EARNING VALUE FROM EARNED
VALUE
USING EV TO IMPROVE THE
PROBABILITY OF PROJECT SUCCESS
EVM WORLD 2009
PMI-CPM 25TH ANNUAL
INTERNATIONAL CONFERENCE
1
Learning Outcomes
 Cost and Schedule Indices (SPI, CPI, TCPI, and IEAC)
do not represent the underlying statistical nature of
projects.
 Modeling this statistical behavior requires addition
activities build around Monte Carlo simulation and
stochastic modeling.
 Creating value from the Earned Value requires both
bottom-up and a top-down work processes.
2
3
Creating Value from EV is More Than Calculating SPI and CPI
LAUNCH ABORT SYSTEM FOR ORION CAPSULE
 What are the technical requirements that fulfill the mission
capabilities?
 How is the work partitioned for the producing the deliverables
that fulfill these requirements?
 What are the Work Packages, Cost and Schedule elements
and programmatic risk elements to assure on-time, on-
budget performance?
CONSTELLATION MISSION TO THE MOON
 What capabilities are needed to fulfill the mission?
 How are these capabilities connected to the technical and
operational requirements?
 What are the programmatic trade space decisions between
capabilities, requirements, cost and schedule?
BRICK LAYING PROJECT
 What are the measures of scope, effort, and duration?
 What are the measures of physical percent complete?
 Can we forecast of final cost and completion date?
What Does Done Look Like?
How will we recognize done?
What is the unit of measure of Done?
Questions Every Program Manager Needs to Ask
and Answer
 How much money will I need to complete this
program on time and on specification?
 What is my confidence that we’ll complete on or
before the planned finish date?
 Do I have enough management reserve to protect
this finish date?
 What is the inherent risk built into my cost and
schedule baseline?
 How can I tell if the program is making progress to
plan?
4
GAINING COMPLIANCE WITH
THE EARNED VALUE GUIDANCE
THE BOTTOM UP APPROACH
5
The Logical Starting Point Of
The Earned Value Journey
6
This progress is
represented by physical,
tangible, measurably
quantifiable evidence.
 How much did we
plan to get done on
this date, measured in
Dollars?
 How much did we
actually get done on
this date, measured in
Dollars?
In This Standard Paradigm …
Earned Value = Physical Percent Complete of the Planned Value
7
What About the Planned Technical Performance?
We’re On Schedule, On Budget
But We Had A Slight Technical Problem With Our Flying Machine
8
9
From the NDIA Earned Value Intent Guide (EVIG)
Notice the inclusion of Technical along with
Cost and Schedule
That’s the next step is generating Value from Earned Value
EV MUST include the Technical Performance Measures
10
 Relate time-phased budgets to specific contract tasks and/or statements of
work (SOW)
 Objectively measure work progress
 Properly relate cost, schedule, and technical accomplishment
 Allow for informed decision making and corrective action
 Is valid, timely, and able to be audited
 Allow for statistical estimation of future costs
 Supply managers at all levels with status information at the appropriate
level, and
 Is derived from the same EVM system used by the contractor to manage
the contract.
The First Set of Promises That Need Actionable Steps
 The EV numbers are just
numbers
 They can show trends
 They can be the basis of
forecasts
 But they must be placed in a
context of an underlying
statistical model
 They must be connected with
the relationship between time
and money
11
Moving from reporting the past
performance to forecasting the
future is the first step in Earning
Value from Earned Value
Management
Does Money
Equal Time?
This is How EV
Measures
Schedule
Variance
But What If It Is
Not Linear?
Time Is Not Money
Unless They Are
Linearly Related
12
The REAL Problem
Models Of Earned Value Are Inherently Probabilistic With Interdependent
Couplings Between Network Elements
13
Using Static, Deterministic, and
Decoupled Measures of Performance
(e.g. The Standard EV Model)
is at best…
14
But Let’s Visit A High Level View of the Earned Value Activities
15
The 32 Criteria for a ANSI/EIA-748B Compliant
Earned Value Management System
16
MANAGEMENT PROCESSES
EXTRACTED FROM 748B
17
Questions Every Program Manager Needs to Ask
and Answer – Part 2
 How much money will I need to complete this
program on time?
 What is my confidence that we’ll complete on or
before the planned finish date?
 Do I have enough management reserve?
 What is the inherent risk built into my cost and
schedule baseline?
 How can I tell if the program is making progress to
plan?
CAN WE MEASURE THE BENEFITS
OF EARNED VALUE
MANAGEMENT?
How Can We
Get A Return
On Our
Investment In
Earned Value?
20
Some Straight Forward Benefits†
 Better Visibility into Program Performance
 Reduce Cycle Time to Deliver a Product
 Foster Accountability
 Reduce Risk
† From the DACS Gold Practices “Track Earned Value” Focus Area
The Missing Piece Is “How” To Obtain
These Benefits
 How do we create better visibility into the program’s performance?
 How do we reduce cycle time to deliver the product?
 How do we foster accountability?
 How do we reduce risk?
Deploying Earned Value Alone Will Not Get Us There
How Do We Get From Where We Are To Our Destination?
22
Claimed Benefit The Reason The Method to Achieve
Better Visibility
into Program
Performance
The combination of advance
planning, baseline maintenance,
and earned value analysis yields
earlier and better visibility into
program performance than is
provided by non-integrated
methods of planning and
control.
 This requires a credible baseline.
But this baseline must be more
than just a list of work, it must
represent the “Programmatic
Architecture” of the system,
matching the technical
architecture.
 This programmatic architecture
formulates the flow of work that
produces products with
increasing maturity.
Step Action Details
Define the
Integrated Master
Plan (IMP)
The IMP is the Strategy for the successful completion of the program.
It is formed from Program Events, the Significant Accomplishments
(SA), and their Accomplishment Criteria (AC).
Sequence the SAs The sequence of SAs for each single PE by the IPT’s is a diagram
sufficiently detailed to show how the increasing maturity of the
deliverables can be achieved.
Assign Budget
Estimates (BOE)
Collect the initial “basis of estimate” from the duration and sequence
of these SAs
23
Claimed Benefit The Reason The Method to Achieve
Reduces Cycle
Time to Deliver
a Product
Earned Value Management is
premised on careful detailed
planning – task decomposition,
scheduling, and budgeting.
This planning often addresses or
prevents problems from surfacing
later in the effort that result in
rework.
As rework is prevented cycle time
may be reduced.
 Again the carefully detailed plan
must adequately represent a
credible schedule, cost
allocation, and resource
assignments.
 How can we know this is the
case?
Step Action Details
Reduce cycle
time by
forecasting
delay
Using TCPI and IEAC the macro level forecast (scalar) can be generated.
What is needed is to locate the specific tasks that are the source of this
delay. This is a network analysis process.
Identify
alternative paths
through the IMS
With the network process flow indentified, alternative paths can be
assessed. These path have associated cost and down stream schedule
impacts that need further analysis.
Probabilistic cost
and schedule
The result is a probabilistic cost and schedule analysis coupled with a
Monte Carlo simulation tool to construct the “probabilistic critical path?
24
Claimed Benefit The Reason The Method to Achieve
Fosters
Accountability
When the engineer understands
how the pieces fit the overall
project effort, they tend to focus
on delivery of a quality product.
Over time they are better able to
estimate the work required to
complete a task, thereby
improving the overall accuracy of
the budget / estimating process
for future efforts.
 Defining the logical sequence of
product or service flow is the
starting point.
 This “systems engineering”
approach starts with a
description of the “increasing
maturity” of the product or
service, and only then assigning
the Earned Value elements
Step Action Details
Work Package
budgets owned
by producers of
value
Once the Value Stream as been defined – this is the logical flow of the
Significant Accomplishment – the ownership for producing this value is
identified in the Work Package owners.
Dependencies
between WPs is a
Systems
Engineering
process
The Value Stream of the collection of Work Package must remove an
impediments to maximizing this value. This is the role of the planning
and controls staff in conjunction with the subject matter experts
accountable for delivering the technical solution. As a collective they
are accountable for the resulting value stream.
25
Claimed Benefit The Reason The Method to Achieve
Reduces Risk Because earned value measures
enable realistic estimates of
completion to be derived early in
the project, it is possible to make
adjustments and take corrective
action to mitigate the risk of cost
overruns and schedule slippage.
 Probabilistic risk analysis
requires a credible baseline and
an understanding of the
underlying probabilistic process
driving cost, schedule, and
technical performance
 If the probabilistic process is
stationary, a Monte Carlo
simulation can be used to
analyze the behaviors of the
system only as a stationary
model.
Step Action Details
Probabilistic
modes expose
risk
Only probabilistic models “enable realistic estimates.” No point
estimate in the absence of a variance is credible.
Risk adjusted
work in IMS
All risk mitigation and retirement activities need to be in the IMS, along
with funding profiles and probabilistic assessment of their
effectiveness. EV alone will not address the issues. An active Risk
Management process is needed.
26
STEPS NEEDED TO EARN THE
VALUE FROM EARNED VALUE
THE TOP DOWN APPROACH
27
28
The Cost of These
Benefits Is Already Built
Into a Credible PMB
 The BCWS spreads define visibility
into costs
 The sequence of Significant
Accomplishments (SA) defines
visibility into deliverables
 Risk mitigations, buy downs, and
retirements are embedded in the PMB
 Small incremental measures of value
are defined by Work Packages
 Visibility provided through measures
of physical percent complete
 Reduced cycle is actually just
maintaining the planned completion
dates, on budget, that meet the
planned technical performance
measurements
Five Core Processes of Successful Program
Planning and Controls
29
Program Success Process Areas Questions To Be Answered
Identify Needed System Capabilities
What capabilities are needed to fulfill the
ConOps and System Requirements?
Establish the Requirements Baseline
What technical and operational
requirements are needed to fulfill these
capabilities?
Establish the Performance Measurement
Baseline
What is the schedule that delivers product
or services that meet the requirements?
Execute the Performance Measurement
Baseline
What are the periodic measures of
physical percent complete?
Perform Continuous Risk Management
What are the impediments to success and
what are the mitigations ?
 Partition system capabilities into classes of service within operational scenarios
 Connect capabilities to system requirements using sysML
 Define Measures of Effectiveness (MOE) and Measures of Performance (MOP)
 Define in the delivery schedule the achievement of each Technical Performance Measure
Define
Operational
Concepts
 Define scenarios for each system capability
 Connect these scenarios to a Value Stream Map of the increasing maturity of the program
 Assess value flow through the map for each needed capability
 Identify capabilities mismatches and make corrections to improve overall value flow
Define
Capabilities
Needed To
Implement
Concepts
 Assign costs to a system element using a value model process model
 Assure risk, probabilistic cost and benefit performance attributes are defined
 Use cost, schedule and technical performance probabilistic models to forecast
potential risks to program performance
Assess Needs,
Costs and Risks
Simultaneously
 Make tradeoffs that connect cost, schedule, and technical performance in a single “trade
space” model
 Measures of Effectiveness and Measures of Performance are the raw materials for
these tradeoffs
Define
Explicit,
Balanced, and
Feasible
Alternatives
Define the set of capabilities to be employed to achieve desired objectives or a particular end
state for a specific scenario. Take the ConOps and define the details of who, where, and how
it is to be accomplished, employed and executed.
Identify Needed
System
Capabilities
What capabilities are needed to fulfill the ConOps and System Requirements?
1.0
1.1
1.2
1.3
1.4
30
 Produce an overall statement of the problem in an operational context.
 Develop the overall operational and technical objectives of the target system.
 Defined the boundaries and interfaces of the target system.
Perform Fact
Finding
 Gather required system capabilities, functional, nonfunctional and environmental
requirements, and design constraints.
 Build a Top Down Capabilities and Functional decomposition of the requirements in a flow
down tree using a Requirements Management System.
Gather
and Classify
Requirements
 Answer the question “why do I need this?” in terms of operational benefits.
 Build a cost benefit / model using probabilistic assessment of all variables and
dependencies.
 For technical requirements, perform a risk assessment to cost and schedule.
Evaluate
and Rationalize
Requirements
 Determine criticality for the functions for the system mission.
 Determine trade off relationships for all requirements to be used when option decisions
are made.
 For technical items prioritize on cost and dependency.
Prioritize
Requirements
 Address completeness of requirements by removing all “TBD” items.
 Validate the requirements agree and are traceable to system capabilities, goals, and
mission.
 Resolve any requirements inconsistencies and conflicts.
Integrate
and Validate
Requirements
Define the technical and operational requirements that must be in place for the system
capabilities to be fulfilled. Define these requirements in terms isolated from any
implementation.
Establish the
Requirements
Baseline
What Technical and Operational Requirements are Needed to Fulfill the Capabilities?
2.0
2.1
2.2
2.3
2.4
2.5
31
Decompose the Project Scope into a product based Work Breakdown Structure (WBS), then
further into Work Packages describing the production of all deliverables traceable to the
requirements
Decompose
Scope into Work
Packages
Assign Responsibility to Work Packages (the groupings of deliverables) for the named
owner accountable for the management of resource allocation and cost baseline and
technical delivery
Assign
Responsibility
for Deliverables
Arrange the Work Packages in a well formed network with defined deliverables,
milestones, internal and external dependencies, appropriate schedule and cost
margin.
Arrange
Work Packages
in Logical Order
Develop a Time–Phased Budgeted Cost for Work Scheduled (BCWS) from labor and
material costs in each Work Package and the Project as a whole. Assure proper resource
allocations can be met and budget profiles match expectations of the project sponsor
Develop
BCWS for Work
Packages
Assign object Measure of Performance (MOP) and Measures of Effectiveness (MOE) for each
Work Package and summarize these for the Project as a whole
Assign WP
Measures of
Performance
Build a time–phased network of schedule activities describing the work to be performed, the
budgeted cost for this work, the organizational elements that produce the deliverables, and
the performance measures showing this work is proceeding according to plan.
Establish
the Performance
Measurement
Baseline
A Baselined Schedule that Creates the Services or Products to Meet The Requirements
3.0
3.1
3.2
3.3
3.4
3.5
Establish a Performance Measurement Baseline (PMB) used to forecast Work Package
and Project ongoing and completion cost and schedule metrics
Set
Performance
Measurement
Baseline
3.6
32
Deliverables Based Planning Handbook for A&D, Copyright © 2008, 2009, Lewis & Fowler
 Using the Work Package sequencing, release work to be performed as planned
 With the RACI based RAM, the Accountable delivery manager guides the development of
the products or services for each Work Package
Perform
the Authorized
Work
 Using Physical Percent Complete or Apportioned Milestones capture measures of
progress to plan for each Work Package
 Report this Physical Percent Complete in a centralized database for each Work Package
and the project as a whole
Accumulate
and Report Work
Package
Performance
 Compare the Physical Percent Complete against the Planned Percent Complete for each
period of performance
 Construct cost and schedule performance indices from this information and the Physical
Percent complete measures
Analyze
Work Package
Performance
 With the Cost and Schedule performance indices, construct a forecast of future
performance of cost, schedule, and technical performance compliance efforts
 Take management actions for any Work Packages not performing as planned
Take
Corrective
Management
Action
 Record past performance based on Work Package completion criteria
 Record past future forecast performance estimates in a historical database
 Forecast next future performance against the Performance Measurements Baseline
 Report this next future performance estimate to the project stakeholders
Maintain
the Performance
Baseline
Execute work packages, while assuring all performance assessment are 0%/100%
complete before proceeding. No rework, no forward transfer of activities or features.
Assure every requirement is traceable to work and all work is traceable to requirements.
Execute the
Performance
Measurement
Baseline Weekly, Bi–monthly, or Monthly Measures of Physical Percent Complete
4.0
4.1
4.2
4.3
4.4
4.5
33
34
5 Practice Areas of Successful Program Controls
How
Where
When
Who
Why
What
Identify Business
Needs
Establish a
Performance
Measurement
Baseline
Execute the
Performance
Measurement
Baseline
Capabilities
Based Plan
Operational
Needs
Earned Value
Performance
0% /100%
Technical
Performance
Measures
System Value
Stream
Technical
Requirements
Identify
Requirements
Baseline
1
2
3
4
Technical
Performance
Measures
PMB
Continuous Risk Management Process
Changes to
business strategy
Changes to
requirements
Changes to
project plan
1
2
3
4
5
6
7
8
9
10
10OrganizingPrinciplesofDeliverablesBasedPlanningsm
The 10 Organizing Principles That
Drive The 5 Practice Areas
35
Capabilities Drive
Requirements
Requirements are
Fulfilled by Work
Packages
Work Packages
Define Deliverables
Measure Physical
Percent Complete of
Each WP
Perform Only
Authorized Work
Earned Value
Defines Progress
Adjust EV for Technical
Performance
Measure
Use Past
Performance to
Forecast Future
Performance
1
2
3
5
6
7
8
9
10
PMB Describes
Work Sequence
4
9
Assess the capabilities being provided through the deliverables
Fulfill the requirements through effort held in the Work Packages
Produce deliverables
from Work Packages
Planned BCWS
Physical % Complete
WP’s contain
deliverables that fulfill
requirements
Capabilities
topology
defines
requirements
flow down
WP flow must describe
the increasing maturity of
the product or service
Producing the deliverables in the
planned sequence maintains the
value stream to the customer
Business Management Is the Purpose of 748B
½ of the Criteria are NOT About Dollars
The Units of Measure in Earned Value
36
Connecting Principles With Earned
Value Processes
37
ANSI/EIA-748B Areas
10 Principles Driving Program
Controls Success
Organization
Planning and
Budgeting
Accounting Analysis Revisions
Capabilities Drive Requirements WBS
Requirements Identify Deliverables WBS
Work Packages Describe
Production of Deliverables
WBS
CWBS
IPTs
BCWS
Master Schedule Sequences
Deliverables through WPs
IMS IMS
Progress Must Be Measured As
Physical Percent Complete
Perf Measure
0/100 or AP
TPM
Work Authorization Assures Proper
Sequencing of Work Packages
OBS WAD
Late Starts
Late Finishes
CCB
Earned Value Identifies Current
Deliverables Performance
Physical %
Complete
BCWP Monte Carlo
Technical Performance Measures
Adjust Earned Value
TPM Measure TPM Monte Carlo
Performance Feedback Adjusts
Work Package Sequencing
Upper Lower
Bounds
CAM Review CCB
Future Performance Using TCPI,
IEAC & Adjusted Work Sequence
IEAC New BL
38
What Did We Learned?
What Did We Learned?
 CPI/SPI are necessary but not sufficient for success
program management.
 All EV variables have probabilistic foundations.
 The sunk cost of successful Earned Value is already
absorbed in a credible PMB and the process used
to build it
39
40
The Light at the End of the Tunnel
 Start with the Top Down approach and define the
needed capabilities to drive the requirements.
 Use these capabilities and requirements to
establish the “business value,” and related Value
Stream Map of the Master Plan.
 Partition the allocated work into Work Packages
that deliver the business value in a credible
sequence meaningful to the customer.
 Use the Bottom Up approach to construct the
details.
 Consider all variables as random variables.
 Use the 32 Criteria as guidance for “business
processes,” not just EV.
 Remember EV’s Unit of Measure of Dollars not
Time. Time ≠ Money on any real program.

More Related Content

What's hot

EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Projectorsmoot
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsIftikhar Anjum
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short CourseGlen Alleman
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 

What's hot (20)

Chap013 4er1
Chap013 4er1Chap013 4er1
Chap013 4er1
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Project
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Control Account Manager Short Course
Control Account Manager Short CourseControl Account Manager Short Course
Control Account Manager Short Course
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
The Benefits of using Earned Value Management
The Benefits of using Earned Value ManagementThe Benefits of using Earned Value Management
The Benefits of using Earned Value Management
 

Viewers also liked

A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Big data meets evm (submitted)
Big data meets evm (submitted)Big data meets evm (submitted)
Big data meets evm (submitted)Glen Alleman
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big DataGlen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPJustAcademy
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resourcesGlen Alleman
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management successGlen Alleman
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless ExecutionGlen Alleman
 

Viewers also liked (19)

A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Control systems
Control systemsControl systems
Control systems
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Ev+agile=success
Ev+agile=successEv+agile=success
Ev+agile=success
 
Big data meets evm (submitted)
Big data meets evm (submitted)Big data meets evm (submitted)
Big data meets evm (submitted)
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big Data
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Earned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMPEarned value management with Examples | Control Cost | PMBOK | PMP
Earned value management with Examples | Control Cost | PMBOK | PMP
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resources
 
Applying the checklist manifesto for project management success
Applying the checklist manifesto for project management successApplying the checklist manifesto for project management success
Applying the checklist manifesto for project management success
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Flawless Execution
Flawless ExecutionFlawless Execution
Flawless Execution
 
Pisano
PisanoPisano
Pisano
 

Similar to Earning Value from Earned Value Management

Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPIGlen Alleman
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementGlen Alleman
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessGlen Alleman
 
Increasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementIncreasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Mihai Buta
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)Glen Alleman
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Glen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Glen Alleman
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 

Similar to Earning Value from Earned Value Management (20)

Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Assessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPIAssessing Project Performance Beyond CPI/SPI
Assessing Project Performance Beyond CPI/SPI
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Beyond CPI and SPI
Beyond CPI and SPIBeyond CPI and SPI
Beyond CPI and SPI
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
 
Increasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value ManagementIncreasing the probability of project success using Earned Value Management
Increasing the probability of project success using Earned Value Management
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 
Agile EVMS
Agile EVMSAgile EVMS
Agile EVMS
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)
 
Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)Building a Credible Performance Measurement Baseline (PM Journal)
Building a Credible Performance Measurement Baseline (PM Journal)
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)Performance based management in a nut shell (v5)
Performance based management in a nut shell (v5)
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 

Recently uploaded

Intellectual Property Licensing Examples
Intellectual Property Licensing ExamplesIntellectual Property Licensing Examples
Intellectual Property Licensing Examplesamberjiles31
 
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...Brian Solis
 
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfTalent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfCharles Cotter, PhD
 
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John MeulemansBCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John MeulemansBBPMedia1
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsyasinnathani
 
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptxChapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptxesiyasmengesha
 
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...Khaled Al Awadi
 
MC Heights construction company in Jhang
MC Heights construction company in JhangMC Heights construction company in Jhang
MC Heights construction company in Jhangmcgroupjeya
 
Cracking the ‘Business Process Outsourcing’ Code Main.pptx
Cracking the ‘Business Process Outsourcing’ Code Main.pptxCracking the ‘Business Process Outsourcing’ Code Main.pptx
Cracking the ‘Business Process Outsourcing’ Code Main.pptxWorkforce Group
 
Developing Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursDeveloping Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursKaiNexus
 
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024Stephan Koning
 
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...AustraliaChapterIIBA
 
Trauma Training Service for First Responders
Trauma Training Service for First RespondersTrauma Training Service for First Responders
Trauma Training Service for First RespondersBPOQe
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyHanna Klim
 
Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..dlewis191
 
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)tazeenaila12
 
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...ISONIKELtd
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access
 
Introduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxIntroduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxJemalSeid25
 
Upgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsUpgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsIntellect Design Arena Ltd
 

Recently uploaded (20)

Intellectual Property Licensing Examples
Intellectual Property Licensing ExamplesIntellectual Property Licensing Examples
Intellectual Property Licensing Examples
 
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
The End of Business as Usual: Rewire the Way You Work to Succeed in the Consu...
 
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdfTalent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
Talent Management research intelligence_13 paradigm shifts_20 March 2024.pdf
 
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John MeulemansBCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story points
 
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptxChapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
Chapter_Five_The_Rural_Development_Policies_and_Strategy_of_Ethiopia.pptx
 
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...NewBase  25 March  2024  Energy News issue - 1710 by Khaled Al Awadi_compress...
NewBase 25 March 2024 Energy News issue - 1710 by Khaled Al Awadi_compress...
 
MC Heights construction company in Jhang
MC Heights construction company in JhangMC Heights construction company in Jhang
MC Heights construction company in Jhang
 
Cracking the ‘Business Process Outsourcing’ Code Main.pptx
Cracking the ‘Business Process Outsourcing’ Code Main.pptxCracking the ‘Business Process Outsourcing’ Code Main.pptx
Cracking the ‘Business Process Outsourcing’ Code Main.pptx
 
Developing Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursDeveloping Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, Ours
 
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
IIBA® Melbourne - Navigating Business Analysis - Excellence for Career Growth...
 
Trauma Training Service for First Responders
Trauma Training Service for First RespondersTrauma Training Service for First Responders
Trauma Training Service for First Responders
 
Anyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agencyAnyhr.io | Presentation HR&Recruiting agency
Anyhr.io | Presentation HR&Recruiting agency
 
Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..Team B Mind Map for Organizational Chg..
Team B Mind Map for Organizational Chg..
 
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
Harvard Business Review.pptx | Navigating Labor Unrest (March-April 2024)
 
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024
 
Introduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxIntroduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptx
 
Upgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking ApplicationsUpgrade Your Banking Experience with Advanced Core Banking Applications
Upgrade Your Banking Experience with Advanced Core Banking Applications
 

Earning Value from Earned Value Management

  • 1. EARNING VALUE FROM EARNED VALUE USING EV TO IMPROVE THE PROBABILITY OF PROJECT SUCCESS EVM WORLD 2009 PMI-CPM 25TH ANNUAL INTERNATIONAL CONFERENCE 1
  • 2. Learning Outcomes  Cost and Schedule Indices (SPI, CPI, TCPI, and IEAC) do not represent the underlying statistical nature of projects.  Modeling this statistical behavior requires addition activities build around Monte Carlo simulation and stochastic modeling.  Creating value from the Earned Value requires both bottom-up and a top-down work processes. 2
  • 3. 3 Creating Value from EV is More Than Calculating SPI and CPI LAUNCH ABORT SYSTEM FOR ORION CAPSULE  What are the technical requirements that fulfill the mission capabilities?  How is the work partitioned for the producing the deliverables that fulfill these requirements?  What are the Work Packages, Cost and Schedule elements and programmatic risk elements to assure on-time, on- budget performance? CONSTELLATION MISSION TO THE MOON  What capabilities are needed to fulfill the mission?  How are these capabilities connected to the technical and operational requirements?  What are the programmatic trade space decisions between capabilities, requirements, cost and schedule? BRICK LAYING PROJECT  What are the measures of scope, effort, and duration?  What are the measures of physical percent complete?  Can we forecast of final cost and completion date? What Does Done Look Like? How will we recognize done? What is the unit of measure of Done?
  • 4. Questions Every Program Manager Needs to Ask and Answer  How much money will I need to complete this program on time and on specification?  What is my confidence that we’ll complete on or before the planned finish date?  Do I have enough management reserve to protect this finish date?  What is the inherent risk built into my cost and schedule baseline?  How can I tell if the program is making progress to plan? 4
  • 5. GAINING COMPLIANCE WITH THE EARNED VALUE GUIDANCE THE BOTTOM UP APPROACH 5
  • 6. The Logical Starting Point Of The Earned Value Journey 6
  • 7. This progress is represented by physical, tangible, measurably quantifiable evidence.  How much did we plan to get done on this date, measured in Dollars?  How much did we actually get done on this date, measured in Dollars? In This Standard Paradigm … Earned Value = Physical Percent Complete of the Planned Value 7
  • 8. What About the Planned Technical Performance? We’re On Schedule, On Budget But We Had A Slight Technical Problem With Our Flying Machine 8
  • 9. 9 From the NDIA Earned Value Intent Guide (EVIG) Notice the inclusion of Technical along with Cost and Schedule That’s the next step is generating Value from Earned Value EV MUST include the Technical Performance Measures
  • 10. 10  Relate time-phased budgets to specific contract tasks and/or statements of work (SOW)  Objectively measure work progress  Properly relate cost, schedule, and technical accomplishment  Allow for informed decision making and corrective action  Is valid, timely, and able to be audited  Allow for statistical estimation of future costs  Supply managers at all levels with status information at the appropriate level, and  Is derived from the same EVM system used by the contractor to manage the contract. The First Set of Promises That Need Actionable Steps
  • 11.  The EV numbers are just numbers  They can show trends  They can be the basis of forecasts  But they must be placed in a context of an underlying statistical model  They must be connected with the relationship between time and money 11 Moving from reporting the past performance to forecasting the future is the first step in Earning Value from Earned Value Management
  • 12. Does Money Equal Time? This is How EV Measures Schedule Variance But What If It Is Not Linear? Time Is Not Money Unless They Are Linearly Related 12
  • 13. The REAL Problem Models Of Earned Value Are Inherently Probabilistic With Interdependent Couplings Between Network Elements 13
  • 14. Using Static, Deterministic, and Decoupled Measures of Performance (e.g. The Standard EV Model) is at best… 14
  • 15. But Let’s Visit A High Level View of the Earned Value Activities 15
  • 16. The 32 Criteria for a ANSI/EIA-748B Compliant Earned Value Management System 16
  • 18. Questions Every Program Manager Needs to Ask and Answer – Part 2  How much money will I need to complete this program on time?  What is my confidence that we’ll complete on or before the planned finish date?  Do I have enough management reserve?  What is the inherent risk built into my cost and schedule baseline?  How can I tell if the program is making progress to plan?
  • 19. CAN WE MEASURE THE BENEFITS OF EARNED VALUE MANAGEMENT?
  • 20. How Can We Get A Return On Our Investment In Earned Value? 20
  • 21. Some Straight Forward Benefits†  Better Visibility into Program Performance  Reduce Cycle Time to Deliver a Product  Foster Accountability  Reduce Risk † From the DACS Gold Practices “Track Earned Value” Focus Area
  • 22. The Missing Piece Is “How” To Obtain These Benefits  How do we create better visibility into the program’s performance?  How do we reduce cycle time to deliver the product?  How do we foster accountability?  How do we reduce risk? Deploying Earned Value Alone Will Not Get Us There How Do We Get From Where We Are To Our Destination? 22
  • 23. Claimed Benefit The Reason The Method to Achieve Better Visibility into Program Performance The combination of advance planning, baseline maintenance, and earned value analysis yields earlier and better visibility into program performance than is provided by non-integrated methods of planning and control.  This requires a credible baseline. But this baseline must be more than just a list of work, it must represent the “Programmatic Architecture” of the system, matching the technical architecture.  This programmatic architecture formulates the flow of work that produces products with increasing maturity. Step Action Details Define the Integrated Master Plan (IMP) The IMP is the Strategy for the successful completion of the program. It is formed from Program Events, the Significant Accomplishments (SA), and their Accomplishment Criteria (AC). Sequence the SAs The sequence of SAs for each single PE by the IPT’s is a diagram sufficiently detailed to show how the increasing maturity of the deliverables can be achieved. Assign Budget Estimates (BOE) Collect the initial “basis of estimate” from the duration and sequence of these SAs 23
  • 24. Claimed Benefit The Reason The Method to Achieve Reduces Cycle Time to Deliver a Product Earned Value Management is premised on careful detailed planning – task decomposition, scheduling, and budgeting. This planning often addresses or prevents problems from surfacing later in the effort that result in rework. As rework is prevented cycle time may be reduced.  Again the carefully detailed plan must adequately represent a credible schedule, cost allocation, and resource assignments.  How can we know this is the case? Step Action Details Reduce cycle time by forecasting delay Using TCPI and IEAC the macro level forecast (scalar) can be generated. What is needed is to locate the specific tasks that are the source of this delay. This is a network analysis process. Identify alternative paths through the IMS With the network process flow indentified, alternative paths can be assessed. These path have associated cost and down stream schedule impacts that need further analysis. Probabilistic cost and schedule The result is a probabilistic cost and schedule analysis coupled with a Monte Carlo simulation tool to construct the “probabilistic critical path? 24
  • 25. Claimed Benefit The Reason The Method to Achieve Fosters Accountability When the engineer understands how the pieces fit the overall project effort, they tend to focus on delivery of a quality product. Over time they are better able to estimate the work required to complete a task, thereby improving the overall accuracy of the budget / estimating process for future efforts.  Defining the logical sequence of product or service flow is the starting point.  This “systems engineering” approach starts with a description of the “increasing maturity” of the product or service, and only then assigning the Earned Value elements Step Action Details Work Package budgets owned by producers of value Once the Value Stream as been defined – this is the logical flow of the Significant Accomplishment – the ownership for producing this value is identified in the Work Package owners. Dependencies between WPs is a Systems Engineering process The Value Stream of the collection of Work Package must remove an impediments to maximizing this value. This is the role of the planning and controls staff in conjunction with the subject matter experts accountable for delivering the technical solution. As a collective they are accountable for the resulting value stream. 25
  • 26. Claimed Benefit The Reason The Method to Achieve Reduces Risk Because earned value measures enable realistic estimates of completion to be derived early in the project, it is possible to make adjustments and take corrective action to mitigate the risk of cost overruns and schedule slippage.  Probabilistic risk analysis requires a credible baseline and an understanding of the underlying probabilistic process driving cost, schedule, and technical performance  If the probabilistic process is stationary, a Monte Carlo simulation can be used to analyze the behaviors of the system only as a stationary model. Step Action Details Probabilistic modes expose risk Only probabilistic models “enable realistic estimates.” No point estimate in the absence of a variance is credible. Risk adjusted work in IMS All risk mitigation and retirement activities need to be in the IMS, along with funding profiles and probabilistic assessment of their effectiveness. EV alone will not address the issues. An active Risk Management process is needed. 26
  • 27. STEPS NEEDED TO EARN THE VALUE FROM EARNED VALUE THE TOP DOWN APPROACH 27
  • 28. 28 The Cost of These Benefits Is Already Built Into a Credible PMB  The BCWS spreads define visibility into costs  The sequence of Significant Accomplishments (SA) defines visibility into deliverables  Risk mitigations, buy downs, and retirements are embedded in the PMB  Small incremental measures of value are defined by Work Packages  Visibility provided through measures of physical percent complete  Reduced cycle is actually just maintaining the planned completion dates, on budget, that meet the planned technical performance measurements
  • 29. Five Core Processes of Successful Program Planning and Controls 29 Program Success Process Areas Questions To Be Answered Identify Needed System Capabilities What capabilities are needed to fulfill the ConOps and System Requirements? Establish the Requirements Baseline What technical and operational requirements are needed to fulfill these capabilities? Establish the Performance Measurement Baseline What is the schedule that delivers product or services that meet the requirements? Execute the Performance Measurement Baseline What are the periodic measures of physical percent complete? Perform Continuous Risk Management What are the impediments to success and what are the mitigations ?
  • 30.  Partition system capabilities into classes of service within operational scenarios  Connect capabilities to system requirements using sysML  Define Measures of Effectiveness (MOE) and Measures of Performance (MOP)  Define in the delivery schedule the achievement of each Technical Performance Measure Define Operational Concepts  Define scenarios for each system capability  Connect these scenarios to a Value Stream Map of the increasing maturity of the program  Assess value flow through the map for each needed capability  Identify capabilities mismatches and make corrections to improve overall value flow Define Capabilities Needed To Implement Concepts  Assign costs to a system element using a value model process model  Assure risk, probabilistic cost and benefit performance attributes are defined  Use cost, schedule and technical performance probabilistic models to forecast potential risks to program performance Assess Needs, Costs and Risks Simultaneously  Make tradeoffs that connect cost, schedule, and technical performance in a single “trade space” model  Measures of Effectiveness and Measures of Performance are the raw materials for these tradeoffs Define Explicit, Balanced, and Feasible Alternatives Define the set of capabilities to be employed to achieve desired objectives or a particular end state for a specific scenario. Take the ConOps and define the details of who, where, and how it is to be accomplished, employed and executed. Identify Needed System Capabilities What capabilities are needed to fulfill the ConOps and System Requirements? 1.0 1.1 1.2 1.3 1.4 30
  • 31.  Produce an overall statement of the problem in an operational context.  Develop the overall operational and technical objectives of the target system.  Defined the boundaries and interfaces of the target system. Perform Fact Finding  Gather required system capabilities, functional, nonfunctional and environmental requirements, and design constraints.  Build a Top Down Capabilities and Functional decomposition of the requirements in a flow down tree using a Requirements Management System. Gather and Classify Requirements  Answer the question “why do I need this?” in terms of operational benefits.  Build a cost benefit / model using probabilistic assessment of all variables and dependencies.  For technical requirements, perform a risk assessment to cost and schedule. Evaluate and Rationalize Requirements  Determine criticality for the functions for the system mission.  Determine trade off relationships for all requirements to be used when option decisions are made.  For technical items prioritize on cost and dependency. Prioritize Requirements  Address completeness of requirements by removing all “TBD” items.  Validate the requirements agree and are traceable to system capabilities, goals, and mission.  Resolve any requirements inconsistencies and conflicts. Integrate and Validate Requirements Define the technical and operational requirements that must be in place for the system capabilities to be fulfilled. Define these requirements in terms isolated from any implementation. Establish the Requirements Baseline What Technical and Operational Requirements are Needed to Fulfill the Capabilities? 2.0 2.1 2.2 2.3 2.4 2.5 31
  • 32. Decompose the Project Scope into a product based Work Breakdown Structure (WBS), then further into Work Packages describing the production of all deliverables traceable to the requirements Decompose Scope into Work Packages Assign Responsibility to Work Packages (the groupings of deliverables) for the named owner accountable for the management of resource allocation and cost baseline and technical delivery Assign Responsibility for Deliverables Arrange the Work Packages in a well formed network with defined deliverables, milestones, internal and external dependencies, appropriate schedule and cost margin. Arrange Work Packages in Logical Order Develop a Time–Phased Budgeted Cost for Work Scheduled (BCWS) from labor and material costs in each Work Package and the Project as a whole. Assure proper resource allocations can be met and budget profiles match expectations of the project sponsor Develop BCWS for Work Packages Assign object Measure of Performance (MOP) and Measures of Effectiveness (MOE) for each Work Package and summarize these for the Project as a whole Assign WP Measures of Performance Build a time–phased network of schedule activities describing the work to be performed, the budgeted cost for this work, the organizational elements that produce the deliverables, and the performance measures showing this work is proceeding according to plan. Establish the Performance Measurement Baseline A Baselined Schedule that Creates the Services or Products to Meet The Requirements 3.0 3.1 3.2 3.3 3.4 3.5 Establish a Performance Measurement Baseline (PMB) used to forecast Work Package and Project ongoing and completion cost and schedule metrics Set Performance Measurement Baseline 3.6 32
  • 33. Deliverables Based Planning Handbook for A&D, Copyright © 2008, 2009, Lewis & Fowler  Using the Work Package sequencing, release work to be performed as planned  With the RACI based RAM, the Accountable delivery manager guides the development of the products or services for each Work Package Perform the Authorized Work  Using Physical Percent Complete or Apportioned Milestones capture measures of progress to plan for each Work Package  Report this Physical Percent Complete in a centralized database for each Work Package and the project as a whole Accumulate and Report Work Package Performance  Compare the Physical Percent Complete against the Planned Percent Complete for each period of performance  Construct cost and schedule performance indices from this information and the Physical Percent complete measures Analyze Work Package Performance  With the Cost and Schedule performance indices, construct a forecast of future performance of cost, schedule, and technical performance compliance efforts  Take management actions for any Work Packages not performing as planned Take Corrective Management Action  Record past performance based on Work Package completion criteria  Record past future forecast performance estimates in a historical database  Forecast next future performance against the Performance Measurements Baseline  Report this next future performance estimate to the project stakeholders Maintain the Performance Baseline Execute work packages, while assuring all performance assessment are 0%/100% complete before proceeding. No rework, no forward transfer of activities or features. Assure every requirement is traceable to work and all work is traceable to requirements. Execute the Performance Measurement Baseline Weekly, Bi–monthly, or Monthly Measures of Physical Percent Complete 4.0 4.1 4.2 4.3 4.4 4.5 33
  • 34. 34 5 Practice Areas of Successful Program Controls How Where When Who Why What Identify Business Needs Establish a Performance Measurement Baseline Execute the Performance Measurement Baseline Capabilities Based Plan Operational Needs Earned Value Performance 0% /100% Technical Performance Measures System Value Stream Technical Requirements Identify Requirements Baseline 1 2 3 4 Technical Performance Measures PMB Continuous Risk Management Process Changes to business strategy Changes to requirements Changes to project plan 1 2 3 4 5 6 7 8 9 10 10OrganizingPrinciplesofDeliverablesBasedPlanningsm
  • 35. The 10 Organizing Principles That Drive The 5 Practice Areas 35 Capabilities Drive Requirements Requirements are Fulfilled by Work Packages Work Packages Define Deliverables Measure Physical Percent Complete of Each WP Perform Only Authorized Work Earned Value Defines Progress Adjust EV for Technical Performance Measure Use Past Performance to Forecast Future Performance 1 2 3 5 6 7 8 9 10 PMB Describes Work Sequence 4 9 Assess the capabilities being provided through the deliverables Fulfill the requirements through effort held in the Work Packages Produce deliverables from Work Packages Planned BCWS Physical % Complete WP’s contain deliverables that fulfill requirements Capabilities topology defines requirements flow down WP flow must describe the increasing maturity of the product or service Producing the deliverables in the planned sequence maintains the value stream to the customer
  • 36. Business Management Is the Purpose of 748B ½ of the Criteria are NOT About Dollars The Units of Measure in Earned Value 36
  • 37. Connecting Principles With Earned Value Processes 37 ANSI/EIA-748B Areas 10 Principles Driving Program Controls Success Organization Planning and Budgeting Accounting Analysis Revisions Capabilities Drive Requirements WBS Requirements Identify Deliverables WBS Work Packages Describe Production of Deliverables WBS CWBS IPTs BCWS Master Schedule Sequences Deliverables through WPs IMS IMS Progress Must Be Measured As Physical Percent Complete Perf Measure 0/100 or AP TPM Work Authorization Assures Proper Sequencing of Work Packages OBS WAD Late Starts Late Finishes CCB Earned Value Identifies Current Deliverables Performance Physical % Complete BCWP Monte Carlo Technical Performance Measures Adjust Earned Value TPM Measure TPM Monte Carlo Performance Feedback Adjusts Work Package Sequencing Upper Lower Bounds CAM Review CCB Future Performance Using TCPI, IEAC & Adjusted Work Sequence IEAC New BL
  • 38. 38 What Did We Learned?
  • 39. What Did We Learned?  CPI/SPI are necessary but not sufficient for success program management.  All EV variables have probabilistic foundations.  The sunk cost of successful Earned Value is already absorbed in a credible PMB and the process used to build it 39
  • 40. 40 The Light at the End of the Tunnel  Start with the Top Down approach and define the needed capabilities to drive the requirements.  Use these capabilities and requirements to establish the “business value,” and related Value Stream Map of the Master Plan.  Partition the allocated work into Work Packages that deliver the business value in a credible sequence meaningful to the customer.  Use the Bottom Up approach to construct the details.  Consider all variables as random variables.  Use the 32 Criteria as guidance for “business processes,” not just EV.  Remember EV’s Unit of Measure of Dollars not Time. Time ≠ Money on any real program.