County of Fairfax, Virginia
Reston Funding Plan
Potential Sources of Revenue for Funding
Reston Transportation Improvements
Reston Network Analysis & Funding Plan Advisory Group
December 14, 2015
Janet Nguyen
Fairfax County Department of Transportation
County of Fairfax, Virginia
Reston Funding Plan
1. Overview
2. Status
3. Sources of Revenue
4. Tysons Cost Allocation Model
5. Next Steps
Department of Transportation
2
County of Fairfax, Virginia
Funding Plan Overview
Strategy for providing financial resources to pay for
transportation improvements in the Reston Phase I
Comprehensive Plan Amendment, Approved February 11,
2014.
•Years FY2015-FY2054 (40 years)
•Project priorities
•Project Cash Flows
•Cost allocations
Department of Transportation
3
County of Fairfax, Virginia
Status of Funding Plan
• Drafted:
– Projects list
– Preliminary cost estimates, in FY2015 dollars
– Potential revenue sources
• In Development:
– Project prioritization
– Cost allocations
Department of Transportation
4
County of Fairfax, Virginia
Transportation Improvement Categories
1. Reston-wide Improvements
– Road transportation improvements1
(Overpasses, Widenings,
Extensions, Interchanges) to enhance connectivity
– Intersection improvements required for adequate traffic
operations
1. Grid of local streets in Reston TSA areas
– Enhance pedestrian and vehicular circulation in, around, and
through, station areas
Department of Transportation
5
1
All roadways will be designed with pedestrian facilities. Many will also have bike facilities.
County of Fairfax, Virginia
Department of Transportation
6
Projects
Major Components of
Reston Phase I
Infrastructure:
Reston-Wide Projects,
$1.345B
•Roadway (Overpasses,
Widenings, Extensions,
Interchanges), $1.280B
•Intersection Projects,
$0.065B
Grid Network, $1.284B
Total $2.629B
County of Fairfax, Virginia
Shared Funding Solutions
Public and private investment in Reston is both critical and responsible for ensuring
Reston’s future success. While each solution is unique to the situation, there are a range
of transportation funding mechanisms available.
Public sector funding will come from federal, state, local, and regional sources.
•Multiple sources within each category
Private sector funding can come from:
•Proffers
•Cash contributions, Road Fund(per square foot/per dwelling unit contributions)
•In-kind Contributions
•Tax Districts/Service Districts and/or
•Other
Department of Transportation
7
County of Fairfax, Virginia
Public and Private Investment
Public and private sources of revenue identified to potentially
fund plan include the following:
•Existing and historical funding sources that have been allocated to
transportation projects
•Existing or potential funding sources available to Fairfax County, as
permitted by law
Department of Transportation
8
County of Fairfax, Virginia
Public | Federal Revenue Sources
Department of Transportation
9
Congestion Mitigation Air Quality (CMAQ)
•Primarily for capital projects that relieve congestion and improve air quality.
•Allocated and approved annually by the Northern Virginia Transportation Authority
(NVTA).
Regional Surface Transportation Program (RSTP)
•Can be used for many transportation capital improvements.
•Allocated and approved annually by NVTA.
Discretionary Grant Programs
•Competitive process, not a predictable source of revenue.
•Amount of funding varies by cycle.
•TIGER – Transportation Infrastructure Generating Economic Recovery.
•Allocated by USDOT.
County of Fairfax, Virginia
Public | Federal Revenue Sources
Department of Transportation
10
Attributes:
•Can provide lump sum of revenue.
•Can be used to leverage other sources of revenue.
•Can provide fairly flexible revenues, e.g., RSTP.
•Tend to increase overall project costs due to additional Federal requirements.
•Tend to lengthen overall project schedule to meet these requirements.
•Requires project funding agreements, which can be a lengthy process.
•Unreliable/Unpredictable due to competitive process for discretionary grants.
Source and Estimated Annual Allocation to County
Congestion Mitigation Air Quality (CMAQ) $14M
Regional Surface Transportation Program (RSTP) $18M
Discretionary Grant Programs $N/A
Total Estimated Annual Allocation to County $32M
County of Fairfax, Virginia
Public | State Revenues Sources
Revenue Sharing
•Can be used for many transportation capital improvements.
•Requires 100% local cash match.
•Between $15 million and $200 million can be allocated and approved annually
by the CTB.
•Limited availability, $10M max application per locality per year.
•The state has allocated approximately $180 million for the program in FY 2016
and has proposed reducing the funding over the next five years:
– $150 million in FY 2017
– $100 million in FY 2018 and 2019
– $50 million in FY 2020 and 2021
Department of Transportation
11
County of Fairfax, Virginia
Public | State Revenues Sources
HB2 and HB1887
HB 2 provides for the development of a prioritization process for projects funded by the
Commonwealth Transportation Board (CTB).
•Considers congestion mitigation, economic development, accessibility, safety, and environmental
quality.
•CTB weights these factors for each of Virginia’s transportation districts and can assign different
weights to the factors for various regions.
•Congestion mitigation must be weighted highest in Northern Virginia and Hampton Roads.
HB 1887 created a new funding formula for the Commonwealth’s roadway construction projects:
•45% of the funding goes to state of good repair.
•27.5% of the funding goes to statewide high-priority projects program (projects of statewide
importance that will be evaluated and selected using the HB2 process).
•27.5% of the funding to highway construction district grant programs (localities would compete for
funds under a regional version of the HB2 process).
The County submits applications for both Statewide and District Grant programs, in accordance with
Board priorities and the Programs’ requirements.
Department of Transportation
12
County of Fairfax, Virginia
Public | State Revenue Sources
Department of Transportation
13
Source and Estimated Annual Allocation to County
Revenue Sharing $10
(HB2/HB1887) Statewide High Priority Projects Program (HPPP) $N/A
(HB2/HB1887) Construction District Grant Program (CDGP) $N/A
Total Estimated Annual Allocation to County $10
Attributes:
•HB 2/HB1887 programs unpredictable due to competitive project selection process.
•Can provide large sums of revenue, e.g. HB2/HB1887
•Can be used to leverage other sources of revenue, e.g. HB2/HB1887, Revenue Sharing.
•Proposed reduction in Revenue Sharing funds may make it more difficult for County to
receive the same amount of funding as in years past.
•Use of State funds requires project funding agreements, which can be a lengthy process.
County of Fairfax, Virginia
Public | Local Revenue Sources
Department of Transportation
14
General Fund
•The General Fund is the County’s primary operating fund and supports all general
purpose functions in the County.
•Revenues derived mostly through real property and personal property taxes.
•Significant portion of General Fund revenues are transferred to finance other county
priorities, the public schools (FCPS), human services, public safety, and debt service
among other things.
Attributes:
•Currently, transfers are primarily for transit projects
•FY 2016 Transfers:
– County Transit $34.5M;
– Metro $11.3M;
– Transportation $7.8M;
– debt-service on transportation related G.O. Bonds N/A.
Source and Estimated Annual Revenue to County
General Fund Transfers to Transportation FY2016 $53.6M
County of Fairfax, Virginia
Public | Local Revenue Sources
Department of Transportation
15
Commercial and Industrial (C&I) Taxes
•For projects that increase transportation capacity.
•Currently set at $0.125/$100 assessed value on commercial and industrial
properties.
•Generates approximately $50M annually
•Allocated by the Board.
Attributes:
•Reliable source of revenue
•Flexible source of revenue and can be easily shifted between projects.
•Must be used to increase capacity.
Source and Estimated Annual Allocation or Revenue to County
Commercial and Industrial (C&I) Taxes $52M
County of Fairfax, Virginia
Public | Local Revenue Sources
Department of Transportation
16
General Obligation (G.O.) Bonds
•Form of long-term borrowing to help finance public facilities.
•Enacted/Approved by referendum.
• In 2014, $100M transportation bond was approved – bicycle, pedestrian, and spot
projects. Projects proposed for bond funding were identified through extensive public
outreach and engagement, called the Countywide Dialogue on Transportation.
•Allocated by the Board.
Attributes:
•Reliable source of revenue.
•Creates long-term future obligation to the county, debt-service.
•Proceeds of bond sales must be used for purpose specified in the referendum question.
•Bond program is not designed to contribute to an increase in tax rate.
Source and Estimated Annual Allocation or Revenue to County
G.O. Bonds $20M
County of Fairfax, Virginia
Public | Local/Regional Revenue Sources
HB2313
Provides approximately $300 million per year to regional transportation by:
•Increasing Northern Virginia sales tax by 0.7%, for total of 6%
•2% Transient Occupancy Tax (hotel tax)
•Imposes a Congestion Relief Fee (grantors tax) of $0.15 per $100 valuation
All of the taxes and fees collected under HB 2313 are sent to the Northern Virginia
Transportation Authority (NVTA). Dollars are divided into one of two categories:
•NVTA 30% Local Distribution Funds
•NVTA 70% Regional Revenue Funds
Department of Transportation
17
County of Fairfax, Virginia
Public | Local Revenue Sources
HB2313 - NVTA 30% Local Distribution Funds
•30% of funds will be distributed to the individual localities on pro-rata basis for
transportation.
•Must be spent on: urban or secondary road construction; capital improvements that
reduce congestion; projects included in NVTA’s long-range plan; or for public
transportation purposes.
•Distributed monthly to the County from NVTA; County receives about $45 million
annually.
•Allocated to projects by the County Board.
Attributes:
•Reliable sources of revenue.
•Flexible source of revenue and can be shifted between projects to optimize availability of
funding.
Department of Transportation
18
Source and Estimated Annual Allocation or Revenue to County
NVTA 30% Local Distribution Funds $45M
County of Fairfax, Virginia
Public | Regional Revenue Sources
HB2313 - NVTA 70% Regional Revenue Funds
•70% will be provided to the Northern Virginia Transportation Authority (NVTA) to be used on:
– Regional projects included in TransAction 2040 or its updates; and
– Projects evaluated by VDOT for reducing congestion as required by HB 599 (2012)
– NVTA must give priority to selecting projects that are expected to provide the greatest
congestion reduction relative to cost of the project
•Approximately $200 million available to be allocated by NVTA each year.
Attributes:
•Can provide large and small sums of revenue.
•Competitive process; NVTA 70% not guaranteed due to limited amount of funds available relating to
amount requested.
•Over the long-term, each locality’s total long-term benefit must be approximately equal to the
proportion of the total of the regional fees and taxes attributable to the locality.
•Projects must meet specific requirements to be eligible (no maintenance, inclusion in regional plan,
etc.)
Department of Transportation
19
County of Fairfax, Virginia
Public | Other Revenues
Sales Tax: Local (Northern Virginia) sales tax rate is 6%
•General sales tax rate for VA is 5.3 percent
•Additional 0.7 percent state tax is imposed in localities in Northern Virginia for
transportation; sent to NVTA to be distributed via NVTA 30% Local and NVTA 70%
Regional Funds. The County generated roughly $106.4M from the additional 0.7 percent
tax for transportation in FY2015.
•Requires Virginia General Assembly authorization to increase the current rate.
Gas Tax: Regional gas tax of 2.1 percent on wholesale gas sales in Northern Virginia.
•These funds are collected by the Northern Virginia Transportation Commission (NVTC)
and distributed directly to the Washington Metropolitan Area Transit Authority (WMATA)
on behalf of Fairfax County.
•Covers portion of County’s subsidy for Metro operations, about $24.8M annually.
•Requires Virginia General Assembly authorization to increase the current rate.
Department of Transportation
20
County of Fairfax, Virginia
Public | Other Revenues
Real-estate tax (base rate): $1.09/$100 assessed value; Board of Supervisors has
authority to annually amend and adopt a new tax rate. An increase of 1 cent could
generate approximately $22M in additional revenues in FY2016.
Car Tax/Personal property tax: $4.57 per $100 of assessed value; Board of
Supervisors has authority to amend and adopt a new tax rate. An increase of 1 cent
could generate approximately $800k in additional revenues in FY2016.
Hotel and motel tax: 6% (2% general transient occupancy tax, 2% for tourism, and 2%
transient occupancy tax for regional transportation (HB2313)). General Assembly
authorization required to increase.
Grantor’s Tax: $0.15 per $100 of value on deeds (for transportation HB2313). General
Assembly authorization required to increase.
Department of Transportation
21
County of Fairfax, Virginia
Public | Other Revenues
Meals Tax
•Tax on prepared food and beverages at restaurants, cafes, coffee shops, etc.
•Counties in Virginia are limited to a rate of up to 4 percent.
•Tax would be in addition to the state’s sales tax (6 percent).
•Virginia law requires voter referendum to levy meals tax.
•Revenues can be earmarked to a specific purpose.
Sales tax on service: currently no sales tax on services in Fairfax County; requires General
Assembly authorization to enact.
Parking fees: currently no fees on county owned parking lots that charge for parking; requires
approval for parking lots and on street parking.
Local income tax: income taxes are collected by the state. The power to enact a 1% local income
tax via referendum was repealed by HB2313. An additional local income tax would require General
Assembly authorization to enact.
Vehicles Miles Traveled (VMT): Tax on miles traveled by vehicles registered in Fairfax County. The
County currently does not have a fee on VMT. This would affect businesses and residents with
vehicles registered in Fairfax County. Requires General Assembly authorization to enact.
Department of Transportation
22
Potential Annual Revenue to County
Meals Tax at 1% rate $22.5M*
Meals Tax at 4% rate $90M*
*Based on calendar year 2013 taxable sales at
Food and Drink Places in Fairfax County
County of Fairfax, Virginia
Public Sources of Revenue
Estimated annual public funds to County for transportation, County-wide from sources discussed:
However, public funding for Reston Funding Plan projects may not be readily available until
FY2021:
•Most of the public sources of revenue have already been committed to projects in the Board’s Six
Year Transportation Project Priorities (TPP) for FY2015-FY2020, which includes about $12.5M for
DTR overpasses (planning level funding only) that are included in the Reston Funding Plan.
•Fairfax County bond packages are planned to fund specific projects. This means that all previous
bond authorizations were planned for or are obligated to specific projects.
•Even after FY2021, public funds for transportation must be programmed to projects throughout
County. Example: Some of the public sources have been committed to the Tysons funding plan
through 2050 or projects initiated during FY2015-2020 timeframe.
Additional funding from private sources of revenue required to fully fund projects in Reston.
Department of Transportation
23
Federal $32,000,000
State $10,000,000
Regional $90,000,000
Local $171,000,000
Total Estimated Annual Public
Funds to County for Transportation $303,000,000
County of Fairfax, Virginia
Private | Proffers/Contributions
Proffers
•Voluntary commitment by landowners/developers to perform an act or to donate money,
land, services or products to address/offset impact(s) arising from their proposed
rezoning.
Proffers may be offered to offset public facility costs via two methods:
1.Cash Proffer: money voluntarily proffered in a writing signed by the owner of property
subject to rezoning, submitted as part of a rezoning application.
– Funding can be pooled from multiple rezonings to fund one or more projects e.g.
Road Fund.
1.In-kind Contribution: projects completed by the developer seeking rezoning;
– On-Site: Improvements directly connected and/or needed for redevelopment.
– Off-Site: Improvements not directly connected and/or needed for redevelopment.
Department of Transportation
24
County of Fairfax, Virginia
Private | Road Fund/In-Kind Contributions
Example: Developers provide in-kind contributions and contribute to two funds to pay for
Tysons improvements over 40 years.
Grid of Streets ($865M) – Will be paid entirely by developers through:
•Tysons Grid of Streets Contributions Fund ($304M): per gross square foot (gsf) or
per dwelling unit contribution
•In-kind Contributions ($561): Developers may elect to construct transportation
improvements outlined in Tysons guidelines in lieu of cash contributions, as negotiated in
individual proffer agreements.
Tysons-Wide Road Improvements – Developers pay for majority of projects inside
Tysons and a portion of projects outside of Tysons ($506M):
•Tysons-Wide Developer Contributions Fund ($253M): per gsf or per dwelling unit
contribution
•Tysons Service District ($253M)
Department of Transportation
25
County of Fairfax, Virginia
Private | Service District
Service District:
•Fund transportation improvements located within a defined geographic area.
•Does not require landowner approval, approved and established by the Board of Supervisors.
•Tysons Service District will fund approximately $253M worth of improvements or 50 percent of
Tysons-Wide Road Improvements. Rate in FY2016 is $0.05 per $100 of assessed real estate value.
Boundary is generally consistent with the Tysons Corner Urban Center.
Attributes:
•Reliable source of revenue
•Bondable
•Applies to both residential and commercial property
•Imposed by the Board of Supervisors
Department of Transportation
26
Source Potential Revenue FY17
Example Reston Service District @ $0.01
•Estimate using FY15 Assessed Values for properties in Reston TSAs
•Assumes 3% annual growth in assessed value
$0.8M
For example
purposes only.
County of Fairfax, Virginia
Private | Tax District
Tax District
•Voluntary petition of landowners and approved by the Board of Supervisors.
•Fund large projects in a defined geographic area.
•Route 28 Transportation Tax District:1987 two-county district for specific purpose of
widening the major arterial in a largely undeveloped area. Rate in FY2016 is $0.18 per
$100 of assessed value of commercial and industrial property. Revenues estimated to
be $11M in FY2016.
•Dulles Rail Phase 1: $400M; Dulles Rail Phase II: $330M.
Attributes:
•Reliable source of revenue
•Bondable
•Self-imposed
Department of Transportation
27
Source Potential Revenue FY17
Example Reston Tax District @ $0.01
•Estimate using FY15 Assessed Values for non-residential (including
commercial residential(apartment))properties in Reston TSAs
•Assumes 3% annual growth in assessed value
$0.6M
For example
purposes only.
County of Fairfax, Virginia
Tysons Model
Major redevelopment over the next 40 years to capitalize on the four Metro
stations in Tysons and transform Tysons into a transit-oriented mixed-use
urban center.
A funding plan was developed to pay for $3.1B transportation improvements in
Tysons to support development with public and private sectors sharing
responsibility for cost of improvements.
Components of Tysons Infrastructure:
1.Grid of Streets
2.Tysons-wide Improvements
3.Neighborhood and Access Improvements
4.Transit
Department of Transportation
28
Cr. Tysons Partnership
County of Fairfax, Virginia
Tysons Cost Allocation Model
Components of Tysons Infrastructure Relevant to the Reston Funding Plan:
1. Grid of Streets – private sources (landowners/developers)
I. Grid of Streets Road Fund: Per square foot/per unit road fund
II. In-kind contributions
2. Tysons-wide Road Improvements
I. Outside of Tysons boundaries – primarily public sources
II. Inside of Tysons boundaries – primarily private
• Tysons-wide Road Fund: Per square foot/per unit road fund contributions
• Tysons Service District
Department of Transportation
29
County of Fairfax, Virginia
Tysons Grid Cost Allocation Model
Grid of Streets
Projects: Improvements to transform superblock network to more urban model
Total: $865,000,000
Funding: Paid for entirely by developers through In-kind contributions and a Grid “Road
Fund”
Department of Transportation
30
Grid of Streets Rate FY2016 Estimated Total Need, $865M
In-kind Contributions N/A $561M
Grid “Road Fund” $304M
• Per Sq. Ft. Commercial Property $6.71
• Per Unit of Residential Property $1,042
County of Fairfax, Virginia
Tysons-wide Cost Allocation Model
In June 2010, staff recommended to the Tysons sub-committee a cost allocation based
on local and through traffic as follows:
Tysons-wide project costs should be a shared responsibility between the public and
private sectors.
The cost share should be allocated based upon the ratio of through (35%) and local
(65%) traffic volumes of 2030 Tysons projects.
Private responsibility: ½ of local traffic generated (32.5%)
Public responsibility: All of through traffic (35%) and ½ of local traffic generated (32.5%)
Cost Split for Tysons-wide Projects ($810M):
Private Sector 32.5% ($263M)
Public Sector 67.5% ($547M)
Department of Transportation
31
County of Fairfax, Virginia
Tysons-wide Cost Allocation Model
In December 2010, the updated funding plan for 2050 included
additional projects totaling $1.208B.
•The Tysons sub-committee recommended a more equitable cost
allocation model that also included 2050 projects.
•Staff worked in cooperation with the Tysons Partnership over many
meetings arrived at a cost allocation model based on a 90/10 split
(discussed in the next slide).
•In June 2012, staff returned to the sub-committee with the 90/10 split
allocation (discussed in next slide), which the sub-committee
determined to be a correct basis for an appropriate allocation.
Department of Transportation
32
County of Fairfax, Virginia
Tysons-wide Cost Allocation Model
Tysons-wide Road Improvements
Projects: These are larger projects, such as new ramps, new roads, and
widening existing roads.
Total: $1,208,000,000
Department of Transportation
33
($mil) Public Private Total Public (%) Private (%)
Outside
Tysons
$653 $73 $726 90% 10%
Inside
Tysons
$48 $434 $482 10% 90%
Total $701 $506 $1208 100% 100%
Share 58% 42%
County of Fairfax, Virginia
Tysons Cost Allocation Model
Tysons-Wide Transportation Fund (Private – Landowner/Developer
contributions) ($506M):
•“Road Fund” ($253) - Developer contributions to a per sq. ft./per unit fund
– Rates are subject to annual inflation adjustment based on CPI
•Service district ($253)
– “Modified Bell Curve” model to meet $253M need.
– Rates: $0.04 in FY 2014, $0.04 in FY 2015, and $0.05 in FY 2016.
– Increases to $0.07 later in Tysons funding plan.
Department of Transportation
34
Tysons-Wide Transportation Fund Rate FY2016 Estimated Total Need, $506M
Service District $0.05 $253M
Road Fund $253M
• Per Sq. Ft. Commercial Property $5.87
• Per Unit of Residential Property $1042
County of Fairfax, Virginia
Tysons Transportation Funding Allocation
County of Fairfax, Virginia
Reston Potential Cost Allocation
• Reston-wide Improvements ($1.345B)
– Outside/Inside
– Outside to be primarily funded by public sector
– Inside to be primarily funded by private sector
contributions
• Grid Network ($1.284B)
– Primarily funded by private sector contributions
• Total funding plan: $2.629 B
Department of Transportation
36
County of Fairfax, Virginia
Next Steps
• Advisory group feedback on potential revenue sources,
including others that should be evaluated
• Development of proposed funding plan to include cost
allocations between public and private sector
• Outreach to stakeholders and public
• Revise plan based on feedback received
• Share proposed funding plan with Board Transportation
Committee
• Seek Board of Supervisors approval
County of Fairfax, Virginia
Comments/Questions?
Department of Transportation
38
County of Fairfax, Virginia
Contact Information
For questions and comments please contact:
Janet Nguyen
Janet.Nguyen@fairfaxcounty.gov
Ray Johnson
Carroll.Johnson@fairfaxcounty.gov

More Related Content

What's hot

Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax County
 
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Fairfax County
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Fairfax County
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilityFairfax County
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Fairfax County
 
Reston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseReston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseFairfax County
 
Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County
 
North Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement StudyNorth Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement StudyFairfax County
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Reston Transportation Funding Plan: Dec. 19, 2016
Reston Transportation Funding Plan: Dec. 19, 2016Reston Transportation Funding Plan: Dec. 19, 2016
Reston Transportation Funding Plan: Dec. 19, 2016Fairfax County
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingFairfax County
 
Agenda Item 3: TPB Long-Range Plan Unfunded Transportation Projects
Agenda Item 3: TPB Long-Range Plan Unfunded Transportation ProjectsAgenda Item 3: TPB Long-Range Plan Unfunded Transportation Projects
Agenda Item 3: TPB Long-Range Plan Unfunded Transportation ProjectsFairfax County
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes ExtensionFairfax County
 
Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...
Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...
Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...Fairfax County
 
Policy on Level of Service in Activity Centers
Policy on Level of Service in Activity CentersPolicy on Level of Service in Activity Centers
Policy on Level of Service in Activity CentersFairfax County
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County
 

What's hot (20)

Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
 
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
Reston Transportation Funding Plan-Updates and Funding Scenarios: Sept. 12, 2016
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
Reston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseReston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open House
 
Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2
 
North Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement StudyNorth Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement Study
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Reston Transportation Funding Plan: Dec. 19, 2016
Reston Transportation Funding Plan: Dec. 19, 2016Reston Transportation Funding Plan: Dec. 19, 2016
Reston Transportation Funding Plan: Dec. 19, 2016
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public Meeting
 
Agenda Item 3: TPB Long-Range Plan Unfunded Transportation Projects
Agenda Item 3: TPB Long-Range Plan Unfunded Transportation ProjectsAgenda Item 3: TPB Long-Range Plan Unfunded Transportation Projects
Agenda Item 3: TPB Long-Range Plan Unfunded Transportation Projects
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes Extension
 
Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...
Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...
Reston Transportation Funding Plan: Public Meeting Summary and Advisory Group...
 
Policy on Level of Service in Activity Centers
Policy on Level of Service in Activity CentersPolicy on Level of Service in Activity Centers
Policy on Level of Service in Activity Centers
 
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
Braddock Road Multimodal Study-Guinea Road to I-495: Community Meeting No. 3:...
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
Fairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction UpdateFairfax County and the NVTA TransAction Update
Fairfax County and the NVTA TransAction Update
 

Viewers also liked

Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare ProgramFairfax County
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the BeltwayFairfax County
 
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4Fairfax County
 
Emergency Vehicle Preemption
Emergency Vehicle PreemptionEmergency Vehicle Preemption
Emergency Vehicle PreemptionFairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of CountywideDialogue on Transportation:Project SelectionA Si...Continuation of CountywideDialogue on Transportation:Project SelectionA Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Fairfax County
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramFairfax County
 
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Fairfax County
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Fairfax County
 
Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Fairfax County
 
Fairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax County
 
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016  Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016 Fairfax County
 
Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016   Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016 Fairfax County
 
Transportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public CommentTransportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public CommentFairfax County
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare ProgramFairfax County
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Fairfax County
 
Reston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsReston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsFairfax County
 
Fairfax County Comprehensive Transit Plan and Transit Development Plan
Fairfax County Comprehensive Transit Plan and Transit Development PlanFairfax County Comprehensive Transit Plan and Transit Development Plan
Fairfax County Comprehensive Transit Plan and Transit Development PlanFairfax County
 
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementI-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementFairfax County
 

Viewers also liked (20)

Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare Program
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the Beltway
 
Protective Helmets
Protective HelmetsProtective Helmets
Protective Helmets
 
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
 
Emergency Vehicle Preemption
Emergency Vehicle PreemptionEmergency Vehicle Preemption
Emergency Vehicle Preemption
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of CountywideDialogue on Transportation:Project SelectionA Si...Continuation of CountywideDialogue on Transportation:Project SelectionA Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light Program
 
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
 
Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016
 
Fairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory Committee
 
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016  Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
 
Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016   Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016
 
Transportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public CommentTransportation Alternatives Program Workshop and Public Comment
Transportation Alternatives Program Workshop and Public Comment
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare Program
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
 
Reston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost AllocationsReston Funding Plan: Potential Cost Allocations
Reston Funding Plan: Potential Cost Allocations
 
Fairfax County Comprehensive Transit Plan and Transit Development Plan
Fairfax County Comprehensive Transit Plan and Transit Development PlanFairfax County Comprehensive Transit Plan and Transit Development Plan
Fairfax County Comprehensive Transit Plan and Transit Development Plan
 
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementI-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
 

Similar to Reston Funding Plan

Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
Status of Transportation Priorities Plan Update
Status of Transportation Priorities Plan UpdateStatus of Transportation Priorities Plan Update
Status of Transportation Priorities Plan UpdateFairfax County
 
Status of Transportation Priorities Plan Update: Board Transportation Committ...
Status of Transportation Priorities Plan Update: Board Transportation Committ...Status of Transportation Priorities Plan Update: Board Transportation Committ...
Status of Transportation Priorities Plan Update: Board Transportation Committ...Fairfax County
 
ROUTES: USDOT’s New Rural Transportation Initiative
ROUTES: USDOT’s New Rural Transportation InitiativeROUTES: USDOT’s New Rural Transportation Initiative
ROUTES: USDOT’s New Rural Transportation Initiativenado-web
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationFairfax County
 
Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)Fairfax County
 
PLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewPLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewMelissaARC
 
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Fairfax County
 
Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016Fairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...Fairfax County
 
Fairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesFairfax County
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Fairfax County
 
Transportation Infrastructure FInancing and Value Capture
Transportation Infrastructure FInancing and Value CaptureTransportation Infrastructure FInancing and Value Capture
Transportation Infrastructure FInancing and Value CaptureRPO America
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017Fairfax County
 
Accessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve InfrastructureAccessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve InfrastructureParsons Behle & Latimer
 
What State & Local Governments Need to Know About the American Rescue Plan Ac...
What State & Local Governments Need to Know About the American Rescue Plan Ac...What State & Local Governments Need to Know About the American Rescue Plan Ac...
What State & Local Governments Need to Know About the American Rescue Plan Ac...Dustin Haisler
 
Artba Senate Summary
Artba Senate SummaryArtba Senate Summary
Artba Senate Summaryartba
 

Similar to Reston Funding Plan (20)

Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
Status of Transportation Priorities Plan Update
Status of Transportation Priorities Plan UpdateStatus of Transportation Priorities Plan Update
Status of Transportation Priorities Plan Update
 
Status of Transportation Priorities Plan Update: Board Transportation Committ...
Status of Transportation Priorities Plan Update: Board Transportation Committ...Status of Transportation Priorities Plan Update: Board Transportation Committ...
Status of Transportation Priorities Plan Update: Board Transportation Committ...
 
ROUTES: USDOT’s New Rural Transportation Initiative
ROUTES: USDOT’s New Rural Transportation InitiativeROUTES: USDOT’s New Rural Transportation Initiative
ROUTES: USDOT’s New Rural Transportation Initiative
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on Transportation
 
Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)Update of Fairfax County's Transportation Priorities Plan (TPP)
Update of Fairfax County's Transportation Priorities Plan (TPP)
 
PLAN 2040 RTP Update Overview
PLAN 2040 RTP Update OverviewPLAN 2040 RTP Update Overview
PLAN 2040 RTP Update Overview
 
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
Reston Transportation Funding Plan: Updates and Recommendation-Community Meet...
 
Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages : Herndo...
 
Surface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & IssuesSurface Transportation - Finance Context & Issues
Surface Transportation - Finance Context & Issues
 
Fairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for Transportation
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future Updates
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
 
Transportation Infrastructure FInancing and Value Capture
Transportation Infrastructure FInancing and Value CaptureTransportation Infrastructure FInancing and Value Capture
Transportation Infrastructure FInancing and Value Capture
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 13, 2017
 
Accessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve InfrastructureAccessing BUILD Grants to Improve Infrastructure
Accessing BUILD Grants to Improve Infrastructure
 
What State & Local Governments Need to Know About the American Rescue Plan Ac...
What State & Local Governments Need to Know About the American Rescue Plan Ac...What State & Local Governments Need to Know About the American Rescue Plan Ac...
What State & Local Governments Need to Know About the American Rescue Plan Ac...
 
Artba Senate Summary
Artba Senate SummaryArtba Senate Summary
Artba Senate Summary
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxSasikiranMarri
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptUsmanKaran
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxunark75
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 

Recently uploaded (9)

15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptx
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.ppt
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptx
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 

Reston Funding Plan

  • 1. County of Fairfax, Virginia Reston Funding Plan Potential Sources of Revenue for Funding Reston Transportation Improvements Reston Network Analysis & Funding Plan Advisory Group December 14, 2015 Janet Nguyen Fairfax County Department of Transportation
  • 2. County of Fairfax, Virginia Reston Funding Plan 1. Overview 2. Status 3. Sources of Revenue 4. Tysons Cost Allocation Model 5. Next Steps Department of Transportation 2
  • 3. County of Fairfax, Virginia Funding Plan Overview Strategy for providing financial resources to pay for transportation improvements in the Reston Phase I Comprehensive Plan Amendment, Approved February 11, 2014. •Years FY2015-FY2054 (40 years) •Project priorities •Project Cash Flows •Cost allocations Department of Transportation 3
  • 4. County of Fairfax, Virginia Status of Funding Plan • Drafted: – Projects list – Preliminary cost estimates, in FY2015 dollars – Potential revenue sources • In Development: – Project prioritization – Cost allocations Department of Transportation 4
  • 5. County of Fairfax, Virginia Transportation Improvement Categories 1. Reston-wide Improvements – Road transportation improvements1 (Overpasses, Widenings, Extensions, Interchanges) to enhance connectivity – Intersection improvements required for adequate traffic operations 1. Grid of local streets in Reston TSA areas – Enhance pedestrian and vehicular circulation in, around, and through, station areas Department of Transportation 5 1 All roadways will be designed with pedestrian facilities. Many will also have bike facilities.
  • 6. County of Fairfax, Virginia Department of Transportation 6 Projects Major Components of Reston Phase I Infrastructure: Reston-Wide Projects, $1.345B •Roadway (Overpasses, Widenings, Extensions, Interchanges), $1.280B •Intersection Projects, $0.065B Grid Network, $1.284B Total $2.629B
  • 7. County of Fairfax, Virginia Shared Funding Solutions Public and private investment in Reston is both critical and responsible for ensuring Reston’s future success. While each solution is unique to the situation, there are a range of transportation funding mechanisms available. Public sector funding will come from federal, state, local, and regional sources. •Multiple sources within each category Private sector funding can come from: •Proffers •Cash contributions, Road Fund(per square foot/per dwelling unit contributions) •In-kind Contributions •Tax Districts/Service Districts and/or •Other Department of Transportation 7
  • 8. County of Fairfax, Virginia Public and Private Investment Public and private sources of revenue identified to potentially fund plan include the following: •Existing and historical funding sources that have been allocated to transportation projects •Existing or potential funding sources available to Fairfax County, as permitted by law Department of Transportation 8
  • 9. County of Fairfax, Virginia Public | Federal Revenue Sources Department of Transportation 9 Congestion Mitigation Air Quality (CMAQ) •Primarily for capital projects that relieve congestion and improve air quality. •Allocated and approved annually by the Northern Virginia Transportation Authority (NVTA). Regional Surface Transportation Program (RSTP) •Can be used for many transportation capital improvements. •Allocated and approved annually by NVTA. Discretionary Grant Programs •Competitive process, not a predictable source of revenue. •Amount of funding varies by cycle. •TIGER – Transportation Infrastructure Generating Economic Recovery. •Allocated by USDOT.
  • 10. County of Fairfax, Virginia Public | Federal Revenue Sources Department of Transportation 10 Attributes: •Can provide lump sum of revenue. •Can be used to leverage other sources of revenue. •Can provide fairly flexible revenues, e.g., RSTP. •Tend to increase overall project costs due to additional Federal requirements. •Tend to lengthen overall project schedule to meet these requirements. •Requires project funding agreements, which can be a lengthy process. •Unreliable/Unpredictable due to competitive process for discretionary grants. Source and Estimated Annual Allocation to County Congestion Mitigation Air Quality (CMAQ) $14M Regional Surface Transportation Program (RSTP) $18M Discretionary Grant Programs $N/A Total Estimated Annual Allocation to County $32M
  • 11. County of Fairfax, Virginia Public | State Revenues Sources Revenue Sharing •Can be used for many transportation capital improvements. •Requires 100% local cash match. •Between $15 million and $200 million can be allocated and approved annually by the CTB. •Limited availability, $10M max application per locality per year. •The state has allocated approximately $180 million for the program in FY 2016 and has proposed reducing the funding over the next five years: – $150 million in FY 2017 – $100 million in FY 2018 and 2019 – $50 million in FY 2020 and 2021 Department of Transportation 11
  • 12. County of Fairfax, Virginia Public | State Revenues Sources HB2 and HB1887 HB 2 provides for the development of a prioritization process for projects funded by the Commonwealth Transportation Board (CTB). •Considers congestion mitigation, economic development, accessibility, safety, and environmental quality. •CTB weights these factors for each of Virginia’s transportation districts and can assign different weights to the factors for various regions. •Congestion mitigation must be weighted highest in Northern Virginia and Hampton Roads. HB 1887 created a new funding formula for the Commonwealth’s roadway construction projects: •45% of the funding goes to state of good repair. •27.5% of the funding goes to statewide high-priority projects program (projects of statewide importance that will be evaluated and selected using the HB2 process). •27.5% of the funding to highway construction district grant programs (localities would compete for funds under a regional version of the HB2 process). The County submits applications for both Statewide and District Grant programs, in accordance with Board priorities and the Programs’ requirements. Department of Transportation 12
  • 13. County of Fairfax, Virginia Public | State Revenue Sources Department of Transportation 13 Source and Estimated Annual Allocation to County Revenue Sharing $10 (HB2/HB1887) Statewide High Priority Projects Program (HPPP) $N/A (HB2/HB1887) Construction District Grant Program (CDGP) $N/A Total Estimated Annual Allocation to County $10 Attributes: •HB 2/HB1887 programs unpredictable due to competitive project selection process. •Can provide large sums of revenue, e.g. HB2/HB1887 •Can be used to leverage other sources of revenue, e.g. HB2/HB1887, Revenue Sharing. •Proposed reduction in Revenue Sharing funds may make it more difficult for County to receive the same amount of funding as in years past. •Use of State funds requires project funding agreements, which can be a lengthy process.
  • 14. County of Fairfax, Virginia Public | Local Revenue Sources Department of Transportation 14 General Fund •The General Fund is the County’s primary operating fund and supports all general purpose functions in the County. •Revenues derived mostly through real property and personal property taxes. •Significant portion of General Fund revenues are transferred to finance other county priorities, the public schools (FCPS), human services, public safety, and debt service among other things. Attributes: •Currently, transfers are primarily for transit projects •FY 2016 Transfers: – County Transit $34.5M; – Metro $11.3M; – Transportation $7.8M; – debt-service on transportation related G.O. Bonds N/A. Source and Estimated Annual Revenue to County General Fund Transfers to Transportation FY2016 $53.6M
  • 15. County of Fairfax, Virginia Public | Local Revenue Sources Department of Transportation 15 Commercial and Industrial (C&I) Taxes •For projects that increase transportation capacity. •Currently set at $0.125/$100 assessed value on commercial and industrial properties. •Generates approximately $50M annually •Allocated by the Board. Attributes: •Reliable source of revenue •Flexible source of revenue and can be easily shifted between projects. •Must be used to increase capacity. Source and Estimated Annual Allocation or Revenue to County Commercial and Industrial (C&I) Taxes $52M
  • 16. County of Fairfax, Virginia Public | Local Revenue Sources Department of Transportation 16 General Obligation (G.O.) Bonds •Form of long-term borrowing to help finance public facilities. •Enacted/Approved by referendum. • In 2014, $100M transportation bond was approved – bicycle, pedestrian, and spot projects. Projects proposed for bond funding were identified through extensive public outreach and engagement, called the Countywide Dialogue on Transportation. •Allocated by the Board. Attributes: •Reliable source of revenue. •Creates long-term future obligation to the county, debt-service. •Proceeds of bond sales must be used for purpose specified in the referendum question. •Bond program is not designed to contribute to an increase in tax rate. Source and Estimated Annual Allocation or Revenue to County G.O. Bonds $20M
  • 17. County of Fairfax, Virginia Public | Local/Regional Revenue Sources HB2313 Provides approximately $300 million per year to regional transportation by: •Increasing Northern Virginia sales tax by 0.7%, for total of 6% •2% Transient Occupancy Tax (hotel tax) •Imposes a Congestion Relief Fee (grantors tax) of $0.15 per $100 valuation All of the taxes and fees collected under HB 2313 are sent to the Northern Virginia Transportation Authority (NVTA). Dollars are divided into one of two categories: •NVTA 30% Local Distribution Funds •NVTA 70% Regional Revenue Funds Department of Transportation 17
  • 18. County of Fairfax, Virginia Public | Local Revenue Sources HB2313 - NVTA 30% Local Distribution Funds •30% of funds will be distributed to the individual localities on pro-rata basis for transportation. •Must be spent on: urban or secondary road construction; capital improvements that reduce congestion; projects included in NVTA’s long-range plan; or for public transportation purposes. •Distributed monthly to the County from NVTA; County receives about $45 million annually. •Allocated to projects by the County Board. Attributes: •Reliable sources of revenue. •Flexible source of revenue and can be shifted between projects to optimize availability of funding. Department of Transportation 18 Source and Estimated Annual Allocation or Revenue to County NVTA 30% Local Distribution Funds $45M
  • 19. County of Fairfax, Virginia Public | Regional Revenue Sources HB2313 - NVTA 70% Regional Revenue Funds •70% will be provided to the Northern Virginia Transportation Authority (NVTA) to be used on: – Regional projects included in TransAction 2040 or its updates; and – Projects evaluated by VDOT for reducing congestion as required by HB 599 (2012) – NVTA must give priority to selecting projects that are expected to provide the greatest congestion reduction relative to cost of the project •Approximately $200 million available to be allocated by NVTA each year. Attributes: •Can provide large and small sums of revenue. •Competitive process; NVTA 70% not guaranteed due to limited amount of funds available relating to amount requested. •Over the long-term, each locality’s total long-term benefit must be approximately equal to the proportion of the total of the regional fees and taxes attributable to the locality. •Projects must meet specific requirements to be eligible (no maintenance, inclusion in regional plan, etc.) Department of Transportation 19
  • 20. County of Fairfax, Virginia Public | Other Revenues Sales Tax: Local (Northern Virginia) sales tax rate is 6% •General sales tax rate for VA is 5.3 percent •Additional 0.7 percent state tax is imposed in localities in Northern Virginia for transportation; sent to NVTA to be distributed via NVTA 30% Local and NVTA 70% Regional Funds. The County generated roughly $106.4M from the additional 0.7 percent tax for transportation in FY2015. •Requires Virginia General Assembly authorization to increase the current rate. Gas Tax: Regional gas tax of 2.1 percent on wholesale gas sales in Northern Virginia. •These funds are collected by the Northern Virginia Transportation Commission (NVTC) and distributed directly to the Washington Metropolitan Area Transit Authority (WMATA) on behalf of Fairfax County. •Covers portion of County’s subsidy for Metro operations, about $24.8M annually. •Requires Virginia General Assembly authorization to increase the current rate. Department of Transportation 20
  • 21. County of Fairfax, Virginia Public | Other Revenues Real-estate tax (base rate): $1.09/$100 assessed value; Board of Supervisors has authority to annually amend and adopt a new tax rate. An increase of 1 cent could generate approximately $22M in additional revenues in FY2016. Car Tax/Personal property tax: $4.57 per $100 of assessed value; Board of Supervisors has authority to amend and adopt a new tax rate. An increase of 1 cent could generate approximately $800k in additional revenues in FY2016. Hotel and motel tax: 6% (2% general transient occupancy tax, 2% for tourism, and 2% transient occupancy tax for regional transportation (HB2313)). General Assembly authorization required to increase. Grantor’s Tax: $0.15 per $100 of value on deeds (for transportation HB2313). General Assembly authorization required to increase. Department of Transportation 21
  • 22. County of Fairfax, Virginia Public | Other Revenues Meals Tax •Tax on prepared food and beverages at restaurants, cafes, coffee shops, etc. •Counties in Virginia are limited to a rate of up to 4 percent. •Tax would be in addition to the state’s sales tax (6 percent). •Virginia law requires voter referendum to levy meals tax. •Revenues can be earmarked to a specific purpose. Sales tax on service: currently no sales tax on services in Fairfax County; requires General Assembly authorization to enact. Parking fees: currently no fees on county owned parking lots that charge for parking; requires approval for parking lots and on street parking. Local income tax: income taxes are collected by the state. The power to enact a 1% local income tax via referendum was repealed by HB2313. An additional local income tax would require General Assembly authorization to enact. Vehicles Miles Traveled (VMT): Tax on miles traveled by vehicles registered in Fairfax County. The County currently does not have a fee on VMT. This would affect businesses and residents with vehicles registered in Fairfax County. Requires General Assembly authorization to enact. Department of Transportation 22 Potential Annual Revenue to County Meals Tax at 1% rate $22.5M* Meals Tax at 4% rate $90M* *Based on calendar year 2013 taxable sales at Food and Drink Places in Fairfax County
  • 23. County of Fairfax, Virginia Public Sources of Revenue Estimated annual public funds to County for transportation, County-wide from sources discussed: However, public funding for Reston Funding Plan projects may not be readily available until FY2021: •Most of the public sources of revenue have already been committed to projects in the Board’s Six Year Transportation Project Priorities (TPP) for FY2015-FY2020, which includes about $12.5M for DTR overpasses (planning level funding only) that are included in the Reston Funding Plan. •Fairfax County bond packages are planned to fund specific projects. This means that all previous bond authorizations were planned for or are obligated to specific projects. •Even after FY2021, public funds for transportation must be programmed to projects throughout County. Example: Some of the public sources have been committed to the Tysons funding plan through 2050 or projects initiated during FY2015-2020 timeframe. Additional funding from private sources of revenue required to fully fund projects in Reston. Department of Transportation 23 Federal $32,000,000 State $10,000,000 Regional $90,000,000 Local $171,000,000 Total Estimated Annual Public Funds to County for Transportation $303,000,000
  • 24. County of Fairfax, Virginia Private | Proffers/Contributions Proffers •Voluntary commitment by landowners/developers to perform an act or to donate money, land, services or products to address/offset impact(s) arising from their proposed rezoning. Proffers may be offered to offset public facility costs via two methods: 1.Cash Proffer: money voluntarily proffered in a writing signed by the owner of property subject to rezoning, submitted as part of a rezoning application. – Funding can be pooled from multiple rezonings to fund one or more projects e.g. Road Fund. 1.In-kind Contribution: projects completed by the developer seeking rezoning; – On-Site: Improvements directly connected and/or needed for redevelopment. – Off-Site: Improvements not directly connected and/or needed for redevelopment. Department of Transportation 24
  • 25. County of Fairfax, Virginia Private | Road Fund/In-Kind Contributions Example: Developers provide in-kind contributions and contribute to two funds to pay for Tysons improvements over 40 years. Grid of Streets ($865M) – Will be paid entirely by developers through: •Tysons Grid of Streets Contributions Fund ($304M): per gross square foot (gsf) or per dwelling unit contribution •In-kind Contributions ($561): Developers may elect to construct transportation improvements outlined in Tysons guidelines in lieu of cash contributions, as negotiated in individual proffer agreements. Tysons-Wide Road Improvements – Developers pay for majority of projects inside Tysons and a portion of projects outside of Tysons ($506M): •Tysons-Wide Developer Contributions Fund ($253M): per gsf or per dwelling unit contribution •Tysons Service District ($253M) Department of Transportation 25
  • 26. County of Fairfax, Virginia Private | Service District Service District: •Fund transportation improvements located within a defined geographic area. •Does not require landowner approval, approved and established by the Board of Supervisors. •Tysons Service District will fund approximately $253M worth of improvements or 50 percent of Tysons-Wide Road Improvements. Rate in FY2016 is $0.05 per $100 of assessed real estate value. Boundary is generally consistent with the Tysons Corner Urban Center. Attributes: •Reliable source of revenue •Bondable •Applies to both residential and commercial property •Imposed by the Board of Supervisors Department of Transportation 26 Source Potential Revenue FY17 Example Reston Service District @ $0.01 •Estimate using FY15 Assessed Values for properties in Reston TSAs •Assumes 3% annual growth in assessed value $0.8M For example purposes only.
  • 27. County of Fairfax, Virginia Private | Tax District Tax District •Voluntary petition of landowners and approved by the Board of Supervisors. •Fund large projects in a defined geographic area. •Route 28 Transportation Tax District:1987 two-county district for specific purpose of widening the major arterial in a largely undeveloped area. Rate in FY2016 is $0.18 per $100 of assessed value of commercial and industrial property. Revenues estimated to be $11M in FY2016. •Dulles Rail Phase 1: $400M; Dulles Rail Phase II: $330M. Attributes: •Reliable source of revenue •Bondable •Self-imposed Department of Transportation 27 Source Potential Revenue FY17 Example Reston Tax District @ $0.01 •Estimate using FY15 Assessed Values for non-residential (including commercial residential(apartment))properties in Reston TSAs •Assumes 3% annual growth in assessed value $0.6M For example purposes only.
  • 28. County of Fairfax, Virginia Tysons Model Major redevelopment over the next 40 years to capitalize on the four Metro stations in Tysons and transform Tysons into a transit-oriented mixed-use urban center. A funding plan was developed to pay for $3.1B transportation improvements in Tysons to support development with public and private sectors sharing responsibility for cost of improvements. Components of Tysons Infrastructure: 1.Grid of Streets 2.Tysons-wide Improvements 3.Neighborhood and Access Improvements 4.Transit Department of Transportation 28 Cr. Tysons Partnership
  • 29. County of Fairfax, Virginia Tysons Cost Allocation Model Components of Tysons Infrastructure Relevant to the Reston Funding Plan: 1. Grid of Streets – private sources (landowners/developers) I. Grid of Streets Road Fund: Per square foot/per unit road fund II. In-kind contributions 2. Tysons-wide Road Improvements I. Outside of Tysons boundaries – primarily public sources II. Inside of Tysons boundaries – primarily private • Tysons-wide Road Fund: Per square foot/per unit road fund contributions • Tysons Service District Department of Transportation 29
  • 30. County of Fairfax, Virginia Tysons Grid Cost Allocation Model Grid of Streets Projects: Improvements to transform superblock network to more urban model Total: $865,000,000 Funding: Paid for entirely by developers through In-kind contributions and a Grid “Road Fund” Department of Transportation 30 Grid of Streets Rate FY2016 Estimated Total Need, $865M In-kind Contributions N/A $561M Grid “Road Fund” $304M • Per Sq. Ft. Commercial Property $6.71 • Per Unit of Residential Property $1,042
  • 31. County of Fairfax, Virginia Tysons-wide Cost Allocation Model In June 2010, staff recommended to the Tysons sub-committee a cost allocation based on local and through traffic as follows: Tysons-wide project costs should be a shared responsibility between the public and private sectors. The cost share should be allocated based upon the ratio of through (35%) and local (65%) traffic volumes of 2030 Tysons projects. Private responsibility: ½ of local traffic generated (32.5%) Public responsibility: All of through traffic (35%) and ½ of local traffic generated (32.5%) Cost Split for Tysons-wide Projects ($810M): Private Sector 32.5% ($263M) Public Sector 67.5% ($547M) Department of Transportation 31
  • 32. County of Fairfax, Virginia Tysons-wide Cost Allocation Model In December 2010, the updated funding plan for 2050 included additional projects totaling $1.208B. •The Tysons sub-committee recommended a more equitable cost allocation model that also included 2050 projects. •Staff worked in cooperation with the Tysons Partnership over many meetings arrived at a cost allocation model based on a 90/10 split (discussed in the next slide). •In June 2012, staff returned to the sub-committee with the 90/10 split allocation (discussed in next slide), which the sub-committee determined to be a correct basis for an appropriate allocation. Department of Transportation 32
  • 33. County of Fairfax, Virginia Tysons-wide Cost Allocation Model Tysons-wide Road Improvements Projects: These are larger projects, such as new ramps, new roads, and widening existing roads. Total: $1,208,000,000 Department of Transportation 33 ($mil) Public Private Total Public (%) Private (%) Outside Tysons $653 $73 $726 90% 10% Inside Tysons $48 $434 $482 10% 90% Total $701 $506 $1208 100% 100% Share 58% 42%
  • 34. County of Fairfax, Virginia Tysons Cost Allocation Model Tysons-Wide Transportation Fund (Private – Landowner/Developer contributions) ($506M): •“Road Fund” ($253) - Developer contributions to a per sq. ft./per unit fund – Rates are subject to annual inflation adjustment based on CPI •Service district ($253) – “Modified Bell Curve” model to meet $253M need. – Rates: $0.04 in FY 2014, $0.04 in FY 2015, and $0.05 in FY 2016. – Increases to $0.07 later in Tysons funding plan. Department of Transportation 34 Tysons-Wide Transportation Fund Rate FY2016 Estimated Total Need, $506M Service District $0.05 $253M Road Fund $253M • Per Sq. Ft. Commercial Property $5.87 • Per Unit of Residential Property $1042
  • 35. County of Fairfax, Virginia Tysons Transportation Funding Allocation
  • 36. County of Fairfax, Virginia Reston Potential Cost Allocation • Reston-wide Improvements ($1.345B) – Outside/Inside – Outside to be primarily funded by public sector – Inside to be primarily funded by private sector contributions • Grid Network ($1.284B) – Primarily funded by private sector contributions • Total funding plan: $2.629 B Department of Transportation 36
  • 37. County of Fairfax, Virginia Next Steps • Advisory group feedback on potential revenue sources, including others that should be evaluated • Development of proposed funding plan to include cost allocations between public and private sector • Outreach to stakeholders and public • Revise plan based on feedback received • Share proposed funding plan with Board Transportation Committee • Seek Board of Supervisors approval
  • 38. County of Fairfax, Virginia Comments/Questions? Department of Transportation 38
  • 39. County of Fairfax, Virginia Contact Information For questions and comments please contact: Janet Nguyen Janet.Nguyen@fairfaxcounty.gov Ray Johnson Carroll.Johnson@fairfaxcounty.gov