SlideShare a Scribd company logo
1 of 13
JOB SAFETY ANALYSIS
Doc. No.: HSE/FRM-22
Rev.: 00
Date:
Page: 1 of 3
Project: Project: Area:
General Comments:
Date: / / Supervisor:
Job Description: Lifting & Rigging Activity (Loading/Unloading of the Equipment)
Item Detail of Activity
Equipment &
Tools used
Risk Involved Preventive Measure Responsible Person
Severity
Rating
1
TRANSPORTATION
OF THE MATERIALS
& CRANE TO JOB
SITE.
• CRANE
• TRAILER
• FLAT BED
• MULTI AXEL
TRAILER
• LIFTING GEARS
(SLINGS,
SHACKLES,
WEB-BELT,
TAG LINE,
CHAIN BLOCK,
LEVER HOST, FORK
LIFTER, PICK WAY
TRUCK & ETC).
• UNEVEN ROAD
• UNSAFE CONDITIONS
• CRANE SHOULD BE CHECKED, BEFORE
TRANSPORTATION TO JOB SITE ON DAILY BASIS.
RIGGING
SUPERVISOR
2
2
2
MATERIAL LOADING /
UNLOADING
• CRANE COLLAPSE DURING
• LIFTING
• PERSONAL INJUREY
• PROPERTY DAMAGE
• PROPER ACCESS (BRIDGES) SHOULD BE USED.
• FLAGMAN WILL BE ASSIGNED WITH THE CRANE &
HEAVY EQUIPMENT.
• MATERIAL MUST BE CHECKED BEFORE LOADING /
UNLOADING.
AREA AUTHORIZES
3
3
2
3
3
SETTING UP CRANE
FOR LIFTING.
• CRANE FAILURE DUE TO
HYDROLIC SYSTEM
• CAUSE OF SERIOUS
• MATERIAL MUST BE PROPERLY SECURED WITH
SLING & SHACKLES BEFORE LIFTING UP.
• CRANE WILL BE SET UP AT LEVEL SURFACE WITH
OUTRIGGER PADS.
• OUTRIGGERS WILL BE FULLY EXTENDED CRANE.
E & P I/C 2
4 LIFTING WITH CRANE • FIRE DUE TO LOOSE WIRING
• CRANE MUST BE 3RD PARTY CERTIFIED.
• ALL LIFTS WILL BE UNDER THE RATED CAPACITY OF
CRANE I.E. LOAD CHART.
HSE INSPECTOR
2
5
INSPECTION OF
CRANE
& RIGGING GEARS
• FALL OF OBJECT
• CERTIFIED CRANE OPERATOR AND RIGGERS (3RD
PARTY CERTIFIED) WILL CARRY OUT THE LIFTING
ACTIVITY.
RIGGING ENGINEER 3
6
DEMOBILIZATION
CRANES
EQUIPMENT’S,
TOOLS AND
WORKER.
• PERSONNEL INJURY
• SLIPPING
• TRIPPING
• ALL LIFTING TACKLES WILL HAVE 3RD PARTY
• CERTIFICATIONS & HEALTHY (GOOD CONDITION).
• RIGGING PLAN & STUDY REQUIRED FOR HEAVY
LIFTING.
RIGGING
SUPERVISOR
2
• ELECTRIC SHOCK
• DUE TO POWER LINE
• ONLY SINGLE PERSON MUST BE GIVEN SIGNAL TO
CRANE OPERATOR.
• EMPLOYEES SHOULD BE TRAINED ON SAFE
RIGGING TECHNIQUES.
• TOOLBOX TALK MUST BE CONDUCTED BEFORE
EACH LIFT.
• LIFTING AREA SHOULD BE BARRICADED WITH
WARNING.
• ALL LOADS WILL BE CONTROLLED BY TAG LINES, IF
LENGTH IS LONG THAN DOUBLE TAG LINE USED.
• LIFTING CREW WILL WORK WITH COMPLETE PPES.
• AREA MUST BE CHECKED & FREE FROM
ELECTRICAL WIRES BEFORE ASSEMBLING TO THE
CRANE.
7
WORK AT HEIGHT
SCAFFOLDING
CHARRY PICKLES
• MATERIAL CAN FALL
• PERSONAL FALL
• IMPROPER SCAFFOLDING
ERECTION
• TOOL & JOINTS ETC. SHOULD BE LIFT BY ROPE &
BASKET
• SCAFFOLDING SHOULD BE ERECTED UNDER
SKILLED SUPERVISION.
• FULL BODY HARNESS MUST BE WORN WHILE WORK
AT HEIGHT 6 FEET & ABOVE.
• SCAFFOLDING MUST BE ERRECTED WITH
STANDARD & INSPECTED BY SCAFFOLDING
INSPECTOR.
RIGGING
SUPERVISOR
SCAFFOLDING
INSPECTOR
2
3
3
8
WORK AT NIGHT
LIGHTS & STANDS
(FLOOD LIGHTS
WHITE)
• MANUAL HANDLING
• SLIP, TRIP & FALL
• POOR ILLUMINATION
• WORK WOULD BE NEVER ALLOWED IN LESS OR
IMPROPERLY DISPRESSED ILLUMINATION/LIGHTS.
• ALL WORK AT NIGHT ARRANGEMENT MUST BE
DONE BEFORE START OF WORK AT NIGHT.
RIGGING
SUPERVISOR
2
2
2
9 HOUSEKEEPING
WASTE DRUMS
SHOPPER BAGS
• ENVIRONMENT HAZARD
• SLIP, TRIP & FALL
• WASTE MATERIAL SHOULD BE STACKED PROPERLY
& DUMPED IN DESIGNATED PLACES.
• WASTE MATERIAL SHOULD BE BARRICADED.
RIGGING
SUPERVISOR
1
2
Severity Rating: (1) First Aid / Minor Property Damage (2) Recordable Accident / Property Damage
(3) Lost Time Accident / Major Property Loss (4) Catastrophic Accident
Are you aware of, and do you have the correct PPE? What are the risks? How do controlled risks?
_______________________________ __________________________
AREA ENGINEER / SUPERVISOR HSE REPRESENTATIVE
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
S.NO SCOPE OF ACTIVITY HAZARD CONTROL MEASURES REQUEST BY
1) Mobile Crane
to
onsite
destination
1) Faults with Crane
2) Plant becoming bogged in
sand & mud
3) Pedestrians
4) Onsite Traffic/plant
1) Pre-start Checks
2) Plant to stick to designated roadways and turning areas
3) Personnel on hand to warn others of crane movement in the
vicinity or via radio where available.
4) Alternate pathway defined by bollards and reflective tape.
EHS SAFETY
OFFICER/SECURITY
OFFICER
2) Pre-job
meeting
and Toolbox
1) Inexperienced workers
2) Inadequate consultation
3) Inadequate understanding of
equipment
4) Site hazards and emergency
Procedures not known
1) Sufficiently skilled employees to complete task
(competencies and Licences)
2) Adequate consultation with all relevant employees
3) Adequate competent supervision throughout the project
4) Proper planning for equipment required for the task
5) Site & work area inductions compulsory for all personnel
EHS SAFETY
OFFICER/SECURITY
OFFICER
3) Locate crane
into
lifting
positions on
site
1) Pedestrians
2) Traffic
3) Other Plant
4) Other Equipment
5) Buildings Power lines &
underground Utilities
6) Lift radius Access
7) Ground Conditions
1) Desired setup area should also be level,
2) unless prior consultation has been made with the supplier of
the crane
3) The workplace is adequately prepared for the incoming
mobile crane, including where possible a clear predefined
area/crane pad for the crane to position upon
4) Check and confirm exclusion areas - Barricades, witches
Hats, Danger Tape, Warning Signs
5) Access road are available and soundly constructed with
suitable entry points to site
6) Crew should always inspect site prior to positioning crane in
final position
7) Elements to observe include
8) Load location and scope of lift
9) Location of any overhead obstructions including wires, trees,
buildings, restricted airspace (i.e. near airport)
10) Location of any underground services and/or trenches
including utilities and drainage arrangements that may affect
integrity of ground
11) Adequate room for rigging and erection of mobile crane
12) Adequate tail (counterweight/winch) swing clearance
13) Ability to cordon off area with suitable barricading
resources
EHS SAFETY
OFFICER/SECURITY
OFFICER
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
4) Inspect chains
and
or slings,
shackles,
hooks and
attachment
points in
preparation for
use
1) Tears in Slings
2) Cracks in chains, shackles,
rings and hooks
3) Dropping of load due to faulty
4) lifting gear or faulty
attachment points
1) Check slings for rips and tears and remove from service is
faults are found
2) Check chains, shackles, hooks and rings for cracks,
corrosion, wears, mechanism faults etc and remove from
service if faults are found
3) Lifting gear/equipment inspected and tagged with appropriate
monthly colour tag
4) Make certain personnel are sufficiently trained with
appropriate certificates/ licences
5) Locate crane in
lifting position
on site
– place timbers
(pads) and set
outriggers
1) Crane overturning due to
unstable ground condition
2) Personnel being crushed by
outriggers
1) Outriggers must be positioned on a flat surface,
2) Using timbers or suitable material for pads to evenly
distribute the load to the ground
3) Crane to be located within the radius for the loads being
Lifted.
4) Outriggers should only be extended on the side where the
Operator is positioned or with a suitable spotter.
5) Where space permits, outriggers shall always be fully
extended
6) Where space is limited, crane should be configured to
maximum capacity – this may require the use of reduced
outriggers or on rubber; when permitted by the manufacturer
7) Outriggers shall always be extended to manufacturers
procedures and specifications, including the requirement to fit
manual pins
8) All outriggers-jacks should be utilized at all time
9) Generally Standard Safe Working Load capacity charts are
based on all outriggers fully extended and set with wheels
clear of ground.
10) Outrigger Packing –
11) Additional packing should always be utilized under outrigger
floats
12) Commonly used Outrigger Mats should carry design
information and be subject to periodic inspection
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
13) When timber packing is utilized, it should be in a ‘pigsty
‘packing
14) Arrangement ‘Rule of Thumb’ formulae and calculations
should be observed;
15) Area (m2) = 0.65 x (Cm + L)
-------------
V
Cm = Total mass of crane (KN)
L = Total mass of load (KN)
V = maximum permissible bearing pressure of soil (kpa
6) Attaching Fly
or Pin
Jib to Crane
Working at heights/falling 1) Follow W/H permit use appropriate attachment point & safety
harness when walking along crane boom
2) Use an EWP or ladder for this task & follow safe work
practices
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
7) Position
counterweight
truck
in an easily
accessible
spot for
the crane to
load its
counterweights
Position
counterweight truck
in an easily
accessible spot for
the crane to load its
counterweights
1) Plant to be positioned in area clear of obstruction. Roads
2) Traffic control in place if required
3) Once crane is elevated and level, a trial operation should be
completed by the operator; this may include
4) Bluffing boom to high angle, and slewing 360 degrees with
spotter in position – purpose to review tail swing and
outrigger packing suitability
5) Executing ‘dry-run’ where load is required to be picked up
and placed – Purpose to ensure crane is capable of task and
set required limits
8) Re-assessing
Situation
throughout
job
Changes in weather
conditions
Changes in operators
Changes in ground suitability
1) Continual safe operation can be aided by periodic inspection
throughout the project of the following;
2) Outrigger Jacks – Leaking oil/retraction of shaft
3) Outrigger Mats – excessive settlement and/or sinking into
ground; i.e., loadings increasing beyond estimated capacity
of ground – such as unknown back-filling
4) Outrigger Floats – Cracking or critical damage
5) Evidence of water content in ground
6) Should requirements change during operation, then crew
shall re-assess and review crane capacity and wider
environment to ensure revised work practice is within limits
and safe to continue operation
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
9) 10.Packing up
and/or
leaving crane
onsite
Unauthorised person access
crane site
Damage to crane
Injury to public
1) Upon completion of project, or specific stage the crane
2) equipment and site shall be left in a secure and safe manner
3) If the crane is to be left onsite;
4) Retract Boom, remove keys from the ignition and secure/lock
5) Outriggers should be inspected prior to next use
6) Barricading should remain in place around the crane and any
work area deemed necessary
10) Packing up and
cleaning up
work site
Trip hazards
Manual handling injuries
Crush & Pinch injuries
Equipment damage
Counterweights coming off
the back of the truck
Crush & pinch injuries
Falls
1) Use correct manual handling techniques
2) Wear appropriate PPE
3) Rubbish to be placed in bins
4) Tools & Equipment to be packed
5) Lifting gear packed
6) Timbers packed
7) Pads loaded
8) Make certain counterweights are stacked on rubber mats and
correctly tied down for trip
9) Guide counterweights onto the truck tray with taglines
10) Where possible use EWP or Platform Ladder Access
otherwise be cautious of footing
JSA FOR crane operation
Name of the Site :
Date of Preparation :
JSA Preparation :
11) Exit site and
return
to Depot
Overhead Powerlines
Collision with
people/personnel and other
vehicles/plant when exiting
site
Counterweights sliding off
during travel
Traffic Accident
1) Crane boom to be down when travelling under power lines
2) Maintain site speed limit when exiting work site
3) Communicate with other vehicles onsite is necessary
4) Observe road rules and take into consideration drivers and
riders who don’t understand the nature of cranes and trucks.
CHANGING CONDITIONS & EMERGENCY PROCEDURE: Stop Work, Switch off equipment, Supervisor Direct Personnel to Nearest and Safety Muster Point considering
wind direction. Supervisor accounts for all workers. In case of emergency contact 911 / 02-425-0911
Job Safety Analysis
PROJECT TITTLE
Company:
Risk Assessment No: NEW REVISED √ PAGE NO. 1 of 6
Type of Job Being Analyzed Risk Assessment on Lifting Works
Department/Section Originate JSA
Risk Assessment
Team
JOB Performers
Additional approvals (Determine by Job Supervisor in Correlation with HSE Manager) GENERAL JOB REQUIREMENTS: TBM & PPE
Company Representative
Name Signature Date 1. Pre task tool box meeting everyday.
2. Personal Protective Equipment
2.1 Safety Shoes with steel toe.
2.2 Safety glasses
2.3 Hard hat
2.4 Hand gloves
2.5 Cover all to workers
2.6 Full body harness on working at heights
2.7 Chin strap for helmets
2.8 Appropriate mask or respirators
GS C
Job Safety Analysis on Lifting Works
Task / Activities Initial Risk
Initial Risk
Rating Control Measures Responsible
Residual
Risk
Rating
H M L H M L
Doc. No. REV. A Page 2 of 4
1. Work permit
Prior to commencing all
works, a work permit is
required.
· Check safety condition of whole area
for electrical exposure
-Slip, trip, fall during site inspection.
-Moving machineries.
L
• Safe Work Permit and other pertinent documents shall
be secured before any works commence.
• Pre-start meeting shall be discussed during daily
toolbox meeting before work commence.
• Equipment and tool inspection must be carried out.
• Concerned supervisor / foreman to prepare required
safe work plan / permit one day in advance.
• Joint Visit of Permit Issuer, Permit Receiver, Supervisor
and HSE Officer should be conducted before issuing
the Work Permit.
• Supervisor / foreman and safety officer to supervise
and monitor the activity respectively
Supervisor
Permit Issuer
Permit Receiver
HSE Officer L
2. Manpower
mobilization
-Lack of hazard recognition and
awareness of the new workers.
- Incompetent and inexperience
workers
-Lack of training
L
• Hire competent workers.
• Safety induction and training.
• Toolbox meeting before work
• All workers shall be issued with basic PPE and must
wear them on site at all time
• Proper supervision and safety coverage
• Initial gas testing should be conducted
Work Supervisor
HSE Officer
L
3. Equipment
mobilization &
Usage of tools &
equipment.
-Injury of workers (cutting, pinch points,
caught in between, struck by flying
objects, etc.)
- Ergonomics and manual handling.
- Moving machineries.
L
• Inspect before use for qualification.
• Defective equip or tool shall not be used.
• Regularly check and maintenance.
• Implementation of color coding system,
• Ensure competent workers with necessary training
• Proper usage of PPE.
• Following proper procedure on tools & equipment
usage.
• Proper supervision and safety coverage.
Work Supervisor
HSE Officer
L
Job Safety Analysis on Lifting Works
Task / Activities Initial Risk
Initial Risk
Rating Control Measures Responsible
Residual
Risk
Rating
H M L H M L
Doc. No. REV. A Page 3 of 4
4. Transportation of
materials
Fatality or serious injury
-Collision with other vehicles & other
properties
H
• The driver or operator shall be trained or certified for
competence. Third Party Certificate or TUV license if
necessary.
• The flagmen shall be stationed when vehicles reversing
• Follow site traffic rule, not overload, shortcut or driving
over speed limit of 20km/h.
• Ensure to follow Defensive Driving Safety to all drivers and
operators.
• The equipment, tools or materials on vehicle shall be
properly fixed.
• Regularly inspect and maintenance.
• Ensure to follow Defensive Driving Safety to all drivers
and operators.
Work Supervisor
HSE Officer
M
5. Unpacking
-unloading and
arrangement of
materials.
-Hand or foot injury (slip, trip & fall
hazard)
-Ergonomics and manual handling.
L
• Properly wear correct PPE, including safety gloves and
steel-toed shoes.
• Handle with care and good position. Proper body
positioning while work execution.
• Proper coordination with fellow workers.
• Proper supervision and safety coverage.
Work Supervisor
HSE Officer
L
6. Lifting, incl. loading
and unloading
-Personal Injury or Equipment Failure
-Tumbling of the crane.
-Collision of crane to powerlines & other
properties.
-Falling of the crane load to workers &
other properties.
-Strong winds & abnormal weather
conditions.
-Working or passing of workers to
suspended load.
H
• Check all the equipment or rigging devices to ensure
good performance.
• Set the barriers around operating area and assign the
watchman to keep non-related persons away.
• The equipment operator and riggers shall be qualified
and certified for competence. (Should have 3rd
Party
Certification).
• Riggers should have designated reflective vest &
whistle.
• Operate as per the lift instruction and load chart.
• Load shall be controlled with taglines during hoisting.
• Only rigging devices (sling, chain block, etc.) of correct
capacity shall be used for hoisting.
• Ground must be even and compacted where the crane is
to be positioned.
• Ensure that the outriggers are fully extended prior to lift.
• Ensure to use proper outrigger pads and proper size.
Work Supervisor
HSE Officer
Rigger
Operator
M
Job Safety Analysis on Lifting Works
Task / Activities Initial Risk
Initial Risk
Rating Control Measures Responsible
Residual
Risk
Rating
H M L H M L
Doc. No. REV. A Page 4 of 4
Risk Assessment Matrix
Severity
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
Risk Rating
1 2 3 4 5
Likelihood
• Proper lifting signage must be in place.
• Ensure to have lifting plans in all critical lifts activities.
• No operation of crane if the wind speed exceeds 32kph
or refers to manufacturer’s specification.
• No working or passing to the suspended load.
• Ensure proper illumination when working at night works.
• Beacon lights should be turned on at all times during
operation.
Please Refer Below for Risk Assessment Rating:
Risk Assessment Table
Likelihood Severity
1. Highly improbable 1. Minor injury, no time off
2. Remotely possible but
known to occur 2. Injury resulting in up to 3 days off
3. Infrequent 3. Injury resulting in 3 or more days off
4. Occasional 4. Major disability injury
5. Frequent and Regular 5. Fatality
Likelihood X Severity = Risk Rating
Likelihood X
Severity Result
Equivalent
Rating
15 to 25 High Risk H
8 to 14 Medium Risk M
1 to 7 Low Risk L

More Related Content

What's hot

Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...Bimal Chandra Das
 
Presentation of Rigger
Presentation of RiggerPresentation of Rigger
Presentation of RiggerMajid Hussain
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranesAzmeel Contracting Company
 
Health And Safety Induction Training
Health And Safety Induction TrainingHealth And Safety Induction Training
Health And Safety Induction Trainingedale07
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at heightsankarnagar
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training PresentationFAIZ FAREED
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsAlan Bassett
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
LOTO Training
LOTO TrainingLOTO Training
LOTO TrainingCM Tiwari
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.paul doherty
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptssuser0ebdc3
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessmentSimba Zhao
 
Mobile crane legal requirements
Mobile crane  legal requirementsMobile crane  legal requirements
Mobile crane legal requirementsHamat, Mohd Kudzi
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting OperationsJames McCann
 

What's hot (20)

Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
Standard Operating Practices (SOPs) and Standard Maintenance Practices (SMPs)...
 
Presentation of Rigger
Presentation of RiggerPresentation of Rigger
Presentation of Rigger
 
Risk assessment for testing & commissioning of cranes
Risk assessment for  testing & commissioning of cranesRisk assessment for  testing & commissioning of cranes
Risk assessment for testing & commissioning of cranes
 
Health And Safety Induction Training
Health And Safety Induction TrainingHealth And Safety Induction Training
Health And Safety Induction Training
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at height
 
Crane Safety Training Presentation
Crane Safety Training PresentationCrane Safety Training Presentation
Crane Safety Training Presentation
 
Permit to Work Training
Permit to Work TrainingPermit to Work Training
Permit to Work Training
 
Work at height safety
Work at height safetyWork at height safety
Work at height safety
 
Hot Works Safety Training
Hot Works Safety TrainingHot Works Safety Training
Hot Works Safety Training
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operations
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
LOTO Training
LOTO TrainingLOTO Training
LOTO Training
 
Lifting Presentation.
Lifting Presentation.Lifting Presentation.
Lifting Presentation.
 
HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.ppt
 
Overhead crane risk assessment
Overhead crane risk assessmentOverhead crane risk assessment
Overhead crane risk assessment
 
Scaffolding checklist
Scaffolding checklistScaffolding checklist
Scaffolding checklist
 
Mobile crane legal requirements
Mobile crane  legal requirementsMobile crane  legal requirements
Mobile crane legal requirements
 
PPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie EPPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie E
 
December -15 Daily Observation Report
December -15 Daily Observation ReportDecember -15 Daily Observation Report
December -15 Daily Observation Report
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 

Similar to Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput

apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.pptapm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.pptLeandroGonzlezDeCecc
 
www.scanrent.com.au
www.scanrent.com.au www.scanrent.com.au
www.scanrent.com.au Ghazanfar Ali
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...AhmedAliKhan38
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekRoseGaming1
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sitesPrastowo Priyatmoko
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLift Events
 
TRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxTRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxPriyaRavirajan
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryRamana Reddy G
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Excavation & Back filling work 02.docx
Excavation & Back filling work 02.docxExcavation & Back filling work 02.docx
Excavation & Back filling work 02.docxnrphsebarauni
 
Hse new microsoft power point presentation
Hse new microsoft power point presentationHse new microsoft power point presentation
Hse new microsoft power point presentationSamip Nathani nathani
 

Similar to Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput (20)

SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1SDV-20253 VALVE MOD 9 lift plan 1
SDV-20253 VALVE MOD 9 lift plan 1
 
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
PA PIPE WORK 14 inch spool TH11177-06-PI-10-004-5
 
apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.pptapm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
apm-et13e-chapter-16-hoisting-and-conveying-equipment.ppt
 
www.scanrent.com.au
www.scanrent.com.au www.scanrent.com.au
www.scanrent.com.au
 
HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...HSE-BMS-011 Crane & Lifting Safety.ppt...
HSE-BMS-011 Crane & Lifting Safety.ppt...
 
Use of Helicopters in Emergency Operations
Use of Helicopters in Emergency OperationsUse of Helicopters in Emergency Operations
Use of Helicopters in Emergency Operations
 
UTA_AST-Rigging.pptx
UTA_AST-Rigging.pptxUTA_AST-Rigging.pptx
UTA_AST-Rigging.pptx
 
Rigger safety .pdf
Rigger safety                        .pdfRigger safety                        .pdf
Rigger safety .pdf
 
Rigging Course .pdf
Rigging Course                       .pdfRigging Course                       .pdf
Rigging Course .pdf
 
Safety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhekSafety engineering module 6 shskwn ejekdndhek
Safety engineering module 6 shskwn ejekdndhek
 
2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites2000 08 safe use of mobile cranes in construction sites
2000 08 safe use of mobile cranes in construction sites
 
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
PowerLogistics Asia 2014 - Lifting & Hoisting - Best Practices – P V N Chandr...
 
TRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docxTRA%20of%20Lifting.Tail.docx
TRA%20of%20Lifting.Tail.docx
 
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industryCrane & Lifting Safety.ppt Crane lifting safety useful for construction industry
Crane & Lifting Safety.ppt Crane lifting safety useful for construction industry
 
Crane safety
Crane safetyCrane safety
Crane safety
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
Excavation & Back filling work 02.docx
Excavation & Back filling work 02.docxExcavation & Back filling work 02.docx
Excavation & Back filling work 02.docx
 
safe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUESsafe lift EMERSON EDUARDO RODRIGUES
safe lift EMERSON EDUARDO RODRIGUES
 
Excavation & Trench Safety by NUCA
Excavation & Trench Safety by NUCAExcavation & Trench Safety by NUCA
Excavation & Trench Safety by NUCA
 
Hse new microsoft power point presentation
Hse new microsoft power point presentationHse new microsoft power point presentation
Hse new microsoft power point presentation
 

More from Gaurav Singh Rajput

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputGaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputGaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Gaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputGaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputGaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputGaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputGaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputGaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputGaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputGaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...Gaurav Singh Rajput
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputGaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputGaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Gaurav Singh Rajput
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputGaurav Singh Rajput
 

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 

Recently uploaded

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 

Recently uploaded (20)

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 

Job Safety Analysis For Lifting Activity By Crane | JSA | Gaurav Singh Rajput

  • 1. JOB SAFETY ANALYSIS Doc. No.: HSE/FRM-22 Rev.: 00 Date: Page: 1 of 3 Project: Project: Area: General Comments: Date: / / Supervisor: Job Description: Lifting & Rigging Activity (Loading/Unloading of the Equipment) Item Detail of Activity Equipment & Tools used Risk Involved Preventive Measure Responsible Person Severity Rating 1 TRANSPORTATION OF THE MATERIALS & CRANE TO JOB SITE. • CRANE • TRAILER • FLAT BED • MULTI AXEL TRAILER • LIFTING GEARS (SLINGS, SHACKLES, WEB-BELT, TAG LINE, CHAIN BLOCK, LEVER HOST, FORK LIFTER, PICK WAY TRUCK & ETC). • UNEVEN ROAD • UNSAFE CONDITIONS • CRANE SHOULD BE CHECKED, BEFORE TRANSPORTATION TO JOB SITE ON DAILY BASIS. RIGGING SUPERVISOR 2 2 2 MATERIAL LOADING / UNLOADING • CRANE COLLAPSE DURING • LIFTING • PERSONAL INJUREY • PROPERTY DAMAGE • PROPER ACCESS (BRIDGES) SHOULD BE USED. • FLAGMAN WILL BE ASSIGNED WITH THE CRANE & HEAVY EQUIPMENT. • MATERIAL MUST BE CHECKED BEFORE LOADING / UNLOADING. AREA AUTHORIZES 3 3 2 3 3 SETTING UP CRANE FOR LIFTING. • CRANE FAILURE DUE TO HYDROLIC SYSTEM • CAUSE OF SERIOUS • MATERIAL MUST BE PROPERLY SECURED WITH SLING & SHACKLES BEFORE LIFTING UP. • CRANE WILL BE SET UP AT LEVEL SURFACE WITH OUTRIGGER PADS. • OUTRIGGERS WILL BE FULLY EXTENDED CRANE. E & P I/C 2 4 LIFTING WITH CRANE • FIRE DUE TO LOOSE WIRING • CRANE MUST BE 3RD PARTY CERTIFIED. • ALL LIFTS WILL BE UNDER THE RATED CAPACITY OF CRANE I.E. LOAD CHART. HSE INSPECTOR 2 5 INSPECTION OF CRANE & RIGGING GEARS • FALL OF OBJECT • CERTIFIED CRANE OPERATOR AND RIGGERS (3RD PARTY CERTIFIED) WILL CARRY OUT THE LIFTING ACTIVITY. RIGGING ENGINEER 3 6 DEMOBILIZATION CRANES EQUIPMENT’S, TOOLS AND WORKER. • PERSONNEL INJURY • SLIPPING • TRIPPING • ALL LIFTING TACKLES WILL HAVE 3RD PARTY • CERTIFICATIONS & HEALTHY (GOOD CONDITION). • RIGGING PLAN & STUDY REQUIRED FOR HEAVY LIFTING. RIGGING SUPERVISOR 2
  • 2. • ELECTRIC SHOCK • DUE TO POWER LINE • ONLY SINGLE PERSON MUST BE GIVEN SIGNAL TO CRANE OPERATOR. • EMPLOYEES SHOULD BE TRAINED ON SAFE RIGGING TECHNIQUES. • TOOLBOX TALK MUST BE CONDUCTED BEFORE EACH LIFT. • LIFTING AREA SHOULD BE BARRICADED WITH WARNING. • ALL LOADS WILL BE CONTROLLED BY TAG LINES, IF LENGTH IS LONG THAN DOUBLE TAG LINE USED. • LIFTING CREW WILL WORK WITH COMPLETE PPES. • AREA MUST BE CHECKED & FREE FROM ELECTRICAL WIRES BEFORE ASSEMBLING TO THE CRANE. 7 WORK AT HEIGHT SCAFFOLDING CHARRY PICKLES • MATERIAL CAN FALL • PERSONAL FALL • IMPROPER SCAFFOLDING ERECTION • TOOL & JOINTS ETC. SHOULD BE LIFT BY ROPE & BASKET • SCAFFOLDING SHOULD BE ERECTED UNDER SKILLED SUPERVISION. • FULL BODY HARNESS MUST BE WORN WHILE WORK AT HEIGHT 6 FEET & ABOVE. • SCAFFOLDING MUST BE ERRECTED WITH STANDARD & INSPECTED BY SCAFFOLDING INSPECTOR. RIGGING SUPERVISOR SCAFFOLDING INSPECTOR 2 3 3 8 WORK AT NIGHT LIGHTS & STANDS (FLOOD LIGHTS WHITE) • MANUAL HANDLING • SLIP, TRIP & FALL • POOR ILLUMINATION • WORK WOULD BE NEVER ALLOWED IN LESS OR IMPROPERLY DISPRESSED ILLUMINATION/LIGHTS. • ALL WORK AT NIGHT ARRANGEMENT MUST BE DONE BEFORE START OF WORK AT NIGHT. RIGGING SUPERVISOR 2 2 2 9 HOUSEKEEPING WASTE DRUMS SHOPPER BAGS • ENVIRONMENT HAZARD • SLIP, TRIP & FALL • WASTE MATERIAL SHOULD BE STACKED PROPERLY & DUMPED IN DESIGNATED PLACES. • WASTE MATERIAL SHOULD BE BARRICADED. RIGGING SUPERVISOR 1 2 Severity Rating: (1) First Aid / Minor Property Damage (2) Recordable Accident / Property Damage (3) Lost Time Accident / Major Property Loss (4) Catastrophic Accident
  • 3. Are you aware of, and do you have the correct PPE? What are the risks? How do controlled risks? _______________________________ __________________________ AREA ENGINEER / SUPERVISOR HSE REPRESENTATIVE
  • 4. JSA FOR crane operation Name of the Site : Date of Preparation : JSA Preparation : S.NO SCOPE OF ACTIVITY HAZARD CONTROL MEASURES REQUEST BY 1) Mobile Crane to onsite destination 1) Faults with Crane 2) Plant becoming bogged in sand & mud 3) Pedestrians 4) Onsite Traffic/plant 1) Pre-start Checks 2) Plant to stick to designated roadways and turning areas 3) Personnel on hand to warn others of crane movement in the vicinity or via radio where available. 4) Alternate pathway defined by bollards and reflective tape. EHS SAFETY OFFICER/SECURITY OFFICER 2) Pre-job meeting and Toolbox 1) Inexperienced workers 2) Inadequate consultation 3) Inadequate understanding of equipment 4) Site hazards and emergency Procedures not known 1) Sufficiently skilled employees to complete task (competencies and Licences) 2) Adequate consultation with all relevant employees 3) Adequate competent supervision throughout the project 4) Proper planning for equipment required for the task 5) Site & work area inductions compulsory for all personnel EHS SAFETY OFFICER/SECURITY OFFICER 3) Locate crane into lifting positions on site 1) Pedestrians 2) Traffic 3) Other Plant 4) Other Equipment 5) Buildings Power lines & underground Utilities 6) Lift radius Access 7) Ground Conditions 1) Desired setup area should also be level, 2) unless prior consultation has been made with the supplier of the crane 3) The workplace is adequately prepared for the incoming mobile crane, including where possible a clear predefined area/crane pad for the crane to position upon 4) Check and confirm exclusion areas - Barricades, witches Hats, Danger Tape, Warning Signs 5) Access road are available and soundly constructed with suitable entry points to site 6) Crew should always inspect site prior to positioning crane in final position 7) Elements to observe include 8) Load location and scope of lift 9) Location of any overhead obstructions including wires, trees, buildings, restricted airspace (i.e. near airport) 10) Location of any underground services and/or trenches including utilities and drainage arrangements that may affect integrity of ground 11) Adequate room for rigging and erection of mobile crane 12) Adequate tail (counterweight/winch) swing clearance 13) Ability to cordon off area with suitable barricading resources EHS SAFETY OFFICER/SECURITY OFFICER
  • 5. JSA FOR crane operation Name of the Site : Date of Preparation : JSA Preparation : 4) Inspect chains and or slings, shackles, hooks and attachment points in preparation for use 1) Tears in Slings 2) Cracks in chains, shackles, rings and hooks 3) Dropping of load due to faulty 4) lifting gear or faulty attachment points 1) Check slings for rips and tears and remove from service is faults are found 2) Check chains, shackles, hooks and rings for cracks, corrosion, wears, mechanism faults etc and remove from service if faults are found 3) Lifting gear/equipment inspected and tagged with appropriate monthly colour tag 4) Make certain personnel are sufficiently trained with appropriate certificates/ licences 5) Locate crane in lifting position on site – place timbers (pads) and set outriggers 1) Crane overturning due to unstable ground condition 2) Personnel being crushed by outriggers 1) Outriggers must be positioned on a flat surface, 2) Using timbers or suitable material for pads to evenly distribute the load to the ground 3) Crane to be located within the radius for the loads being Lifted. 4) Outriggers should only be extended on the side where the Operator is positioned or with a suitable spotter. 5) Where space permits, outriggers shall always be fully extended 6) Where space is limited, crane should be configured to maximum capacity – this may require the use of reduced outriggers or on rubber; when permitted by the manufacturer 7) Outriggers shall always be extended to manufacturers procedures and specifications, including the requirement to fit manual pins 8) All outriggers-jacks should be utilized at all time 9) Generally Standard Safe Working Load capacity charts are based on all outriggers fully extended and set with wheels clear of ground. 10) Outrigger Packing – 11) Additional packing should always be utilized under outrigger floats 12) Commonly used Outrigger Mats should carry design information and be subject to periodic inspection
  • 6. JSA FOR crane operation Name of the Site : Date of Preparation : JSA Preparation : 13) When timber packing is utilized, it should be in a ‘pigsty ‘packing 14) Arrangement ‘Rule of Thumb’ formulae and calculations should be observed; 15) Area (m2) = 0.65 x (Cm + L) ------------- V Cm = Total mass of crane (KN) L = Total mass of load (KN) V = maximum permissible bearing pressure of soil (kpa 6) Attaching Fly or Pin Jib to Crane Working at heights/falling 1) Follow W/H permit use appropriate attachment point & safety harness when walking along crane boom 2) Use an EWP or ladder for this task & follow safe work practices
  • 7. JSA FOR crane operation Name of the Site : Date of Preparation : JSA Preparation : 7) Position counterweight truck in an easily accessible spot for the crane to load its counterweights Position counterweight truck in an easily accessible spot for the crane to load its counterweights 1) Plant to be positioned in area clear of obstruction. Roads 2) Traffic control in place if required 3) Once crane is elevated and level, a trial operation should be completed by the operator; this may include 4) Bluffing boom to high angle, and slewing 360 degrees with spotter in position – purpose to review tail swing and outrigger packing suitability 5) Executing ‘dry-run’ where load is required to be picked up and placed – Purpose to ensure crane is capable of task and set required limits 8) Re-assessing Situation throughout job Changes in weather conditions Changes in operators Changes in ground suitability 1) Continual safe operation can be aided by periodic inspection throughout the project of the following; 2) Outrigger Jacks – Leaking oil/retraction of shaft 3) Outrigger Mats – excessive settlement and/or sinking into ground; i.e., loadings increasing beyond estimated capacity of ground – such as unknown back-filling 4) Outrigger Floats – Cracking or critical damage 5) Evidence of water content in ground 6) Should requirements change during operation, then crew shall re-assess and review crane capacity and wider environment to ensure revised work practice is within limits and safe to continue operation
  • 8. JSA FOR crane operation Name of the Site : Date of Preparation : JSA Preparation : 9) 10.Packing up and/or leaving crane onsite Unauthorised person access crane site Damage to crane Injury to public 1) Upon completion of project, or specific stage the crane 2) equipment and site shall be left in a secure and safe manner 3) If the crane is to be left onsite; 4) Retract Boom, remove keys from the ignition and secure/lock 5) Outriggers should be inspected prior to next use 6) Barricading should remain in place around the crane and any work area deemed necessary 10) Packing up and cleaning up work site Trip hazards Manual handling injuries Crush & Pinch injuries Equipment damage Counterweights coming off the back of the truck Crush & pinch injuries Falls 1) Use correct manual handling techniques 2) Wear appropriate PPE 3) Rubbish to be placed in bins 4) Tools & Equipment to be packed 5) Lifting gear packed 6) Timbers packed 7) Pads loaded 8) Make certain counterweights are stacked on rubber mats and correctly tied down for trip 9) Guide counterweights onto the truck tray with taglines 10) Where possible use EWP or Platform Ladder Access otherwise be cautious of footing
  • 9. JSA FOR crane operation Name of the Site : Date of Preparation : JSA Preparation : 11) Exit site and return to Depot Overhead Powerlines Collision with people/personnel and other vehicles/plant when exiting site Counterweights sliding off during travel Traffic Accident 1) Crane boom to be down when travelling under power lines 2) Maintain site speed limit when exiting work site 3) Communicate with other vehicles onsite is necessary 4) Observe road rules and take into consideration drivers and riders who don’t understand the nature of cranes and trucks.
  • 10. CHANGING CONDITIONS & EMERGENCY PROCEDURE: Stop Work, Switch off equipment, Supervisor Direct Personnel to Nearest and Safety Muster Point considering wind direction. Supervisor accounts for all workers. In case of emergency contact 911 / 02-425-0911 Job Safety Analysis PROJECT TITTLE Company: Risk Assessment No: NEW REVISED √ PAGE NO. 1 of 6 Type of Job Being Analyzed Risk Assessment on Lifting Works Department/Section Originate JSA Risk Assessment Team JOB Performers Additional approvals (Determine by Job Supervisor in Correlation with HSE Manager) GENERAL JOB REQUIREMENTS: TBM & PPE Company Representative Name Signature Date 1. Pre task tool box meeting everyday. 2. Personal Protective Equipment 2.1 Safety Shoes with steel toe. 2.2 Safety glasses 2.3 Hard hat 2.4 Hand gloves 2.5 Cover all to workers 2.6 Full body harness on working at heights 2.7 Chin strap for helmets 2.8 Appropriate mask or respirators GS C
  • 11. Job Safety Analysis on Lifting Works Task / Activities Initial Risk Initial Risk Rating Control Measures Responsible Residual Risk Rating H M L H M L Doc. No. REV. A Page 2 of 4 1. Work permit Prior to commencing all works, a work permit is required. · Check safety condition of whole area for electrical exposure -Slip, trip, fall during site inspection. -Moving machineries. L • Safe Work Permit and other pertinent documents shall be secured before any works commence. • Pre-start meeting shall be discussed during daily toolbox meeting before work commence. • Equipment and tool inspection must be carried out. • Concerned supervisor / foreman to prepare required safe work plan / permit one day in advance. • Joint Visit of Permit Issuer, Permit Receiver, Supervisor and HSE Officer should be conducted before issuing the Work Permit. • Supervisor / foreman and safety officer to supervise and monitor the activity respectively Supervisor Permit Issuer Permit Receiver HSE Officer L 2. Manpower mobilization -Lack of hazard recognition and awareness of the new workers. - Incompetent and inexperience workers -Lack of training L • Hire competent workers. • Safety induction and training. • Toolbox meeting before work • All workers shall be issued with basic PPE and must wear them on site at all time • Proper supervision and safety coverage • Initial gas testing should be conducted Work Supervisor HSE Officer L 3. Equipment mobilization & Usage of tools & equipment. -Injury of workers (cutting, pinch points, caught in between, struck by flying objects, etc.) - Ergonomics and manual handling. - Moving machineries. L • Inspect before use for qualification. • Defective equip or tool shall not be used. • Regularly check and maintenance. • Implementation of color coding system, • Ensure competent workers with necessary training • Proper usage of PPE. • Following proper procedure on tools & equipment usage. • Proper supervision and safety coverage. Work Supervisor HSE Officer L
  • 12. Job Safety Analysis on Lifting Works Task / Activities Initial Risk Initial Risk Rating Control Measures Responsible Residual Risk Rating H M L H M L Doc. No. REV. A Page 3 of 4 4. Transportation of materials Fatality or serious injury -Collision with other vehicles & other properties H • The driver or operator shall be trained or certified for competence. Third Party Certificate or TUV license if necessary. • The flagmen shall be stationed when vehicles reversing • Follow site traffic rule, not overload, shortcut or driving over speed limit of 20km/h. • Ensure to follow Defensive Driving Safety to all drivers and operators. • The equipment, tools or materials on vehicle shall be properly fixed. • Regularly inspect and maintenance. • Ensure to follow Defensive Driving Safety to all drivers and operators. Work Supervisor HSE Officer M 5. Unpacking -unloading and arrangement of materials. -Hand or foot injury (slip, trip & fall hazard) -Ergonomics and manual handling. L • Properly wear correct PPE, including safety gloves and steel-toed shoes. • Handle with care and good position. Proper body positioning while work execution. • Proper coordination with fellow workers. • Proper supervision and safety coverage. Work Supervisor HSE Officer L 6. Lifting, incl. loading and unloading -Personal Injury or Equipment Failure -Tumbling of the crane. -Collision of crane to powerlines & other properties. -Falling of the crane load to workers & other properties. -Strong winds & abnormal weather conditions. -Working or passing of workers to suspended load. H • Check all the equipment or rigging devices to ensure good performance. • Set the barriers around operating area and assign the watchman to keep non-related persons away. • The equipment operator and riggers shall be qualified and certified for competence. (Should have 3rd Party Certification). • Riggers should have designated reflective vest & whistle. • Operate as per the lift instruction and load chart. • Load shall be controlled with taglines during hoisting. • Only rigging devices (sling, chain block, etc.) of correct capacity shall be used for hoisting. • Ground must be even and compacted where the crane is to be positioned. • Ensure that the outriggers are fully extended prior to lift. • Ensure to use proper outrigger pads and proper size. Work Supervisor HSE Officer Rigger Operator M
  • 13. Job Safety Analysis on Lifting Works Task / Activities Initial Risk Initial Risk Rating Control Measures Responsible Residual Risk Rating H M L H M L Doc. No. REV. A Page 4 of 4 Risk Assessment Matrix Severity 5 5 10 15 20 25 4 4 8 12 16 20 3 3 6 9 12 15 2 2 4 6 8 10 1 1 2 3 4 5 Risk Rating 1 2 3 4 5 Likelihood • Proper lifting signage must be in place. • Ensure to have lifting plans in all critical lifts activities. • No operation of crane if the wind speed exceeds 32kph or refers to manufacturer’s specification. • No working or passing to the suspended load. • Ensure proper illumination when working at night works. • Beacon lights should be turned on at all times during operation. Please Refer Below for Risk Assessment Rating: Risk Assessment Table Likelihood Severity 1. Highly improbable 1. Minor injury, no time off 2. Remotely possible but known to occur 2. Injury resulting in up to 3 days off 3. Infrequent 3. Injury resulting in 3 or more days off 4. Occasional 4. Major disability injury 5. Frequent and Regular 5. Fatality Likelihood X Severity = Risk Rating Likelihood X Severity Result Equivalent Rating 15 to 25 High Risk H 8 to 14 Medium Risk M 1 to 7 Low Risk L