Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Turnkey implementation of distribution projects
1. Turnkey implementation of Distribution Projects :
Few DO’s & DON’T’s
* D. Pawan Kumar & A. K. Sinha
Preamble :
Phenomenal growth in power sector and the advent of heavy investment in
distribution sector throughout the country have brought in a need for new models of
implementation such as turnkey projects. Additionally, the utilities are accustomed to
departmental implementation process, which are okay for small time O&M jobs,
while turnkey approach helps to bring in several advantages like quality assurance,
time and cost control, alongside, best practices, if due care is exercised. Following
do’s & don’ts sound simple, yet, they reflect major concerns for careful attention.
The major activities in turnkey implementation are found to be included the following based on
the nature, type and scope of the project. For a traditional turnkey contract, comprising of
investment of huge investments and timely and effective implementation, the projects require
commitment of varied skills and resources in almost all the areas as follows:
• Project Initiation / Identification /Formulation
• Preparation of Detailed project report along with
Bill of Materials
Bill of Quantities
Component wise /Lump sum cost details
Estimation of project Completion time & cost
• Technical / Financial vetting & Approval of DPR both technical & financial
• Preparation of bid provisions & complete document comprising of :
2. General conditions of contract,
Special conditions of contract,
Technical specifications,
Drawings,
Bid proposal Sheets
• Finalization of Document & Floating of tender
• Pre bid conference for the intending bidders expressing interest, including
arrangement of site visit
• Finalization of bid & issuance of LoA
• Project Monitoring, Physical (supply / Erection) & financial progress,
measurement, Verification, Inspection, Quality Assurance
• Closure of the project, documenting improvements, benefits achieved, best
practices, case studies, Impact Assessment,
• The detailed project report or DPR is the first major document based on which
proposals/funds are approved and should represent and overall view of the project
including technical and financial benefits. Features of what a DPR should contain
are:
EXECUTIVE SUMMARY
DESCRIPTION OF EXISTING SYSTEM
DEFICIENCIES IN EXISTING SYSTEM
ON-GOING INITIATIVES
PROPOSED SYSTEM
COST ESTIMATE
COST BENEFITS
MANAGEMENT & TECHNOLOGY
3. MAJOR AREAS REQUIRING CAREFUL ATTENTION:
• During the preparation of the Bid documents, many times, costs are taken from internal
documents, references and past data and often, these costs are old/outdated, specially when
the technical specifications, equipment specifications, demand, international level quality
assurance. Therefore, care needs to be taken, to get latest cost/revised cost of equipment,
with flexibility for factoring increments, since implementation cycle may take few
months/years often.
• In certain difficult terrains, cost of erection may on the higher side. These need to be
factored while preparing the DPR.
• In case of supply of certain items, there is a special procurement preference by
State/Central Governments to boost the local SSIs, manufacturers and price advantages for
local manufacturers, towards growth of local industries, which often are not considered while
preparing the project report, and may cause derailment/delay/cost escalation of the project.
• Many a time, the project approval and fund approval take considerable time delay, specially in
case of national and international projects and during the time of tender floating, a snap shot price
validation/review may be carried out, towards revised project cost estimation (e.g. the prices of steel
and associated materials has increased by several folds in the very recent past and is continuously
increasing and majority of sub-transmission and distribution projects consume a substantial quantity
of steel and steel material like rail poles, angles, channels and similar other items). Such cost
overruns makes the estimated price unrealistic and therefore offered price may be much higher, even
for the lowest bidder and makes bid evaluation and approval process difficult with special
justification is called for. Similarly IT related projects may need to factor in latest versions of
hardware/software with scalability provisions.
• Sometimes, intending bidders bid without surveying the site conditions, specially in case of green
field projects and often land themselves, as well as the owner, into difficult situation.
• In case of green field projects, where site/land has to be acquired, planning may be initiated
during the DPR stage itself, towards process of land acquisition (specially in urban areas). This takes
time and requires formalities, co-ordination between various departments and may become one of the
reasons for time and cost overrun.
• While the Bid is finalized and LoA issued, care may be taken to get the weekly, monthly schedule
of supply and erection activities through formal project planning technique, and linking the same with
fund flow is crucial towards smooth implementation of the project and avoidance of delay in progress
of work.
• While the project is under implementation, streamlining various procedures like the following
go a long way towards timely completion of the project:
4. Deployment of a dedicated team towards inspection, testing of materials as per
specifications and project requirements.
Deployment of a project team for monitoring of the project progress both for supply and
erection.
Formalizing the measurement books of the project.
Quick estimation of materials and quantities for the items which are required over and
above LoA quantity for completion of the job as per site requirement and conditions.
Systematizing the procedure towards incorporating deviations and also bringing
necessary amendments in the project arising out of such variations in items, quantities,
and specification and price implications of the same.
• The above precautions taken at the Planning stage will enable both the contractor as well as
owner to complete the project within the time and also tuning the internal team adequately to
meet the project requirements (the activities which requires approval from the owner) will also
avoid conflicts.
• However, though money is invested and project is completed, formal closure of the project takes
a long time due to missing links in any one of the areas brought out in the above paras.
• In case of modern technologies, IT enabled projects, like SCADA, static metering, DCS, etc., it
would be very desirable to incorporate 3 to 5 year MIS support as part of project deliverables to
help capacity building of owner’s team. This also ensures commitment of the bidder/supplier for
Quality Assurance in the long run.
• Distribution projects are often implemented with certain goals such as the following :
Capacity enhancement
Loss Reduction
Outage reduction
Overall Revenue performance improvement
Improvement of image to customers, consumers
It is also obligatory to document benefits achieved, best practices implemented, impact
assessment of the projects, which are normally missed and given least priority. Therefore, documentation
through case studies will go a long way in formulating, identification of similar projects and also clearing
the project documents for similar projects in future.