Risk Assessment & Job
Safety Analysis
2
Majority of accident that happens in the construction site
is due to the fact that more personnel involved in the
construction activities lack the basic knowledge of the
various job step, the hazards and the control measures
for each hazard
The Work Method of Statement, Risk Assessment & Job
Safety Analysis (JSA) will cover this gap by giving the
people the necessary training, information etc… about
each job (task) and how to carry it out without accidents
Introduction
3
JSA
⚫ JSA shall be conducted during;
➢ Critical task
➢ Non-routine Task
➢ Permit To Work Task
➢ Routine Task (Daily/pre-task)
⚫ Every work activities shall have a corresponding Work
Method of Statement prepared by the task Supervisor or
task Manager.
⚫ Risk Assessment shall be done with respect to the
corresponding hazard that will be analyzed and mitigating
measures during job hazard analysis.
⚫ JSA will be conducted to break down each job steps into
safe more detailed procedures.
4
Risk Assessment is an extremely useful tool in
providing a framework in which to identify the potential
hazards & evaluate the risks associated with all our
activities.
Risk Assessment now forms a routine element in
education & training within the Project.
Risk Assessment
5
To prevent workplace injury, disease & property
damage, it is necessary to identify the cause of
accidents
• This can de done:
➢ Reactively by accident investigation, or
➢ Proactively by carrying out risk assessments
• Risk assessment enables the identification of those
events or activities, which could cause harm &
evaluation of the associated risks.
Risk Assessment
6
IDENTIFY POTENTIAL LOSS
• Risk Assessments involve addressing the following
questions:
➢ What could go wrong?
➢ How likely are such events?
➢ What would happen if such events occurred?
➢ What are the associated risks?
➢ Are the risks acceptable?
➢ How can the risks be reduced...or removed?
Risk Assessment
7
• There is confusion in the interpretations of familiar words
such as accident, hazard, risk & danger and so on;
• Different sources of information put similar but different
interpretations on these expressions or terms
• So for the purpose of discussing risk assessment the
following conditions apply on the Project:
1. RISK ASSESSMENT
This is the process of identifying hazards and assessing
the risk of harm and loss threatened by the hazard.
Definition
8
2. RISK MANAGEMENT
Risk Management in its broadest sense represents the
successful control of all threats of harm and loss to an
organisation, group of people or an individual
3. QUANTITATIVE RISK ASSESSMENT
This type of assessment produces numerical values of
the risk involved and evaluates the results against
specified risk criteria.
4. DANGER
Danger is a state or situation, which is a product of a
hazard and it’s associated risk.
Definition
9
5. ACCIDENT
An accident is commonly defined as an unplanned
event, which result in Injury or Damage.
6. INCIDENT
An incident is an event, which represents deviation from
the intended sequence of designed steps. Commonly
defined as an unplanned event, which does not result in
Injury or Damage A “Near Miss” is by definition an
Incident.
7. RISK
A risk is the likelihood that harm may result being a
function of both frequency and severity. The risk can
range from the trivial (a paper cut) to catastrophic
accident
Definition
10
8. SAFE OR SAFETY
Often thought of as representing the level of security and
freedom from harm.There is no such thing as complete
safety, an appropriate definition might be “the maximum
level of risk a person or organisation is prepared to accept”
9. HAZARD
A hazard is something with the potential to cause harm.
This can be substances or machines, methods of work and
other aspects of work organisations
10. Harm
Harm represents physical injury, death, ill health, property
and equipment damage and any from of associated loss
Definition
11
• Risk assessments for all field
(site activities)
• Hazard Operability Studies
(HAZOPS)
• Hazard Identification Studies
(HAZIDS)
• Job Safety Analysis (JSA)
• Tool Box Talks
Risk management Tools
Communication
and
Documentation
12
GENERIC RISK ASSESSMENT
A generic or group assessment is a general
assessment of the risk posed by a combination of
discrete or separate risks of varying type & severity.
The risk assessment process can be managed more
efficiently by producing generic risk assessments that
are applicable to as many people or places as possible
SPECIFIC RISK ASSESSMENT
Some specific hazards where a generic risk
assessment has not been carried out, or where it is not
considered suitable or sufficient, then a specific risk
assesment should be made.
Risk Assessment Process
13
Safe Place
Strategies
1. Eliminate the Hazard – the very
best thing to do if possible
2. Reduce the Hazard
3. Isolate Hazard from people
4. Control the extent of
exposure/contact with the hazard
5. Personal Protective Equipment
(PPE) almost the last resort
6. Discipline
Hierarchy of Control
Safe Person
Strategies
14
STAGES
1. Identify & analyse all tasks
2. Identify hazards that are, or may be involved
3. Identify those who may be exposed to the hazards
4. Analyse the risks of injury or loss from hazards
5. Evaluate if the risk is adequately controlled (consider
existing control measures)
6. Monitor & review
Risk Management Process
15
METHODS OF HAZARD IDENTIFICATION
• Accident Investigations
• Safety Survey or Safety Tours
• Communication (Tool Box Talks etc)
• Job Safety Analysis (JSA)
• Special Risk Assessment techniques such as:
➢ Hazard Operability Studies (HAZOPs)
➢ Quantified Risk Assessment (QRA)
➢ Hazard Operability Studies (HAZIDs)
Stage Two – Identify Hazards
16
• Workforce directly involved in activity
• Other employees personnel
• Visitors
• Members of the public
Stage Three – Identify People at Risk
17
The purpose of the Risk Analysis stage is to obtain an
idea of the size or the scale of the risk.
Put simply,
A Risk Assessment is finding out what could cause harm
to people (Environment, Task or Equipment)
and deciding if we have done enough, or need to do
more to protect them,
or better still to ensure we meet the Project H&S Policy
that all risks are As Low As Reasonably Practicable
(ALARP)
Stage Four – Risk Assessment
18
QUALITATIVE TECHNIQUES
Where risk is expressed in terms of High, Medium or Low
QUANTITATIVE TECHNIQUES
Attempt to express risk in numerical terms & will be based on
calculation using data of failure rates of equipment, human
error, etc
RISK EVALUATION
Risk evaluation is determined by the Likelihood of the incident
event occurring multiplied by the Severity of the incident
LIKELIHOOD X SEVERITY = RISK
Stage Four – Risk Assessment
19
Risk Assessment Matrix
20
LIKELIHOOD POTENTIAL is determined as follows:
E - Happens several time per year in this project – could happen at
any time
D - Happens several time per year in our Corporate – could happen
sometimes
C - Incident has occurred in our Corporate – could happen, but very
rarely
B - Heard of in construction industry – could happen, but probably
never will
A - Never heard in construction industry – theoretical
Risk Evaluation - Likelihood
21
Risk Evaluation - Severity
Harm to People
0 No injury or damage to health.
1 Slight injury or health effects (including First Aid case
and Medical Treatment case and Occupational illness)
- Not affecting work performance or causing disability.
2 Minor injury or health effects (Lost Time Injury )
-Affecting work performance, such as restriction to
activities (Restricted work Case or Occupational
Illness) or a need to take a few days to fully recover
(Lost Workday Case). Minor health effects, which are
reversible, e.g. skin irritation, food poisoning.
22
Risk Evaluation - Severity
Harm to People
3 Major injury or health effects (including Permanent Partial
Disability and Occupational Illness)
-Affecting work performance in the longer term, such as a
prolonged absence from work.
Irreversible health damage without loss of life, e.g. noise
induced hearing loss, chronic back injuries, sensitization,
hand/arm vibration syndrome, repetitive strain injury.
4 Permanent Total Disability or one to three fatalities
- from an accident or occupational illness.
Irreversible health damage with serious disability or death,
e.g. corrosive burns, heat stroke, cancer (small exposed
population)
5 Multiple fatalities
- from an accident or occupational illness (e.g. chemical
asphyxiation or cancer (large exposed population)
23
Risk Evaluation - Severity
Asset Damage and other Consequential
Business Losses (USD)
0 Zero damage
1 Slight damage - No disruption to operation (costs less
than 10,000)
2 Minor damage- Brief disruption (cost less than 100,000)
3 Local damage- Partial shutdown (can be restarted but
costs up to 1,000,000)
4 Major damage- Partial operation loss (2 weeks shutdown
costs up to 10,000,000)
5 Extensive damage- Substantial or total loss of operation
(costs in excess of 10,000,000)
24
Risk Evaluation - Severity
Environmental Effect
0 Zero effect - No environmental damage. No financial
consequences.
1 Slight effect - Slight environmental damage, within the fence
and within systems. Negligible financial consequences.
2 Minor effect - Sufficiently large contamination or discharge to
damage to attack the environment, but no lasting effect.
Single breach of statutory or prescribed limit, or single
complaint.
3 Localized effect - Limited discharges affecting the
neighborhood and damaging the environment. Repeated
breaches of statutory or prescribed limit, or many complains.
25
Risk Evaluation - Severity
Environmental Effect
4 Major effect - Severe environmental damage. The
company is required to take extensive measures to
restore the damaged environment. Extended
breaches of statutory or prescribed limits, or
widespread nuisance.
5 Massive effect - Persistent severe environmental
damage or severe nuisance extending over a large
area. Loss of commercial, or recreational use or
nature conservancy resulting in major financial
consequences for the Company. Ongoing breaches
well above statutory or prescribed limits.
26
Risk Evaluation - Severity
Impact on reputation
0 Zero effect - No public awareness.
1 Slight impact - Public awareness may exist, but
there is no public concern.
2 Limited impact - some local public concern. Some
local media and/or local political attention with
potentially adverse aspects for company operations.
3 Considerable impact - Regional public concern.
Extensive adverse attention in local media.
Slight national media and/or local/regional political
attention. Adverse stance of local government and/or
action groups.
27
Risk Evaluation - Severity
Impact on Reputation
4 National impact - National public concern. Extensive
adverse attention in the national media.
Effect on Regional/national policies with potentially
restrictive measures and/or impact on grant of
licenses. Mobilization of action groups.
5 International impact - International public attention.
Extensive adverse attention in international media.
National/international policies with potentially severe
impact on access to new areas, grants of licenses
and/or tax legislation.
28
Risk Assessment - Sample
All
B2
B
2
Foreman
Check scaffolds after adverse weather
condition
C2
C
2
Adverse
weather
Scaffolders /
All
B1
B
1
Foreman
Barricade area during erection &
Dismantling
E3
E
3
Falls of
Materials
Scaffolders
B2
B
2
Foreman
Check ground condition. Use base plate
& sole plate. Use proper materials
B4
B
4
Collapse of
Scaffold
Scaffolders
B3
B
3
Foreman/
Scaffolders
Scaffolders working above 1.8m mustbe
100% tie off. Hand rails to be fitted
D3
D
3
Fall from
Height
Scaffolders
B1
B
1
Foreman
Sufficient personnel, “No Bombing”
C1
C
1
Manual
Handling
Scaffolder /
Foreman
B1
B
1
Foreman
Only trained and competentpersonnel to
utilized for the task. All scaffolds to be
certified prior to use
C3
C
3
Competence
Level
Scaffold
Erection /
Dismantling
R
L
F
S
F
R
L
F
S
F
Person
affected
(to be
informed)
Risk
After
Control
By
whom
Precautions
Risk
Before
Control
Hazards
Activities
29
What Is Job Safety Analysis
⚫ It is the breaking down of a particular task into steps
to be taken in a sequence
⚫ Exposing the hazards involved in each of the steps
⚫ Putting in place control measures for each of the
hazards
⚫ Considering the PPE requirement for each step
30
Purpose of JSA
⚫ To improve understanding and safety
⚫ To ensure that there is a written, and approve Work
Method of Statement for every job on site
⚫ For proper control of safety on the job
31
Benefits of JSA
⚫ Supervisors learn more about the jobs their
subordinates perform and how better to manage
them.
⚫ When regularly performed, developed safe work
practices reduced employee injuries.
32
Five Basic Steps
⚫ Select job to be analyzed
⚫ Break job down into it’s smallest steps
⚫ Identify hazard associated with each steps
⚫ Develop control measures to eliminate hazards
⚫ Monitoring and periodic reviews
33
Job Safety Analysis Training
⚫ All new employee should be aware of the various
step involved in their operations.
⚫ Let employees learn how to perform a job efficiently
and safely.
⚫ Supervisors shall clearly explains to his subordinates
all the proper steps in doing the task safe
34
TBM before start ofthe job, 100% tie off, using harness with 2 lanyards,
Secure all materials for all work at height when there is a rain or wet surface,
Experience scaffolders shall be utilized to erectand dismantle suspended
scaffold. Other fall protection equipmentshall be utilized e.g. Retractable lanyard,
Lifeline.
Fall ofpersonnel from
height,
falling of material,
Slippery surface,
Inexperience scaffolder
Erection of
suspended
scaffold
TBM regarding responsibility during dismantling,
Only experience,trained and authorized person can dismantle scaffold
Material shall be lowered using rope and bucketor by passing manually
Area must be barricaded to keep away all unauthorized persons from the area
Falling of scaffold material,
collapsing ofscaffold.
Fall ofpersonnel,
Damage to scaffold
material
Dismantling of
Scaffold
TBM before work regarding handling ofmaterials
Use of gin wheel to hoist material or mechanical equipment
Barricading of lifting area
Injury to personnel,
material from height
Lifting of Scaffold
TBM before work, Inspection ofmaterials before work
Compacted ground before erection, Work area to be barricaded
Material used for work on height should be tie offto preventfrom falling
Purpose oferecting scaffold should be known, Kind ofwork to be done on
scaffold erection, Complete PPE mustbe worn e.g. hand gloves, safety glass,
safety shoes, hardhat, Body harness
Bad foundation,
Drainage, material falling,
unknown purpose for
erection of scaffold
Scaffold Erection
Preventive Measure
Hazard
Activity
Job Safety Analysis (JSA)
35
• Keep it simple
• Developed (at least in part) by the personnel
performing work
• We believe that JSA should be a thoughtful process
... Not simply a form to complete.
• JSA must be reviewed with all personnel coming on
shift
• OK to use previously developed JSA, but must be
upgraded based on current scope and conditions,
and actively reviewed by the crew
• For jobs that are repetitive, review and upgrade
JSA before starting the work.
Job Safety Analysis Guidelines
36
• When work is already completed, update the JSA to
identify lesson learned and unexpected results
• Update the JSA if an accident or near-miss occurs
• Ask for feedback each day consider new ideas and
include in the JSA form
• Include job setup and demobilization in the JSA
• A JSA should;
➢ Identify the location of the work to be performed
➢ Address how the job may affect others
➢ Address emergency situation
➢ Identify communication requirements
Job Safety Analysis Guidelines
37
• When work is complete, why not update the Pre-task
Safety Plan to identify learnings and unexpected results
Update the Pre-task Safety Plan if an accident or Near
Miss occurs
• Ask for feedback each day – consider adding a place
for it on the form
• Include job setup and demobilization in the Pre-task
Safety Plan
Job Safety Analysis Guidelines
38
How is it done at your site?
• Is it similar?
• Is it truly different?
• Is it effective? (How do you verify?)
• What are your success stories?
• What are your challenges?
39
• Few accidents occur during extremely hazardous
operations because we are fully aware of the risk
• Most accidents occur during routine, repetitious jobs
because we become complacent
• Therefore, all supervisors are expected to insure
effective Risk Assessment and JSA are conducted
and all their crews will follow all the provisions in the
form. Supervisor should make sure that pre-task
meeting is conducted before beginning each work.
Summary

More Related Content

What's hot

How to Increase Near Miss Reporting
How to Increase Near Miss ReportingHow to Increase Near Miss Reporting
How to Increase Near Miss ReportingSteve Wise
 
OHS Risk Assessment and Hierarchy of Control
OHS Risk Assessment and Hierarchy of ControlOHS Risk Assessment and Hierarchy of Control
OHS Risk Assessment and Hierarchy of ControlPECB
 
Behaviour based safety
Behaviour based safetyBehaviour based safety
Behaviour based safetyPrudhvi raj
 
Behavior based safety
Behavior based safetyBehavior based safety
Behavior based safetyAdnan Masood
 
Behavior-Based Safety PPT Slide Template
Behavior-Based Safety PPT Slide TemplateBehavior-Based Safety PPT Slide Template
Behavior-Based Safety PPT Slide TemplatePresentationLoad
 
unsafe acts & unsafe conditions.ppt
unsafe acts & unsafe conditions.pptunsafe acts & unsafe conditions.ppt
unsafe acts & unsafe conditions.pptVipinChhabra5
 
BBS Overview
BBS OverviewBBS Overview
BBS Overviewtpuyleart
 
Health And Safety Induction Training
Health And Safety Induction TrainingHealth And Safety Induction Training
Health And Safety Induction Trainingedale07
 
Safety induction presentation
Safety induction presentationSafety induction presentation
Safety induction presentationLucy Reimer
 
General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1debandleigh
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at heightsankarnagar
 

What's hot (20)

How to Increase Near Miss Reporting
How to Increase Near Miss ReportingHow to Increase Near Miss Reporting
How to Increase Near Miss Reporting
 
OHS Risk Assessment and Hierarchy of Control
OHS Risk Assessment and Hierarchy of ControlOHS Risk Assessment and Hierarchy of Control
OHS Risk Assessment and Hierarchy of Control
 
Behavior Based Safety
Behavior Based Safety Behavior Based Safety
Behavior Based Safety
 
Hazard identification
Hazard identificationHazard identification
Hazard identification
 
HIRA training
HIRA   trainingHIRA   training
HIRA training
 
Behaviour based safety
Behaviour based safetyBehaviour based safety
Behaviour based safety
 
Behavior based safety
Behavior based safetyBehavior based safety
Behavior based safety
 
Accident Causation
Accident CausationAccident Causation
Accident Causation
 
Behavior-Based Safety PPT Slide Template
Behavior-Based Safety PPT Slide TemplateBehavior-Based Safety PPT Slide Template
Behavior-Based Safety PPT Slide Template
 
Unsafe Act and Unsafe condition
Unsafe Act and Unsafe conditionUnsafe Act and Unsafe condition
Unsafe Act and Unsafe condition
 
Emergency response planning
Emergency response planningEmergency response planning
Emergency response planning
 
unsafe acts & unsafe conditions.ppt
unsafe acts & unsafe conditions.pptunsafe acts & unsafe conditions.ppt
unsafe acts & unsafe conditions.ppt
 
safety training
safety training   safety training
safety training
 
BBS Overview
BBS OverviewBBS Overview
BBS Overview
 
Work at height safety
Work at height safetyWork at height safety
Work at height safety
 
Health And Safety Induction Training
Health And Safety Induction TrainingHealth And Safety Induction Training
Health And Safety Induction Training
 
Health and safety culture
Health and safety cultureHealth and safety culture
Health and safety culture
 
Safety induction presentation
Safety induction presentationSafety induction presentation
Safety induction presentation
 
General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1
 
Presentation working at height
Presentation working at heightPresentation working at height
Presentation working at height
 

Similar to Risk Assessment and Job Safety Analysis

HSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.pptHSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.pptGkMechanical
 
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...Muizz Anibire
 
12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptx
12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptx12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptx
12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptxsafetygoodwe
 
Performing Risk Assessments1
Performing Risk Assessments1Performing Risk Assessments1
Performing Risk Assessments1Mary Harris
 
Risk Assessment.pptx
Risk Assessment.pptxRisk Assessment.pptx
Risk Assessment.pptxDivyesh Jha
 
Safety training: Risk Assessment & Job Safety Analysis
Safety training: Risk Assessment & Job Safety AnalysisSafety training: Risk Assessment & Job Safety Analysis
Safety training: Risk Assessment & Job Safety AnalysisC.P Prasanth
 
Various steps of risk assessment. md. anwar ibrahim miraz
Various steps of risk assessment. md. anwar ibrahim mirazVarious steps of risk assessment. md. anwar ibrahim miraz
Various steps of risk assessment. md. anwar ibrahim mirazMDAnwarIbrahimMiraz
 
Ppt for IMPROVEMENT OF SAFETY THROUGH SAFETY MANAGAMENT PLAN – office p...
Ppt for IMPROVEMENT OF SAFETY   THROUGH    SAFETY MANAGAMENT PLAN –  office p...Ppt for IMPROVEMENT OF SAFETY   THROUGH    SAFETY MANAGAMENT PLAN –  office p...
Ppt for IMPROVEMENT OF SAFETY THROUGH SAFETY MANAGAMENT PLAN – office p...AMIT SAHU
 
SAFETY MANAGAMENT PLAN –
SAFETY MANAGAMENT PLAN –SAFETY MANAGAMENT PLAN –
SAFETY MANAGAMENT PLAN –AMIT SAHU
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptAsifHussain654789
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptShahbazAhmad736457
 
Unit IV GE8076 Professional Ethics in Engineering
Unit IV GE8076 Professional Ethics in Engineering Unit IV GE8076 Professional Ethics in Engineering
Unit IV GE8076 Professional Ethics in Engineering Dr. SELVAGANESAN S
 
Risk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix PresentationRisk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix PresentationUsama Saeed
 
Risk Management (1) (1).ppt
Risk Management (1) (1).pptRisk Management (1) (1).ppt
Risk Management (1) (1).pptAjjuSingh2
 
HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)PrasantakumarNayak4
 
Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment Salim Solanki
 
Risk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in MyanmarRisk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in Myanmarijtsrd
 
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB
 

Similar to Risk Assessment and Job Safety Analysis (20)

HSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.pptHSE-BMS-006 Risk Assessment & JSA.ppt
HSE-BMS-006 Risk Assessment & JSA.ppt
 
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
Construction Safety Training_Session 10_Risk Assessment, Hierarchy of Control...
 
12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptx
12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptx12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptx
12._SGW-_Risk_Assessment__Job_Safety_Analysis.pptx
 
Performing Risk Assessments1
Performing Risk Assessments1Performing Risk Assessments1
Performing Risk Assessments1
 
Risk Assessment.pptx
Risk Assessment.pptxRisk Assessment.pptx
Risk Assessment.pptx
 
Safety training: Risk Assessment & Job Safety Analysis
Safety training: Risk Assessment & Job Safety AnalysisSafety training: Risk Assessment & Job Safety Analysis
Safety training: Risk Assessment & Job Safety Analysis
 
Various steps of risk assessment. md. anwar ibrahim miraz
Various steps of risk assessment. md. anwar ibrahim mirazVarious steps of risk assessment. md. anwar ibrahim miraz
Various steps of risk assessment. md. anwar ibrahim miraz
 
Ppt for IMPROVEMENT OF SAFETY THROUGH SAFETY MANAGAMENT PLAN – office p...
Ppt for IMPROVEMENT OF SAFETY   THROUGH    SAFETY MANAGAMENT PLAN –  office p...Ppt for IMPROVEMENT OF SAFETY   THROUGH    SAFETY MANAGAMENT PLAN –  office p...
Ppt for IMPROVEMENT OF SAFETY THROUGH SAFETY MANAGAMENT PLAN – office p...
 
SAFETY MANAGAMENT PLAN –
SAFETY MANAGAMENT PLAN –SAFETY MANAGAMENT PLAN –
SAFETY MANAGAMENT PLAN –
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.ppt
 
pilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.pptpilot-Risk_Assessment_at_Workplace.ppt
pilot-Risk_Assessment_at_Workplace.ppt
 
Unit IV GE8076 Professional Ethics in Engineering
Unit IV GE8076 Professional Ethics in Engineering Unit IV GE8076 Professional Ethics in Engineering
Unit IV GE8076 Professional Ethics in Engineering
 
Risk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix PresentationRisk Assessment and Risk Assessment Matrix Presentation
Risk Assessment and Risk Assessment Matrix Presentation
 
Risk Management (1) (1).ppt
Risk Management (1) (1).pptRisk Management (1) (1).ppt
Risk Management (1) (1).ppt
 
HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)HIRA (hazard identification risk assessment)
HIRA (hazard identification risk assessment)
 
Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment Hira – hazard identification & risk assessment
Hira – hazard identification & risk assessment
 
Topic 04 risk mangement
Topic 04 risk mangementTopic 04 risk mangement
Topic 04 risk mangement
 
Risk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in MyanmarRisk Assessment for Building Construction Sites in Myanmar
Risk Assessment for Building Construction Sites in Myanmar
 
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
PECB Webinar: Hazard Identification, Risk Assessment and Determining Controls...
 
Risk Management 1 (2)
Risk Management 1 (2)Risk Management 1 (2)
Risk Management 1 (2)
 

More from Gaurav Singh Rajput

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputGaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputGaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputGaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Gaurav Singh Rajput
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputGaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputGaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputGaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputGaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputGaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputGaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputGaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...Gaurav Singh Rajput
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputGaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputGaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Gaurav Singh Rajput
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputGaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputGaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputGaurav Singh Rajput
 

More from Gaurav Singh Rajput (20)

Site Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh RajputSite Emergency Response | Gaurav Singh Rajput
Site Emergency Response | Gaurav Singh Rajput
 
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh RajputQuantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
Quantitative Risk Assessment | QRA | Risk Assessment | Gaurav Singh Rajput
 
Basic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh RajputBasic of Instrumentation and Control | Gaurav Singh Rajput
Basic of Instrumentation and Control | Gaurav Singh Rajput
 
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
Lifting Plan | Lifting Plan for Different Process Equipment | Gaurav Singh Ra...
 
Fire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh RajputFire Protection System | Gaurav Singh Rajput
Fire Protection System | Gaurav Singh Rajput
 
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh RajputBasic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
Basic Instrumentation Symbols | P&ID | PFD | Gaurav Singh Rajput
 
Hzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh RajputHzard Communication | Gaurav Singh Rajput
Hzard Communication | Gaurav Singh Rajput
 
Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput Risk Analysis & Management | Gaurav Singh Rajput
Risk Analysis & Management | Gaurav Singh Rajput
 
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh RajputInspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
Inspection of Fire Fighting Equipments | NFPA Regulations | Gaurav Singh Rajput
 
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh RajputBasic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
Basic LNG Training | Liquefied Natural Gas | Gaurav Singh Rajput
 
Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput Noise Analysis | Gaurav Singh Rajput
Noise Analysis | Gaurav Singh Rajput
 
BBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh RajputBBS - Behaviour Based Safety | Gaurav Singh Rajput
BBS - Behaviour Based Safety | Gaurav Singh Rajput
 
HAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh RajputHAZID | Hazard Indentification | Gaurav Singh Rajput
HAZID | Hazard Indentification | Gaurav Singh Rajput
 
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
SIL Awareness | Introduction to Safety Life-Cycle | IEC - 61508 & IEC- 61511 ...
 
Accident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh RajputAccident & Incident Investigation | Gaurav Singh Rajput
Accident & Incident Investigation | Gaurav Singh Rajput
 
Calculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh RajputCalculating Scaffold Loads | Gaurav Singh Rajput
Calculating Scaffold Loads | Gaurav Singh Rajput
 
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1Inspection of Pressure Vessels as per ASME Sec VIII Division -1
Inspection of Pressure Vessels as per ASME Sec VIII Division -1
 
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh RajputProcess Safety | Process Safety Management | PSM | Gaurav Singh Rajput
Process Safety | Process Safety Management | PSM | Gaurav Singh Rajput
 
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh RajputPigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
Pigging | Pipeline Cleaning | Pigging Safety | Gaurav Singh Rajput
 
Process Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh RajputProcess Safety Awareness | PSM | Gaurav Singh Rajput
Process Safety Awareness | PSM | Gaurav Singh Rajput
 

Recently uploaded

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 

Recently uploaded (20)

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 

Risk Assessment and Job Safety Analysis

  • 1. Risk Assessment & Job Safety Analysis
  • 2. 2 Majority of accident that happens in the construction site is due to the fact that more personnel involved in the construction activities lack the basic knowledge of the various job step, the hazards and the control measures for each hazard The Work Method of Statement, Risk Assessment & Job Safety Analysis (JSA) will cover this gap by giving the people the necessary training, information etc… about each job (task) and how to carry it out without accidents Introduction
  • 3. 3 JSA ⚫ JSA shall be conducted during; ➢ Critical task ➢ Non-routine Task ➢ Permit To Work Task ➢ Routine Task (Daily/pre-task) ⚫ Every work activities shall have a corresponding Work Method of Statement prepared by the task Supervisor or task Manager. ⚫ Risk Assessment shall be done with respect to the corresponding hazard that will be analyzed and mitigating measures during job hazard analysis. ⚫ JSA will be conducted to break down each job steps into safe more detailed procedures.
  • 4. 4 Risk Assessment is an extremely useful tool in providing a framework in which to identify the potential hazards & evaluate the risks associated with all our activities. Risk Assessment now forms a routine element in education & training within the Project. Risk Assessment
  • 5. 5 To prevent workplace injury, disease & property damage, it is necessary to identify the cause of accidents • This can de done: ➢ Reactively by accident investigation, or ➢ Proactively by carrying out risk assessments • Risk assessment enables the identification of those events or activities, which could cause harm & evaluation of the associated risks. Risk Assessment
  • 6. 6 IDENTIFY POTENTIAL LOSS • Risk Assessments involve addressing the following questions: ➢ What could go wrong? ➢ How likely are such events? ➢ What would happen if such events occurred? ➢ What are the associated risks? ➢ Are the risks acceptable? ➢ How can the risks be reduced...or removed? Risk Assessment
  • 7. 7 • There is confusion in the interpretations of familiar words such as accident, hazard, risk & danger and so on; • Different sources of information put similar but different interpretations on these expressions or terms • So for the purpose of discussing risk assessment the following conditions apply on the Project: 1. RISK ASSESSMENT This is the process of identifying hazards and assessing the risk of harm and loss threatened by the hazard. Definition
  • 8. 8 2. RISK MANAGEMENT Risk Management in its broadest sense represents the successful control of all threats of harm and loss to an organisation, group of people or an individual 3. QUANTITATIVE RISK ASSESSMENT This type of assessment produces numerical values of the risk involved and evaluates the results against specified risk criteria. 4. DANGER Danger is a state or situation, which is a product of a hazard and it’s associated risk. Definition
  • 9. 9 5. ACCIDENT An accident is commonly defined as an unplanned event, which result in Injury or Damage. 6. INCIDENT An incident is an event, which represents deviation from the intended sequence of designed steps. Commonly defined as an unplanned event, which does not result in Injury or Damage A “Near Miss” is by definition an Incident. 7. RISK A risk is the likelihood that harm may result being a function of both frequency and severity. The risk can range from the trivial (a paper cut) to catastrophic accident Definition
  • 10. 10 8. SAFE OR SAFETY Often thought of as representing the level of security and freedom from harm.There is no such thing as complete safety, an appropriate definition might be “the maximum level of risk a person or organisation is prepared to accept” 9. HAZARD A hazard is something with the potential to cause harm. This can be substances or machines, methods of work and other aspects of work organisations 10. Harm Harm represents physical injury, death, ill health, property and equipment damage and any from of associated loss Definition
  • 11. 11 • Risk assessments for all field (site activities) • Hazard Operability Studies (HAZOPS) • Hazard Identification Studies (HAZIDS) • Job Safety Analysis (JSA) • Tool Box Talks Risk management Tools Communication and Documentation
  • 12. 12 GENERIC RISK ASSESSMENT A generic or group assessment is a general assessment of the risk posed by a combination of discrete or separate risks of varying type & severity. The risk assessment process can be managed more efficiently by producing generic risk assessments that are applicable to as many people or places as possible SPECIFIC RISK ASSESSMENT Some specific hazards where a generic risk assessment has not been carried out, or where it is not considered suitable or sufficient, then a specific risk assesment should be made. Risk Assessment Process
  • 13. 13 Safe Place Strategies 1. Eliminate the Hazard – the very best thing to do if possible 2. Reduce the Hazard 3. Isolate Hazard from people 4. Control the extent of exposure/contact with the hazard 5. Personal Protective Equipment (PPE) almost the last resort 6. Discipline Hierarchy of Control Safe Person Strategies
  • 14. 14 STAGES 1. Identify & analyse all tasks 2. Identify hazards that are, or may be involved 3. Identify those who may be exposed to the hazards 4. Analyse the risks of injury or loss from hazards 5. Evaluate if the risk is adequately controlled (consider existing control measures) 6. Monitor & review Risk Management Process
  • 15. 15 METHODS OF HAZARD IDENTIFICATION • Accident Investigations • Safety Survey or Safety Tours • Communication (Tool Box Talks etc) • Job Safety Analysis (JSA) • Special Risk Assessment techniques such as: ➢ Hazard Operability Studies (HAZOPs) ➢ Quantified Risk Assessment (QRA) ➢ Hazard Operability Studies (HAZIDs) Stage Two – Identify Hazards
  • 16. 16 • Workforce directly involved in activity • Other employees personnel • Visitors • Members of the public Stage Three – Identify People at Risk
  • 17. 17 The purpose of the Risk Analysis stage is to obtain an idea of the size or the scale of the risk. Put simply, A Risk Assessment is finding out what could cause harm to people (Environment, Task or Equipment) and deciding if we have done enough, or need to do more to protect them, or better still to ensure we meet the Project H&S Policy that all risks are As Low As Reasonably Practicable (ALARP) Stage Four – Risk Assessment
  • 18. 18 QUALITATIVE TECHNIQUES Where risk is expressed in terms of High, Medium or Low QUANTITATIVE TECHNIQUES Attempt to express risk in numerical terms & will be based on calculation using data of failure rates of equipment, human error, etc RISK EVALUATION Risk evaluation is determined by the Likelihood of the incident event occurring multiplied by the Severity of the incident LIKELIHOOD X SEVERITY = RISK Stage Four – Risk Assessment
  • 20. 20 LIKELIHOOD POTENTIAL is determined as follows: E - Happens several time per year in this project – could happen at any time D - Happens several time per year in our Corporate – could happen sometimes C - Incident has occurred in our Corporate – could happen, but very rarely B - Heard of in construction industry – could happen, but probably never will A - Never heard in construction industry – theoretical Risk Evaluation - Likelihood
  • 21. 21 Risk Evaluation - Severity Harm to People 0 No injury or damage to health. 1 Slight injury or health effects (including First Aid case and Medical Treatment case and Occupational illness) - Not affecting work performance or causing disability. 2 Minor injury or health effects (Lost Time Injury ) -Affecting work performance, such as restriction to activities (Restricted work Case or Occupational Illness) or a need to take a few days to fully recover (Lost Workday Case). Minor health effects, which are reversible, e.g. skin irritation, food poisoning.
  • 22. 22 Risk Evaluation - Severity Harm to People 3 Major injury or health effects (including Permanent Partial Disability and Occupational Illness) -Affecting work performance in the longer term, such as a prolonged absence from work. Irreversible health damage without loss of life, e.g. noise induced hearing loss, chronic back injuries, sensitization, hand/arm vibration syndrome, repetitive strain injury. 4 Permanent Total Disability or one to three fatalities - from an accident or occupational illness. Irreversible health damage with serious disability or death, e.g. corrosive burns, heat stroke, cancer (small exposed population) 5 Multiple fatalities - from an accident or occupational illness (e.g. chemical asphyxiation or cancer (large exposed population)
  • 23. 23 Risk Evaluation - Severity Asset Damage and other Consequential Business Losses (USD) 0 Zero damage 1 Slight damage - No disruption to operation (costs less than 10,000) 2 Minor damage- Brief disruption (cost less than 100,000) 3 Local damage- Partial shutdown (can be restarted but costs up to 1,000,000) 4 Major damage- Partial operation loss (2 weeks shutdown costs up to 10,000,000) 5 Extensive damage- Substantial or total loss of operation (costs in excess of 10,000,000)
  • 24. 24 Risk Evaluation - Severity Environmental Effect 0 Zero effect - No environmental damage. No financial consequences. 1 Slight effect - Slight environmental damage, within the fence and within systems. Negligible financial consequences. 2 Minor effect - Sufficiently large contamination or discharge to damage to attack the environment, but no lasting effect. Single breach of statutory or prescribed limit, or single complaint. 3 Localized effect - Limited discharges affecting the neighborhood and damaging the environment. Repeated breaches of statutory or prescribed limit, or many complains.
  • 25. 25 Risk Evaluation - Severity Environmental Effect 4 Major effect - Severe environmental damage. The company is required to take extensive measures to restore the damaged environment. Extended breaches of statutory or prescribed limits, or widespread nuisance. 5 Massive effect - Persistent severe environmental damage or severe nuisance extending over a large area. Loss of commercial, or recreational use or nature conservancy resulting in major financial consequences for the Company. Ongoing breaches well above statutory or prescribed limits.
  • 26. 26 Risk Evaluation - Severity Impact on reputation 0 Zero effect - No public awareness. 1 Slight impact - Public awareness may exist, but there is no public concern. 2 Limited impact - some local public concern. Some local media and/or local political attention with potentially adverse aspects for company operations. 3 Considerable impact - Regional public concern. Extensive adverse attention in local media. Slight national media and/or local/regional political attention. Adverse stance of local government and/or action groups.
  • 27. 27 Risk Evaluation - Severity Impact on Reputation 4 National impact - National public concern. Extensive adverse attention in the national media. Effect on Regional/national policies with potentially restrictive measures and/or impact on grant of licenses. Mobilization of action groups. 5 International impact - International public attention. Extensive adverse attention in international media. National/international policies with potentially severe impact on access to new areas, grants of licenses and/or tax legislation.
  • 28. 28 Risk Assessment - Sample All B2 B 2 Foreman Check scaffolds after adverse weather condition C2 C 2 Adverse weather Scaffolders / All B1 B 1 Foreman Barricade area during erection & Dismantling E3 E 3 Falls of Materials Scaffolders B2 B 2 Foreman Check ground condition. Use base plate & sole plate. Use proper materials B4 B 4 Collapse of Scaffold Scaffolders B3 B 3 Foreman/ Scaffolders Scaffolders working above 1.8m mustbe 100% tie off. Hand rails to be fitted D3 D 3 Fall from Height Scaffolders B1 B 1 Foreman Sufficient personnel, “No Bombing” C1 C 1 Manual Handling Scaffolder / Foreman B1 B 1 Foreman Only trained and competentpersonnel to utilized for the task. All scaffolds to be certified prior to use C3 C 3 Competence Level Scaffold Erection / Dismantling R L F S F R L F S F Person affected (to be informed) Risk After Control By whom Precautions Risk Before Control Hazards Activities
  • 29. 29 What Is Job Safety Analysis ⚫ It is the breaking down of a particular task into steps to be taken in a sequence ⚫ Exposing the hazards involved in each of the steps ⚫ Putting in place control measures for each of the hazards ⚫ Considering the PPE requirement for each step
  • 30. 30 Purpose of JSA ⚫ To improve understanding and safety ⚫ To ensure that there is a written, and approve Work Method of Statement for every job on site ⚫ For proper control of safety on the job
  • 31. 31 Benefits of JSA ⚫ Supervisors learn more about the jobs their subordinates perform and how better to manage them. ⚫ When regularly performed, developed safe work practices reduced employee injuries.
  • 32. 32 Five Basic Steps ⚫ Select job to be analyzed ⚫ Break job down into it’s smallest steps ⚫ Identify hazard associated with each steps ⚫ Develop control measures to eliminate hazards ⚫ Monitoring and periodic reviews
  • 33. 33 Job Safety Analysis Training ⚫ All new employee should be aware of the various step involved in their operations. ⚫ Let employees learn how to perform a job efficiently and safely. ⚫ Supervisors shall clearly explains to his subordinates all the proper steps in doing the task safe
  • 34. 34 TBM before start ofthe job, 100% tie off, using harness with 2 lanyards, Secure all materials for all work at height when there is a rain or wet surface, Experience scaffolders shall be utilized to erectand dismantle suspended scaffold. Other fall protection equipmentshall be utilized e.g. Retractable lanyard, Lifeline. Fall ofpersonnel from height, falling of material, Slippery surface, Inexperience scaffolder Erection of suspended scaffold TBM regarding responsibility during dismantling, Only experience,trained and authorized person can dismantle scaffold Material shall be lowered using rope and bucketor by passing manually Area must be barricaded to keep away all unauthorized persons from the area Falling of scaffold material, collapsing ofscaffold. Fall ofpersonnel, Damage to scaffold material Dismantling of Scaffold TBM before work regarding handling ofmaterials Use of gin wheel to hoist material or mechanical equipment Barricading of lifting area Injury to personnel, material from height Lifting of Scaffold TBM before work, Inspection ofmaterials before work Compacted ground before erection, Work area to be barricaded Material used for work on height should be tie offto preventfrom falling Purpose oferecting scaffold should be known, Kind ofwork to be done on scaffold erection, Complete PPE mustbe worn e.g. hand gloves, safety glass, safety shoes, hardhat, Body harness Bad foundation, Drainage, material falling, unknown purpose for erection of scaffold Scaffold Erection Preventive Measure Hazard Activity Job Safety Analysis (JSA)
  • 35. 35 • Keep it simple • Developed (at least in part) by the personnel performing work • We believe that JSA should be a thoughtful process ... Not simply a form to complete. • JSA must be reviewed with all personnel coming on shift • OK to use previously developed JSA, but must be upgraded based on current scope and conditions, and actively reviewed by the crew • For jobs that are repetitive, review and upgrade JSA before starting the work. Job Safety Analysis Guidelines
  • 36. 36 • When work is already completed, update the JSA to identify lesson learned and unexpected results • Update the JSA if an accident or near-miss occurs • Ask for feedback each day consider new ideas and include in the JSA form • Include job setup and demobilization in the JSA • A JSA should; ➢ Identify the location of the work to be performed ➢ Address how the job may affect others ➢ Address emergency situation ➢ Identify communication requirements Job Safety Analysis Guidelines
  • 37. 37 • When work is complete, why not update the Pre-task Safety Plan to identify learnings and unexpected results Update the Pre-task Safety Plan if an accident or Near Miss occurs • Ask for feedback each day – consider adding a place for it on the form • Include job setup and demobilization in the Pre-task Safety Plan Job Safety Analysis Guidelines
  • 38. 38 How is it done at your site? • Is it similar? • Is it truly different? • Is it effective? (How do you verify?) • What are your success stories? • What are your challenges?
  • 39. 39 • Few accidents occur during extremely hazardous operations because we are fully aware of the risk • Most accidents occur during routine, repetitious jobs because we become complacent • Therefore, all supervisors are expected to insure effective Risk Assessment and JSA are conducted and all their crews will follow all the provisions in the form. Supervisor should make sure that pre-task meeting is conducted before beginning each work. Summary