-B92SL-15139D-S101 5 A140-A141-B92SL-15139D-S101 Activity Start Date and Time Welding 03/04/2013 11:01 Welding 03/04/2013 11:01 Welding 03/03/2013 15:01 Painting 3/14/13 8:00 End Date and Time Resources 03/04/2013 11:23 1 03/04/2013 11:23 1 03/03/2013 15:23 1 3/16/13 10:00 1 • For each entity/activity/resource occurrence, the data contains a start date and time, an end date and time, and a number of resources utilized for the duration
  • 16. Potential Benefits • The model provides stakeholders and end users with a tool to proactively perform low level resource planning on pipe fabrication activities on large industrial projects • The model can be run during the different phases of a project: – Ahead of the project in predictive mode – During execution to aid in optimization and forecasting – Retrospectively for change impact assessment and/or lessons-learned analysis
  • 17. Future Work • The pipe spool fabrication model described in this paper is a first step at aiding in the management of pipe spool fabrication operations • Further development and enhancements to this model include: – A material constraint module – A pipe installation simulation model covering pipe spool construction activities until spools are installed in place on site and given final release
  • 18. Conclusions • This paper presented a special purpose discrete event simulation model for managing pipe spool fabrication operations in pipe fabrication shops on industrial projects • The simulation model helps stakeholders manage their activities and perform low level resource planning for all shop pipe spool fabrication activities • The main benefits of the model are – predictive analysis of fabrication resource requirements – managing operations and forecasting resource and time requirements during project execution – Retrospective analysis
  • 19. Acknowledgements • The pipe fabrication model described in this paper was developed and implemented at Consolidated Contractors Group (CCC) to aid in estimating, planning and managing pipe fabrication operations on large industrial construction projects

Editor's Notes

  1. The ability of computer based modeling and simulation to model resource and activity interactions, queuing, and uncertainties renders it a good fit for modeling the pipe spool fabrication process.
  2. extended visits to multiple mega industrial projects were conducted to observe and document pipe spool fabrication activitiesBenchmarking for every activity was conducted via numerous observations of the activity being performed on different spools of varying characteristics. Both crew composition information and productivity figures were collected. In this paper we will not deal with the analysis of the observed productivity data; this matter will be dealt with at a different time. Instead, for this paper, we will assume the resulting productivity norms deduced from the observations as our activity productivity norms for the tasks. The simulator was developed as a discrete event simulation model with spools as the main entity. For the welding tasks, welds are the entities - where spools are split into their constituent welds - in order to process welds individually and collect their artificial history.
  3. Spool data required: spool ID, current spool status, line class, material type, paint code, surface area, spool specific priority information Joint data required: weld type, inch-dia, post weld heat treatment (PWHT) requirement and non-destructive testing (NDT) requirements
  4. For the purpose of this paper, we will only cover the main activities of the pipe spool fabrication process, and not include logistical activities such as crane and trailer operations.