County of Fairfax, Virginia
Reston Funding Plan
Potential Cost Allocations
Reston Network Analysis & Funding Plan Advisory Group
February 22, 2016
Janet Nguyen
Fairfax County Department of Transportation
County of Fairfax, Virginia
Reston Funding Plan Projects
1. Reston Phase I Improvements (non-grid)
– Road transportation improvements1
(Overpasses, Underpass,
Interchange, Widenings, Extensions) to enhance connectivity
– Intersection improvements required for adequate traffic
operations
1. Grid of local streets in Reston TSA areas
– Enhance pedestrian and vehicular circulation in, around, and
through, station areas
Department of Transportation
2
1
All roadways will be designed with pedestrian facilities. Many will also have bike facilities.
County of Fairfax, Virginia
Reston Funding Plan Projects
Department of Transportation
3
1
All roadways will be designed with pedestrian facilities. Many will also have bike facilities.
2
Signal costs updated.
Projects Recommended by Reston Phase I
Comprehensive Plan Amendment
Cost Estimate, $Billion
Reston Phase I Projects (non-grid)
• Road transportation improvements1
(Overpasses, Underpasses, Widenings,
Extensions, Interchanges)
$1.280
• Intersection improvements $0.065
Total Reston Phase I Projects (non-grid) $1.345
Grid Network2
$1.244
Funding Plan Total $2.589B
County of Fairfax, Virginia
Cost Allocation Models
• Option 1: Tysons Cost Allocation Model Applied to Reston
• Option 2: Location – Outside or Inside Reston TSAs
• Option 3: Through/Local Ratios
• Option 4: Location and Through/Local Ratios
• Option 5: Project Category
• Option 6: Regional vs. Local Significance
Department of Transportation
4
County of Fairfax, Virginia
Option 1: Tysons Cost Allocation Model Applied to Reston
Department of Transportation
5
Projects
Outside
Reston
TSAs
Projects
Outside
Reston
TSAs
Projects
Inside
Reston
TSAs
Projects
Inside
Reston
TSAs
County of Fairfax, Virginia
Option 1: Tysons Cost Allocation Model Applied to Reston
Department of Transportation
6
Applies the Tysons Cost Allocation
Model to the Reston Funding Plan.
Reston Phase I Outside of the Reston
TSAs would primarily be a public
responsibility. These are projects and
portions of projects that are outside of
the Reston Transit Station Areas (TSA)
(Herndon, Reston Town Center, and
Wiehle Reston East defined in the
Reston Phase I Comprehensive Plan
Amendment, Approved February 11,
2014)
Reston Phase I Inside of the Reston
TSAs would primarily be a private sector
responsibility. These are projects and
portions of projects inside the Reston
TSAs.
The grid is inside the Reston TSAs and
would be a private sector responsibility.
Project Estimate Allocation ($)
Reston Phase I Outside TSAs $421,000,000
Public Share 90% $378,900,000
Private Share 10% $42,100,000
Reston Phase I Inside TSAs $924,000,000
Public Share 10% $92,400,000
Private Share 90% $831,600,000
Grid $1,244,000,000
Public Share 0% $0
Private Share 100% $1,244,000,000
Total $2,589,000,000
Public Share 18% $471,300,000
Private Share 82% $2,117,700,000
Option 1: Tysons Cost Allocation Model Applied to Reston
County of Fairfax, Virginia
Option 2: Location – Outside or Inside Reston TSAs
Department of Transportation
7
Allocates cost responsibility
based on location of
improvements.
Reston Phase I improvements
outside of the Reston TSAs
would be a public responsibility.
Reston Phase I improvements
located inside of the Reston
TSAs would be a private sector
responsibility.
The grid network would be a
private sector responsibility.
Project Estimate Allocation ($)
Reston Phase I Outside TSAs $421,000,000
Public Share 100% $421,000,000
Private Share 0% $0
Reston Phase I Inside TSAs $924,000,000
Public Share 0% $0
Private Share 100% $924,000,000
Grid $1,244,000,000
Public Share 0% $0
Private Share 100% $1,244,000,000
Total $2,589,000,000
Public Share 16% $421,000,000
Private Share 84% $2,168,000,000
Option 2: Location – Outside or Inside Reston TSAs
County of Fairfax, Virginia
Option 3: Through/Local Ratios
Department of Transportation
8
Allocates cost responsibility
based on the ratio of through and
local traffic volumes.
Through Traffic: 35%
Local Traffic: 65%
Public sector responsibility:
Through traffic (35%) and half of
locally generated traffic (32.5%).
Private sector responsibility:
Half of locally generated traffic
(32.5%) and the grid network.
Project Estimate Allocation ($)
Reston Phase I $1,345,000,000
Public Share (% Through) 35% $470,750,000
Public Share (% Local) 32.5% $437,125,000
Private Share (% Local) 32.5% $437,125,000
Grid $1,244,000,000
Public Share 0% $0
Private Share 100% $1,244,000,000
Total $2,589,000,000
Public Share 35% $907,875,000
Private Share 65% $1,681,125,000
Option 3: Through/Local Ratios
County of Fairfax, Virginia
Option 4: Location and Through/Local Ratios
Department of Transportation
9
Incorporates location and
through/local ratios.
Reston Phase I Projects Outside
of Reston TSAs: public sector
responsibility
Reston Phase I Projects Inside of
the Reston TSAs: shared public
and private sector responsibility
based on through/local traffic
ratios.
Grid network: private sector
responsibility.
Project Estimate Allocation ($)
Reston Phase I Outside TSAs $421,000,000
Public Share 100% $421,000,000
Private Share 0% $0
Reston Phase I Inside TSAs $924,000,000
Public Share (% Through) 35% $323,400,000
Public Share (% Local) 32.5% $300,300,000
Private Share (% Local) 32.5% $300,300,000
Grid $1,244,000,000
Public Share 0% $0
Private Share 100% $1,244,000,000
Total $2,589,000,000
Public Share 40% $1,044,700,000
Private Share 60% $1,544,300,000
Option 4: Location and Through/Local Ratios
County of Fairfax, Virginia
Option 5: Project Category
Department of Transportation
10
Allocates costs on the basis of
project type.
Reston Phase I Roadway
projects would be a public sector
responsibility.
Reston Phase I Intersection
projects and the grid network
would be the responsibility of the
private sector.
Project Estimate Allocation ($)
Reston Phase I Roadways $1,280,000,000
Public Share 100% $1,280,000,000
Private Share 0% $0
Reston Phase I Intersections $65,000,000
Public Share 0% $0
Private Share 100% $65,000,000
Grid $1,244,000,000
Public Share 0% $0
Private Share 100% $1,244,000,000
Total $2,589,000,000
Public Share 49% $1,280,000,000
Private Share 51% $1,309,000,000
Option 5: Project Category
County of Fairfax, Virginia
Option 6: Regional vs. Local Significance
Department of Transportation
11
Cost allocation based on
Regional or Local benefit and
significance.
Regional projects such as the
overpasses, underpass, and
interchange: public sector
responsibility.
Local projects and grid: private
sector responsibility.
Project Estimate Allocation ($)
Reston Phase I Regional $980,000,000
Public Share 100% $980,000,000
Private Share 0% $0
Reston Phase I Local $365,000,000
Public Share 0% $0
Private Share 100% $365,000,000
Grid $1,244,000,000
Public Share 0% $0
Private Share 100% $1,244,000,000
Total $2,589,000,000
Public Share 38% $980,000,000
Private Share 62% $1,609,000,000
Option 6: Regional vs. Local Significance
County of Fairfax, Virginia
Cost Allocation Options
• Discussion
Department of Transportation
12
County of Fairfax, Virginia
Grid Contributions
Department of Transportation
13
County of Fairfax, Virginia
In-Kind and Road Fund Contributions
Portions of the grid are expected to be constructed
with redevelopment (in-kind contributions) in the
following areas:
•Transit Station Mixed Use
•Residential Mixed Use
•Town Center North Mixed Use
The remaining portion of the grid is expected to be
constructed with contributions to a road fund.
Department of Transportation
14
County of Fairfax, Virginia
Department of Transportation
15
Reston Phase I Plan Amendment:
Conceptual Land Use
County of Fairfax, Virginia
Potential Grid Contributions
Department of Transportation
16
Potential Grid Contributions
Grid estimate $1,244,000,000
Less: Expected in-kind contributions - 805,000,000
Road fund contributions required for
grid $439,000,000
County of Fairfax, Virginia
Road Fund
• Road fund revenues will be based on new residential
and commercial development.
• Developers will pay into road fund as redevelopment
occurs.
• Commercial rates are paid on a per square foot basis.
• Residential rates are paid on a per dwelling unit basis.
• When developing rates, the expected rate of
development, type of development and the balance
between near future and far future should be taken into
account.
Department of Transportation
17
County of Fairfax, Virginia
Development Levels
Department of Transportation
18
Reston TSA Comprehensive Plan Development Potential
Land Use
2010 Existing Land
Use
Development
Potential
New Development
(sq. ft.) (sq. ft.)
Residential
5,860,000
(5,860 Units)
52,800,000
(44,000 units)
46,940,000
(38,140 Units)
Office 20,982,169 29,700,000 8,717,831
Retail 1,094,476 2,100,000 1,005,524
Industrial 841,957 590,000 -251,957
Institutional 2,096,840 2,400,000 303,160
Hotel 936,782 4,900,000 3,963,218
Total 31,812,224 92,490,000 60,677,776
Total new
non-
residential
potential:
13,737,776
sq. ft.
Total new
residential
potential
County of Fairfax, Virginia
Contribution Rates
Board of Supervisors approved rate changes on
February 2, 2016.
Department of Transportation
19
Fund Area
Non-Residential
Rate per Sq. Ft.
Residential Rate
per Dwelling Unit
Fairfax Center $5.94 $1,316
Centreville $6.38 $2,522
Tysons (Rezonings Prior to 2/1/2013) $4.37 $970
Tysons-Wide $5.90 $1,045
Tysons Grid of Streets $6.73 $1,045
County of Fairfax, Virginia
Private Sector Responsibility in the
Tysons Funding Plan
Department of Transportation
20
County of Fairfax, Virginia
Tysons Private Sector Contributions
In-Kind Contributions
1. Tysons Grid of Streets In-Kind Contributions, $561 million
Fund(s) Contributions
1. Tysons Grid of Streets Fund*, $304 million
• Non-residential rate: $6.73 per sq. ft.
• Residential rate: $1,045 per dwelling unit
1. Tysons-Wide Fund*, $253 million (Tysons-Wide Improvements)
• Non-residential rate: $5.90 per sq. ft.
• Residential rate: $1,045 per dwelling unit
1. Tysons Service District, $253 million (Tysons-Wide Improvements)
• FY 2016 Rate: $0.06 per $100 assessed value on all properties in service district
*Tysons Grid of Streets Fund and Tysons-Wide Fund rates effective Feb. 3, 2016.
Department of Transportation
21
County of Fairfax, Virginia
Next Steps
• Seek advisory group feedback on cost allocation options
and initial thoughts on development of contribution rates
• Develop framework for funding plan
• Outreach to stakeholders and public
• Revise plan based on feedback received and results
from Network Analysis
• Share proposed funding plan with Board Transportation
Committee
• Seek Board of Supervisors approval
Department of Transportation
22
County of Fairfax, Virginia
Comments/Questions?
Department of Transportation
23
County of Fairfax, Virginia
Contact Information
For questions and comments please contact:
Janet Nguyen
Janet.Nguyen@fairfaxcounty.gov
Ray Johnson
Carroll.Johnson@fairfaxcounty.gov

More Related Content

What's hot

Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of CountywideDialogue on Transportation:Project SelectionA Si...Continuation of CountywideDialogue on Transportation:Project SelectionA Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...Fairfax County
 
Reston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseReston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseFairfax County
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Fairfax County
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Fairfax County
 
Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016   Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016 Fairfax County
 
Reston Funding Plan: Rates/Contributions Discussion
Reston Funding Plan: Rates/Contributions DiscussionReston Funding Plan: Rates/Contributions Discussion
Reston Funding Plan: Rates/Contributions DiscussionFairfax County
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes ExtensionFairfax County
 
North Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement StudyNorth Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement StudyFairfax County
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County
 
Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Fairfax County
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County
 
I-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the BeltwayI-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the BeltwayFairfax County
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Fairfax County
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingFairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 

What's hot (20)

Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of CountywideDialogue on Transportation:Project SelectionA Si...Continuation of CountywideDialogue on Transportation:Project SelectionA Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
Reston Transportation Funding Plan: Funding Scenarios and Advisory Group Work...
 
Reston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open HouseReston Bike Share Feasibility Study: Public Open House
Reston Bike Share Feasibility Study: Public Open House
 
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
Transportation Funding: Implementing HB 2313, Funding Process, Benefit Cost A...
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
 
Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016   Fairfax County TDM in Land Development: April 19, 2016
Fairfax County TDM in Land Development: April 19, 2016
 
Reston Funding Plan: Rates/Contributions Discussion
Reston Funding Plan: Rates/Contributions DiscussionReston Funding Plan: Rates/Contributions Discussion
Reston Funding Plan: Rates/Contributions Discussion
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
I-395 Express Lanes Extension
I-395 Express Lanes ExtensionI-395 Express Lanes Extension
I-395 Express Lanes Extension
 
North Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement StudyNorth Kings Highway (VA 241) Intersection Improvement Study
North Kings Highway (VA 241) Intersection Improvement Study
 
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
Fairfax County Countywide Transit Network Study-February 2016 Public Meeting:...
 
Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2Fairfax County Countywide Transit Network Study: Public Workshop #2
Fairfax County Countywide Transit Network Study: Public Workshop #2
 
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
Board of Supervisors Transportation Committee: Proposed High Quality Transit ...
 
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
Fairfax County Countywide Transit Network Study: Proposed High Quality Transi...
 
I-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the BeltwayI-66 Corridor Improvements Outside the Beltway
I-66 Corridor Improvements Outside the Beltway
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
 
Countywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public MeetingCountywide Transit Network Study: Introductory Public Meeting
Countywide Transit Network Study: Introductory Public Meeting
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 

Viewers also liked

Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Fairfax County
 
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...Fairfax County
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilityFairfax County
 
Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016
Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016
Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016Fairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Fairfax County
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Fairfax County
 
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016  Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016 Fairfax County
 
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Fairfax County
 
Mobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-WayMobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-WayFairfax County
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Fairfax County
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyFairfax County
 
Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016Fairfax County
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
 
Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...Fairfax County
 
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...Fairfax County
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare ProgramFairfax County
 
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4Fairfax County
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramFairfax County
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Fairfax County
 

Viewers also liked (20)

Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
Pardon Our Dust Meeting: Pedestrian Improvements at the Intersection of Old D...
 
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
Countywide Transit Network Study: Proposed High Quality Transit Network: Janu...
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
 
Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016
Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016
Transportation Alternatives Workshop and Public Comment: Sept. 15, 2016
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016Silver Line Update - Feb. 12, 2016
Silver Line Update - Feb. 12, 2016
 
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016  Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
Fairfax County Taxicab Regulation: A Review of Chapter 84.1 : May 17, 2016
 
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
Reston Network Analysis: Tier 3 Mitigation Results: Sept. 26, 2016
 
Protective Helmets
Protective HelmetsProtective Helmets
Protective Helmets
 
Mobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-WayMobile Food Vending within VDOT Right-of-Way
Mobile Food Vending within VDOT Right-of-Way
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Shirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning StudyShirley Gate Road Extended Corridor Planning Study
Shirley Gate Road Extended Corridor Planning Study
 
Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...Discussion of Converting Roads from the Secondary System to the Primary Syste...
Discussion of Converting Roads from the Secondary System to the Primary Syste...
 
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
Endorsement of the Recommended Design Concept (Preferred Alternative) for Tra...
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare Program
 
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
Hunter Mill Road and Sunset Hills Road Study-Community Meeting #4
 
Potential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light ProgramPotential Fairfax County Photo Red Light Program
Potential Fairfax County Photo Red Light Program
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
 

Similar to Reston Funding Plan Cost Allocation Analysis

Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Fairfax County
 
Reston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosReston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosFairfax County
 
Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016Fairfax County
 
Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...Fairfax County
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Fairfax County
 
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1Fairfax County
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Fairfax County
 
Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Fairfax County
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsFairfax County
 
Moving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and BeyondMoving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and Beyondpreservationcombination
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Fairfax County
 
RV 2014: Value Capture: Myth or Reality? by Nadine Fogarty
RV 2014: Value Capture: Myth or Reality? by Nadine FogartyRV 2014: Value Capture: Myth or Reality? by Nadine Fogarty
RV 2014: Value Capture: Myth or Reality? by Nadine FogartyRail~Volution
 
Oakland A's Waterfront Ballpark
Oakland A's Waterfront BallparkOakland A's Waterfront Ballpark
Oakland A's Waterfront Ballparkostadium
 
2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant Workshop2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant WorkshopCuyahoga County Planning Commission
 
Granite Ridge Tax Increment Financing Plan
Granite Ridge Tax Increment Financing PlanGranite Ridge Tax Increment Financing Plan
Granite Ridge Tax Increment Financing PlanKaren Pollard, CEcD, EDP
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 

Similar to Reston Funding Plan Cost Allocation Analysis (20)

Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
 
Reston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosReston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding Scenarios
 
Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016Reston Transportation Funding Plan: Dec. 13, 2016
Reston Transportation Funding Plan: Dec. 13, 2016
 
Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...Reston Transportation Service District: Informational Meetings March 21 & 29,...
Reston Transportation Service District: Informational Meetings March 21 & 29,...
 
Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016Reston Transportation Funding Plan: Community Meeting June 27, 2016
Reston Transportation Funding Plan: Community Meeting June 27, 2016
 
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
Reston Transportation Service District Advisory Board - 2019 Spring Meeting #1
 
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
 
SMART Plan Regional Funding Profiles
SMART Plan Regional Funding ProfilesSMART Plan Regional Funding Profiles
SMART Plan Regional Funding Profiles
 
Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016
 
Update on Reston Development and Transportation Projects
Update on Reston Development and Transportation ProjectsUpdate on Reston Development and Transportation Projects
Update on Reston Development and Transportation Projects
 
Moving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and BeyondMoving Ahead for Progress in the 21st Century Act and Beyond
Moving Ahead for Progress in the 21st Century Act and Beyond
 
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure...
 
Denver9/28_James Corless
Denver9/28_James Corless Denver9/28_James Corless
Denver9/28_James Corless
 
RV 2014: Value Capture: Myth or Reality? by Nadine Fogarty
RV 2014: Value Capture: Myth or Reality? by Nadine FogartyRV 2014: Value Capture: Myth or Reality? by Nadine Fogarty
RV 2014: Value Capture: Myth or Reality? by Nadine Fogarty
 
Oakland A's Waterfront Ballpark
Oakland A's Waterfront BallparkOakland A's Waterfront Ballpark
Oakland A's Waterfront Ballpark
 
2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant Workshop2011 District One Public Works Integrating Committee Applicant Workshop
2011 District One Public Works Integrating Committee Applicant Workshop
 
Granite Ridge Tax Increment Financing Plan
Granite Ridge Tax Increment Financing PlanGranite Ridge Tax Increment Financing Plan
Granite Ridge Tax Increment Financing Plan
 
Granite ridge tif
Granite ridge tifGranite ridge tif
Granite ridge tif
 
A smart step forward1
A smart step forward1A smart step forward1
A smart step forward1
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Recently uploaded

14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptUsmanKaran
 
lok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxlok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxdigiyvbmrkt
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxSasikiranMarri
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...The Lifesciences Magazine
 
12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxunark75
 
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road ConnectivityTransforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivitynarsireddynannuri1
 
11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Emerging issues in migration policies.ppt
Emerging issues in migration policies.pptEmerging issues in migration policies.ppt
Emerging issues in migration policies.pptNandinituteja1
 
Power in International Relations (Pol 5)
Power in International Relations (Pol 5)Power in International Relations (Pol 5)
Power in International Relations (Pol 5)ssuser583c35
 

Recently uploaded (14)

14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf14042024_First India Newspaper Jaipur.pdf
14042024_First India Newspaper Jaipur.pdf
 
Geostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.pptGeostrategic significance of South Asian countries.ppt
Geostrategic significance of South Asian countries.ppt
 
lok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptxlok sabha Elections in india- 2024 .pptx
lok sabha Elections in india- 2024 .pptx
 
Political-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptxPolitical-Ideologies-and-The-Movements.pptx
Political-Ideologies-and-The-Movements.pptx
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
Mitochondrial Fusion Vital for Adult Brain Function and Disease Understanding...
 
12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf12042024_First India Newspaper Jaipur.pdf
12042024_First India Newspaper Jaipur.pdf
 
13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf13042024_First India Newspaper Jaipur.pdf
13042024_First India Newspaper Jaipur.pdf
 
Foreign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptxForeign Relation of Pakistan with Neighboring Countries.pptx
Foreign Relation of Pakistan with Neighboring Countries.pptx
 
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road ConnectivityTransforming Andhra Pradesh: TDP's Legacy in Road Connectivity
Transforming Andhra Pradesh: TDP's Legacy in Road Connectivity
 
11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf11042024_First India Newspaper Jaipur.pdf
11042024_First India Newspaper Jaipur.pdf
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 
Emerging issues in migration policies.ppt
Emerging issues in migration policies.pptEmerging issues in migration policies.ppt
Emerging issues in migration policies.ppt
 
Power in International Relations (Pol 5)
Power in International Relations (Pol 5)Power in International Relations (Pol 5)
Power in International Relations (Pol 5)
 

Reston Funding Plan Cost Allocation Analysis

  • 1. County of Fairfax, Virginia Reston Funding Plan Potential Cost Allocations Reston Network Analysis & Funding Plan Advisory Group February 22, 2016 Janet Nguyen Fairfax County Department of Transportation
  • 2. County of Fairfax, Virginia Reston Funding Plan Projects 1. Reston Phase I Improvements (non-grid) – Road transportation improvements1 (Overpasses, Underpass, Interchange, Widenings, Extensions) to enhance connectivity – Intersection improvements required for adequate traffic operations 1. Grid of local streets in Reston TSA areas – Enhance pedestrian and vehicular circulation in, around, and through, station areas Department of Transportation 2 1 All roadways will be designed with pedestrian facilities. Many will also have bike facilities.
  • 3. County of Fairfax, Virginia Reston Funding Plan Projects Department of Transportation 3 1 All roadways will be designed with pedestrian facilities. Many will also have bike facilities. 2 Signal costs updated. Projects Recommended by Reston Phase I Comprehensive Plan Amendment Cost Estimate, $Billion Reston Phase I Projects (non-grid) • Road transportation improvements1 (Overpasses, Underpasses, Widenings, Extensions, Interchanges) $1.280 • Intersection improvements $0.065 Total Reston Phase I Projects (non-grid) $1.345 Grid Network2 $1.244 Funding Plan Total $2.589B
  • 4. County of Fairfax, Virginia Cost Allocation Models • Option 1: Tysons Cost Allocation Model Applied to Reston • Option 2: Location – Outside or Inside Reston TSAs • Option 3: Through/Local Ratios • Option 4: Location and Through/Local Ratios • Option 5: Project Category • Option 6: Regional vs. Local Significance Department of Transportation 4
  • 5. County of Fairfax, Virginia Option 1: Tysons Cost Allocation Model Applied to Reston Department of Transportation 5 Projects Outside Reston TSAs Projects Outside Reston TSAs Projects Inside Reston TSAs Projects Inside Reston TSAs
  • 6. County of Fairfax, Virginia Option 1: Tysons Cost Allocation Model Applied to Reston Department of Transportation 6 Applies the Tysons Cost Allocation Model to the Reston Funding Plan. Reston Phase I Outside of the Reston TSAs would primarily be a public responsibility. These are projects and portions of projects that are outside of the Reston Transit Station Areas (TSA) (Herndon, Reston Town Center, and Wiehle Reston East defined in the Reston Phase I Comprehensive Plan Amendment, Approved February 11, 2014) Reston Phase I Inside of the Reston TSAs would primarily be a private sector responsibility. These are projects and portions of projects inside the Reston TSAs. The grid is inside the Reston TSAs and would be a private sector responsibility. Project Estimate Allocation ($) Reston Phase I Outside TSAs $421,000,000 Public Share 90% $378,900,000 Private Share 10% $42,100,000 Reston Phase I Inside TSAs $924,000,000 Public Share 10% $92,400,000 Private Share 90% $831,600,000 Grid $1,244,000,000 Public Share 0% $0 Private Share 100% $1,244,000,000 Total $2,589,000,000 Public Share 18% $471,300,000 Private Share 82% $2,117,700,000 Option 1: Tysons Cost Allocation Model Applied to Reston
  • 7. County of Fairfax, Virginia Option 2: Location – Outside or Inside Reston TSAs Department of Transportation 7 Allocates cost responsibility based on location of improvements. Reston Phase I improvements outside of the Reston TSAs would be a public responsibility. Reston Phase I improvements located inside of the Reston TSAs would be a private sector responsibility. The grid network would be a private sector responsibility. Project Estimate Allocation ($) Reston Phase I Outside TSAs $421,000,000 Public Share 100% $421,000,000 Private Share 0% $0 Reston Phase I Inside TSAs $924,000,000 Public Share 0% $0 Private Share 100% $924,000,000 Grid $1,244,000,000 Public Share 0% $0 Private Share 100% $1,244,000,000 Total $2,589,000,000 Public Share 16% $421,000,000 Private Share 84% $2,168,000,000 Option 2: Location – Outside or Inside Reston TSAs
  • 8. County of Fairfax, Virginia Option 3: Through/Local Ratios Department of Transportation 8 Allocates cost responsibility based on the ratio of through and local traffic volumes. Through Traffic: 35% Local Traffic: 65% Public sector responsibility: Through traffic (35%) and half of locally generated traffic (32.5%). Private sector responsibility: Half of locally generated traffic (32.5%) and the grid network. Project Estimate Allocation ($) Reston Phase I $1,345,000,000 Public Share (% Through) 35% $470,750,000 Public Share (% Local) 32.5% $437,125,000 Private Share (% Local) 32.5% $437,125,000 Grid $1,244,000,000 Public Share 0% $0 Private Share 100% $1,244,000,000 Total $2,589,000,000 Public Share 35% $907,875,000 Private Share 65% $1,681,125,000 Option 3: Through/Local Ratios
  • 9. County of Fairfax, Virginia Option 4: Location and Through/Local Ratios Department of Transportation 9 Incorporates location and through/local ratios. Reston Phase I Projects Outside of Reston TSAs: public sector responsibility Reston Phase I Projects Inside of the Reston TSAs: shared public and private sector responsibility based on through/local traffic ratios. Grid network: private sector responsibility. Project Estimate Allocation ($) Reston Phase I Outside TSAs $421,000,000 Public Share 100% $421,000,000 Private Share 0% $0 Reston Phase I Inside TSAs $924,000,000 Public Share (% Through) 35% $323,400,000 Public Share (% Local) 32.5% $300,300,000 Private Share (% Local) 32.5% $300,300,000 Grid $1,244,000,000 Public Share 0% $0 Private Share 100% $1,244,000,000 Total $2,589,000,000 Public Share 40% $1,044,700,000 Private Share 60% $1,544,300,000 Option 4: Location and Through/Local Ratios
  • 10. County of Fairfax, Virginia Option 5: Project Category Department of Transportation 10 Allocates costs on the basis of project type. Reston Phase I Roadway projects would be a public sector responsibility. Reston Phase I Intersection projects and the grid network would be the responsibility of the private sector. Project Estimate Allocation ($) Reston Phase I Roadways $1,280,000,000 Public Share 100% $1,280,000,000 Private Share 0% $0 Reston Phase I Intersections $65,000,000 Public Share 0% $0 Private Share 100% $65,000,000 Grid $1,244,000,000 Public Share 0% $0 Private Share 100% $1,244,000,000 Total $2,589,000,000 Public Share 49% $1,280,000,000 Private Share 51% $1,309,000,000 Option 5: Project Category
  • 11. County of Fairfax, Virginia Option 6: Regional vs. Local Significance Department of Transportation 11 Cost allocation based on Regional or Local benefit and significance. Regional projects such as the overpasses, underpass, and interchange: public sector responsibility. Local projects and grid: private sector responsibility. Project Estimate Allocation ($) Reston Phase I Regional $980,000,000 Public Share 100% $980,000,000 Private Share 0% $0 Reston Phase I Local $365,000,000 Public Share 0% $0 Private Share 100% $365,000,000 Grid $1,244,000,000 Public Share 0% $0 Private Share 100% $1,244,000,000 Total $2,589,000,000 Public Share 38% $980,000,000 Private Share 62% $1,609,000,000 Option 6: Regional vs. Local Significance
  • 12. County of Fairfax, Virginia Cost Allocation Options • Discussion Department of Transportation 12
  • 13. County of Fairfax, Virginia Grid Contributions Department of Transportation 13
  • 14. County of Fairfax, Virginia In-Kind and Road Fund Contributions Portions of the grid are expected to be constructed with redevelopment (in-kind contributions) in the following areas: •Transit Station Mixed Use •Residential Mixed Use •Town Center North Mixed Use The remaining portion of the grid is expected to be constructed with contributions to a road fund. Department of Transportation 14
  • 15. County of Fairfax, Virginia Department of Transportation 15 Reston Phase I Plan Amendment: Conceptual Land Use
  • 16. County of Fairfax, Virginia Potential Grid Contributions Department of Transportation 16 Potential Grid Contributions Grid estimate $1,244,000,000 Less: Expected in-kind contributions - 805,000,000 Road fund contributions required for grid $439,000,000
  • 17. County of Fairfax, Virginia Road Fund • Road fund revenues will be based on new residential and commercial development. • Developers will pay into road fund as redevelopment occurs. • Commercial rates are paid on a per square foot basis. • Residential rates are paid on a per dwelling unit basis. • When developing rates, the expected rate of development, type of development and the balance between near future and far future should be taken into account. Department of Transportation 17
  • 18. County of Fairfax, Virginia Development Levels Department of Transportation 18 Reston TSA Comprehensive Plan Development Potential Land Use 2010 Existing Land Use Development Potential New Development (sq. ft.) (sq. ft.) Residential 5,860,000 (5,860 Units) 52,800,000 (44,000 units) 46,940,000 (38,140 Units) Office 20,982,169 29,700,000 8,717,831 Retail 1,094,476 2,100,000 1,005,524 Industrial 841,957 590,000 -251,957 Institutional 2,096,840 2,400,000 303,160 Hotel 936,782 4,900,000 3,963,218 Total 31,812,224 92,490,000 60,677,776 Total new non- residential potential: 13,737,776 sq. ft. Total new residential potential
  • 19. County of Fairfax, Virginia Contribution Rates Board of Supervisors approved rate changes on February 2, 2016. Department of Transportation 19 Fund Area Non-Residential Rate per Sq. Ft. Residential Rate per Dwelling Unit Fairfax Center $5.94 $1,316 Centreville $6.38 $2,522 Tysons (Rezonings Prior to 2/1/2013) $4.37 $970 Tysons-Wide $5.90 $1,045 Tysons Grid of Streets $6.73 $1,045
  • 20. County of Fairfax, Virginia Private Sector Responsibility in the Tysons Funding Plan Department of Transportation 20
  • 21. County of Fairfax, Virginia Tysons Private Sector Contributions In-Kind Contributions 1. Tysons Grid of Streets In-Kind Contributions, $561 million Fund(s) Contributions 1. Tysons Grid of Streets Fund*, $304 million • Non-residential rate: $6.73 per sq. ft. • Residential rate: $1,045 per dwelling unit 1. Tysons-Wide Fund*, $253 million (Tysons-Wide Improvements) • Non-residential rate: $5.90 per sq. ft. • Residential rate: $1,045 per dwelling unit 1. Tysons Service District, $253 million (Tysons-Wide Improvements) • FY 2016 Rate: $0.06 per $100 assessed value on all properties in service district *Tysons Grid of Streets Fund and Tysons-Wide Fund rates effective Feb. 3, 2016. Department of Transportation 21
  • 22. County of Fairfax, Virginia Next Steps • Seek advisory group feedback on cost allocation options and initial thoughts on development of contribution rates • Develop framework for funding plan • Outreach to stakeholders and public • Revise plan based on feedback received and results from Network Analysis • Share proposed funding plan with Board Transportation Committee • Seek Board of Supervisors approval Department of Transportation 22
  • 23. County of Fairfax, Virginia Comments/Questions? Department of Transportation 23
  • 24. County of Fairfax, Virginia Contact Information For questions and comments please contact: Janet Nguyen Janet.Nguyen@fairfaxcounty.gov Ray Johnson Carroll.Johnson@fairfaxcounty.gov