SlideShare a Scribd company logo
1 of 24
Download to read offline
Thank you for attending our webcast today.
This topic should be one we all are familiar with, since it is nearly impossible to
not have experienced a project failure at least once in our career.
We usually start our project management quest with capturing requirements,
building a schedule to deliver them, executing that schedule, and making
adjustments along the way when we’re not staying on schedule.
The principles I’m going to speak to you about are universal. Applicable to any
project, of any size, in any domain.
What you’re going to hear is not the solution to avoid project failure. It is the
framework for project success.
The actual mechanics of managing a project are based on these principles.
The practices used in this management should be based on the se principles.
And of course the process ad tools should implement the practices.
5 Proven Approaches for Mitigating Project Failure
Page 10:44
Nearly every business activity is based on a project in some way.
Even the operational aspects of a business are projectized through processes,
procedures, and business management governance.
Today I’d like to focus on the types of projects Land speaks of. The really
important ones that are nearly impossible.
I was a participant in one of those projects – Rocky Flats Environmental
Technology Site. The name of the site was a nice marketing term for the
cleanup of a nuclear bomb factory.
It was nearly impossible. And manifestly important The previous contractor had
spent $4B and not done much.
When Kaiser-Hill (a joint venture between ICF Kaiser and CH2MHill) won the
contract for $7B, they had a plan that was dramatically different from the past
attempts to cleanup and close the site.
This plan focused on applying the 5 Immutable Principles, defining the
“packages of work” that delivered the outcomes, measuring progress as
physical percent complete, and risk adjusting everything to produce a credible
Estimate to Complete on a weekly basis for 5,000 staff working on site.
Page 21:06
5 Proven Approaches for Mitigating Project Failure
I’m going to present 5 Immutable Principles today that are the foundation of
project success.
These Principles are “Immutable” because they must always be present. They
are the foundation on which the Practices and Processes are built.
We won’t look at the Practices and Processes, but they are critical to the
success of any project as well.
Those are available in the book from AMACOM.
Page 30:20
5 Proven Approaches for Mitigating Project Failure
There are nearly unlimited reasons for project failures.
Root Cause Analysis is the means to separate the symptoms of project
difficulties from the actual causes of those difficulties.
If the Root Cause is not found, prevented or corrected, it will reappear.
This is a short list of Root Causes.
You’ll likely have your own list, but I suspect it will overlap with these.
4
5 Proven Approaches for Mitigating Project Failure
With this background, let’s start with the 5 Immutable Principles of Project
Success.
I would suggest these are applicable in any technical domain.
Any project management method.
Any business domain.
They are universal and Immutable – meaning they don’t change over time.
They are permanent principles that must be applied for the success of any
project.
The Principles are in the form of questions in this example. There are more
formal statements about the Principles, but starting by asking 5 questions
shows how the principles can be applied in any situation.
When there is not a credible answer to the question, this is an indication there
is likely trouble on the project and the probability of success has been lowered.
Page 50:40
5 Proven Approaches for Mitigating Project Failure
With the Principles and Practices, we need Processes to put to work.
Some of you may recognize these as part of the Earned Value Management
processes in EIA-748-C.
But there are also the basis of all good project management work. You really
can’t be managing a project – in any credible manner – if you are doing these
11 processes.
• What are we building?
• Who’s on our team?
• Who’s doing what?
• What’s the sequence of the work?
• What are the outcomes of that work?
• What’s the budget for the work to produce those outcomes?
• What did it cost to produce each outcome?
• What was the difference between our budget and the actual costs?
• What’s the total differences for the entire project?
• What are we going to change to get back on budget and schedule?
• Did we record these changes?
6
5 Proven Approaches for Mitigating Project Failure
We keep using the term Deliverable.
Here’s what that means.
It means the customer bought something they can put to work to fulfill a
business case or accomplish a mission.
The deliverables, taken individual are just individual functions of the project.
Taken as whole, they provide a set of capabilities that can be used by the
customer to accomplish something.
Along the way, each deliverable increases the maturity of the projects
capabilities.
We can start with a few deliverables. The customer may or may not be able to
accomplish something with those deliverables, but their presence may be
necessary for further deliverables to provide a capability.
There is a myth in the agile development business, that Value products need
to be delivered starting on day one. This may be appropriate for simple
projects. But most complex systems have pre-conditions for success. We need
to install the Database Server before we can use build databases. We have
foundation activities on which we build other capabilities.
So the challenge is to determine the order of the needed capabilities to reach
the needed maturity at the time that maturity is needed
7
5 Proven Approaches for Mitigating Project Failure
So let’s revisit our 5 Immutable Principles once more with the Practices and
Processes in hand.
• What does our customer need to fulfill their business case or accomplish
their mission?
• What are the technical and operational requirements that must be delivered
to fulfill that mission?
• What’s the schedule for that work?
• How are we going to measure progress to plan?
• What impediments are we going to encounter along the way and how are
we going to deal with them, so they don’t impact the success of our project?
This is the basis of Capabilities Based Planning. It’s the capabilities that are
delivered. These are enabled by through the deliverables appearing tin the
right order, fulfilling the right requirements, each building on the previous
requirements and capabilities.
8
5 Proven Approaches for Mitigating Project Failure
Traditional project management is a good foundation for all project work.
Performance-Based Project Management® adds another paradigm to that
foundation – we measure progress to plan in terms of performance outcomes.
This separate Output (effort, cost, deliverables) from Outcomes (the capability
to do something needed for success).
Performance-Based Project Management® is risk based, from Tim Lister’s
advice Risk Management is How Adults Manage Projects.
9
5 Proven Approaches for Mitigating Project Failure
Here’s how to assemble the Practices to increase the probability of project
success.
This is a simple diagram, showing the order of work.
• Answer the question Why Do We Need This – by defining the needed
capabilities. If you start with requirements, you may or may not know why
those requirements are there. What there purpose is. These capabilities
have Measures of Effectiveness.
• Identify the requirements that produce the capability to do something. These
requirements have Measures of Performance.
• Layout all the work in the right sequence – this can be an agile sequence,
with current releases, future release, sprints and the like. But knowing what
capabilities we’ll need for project success is a Critical Success Factor, no
mater what development method you use.
• Execute that sequence of work and measure physical percent complete to
plan.
• Along the way, make sure you have all the risks identified, handled, and the
results included in future planning processes
10
5 Proven Approaches for Mitigating Project Failure
So let’s move to the next step. Applying the Practices and Processes
11
5 Proven Approaches for Mitigating Project Failure
The first Principle is to assure we know what Done looks like. This sounds like
a simple process. But turns out to be the root cause of most project failures.
Done is not described in any meaningful units of measure for the decision
makers.
Our first response is usually to make a list of features and functions for the
product or service produced by the project. This is necessary but far from
sufficient to describe Done. We don’t know how these features and functions
interact, how and when they provide value to the customer.
The interdependencies are next. We need to show how each feature or
function is dependent – if it is – on other features and functions. This usually
starts with the Work Breakdown Structure (WBS) showing all the deliverables
from the project. The WBS needs a WBS Dictionary to show how we are going
to measure the performance, quality, compliance of these outcomes with each
other and the customer.
But the WBS and its Dictionary are not enough to know what Done looks like.
We need to know what Capabilities are being provided by the project. What is
the customer going to DO with these outcomes? How are they going to satisfy
the business needs or mission?
The Capability to do something is what the customer bought.
Page 121:08
5 Proven Approaches for Mitigating Project Failure
These Capability statements are clear and concise. Long before we ever arrived in
the moon, Robert Goddard knew what capabilities were needed to get there.
On October 19, 1899, Goddard climbed a dead tree to trim some branches. He was
17. He is quoted as saying … “I imagined,” he later recalled, “how wonderful it would
be to make some device which had even the possibility of ascending to Mars, and
how it would look on a small scale, if sent up from the meadow at my feet. . . I was a
different boy when I descended the tree from when I ascended, for existence at last
seemed very purposive.”
He had in his mind what capabilities were needed to fly outside the Earths
atmosphere. He knew some of the units of measure that had to be fulfilled to do this.
If we don’t have some vision of the project at the Capabilities level, we really can’t say
what Done looks like. We can describe the technical aspects, but we can’t say what
we are going to do with those technical aspects.
This definition of Capabilities is a Systems Engineering role. There are formal
processes to elicit these Capabilities through the Concept of Operations, Scenarios,
and Use Cases, making tradeoffs between cost, risk, schedule, and technical
performance, and balancing all the feasible alternatives.
The result is the Measures of Effectiveness which tell the customer the project will
meet the needed capabilities.
Page 131:15
5 Proven Approaches for Mitigating Project Failure
With the needed Capabilities we can now develop a plan and schedule for the work.
Knowing how to get Done on–budget and on–schedule means knowing what
requirements will have to be fulfilled.
Poorly formed requirements contribute as much as 25% to the failure modes of
programs and projects.
This starts with Fact Finding, Gathering and Classifying the Requirements, Evaluating
and Rationalizing the Requirements, Prioritizing them, and Integrating and Validating
the Requirements.
With this in hand we can start building the packages of work that implement the
requirements.
The result is a Plan and a Schedule. The Plan is the Strategy for the proper delivery
of the Capabilities produced by the project. The Schedule is the sequence of work
needed to implement the Strategy. Both are needed.
The Plan is emergent, since it is a strategy. The Schedule tests this strategy on short
term boundaries, with measures of physical percent complete.
Both the Plan and the Schedule must be capable of responding to change as new
information about requirements, program performance, and risks emerge.
But the needed capabilities should remain stable if we are to have a baseline on
which to execute our project.
Page 141:05
5 Proven Approaches for Mitigating Project Failure
The Plan can be very simple or it can be complex.
Here’s a plan that took us to the moon and back.
This picture shows a simple concept. Build the launch vehicle, the fuel to
power it, the space craft on the top, train the astronauts, do the testing, and fly.
The Plan shows the 6 major systems , their approximate duration in years, and
the dependencies between them are all that is needed to confirm the feasibility
of the project.
Notice the longest activity is the training of the crew. No one had ever flown in
space before all the way to the moon and back. So training was high risk and
critical to success.
Page 150:35
5 Proven Approaches for Mitigating Project Failure
One view of the Plan is the vertical integration of the deliverables.
This is the deliverables traceability view. At the bottom is our deliverable.
The deliverable is produced by work contained in a work package. A Work
Package says its name. it produces a single outcome.
The technical capabilities needed for the project’s success are produced by
the Work Packages.
Finally these Technical Capabilities produce business or mission capabilities
needed by the customer for project success.
This traceability is necessary for a credible Plan and Schedule. It is also
necessary for a credible project delivery process.
This traceability tells everyone what Done looks like and how we are going to
get there.
Page 160:35
5 Proven Approaches for Mitigating Project Failure
With the Plan in place and the “packages of work” identified in the Schedule,
we can construct a picture of how we are going to reach Done.
This picture is not like the typical horizontal scheduling activities we see in all
the scheduling tools.
This picture starts with the vertical integration of the deliverables as they
progress through their maturity life cycle.
This is called the Integrated Master Plan. This Plan shows the Measures of
Effectiveness and Measures of Performance we need to achieve to reach a
specific level of maturity.
This notion of levels of maturity can be seen is we use some words
Preliminary is a work. We all know what preliminary means. It means we’re not
done yet. We have a preliminary design, we have a preliminary cost estimate,
or a preliminary list of subcontractors. We know enough about the project to
make some decisions, but we need more details before we can say for sure
the cost, the design, and the subcontractors are all in place.
This incremental approach allows us to move foreword without all the details,
while still having visibility into what Done looks like.
Since many projects are discovery driven, planning needs to be increasing
maturity driven without the planning horizon.
Page 171:08
5 Proven Approaches for Mitigating Project Failure
Projects are executed by people.
People consume time, money, and materials.
How can we know if we have enough of everything we need for success?
We need a Plan of course, in this case a Resource Management Plan,
showing people, funding, and materials, and when and where we need it.
We can start with a simple list. This gets us to write it down.
Next we need to assign people and money to the needed resources. How
many of each special skill type will we need for this project.
In the end though, we need to lay out these needs against the schedule of
work. We need to resource load the schedule. This sounds like a lot of work
and it is. But without this in place we really have no idea if the project is
feasible.
Page 180:40
5 Proven Approaches for Mitigating Project Failure
We usually start by identifying risks. But risk is the result of uncertainty. There
are two types of uncertainty – reducible uncertainty and irreducible uncertainty.
We can do something about reducible uncertainty. We can buy more
knowledge about this uncertainty – it is epistemic. We can run tests, build
prototypes, look at what others have done. The risk that results is reducible.
The irreducible uncertainty is part of the world around use. This uncertainty
cannot be reduced – it is Aleatory uncertainty. The only way to deal with this
uncertainty is through margin. Cost margin, schedule margin, technical
margin.
We have to start by identifying these uncertainties and associating them with
the risks.
Then the impacts of the risk are identified along with their dependencies.
The probability of occurrence and the probability of their impact can be
assessed.
With these impediments in hand we can take actions to either protect our
project with margin or spend money to retire or handle the resulting risk.
Page 190:57
5 Proven Approaches for Mitigating Project Failure
With our Plan, Schedule, Resources, and Risk Management Plan, we can now
determine how we are going to measure progress to these plans.
The customer bought outcomes, deliverables, capabilities. We need to
describe these in a way the customer understands. Units of measure that are
meaningful for making decisions.
These are best described as Technical Performance Measures. These are
attributes that determine how well a system or system element is satisfying or
expected to satisfy a technical requirement or goal
But these alone are not sufficient for the success of the project. We need
Measures of Effectiveness (MoE), Measures of Performance (MoP), and Key
Performance Parameters (KPP).
MoEs are operational measures of success that are closely related to
the achievements of the mission or operational objectives evaluated in
the operational environment, under a specific set of conditions.
MoPs characterize physical or functional attributes relating to the
system operation, measured or estimated under specific conditions.
KPPs represent the capabilities and characteristics so significant that
failure to meet them can be cause for reevaluation, reassessing, or
termination of the program.
Page 201:09
5 Proven Approaches for Mitigating Project Failure
If we don’t have a plan. If we don’t have the proper resources available at the
needed time. If we don’t handle risks if we don’t have measures of physical;
percent complete.
We can’t have confidence the project will be successful.
Without these elements, the probability of project success is reduced. Possibly
to the point of project failure.
Without these elements, we have created risk to our success with no handling
plans.
It is this unmitigated risk that creates the unanticipated growth in our Estimate
At Completion.
Page 210:29
5 Proven Approaches for Mitigating Project Failure
Over a large number of complex, high risk programs there have been a small
number of root causes discovered for failure.
There are shown here.
Reading them they seem obvious.
Dealing with them is more difficult .
But we must deal with them and we must have information needed to deal with
them.
This information comes from the tools and processes used to manage the
project.
Scheduling, cost, risk, performance measurement, and forecasting tools and
the processes used to apply them.
Only when all this information, integrated though a single “lens” can we have
the needed visibility to take corrective action to keep the project GREEN.
Stay on schedule, stay on budget, comply with the technical requirements. Or
if not, know about the variances soon enough to take corrective action.
Page 220:41
5 Proven Approaches for Mitigating Project Failure
Let’s quickly review the 5 principles of project success in the time remaining.
What does done look like? The customer needs to know what capabilities will
be possessed when the project is done. The capabilities produce the business
value or fulfill the mission objective.
How do we get there? We need a plan and a schedule. We need to sequence
the work properly in the order to produce continuous value.
Are there enough resources? People, material, facilities? Are they the right
people, does the material arrive at the needed time, are the facilities adequate
to produce the needed outcomes?
What are the impediments to progress? Risk management is how adults
manage projects. Do we have a risk register? Do the risks have handling
plans? Is the cost and schedule baseline adjusted for these risks?
How do we measure progress? The only way is tangible evidence of physical
percent complete. This means “show me” the outcomes and show me they
meet the specifications, on the planned day for the planned cost. If not we’re
late, over budget, and out outcomes probably don’t work right.
Page 230:57
5 Proven Approaches for Mitigating Project Failure
24
5 Proven Approaches for Mitigating Project Failure

More Related Content

What's hot

Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellGlen Alleman
 
Project management best practices
Project management best practicesProject management best practices
Project management best practicesJackson Chan
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Phil Comelio
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Glen Alleman
 
Software Quality Dashboard Benchmarking Study
Software Quality Dashboard Benchmarking StudySoftware Quality Dashboard Benchmarking Study
Software Quality Dashboard Benchmarking StudyJohn Carter
 
Speak Like a Test Manager
Speak Like a Test ManagerSpeak Like a Test Manager
Speak Like a Test ManagerTechWell
 
The Good, The Bad, and The Metrics
 The Good, The Bad, and The Metrics The Good, The Bad, and The Metrics
The Good, The Bad, and The MetricsTeamQualityPro
 
Project Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesProject Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesSlideTeam
 
5 immutable principles of project success (v3)(notes)
5 immutable principles of project success (v3)(notes)5 immutable principles of project success (v3)(notes)
5 immutable principles of project success (v3)(notes)Glen Alleman
 
Flawless Project Execution The Road To Greatness For Professional Services Firms
Flawless Project Execution The Road To Greatness For Professional Services FirmsFlawless Project Execution The Road To Greatness For Professional Services Firms
Flawless Project Execution The Road To Greatness For Professional Services Firmsarjencornelisse
 
If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...p6academy
 
Agile Development
Agile DevelopmentAgile Development
Agile Developmentabdpse
 
Requirements = Scope
Requirements = ScopeRequirements = Scope
Requirements = ScopeCraig Brown
 
Project Management Best Practices: Brock Boddie/General Assembly
Project Management Best Practices: Brock Boddie/General AssemblyProject Management Best Practices: Brock Boddie/General Assembly
Project Management Best Practices: Brock Boddie/General AssemblyGeneral Assembly
 
An Agile approach to Business Metrics
An Agile approach to Business MetricsAn Agile approach to Business Metrics
An Agile approach to Business MetricsPablo Valcárcel
 
Agile Metrics...That Matter
Agile Metrics...That MatterAgile Metrics...That Matter
Agile Metrics...That MatterErik Weber
 

What's hot (20)

Performance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut ShellPerformance-Based Project Management In A Nut Shell
Performance-Based Project Management In A Nut Shell
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?Why Do So Many Software Projects Fail?
Why Do So Many Software Projects Fail?
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®
 
Software Quality Dashboard Benchmarking Study
Software Quality Dashboard Benchmarking StudySoftware Quality Dashboard Benchmarking Study
Software Quality Dashboard Benchmarking Study
 
Speak Like a Test Manager
Speak Like a Test ManagerSpeak Like a Test Manager
Speak Like a Test Manager
 
Agile by numbers
Agile by numbersAgile by numbers
Agile by numbers
 
Pre mortem-pradeeep patel
Pre mortem-pradeeep patelPre mortem-pradeeep patel
Pre mortem-pradeeep patel
 
The Good, The Bad, and The Metrics
 The Good, The Bad, and The Metrics The Good, The Bad, and The Metrics
The Good, The Bad, and The Metrics
 
Project Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation SlidesProject Prioritizing Model Powerpoint Presentation Slides
Project Prioritizing Model Powerpoint Presentation Slides
 
Agile Metrics V6
Agile Metrics V6Agile Metrics V6
Agile Metrics V6
 
5 immutable principles of project success (v3)(notes)
5 immutable principles of project success (v3)(notes)5 immutable principles of project success (v3)(notes)
5 immutable principles of project success (v3)(notes)
 
Flawless Project Execution The Road To Greatness For Professional Services Firms
Flawless Project Execution The Road To Greatness For Professional Services FirmsFlawless Project Execution The Road To Greatness For Professional Services Firms
Flawless Project Execution The Road To Greatness For Professional Services Firms
 
Going Agile
Going  AgileGoing  Agile
Going Agile
 
If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...If you dont know where you are going any road will do visioning for implement...
If you dont know where you are going any road will do visioning for implement...
 
Agile Development
Agile DevelopmentAgile Development
Agile Development
 
Requirements = Scope
Requirements = ScopeRequirements = Scope
Requirements = Scope
 
Project Management Best Practices: Brock Boddie/General Assembly
Project Management Best Practices: Brock Boddie/General AssemblyProject Management Best Practices: Brock Boddie/General Assembly
Project Management Best Practices: Brock Boddie/General Assembly
 
An Agile approach to Business Metrics
An Agile approach to Business MetricsAn Agile approach to Business Metrics
An Agile approach to Business Metrics
 
Agile Metrics...That Matter
Agile Metrics...That MatterAgile Metrics...That Matter
Agile Metrics...That Matter
 

Similar to 5 Proven Approaches for Project Success

Five immutable principles of project success
Five immutable principles of project successFive immutable principles of project success
Five immutable principles of project successGlen Alleman
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineGlen Alleman
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baselineguest9da059
 
The Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccessThe Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccessGlen Alleman
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersGlen Alleman
 
5 immutable principles of project success (v2)(notes)
5 immutable principles of project success (v2)(notes)5 immutable principles of project success (v2)(notes)
5 immutable principles of project success (v2)(notes)Glen Alleman
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 secondsGlen Alleman
 
Gestión de Proyectos y mejores practicas
Gestión de Proyectos y mejores practicas Gestión de Proyectos y mejores practicas
Gestión de Proyectos y mejores practicas ✔Alejandro J. Román
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesGlen Alleman
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleKate Pynn
 
20 things you should know
20 things you should know20 things you should know
20 things you should knowPiet Neirinck
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementRobert McGeachy
 
The Value PMLC Process Capability
The Value PMLC Process CapabilityThe Value PMLC Process Capability
The Value PMLC Process CapabilityBill Monroe
 
Release Management: Managing Your Internal Releases
Release Management: Managing Your Internal ReleasesRelease Management: Managing Your Internal Releases
Release Management: Managing Your Internal ReleasesJoshua Hoskins
 
Managing your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environmentManaging your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environmentStephen Hightower
 
Strategy Deployment: Accelerating Improvement Through Focus and Alignment
Strategy Deployment: Accelerating Improvement Through Focus and AlignmentStrategy Deployment: Accelerating Improvement Through Focus and Alignment
Strategy Deployment: Accelerating Improvement Through Focus and AlignmentTKMG, Inc.
 

Similar to 5 Proven Approaches for Project Success (20)

Five immutable principles of project success
Five immutable principles of project successFive immutable principles of project success
Five immutable principles of project success
 
Del
DelDel
Del
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
The Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccessThe Five Immutable Principles of Project DSuccess
The Five Immutable Principles of Project DSuccess
 
A Guide for Capital Project Mamnagers
A Guide for Capital Project MamnagersA Guide for Capital Project Mamnagers
A Guide for Capital Project Mamnagers
 
5 immutable principles of project success (v2)(notes)
5 immutable principles of project success (v2)(notes)5 immutable principles of project success (v2)(notes)
5 immutable principles of project success (v2)(notes)
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
 
Gestión de Proyectos y mejores practicas
Gestión de Proyectos y mejores practicas Gestión de Proyectos y mejores practicas
Gestión de Proyectos y mejores practicas
 
Project Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable PrinciplesProject Success: The Basis of the Five Immutable Principles
Project Success: The Basis of the Five Immutable Principles
 
Project Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training ExampleProject Plan Development - A FlackVentures Training Example
Project Plan Development - A FlackVentures Training Example
 
L 63 Article Successful PM
L 63 Article Successful PML 63 Article Successful PM
L 63 Article Successful PM
 
20 things you should know
20 things you should know20 things you should know
20 things you should know
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project Management
 
The Value PMLC Process Capability
The Value PMLC Process CapabilityThe Value PMLC Process Capability
The Value PMLC Process Capability
 
Release Management: Managing Your Internal Releases
Release Management: Managing Your Internal ReleasesRelease Management: Managing Your Internal Releases
Release Management: Managing Your Internal Releases
 
Managing your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environmentManaging your projects effectively in a shared resource environment
Managing your projects effectively in a shared resource environment
 
Strategy Deployment: Accelerating Improvement Through Focus and Alignment
Strategy Deployment: Accelerating Improvement Through Focus and AlignmentStrategy Deployment: Accelerating Improvement Through Focus and Alignment
Strategy Deployment: Accelerating Improvement Through Focus and Alignment
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Recently uploaded

Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 

Recently uploaded (20)

Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate AgentsRyan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
Ryan Mahoney - Will Artificial Intelligence Replace Real Estate Agents
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 

5 Proven Approaches for Project Success

  • 1. Thank you for attending our webcast today. This topic should be one we all are familiar with, since it is nearly impossible to not have experienced a project failure at least once in our career. We usually start our project management quest with capturing requirements, building a schedule to deliver them, executing that schedule, and making adjustments along the way when we’re not staying on schedule. The principles I’m going to speak to you about are universal. Applicable to any project, of any size, in any domain. What you’re going to hear is not the solution to avoid project failure. It is the framework for project success. The actual mechanics of managing a project are based on these principles. The practices used in this management should be based on the se principles. And of course the process ad tools should implement the practices. 5 Proven Approaches for Mitigating Project Failure Page 10:44
  • 2. Nearly every business activity is based on a project in some way. Even the operational aspects of a business are projectized through processes, procedures, and business management governance. Today I’d like to focus on the types of projects Land speaks of. The really important ones that are nearly impossible. I was a participant in one of those projects – Rocky Flats Environmental Technology Site. The name of the site was a nice marketing term for the cleanup of a nuclear bomb factory. It was nearly impossible. And manifestly important The previous contractor had spent $4B and not done much. When Kaiser-Hill (a joint venture between ICF Kaiser and CH2MHill) won the contract for $7B, they had a plan that was dramatically different from the past attempts to cleanup and close the site. This plan focused on applying the 5 Immutable Principles, defining the “packages of work” that delivered the outcomes, measuring progress as physical percent complete, and risk adjusting everything to produce a credible Estimate to Complete on a weekly basis for 5,000 staff working on site. Page 21:06 5 Proven Approaches for Mitigating Project Failure
  • 3. I’m going to present 5 Immutable Principles today that are the foundation of project success. These Principles are “Immutable” because they must always be present. They are the foundation on which the Practices and Processes are built. We won’t look at the Practices and Processes, but they are critical to the success of any project as well. Those are available in the book from AMACOM. Page 30:20 5 Proven Approaches for Mitigating Project Failure
  • 4. There are nearly unlimited reasons for project failures. Root Cause Analysis is the means to separate the symptoms of project difficulties from the actual causes of those difficulties. If the Root Cause is not found, prevented or corrected, it will reappear. This is a short list of Root Causes. You’ll likely have your own list, but I suspect it will overlap with these. 4 5 Proven Approaches for Mitigating Project Failure
  • 5. With this background, let’s start with the 5 Immutable Principles of Project Success. I would suggest these are applicable in any technical domain. Any project management method. Any business domain. They are universal and Immutable – meaning they don’t change over time. They are permanent principles that must be applied for the success of any project. The Principles are in the form of questions in this example. There are more formal statements about the Principles, but starting by asking 5 questions shows how the principles can be applied in any situation. When there is not a credible answer to the question, this is an indication there is likely trouble on the project and the probability of success has been lowered. Page 50:40 5 Proven Approaches for Mitigating Project Failure
  • 6. With the Principles and Practices, we need Processes to put to work. Some of you may recognize these as part of the Earned Value Management processes in EIA-748-C. But there are also the basis of all good project management work. You really can’t be managing a project – in any credible manner – if you are doing these 11 processes. • What are we building? • Who’s on our team? • Who’s doing what? • What’s the sequence of the work? • What are the outcomes of that work? • What’s the budget for the work to produce those outcomes? • What did it cost to produce each outcome? • What was the difference between our budget and the actual costs? • What’s the total differences for the entire project? • What are we going to change to get back on budget and schedule? • Did we record these changes? 6 5 Proven Approaches for Mitigating Project Failure
  • 7. We keep using the term Deliverable. Here’s what that means. It means the customer bought something they can put to work to fulfill a business case or accomplish a mission. The deliverables, taken individual are just individual functions of the project. Taken as whole, they provide a set of capabilities that can be used by the customer to accomplish something. Along the way, each deliverable increases the maturity of the projects capabilities. We can start with a few deliverables. The customer may or may not be able to accomplish something with those deliverables, but their presence may be necessary for further deliverables to provide a capability. There is a myth in the agile development business, that Value products need to be delivered starting on day one. This may be appropriate for simple projects. But most complex systems have pre-conditions for success. We need to install the Database Server before we can use build databases. We have foundation activities on which we build other capabilities. So the challenge is to determine the order of the needed capabilities to reach the needed maturity at the time that maturity is needed 7 5 Proven Approaches for Mitigating Project Failure
  • 8. So let’s revisit our 5 Immutable Principles once more with the Practices and Processes in hand. • What does our customer need to fulfill their business case or accomplish their mission? • What are the technical and operational requirements that must be delivered to fulfill that mission? • What’s the schedule for that work? • How are we going to measure progress to plan? • What impediments are we going to encounter along the way and how are we going to deal with them, so they don’t impact the success of our project? This is the basis of Capabilities Based Planning. It’s the capabilities that are delivered. These are enabled by through the deliverables appearing tin the right order, fulfilling the right requirements, each building on the previous requirements and capabilities. 8 5 Proven Approaches for Mitigating Project Failure
  • 9. Traditional project management is a good foundation for all project work. Performance-Based Project Management® adds another paradigm to that foundation – we measure progress to plan in terms of performance outcomes. This separate Output (effort, cost, deliverables) from Outcomes (the capability to do something needed for success). Performance-Based Project Management® is risk based, from Tim Lister’s advice Risk Management is How Adults Manage Projects. 9 5 Proven Approaches for Mitigating Project Failure
  • 10. Here’s how to assemble the Practices to increase the probability of project success. This is a simple diagram, showing the order of work. • Answer the question Why Do We Need This – by defining the needed capabilities. If you start with requirements, you may or may not know why those requirements are there. What there purpose is. These capabilities have Measures of Effectiveness. • Identify the requirements that produce the capability to do something. These requirements have Measures of Performance. • Layout all the work in the right sequence – this can be an agile sequence, with current releases, future release, sprints and the like. But knowing what capabilities we’ll need for project success is a Critical Success Factor, no mater what development method you use. • Execute that sequence of work and measure physical percent complete to plan. • Along the way, make sure you have all the risks identified, handled, and the results included in future planning processes 10 5 Proven Approaches for Mitigating Project Failure
  • 11. So let’s move to the next step. Applying the Practices and Processes 11 5 Proven Approaches for Mitigating Project Failure
  • 12. The first Principle is to assure we know what Done looks like. This sounds like a simple process. But turns out to be the root cause of most project failures. Done is not described in any meaningful units of measure for the decision makers. Our first response is usually to make a list of features and functions for the product or service produced by the project. This is necessary but far from sufficient to describe Done. We don’t know how these features and functions interact, how and when they provide value to the customer. The interdependencies are next. We need to show how each feature or function is dependent – if it is – on other features and functions. This usually starts with the Work Breakdown Structure (WBS) showing all the deliverables from the project. The WBS needs a WBS Dictionary to show how we are going to measure the performance, quality, compliance of these outcomes with each other and the customer. But the WBS and its Dictionary are not enough to know what Done looks like. We need to know what Capabilities are being provided by the project. What is the customer going to DO with these outcomes? How are they going to satisfy the business needs or mission? The Capability to do something is what the customer bought. Page 121:08 5 Proven Approaches for Mitigating Project Failure
  • 13. These Capability statements are clear and concise. Long before we ever arrived in the moon, Robert Goddard knew what capabilities were needed to get there. On October 19, 1899, Goddard climbed a dead tree to trim some branches. He was 17. He is quoted as saying … “I imagined,” he later recalled, “how wonderful it would be to make some device which had even the possibility of ascending to Mars, and how it would look on a small scale, if sent up from the meadow at my feet. . . I was a different boy when I descended the tree from when I ascended, for existence at last seemed very purposive.” He had in his mind what capabilities were needed to fly outside the Earths atmosphere. He knew some of the units of measure that had to be fulfilled to do this. If we don’t have some vision of the project at the Capabilities level, we really can’t say what Done looks like. We can describe the technical aspects, but we can’t say what we are going to do with those technical aspects. This definition of Capabilities is a Systems Engineering role. There are formal processes to elicit these Capabilities through the Concept of Operations, Scenarios, and Use Cases, making tradeoffs between cost, risk, schedule, and technical performance, and balancing all the feasible alternatives. The result is the Measures of Effectiveness which tell the customer the project will meet the needed capabilities. Page 131:15 5 Proven Approaches for Mitigating Project Failure
  • 14. With the needed Capabilities we can now develop a plan and schedule for the work. Knowing how to get Done on–budget and on–schedule means knowing what requirements will have to be fulfilled. Poorly formed requirements contribute as much as 25% to the failure modes of programs and projects. This starts with Fact Finding, Gathering and Classifying the Requirements, Evaluating and Rationalizing the Requirements, Prioritizing them, and Integrating and Validating the Requirements. With this in hand we can start building the packages of work that implement the requirements. The result is a Plan and a Schedule. The Plan is the Strategy for the proper delivery of the Capabilities produced by the project. The Schedule is the sequence of work needed to implement the Strategy. Both are needed. The Plan is emergent, since it is a strategy. The Schedule tests this strategy on short term boundaries, with measures of physical percent complete. Both the Plan and the Schedule must be capable of responding to change as new information about requirements, program performance, and risks emerge. But the needed capabilities should remain stable if we are to have a baseline on which to execute our project. Page 141:05 5 Proven Approaches for Mitigating Project Failure
  • 15. The Plan can be very simple or it can be complex. Here’s a plan that took us to the moon and back. This picture shows a simple concept. Build the launch vehicle, the fuel to power it, the space craft on the top, train the astronauts, do the testing, and fly. The Plan shows the 6 major systems , their approximate duration in years, and the dependencies between them are all that is needed to confirm the feasibility of the project. Notice the longest activity is the training of the crew. No one had ever flown in space before all the way to the moon and back. So training was high risk and critical to success. Page 150:35 5 Proven Approaches for Mitigating Project Failure
  • 16. One view of the Plan is the vertical integration of the deliverables. This is the deliverables traceability view. At the bottom is our deliverable. The deliverable is produced by work contained in a work package. A Work Package says its name. it produces a single outcome. The technical capabilities needed for the project’s success are produced by the Work Packages. Finally these Technical Capabilities produce business or mission capabilities needed by the customer for project success. This traceability is necessary for a credible Plan and Schedule. It is also necessary for a credible project delivery process. This traceability tells everyone what Done looks like and how we are going to get there. Page 160:35 5 Proven Approaches for Mitigating Project Failure
  • 17. With the Plan in place and the “packages of work” identified in the Schedule, we can construct a picture of how we are going to reach Done. This picture is not like the typical horizontal scheduling activities we see in all the scheduling tools. This picture starts with the vertical integration of the deliverables as they progress through their maturity life cycle. This is called the Integrated Master Plan. This Plan shows the Measures of Effectiveness and Measures of Performance we need to achieve to reach a specific level of maturity. This notion of levels of maturity can be seen is we use some words Preliminary is a work. We all know what preliminary means. It means we’re not done yet. We have a preliminary design, we have a preliminary cost estimate, or a preliminary list of subcontractors. We know enough about the project to make some decisions, but we need more details before we can say for sure the cost, the design, and the subcontractors are all in place. This incremental approach allows us to move foreword without all the details, while still having visibility into what Done looks like. Since many projects are discovery driven, planning needs to be increasing maturity driven without the planning horizon. Page 171:08 5 Proven Approaches for Mitigating Project Failure
  • 18. Projects are executed by people. People consume time, money, and materials. How can we know if we have enough of everything we need for success? We need a Plan of course, in this case a Resource Management Plan, showing people, funding, and materials, and when and where we need it. We can start with a simple list. This gets us to write it down. Next we need to assign people and money to the needed resources. How many of each special skill type will we need for this project. In the end though, we need to lay out these needs against the schedule of work. We need to resource load the schedule. This sounds like a lot of work and it is. But without this in place we really have no idea if the project is feasible. Page 180:40 5 Proven Approaches for Mitigating Project Failure
  • 19. We usually start by identifying risks. But risk is the result of uncertainty. There are two types of uncertainty – reducible uncertainty and irreducible uncertainty. We can do something about reducible uncertainty. We can buy more knowledge about this uncertainty – it is epistemic. We can run tests, build prototypes, look at what others have done. The risk that results is reducible. The irreducible uncertainty is part of the world around use. This uncertainty cannot be reduced – it is Aleatory uncertainty. The only way to deal with this uncertainty is through margin. Cost margin, schedule margin, technical margin. We have to start by identifying these uncertainties and associating them with the risks. Then the impacts of the risk are identified along with their dependencies. The probability of occurrence and the probability of their impact can be assessed. With these impediments in hand we can take actions to either protect our project with margin or spend money to retire or handle the resulting risk. Page 190:57 5 Proven Approaches for Mitigating Project Failure
  • 20. With our Plan, Schedule, Resources, and Risk Management Plan, we can now determine how we are going to measure progress to these plans. The customer bought outcomes, deliverables, capabilities. We need to describe these in a way the customer understands. Units of measure that are meaningful for making decisions. These are best described as Technical Performance Measures. These are attributes that determine how well a system or system element is satisfying or expected to satisfy a technical requirement or goal But these alone are not sufficient for the success of the project. We need Measures of Effectiveness (MoE), Measures of Performance (MoP), and Key Performance Parameters (KPP). MoEs are operational measures of success that are closely related to the achievements of the mission or operational objectives evaluated in the operational environment, under a specific set of conditions. MoPs characterize physical or functional attributes relating to the system operation, measured or estimated under specific conditions. KPPs represent the capabilities and characteristics so significant that failure to meet them can be cause for reevaluation, reassessing, or termination of the program. Page 201:09 5 Proven Approaches for Mitigating Project Failure
  • 21. If we don’t have a plan. If we don’t have the proper resources available at the needed time. If we don’t handle risks if we don’t have measures of physical; percent complete. We can’t have confidence the project will be successful. Without these elements, the probability of project success is reduced. Possibly to the point of project failure. Without these elements, we have created risk to our success with no handling plans. It is this unmitigated risk that creates the unanticipated growth in our Estimate At Completion. Page 210:29 5 Proven Approaches for Mitigating Project Failure
  • 22. Over a large number of complex, high risk programs there have been a small number of root causes discovered for failure. There are shown here. Reading them they seem obvious. Dealing with them is more difficult . But we must deal with them and we must have information needed to deal with them. This information comes from the tools and processes used to manage the project. Scheduling, cost, risk, performance measurement, and forecasting tools and the processes used to apply them. Only when all this information, integrated though a single “lens” can we have the needed visibility to take corrective action to keep the project GREEN. Stay on schedule, stay on budget, comply with the technical requirements. Or if not, know about the variances soon enough to take corrective action. Page 220:41 5 Proven Approaches for Mitigating Project Failure
  • 23. Let’s quickly review the 5 principles of project success in the time remaining. What does done look like? The customer needs to know what capabilities will be possessed when the project is done. The capabilities produce the business value or fulfill the mission objective. How do we get there? We need a plan and a schedule. We need to sequence the work properly in the order to produce continuous value. Are there enough resources? People, material, facilities? Are they the right people, does the material arrive at the needed time, are the facilities adequate to produce the needed outcomes? What are the impediments to progress? Risk management is how adults manage projects. Do we have a risk register? Do the risks have handling plans? Is the cost and schedule baseline adjusted for these risks? How do we measure progress? The only way is tangible evidence of physical percent complete. This means “show me” the outcomes and show me they meet the specifications, on the planned day for the planned cost. If not we’re late, over budget, and out outcomes probably don’t work right. Page 230:57 5 Proven Approaches for Mitigating Project Failure
  • 24. 24 5 Proven Approaches for Mitigating Project Failure