SlideShare a Scribd company logo
1 of 13
Chapter 1 :
Claims Management Framework
• Lets assume that during execution phase , you found some issues - not under your responsibility -
in your project ,that will hinder your progress or incurring you extra costs , but don't know how to
claim your rights , in that case you may loose your rights or may the work stopped completely .
• In addition , you may have some rights , but may you don’t know that you should ask for it , for
example if you found some issues in the project design , and you informed the owner (or consultant)
with these issues , but he asked you to make the redesign or to suggest a proposal , although , your
contract does not include design works , So , if you are not aware of claim management you will do
that and carry this responsibility for free , Hence the importance of Claims Management
1 - Introduction
• As per PMI , claim is defined as :
• A request, demand, or assertion of rights , by the contractor against the
owner , or by the owner against the contractor , for consideration,
compensation, or payment under the terms of a legally binding contract, such
as for a disputed change.”
• In simple words , we can say that , claim is a request from one of contract parties to be
compensated due to occurrence of certain events
2 – Claim Definition
1 – Establish a strong Monitoring system
2 - Identify the root causes behind
claims occurrence
3 - Identify the claim type to determine
techniques that will be used
Event that
leads to claim
If you ask for Time conduct Delay
Analysis Techniques
If you ask for Cost conduct Cost
Analysis Techniques
Gather all supporting
documents
4 - Claim Preparation5 - Claim Settlement
3 – Claims Management Processes
Claim Approval
• What causes claims on construction projects?
• There are many kind of conflicts occur in construction industry between the
parties which mostly converts into the claims
• Understanding what causes construction claims is the first step in avoiding them.
• In general, There are many classifications of for construction claims reasons , For example
…..
4 – Causes of Construction Claims
• In 2003 (James Kerbs ) identifies possible claims reasons into 10 categories as follow
• Almost 46% of construction claims , resulted from design errors
Note That
4 – 1 - Classification according to (James E. Kerbs)
1 – Design errors and omissions 2 – Differing site conditions 3 – Contract changes
4 – Owner interference 5 – Poor subcontractor performance 6 – Schedule Delays
7 – Equipment / System failure 8 – Labor shortage 9 – Poor installation quality
10 – Construction accidents
• In 2001 (MPM Construction Engineering Group) found that the root causes of disputes are
universal for most projects , as follows
4 – 2 - Classification according to (MPM Construction Engineering Group)
1 – Uncertainty 2 – The Human element
3 – The significances changes 4 – Contract Limitations
• Claims due to contractor practices , in this case owner should
make a claim to be compensated .
• Claims due to owner practices , in this case contractor should
make a claim to be compensated .
Owner practices
Contractor practices
4 – 3 - Classification according to the responsible party
• For example , but not limited to
1 – Contractor failure to follow authorized procedures
2 – Poor planning and use of wrong equipment.
3 – Inadequate investigation before bidding.
4 – Delay in Supply of Shop Drawings.
5 – Contractor poor management and administration of the construction site .
4 – 3 - 1 - Causes due to contractor Practices
• For example , but not limited to
1 – Delay in Handing over the site
2 – Delay in payments .
3 – Inadequate Bid information.
4 – Change in work scope .
5 – Extra Items and variations.
6 – Owner poor management and administration of the construction site .
4 – 3 - 2 - Causes due to owner Practices
• We can divide reasons of construction claims according to the occurrence time , as follows .
2 – Claims during Construction Phase
1 – Claims during bidding phase
4 – 4 - Classification according to occurrence time
• For example , but not limited to
1 – Incomplete, Inaccurate, or Unclear Designs
2 – Deficient Site Investigation
3 – Insufficient Bid Time Allowance
4 – Ambiguous Plans and Specifications .
5 – Rejection of Bids .
7 – Unrealistic Scheduling Requirements .
6 - Lack of Communication with Subcontractors and Suppliers During the Bidding Stage
4 – 4 -1 Causes during Bidding Phase
• For example , but not limited to
1 – Lack of Control and Good Communication even by owner or contractor
2 – Changes in design and specification
3 – Force majeure
4 – Contractor failure to follow authorized procedures.
5 – Employer lack of construction knowledge.
7 – Delay in handing over of site from preceding contract work .
6 - Late notice to proceed or delay in making site available for next phase of work
4 – 4 -1 Causes during Construction Phase

More Related Content

What's hot

Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Michael Audu
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6Moustafa Ismail Abu Dief
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5Moustafa Ismail Abu Dief
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 

What's hot (20)

Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Claims
ClaimsClaims
Claims
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Contract management sys
Contract management sysContract management sys
Contract management sys
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Fidic
FidicFidic
Fidic
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 

Viewers also liked

WorkiQ Automation Solution Brief : Auto-Adjudication for Insurance Claims
WorkiQ Automation Solution Brief : Auto-Adjudication for Insurance ClaimsWorkiQ Automation Solution Brief : Auto-Adjudication for Insurance Claims
WorkiQ Automation Solution Brief : Auto-Adjudication for Insurance ClaimsOpenConnect
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
JDi Data Claims Management & Policy Administration System Overview
JDi Data Claims Management & Policy Administration System OverviewJDi Data Claims Management & Policy Administration System Overview
JDi Data Claims Management & Policy Administration System Overviewjdidata
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Antonio Coladarce
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Frank.
 
How Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant ManagementHow Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant ManagementPar Sut
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...HIMADRI BANERJI
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Bodman PLC
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control ChecklistAnand Subramaniam
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminarKegler Brown Hill + Ritter
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution ProcessC K Vishwakarma
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 

Viewers also liked (20)

WorkiQ Automation Solution Brief : Auto-Adjudication for Insurance Claims
WorkiQ Automation Solution Brief : Auto-Adjudication for Insurance ClaimsWorkiQ Automation Solution Brief : Auto-Adjudication for Insurance Claims
WorkiQ Automation Solution Brief : Auto-Adjudication for Insurance Claims
 
Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
JDi Data Claims Management & Policy Administration System Overview
JDi Data Claims Management & Policy Administration System OverviewJDi Data Claims Management & Policy Administration System Overview
JDi Data Claims Management & Policy Administration System Overview
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
Conference ANIMP & ECI Oct 2012 korean companies strategies for overseas cons...
 
Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016Thomas Koziarski Consulting brief presentation 2016
Thomas Koziarski Consulting brief presentation 2016
 
How Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant ManagementHow Economic Value Management can be Applied to Power Plant Management
How Economic Value Management can be Applied to Power Plant Management
 
Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...Assessment of Risks in International EPC Projects Reference Current Global Ec...
Assessment of Risks in International EPC Projects Reference Current Global Ec...
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Project Execution & Control Checklist
Project Execution & Control ChecklistProject Execution & Control Checklist
Project Execution & Control Checklist
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Claims management
Claims managementClaims management
Claims management
 
Construction claims management + project documentation seminar
Construction claims management + project documentation seminarConstruction claims management + project documentation seminar
Construction claims management + project documentation seminar
 
7 Steps Project Execution Process
7 Steps Project Execution Process7 Steps Project Execution Process
7 Steps Project Execution Process
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 

Similar to claims management framework

PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGCCordell Parvin
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
Civil Eng Assessment for Maintenance Management.pptx
Civil Eng Assessment for Maintenance Management.pptxCivil Eng Assessment for Maintenance Management.pptx
Civil Eng Assessment for Maintenance Management.pptxRajivDass1
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02jitendra kumar biswas
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx2ke21cv405
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in IndiaSanjay Kedia
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017Browne Jacobson LLP
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesGensol Engineering Limited
 

Similar to claims management framework (20)

PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Civil Eng Assessment for Maintenance Management.pptx
Civil Eng Assessment for Maintenance Management.pptxCivil Eng Assessment for Maintenance Management.pptx
Civil Eng Assessment for Maintenance Management.pptx
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
challenges of highway projects in India
challenges of highway projects in Indiachallenges of highway projects in India
challenges of highway projects in India
 
NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017NEC4 overview: key changes and impacts - Birmingham, September 2017
NEC4 overview: key changes and impacts - Birmingham, September 2017
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 

Recently uploaded

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfrs7054576148
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 

Recently uploaded (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 

claims management framework

  • 1. Chapter 1 : Claims Management Framework
  • 2. • Lets assume that during execution phase , you found some issues - not under your responsibility - in your project ,that will hinder your progress or incurring you extra costs , but don't know how to claim your rights , in that case you may loose your rights or may the work stopped completely . • In addition , you may have some rights , but may you don’t know that you should ask for it , for example if you found some issues in the project design , and you informed the owner (or consultant) with these issues , but he asked you to make the redesign or to suggest a proposal , although , your contract does not include design works , So , if you are not aware of claim management you will do that and carry this responsibility for free , Hence the importance of Claims Management 1 - Introduction
  • 3. • As per PMI , claim is defined as : • A request, demand, or assertion of rights , by the contractor against the owner , or by the owner against the contractor , for consideration, compensation, or payment under the terms of a legally binding contract, such as for a disputed change.” • In simple words , we can say that , claim is a request from one of contract parties to be compensated due to occurrence of certain events 2 – Claim Definition
  • 4. 1 – Establish a strong Monitoring system 2 - Identify the root causes behind claims occurrence 3 - Identify the claim type to determine techniques that will be used Event that leads to claim If you ask for Time conduct Delay Analysis Techniques If you ask for Cost conduct Cost Analysis Techniques Gather all supporting documents 4 - Claim Preparation5 - Claim Settlement 3 – Claims Management Processes Claim Approval
  • 5. • What causes claims on construction projects? • There are many kind of conflicts occur in construction industry between the parties which mostly converts into the claims • Understanding what causes construction claims is the first step in avoiding them. • In general, There are many classifications of for construction claims reasons , For example ….. 4 – Causes of Construction Claims
  • 6. • In 2003 (James Kerbs ) identifies possible claims reasons into 10 categories as follow • Almost 46% of construction claims , resulted from design errors Note That 4 – 1 - Classification according to (James E. Kerbs) 1 – Design errors and omissions 2 – Differing site conditions 3 – Contract changes 4 – Owner interference 5 – Poor subcontractor performance 6 – Schedule Delays 7 – Equipment / System failure 8 – Labor shortage 9 – Poor installation quality 10 – Construction accidents
  • 7. • In 2001 (MPM Construction Engineering Group) found that the root causes of disputes are universal for most projects , as follows 4 – 2 - Classification according to (MPM Construction Engineering Group) 1 – Uncertainty 2 – The Human element 3 – The significances changes 4 – Contract Limitations
  • 8. • Claims due to contractor practices , in this case owner should make a claim to be compensated . • Claims due to owner practices , in this case contractor should make a claim to be compensated . Owner practices Contractor practices 4 – 3 - Classification according to the responsible party
  • 9. • For example , but not limited to 1 – Contractor failure to follow authorized procedures 2 – Poor planning and use of wrong equipment. 3 – Inadequate investigation before bidding. 4 – Delay in Supply of Shop Drawings. 5 – Contractor poor management and administration of the construction site . 4 – 3 - 1 - Causes due to contractor Practices
  • 10. • For example , but not limited to 1 – Delay in Handing over the site 2 – Delay in payments . 3 – Inadequate Bid information. 4 – Change in work scope . 5 – Extra Items and variations. 6 – Owner poor management and administration of the construction site . 4 – 3 - 2 - Causes due to owner Practices
  • 11. • We can divide reasons of construction claims according to the occurrence time , as follows . 2 – Claims during Construction Phase 1 – Claims during bidding phase 4 – 4 - Classification according to occurrence time
  • 12. • For example , but not limited to 1 – Incomplete, Inaccurate, or Unclear Designs 2 – Deficient Site Investigation 3 – Insufficient Bid Time Allowance 4 – Ambiguous Plans and Specifications . 5 – Rejection of Bids . 7 – Unrealistic Scheduling Requirements . 6 - Lack of Communication with Subcontractors and Suppliers During the Bidding Stage 4 – 4 -1 Causes during Bidding Phase
  • 13. • For example , but not limited to 1 – Lack of Control and Good Communication even by owner or contractor 2 – Changes in design and specification 3 – Force majeure 4 – Contractor failure to follow authorized procedures. 5 – Employer lack of construction knowledge. 7 – Delay in handing over of site from preceding contract work . 6 - Late notice to proceed or delay in making site available for next phase of work 4 – 4 -1 Causes during Construction Phase

Editor's Notes

  1. 1 – Incomplete, Inaccurate, or Unclear Designs
  2. 1 – Incomplete, Inaccurate, or Unclear Designs