• DM Consunji, Inc. (DMCI) – the lead contractor for the
Metro Manila Skyway Stage 2.
• Citra Metro Manila Tollways Corporation (CMMTC) – the
proponent for the Skyway Project.
• April 2009 Citra announced the construction on the
second stage.
• By May 2010, rotating the highest pierhead in the Sucat
area.
• By July, concreting 134 of the required 238 spans and
started pouring the Asphalt overlay.
• Started mobilization in May 2009 and finishing in March
2011.
• On December 15, 2010, The Bicutan-to-Sucat portion of
Stage 2 opened to the public.
• April 2011 – opened to public.
• STAGE 2 involved the construction of a 6.88km-long
expressway from BICUTAN to ALABANG.
• Accommodates an estimated of 300,000 vehicles per day
• 6-lane elevated toll way to the public from Bicutan to
Alabang.
• Total Project Cost: 2 Billion Pesos
• Minimum Speed : 60kph
• Maximum Speed : 100kph for Class 1 Vehicles
80kph for buses and trucks
• The project aims to provide a vital link between
ALABANG AND BICUTAN through elevated expressway
system.
• It also aimed at helping decongest Metro Manila’s major
road system
• The project is also to boost the conduct of trade and
commercial activities
ISSUE
• Worsening traffic condition in Metro Manila
SOLUTION
• The government proposed to build the Skyway Stage3.

More Related Content

What's hot

Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli SealinkDesignTeja
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,Indiaoyepuneeta
 
2010-RTA Corona Transit Center Update
2010-RTA Corona Transit Center Update2010-RTA Corona Transit Center Update
2010-RTA Corona Transit Center UpdateDarrell Talbert
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealinkpeepkya
 
Bandra worli sealink
Bandra worli sealinkBandra worli sealink
Bandra worli sealinkAmit Kumar
 
Bangladesh studies presentation slide
Bangladesh studies presentation slideBangladesh studies presentation slide
Bangladesh studies presentation slideMD Jannatul Giyem
 
Bandra worli sea link jay
Bandra worli sea link jayBandra worli sea link jay
Bandra worli sea link jayDhruv Seth
 
Innovations of civil engineering
Innovations of civil engineeringInnovations of civil engineering
Innovations of civil engineeringAbhijit Pal
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea linkAnkita Pal
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkUnni Krishnan
 
Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case studyAKSHAY CHATURVEDI
 
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsPADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsSajal Eahsan
 
Project on padma bridge
Project on padma bridgeProject on padma bridge
Project on padma bridgeAbid Hasan
 
Geography Chapter 7
Geography Chapter 7Geography Chapter 7
Geography Chapter 7HaasviSawant
 

What's hot (20)

Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
 
2010-RTA Corona Transit Center Update
2010-RTA Corona Transit Center Update2010-RTA Corona Transit Center Update
2010-RTA Corona Transit Center Update
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bandra worli sealink
Bandra worli sealinkBandra worli sealink
Bandra worli sealink
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bangladesh studies presentation slide
Bangladesh studies presentation slideBangladesh studies presentation slide
Bangladesh studies presentation slide
 
Bandra Worli Sealink
Bandra Worli SealinkBandra Worli Sealink
Bandra Worli Sealink
 
Bandra worli sea link jay
Bandra worli sea link jayBandra worli sea link jay
Bandra worli sea link jay
 
Innovations of civil engineering
Innovations of civil engineeringInnovations of civil engineering
Innovations of civil engineering
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea link
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Mmmodified copy
Mmmodified   copyMmmodified   copy
Mmmodified copy
 
Bandra worli sea link case study
Bandra worli sea link  case studyBandra worli sea link  case study
Bandra worli sea link case study
 
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goalsPADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
PADMA MULTIPURPOSE BRIDGE – Mission, Vision, Objective and goals
 
Project on padma bridge
Project on padma bridgeProject on padma bridge
Project on padma bridge
 
Bandra worli sealink
Bandra worli sealinkBandra worli sealink
Bandra worli sealink
 
Bandra worli sealink
Bandra worli sealinkBandra worli sealink
Bandra worli sealink
 
Geography Chapter 7
Geography Chapter 7Geography Chapter 7
Geography Chapter 7
 

Similar to ROAD BED CONSTRUCTION IN METRO MANILA SKY WAY (STAGE 2)

Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresBimenpreet Kaur
 
Light rail-transit-2
Light rail-transit-2Light rail-transit-2
Light rail-transit-2Jade Lustria
 
CIRCUMFERENTIAL ROAD 6 in Taguig City
CIRCUMFERENTIAL ROAD 6 in Taguig CityCIRCUMFERENTIAL ROAD 6 in Taguig City
CIRCUMFERENTIAL ROAD 6 in Taguig Cityharoldtaylor1113
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019Crosstown TO
 
Cantonment metro station a case study1 rajkumar
Cantonment metro station   a case study1  rajkumarCantonment metro station   a case study1  rajkumar
Cantonment metro station a case study1 rajkumarSanjeev Dyamannavar
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018Crosstown TO
 
A_detailed_training_report_on_JAIPUR_ME.pdf
A_detailed_training_report_on_JAIPUR_ME.pdfA_detailed_training_report_on_JAIPUR_ME.pdf
A_detailed_training_report_on_JAIPUR_ME.pdfDeebakAshwinViswanat2
 
Bangalore metro rail project
Bangalore metro rail projectBangalore metro rail project
Bangalore metro rail projectSaravanan rulez
 
Development Potentials of the North-South Commuter Railway.pptx
Development Potentials of the North-South Commuter Railway.pptxDevelopment Potentials of the North-South Commuter Railway.pptx
Development Potentials of the North-South Commuter Railway.pptxCREBAWebmaster
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Crosstown TO
 
Uemc apr 19_2011
Uemc apr 19_2011Uemc apr 19_2011
Uemc apr 19_2011Harith
 
DMRC CC 66 training ppt
DMRC CC 66 training pptDMRC CC 66 training ppt
DMRC CC 66 training pptVikas Kumar
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Crosstown TO
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
Status of roads in nairobi by ps mo r 2nd august 2012
Status of roads in nairobi  by ps mo r 2nd august 2012Status of roads in nairobi  by ps mo r 2nd august 2012
Status of roads in nairobi by ps mo r 2nd august 2012Functional Eco
 

Similar to ROAD BED CONSTRUCTION IN METRO MANILA SKY WAY (STAGE 2) (20)

Atal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and featuresAtal Rohtang Tunnel - construction process ,challenges and features
Atal Rohtang Tunnel - construction process ,challenges and features
 
Light rail-transit-2
Light rail-transit-2Light rail-transit-2
Light rail-transit-2
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
 
CIRCUMFERENTIAL ROAD 6 in Taguig City
CIRCUMFERENTIAL ROAD 6 in Taguig CityCIRCUMFERENTIAL ROAD 6 in Taguig City
CIRCUMFERENTIAL ROAD 6 in Taguig City
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
 
Smart tunnel
Smart  tunnelSmart  tunnel
Smart tunnel
 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
 
Cantonment metro station a case study1 rajkumar
Cantonment metro station   a case study1  rajkumarCantonment metro station   a case study1  rajkumar
Cantonment metro station a case study1 rajkumar
 
KL structure plan 1981 2000
KL structure plan 1981 2000KL structure plan 1981 2000
KL structure plan 1981 2000
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Usbrlp at a glance
Usbrlp at a glanceUsbrlp at a glance
Usbrlp at a glance
 
A_detailed_training_report_on_JAIPUR_ME.pdf
A_detailed_training_report_on_JAIPUR_ME.pdfA_detailed_training_report_on_JAIPUR_ME.pdf
A_detailed_training_report_on_JAIPUR_ME.pdf
 
Bangalore metro rail project
Bangalore metro rail projectBangalore metro rail project
Bangalore metro rail project
 
Development Potentials of the North-South Commuter Railway.pptx
Development Potentials of the North-South Commuter Railway.pptxDevelopment Potentials of the North-South Commuter Railway.pptx
Development Potentials of the North-South Commuter Railway.pptx
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
Uemc apr 19_2011
Uemc apr 19_2011Uemc apr 19_2011
Uemc apr 19_2011
 
DMRC CC 66 training ppt
DMRC CC 66 training pptDMRC CC 66 training ppt
DMRC CC 66 training ppt
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Status of roads in nairobi by ps mo r 2nd august 2012
Status of roads in nairobi  by ps mo r 2nd august 2012Status of roads in nairobi  by ps mo r 2nd august 2012
Status of roads in nairobi by ps mo r 2nd august 2012
 

More from haroldtaylor1113

Design Coordinates Incorporated
Design Coordinates IncorporatedDesign Coordinates Incorporated
Design Coordinates Incorporatedharoldtaylor1113
 
Case Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater ManagementCase Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater Managementharoldtaylor1113
 
Case Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in LagunaCase Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in Lagunaharoldtaylor1113
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Provinceharoldtaylor1113
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manilaharoldtaylor1113
 
Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067haroldtaylor1113
 
Case Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the PhilippinesCase Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the Philippinesharoldtaylor1113
 
Case Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the PhilippinesCase Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the Philippinesharoldtaylor1113
 
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan CityCase Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan Cityharoldtaylor1113
 
Case Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in AquacultureCase Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in Aquacultureharoldtaylor1113
 
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...haroldtaylor1113
 
Case Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, CaviteCase Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, Caviteharoldtaylor1113
 
Case Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of SuccessCase Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of Successharoldtaylor1113
 
Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen  Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen haroldtaylor1113
 
Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine haroldtaylor1113
 
Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection haroldtaylor1113
 
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...haroldtaylor1113
 
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...haroldtaylor1113
 
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...haroldtaylor1113
 
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...haroldtaylor1113
 

More from haroldtaylor1113 (20)

Design Coordinates Incorporated
Design Coordinates IncorporatedDesign Coordinates Incorporated
Design Coordinates Incorporated
 
Case Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater ManagementCase Study No. 9-Philippines’ Integrated Stormwater Management
Case Study No. 9-Philippines’ Integrated Stormwater Management
 
Case Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in LagunaCase Study No. 2-Lumot lake in Laguna
Case Study No. 2-Lumot lake in Laguna
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Province
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manila
 
Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067Case Study No. 12-Presidential Decree No. 1067
Case Study No. 12-Presidential Decree No. 1067
 
Case Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the PhilippinesCase Study No. 11- Hydroelectric Power Plant in the Philippines
Case Study No. 11- Hydroelectric Power Plant in the Philippines
 
Case Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the PhilippinesCase Study No. 10-Construction of Box Culverts in the Philippines
Case Study No. 10-Construction of Box Culverts in the Philippines
 
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan CityCase Study No. 6-Road and Drainage Improvement Project in Caloocan City
Case Study No. 6-Road and Drainage Improvement Project in Caloocan City
 
Case Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in AquacultureCase Study No. 5-Pasig River Open Channel in Aquaculture
Case Study No. 5-Pasig River Open Channel in Aquaculture
 
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
Case Study No. 4-Design of Water Distribution System using Naugong spring as ...
 
Case Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, CaviteCase Study No. 3-Molino Dam in Bacoor, Cavite
Case Study No. 3-Molino Dam in Bacoor, Cavite
 
Case Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of SuccessCase Study 13-A Color for All Seasons & A New Variety of Success
Case Study 13-A Color for All Seasons & A New Variety of Success
 
Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen  Case Study 12B-The Gugo Queen
Case Study 12B-The Gugo Queen
 
Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine Case Study 12A-From Herbal Folklore to Modern Medicine
Case Study 12A-From Herbal Folklore to Modern Medicine
 
Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection Case Study 11-Rising Above the Competition & Thriving on IP Protection
Case Study 11-Rising Above the Competition & Thriving on IP Protection
 
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
Case Study 10-Shaping a Regional IP Tool & Folk Art and the Opportunities of ...
 
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
Case Study 8-Electrifying Economic Development & From Heavy to Light_Accelera...
 
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
Case Study 9-Strategic Partnership Linked to IP in the Development & Planting...
 
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
Case Study 7- A Bold Step into the Modern Economy & A Remote Solution for a G...
 

Recently uploaded

Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfEr. Suman Jyoti
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfrs7054576148
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

ROAD BED CONSTRUCTION IN METRO MANILA SKY WAY (STAGE 2)

  • 1. PRESENTED TO: Dr. Tomas U. Ganiron Jr PRESENTED BY: Peter Kha Bang Joyce D. Danila Samantha Jacinto Henry Lyn Romero Adrian Bryan Estember
  • 2. • DM Consunji, Inc. (DMCI) – the lead contractor for the Metro Manila Skyway Stage 2. • Citra Metro Manila Tollways Corporation (CMMTC) – the proponent for the Skyway Project.
  • 3. • April 2009 Citra announced the construction on the second stage. • By May 2010, rotating the highest pierhead in the Sucat area. • By July, concreting 134 of the required 238 spans and started pouring the Asphalt overlay.
  • 4. • Started mobilization in May 2009 and finishing in March 2011. • On December 15, 2010, The Bicutan-to-Sucat portion of Stage 2 opened to the public. • April 2011 – opened to public.
  • 5. • STAGE 2 involved the construction of a 6.88km-long expressway from BICUTAN to ALABANG. • Accommodates an estimated of 300,000 vehicles per day
  • 6. • 6-lane elevated toll way to the public from Bicutan to Alabang.
  • 7. • Total Project Cost: 2 Billion Pesos • Minimum Speed : 60kph • Maximum Speed : 100kph for Class 1 Vehicles 80kph for buses and trucks
  • 8. • The project aims to provide a vital link between ALABANG AND BICUTAN through elevated expressway system. • It also aimed at helping decongest Metro Manila’s major road system • The project is also to boost the conduct of trade and commercial activities
  • 9. ISSUE • Worsening traffic condition in Metro Manila SOLUTION • The government proposed to build the Skyway Stage3.