Integrating	
Agile	Software	Development	
with	
Earned	Value	Management
Glen	B.	Alleman
Prime	Project	Management
+1	303	241	9633
glen.alleman@niwotridge.com
IPM	Workshop	 2015
Jeff	Lutton
Prime	Project	Management
+1	571	330	2878
jlutton@primepm.net
2
Today’s Briefing
• How can Agile Software Development methods increase the
Probability of Program Success (PoPS) on Earned Value
programs?
• How can Agile development integrate with the FAR / DFAR and
OMB mandates for program performance measures using
Earned Value?
• What are the “touch” points (or possible collision points)
between Agile and EIA-748-C?
• What are the measures of success for Agile methods in the
context of EIA-748-C?
3
3
Let’s Start With A Critical
Assumption:
Project Controls are needed
for Project Success
4
In case we’ve forgotten what EIA-748-C says
• EIA-748-C, page 1, defines the top level activities for
a successful EV based project.
• We need to “connect the dots” between these and
agile development.
§ Plan all work scope for the program from inception to completion.
§ Break down the program work into finite pieces that can be assigned to a
responsible person or organization for control of technical, schedule, and cost
objectives.
§ Integrate program work scope, schedule, cost objectives into a performance
measurement baseline plan against with accomplishments may be measured.
Control changes to the baseline.
§ Use actual costs incurred and recorded in accomplishing the work performed.
§ Objectively assess accomplishments at the work performance level.
§ Analyze significant variances from the plan, forecast impacts, and prepare and
estimate at completion based on performance to date and work to be performed.
§ Use this information in the organization's management processes
5
When we Hear Agile, What Does That Mean?
† Dr. Ashton Carter, Under Secretary of Defense for Acquisition, Technology and Logistics,
Sep/Oct, 2010 Defense AT&L
“Being able to turn inside the loop of unfolding events.”†
6
12 Principles of the Agile Manifesto
7
IMP Captures End User Requirements in
Terms MOEs, MOPs, KPPs, and TPMs
SOW
ConOps
WBS
CWBS
Technical	Performance	
Measures	
(TPM)
Messages	of	Performance
(MOP)
Measures	of	Effectiveness
(MOE)
Key	Performance	
Parameters
(KPP)
Integrated	Master	Plan
(IMP)
Integrated	Master	
Schedule
(IMS)
Performance	
Measurement	Baseline
(PMB)
Technical	Requirements
8
Some Critical Concepts in Agile
Product Time
Capabilities
A high level system
function completed
across multiple
releases
Features
Stories
A well define system
function to be
completed within a
release
A small well defined
system function that
can be developed
within one sprint
Release
Sprint
† Earned Value Managementfor Scrum Programs:Industry Best Practices, National Defense Industry Association
Integrated Program ManagementDivision (NDIAIPMD) Scrum EVM Working Group
9
Putting Earned Value Management and Agile
Software Development Together
Feature 1,2,3
Feature 4,5,6
Feature 7,8,9
Release 1 Release 2
Release 2 PP’s
WP
PP
SLPP
in IMS
CA
EVM Reporting from
Work Package
Performance
EVM Performance
• BCWS – fromWBS
Basis of Estimate
• ACWP – fromtime
cards
• BCWP – from
completed Story
Points
Sprints
Time Now
n Starting with the IMP,defined Capabilitiesare flowed to the PMB
n Capabilitiesproduce the value fromeach Release
n Control Accounts and Work Packages are on baseline in the PMB
n Work Packages contain Features produced in each Release by Sprints
n Release Planning baseline for period of performance and BCWS
Vertical and horizontal integration
of all work planned fromthe
IMP/IMSdown to Releases, Sprints,
and Tasks in the Scrum
Development Management system.
Performance Measurement Baseline
Scrum Software Development Lifecycle
Feature n
The Bright Line
Milestones
Data Items
IMP ProgramEvents
IMP Accomplishments
and Criteria
Scrum Development Control Account
Task
Task
Task
Task
Task
Task
Task
Task
Task
…
10
Ordinal Story Point cannot be basis of
BCWS higher than a Feature
10
Feature 1
Story
Story
Story
Story
Story
Story
Team 1’s
Uncalibrated
Ordinal SP
estimates
Feature n
Story
Story
Story
Story
Story
Story
Team 2’s
Uncalibrated
Ordinal SP
estimates
∑ F1(SP) ∑ Fn(SP)
Release 1 ∑ of SP’s
• • •
§ At the Story level,
relative effort defines
individual estimates.
§ At the Feature level,
lower level SP’s don’t
have the same unit of
measure in the way
Dollars do.
§ When Features
summed to the
Release, relative
measures do not
provide basis of
Physical Percent
Complete.
Not same units of measure between
Features – Uncalibrated SP’s
11
Building the PMB in a Agile Paradigm
WBS
Iteration 1 Iteration 2 Iteration 3 … Iteration n Close Out
§ Deliverables
§ Tasks
§ Tasks
§ Deliverables
§ Deliverables
§ Deliverables
§ Tasks
§ Tasks
CA CoDR
…
PDR
WBS basis of deliverables Backlog, per MIL-STD-881C,
decomposed into Release Backlog, then into Iteration
Backlog for delivery by Stories and Tasks.
12
An Actual Earned Value + Agile Program
13
CONNECTING THE MOVING PARTS
INTO AN INTEGRATED WHOLE
With both Earned Value and Agile parts, let’s connect them into a
Performance Measurement Baseline ready for execution and
reporting in the IPMR
14
Three Systems are Needed for an Integrated
Solution
• Shared data between
each system with a
single system of
record.
• Planning flowed from
IMS to Agile
development system
• Physical Percent
Complete flowed
back to IMS then to
EVMS
15
Data Connectivity in the Integrated System
16
Simplified Data Model
16
17
STEPS TO SETTING UP THE
PMB FOR AGILE + EVM
Here’s the step-by-step activities to define the Performance
Measurement Baseline (PMB) and get it on Baseline in Team
Foundation Server, the IMS, and COBRA.
This includes Baseline Change Requests and statusing of the
baseline to report EV in the IPMR.
This is the secret sauce of the principles and theory
18
Simple Rule for Earning Value in Agile
Each Iteration of each Release is a
“value earning” opportunity
The next step is to connect Agile’s
definition of Value with Earned Value’s
definition of Value
Business Value ≠ BCWP
19
Starting to “Connect the Dots” † ‡
Agile Point of View DoD Program Point of View
Requirements evolve Scope agreed to and maintained
Simple designs are best Architecture thought out and maintained
Teams are self organizing
Organizational structure establishes
boundaries
Delivery teams establish
best prescriptive processes
High level guidance organizes work
Development teams know
what to do
Process professionals define the
boundaries
Agile teams work in an
iterative manner
Product Development Lifecycle is serial
over broader periods of time
† Abstracted from “Reality over Rhetoric,” Scott Ambler IBM Developer Works
‡ John Goodpastuer, Project Management the Agile Way
20
Let’s Start With 3 Simple Connections
Earned Value Management Agile
Both EV and Agile Development Measure Progress as
Physical Percent Complete
+
1
Measures of progress in units of
“physical percent complete.”
Each sprint produces 100%
working product.
2
Forecast of future performance
provided by past performance.
Forecast performance in units of
product(s) produced.
3
A systems approach to the
development of products and
connecting Cost, Schedule, and
Technical Performance.
Increasing fidelity of product and
problem understanding takes
place after each sprint and
release.
21
EVM + Agile Process Flow
WBS
Story
Feature
Place	Work	
on	Backlog
Estimate	
Story Points
Work	Package
BCWS	
Execute	
Sprint
Record	SPs	
Complete
Calculate	P%C	
with	SPs
Load	P%C	for	
WP	in	IMS	
Send	P%C	to	
Cobra
Calculate	
BCWP
1. With the WBS decomposed to
Features, Stories, and Story
Point estimates
2. Place Features and Stories on
Scrum backlog.
3. Perform work in Sprints.
4. Record Stories earned and
calculate Physical Percent
Complete (P%C)
5. Send to the IMS and to Cobra
6. Calculate BCWP = BCWS ×
P%C in Cobra
The Bright Line
SOW
ConOps
22
Assess Performance On A Weekly Basis
Feature
Story
Story
Story
Story
Planned	
24	SP
%	Complete
100%
100%
0%
0%
Remaining	
4	SP
Earned
20	SP
Week 1 Week 2 Week 3 Week 4
20 Day Sprints
Every Thursday Status
§ Physical Percent Complete
§ SP’s remaining to 100%
8 SP’s
8 SP’s
4 SP’s
4 SP’s
23
Here’s Those Connections
GL EVM Criteria Agile Approach
1 Define WBS Features and Stories define tasks
2 Identify Organization Self organizing teams
5 Integrate WBS and OBS Self organized teams with a customer
6 Schedule Work Iterations and Releases
7 Identify Products & Milestones Working software at the end of iterations
8 Set time phased budget Fixed length iterations and releases
16 Record direct costs Fixed staff = Level of Effort
23 Determine variances EV + Velocity measures missed features
25 Sum data and variance Missed features moved to next iteration
26 Manage action plans Replan missed features, adjust velocity
28 Incorporate changes Replan missed features, adjust velocity
24
Provide managers
with information at a
practical level of
summarization
Relate time
phased budgets to
specific contract
tasks
Enable statistical
estimation of
completion costs
Track and
monitor
discrete project
metrics
Communicate
project status
Provide
quantitative data
for decision
making
Provide a
documented
project
performance trail
Alert project
managers to
potential schedule
and cost risk
Program
Controls
Practice
But First, Let’s Not Forget Business Management Practices …
…That Must Be Recognized Before Connecting Agile and EVM
25
11 EVM GL’s and 12 Agile Principles
Connecting Agile with Earned Value
Management is actually obvious
once we get over the social aspects
and focus on the Program Planning
and Controls aspects.
WBS
OBS
WBS+OBS
IMS
Productsand
Milestones
PMB
ACWP
Variances
Sumof
Variances
Corrective
Action
Record
Changes
Early and Continuous Delivery ✔ ✔ ✔
Welcome Change ✔ ✔ ✔ ✔
Deliver working Software ✔ ✔ ✔
Business and DEV work together ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔
Motivated individuals ✔
Sustainable development ✔ ✔ ✔ ✔ ✔
Working SW measure of progress ✔ ✔
Face-to-Face communications ✔ ✔ ✔ ✔
Continuous technical excellence ✔ ✔
Maximize work not done ✔
Self-organizing teams ✔ ✔
Regular reflections ✔ ✔ ✔ ✔ ✔
26
Putting Earned Value Management and Agile
Software Development Together one more time
Feature 1,2,3
Feature 4,5,6
Feature 7,8,9
Release 1 Release 2
Release 2 PP’s
WP
PP
SLPP
in IMS
CA
EVM Reporting from
Work Package
Performance
EVM Performance
• BCWS – fromWBS
Basis of Estimate
• ACWP – fromtime
cards
• BCWP – from
completed Story
Points
Sprints
Time Now
n Starting with the IMP,defined Capabilitiesare flowed to the PMB
n Capabilitiesproduce the value fromeach Release
n Control Accounts and Work Packages are on baseline in the PMB
n Work Packages contain Features produced in each Release by Sprints
n Release Planning baseline for period of performance and BCWS
Vertical and horizontal integration
of all work planned fromthe
IMP/IMSdown to Releases, Sprints,
and Tasks in the Scrum
Development Management system.
Performance Measurement Baseline
Scrum Software Development Lifecycle
Feature n
The Bright Line
Milestones
Data Items
IMP ProgramEvents
IMP Accomplishments
and Criteria
Scrum Development Control Account
Task
Task
Task
Task
Task
Task
Task
Task
Task
…
27
The Reason EV + Agile is a
Match Made in Heaven
The faster you obtain your intelligence
The more intelligent your decisions
From an Aviation Week & Space Technology Ad†
Agile forces the measures of physical percent complete
at the end of every Sprint.
By adopting this principle alone, EVM will have
measures of Physical Percent Complete – Working
Software – assessment every two weeks
Otherwise you’re not doing Agile
† L3 ad for UAV, AW&ST, September 14-27, 2014, pg. 37
28
29
PUTTING THESE IDEAS TO
WORK
Using the Earned Value Management Intent Guide (EVMIG), here’s
how to connect the dots at the next level down.
The 11 criteria of Earned Value connected with the 12 principles of
Agile.
30
Assemble a credible WBS and Integrated Master Plan / Integrated
Master Schedule (IMP/IMS)
–WBS Dictionary says what will be built
–IMP/IMS says how, where, when, and what will be built and the
processes to build it.
Identify Reducible – Event Based – uncertainties and the
resulting risks from WBS Dictionary and IMP Narratives in the
Risk Register
Put these these risks in the Risk Register, with probability and
impacts
Develop risk retirement plans and place them in the IMS using
CBB funding for risk buy down.
30
Building a Risk Adjusted PMB in Steps
0
1
2
3
8
31
Assess the Irreducible – naturally occurring –
uncertainties and the resulting schedule and cost
risks in the WBS and IMS.
Use Monte Carlo Simulation to determine schedule
margin and budget impacts from work activity
durations to handle these irreducible uncertainties.
Assign schedule and cost margin to protect key
item deliverables in the IMS.
31
Building a Risk Adjusted PMB in Steps
4
5
6
8
32
Determine cost and schedule impacts of unmitigated
risks in the risk register and place them in
Management Reserve, with their exposure and impact
Assemble mitigated Irreducible (Aleatory) and
Reducible (Epistemic) risks with the unmitigated
event–based risks into the Total Allocated Budget
– Risk handling an baseline for reducible and
irreducible in the PMB.
– Risk Handling in Management Reserve.
32
Building a Risk Adjusted PMB in Steps
(Concluded)
8
7
8
33
Steps to connecting the Agile Release Cycle
with the Performance Measurement Baseline
1. Establish Releases
2. Establish Iterations within each release
3. Establish Stories from the WBS and allocate them to each
release
4. Assign resources to each Story
5. Estimate work effort – in hours – to each story
6. Assess if capacity for work ≥ demand for work
7. Repeat Steps 4, 5, and 6 until demand equals capacity
34
GL 1: Define Authorized Work Elements
Define the authorized work elements for the program. A work breakdown structure
(WBS), tailored for effective internal management control, is commonly used in this
process.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Work Breakdown Structure (WBS).
§ Road Map & Release Plan consisting of
Capabilities, Product Backlog & Iteration
Backlog.
§ WBS dictionary (may or may not be used,
but a method to reconcile the statement
of work to the WBS structure must be
demonstrated).
§ WBS dictionary: agile user stories are
deliverables that you can measure “done”
for, therefore user stories satisfy wbs
dictionary.
35
GL 2: Identify Program Organizational Structure
Identify the program organizational structure, including the major subcontractors
responsible for accomplishing the authorized work, and define the organizational
elements in which work will be planned and controlled.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Organization Breakdown Structure
(OBS).
§ CAM just builds a team as usual, but the
team needs to be persistent, and not
interchangeable parts.
§ OBS intersections with the WBS.
§ Team hierarchy definition with resources
associated with their sub–teams.
§ Done at the level of granularity to
support the basis of estimate (BOE).
§ Persistent teams are needed to apply
throughput benchmarks to product
backlogs to validate plans.
36
GL 5: Integrate WBS and OBS
Provide for integration of the program work breakdown structure and the program
organizational structure in a manner that permits cost and schedule performance
measurement by elements of either or both structures as needed.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Control accounts.
§ Evidence that the CA meets the 90%
discrete work rule.
§ Defend schedule & cost performance at
the CA level?
§ Agile CA = one release.
§ Actuals captured at the story level.
§ Responsibility Assignment Matrix (RAM).
§ Done at too high a level for the SW
development approach to make a
difference.
§ Contract Performance Reports (CPRs), if
applicable.
§ Given an objective of X stories in
iteration Y, completed stories are earned;
all unearned return to backlog and a new
ETC is developed from the benchmarks
& backlog.
37
GL 6: Schedule the Work
Schedule the authorized work in a manner which describes the sequence of work and
identifies significant task interdependencies required to meet the requirements of the
program.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Integrated network schedules including
master, intermediate (if any), and detailed
schedules.
§ CAM’s agile roadmap becomes the
auditable intermediate schedule
demonstrating significant
accomplishments (SA).
§ MRP or ERP schedules, or planned order
reports.
§ Each task in IMS has associated
resources.
§ Control account plans (may be separate
plans or detail schedules).
§ CAM creates schedules compliant to
DCMA 14 point assessment.
§ Work authorization documents. § Nothing different.
38
GL 7: Identify Products and Milestones
Identify physical products, milestones, technical performance goals, or other indicators
that will be used to measure progress.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Integrated schedules including master,
intermediate (if any), and detailed
schedules that identify contract
milestones and key events.
§ Agile dev performance reporting follows
the approved program system description
§ Apportioned technical performance
milestones to reduce risk & roll up
intermediate technical performance.
§ MRP or ERP production planned order
reports.
§ Not relevant to sw development.
§ Control account plans (may be separate
plans or detail schedules)
§ Not relevant to Software Development
because we are reporting tasks as
physical % complete, which will
automatically roll up.
39
GL 8: Set Time Phased Budget
Establish and maintain a time–phased budget baseline, at the control account level,
against which program performance can be measured. Initial budgets established for
performance measurement will be based on either internal management goals or the
external customer negotiated target cost including estimates for authorized but
undefinitized work.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Control account plans.
§ Time phased budget created for the current iteration(s)
and future work.
§ Summary level planning
packages.
§ Agile summary level planning documented in road
map. Comprises capabilities, features and stories
§ Agile planning packages driven by persistent teams
with proven benchmarks.
§ Performance Measurement
baseline.
§ Is there a target threshold for future work as described
in a PMB? Within 10% OTB?
§ Undistributed budget logs. § Does this have anything to do with SW dev approach?
§ Notification to the customer
of an over–target baseline.
§ Does this have anything to do with SW dev approach?
§ Work authorization
document.
§ Does this have anything to do with sw dev approach?
40
GL 16: Record Direct Costs
Record direct costs in a manner consistent with the budgets in a formal system
controlled by the general books of account.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Reconciliation of project costs with the
accounting system.
§ CAM would follow program direction on
these.
§ These are not impacted by sw dev
approach
§ Actual costs are reported at the control
account level at a minimum.
§ Not impacted by SW development
approach.
§ Reconciliation of subcontract reported
actual costs to subcontract payments.
§ Not impacted by SW development
approach.
§ Internal and external performance reports
for subcontractors.
§ Not impacted by SW development
approach.
§ Subcontractor control account plans,
when utilized.
§ Not impacted by SW development
approach.
41
GL 23: Determine Variances
Identify, at least monthly, the significant differences between both planned and actual
schedule performance and planned and actual cost performance, and provide the
reasons for the variances in the detail needed by program management.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Variance analyses (budget based
schedule variances and cost variances).
§ Can track & report variances per the
approved program system description
§ Management action plans. § Actionable recovery plans per issue.
§ Updated schedule task completion and
cost–at–completion forecasts.
§ Scrum Agile has a POD and Plan for
Iteration.
§ CAM’s monthly EAC reporting follows
the approved program system
description
§ Project schedules and schedule analysis
outputs.
§ PM tracks the dynamic backlog, which
will go up and down based on sponsor
feedback
42
GL 25: Summarize Variances
Summarize the data elements and associated variances through the program
organization and/or work breakdown structure to support management needs and any
customer reporting specified in the project.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Variance analyses. § There is nothing in Agile’s approach to SW
development that precludes reporting variances at
the WP level.
§ Agile is more dynamic than EVM so variances are
less the issue than the evolving baseline, as
approved in governance. The sponsor will want to
track accumulating business value and variances
to total product needs.
§ Schedule and cost performance
reports.
§ Similar – but measures of performance not
usually in dollars
§ Management action plans. § Similar – but less formal. Collaborative discussion
of what actions to take include the customer.
§ Updated schedule and cost
forecasts.
§ Similar – but less formal. Planning processes
include the customer.
43
GL 26: Implement Management Plan
Implement managerial action taken as the result of earned value information.
EVMIG Objective
Evidence
Agile Objective Evidence for EV
§ To–Complete
Performance Index
(TCPI).
§ TCPI = Work Remaining / Cost Remaining ((BAC –
BCWPcum) / (EAC – ACWPcum)). In Agile, work remaining
is the product backlog. Backlog is BAC – BCWP.
§ Independent
completion estimates.
§ No longer used in 2010
§ Risk management data
and similar metrics.
§ Qualitative Risk Burn–down Chart (risk rating)
§ Management action
plans and review
briefings.
§ Agile approach called Commitment Based Planning –
where the SCRUM team makes and meets its time phase
BCWS commitments.
§ Any team, when behind, gives voice to the customer when
evaluating/reweighting the triple constraint.
§ Variance analyses.
§ This is an issue of cost mgmt and system description
would define when and where team members would bill
44
GL 28: Incorporate Changes (1)
Incorporate authorized changes in a timely manner, recording the effects of such
changes in the budgets and schedules.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Contractual change documents.
§ Bug reports, new user stories, but not
necessarily cost sized.
§ User stories above baseline are tracked as
new scope (with a valid BOE) and require
BCWS
§ Change control logs (management
reserve, undistributed budget,
performance measurement baseline,
and contract budget base).
§ New or materially altered features or stories
are changes.
§ Control account/work
package/planning package plans.
§ Product and iteration backlogs are frozen
during the development period
45
GL 28: Incorporate Changes (2)
Incorporate authorized changes in a timely manner, recording the effects of such
changes in the budgets and schedules.
EVMIG Objective Evidence Agile Objective Evidence for EV
§ Master schedules, intermediate
schedules (if any), and detailed
schedules.
§ Iterations and evolutionary planning at the
detailed levels merges with the end to end
planning for agile.
§ Statement of work, WBS, and WBS
dictionary.
§ Customer owner and Planning processes
identify requires work and its description.
§ Work authorization documents.
§ Planning sessions, authorize a set of
Stories to be developed during the iteration.
§ Management reports (contract
performance reports or other
applicable management reports).
§ Big Visible Charts, “sticky notes” display
progress to plan for the agile team.

More Related Content

What's hot

Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingGlen Alleman
 
Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Glen Alleman
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance ManagementGlen Alleman
 
Parametric project metrics
Parametric project metricsParametric project metrics
Parametric project metricsGlen Alleman
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darksideGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Glen Alleman
 
Failure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value ManagementFailure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value ManagementGlen Alleman
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMGlen Alleman
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)Glen Alleman
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based PlanningGlen Alleman
 
Calculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsCalculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsGlen Alleman
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management HandbookGlen Alleman
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contractsGlen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to programGlen Alleman
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsGlen Alleman
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)Glen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 

What's hot (20)

Building a Credible Performance Measurement Baseling
Building a Credible Performance Measurement BaselingBuilding a Credible Performance Measurement Baseling
Building a Credible Performance Measurement Baseling
 
Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2Using balanced scorecard to build a project focused org2
Using balanced scorecard to build a project focused org2
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
Parametric project metrics
Parametric project metricsParametric project metrics
Parametric project metrics
 
EVM+Agile the darkside
EVM+Agile the darksideEVM+Agile the darkside
EVM+Agile the darkside
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)Agile+EVM bibliography (v2)
Agile+EVM bibliography (v2)
 
Failure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value ManagementFailure Modes of Integrating Agile with Earned Value Management
Failure Modes of Integrating Agile with Earned Value Management
 
Six ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAMSix ½ Day Sessions on the Road To Becoming a CAM
Six ½ Day Sessions on the Road To Becoming a CAM
 
Focus on the nine I's (v9)
Focus on the nine I's (v9)Focus on the nine I's (v9)
Focus on the nine I's (v9)
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based Planning
 
Calculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile ProjectsCalculating Physical Percent Complete on Agile Projects
Calculating Physical Percent Complete on Agile Projects
 
Performance Based Management Handbook
Performance Based Management HandbookPerformance Based Management Handbook
Performance Based Management Handbook
 
Earned value, XP and government contracts
Earned value, XP and government contractsEarned value, XP and government contracts
Earned value, XP and government contracts
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 
A credible pmb is the window to program
A credible pmb is the window to programA credible pmb is the window to program
A credible pmb is the window to program
 
Estimating and Reporting Agile Projects
Estimating and Reporting Agile ProjectsEstimating and Reporting Agile Projects
Estimating and Reporting Agile Projects
 
Alleman ps03 - physical percent complete (v2)
Alleman   ps03 - physical percent complete (v2)Alleman   ps03 - physical percent complete (v2)
Alleman ps03 - physical percent complete (v2)
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 

Similar to Integrated Agile Software Development with Earned Value Management

Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentGlen Alleman
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = SuccessGlen Alleman
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)Glen Alleman
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government ContractingGlen Alleman
 
WBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP ProjectsWBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP ProjectsGlen Alleman
 
DevOps, SAFe and critical information bearers: A practical approach for plann...
DevOps, SAFe and critical information bearers: A practical approach for plann...DevOps, SAFe and critical information bearers: A practical approach for plann...
DevOps, SAFe and critical information bearers: A practical approach for plann...Bosnia Agile
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Software Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer ScienceSoftware Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer ScienceArti Parab Academics
 
Physical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsPhysical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsGlen Alleman
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessGlen Alleman
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementGlen Alleman
 

Similar to Integrated Agile Software Development with Earned Value Management (20)

Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = Success
 
How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)How should we estimates agile projects (CAST)
How should we estimates agile projects (CAST)
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)How to build a credible performance measurement baseline (v5)
How to build a credible performance measurement baseline (v5)
 
Making Agile Development work in Government Contracting
Making Agile Development work in Government ContractingMaking Agile Development work in Government Contracting
Making Agile Development work in Government Contracting
 
WBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP ProjectsWBS Compliance Challenges for Agile ERP Projects
WBS Compliance Challenges for Agile ERP Projects
 
DevOps, SAFe and critical information bearers: A practical approach for plann...
DevOps, SAFe and critical information bearers: A practical approach for plann...DevOps, SAFe and critical information bearers: A practical approach for plann...
DevOps, SAFe and critical information bearers: A practical approach for plann...
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Slides chapters 24-25
Slides chapters 24-25Slides chapters 24-25
Slides chapters 24-25
 
SE chapters 24-25
SE chapters 24-25SE chapters 24-25
SE chapters 24-25
 
Software Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer ScienceSoftware Engineering Fundamentals in Computer Science
Software Engineering Fundamentals in Computer Science
 
Physical Percent Complete for Agile Projects
Physical Percent Complete for Agile ProjectsPhysical Percent Complete for Agile Projects
Physical Percent Complete for Agile Projects
 
Five Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation SuccessFive Immutable Principles of Project of Digital Transformation Success
Five Immutable Principles of Project of Digital Transformation Success
 
Agile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value ManagementAgile Project Management Meets Earned Value Management
Agile Project Management Meets Earned Value Management
 
DPPM1
DPPM1DPPM1
DPPM1
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesGlen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Increasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and PracticesIncreasing the Probability of Project Success with Five Principles and Practices
Increasing the Probability of Project Success with Five Principles and Practices
 

Recently uploaded

[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProduct Anonymous
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 

Recently uploaded (20)

[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 

Integrated Agile Software Development with Earned Value Management

  • 2. 2 Today’s Briefing • How can Agile Software Development methods increase the Probability of Program Success (PoPS) on Earned Value programs? • How can Agile development integrate with the FAR / DFAR and OMB mandates for program performance measures using Earned Value? • What are the “touch” points (or possible collision points) between Agile and EIA-748-C? • What are the measures of success for Agile methods in the context of EIA-748-C?
  • 3. 3 3 Let’s Start With A Critical Assumption: Project Controls are needed for Project Success
  • 4. 4 In case we’ve forgotten what EIA-748-C says • EIA-748-C, page 1, defines the top level activities for a successful EV based project. • We need to “connect the dots” between these and agile development. § Plan all work scope for the program from inception to completion. § Break down the program work into finite pieces that can be assigned to a responsible person or organization for control of technical, schedule, and cost objectives. § Integrate program work scope, schedule, cost objectives into a performance measurement baseline plan against with accomplishments may be measured. Control changes to the baseline. § Use actual costs incurred and recorded in accomplishing the work performed. § Objectively assess accomplishments at the work performance level. § Analyze significant variances from the plan, forecast impacts, and prepare and estimate at completion based on performance to date and work to be performed. § Use this information in the organization's management processes
  • 5. 5 When we Hear Agile, What Does That Mean? † Dr. Ashton Carter, Under Secretary of Defense for Acquisition, Technology and Logistics, Sep/Oct, 2010 Defense AT&L “Being able to turn inside the loop of unfolding events.”†
  • 6. 6 12 Principles of the Agile Manifesto
  • 7. 7 IMP Captures End User Requirements in Terms MOEs, MOPs, KPPs, and TPMs SOW ConOps WBS CWBS Technical Performance Measures (TPM) Messages of Performance (MOP) Measures of Effectiveness (MOE) Key Performance Parameters (KPP) Integrated Master Plan (IMP) Integrated Master Schedule (IMS) Performance Measurement Baseline (PMB) Technical Requirements
  • 8. 8 Some Critical Concepts in Agile Product Time Capabilities A high level system function completed across multiple releases Features Stories A well define system function to be completed within a release A small well defined system function that can be developed within one sprint Release Sprint † Earned Value Managementfor Scrum Programs:Industry Best Practices, National Defense Industry Association Integrated Program ManagementDivision (NDIAIPMD) Scrum EVM Working Group
  • 9. 9 Putting Earned Value Management and Agile Software Development Together Feature 1,2,3 Feature 4,5,6 Feature 7,8,9 Release 1 Release 2 Release 2 PP’s WP PP SLPP in IMS CA EVM Reporting from Work Package Performance EVM Performance • BCWS – fromWBS Basis of Estimate • ACWP – fromtime cards • BCWP – from completed Story Points Sprints Time Now n Starting with the IMP,defined Capabilitiesare flowed to the PMB n Capabilitiesproduce the value fromeach Release n Control Accounts and Work Packages are on baseline in the PMB n Work Packages contain Features produced in each Release by Sprints n Release Planning baseline for period of performance and BCWS Vertical and horizontal integration of all work planned fromthe IMP/IMSdown to Releases, Sprints, and Tasks in the Scrum Development Management system. Performance Measurement Baseline Scrum Software Development Lifecycle Feature n The Bright Line Milestones Data Items IMP ProgramEvents IMP Accomplishments and Criteria Scrum Development Control Account Task Task Task Task Task Task Task Task Task …
  • 10. 10 Ordinal Story Point cannot be basis of BCWS higher than a Feature 10 Feature 1 Story Story Story Story Story Story Team 1’s Uncalibrated Ordinal SP estimates Feature n Story Story Story Story Story Story Team 2’s Uncalibrated Ordinal SP estimates ∑ F1(SP) ∑ Fn(SP) Release 1 ∑ of SP’s • • • § At the Story level, relative effort defines individual estimates. § At the Feature level, lower level SP’s don’t have the same unit of measure in the way Dollars do. § When Features summed to the Release, relative measures do not provide basis of Physical Percent Complete. Not same units of measure between Features – Uncalibrated SP’s
  • 11. 11 Building the PMB in a Agile Paradigm WBS Iteration 1 Iteration 2 Iteration 3 … Iteration n Close Out § Deliverables § Tasks § Tasks § Deliverables § Deliverables § Deliverables § Tasks § Tasks CA CoDR … PDR WBS basis of deliverables Backlog, per MIL-STD-881C, decomposed into Release Backlog, then into Iteration Backlog for delivery by Stories and Tasks.
  • 12. 12 An Actual Earned Value + Agile Program
  • 13. 13 CONNECTING THE MOVING PARTS INTO AN INTEGRATED WHOLE With both Earned Value and Agile parts, let’s connect them into a Performance Measurement Baseline ready for execution and reporting in the IPMR
  • 14. 14 Three Systems are Needed for an Integrated Solution • Shared data between each system with a single system of record. • Planning flowed from IMS to Agile development system • Physical Percent Complete flowed back to IMS then to EVMS
  • 15. 15 Data Connectivity in the Integrated System
  • 17. 17 STEPS TO SETTING UP THE PMB FOR AGILE + EVM Here’s the step-by-step activities to define the Performance Measurement Baseline (PMB) and get it on Baseline in Team Foundation Server, the IMS, and COBRA. This includes Baseline Change Requests and statusing of the baseline to report EV in the IPMR. This is the secret sauce of the principles and theory
  • 18. 18 Simple Rule for Earning Value in Agile Each Iteration of each Release is a “value earning” opportunity The next step is to connect Agile’s definition of Value with Earned Value’s definition of Value Business Value ≠ BCWP
  • 19. 19 Starting to “Connect the Dots” † ‡ Agile Point of View DoD Program Point of View Requirements evolve Scope agreed to and maintained Simple designs are best Architecture thought out and maintained Teams are self organizing Organizational structure establishes boundaries Delivery teams establish best prescriptive processes High level guidance organizes work Development teams know what to do Process professionals define the boundaries Agile teams work in an iterative manner Product Development Lifecycle is serial over broader periods of time † Abstracted from “Reality over Rhetoric,” Scott Ambler IBM Developer Works ‡ John Goodpastuer, Project Management the Agile Way
  • 20. 20 Let’s Start With 3 Simple Connections Earned Value Management Agile Both EV and Agile Development Measure Progress as Physical Percent Complete + 1 Measures of progress in units of “physical percent complete.” Each sprint produces 100% working product. 2 Forecast of future performance provided by past performance. Forecast performance in units of product(s) produced. 3 A systems approach to the development of products and connecting Cost, Schedule, and Technical Performance. Increasing fidelity of product and problem understanding takes place after each sprint and release.
  • 21. 21 EVM + Agile Process Flow WBS Story Feature Place Work on Backlog Estimate Story Points Work Package BCWS Execute Sprint Record SPs Complete Calculate P%C with SPs Load P%C for WP in IMS Send P%C to Cobra Calculate BCWP 1. With the WBS decomposed to Features, Stories, and Story Point estimates 2. Place Features and Stories on Scrum backlog. 3. Perform work in Sprints. 4. Record Stories earned and calculate Physical Percent Complete (P%C) 5. Send to the IMS and to Cobra 6. Calculate BCWP = BCWS × P%C in Cobra The Bright Line SOW ConOps
  • 22. 22 Assess Performance On A Weekly Basis Feature Story Story Story Story Planned 24 SP % Complete 100% 100% 0% 0% Remaining 4 SP Earned 20 SP Week 1 Week 2 Week 3 Week 4 20 Day Sprints Every Thursday Status § Physical Percent Complete § SP’s remaining to 100% 8 SP’s 8 SP’s 4 SP’s 4 SP’s
  • 23. 23 Here’s Those Connections GL EVM Criteria Agile Approach 1 Define WBS Features and Stories define tasks 2 Identify Organization Self organizing teams 5 Integrate WBS and OBS Self organized teams with a customer 6 Schedule Work Iterations and Releases 7 Identify Products & Milestones Working software at the end of iterations 8 Set time phased budget Fixed length iterations and releases 16 Record direct costs Fixed staff = Level of Effort 23 Determine variances EV + Velocity measures missed features 25 Sum data and variance Missed features moved to next iteration 26 Manage action plans Replan missed features, adjust velocity 28 Incorporate changes Replan missed features, adjust velocity
  • 24. 24 Provide managers with information at a practical level of summarization Relate time phased budgets to specific contract tasks Enable statistical estimation of completion costs Track and monitor discrete project metrics Communicate project status Provide quantitative data for decision making Provide a documented project performance trail Alert project managers to potential schedule and cost risk Program Controls Practice But First, Let’s Not Forget Business Management Practices … …That Must Be Recognized Before Connecting Agile and EVM
  • 25. 25 11 EVM GL’s and 12 Agile Principles Connecting Agile with Earned Value Management is actually obvious once we get over the social aspects and focus on the Program Planning and Controls aspects. WBS OBS WBS+OBS IMS Productsand Milestones PMB ACWP Variances Sumof Variances Corrective Action Record Changes Early and Continuous Delivery ✔ ✔ ✔ Welcome Change ✔ ✔ ✔ ✔ Deliver working Software ✔ ✔ ✔ Business and DEV work together ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ ✔ Motivated individuals ✔ Sustainable development ✔ ✔ ✔ ✔ ✔ Working SW measure of progress ✔ ✔ Face-to-Face communications ✔ ✔ ✔ ✔ Continuous technical excellence ✔ ✔ Maximize work not done ✔ Self-organizing teams ✔ ✔ Regular reflections ✔ ✔ ✔ ✔ ✔
  • 26. 26 Putting Earned Value Management and Agile Software Development Together one more time Feature 1,2,3 Feature 4,5,6 Feature 7,8,9 Release 1 Release 2 Release 2 PP’s WP PP SLPP in IMS CA EVM Reporting from Work Package Performance EVM Performance • BCWS – fromWBS Basis of Estimate • ACWP – fromtime cards • BCWP – from completed Story Points Sprints Time Now n Starting with the IMP,defined Capabilitiesare flowed to the PMB n Capabilitiesproduce the value fromeach Release n Control Accounts and Work Packages are on baseline in the PMB n Work Packages contain Features produced in each Release by Sprints n Release Planning baseline for period of performance and BCWS Vertical and horizontal integration of all work planned fromthe IMP/IMSdown to Releases, Sprints, and Tasks in the Scrum Development Management system. Performance Measurement Baseline Scrum Software Development Lifecycle Feature n The Bright Line Milestones Data Items IMP ProgramEvents IMP Accomplishments and Criteria Scrum Development Control Account Task Task Task Task Task Task Task Task Task …
  • 27. 27 The Reason EV + Agile is a Match Made in Heaven The faster you obtain your intelligence The more intelligent your decisions From an Aviation Week & Space Technology Ad† Agile forces the measures of physical percent complete at the end of every Sprint. By adopting this principle alone, EVM will have measures of Physical Percent Complete – Working Software – assessment every two weeks Otherwise you’re not doing Agile † L3 ad for UAV, AW&ST, September 14-27, 2014, pg. 37
  • 28. 28
  • 29. 29 PUTTING THESE IDEAS TO WORK Using the Earned Value Management Intent Guide (EVMIG), here’s how to connect the dots at the next level down. The 11 criteria of Earned Value connected with the 12 principles of Agile.
  • 30. 30 Assemble a credible WBS and Integrated Master Plan / Integrated Master Schedule (IMP/IMS) –WBS Dictionary says what will be built –IMP/IMS says how, where, when, and what will be built and the processes to build it. Identify Reducible – Event Based – uncertainties and the resulting risks from WBS Dictionary and IMP Narratives in the Risk Register Put these these risks in the Risk Register, with probability and impacts Develop risk retirement plans and place them in the IMS using CBB funding for risk buy down. 30 Building a Risk Adjusted PMB in Steps 0 1 2 3 8
  • 31. 31 Assess the Irreducible – naturally occurring – uncertainties and the resulting schedule and cost risks in the WBS and IMS. Use Monte Carlo Simulation to determine schedule margin and budget impacts from work activity durations to handle these irreducible uncertainties. Assign schedule and cost margin to protect key item deliverables in the IMS. 31 Building a Risk Adjusted PMB in Steps 4 5 6 8
  • 32. 32 Determine cost and schedule impacts of unmitigated risks in the risk register and place them in Management Reserve, with their exposure and impact Assemble mitigated Irreducible (Aleatory) and Reducible (Epistemic) risks with the unmitigated event–based risks into the Total Allocated Budget – Risk handling an baseline for reducible and irreducible in the PMB. – Risk Handling in Management Reserve. 32 Building a Risk Adjusted PMB in Steps (Concluded) 8 7 8
  • 33. 33 Steps to connecting the Agile Release Cycle with the Performance Measurement Baseline 1. Establish Releases 2. Establish Iterations within each release 3. Establish Stories from the WBS and allocate them to each release 4. Assign resources to each Story 5. Estimate work effort – in hours – to each story 6. Assess if capacity for work ≥ demand for work 7. Repeat Steps 4, 5, and 6 until demand equals capacity
  • 34. 34 GL 1: Define Authorized Work Elements Define the authorized work elements for the program. A work breakdown structure (WBS), tailored for effective internal management control, is commonly used in this process. EVMIG Objective Evidence Agile Objective Evidence for EV § Work Breakdown Structure (WBS). § Road Map & Release Plan consisting of Capabilities, Product Backlog & Iteration Backlog. § WBS dictionary (may or may not be used, but a method to reconcile the statement of work to the WBS structure must be demonstrated). § WBS dictionary: agile user stories are deliverables that you can measure “done” for, therefore user stories satisfy wbs dictionary.
  • 35. 35 GL 2: Identify Program Organizational Structure Identify the program organizational structure, including the major subcontractors responsible for accomplishing the authorized work, and define the organizational elements in which work will be planned and controlled. EVMIG Objective Evidence Agile Objective Evidence for EV § Organization Breakdown Structure (OBS). § CAM just builds a team as usual, but the team needs to be persistent, and not interchangeable parts. § OBS intersections with the WBS. § Team hierarchy definition with resources associated with their sub–teams. § Done at the level of granularity to support the basis of estimate (BOE). § Persistent teams are needed to apply throughput benchmarks to product backlogs to validate plans.
  • 36. 36 GL 5: Integrate WBS and OBS Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed. EVMIG Objective Evidence Agile Objective Evidence for EV § Control accounts. § Evidence that the CA meets the 90% discrete work rule. § Defend schedule & cost performance at the CA level? § Agile CA = one release. § Actuals captured at the story level. § Responsibility Assignment Matrix (RAM). § Done at too high a level for the SW development approach to make a difference. § Contract Performance Reports (CPRs), if applicable. § Given an objective of X stories in iteration Y, completed stories are earned; all unearned return to backlog and a new ETC is developed from the benchmarks & backlog.
  • 37. 37 GL 6: Schedule the Work Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program. EVMIG Objective Evidence Agile Objective Evidence for EV § Integrated network schedules including master, intermediate (if any), and detailed schedules. § CAM’s agile roadmap becomes the auditable intermediate schedule demonstrating significant accomplishments (SA). § MRP or ERP schedules, or planned order reports. § Each task in IMS has associated resources. § Control account plans (may be separate plans or detail schedules). § CAM creates schedules compliant to DCMA 14 point assessment. § Work authorization documents. § Nothing different.
  • 38. 38 GL 7: Identify Products and Milestones Identify physical products, milestones, technical performance goals, or other indicators that will be used to measure progress. EVMIG Objective Evidence Agile Objective Evidence for EV § Integrated schedules including master, intermediate (if any), and detailed schedules that identify contract milestones and key events. § Agile dev performance reporting follows the approved program system description § Apportioned technical performance milestones to reduce risk & roll up intermediate technical performance. § MRP or ERP production planned order reports. § Not relevant to sw development. § Control account plans (may be separate plans or detail schedules) § Not relevant to Software Development because we are reporting tasks as physical % complete, which will automatically roll up.
  • 39. 39 GL 8: Set Time Phased Budget Establish and maintain a time–phased budget baseline, at the control account level, against which program performance can be measured. Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work. EVMIG Objective Evidence Agile Objective Evidence for EV § Control account plans. § Time phased budget created for the current iteration(s) and future work. § Summary level planning packages. § Agile summary level planning documented in road map. Comprises capabilities, features and stories § Agile planning packages driven by persistent teams with proven benchmarks. § Performance Measurement baseline. § Is there a target threshold for future work as described in a PMB? Within 10% OTB? § Undistributed budget logs. § Does this have anything to do with SW dev approach? § Notification to the customer of an over–target baseline. § Does this have anything to do with SW dev approach? § Work authorization document. § Does this have anything to do with sw dev approach?
  • 40. 40 GL 16: Record Direct Costs Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account. EVMIG Objective Evidence Agile Objective Evidence for EV § Reconciliation of project costs with the accounting system. § CAM would follow program direction on these. § These are not impacted by sw dev approach § Actual costs are reported at the control account level at a minimum. § Not impacted by SW development approach. § Reconciliation of subcontract reported actual costs to subcontract payments. § Not impacted by SW development approach. § Internal and external performance reports for subcontractors. § Not impacted by SW development approach. § Subcontractor control account plans, when utilized. § Not impacted by SW development approach.
  • 41. 41 GL 23: Determine Variances Identify, at least monthly, the significant differences between both planned and actual schedule performance and planned and actual cost performance, and provide the reasons for the variances in the detail needed by program management. EVMIG Objective Evidence Agile Objective Evidence for EV § Variance analyses (budget based schedule variances and cost variances). § Can track & report variances per the approved program system description § Management action plans. § Actionable recovery plans per issue. § Updated schedule task completion and cost–at–completion forecasts. § Scrum Agile has a POD and Plan for Iteration. § CAM’s monthly EAC reporting follows the approved program system description § Project schedules and schedule analysis outputs. § PM tracks the dynamic backlog, which will go up and down based on sponsor feedback
  • 42. 42 GL 25: Summarize Variances Summarize the data elements and associated variances through the program organization and/or work breakdown structure to support management needs and any customer reporting specified in the project. EVMIG Objective Evidence Agile Objective Evidence for EV § Variance analyses. § There is nothing in Agile’s approach to SW development that precludes reporting variances at the WP level. § Agile is more dynamic than EVM so variances are less the issue than the evolving baseline, as approved in governance. The sponsor will want to track accumulating business value and variances to total product needs. § Schedule and cost performance reports. § Similar – but measures of performance not usually in dollars § Management action plans. § Similar – but less formal. Collaborative discussion of what actions to take include the customer. § Updated schedule and cost forecasts. § Similar – but less formal. Planning processes include the customer.
  • 43. 43 GL 26: Implement Management Plan Implement managerial action taken as the result of earned value information. EVMIG Objective Evidence Agile Objective Evidence for EV § To–Complete Performance Index (TCPI). § TCPI = Work Remaining / Cost Remaining ((BAC – BCWPcum) / (EAC – ACWPcum)). In Agile, work remaining is the product backlog. Backlog is BAC – BCWP. § Independent completion estimates. § No longer used in 2010 § Risk management data and similar metrics. § Qualitative Risk Burn–down Chart (risk rating) § Management action plans and review briefings. § Agile approach called Commitment Based Planning – where the SCRUM team makes and meets its time phase BCWS commitments. § Any team, when behind, gives voice to the customer when evaluating/reweighting the triple constraint. § Variance analyses. § This is an issue of cost mgmt and system description would define when and where team members would bill
  • 44. 44 GL 28: Incorporate Changes (1) Incorporate authorized changes in a timely manner, recording the effects of such changes in the budgets and schedules. EVMIG Objective Evidence Agile Objective Evidence for EV § Contractual change documents. § Bug reports, new user stories, but not necessarily cost sized. § User stories above baseline are tracked as new scope (with a valid BOE) and require BCWS § Change control logs (management reserve, undistributed budget, performance measurement baseline, and contract budget base). § New or materially altered features or stories are changes. § Control account/work package/planning package plans. § Product and iteration backlogs are frozen during the development period
  • 45. 45 GL 28: Incorporate Changes (2) Incorporate authorized changes in a timely manner, recording the effects of such changes in the budgets and schedules. EVMIG Objective Evidence Agile Objective Evidence for EV § Master schedules, intermediate schedules (if any), and detailed schedules. § Iterations and evolutionary planning at the detailed levels merges with the end to end planning for agile. § Statement of work, WBS, and WBS dictionary. § Customer owner and Planning processes identify requires work and its description. § Work authorization documents. § Planning sessions, authorize a set of Stories to be developed during the iteration. § Management reports (contract performance reports or other applicable management reports). § Big Visible Charts, “sticky notes” display progress to plan for the agile team.