Assigning Constraints in Primavera P6
Version 8.2
When setting constraints sometimes the constraint
time will not be set at the start or finish of the
activity calendar but set at 00:00 or some other
irrelevant time. Therefore when setting constraints
you should always display the time by
selecting Edit, User Preferences …,Dates tab to
ensure the constraint time is compatible with the
activity calendar.
Number of Constraints per Activity
Two constraints are permitted against each activity.
They are titled Primary and Secondary Constraint. After
the Primary has been set, a Secondary may be set only
when the combination is logical and therefore a reduced
list of constraints is available from the Secondary
Constraint list after the Primary has been set.
Setting a Primary Constraint Using the Activity
Details Form
To assign a constraint using the Activity Details form:
 Select the activity requiring a constraint,
 Open the Status tab on the Activity Details form,
 Select the Primary Constraint type from
the Date drop down list to the right of Primary:
Setting a Secondary Constraint Using the Activity
Details Form
To assign a constraint using the Activity Details form:
 Select the activity requiring a constraint,
 Open the Status tab on the Activity Details form,
 Select the Secondary Constraint type from
the Date drop down list to the right of Secondary:
The picture above shows that after a Primary Start On
or After constraint is set there are only two Secondary
Constraints available. After a constraint is set the date will
have an asterisk “*” next to it.
 Start Constraints will have the “*” next to the Start
Date, and
 Finish Constraints will have the “*” next to the Finish
Date.
 Unlike P3 and SureTrak one does not have to display
the Late Dates to see a Late Constraint “*”.
Expected Finish Constraint
This constraint is set in the dates Status area above
the Constraints area and will only work if the
Tools, Schedule…, , Use Expected Finish dates check
box is checked.
Paul Harris writes training manuals for MS
Project and Primavera P6 and Delivers Project
Management Training Courses Throughout
Australia and the world. His books are available
on Amazon and Kindle.

More Related Content

Viewers also liked

How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project ManagementTotalSoft
 
P6 professional standalone_install_and_config_guide
P6 professional standalone_install_and_config_guideP6 professional standalone_install_and_config_guide
P6 professional standalone_install_and_config_guideSuresh G Sankarankutty
 
Installing Oracle Primavera P6 Professional standalone
Installing Oracle Primavera P6 Professional standaloneInstalling Oracle Primavera P6 Professional standalone
Installing Oracle Primavera P6 Professional standaloneTen Six Consulting
 
Primavera P6 installation
Primavera P6 installationPrimavera P6 installation
Primavera P6 installationMansoor Shoaib
 
Primavera Project Management P6 Course Session 1
Primavera Project Management P6 Course Session 1Primavera Project Management P6 Course Session 1
Primavera Project Management P6 Course Session 1Mohamed Adel
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14p6academy
 
Oracle Primavera P6 R16.1
Oracle Primavera P6 R16.1Oracle Primavera P6 R16.1
Oracle Primavera P6 R16.1Eduard Enache
 

Viewers also liked (11)

How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Primavera Project Management
Primavera Project ManagementPrimavera Project Management
Primavera Project Management
 
P6 professional standalone_install_and_config_guide
P6 professional standalone_install_and_config_guideP6 professional standalone_install_and_config_guide
P6 professional standalone_install_and_config_guide
 
Installing Oracle Primavera P6 Professional standalone
Installing Oracle Primavera P6 Professional standaloneInstalling Oracle Primavera P6 Professional standalone
Installing Oracle Primavera P6 Professional standalone
 
Primavera P6 installation
Primavera P6 installationPrimavera P6 installation
Primavera P6 installation
 
Primavera Project Management P6 Course Session 1
Primavera Project Management P6 Course Session 1Primavera Project Management P6 Course Session 1
Primavera Project Management P6 Course Session 1
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....
 
Oracle Primavera P6 R16.1
Oracle Primavera P6 R16.1Oracle Primavera P6 R16.1
Oracle Primavera P6 R16.1
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Primavera P6 Online Training
Primavera  P6 Online TrainingPrimavera  P6 Online Training
Primavera P6 Online Training
 

More from danieljohn810

Change Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from StaffChange Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from Staffdanieljohn810
 
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...danieljohn810
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Managementdanieljohn810
 
Destination Wedding Etiquette
Destination Wedding EtiquetteDestination Wedding Etiquette
Destination Wedding Etiquettedanieljohn810
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequencesdanieljohn810
 
Australian Workplace Health and Safety Resources
Australian Workplace Health and Safety ResourcesAustralian Workplace Health and Safety Resources
Australian Workplace Health and Safety Resourcesdanieljohn810
 
Cert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative RequirementsCert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative Requirementsdanieljohn810
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)danieljohn810
 
Certificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS TermsCertificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS Termsdanieljohn810
 
Writing Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training CoursesWriting Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training Coursesdanieljohn810
 
Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)danieljohn810
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)danieljohn810
 
Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management danieljohn810
 
Occupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSOccupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSdanieljohn810
 
Executive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA TrainingExecutive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA Trainingdanieljohn810
 
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...danieljohn810
 
Occupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and PrioritiesOccupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and Prioritiesdanieljohn810
 
Office 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfOffice 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfdanieljohn810
 
Glossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and SafetyGlossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and Safetydanieljohn810
 
How to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS InformationHow to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS Informationdanieljohn810
 

More from danieljohn810 (20)

Change Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from StaffChange Management Training – Gaining Support from Staff
Change Management Training – Gaining Support from Staff
 
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
Diploma in Project Management – How to Create a Work Breakdown Structure (WBS...
 
Basic Principles of Project Management
Basic Principles of Project ManagementBasic Principles of Project Management
Basic Principles of Project Management
 
Destination Wedding Etiquette
Destination Wedding EtiquetteDestination Wedding Etiquette
Destination Wedding Etiquette
 
Diploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity SequencesDiploma of Project Management – How to Set Up Project Activity Sequences
Diploma of Project Management – How to Set Up Project Activity Sequences
 
Australian Workplace Health and Safety Resources
Australian Workplace Health and Safety ResourcesAustralian Workplace Health and Safety Resources
Australian Workplace Health and Safety Resources
 
Cert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative RequirementsCert IV OHS - WHS Responsibilities and Legislative Requirements
Cert IV OHS - WHS Responsibilities and Legislative Requirements
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Certificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS TermsCertificate IV OHS - Glossary of Common OHS Terms
Certificate IV OHS - Glossary of Common OHS Terms
 
Writing Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training CoursesWriting Meeting Agendas - Business Writing Skills Training Courses
Writing Meeting Agendas - Business Writing Skills Training Courses
 
Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)Diploma of Project Management - Activity Resource Estimating (Outputs)
Diploma of Project Management - Activity Resource Estimating (Outputs)
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
 
Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management Schedule Development - Diploma in Project Management
Schedule Development - Diploma in Project Management
 
Occupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHSOccupational Health and Safety Training -The Role of Managers in WHS
Occupational Health and Safety Training -The Role of Managers in WHS
 
Executive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA TrainingExecutive Assistant Training - Advanced PA Training
Executive Assistant Training - Advanced PA Training
 
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
Occupational Health and Safety Training - WHS Needs and Priorities (Legal Req...
 
Occupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and PrioritiesOccupational Health and Safety Training - WHS Needs and Priorities
Occupational Health and Safety Training - WHS Needs and Priorities
 
Office 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdfOffice 365 Excel Essentials Training Course.pdf
Office 365 Excel Essentials Training Course.pdf
 
Glossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and SafetyGlossary of OHS Terms - Diploma in Occupational Health and Safety
Glossary of OHS Terms - Diploma in Occupational Health and Safety
 
How to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS InformationHow to Measure the Relevance and Accuracy of OHS Information
How to Measure the Relevance and Accuracy of OHS Information
 

Recently uploaded

Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan
 
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...JeylaisaManabat1
 
E J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxE J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxJackieSparrow3
 
Inspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptxInspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptxShubham Rawat
 
(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)oannq
 
南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证kbdhl05e
 

Recently uploaded (6)

Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
Authentic No 1 Amil Baba In Pakistan Amil Baba In Faisalabad Amil Baba In Kar...
 
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
Module-2-Lesson-2-COMMUNICATION-AIDS-AND-STRATEGIES-USING-TOOLS-OF-TECHNOLOGY...
 
E J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptxE J Waggoner against Kellogg's Pantheism 8.pptx
E J Waggoner against Kellogg's Pantheism 8.pptx
 
Inspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptxInspiring Through Words Power of Inspiration.pptx
Inspiring Through Words Power of Inspiration.pptx
 
(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)(南达科他州立大学毕业证学位证成绩单-永久存档)
(南达科他州立大学毕业证学位证成绩单-永久存档)
 
南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证南新罕布什尔大学毕业证学位证成绩单-学历认证
南新罕布什尔大学毕业证学位证成绩单-学历认证
 

How to Assign Constraints in Primavera P6 – Project Management Software

  • 2. Assigning Constraints in Primavera P6 Version 8.2
  • 3. When setting constraints sometimes the constraint time will not be set at the start or finish of the activity calendar but set at 00:00 or some other irrelevant time. Therefore when setting constraints you should always display the time by selecting Edit, User Preferences …,Dates tab to ensure the constraint time is compatible with the activity calendar.
  • 4. Number of Constraints per Activity Two constraints are permitted against each activity. They are titled Primary and Secondary Constraint. After the Primary has been set, a Secondary may be set only when the combination is logical and therefore a reduced list of constraints is available from the Secondary Constraint list after the Primary has been set.
  • 5. Setting a Primary Constraint Using the Activity Details Form To assign a constraint using the Activity Details form:  Select the activity requiring a constraint,  Open the Status tab on the Activity Details form,  Select the Primary Constraint type from the Date drop down list to the right of Primary:
  • 6. Setting a Secondary Constraint Using the Activity Details Form To assign a constraint using the Activity Details form:  Select the activity requiring a constraint,  Open the Status tab on the Activity Details form,  Select the Secondary Constraint type from the Date drop down list to the right of Secondary:
  • 7. The picture above shows that after a Primary Start On or After constraint is set there are only two Secondary Constraints available. After a constraint is set the date will have an asterisk “*” next to it.  Start Constraints will have the “*” next to the Start Date, and  Finish Constraints will have the “*” next to the Finish Date.  Unlike P3 and SureTrak one does not have to display the Late Dates to see a Late Constraint “*”.
  • 8. Expected Finish Constraint This constraint is set in the dates Status area above the Constraints area and will only work if the Tools, Schedule…, , Use Expected Finish dates check box is checked. Paul Harris writes training manuals for MS Project and Primavera P6 and Delivers Project Management Training Courses Throughout Australia and the world. His books are available on Amazon and Kindle.