SlideShare a Scribd company logo
1 of 91
Download to read offline
Building Science Consultations

APPLIED ENERGY SOLUTIONS



 COMMISSIONING PROCESS
     ASHRAE Guideline 0-2005
     ASHRAE Guideline 1.1-2007
     NIBS Guideline 3-2006




by David J. MacKay LEED AP, CPMP
Applied Energy Solutions
•   Commissioning Framework
     – ASHRAE 0-2005
     – ASHRAE 1.1-2007
     – ASHRAE/NIBS Guideline 3

•   Commissioning Defined

•   Commissioning Process
     –   Pre-Design Phase
     –   Design Phase
     –   Construction Phase
     –   Occupancy & Operations

•   Ongoing Commissioning

•   Commissioning Keys to Success
COMMISSIONING FRAMEWORK
Total Building Commissioning Process

                           ASHRAE Guideline 0-2005: The
                           Commissioning Process (Used
                            as a foundation for ASHRAE
                           Guideline 1, NIBS Guideline 3,
                              and other Total Building
                              Commissioning Process
                                technical guidelines




                                                            Guidelines 2-200X & 4-200X
ASHRAE Guideline 1-2007:      NIBS Guideline 3-2006:        through 14-200X: Technical
   HVAC&R Technical         Exterior Enclosure Technical     commissioning guidelines
  Requirements for the         Requirements for the            dealing with structure,
 Commissioning Process        Commissioning Process         electrical, lighting, interiors,
                                                                   plumbing, etc.
• ASHRAE Guideline 0-2005
   – Defines the process
   – Generic: any system or discipline

• ASHRAE Guideline 1.1-2007
   – How to apply the process to HVAC&R
   – Several annexes/examples

• ASHRAE/NIBS Guideline 3
   – How to apply the process to enclosure elements
   – Walls, floors, roofs, fenestration
   – Several annexes/examples
• Total building Commissioning (Cx) guidelines are in the works:
   – Guideline X Plumbing (ASPE)
   – Guideline Y Lighting (IESNA)
   – Guideline 1.2 Existing HVAC&R (ASHRAE)
   – Guideline 1.3 Operator Training (ASHRAE)

• This presentation will focus on ASHRAE Guideline 0-2005 and
  the overall Cx Process
COMMISSIONING DEFINED
•   An ongoing & structured quality assurance process (ideally spanning from pre-
    design into occupancy) that ensures continual:
     – Communication
     – Documentation
     – Verification

•   In simplest terms, commissioning is intended to ensure a building meets the
    owner’s requirements upon turnover

•   It is NOT:
     – An event
     – A short term task
     – Punch list clearance

•   It is a Team sport—for successful commissioning, everyone must buy in to and
    participate in the process
A quality-focused process for enhancing the delivery of
  a project. The process focuses upon verifying and
  documenting that the facility and all of its systems and
  assemblies are planned, designed, installed, tested,
  operated, and maintained to meet the Owner’s Project
  Requirements (OPR).


* ASHRAE Guideline 0-2005: 4. Definitions
• The OPR document explicitly calls out the minimum characteristics
  that will define a successful project from the owner’s perspective

• Must address quality as well as quantity

• Must include verifiable benchmarks (criteria)

• OPR is completed during pre-design

• This document becomes the basis for all commissioning verification
  efforts—and is thus critical to a successful commissioning outcome
• The Commissioning Process is a quality-oriented process for
  achieving, verifying, and documenting that the performance of
  facilities, systems, and assemblies meets defined objectives and
  criteria.

• The Commissioning Team uses methods and tools to verify that the
  project is achieving the Owner’s Project Requirements throughout
  the delivery of the project.

• The Commissioning Process assumes that owners, programmers,
  designers, contractors, commissioning team members, and
  operations and maintenance entities are fully accountable for the
  quality of their work.
COMMISSIONING PROCESS
  PRE-DESIGN PHASE
• Develop the Owner’s Project Requirements (OPR)

 • Review lessons from previous projects

 • Identify Cx scope and budget

 • Develop initial Cx Plan

 • Owner acceptance of pre-design Cx activities

* ASHRAE Guideline 0-2005: 6.1.2… Objectives
• To get the process off on the right foot

• Ensure development of a thorough OPR document
• The Commissioning Authority (CxA)

• The Cx Team

• Pre-Design Cx Documents
• The Commissioning Authority (CxA)

• The Cx Team

• Pre-Design Cx Documents
• “Authority” (or “Provider”) versus “Agent”
   – An authority acts for the owner
   – An agent can act as the owner (NOT intended)

• Professional services contract must spell out roles and responsibilities for
  this crucial party—including scope of work to be conducted (which can
  vary greatly)

• CxA may be:
   – An independent entity
   – Owner’s in-house staff

• THE CXA WILL NOT SINGLE-HANDEDLY COMMISSION A PROJECT
• Should have actual and perceived independence of action (an
  unbiased party)

• Should have a background and experience to match project
  expectations

• Will act in the best interests of the owner

• Will interact with owner’s representatives, the design team, the
  contractor and subcontractors

• Will lead the Cx Team and team meetings

• Should have outstanding people skills
• The Commissioning Authority (CxA)

• The Commissioning Team

• Pre-Design Cx Documents
• Includes many members:
  – CxA
  – Programming Consultants
  – Owner’s representatives
     • Users
     • Maintenance Staff
  – Design Team representatives
  – Contractor representatives (if possible)

• Members (numbers and bodies) will change from
  phase to phase
• The team is led by the CxA

• The team will complete a variety of tasks

• Specific pre-design roles and responsibilities will vary
  from project to project

• Responsibility for team members must be clearly
  allocated and contractually assigned
• The Commissioning Authority (CxA)

• The Commissioning Team

• Pre-Design Cx Documents
• OPR

• Cx/design service contract integration

• Cx Plan

• Issues Log

• Systems Manual
Project Inception
Building Development                                                                                       Commissioning
       Process                                             Pre-Design Phase
                                                                                                              Process

                         Form Building Development                                      Form Commissioning
                                    Team                                                  (Cx) Team-S5.2,1


                                 Project                                                Participate in Project
                                 Review                                                 Review Meeting-S5.2
                                 Meeting
                                                                           Develop          Determine
                                                                                                                  Develop Initial
                                                                           Owner’s        Commissioning
                                                                           Project                                Commissioning
                                                                                         Scope & Budget-
          Develop              Develop Overall       Develop Building                                               Plan-5.2.4
                                                                        Requirements-        S5.2.2[c]
     Design/Constructio        Building Budget          Program             S5.2.2
       n Mgmt. Plans
                                                                                                                 Owner Acceptance
                                                                                                                  of Cx Products
      Other Pre-design
          Services

    Owner Acceptance of                                                                                           To Design Phase
    Pre-Design Products


      To Design Phase
COMMISSIONING PROCESS
   DESIGN PHASE
• Update the Commissioning Plan
 • Verify the Basis of Design
 • Develop commissioning process requirements for the
   Construction Documents
 • Develop draft Construction Checklists
 • Develop draft Test Procedures
 • Define training requirements
 • Perform OPR-based design preview
 • Update OPR
* ASHRAE Guideline 0-2005: 6.1.2… Objectives
• Prepare for construction phase Cx activities

• Verify design decisions and documentation match OPR
• The Cx Team

• Design Phase Cx Documents

• Ensuring the Contractor is on Board

• Design Phase Verifications
• The Cx Team

• Design Phase Cx Documents

• Ensuring the Contractor is on Board

• Design Phase Verifications
• CxA

• Owner’s representatives
   – Project Manager
   – O&M Staff

• Design team representatives (including specialty consultants)

• Contractor representatives (if possible-input on Construction
  Checklists and testing can be exceptionally valuable)

• Major equipment/assembly manufacturer representatives
• The Cx Team

• Design Phase Cx Documents

• Ensuring the Contractor is on Board

• Design Phase Verifications
• Basis of Design (BOD)
   – This is considered a formal Cx process document that captures—in a
     usable format—key design influencing assumptions, methods, selections,
     and decisions

   – The purpose of the BOD is to give other parties easy access to the
     rationale behind design decisions

   – Construction Documents show WHAT was selected but not WHY

   – The WHY can be very valuable when considering a contractor-proposed
     substitution or making a decision on building operations

   – This document is valuable when design proposals are compared against
     OPR
• BOD document typically includes:
    – Codes, standards, guidelines used

    – Basis for system/assembly selection

    – System and assembly options considered

    – Calculation/analysis methods used

    – Key inputs to calculations/analysis
        • Data (U-factors, climate, etc.)
        • Assumptions (energy costs, maintenance capabilities, etc.)

    – Narrative descriptions of system/assembly operations

    – Narrative descriptions of system/assembly control sequences

    – Equipment/products used as a basis of design
• Cx Plan

   – This is a continually developing roadmap for upcoming activities and
     record of completed activities

   – During the design phase, the plan will be updated to provide details
     regarding construction phase commissioning activities-an outline of
     occupancy and operations phase activities will be included

   – A detailed Training Plan will be developed as a section of the Cx Plan

   – Ensure that the Cx Plan adequately addresses Cx process activities,
     responsibilities, and schedule
• Construction Checklists

   – These are pre-prepared forms used to structure and facilitate
     verifications conducted as part of the Cx process

   – Ideally, they would be part of the Construction Documents (or
     provided as “for information” documents)

   – Typically will be completed in stages as construction progresses

   – Properly used they can help in catching deviations before they become
     problems

   – When completed, they become part of the Systems Manual and can
     assist with ongoing building operations
• Test Procedures

   – Test Procedures are an extension of verification procedures beyond the
     level of complexity that can reasonably be handled by Construction
     Checklists

   – An example: a protocol to verify that upon smoke detection in an atrium,
     the HVAC, electrical and alarm systems do what they should to meet OPR

   – Another example: a protocol to verify that the HVAC system functions as it
     should to meet the OPR under a range of anticipated loading and weather
     conditions

   – Test Procedures must be scripted and ideally will allow for easy recording
     and archiving of results for inclusion in the Systems Manual
• Systems Manual

   – A critical document for the owner

   – Requires input from:
       • Design team- need for input called out during pre-design and product verified
         during design phase
       • Contractor- responsibilities must be included in the contract documents during
         design phase
       • CxA

   – This document really needs a champion (a responsible and capable
     party)

   – Without a good Systems Manual, many of the ongoing benefits of Cx
     will be lost during occupancy and operations
• Issues Log

   – The Issues Log is essentially the collective memory of the Cx
     Team regarding problems that arise throughout the Cx process

   – It should be easy to access and use

   – It should be helpful (not litigious)

   – It should show all (or most) issues resolved upon occupancy

   – Resolution may take many routes (a change in OPR, a change in
     design, change in component, and adjustment, etc.)
• Training Plan
   – Constitutes a defined section of the Cx Plan

   – Lays out training needs and expectations

   – Lists training requirements
       • Intended audience
       • Expected outcomes
       • Suggests venue/approach
       • Estimates time allocations

   – Outlines training verification

   – Must be detailed enough to permit a reasonable bidding and scheduling by contractor

   – Will likely require involvement of design team members
Document                           Responsibility
Basis of Design                    Design Team
Cx Requirements for Construction   Design Team & CxA/Cx Team
Documents
Construction Checklists            Design Team & CxA/CxTeam
Test Procedures                    CxA/Cx Team
Training Plan                      CxA/Cx Team
Systems Manual-Content and         Design team
Contract Document Requirements
Issues Log                         CxA/Cx Team
Cx Plan                            CxA
• The Cx Team

• Design Phase Cx Documents

• Ensuring the Contractor is on Board

• Design Phase Verifications
•   Communicating commissioning process requirements to the contractor
     – Specifications
         • General Conditions requirements
              – Participation in activities
              – Ramifications for non-compliance
         • Section specific requirements
              – Construction Checklists
              – Test Procedures
              – Training
     – Provide a clear picture of responsibilities
     – Allow for a reasonable bid to be prepared
     – Permit impacts on schedule to be reasonably estimated
• The Cx Team

• Design Phase Cx Documents

• Ensuring the Contractor is on Board

• Design Phase Verifications
• Intent is not to second guess (or become) the design
  team

• Intent is to verify that design will reasonably deliver the
  owner’s project requirements

• Sampling of design documents is highly recommended as
  a procedure

• The owner possesses ultimate acceptance authority
From Pre-Design
Building Development                                                Phase-S5                                        Commissioning
       Process                                                     Design Phase:
                                                                 Schematic Design
                                                                                                                       Process
                                                                        S6

                 Project Objectives Meeting                                                Participate in Project         Update Cx Team S6.2.1
                                                                                            Objectives Meeting
                                                                                                  S6.2.9.1

Identify Macro                                 Select
                         Evaluate Options                          Prepare BOD Document        Determine Systems Manual           Determine Training
System Options                                Systems
                                                                      S6.1.1& S6.2.2.1              Structure S6.2.6             Requirements S6.2.7


                     Prepare Schematic                                                              Update OPR             Update Cx Plan
                                                                     Reviews of Design
                     Design Documents                                Documents S6.2.8                 S6.2.8.1               S6.2.3.1(a)

                    Project Objectives
                         Meeting                             Final Objectives Review for
                                                                    Phase S6.2.9.2
                   Owner Acceptance of
                    Schematic Design
                        Products
                                                        Owner Acceptance of Cx Products S6.3

                        To Design
                    Development Phase                              To Design
                                                               Development Phase
From Design Phase:
Building Development                                            Schematic Design S6                                 Commissioning
       Process                                                      Design Phase:
                                                                       Design
                                                                                                                       Process
                                                                   Development S6

                 Project Objectives Meeting                                              Participate in Project
                                                                                          Objectives Meeting              Update Cx Team S6.2.1
                                                                                                S6.2.9.1
                                                Prepare
   Identify &
                   Refine Design of              Design
Evaluate Micro                                                           Design Reviews
                       Systems                Development                                          Update BOD S6.2.2.2        Update OPR S6.2.2.2
System Options                                                               S6.2.8
                                               Documents

                                                                                                        Update Training             Update Cx Plan
                                                                           Update Systems
                                                                                                         Requirements
                                                                            Manual S6.2.6                                             S6.2.3.1(b)
                                                                                                            S6.2.7


                      Project Objectives                            Participate in Project
                           Meeting                               Objectives Meeting S6.2.9.2


                 Owner Acceptance of Design
                   Development Products                     Owner Acceptance of Cx Products S6.3

                     To Design Phase:
                  Construction Documents                     To Design Phase: Construction
                             S6                                      Documents S6
From Design Phase: Design
Building Development                            Development S6                                                        Commissioning
       Process                                    Design Phase:                                                          Process
                                                  Construction
                                                   Documents
                                                                                                       Participate in Project
         Project Objectives Meeting                                                                 Objectives Meeting S6.2.9.1



                                                                            Cx Reviews of Design
                                                                                                         Update OPR S6.2.2.2         Update BOD S6.2.2.2
      Identify                 Prepare                                          Docs. S6.2.8
    Outstanding              Construction
  Enclosure Issues            Documents
                                                                          Update Cx Plan           Develop Cx Process Req. for            Construction
                                                                           S6.2.3.1(b)              Const. Documents S6.2.4              Checklists S6.2.5



                                                       Update Systems Manual S6.2.6            Review @ 20% of systems re           Develop Cx Req. for Constr.
                                                                                                      BOD S6.2.8.4                       Documents S6.4



                                                    Acceptance Requirements S6.3                   Training Requirements S6.2.7 &
                                                                                                                S6.5



               Project Objectives                  Final Objectives Meeting for
                    Meeting                               Phase S6.2.9.2


             Owner Acceptance of                  Owner Acceptance of Cx
                Construction                          Products S6.3
                 Documents


            To Construction Phase                 To Construction Phase
COMMISSIONING PROCESS
 CONSTRUCTION PHASE
• Verify that submittals meet the OPR

 • Finalize Construction Checklists and Test Procedures

 • Verify that systems and assemblies meet the OPR

 • Verify training of owner’s personnel

 • Verify the Systems Manual

 • Update the OPR and Cx Plan
* ASHRAE Guideline 0-2005: 7.1.2… Objectives
• To verify construction activities

• To prepare project (and O&M staff) for handover to
  owner
• Meetings and Communications

• Updating Cx Documents

• Submittal Reviews

• Construction Checklists and Test Procedures

• Training
• Meetings and Communications

• Updating Cx Documents

• Submittal Reviews

• Construction Checklists and Test Procedures

• Training
• The Cx team is the avenue for effective communications
   – Via regular meetings and
   – Skillful use of the Issues Log

• Cx Team Members:
   – CxA
   – Owner’s representatives
       • PM
       • O&M staff
   – Design team representatives (including specialty consultants)
   – Contractor representatives
       • Subs
       • TAB
       • Controls
   – Major equipment/assembly manufacturer representatives
• Meetings and Communications

• Updating Cx Documents

• Submittal Reviews

• Construction Checklists and Test Procedures

• Training
Document        Action                                Responsibility

BOD update      Update as required by owner change    Design team
                orders and contractor substitutions
OPR update      Update as required by owner change    Cx Team (w/owner explicit
                orders and contractor substitutions   agreement)
Construction    Finalize and implement                Used by contractor, verified by Cx
Checklists                                            Team
Test            Finalize and implement                Used by contractor, verified by Cx
Procedures                                            Team
Systems         Complete and verify                   Completed by assigned party,
Manual                                                verified by Cx Team
Training Plan   Finalize and implement                Implemented by Contractor, design
                                                      team, and CxA
Issues Log      Use                                   Used by Cx Team

Cx Plan         Update and expand                     CxA
• Meetings and Communications

• Updating Cx Documents

• Submittal Reviews

• Construction Checklists and Test Procedures

• Training
•   Principles:

     – The purpose of verifications is NOT to provide the contractor with free quality control
       services; it is to provide the owner with assurance that the OPR are being delivered

     – ASHRAE Guideline 0 strongly recommends that a sampling strategy be used for all
       verifications

     – The sampling frequency will be established by the CxA, 5%-10% is generally
       recommended
         • Sampling is a controversial issue—and each CxA will have his/her own take on how
            to approach this.
         • Spell out sampling % in RFP

     – If deviations are found during sampling, a pre-established response is implemented—
       this may involve additional sampling or rejection of the activity

     – Financial responsibility for re-verification activities must be spelled out in construction
       contracts and service contracts
•   Quandaries:

     – ASHRAE Guideline 0-2005 sets the OPR as the benchmark against which verifications are
       to be conducted

     – The contractor is not contractually bound (generally) to meet the OPR, but rather the
       Contract Documents

     – If deviations are found relative to Contract Documents, corrective action is reasonably
       easy to justify

     – If deviations are found relative to OPR, but not the Contract Documents, then things can
       get tricky

     – Contingencies for addressing the above scenario should be spelled out for all interested
       parties

     – In theory, verification of design documents should head off OPR / Construction
       Document conflicts
•   Implementations:

     – Construction Checklist elements and Test Procedures that involve
       activating a device, system, or assembly should generally be done by the
       contractor under the observation of the CxA and other interested parties
       (the owner’s operating personnel, etc.)

     – Verification of such activities would be based upon witnessing of tests and
       review of testing documentation

     – Verifications of documents (such as the Systems Manual) would normally
       be accomplished by CxA/Cx Team review

     – Verification of training might be accomplished by witnessing, testing,
       and/or interviews
• Meetings and Communications

• Updating Cx Documents

• Submittal Verification Reviews

• Construction Checklists and Test Procedures

• Training
• The CxA conducts some checking, witnesses other checking, and
  verifies that a sample of the Construction Checklists meets quality
  expectations and demonstrates quality that conforms with the OPR
  and Construction Documents

• The verification process is seeking systemic problems

• Minor deviations would be addressed via the Issues Log

• Major deviations might require concerted action from the Cx Team

• The owner retains ultimate acceptance responsibility for any
  deviations that negatively impact the OPR
Example
Construction
Checklist
• The CxA witnesses selected tests and verifies that the results of the
  Test Procedures meet quality expectations and conform with the OPR
  and Contract Documents

• The verification process is seeking systemic problems

• Minor deviations would be addressed via the Issues Log

• Major deviations might require concerted action from the Cx Team

• The owner retains ultimate acceptance responsibility for any
  deviations that negatively impact the OPR
Example
Test
Procedure




ASHRAE
Guideline
1.1-2007
Example
Test
Procedure




ASHRAE
Guideline
1.1-2007
Example
Test
Procedure




ASHRAE
Guideline
1.1-2007
• Meetings and Communications

• Updating Cx Documents

• Submittal Verification Reviews

• Construction Checklists and Test Procedures

• Training
• The CxA verifies that the results of the training activities meets quality
  expectations and conforms with the OPR and Contract Documents

• The verification process is seeking systemic problems

• Minor deviations would be addressed via the Issues Log

• Major deviations might require concerted action from the Cx Team

• The owner retains ultimate acceptance responsibility for any
  deviations that negatively impact the OPR
• The CxA verifies that the Systems Manual is complete (to the extent
  possible) and that a sample of the manual meets quality expectations
  and conforms with the OPR and Contract Documents

• The verification process is seeking systemic problems

• Minor deviations would be addressed via the Issues Log

• Major deviations might require concerted action from the Cx Team

• The owner retains ultimate acceptance responsibility for any
  deviations that negatively impact the OPR
From Design Phase:
                                 Construction Documents

Building Development                                                                   Commissioning
                                      Construction
       Process                          Phase S7                                          Process
            Pre-Bid Conference                          Participate in Pre-Bid             Update Cx Team
                                                         Conference S7.2.2                    S7.2.1.2


                    Receive                             Verify & Coordinate                Verify Systems Manual and
                   Submittals                            Submittals S7.2.7                  Const. Checklist S7.2.16


                                                       QA/QC Plan & Site Specific
                                                            Testing Plan


                                                       Pre-Installation Meeting for
                                                                Mock-Ups

          Laboratory Testing
                                                         Verify Lab Performance


           Field Mockups
                                       Verify Mockup                                               Update Issues Log
                                        Performance              Update OPR & BOD S7.2.4


           Sample Testing
                                                                     Verify Sample
Building Development                          From Construction
                                                 Phase Part 1
                                                                                                       Commissioning
       Process                                                                                            Process
                                                 Construction
                                                Phase Part 2 S7

           Pre-Construction                                                      Pre-Construction Cx
               Meetings                                                        Process Meetings S7.2.6


    Install/Construct Exterior
    Enclosure Components &            Verify Construction Checklist        Update OPR & BOD              Update Issues     Resolve
             Systems                    Completeness S7.2.15(c)         S7.2.16.1(f) & S7.2.16.1(g)     Log S7.2.16.1(i)    Issue




                                                                            Update Issues             Resolve
                                        Direct & Verify Tests S7.2.13
                                                                            Log S7.2.16(i)             Issue


                                 Update Cx Plan S7.2.5             Provide Training &
                                                                  Update Requirements
                                                                          S7.5
      Owner Accepts
  Substantial Completion             Owner Acceptance of Cx
   of Exterior Enclosure                 Products S7.3

   To Occupancy and                    To Occupancy and
  Operations Phase S8                  Operations Phase
From Construction Phase
Building Development                                                                                                Commissioning
       Process                                                                                                         Process
                                                          Occupancy and
                                                        Operations Phase S8

                      Substantial Completion
                                                                                       Participate in Substantial
                             Meeting
                                                                                       Completion Meeting S8.1

    Contractual
                            Owner Begins
Warranty/Correction                                                                     Update Owner’s Project
                            Beneficial Use
  Period Begins                                                                          Requirements S8.1.1


                                                                                    Coordinate Contractor           Performance Verification
                                                 Direct & Verify Seasonal Tests
                                                                                       Callback S8.2.2                      S8.2.3
                                                           S8.2.1.3(b)

 Ongoing Operation, Maintenance,
  and Modification of the Building                                                 Update Systems Manual
     Systems, Assemblies and                                                               S8.2.6
 Components, and their Associated
         Documentation                                                                 Resolve Issue


       Owner Final
                                               Acceptance Req. S8.35                                                   Training Req S8.5
      Acceptance of                                                                  Docum. Req. S8.4
   Constructed Building

                                                                                  Owner Acceptance of Cx
  End of Typical Building                                                               Products
  Development Contract
COMMISSIONING PROCESS
OCCUPANCY & OPERATIONS PHASE
• Complete seasonal or deferred testing

 • Minimize contractor callbacks

 • Document lessons learned

 • Assist with any warranty issues

 • Provide assistance with ongoing facility operations to meet
   the OPR

 • Close out the process via formal owner acceptance
* ASHRAE Guideline 0-2005: 8.1.3… Objectives
• Close out the (initial) commissioning process

• Prepare the owner for long-term beneficial use of
  the facility
• The Cx Team

• Updating Cx Documents

• Lessons-Learned Workshop

• Final Cx Report
• The Cx Team

• Updating Cx Documents

• Lessons-Learned Workshop

• Final Cx Report
• CxA

• Owner’s representatives
   – Project Manager
   – O&M Staff

• Design team representatives (as required)

• Contractor representatives (including subs)

• Major equipment/assembly manufacturer representatives
  (as required)
• The Cx Team

• Updating Cx Documents

• Lessons-Learned Workshop

• Final Cx Report
Document        Action                                Responsibility

BOD update      Update as required by owner change    Design team
                orders and contractor substitutions

OPR update      Update as required by owner change    Cx Team (w/owner explicit
                orders and contractor substitutions   agreement)

Systems         Verify and employ                     Completed by assigned party,
Manual                                                verified by Cx Team

Training Plan   Finalize and implement                Implemented by Contractor, design
                                                      team, and CxA

Issues Log      Close out                             Cx Team

Cx Plan         Develop and deliver                   CxA
• The Cx Team

• Updating Cx Documents

• Lessons-Learned Workshop

• Final Cx Report
• Although most involved parties are ready to move on at this stage, all can
  benefit from reflecting on the Cx process

• The owner can benefit form information gleaned by the various parties
  that relates completed product performance to the original owner’s
  project requirements

• The design team can benefit from issues that relate design process to
  implementation of design intent and criteria (objectives and benchmarks)

• The contractor can benefit from issues that relate construction and quality
  control processes to design intent and Construction Documents

• The CxA can benefit from feedback on all aspects of the process
• The Cx Team

• Updating Cx Documents

• Lessons-Learned Workshop

• Final Cx Report
• Identify any systems or assemblies that do not perform in accordance with
  the OPR and note likely ramifications of such deviations

• Evaluate operating condition of systems/assemblies upon completion of
  testing

• Summarize the contents of the Issues Log—extent of concerns, costs,
  operational impacts

• System performance benchmarks

• Lessons Learned

• Ideally, provide a sense of worth of the Cx process on the project
COMMISSIONING PROCESS
ONGOING COMMISSIONING
• Ongoing Cx extends the process beyond the termination
  of the original commissioning services agreement
  (typically about a year into building occupancy, upon
  major equipment warranty expiration)

• The intent is to continue to assist the owner in
  maximizing beneficial use of the facility for the long term

• It appears likely that ASHRAE Guideline 0 will in the
  future include more information on the ongoing Cx
  process
Ongoing Building                                                                          Commissioning
  Operations                             From End of Typical Building Development
                                                         Contract
                                                                                             Process



                                                                     Update Owner’s           Direct & Verify
                                                                   Project Requirements     Periodic Tests and
                                                                           S8.6.1           Benchmarks S8.6.1



 Ongoing Operation, Maintenance, and
 Modification of the Building Systems,
  Assemblies, Components, and their
      Associated Documentation                                                               Whole Building
                                                                    Maintain Systems          Performance
                                                                     Manual S8.6.1          Verification S8.6.2




            Continue
                                                                      Resolve Issues



                                                                        Continue
COMMISSIONING PROCESS
   KEYS TO SUCCESS
•   Good Benchmarking and archiving of documents
     –   Owner’s Project Requirements (OPR)
     –   Basis of Design (BOD)
     –   Commissioning (Cx) Plan
     –   Construction Checklists
     –   Test Protocols
     –   Training Plan
     –   Systems Manual
     –   Cx Process Reports

•   Explicit expectations and responsibilities
     – Clear RFQ/RFP for CxA
     – Professional service contracts that address commissioning
     – Construction specifications that address commissioning and provide clear statements of
       “who” and “if-then”

•   Enforcement of Cx related contract provisions
• Ongoing Communications
   – Cx Meetings
   – Cx Reports
   – Issues Log

• Well reasoned clarity of purpose

• Verification by Cx Team of all key elements against OPR

• Serious owner buy-in and support

• Owner Acceptance of all Deliverables/Products
QUESTIONS?

More Related Content

What's hot

Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In ConstructionIsidro Sid Calayag
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management pptRajeshPV12
 
Quality management for civil engineering
Quality management for civil engineeringQuality management for civil engineering
Quality management for civil engineeringJayanta Sen
 
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...AELC
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansLiving Online
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guidelineMahmoud Ezz
 
Mechanical & electrical building services engineering guidelines
Mechanical & electrical building services engineering guidelinesMechanical & electrical building services engineering guidelines
Mechanical & electrical building services engineering guidelinesAsangaHArshan
 
HVAC Air Balance 101
HVAC Air Balance 101HVAC Air Balance 101
HVAC Air Balance 101Luci Feie
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONSANJEEV Wazir
 
Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5Hari Krishna Shrestha
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONDAVIDSON ECHIDIKE
 

What's hot (20)

MEP- Building services
MEP- Building servicesMEP- Building services
MEP- Building services
 
Quality management
Quality managementQuality management
Quality management
 
Quality Management In Construction
Quality Management In ConstructionQuality Management In Construction
Quality Management In Construction
 
Plant Maintenance
Plant MaintenancePlant Maintenance
Plant Maintenance
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Quality management for civil engineering
Quality management for civil engineeringQuality management for civil engineering
Quality management for civil engineering
 
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and Technicians
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guideline
 
Mechanical & electrical building services engineering guidelines
Mechanical & electrical building services engineering guidelinesMechanical & electrical building services engineering guidelines
Mechanical & electrical building services engineering guidelines
 
HVAC Air Balance 101
HVAC Air Balance 101HVAC Air Balance 101
HVAC Air Balance 101
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Quality control IN CONSTRUCTION
Quality control IN CONSTRUCTIONQuality control IN CONSTRUCTION
Quality control IN CONSTRUCTION
 
Piping presentation (master)
Piping presentation (master)Piping presentation (master)
Piping presentation (master)
 
System Assurance & RAMS
System Assurance & RAMSSystem Assurance & RAMS
System Assurance & RAMS
 
Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5
 
107 quality control
107 quality control107 quality control
107 quality control
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
Detailed engineering-design-phase
Detailed engineering-design-phaseDetailed engineering-design-phase
Detailed engineering-design-phase
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
 

Viewers also liked

Going Native: The Anthropology of Mobile Apps
Going Native: The Anthropology of Mobile AppsGoing Native: The Anthropology of Mobile Apps
Going Native: The Anthropology of Mobile AppsJosh Clark
 
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Probir Bidhan
 
Data Modeling with Neo4j
Data Modeling with Neo4jData Modeling with Neo4j
Data Modeling with Neo4jNeo4j
 
Operative instruments in Conservative Dentistry & Endodontics
Operative instruments in Conservative Dentistry & EndodonticsOperative instruments in Conservative Dentistry & Endodontics
Operative instruments in Conservative Dentistry & EndodonticsAshok Ayer
 
Bringing Design to Life
Bringing Design to LifeBringing Design to Life
Bringing Design to LifeBill Scott
 
4. heredity and evolution
4. heredity and evolution4. heredity and evolution
4. heredity and evolutionAbhay Goyal
 
Web Trends to Watch in 2014
Web Trends to Watch in 2014Web Trends to Watch in 2014
Web Trends to Watch in 2014David King
 
Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.Emiland
 
What I Carry: 10 Tools for Success
What I Carry: 10 Tools for SuccessWhat I Carry: 10 Tools for Success
What I Carry: 10 Tools for SuccessJonathon Colman
 
BCG Matrix of Engro foods
BCG Matrix of Engro foodsBCG Matrix of Engro foods
BCG Matrix of Engro foodsMutahir Bilal
 
Doctrine 2: Enterprise Persistence Layer for PHP
Doctrine 2: Enterprise Persistence Layer for PHPDoctrine 2: Enterprise Persistence Layer for PHP
Doctrine 2: Enterprise Persistence Layer for PHPJonathan Wage
 
Asean quiz championship_2012
Asean quiz championship_2012Asean quiz championship_2012
Asean quiz championship_2012Movin Miranda
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShareSlideShare
 
Deep Learning through Examples
Deep Learning through ExamplesDeep Learning through Examples
Deep Learning through ExamplesSri Ambati
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...SlideShare
 
Classroom Management Techniques
Classroom Management TechniquesClassroom Management Techniques
Classroom Management TechniquesBaita Sapad
 
GMAT Math Flashcards
GMAT Math FlashcardsGMAT Math Flashcards
GMAT Math FlashcardsGMAT Prep Now
 

Viewers also liked (20)

Antidepressants
Antidepressants Antidepressants
Antidepressants
 
Going Native: The Anthropology of Mobile Apps
Going Native: The Anthropology of Mobile AppsGoing Native: The Anthropology of Mobile Apps
Going Native: The Anthropology of Mobile Apps
 
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
Environmental Impact Assessment (EIA) report on Rampal 1320MW coal-based powe...
 
Data Modeling with Neo4j
Data Modeling with Neo4jData Modeling with Neo4j
Data Modeling with Neo4j
 
Operative instruments in Conservative Dentistry & Endodontics
Operative instruments in Conservative Dentistry & EndodonticsOperative instruments in Conservative Dentistry & Endodontics
Operative instruments in Conservative Dentistry & Endodontics
 
Bringing Design to Life
Bringing Design to LifeBringing Design to Life
Bringing Design to Life
 
4. heredity and evolution
4. heredity and evolution4. heredity and evolution
4. heredity and evolution
 
Web Trends to Watch in 2014
Web Trends to Watch in 2014Web Trends to Watch in 2014
Web Trends to Watch in 2014
 
Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.
 
What I Carry: 10 Tools for Success
What I Carry: 10 Tools for SuccessWhat I Carry: 10 Tools for Success
What I Carry: 10 Tools for Success
 
Employee Discipline and Grievance Handling
Employee Discipline and Grievance HandlingEmployee Discipline and Grievance Handling
Employee Discipline and Grievance Handling
 
5000 Sat Words With Definitions
5000 Sat Words With Definitions5000 Sat Words With Definitions
5000 Sat Words With Definitions
 
BCG Matrix of Engro foods
BCG Matrix of Engro foodsBCG Matrix of Engro foods
BCG Matrix of Engro foods
 
Doctrine 2: Enterprise Persistence Layer for PHP
Doctrine 2: Enterprise Persistence Layer for PHPDoctrine 2: Enterprise Persistence Layer for PHP
Doctrine 2: Enterprise Persistence Layer for PHP
 
Asean quiz championship_2012
Asean quiz championship_2012Asean quiz championship_2012
Asean quiz championship_2012
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 
Deep Learning through Examples
Deep Learning through ExamplesDeep Learning through Examples
Deep Learning through Examples
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
 
Classroom Management Techniques
Classroom Management TechniquesClassroom Management Techniques
Classroom Management Techniques
 
GMAT Math Flashcards
GMAT Math FlashcardsGMAT Math Flashcards
GMAT Math Flashcards
 

Similar to ASHRAE Guideline Commissioning Process Overview

AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdfMy own
 
Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012REDceo.net
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Anthony Davies
 
The Digital Creative Process
The Digital Creative ProcessThe Digital Creative Process
The Digital Creative Processstorybridge
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projectsmtingle
 
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Aestikani Mahani
 
Walley.tina
Walley.tinaWalley.tina
Walley.tinaNASAPMC
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projectsharoldtaylor1113
 
Nice Pm Introduction Cert
Nice Pm Introduction CertNice Pm Introduction Cert
Nice Pm Introduction Certguest78aa88
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrongNASAPMC
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrongNASAPMC
 
Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioningjeff_ranson
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 
Software management framework
Software management frameworkSoftware management framework
Software management frameworkKuppusamy P
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsCCT International
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyersNASAPMC
 
CMAD Group Workbook 3.1 Op Model Enable
CMAD Group Workbook 3.1 Op Model Enable CMAD Group Workbook 3.1 Op Model Enable
CMAD Group Workbook 3.1 Op Model Enable Alexander Doré
 

Similar to ASHRAE Guideline Commissioning Process Overview (20)

Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
 
The Value of Building Commissioning
The Value of Building CommissioningThe Value of Building Commissioning
The Value of Building Commissioning
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
 
Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012Comfori red-sop seminar-ppt brochure-091012
Comfori red-sop seminar-ppt brochure-091012
 
Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)Consultancy brochure_Europe (final)
Consultancy brochure_Europe (final)
 
The Digital Creative Process
The Digital Creative ProcessThe Digital Creative Process
The Digital Creative Process
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
 
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
Manajemen proyek epci offshore utk kontraktor EPCI 23 aug 2014
 
Walley.tina
Walley.tinaWalley.tina
Walley.tina
 
Project Scheduling and Control Projects
Project Scheduling and Control ProjectsProject Scheduling and Control Projects
Project Scheduling and Control Projects
 
Nice Pm Introduction Cert
Nice Pm Introduction CertNice Pm Introduction Cert
Nice Pm Introduction Cert
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrong
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrong
 
Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioning
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
Software management framework
Software management frameworkSoftware management framework
Software management framework
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
 
CV - Abhijit
CV - AbhijitCV - Abhijit
CV - Abhijit
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyers
 
CMAD Group Workbook 3.1 Op Model Enable
CMAD Group Workbook 3.1 Op Model Enable CMAD Group Workbook 3.1 Op Model Enable
CMAD Group Workbook 3.1 Op Model Enable
 

ASHRAE Guideline Commissioning Process Overview

  • 1. Building Science Consultations APPLIED ENERGY SOLUTIONS COMMISSIONING PROCESS ASHRAE Guideline 0-2005 ASHRAE Guideline 1.1-2007 NIBS Guideline 3-2006 by David J. MacKay LEED AP, CPMP Applied Energy Solutions
  • 2. Commissioning Framework – ASHRAE 0-2005 – ASHRAE 1.1-2007 – ASHRAE/NIBS Guideline 3 • Commissioning Defined • Commissioning Process – Pre-Design Phase – Design Phase – Construction Phase – Occupancy & Operations • Ongoing Commissioning • Commissioning Keys to Success
  • 4. Total Building Commissioning Process ASHRAE Guideline 0-2005: The Commissioning Process (Used as a foundation for ASHRAE Guideline 1, NIBS Guideline 3, and other Total Building Commissioning Process technical guidelines Guidelines 2-200X & 4-200X ASHRAE Guideline 1-2007: NIBS Guideline 3-2006: through 14-200X: Technical HVAC&R Technical Exterior Enclosure Technical commissioning guidelines Requirements for the Requirements for the dealing with structure, Commissioning Process Commissioning Process electrical, lighting, interiors, plumbing, etc.
  • 5. • ASHRAE Guideline 0-2005 – Defines the process – Generic: any system or discipline • ASHRAE Guideline 1.1-2007 – How to apply the process to HVAC&R – Several annexes/examples • ASHRAE/NIBS Guideline 3 – How to apply the process to enclosure elements – Walls, floors, roofs, fenestration – Several annexes/examples
  • 6. • Total building Commissioning (Cx) guidelines are in the works: – Guideline X Plumbing (ASPE) – Guideline Y Lighting (IESNA) – Guideline 1.2 Existing HVAC&R (ASHRAE) – Guideline 1.3 Operator Training (ASHRAE) • This presentation will focus on ASHRAE Guideline 0-2005 and the overall Cx Process
  • 8. An ongoing & structured quality assurance process (ideally spanning from pre- design into occupancy) that ensures continual: – Communication – Documentation – Verification • In simplest terms, commissioning is intended to ensure a building meets the owner’s requirements upon turnover • It is NOT: – An event – A short term task – Punch list clearance • It is a Team sport—for successful commissioning, everyone must buy in to and participate in the process
  • 9. A quality-focused process for enhancing the delivery of a project. The process focuses upon verifying and documenting that the facility and all of its systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the Owner’s Project Requirements (OPR). * ASHRAE Guideline 0-2005: 4. Definitions
  • 10. • The OPR document explicitly calls out the minimum characteristics that will define a successful project from the owner’s perspective • Must address quality as well as quantity • Must include verifiable benchmarks (criteria) • OPR is completed during pre-design • This document becomes the basis for all commissioning verification efforts—and is thus critical to a successful commissioning outcome
  • 11. • The Commissioning Process is a quality-oriented process for achieving, verifying, and documenting that the performance of facilities, systems, and assemblies meets defined objectives and criteria. • The Commissioning Team uses methods and tools to verify that the project is achieving the Owner’s Project Requirements throughout the delivery of the project. • The Commissioning Process assumes that owners, programmers, designers, contractors, commissioning team members, and operations and maintenance entities are fully accountable for the quality of their work.
  • 12. COMMISSIONING PROCESS PRE-DESIGN PHASE
  • 13. • Develop the Owner’s Project Requirements (OPR) • Review lessons from previous projects • Identify Cx scope and budget • Develop initial Cx Plan • Owner acceptance of pre-design Cx activities * ASHRAE Guideline 0-2005: 6.1.2… Objectives
  • 14. • To get the process off on the right foot • Ensure development of a thorough OPR document
  • 15. • The Commissioning Authority (CxA) • The Cx Team • Pre-Design Cx Documents
  • 16. • The Commissioning Authority (CxA) • The Cx Team • Pre-Design Cx Documents
  • 17. • “Authority” (or “Provider”) versus “Agent” – An authority acts for the owner – An agent can act as the owner (NOT intended) • Professional services contract must spell out roles and responsibilities for this crucial party—including scope of work to be conducted (which can vary greatly) • CxA may be: – An independent entity – Owner’s in-house staff • THE CXA WILL NOT SINGLE-HANDEDLY COMMISSION A PROJECT
  • 18. • Should have actual and perceived independence of action (an unbiased party) • Should have a background and experience to match project expectations • Will act in the best interests of the owner • Will interact with owner’s representatives, the design team, the contractor and subcontractors • Will lead the Cx Team and team meetings • Should have outstanding people skills
  • 19. • The Commissioning Authority (CxA) • The Commissioning Team • Pre-Design Cx Documents
  • 20. • Includes many members: – CxA – Programming Consultants – Owner’s representatives • Users • Maintenance Staff – Design Team representatives – Contractor representatives (if possible) • Members (numbers and bodies) will change from phase to phase
  • 21. • The team is led by the CxA • The team will complete a variety of tasks • Specific pre-design roles and responsibilities will vary from project to project • Responsibility for team members must be clearly allocated and contractually assigned
  • 22. • The Commissioning Authority (CxA) • The Commissioning Team • Pre-Design Cx Documents
  • 23. • OPR • Cx/design service contract integration • Cx Plan • Issues Log • Systems Manual
  • 24. Project Inception Building Development Commissioning Process Pre-Design Phase Process Form Building Development Form Commissioning Team (Cx) Team-S5.2,1 Project Participate in Project Review Review Meeting-S5.2 Meeting Develop Determine Develop Initial Owner’s Commissioning Project Commissioning Scope & Budget- Develop Develop Overall Develop Building Plan-5.2.4 Requirements- S5.2.2[c] Design/Constructio Building Budget Program S5.2.2 n Mgmt. Plans Owner Acceptance of Cx Products Other Pre-design Services Owner Acceptance of To Design Phase Pre-Design Products To Design Phase
  • 25. COMMISSIONING PROCESS DESIGN PHASE
  • 26. • Update the Commissioning Plan • Verify the Basis of Design • Develop commissioning process requirements for the Construction Documents • Develop draft Construction Checklists • Develop draft Test Procedures • Define training requirements • Perform OPR-based design preview • Update OPR * ASHRAE Guideline 0-2005: 6.1.2… Objectives
  • 27. • Prepare for construction phase Cx activities • Verify design decisions and documentation match OPR
  • 28. • The Cx Team • Design Phase Cx Documents • Ensuring the Contractor is on Board • Design Phase Verifications
  • 29. • The Cx Team • Design Phase Cx Documents • Ensuring the Contractor is on Board • Design Phase Verifications
  • 30. • CxA • Owner’s representatives – Project Manager – O&M Staff • Design team representatives (including specialty consultants) • Contractor representatives (if possible-input on Construction Checklists and testing can be exceptionally valuable) • Major equipment/assembly manufacturer representatives
  • 31. • The Cx Team • Design Phase Cx Documents • Ensuring the Contractor is on Board • Design Phase Verifications
  • 32. • Basis of Design (BOD) – This is considered a formal Cx process document that captures—in a usable format—key design influencing assumptions, methods, selections, and decisions – The purpose of the BOD is to give other parties easy access to the rationale behind design decisions – Construction Documents show WHAT was selected but not WHY – The WHY can be very valuable when considering a contractor-proposed substitution or making a decision on building operations – This document is valuable when design proposals are compared against OPR
  • 33. • BOD document typically includes: – Codes, standards, guidelines used – Basis for system/assembly selection – System and assembly options considered – Calculation/analysis methods used – Key inputs to calculations/analysis • Data (U-factors, climate, etc.) • Assumptions (energy costs, maintenance capabilities, etc.) – Narrative descriptions of system/assembly operations – Narrative descriptions of system/assembly control sequences – Equipment/products used as a basis of design
  • 34. • Cx Plan – This is a continually developing roadmap for upcoming activities and record of completed activities – During the design phase, the plan will be updated to provide details regarding construction phase commissioning activities-an outline of occupancy and operations phase activities will be included – A detailed Training Plan will be developed as a section of the Cx Plan – Ensure that the Cx Plan adequately addresses Cx process activities, responsibilities, and schedule
  • 35. • Construction Checklists – These are pre-prepared forms used to structure and facilitate verifications conducted as part of the Cx process – Ideally, they would be part of the Construction Documents (or provided as “for information” documents) – Typically will be completed in stages as construction progresses – Properly used they can help in catching deviations before they become problems – When completed, they become part of the Systems Manual and can assist with ongoing building operations
  • 36. • Test Procedures – Test Procedures are an extension of verification procedures beyond the level of complexity that can reasonably be handled by Construction Checklists – An example: a protocol to verify that upon smoke detection in an atrium, the HVAC, electrical and alarm systems do what they should to meet OPR – Another example: a protocol to verify that the HVAC system functions as it should to meet the OPR under a range of anticipated loading and weather conditions – Test Procedures must be scripted and ideally will allow for easy recording and archiving of results for inclusion in the Systems Manual
  • 37. • Systems Manual – A critical document for the owner – Requires input from: • Design team- need for input called out during pre-design and product verified during design phase • Contractor- responsibilities must be included in the contract documents during design phase • CxA – This document really needs a champion (a responsible and capable party) – Without a good Systems Manual, many of the ongoing benefits of Cx will be lost during occupancy and operations
  • 38. • Issues Log – The Issues Log is essentially the collective memory of the Cx Team regarding problems that arise throughout the Cx process – It should be easy to access and use – It should be helpful (not litigious) – It should show all (or most) issues resolved upon occupancy – Resolution may take many routes (a change in OPR, a change in design, change in component, and adjustment, etc.)
  • 39. • Training Plan – Constitutes a defined section of the Cx Plan – Lays out training needs and expectations – Lists training requirements • Intended audience • Expected outcomes • Suggests venue/approach • Estimates time allocations – Outlines training verification – Must be detailed enough to permit a reasonable bidding and scheduling by contractor – Will likely require involvement of design team members
  • 40. Document Responsibility Basis of Design Design Team Cx Requirements for Construction Design Team & CxA/Cx Team Documents Construction Checklists Design Team & CxA/CxTeam Test Procedures CxA/Cx Team Training Plan CxA/Cx Team Systems Manual-Content and Design team Contract Document Requirements Issues Log CxA/Cx Team Cx Plan CxA
  • 41. • The Cx Team • Design Phase Cx Documents • Ensuring the Contractor is on Board • Design Phase Verifications
  • 42. Communicating commissioning process requirements to the contractor – Specifications • General Conditions requirements – Participation in activities – Ramifications for non-compliance • Section specific requirements – Construction Checklists – Test Procedures – Training – Provide a clear picture of responsibilities – Allow for a reasonable bid to be prepared – Permit impacts on schedule to be reasonably estimated
  • 43. • The Cx Team • Design Phase Cx Documents • Ensuring the Contractor is on Board • Design Phase Verifications
  • 44. • Intent is not to second guess (or become) the design team • Intent is to verify that design will reasonably deliver the owner’s project requirements • Sampling of design documents is highly recommended as a procedure • The owner possesses ultimate acceptance authority
  • 45. From Pre-Design Building Development Phase-S5 Commissioning Process Design Phase: Schematic Design Process S6 Project Objectives Meeting Participate in Project Update Cx Team S6.2.1 Objectives Meeting S6.2.9.1 Identify Macro Select Evaluate Options Prepare BOD Document Determine Systems Manual Determine Training System Options Systems S6.1.1& S6.2.2.1 Structure S6.2.6 Requirements S6.2.7 Prepare Schematic Update OPR Update Cx Plan Reviews of Design Design Documents Documents S6.2.8 S6.2.8.1 S6.2.3.1(a) Project Objectives Meeting Final Objectives Review for Phase S6.2.9.2 Owner Acceptance of Schematic Design Products Owner Acceptance of Cx Products S6.3 To Design Development Phase To Design Development Phase
  • 46. From Design Phase: Building Development Schematic Design S6 Commissioning Process Design Phase: Design Process Development S6 Project Objectives Meeting Participate in Project Objectives Meeting Update Cx Team S6.2.1 S6.2.9.1 Prepare Identify & Refine Design of Design Evaluate Micro Design Reviews Systems Development Update BOD S6.2.2.2 Update OPR S6.2.2.2 System Options S6.2.8 Documents Update Training Update Cx Plan Update Systems Requirements Manual S6.2.6 S6.2.3.1(b) S6.2.7 Project Objectives Participate in Project Meeting Objectives Meeting S6.2.9.2 Owner Acceptance of Design Development Products Owner Acceptance of Cx Products S6.3 To Design Phase: Construction Documents To Design Phase: Construction S6 Documents S6
  • 47. From Design Phase: Design Building Development Development S6 Commissioning Process Design Phase: Process Construction Documents Participate in Project Project Objectives Meeting Objectives Meeting S6.2.9.1 Cx Reviews of Design Update OPR S6.2.2.2 Update BOD S6.2.2.2 Identify Prepare Docs. S6.2.8 Outstanding Construction Enclosure Issues Documents Update Cx Plan Develop Cx Process Req. for Construction S6.2.3.1(b) Const. Documents S6.2.4 Checklists S6.2.5 Update Systems Manual S6.2.6 Review @ 20% of systems re Develop Cx Req. for Constr. BOD S6.2.8.4 Documents S6.4 Acceptance Requirements S6.3 Training Requirements S6.2.7 & S6.5 Project Objectives Final Objectives Meeting for Meeting Phase S6.2.9.2 Owner Acceptance of Owner Acceptance of Cx Construction Products S6.3 Documents To Construction Phase To Construction Phase
  • 49. • Verify that submittals meet the OPR • Finalize Construction Checklists and Test Procedures • Verify that systems and assemblies meet the OPR • Verify training of owner’s personnel • Verify the Systems Manual • Update the OPR and Cx Plan * ASHRAE Guideline 0-2005: 7.1.2… Objectives
  • 50. • To verify construction activities • To prepare project (and O&M staff) for handover to owner
  • 51. • Meetings and Communications • Updating Cx Documents • Submittal Reviews • Construction Checklists and Test Procedures • Training
  • 52. • Meetings and Communications • Updating Cx Documents • Submittal Reviews • Construction Checklists and Test Procedures • Training
  • 53. • The Cx team is the avenue for effective communications – Via regular meetings and – Skillful use of the Issues Log • Cx Team Members: – CxA – Owner’s representatives • PM • O&M staff – Design team representatives (including specialty consultants) – Contractor representatives • Subs • TAB • Controls – Major equipment/assembly manufacturer representatives
  • 54. • Meetings and Communications • Updating Cx Documents • Submittal Reviews • Construction Checklists and Test Procedures • Training
  • 55. Document Action Responsibility BOD update Update as required by owner change Design team orders and contractor substitutions OPR update Update as required by owner change Cx Team (w/owner explicit orders and contractor substitutions agreement) Construction Finalize and implement Used by contractor, verified by Cx Checklists Team Test Finalize and implement Used by contractor, verified by Cx Procedures Team Systems Complete and verify Completed by assigned party, Manual verified by Cx Team Training Plan Finalize and implement Implemented by Contractor, design team, and CxA Issues Log Use Used by Cx Team Cx Plan Update and expand CxA
  • 56. • Meetings and Communications • Updating Cx Documents • Submittal Reviews • Construction Checklists and Test Procedures • Training
  • 57. Principles: – The purpose of verifications is NOT to provide the contractor with free quality control services; it is to provide the owner with assurance that the OPR are being delivered – ASHRAE Guideline 0 strongly recommends that a sampling strategy be used for all verifications – The sampling frequency will be established by the CxA, 5%-10% is generally recommended • Sampling is a controversial issue—and each CxA will have his/her own take on how to approach this. • Spell out sampling % in RFP – If deviations are found during sampling, a pre-established response is implemented— this may involve additional sampling or rejection of the activity – Financial responsibility for re-verification activities must be spelled out in construction contracts and service contracts
  • 58. Quandaries: – ASHRAE Guideline 0-2005 sets the OPR as the benchmark against which verifications are to be conducted – The contractor is not contractually bound (generally) to meet the OPR, but rather the Contract Documents – If deviations are found relative to Contract Documents, corrective action is reasonably easy to justify – If deviations are found relative to OPR, but not the Contract Documents, then things can get tricky – Contingencies for addressing the above scenario should be spelled out for all interested parties – In theory, verification of design documents should head off OPR / Construction Document conflicts
  • 59. Implementations: – Construction Checklist elements and Test Procedures that involve activating a device, system, or assembly should generally be done by the contractor under the observation of the CxA and other interested parties (the owner’s operating personnel, etc.) – Verification of such activities would be based upon witnessing of tests and review of testing documentation – Verifications of documents (such as the Systems Manual) would normally be accomplished by CxA/Cx Team review – Verification of training might be accomplished by witnessing, testing, and/or interviews
  • 60. • Meetings and Communications • Updating Cx Documents • Submittal Verification Reviews • Construction Checklists and Test Procedures • Training
  • 61. • The CxA conducts some checking, witnesses other checking, and verifies that a sample of the Construction Checklists meets quality expectations and demonstrates quality that conforms with the OPR and Construction Documents • The verification process is seeking systemic problems • Minor deviations would be addressed via the Issues Log • Major deviations might require concerted action from the Cx Team • The owner retains ultimate acceptance responsibility for any deviations that negatively impact the OPR
  • 63. • The CxA witnesses selected tests and verifies that the results of the Test Procedures meet quality expectations and conform with the OPR and Contract Documents • The verification process is seeking systemic problems • Minor deviations would be addressed via the Issues Log • Major deviations might require concerted action from the Cx Team • The owner retains ultimate acceptance responsibility for any deviations that negatively impact the OPR
  • 67. • Meetings and Communications • Updating Cx Documents • Submittal Verification Reviews • Construction Checklists and Test Procedures • Training
  • 68. • The CxA verifies that the results of the training activities meets quality expectations and conforms with the OPR and Contract Documents • The verification process is seeking systemic problems • Minor deviations would be addressed via the Issues Log • Major deviations might require concerted action from the Cx Team • The owner retains ultimate acceptance responsibility for any deviations that negatively impact the OPR
  • 69. • The CxA verifies that the Systems Manual is complete (to the extent possible) and that a sample of the manual meets quality expectations and conforms with the OPR and Contract Documents • The verification process is seeking systemic problems • Minor deviations would be addressed via the Issues Log • Major deviations might require concerted action from the Cx Team • The owner retains ultimate acceptance responsibility for any deviations that negatively impact the OPR
  • 70. From Design Phase: Construction Documents Building Development Commissioning Construction Process Phase S7 Process Pre-Bid Conference Participate in Pre-Bid Update Cx Team Conference S7.2.2 S7.2.1.2 Receive Verify & Coordinate Verify Systems Manual and Submittals Submittals S7.2.7 Const. Checklist S7.2.16 QA/QC Plan & Site Specific Testing Plan Pre-Installation Meeting for Mock-Ups Laboratory Testing Verify Lab Performance Field Mockups Verify Mockup Update Issues Log Performance Update OPR & BOD S7.2.4 Sample Testing Verify Sample
  • 71. Building Development From Construction Phase Part 1 Commissioning Process Process Construction Phase Part 2 S7 Pre-Construction Pre-Construction Cx Meetings Process Meetings S7.2.6 Install/Construct Exterior Enclosure Components & Verify Construction Checklist Update OPR & BOD Update Issues Resolve Systems Completeness S7.2.15(c) S7.2.16.1(f) & S7.2.16.1(g) Log S7.2.16.1(i) Issue Update Issues Resolve Direct & Verify Tests S7.2.13 Log S7.2.16(i) Issue Update Cx Plan S7.2.5 Provide Training & Update Requirements S7.5 Owner Accepts Substantial Completion Owner Acceptance of Cx of Exterior Enclosure Products S7.3 To Occupancy and To Occupancy and Operations Phase S8 Operations Phase
  • 72. From Construction Phase Building Development Commissioning Process Process Occupancy and Operations Phase S8 Substantial Completion Participate in Substantial Meeting Completion Meeting S8.1 Contractual Owner Begins Warranty/Correction Update Owner’s Project Beneficial Use Period Begins Requirements S8.1.1 Coordinate Contractor Performance Verification Direct & Verify Seasonal Tests Callback S8.2.2 S8.2.3 S8.2.1.3(b) Ongoing Operation, Maintenance, and Modification of the Building Update Systems Manual Systems, Assemblies and S8.2.6 Components, and their Associated Documentation Resolve Issue Owner Final Acceptance Req. S8.35 Training Req S8.5 Acceptance of Docum. Req. S8.4 Constructed Building Owner Acceptance of Cx End of Typical Building Products Development Contract
  • 74. • Complete seasonal or deferred testing • Minimize contractor callbacks • Document lessons learned • Assist with any warranty issues • Provide assistance with ongoing facility operations to meet the OPR • Close out the process via formal owner acceptance * ASHRAE Guideline 0-2005: 8.1.3… Objectives
  • 75. • Close out the (initial) commissioning process • Prepare the owner for long-term beneficial use of the facility
  • 76. • The Cx Team • Updating Cx Documents • Lessons-Learned Workshop • Final Cx Report
  • 77. • The Cx Team • Updating Cx Documents • Lessons-Learned Workshop • Final Cx Report
  • 78. • CxA • Owner’s representatives – Project Manager – O&M Staff • Design team representatives (as required) • Contractor representatives (including subs) • Major equipment/assembly manufacturer representatives (as required)
  • 79. • The Cx Team • Updating Cx Documents • Lessons-Learned Workshop • Final Cx Report
  • 80. Document Action Responsibility BOD update Update as required by owner change Design team orders and contractor substitutions OPR update Update as required by owner change Cx Team (w/owner explicit orders and contractor substitutions agreement) Systems Verify and employ Completed by assigned party, Manual verified by Cx Team Training Plan Finalize and implement Implemented by Contractor, design team, and CxA Issues Log Close out Cx Team Cx Plan Develop and deliver CxA
  • 81. • The Cx Team • Updating Cx Documents • Lessons-Learned Workshop • Final Cx Report
  • 82. • Although most involved parties are ready to move on at this stage, all can benefit from reflecting on the Cx process • The owner can benefit form information gleaned by the various parties that relates completed product performance to the original owner’s project requirements • The design team can benefit from issues that relate design process to implementation of design intent and criteria (objectives and benchmarks) • The contractor can benefit from issues that relate construction and quality control processes to design intent and Construction Documents • The CxA can benefit from feedback on all aspects of the process
  • 83. • The Cx Team • Updating Cx Documents • Lessons-Learned Workshop • Final Cx Report
  • 84. • Identify any systems or assemblies that do not perform in accordance with the OPR and note likely ramifications of such deviations • Evaluate operating condition of systems/assemblies upon completion of testing • Summarize the contents of the Issues Log—extent of concerns, costs, operational impacts • System performance benchmarks • Lessons Learned • Ideally, provide a sense of worth of the Cx process on the project
  • 86. • Ongoing Cx extends the process beyond the termination of the original commissioning services agreement (typically about a year into building occupancy, upon major equipment warranty expiration) • The intent is to continue to assist the owner in maximizing beneficial use of the facility for the long term • It appears likely that ASHRAE Guideline 0 will in the future include more information on the ongoing Cx process
  • 87. Ongoing Building Commissioning Operations From End of Typical Building Development Contract Process Update Owner’s Direct & Verify Project Requirements Periodic Tests and S8.6.1 Benchmarks S8.6.1 Ongoing Operation, Maintenance, and Modification of the Building Systems, Assemblies, Components, and their Associated Documentation Whole Building Maintain Systems Performance Manual S8.6.1 Verification S8.6.2 Continue Resolve Issues Continue
  • 88. COMMISSIONING PROCESS KEYS TO SUCCESS
  • 89. Good Benchmarking and archiving of documents – Owner’s Project Requirements (OPR) – Basis of Design (BOD) – Commissioning (Cx) Plan – Construction Checklists – Test Protocols – Training Plan – Systems Manual – Cx Process Reports • Explicit expectations and responsibilities – Clear RFQ/RFP for CxA – Professional service contracts that address commissioning – Construction specifications that address commissioning and provide clear statements of “who” and “if-then” • Enforcement of Cx related contract provisions
  • 90. • Ongoing Communications – Cx Meetings – Cx Reports – Issues Log • Well reasoned clarity of purpose • Verification by Cx Team of all key elements against OPR • Serious owner buy-in and support • Owner Acceptance of all Deliverables/Products