SlideShare a Scribd company logo
1 of 26
Claim Analysis
1
Group 7:
Ali Zahedi Anaraki
Rabih Ataya
Rachid Tawil
Hossein Khodaverdipoursarbandi
Seyed Mohammadsadegh Tabatabaei
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
 Project overview
 Scope of work
 Major Problems
 Delay analysis
 Productivity analysis
 Damage Quantification
 Claim Summary
 Conclusion
 Questions
Outline
2
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Project overview
3
 The project is an upgrade of an existing mill plant.
 Mechanical Contract: Erection of mechanical equipment and
installation of piping for the New SAG MILL.
 Mechanical Contract is Lump-sum with a total value of $2,549,130
 The Contractor selected based on:
 lowest bid
 Proposal technically acceptable
 Satisfied all terms of the Contract
 Key Dates and Events:
 April 30th 1990 Scheduled Start Date
 May 3rd, 1990 Actual Start Date
 August 31st 1990 Scheduled Finish Date
 December 19th 1990 Actual Finish Date
4
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Scope of work
4
 The contract identifies six main physical areas for the mechanical
equipment erection.
 Piping work which occurs in all of these areas, identified as a seventh
"area”.
 The areas, and the relative volume of the labor shown in the bar chart:
0
5
10
15
20
25
PersentageofLabor
Areas of Work
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Scope of work
5
Work Included
 Unloading and Transportation of Equipment to installation site
 Installation of 107 Equipment in 6 Areas of the Project
 Including removal of old equipment to be replaced
 Supply and Installation of Piping in all Areas
 Miscellaneous Works and Installations for the completion and
commissioning of the Installed Equipment.
Work Excluded
 Supply of Mechanical Equipment.
 Civil and Structural works
 Equipment Installation Procedures and Engineering Plans
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Major Problems
6
Equipment Delivery
 According to the project’s schedule:
 39 pieces on site at the beginning of work.
 24 units on site in May 1990.
 41 pieces on site in June 1190.
 3 pieces on site in early July 1990.
19.57%
26.09%
26.09%
14.13%
6.52%
2.17%
5.43%
Equipment Delivery - Months Late
1
2
3
4
5
6
7
 On average, equipment delivery
was 3 months later than the
agreed contractual delivery dates.
 The longest delay in equipment
delivery was for a component of
the Sag Mill at 194 days and the
Ball Mill Pinion Shaft at 193 days.
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Major Problems
7
Defective Equipment
 Several equipment were supplied with deficiencies. Examples:
 Minor deficiency: faulty welds on Conveyor Assembly
 Major deficiency: Overcast discharge head sections in the Ball Mill
 Out of 107 delivered Equipment, 30 had some sort of deficiency.
 Civil & Structural Deficiencies:
 Works by others were delivered with construction errors on many
occasions, namely the Anchorages of the Sole Plates.
 Lost Time on the execution of the works:
 Identifying problems
 Coordinating solutions with the Engineer
 Executing the corrective actions
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Major Problems
8
Drawing Revisions
 Out of 374 drawings issued to the Contractor:
 Only 93 were issued with final revision prior to start of the works
 75% of drawings were issued or revised after start of the works
 17% of drawings were issued to the Contractor in November 1990
 Effect on the work:
 Change Orders
 Rework
 Loss of Productivity – Works on hold or change in work method
Month March April May June July August September October November Unknown
Number of Dwgs Issued 93 0 185 44 29 15 24 5 17 55
Percentage of Total 24.87% 0.00% 49.47% 11.76% 7.75% 4.01% 6.42% 1.34% 4.55% 14.71%
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Major Problems
9
Access
 Access to work area was not ready for the Mechanical Contractor on
many occasions, the most significant are summarized below:
 Civil and Structures contractors were late on delivering installation
areas or works required by the Mechanical Contractor.
 Delays were carried on by the Mechanical Contractor.
 Co-activity in work areas was not properly managed by the Engineer.
Area Planned Activity Planned Access Date Actual Access Date Access Delay
1 Conveyors July 7, 1990 September 5, 1990 60
3 Feeder June 13, 1990 June 22, 1990 9
4 Mill Shell July 9, 1990 July 12, 1990 3
5 Cone Crusher June 3, 1990 July 6, 1990 33
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Delay analysis
10
Chosen method : Impacted As-Planned
Steps done in this method :
 Importing Primavera files for all areas and filter to Critical path
 Find actual start and finish dates of all critical activities from
daily log and Equipment delivery
 Inserting these dates into software month by month in order to
cover all parallel delays and their impacts
 Calculating the difference between As-planned finish date of
project and Impacted finish date of project by each activity in
critical path
 Finally, calculating all impacted days of delay
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Delay analysis
11
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Delay analysis
12
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Delay analysis
13
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Delay analysis
14
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Delay analysis
15
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Delay analysis
16
chronology of
delays
activity
delay
type duration delays
Impact
delays(working
days)
1
CHUTES DELIVERED FOR FEEDER #
6
EC 0 4
2 PEBBLE CONVEYOR DELIVERED EC 0 29
3 INSTALL PLATEWORK-SAG EC -59 22
4 REMOVE EXISTING CONVEYOR # 1 EC -5 9
5
MODIFY EXISTING MILL 3&4 (PART
2)
EC -21 12
6 DEMOBILIZATION . EC 0 3
Owner is responsible for 79 working days of delay -85 79
5%
37%
28%
11%
15%
4%
chronology of delays
CHUTES DELIVERED FOR FEEDER # 6
PEBBLE CONVEYOR DELIVERED
INSTALL PLATEWORK-SAG
REMOVE EXISTING CONVEYOR # 1
MODIFY EXISTING MILL 3&4 (PART 2)
DEMOBILIZATION .
Project overview
Scope of work
Major problems
Delay Analysis
Damage
Quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Damage Quantification
17
Change Orders
 Approved-Unpaid Change Orders, totaling $504,662.00 :
 Unapproved-Unpaid Change Orders, totaling $1,528,412.00 :
Date Item Description Amount ($)
November 21,
1990
Change Order
No. 1
This work was carried out
during the month of November.
345,271
November 21,
1990
Change Order
No. 2
FWI's 1 to 7 inclusive, 9 to 17
inclusive and 19 to 22 inclusive.
4,049
December 6,
1990
Change Order
No. 3
FWI's 23, 29, 33, 34, 37, 39,
41, 42, 44 and 51.
155,342
Date Item Description Amount ($)
August 22, 1990
re-drawing
revisions
Additional costs for drawing
revisions and additional cost for
site overheads and equipment.
345,271
October 17, 1990
re-drawing
revisions
Verbal instruction to proceed with
the work and that CONTRACTOR
will receive compensation for this
additional work.
4,049
November 26, 1990
drawing
revisions
Costs associated with extended
contract schedule will be
addressed at a later date.
155,342
December 11, 1990
Vendor
Drawings
additional costs from BOLLIDEN-
ALLIS vendor drawings
568,407
December 21, 1990
signed
Change
Order No. 4
Re-drawing revisions and FWI's
58 and 59. This Change Order
was never signed by ENGINEER.
455,3423
Project overview
Scope of work
Major problems
Delay Analysis
Damage
Quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Damage Quantification
18
Loss of Profit
 Original Contract value, including Contractor profit, is $2,549,130.
 Terminated Contract value is $1,814,598.
 According to Clause 6.3.3 of contract, the contractor has the right to
claim the loss of profit for the difference between the contract price
and the earned amount.
 For a profit of 5%
 Profit loss = 5% x ($2,549,130 – $1,814,598) = 5% x $734,532
 Claimable profit loss = $36,727
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Productivity analysis
19
1. Total Cost Method
2. Modified Total Cost Method
3. Measured Mile
4. Industry Studies on change orders such as Leonard and Ibbs studies.
The total cost method
Claim amount = (incurred costs + Mark-up) - Received payment
Claim amount = [(64,506 hours x 1.05) – 29,917] x $40/hour ≈ $1,512,600
Measured Mile Method
Claimable hours = Total Manhours - Total Normal Hours – Hours claimed separately for changes
Claimable hours = 34,367 hours
Claimable amount = $1,374,680
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Productivity analysis
20
Area
Duration
(days)
Earned
Man-hours
Spent
Man-hours
Productivity
Normal
Hours
0 216 120 3,324 27.70 121
1 120 1,368 2,687 1.96 1,378
2 212 2,972 7,475 2.51 2,994
3 176 1,405 3,084 2.19 1,415
4 199 2,804 15,936 5.68 2,825
5 174 3,715 6,513 1.75 3,743
6 139 1,004 1,808 1.80 1,011
7 157 16,529 16,652 1.01 16,652
9 226 - 18,672 - 0
Total 29,917 76,149 30,139
Table 1 : Loss of productivity estimation using measured mile method
Leonard Study
% Change orders =
Change order hours
Actual labour hours − change order hours
= 12%  37% loss of productivity
Productivity loss hours = 64,506 hours x 0.37 = 23,868 hours
Claimable amount = 23,868 hours x $40/hour = $954,720
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Productivity analysis
21
Figure 1 : The effect of change orders on productivity for electrical and mechanical work by Charles A. Leonard
Leonard Study
12% change  construction productivity = 0.75  loss of productivity = 25%
Productivity loss hours = 64,506 hours x 0.25 = 16,127 hours
Claimable amount = 16,127 hours x $40/hour = $645,080
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Productivity analysis
22
Figure 2 : The effect of change orders on productivity by William Ibbs
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Productivity analysis
23
Method Total Cost Measured Mile Leonard study Ibbs adapted study
Claimable hours 37,815 34,367 23,868 16,127
Claimable
amount
$1,512,600 1,374,680 $954,720 $645,080
Productivity 1 1.01
37% loss of
productivity
25% loss of
productivity
Table 2 : Comparison of available methods to measure the loss of productivity
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Claim summary
24
Summary of the claimed amounts for the contract dispute:
Description Amount ($)
Unpaid approved changes 504,662
Unpaid unapproved changes 1,528,412
Loss of profit 36,727
Indirect cost 133,065
Loss of productivity 645,080
Total 2,847,946
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Conclusion
25
 A lump sum contract of $2,549,130 was awarded for the Sag mill
mechanical project.
 The Engineer terminated the contract with a total payment of
$1,814,598.
 The total claim amount of $2,847,946 is submitted by the Contractor.
Project overview
Scope of work
Major problems
Delay analysis
Damage
quantification
Productivity
analysis
Claim summary
Conclusion
Questions
Questions
26

More Related Content

What's hot

Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Francis Ho
 

What's hot (20)

Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays Analysis
 
Claims
ClaimsClaims
Claims
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Extension of time in construction contracts
Extension of time in construction contractsExtension of time in construction contracts
Extension of time in construction contracts
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
Fidic comparison red yellow - silver book
Fidic comparison red   yellow - silver bookFidic comparison red   yellow - silver book
Fidic comparison red yellow - silver book
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law ConferenceClaim Preparation and Project Records - 2014 Olswang Construction Law Conference
Claim Preparation and Project Records - 2014 Olswang Construction Law Conference
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 

Similar to Claim Presentation Rev 03 FINAL

INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
Nur Ain Samsudin
 
ie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.pptie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.ppt
BasemAbdo4
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
IrfanAwan25
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
BayuDarma4
 

Similar to Claim Presentation Rev 03 FINAL (20)

Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
INDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORTINDUSTRIAL TRAINING REPORT
INDUSTRIAL TRAINING REPORT
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
B012140812
B012140812B012140812
B012140812
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
ie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.pptie550cappie550cappie550cappie550capp.ppt
ie550cappie550cappie550cappie550capp.ppt
 
Final April 18 LMKAIZEN
Final April 18 LMKAIZENFinal April 18 LMKAIZEN
Final April 18 LMKAIZEN
 
Presntation (MNIT).pptx
Presntation (MNIT).pptxPresntation (MNIT).pptx
Presntation (MNIT).pptx
 
ie550capp.ppt
ie550capp.pptie550capp.ppt
ie550capp.ppt
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
API 610 pumps .pdf
API 610 pumps .pdfAPI 610 pumps .pdf
API 610 pumps .pdf
 
MRM-16 (2020).pptx
MRM-16 (2020).pptxMRM-16 (2020).pptx
MRM-16 (2020).pptx
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
ie550capp.ppt
ie550capp.pptie550capp.ppt
ie550capp.ppt
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
 

More from Hossein Khodaverdi M.Eng

More from Hossein Khodaverdi M.Eng (6)

Final Presentation
Final Presentation Final Presentation
Final Presentation
 
Hall Building Escalators_Case Study
Hall Building Escalators_Case StudyHall Building Escalators_Case Study
Hall Building Escalators_Case Study
 
Health and Safety Presentation FINAL
Health and Safety Presentation FINALHealth and Safety Presentation FINAL
Health and Safety Presentation FINAL
 
building group 5
building group 5building group 5
building group 5
 
Urban Transportation Planning and Design (Montreal-Montreal Nord)
Urban Transportation Planning and Design (Montreal-Montreal Nord)Urban Transportation Planning and Design (Montreal-Montreal Nord)
Urban Transportation Planning and Design (Montreal-Montreal Nord)
 
Trenchless Technology
Trenchless TechnologyTrenchless Technology
Trenchless Technology
 

Claim Presentation Rev 03 FINAL

  • 1. Claim Analysis 1 Group 7: Ali Zahedi Anaraki Rabih Ataya Rachid Tawil Hossein Khodaverdipoursarbandi Seyed Mohammadsadegh Tabatabaei
  • 2. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions  Project overview  Scope of work  Major Problems  Delay analysis  Productivity analysis  Damage Quantification  Claim Summary  Conclusion  Questions Outline 2
  • 3. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Project overview 3  The project is an upgrade of an existing mill plant.  Mechanical Contract: Erection of mechanical equipment and installation of piping for the New SAG MILL.  Mechanical Contract is Lump-sum with a total value of $2,549,130  The Contractor selected based on:  lowest bid  Proposal technically acceptable  Satisfied all terms of the Contract  Key Dates and Events:  April 30th 1990 Scheduled Start Date  May 3rd, 1990 Actual Start Date  August 31st 1990 Scheduled Finish Date  December 19th 1990 Actual Finish Date
  • 4. 4 Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Scope of work 4  The contract identifies six main physical areas for the mechanical equipment erection.  Piping work which occurs in all of these areas, identified as a seventh "area”.  The areas, and the relative volume of the labor shown in the bar chart: 0 5 10 15 20 25 PersentageofLabor Areas of Work
  • 5. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Scope of work 5 Work Included  Unloading and Transportation of Equipment to installation site  Installation of 107 Equipment in 6 Areas of the Project  Including removal of old equipment to be replaced  Supply and Installation of Piping in all Areas  Miscellaneous Works and Installations for the completion and commissioning of the Installed Equipment. Work Excluded  Supply of Mechanical Equipment.  Civil and Structural works  Equipment Installation Procedures and Engineering Plans
  • 6. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Major Problems 6 Equipment Delivery  According to the project’s schedule:  39 pieces on site at the beginning of work.  24 units on site in May 1990.  41 pieces on site in June 1190.  3 pieces on site in early July 1990. 19.57% 26.09% 26.09% 14.13% 6.52% 2.17% 5.43% Equipment Delivery - Months Late 1 2 3 4 5 6 7  On average, equipment delivery was 3 months later than the agreed contractual delivery dates.  The longest delay in equipment delivery was for a component of the Sag Mill at 194 days and the Ball Mill Pinion Shaft at 193 days.
  • 7. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Major Problems 7 Defective Equipment  Several equipment were supplied with deficiencies. Examples:  Minor deficiency: faulty welds on Conveyor Assembly  Major deficiency: Overcast discharge head sections in the Ball Mill  Out of 107 delivered Equipment, 30 had some sort of deficiency.  Civil & Structural Deficiencies:  Works by others were delivered with construction errors on many occasions, namely the Anchorages of the Sole Plates.  Lost Time on the execution of the works:  Identifying problems  Coordinating solutions with the Engineer  Executing the corrective actions
  • 8. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Major Problems 8 Drawing Revisions  Out of 374 drawings issued to the Contractor:  Only 93 were issued with final revision prior to start of the works  75% of drawings were issued or revised after start of the works  17% of drawings were issued to the Contractor in November 1990  Effect on the work:  Change Orders  Rework  Loss of Productivity – Works on hold or change in work method Month March April May June July August September October November Unknown Number of Dwgs Issued 93 0 185 44 29 15 24 5 17 55 Percentage of Total 24.87% 0.00% 49.47% 11.76% 7.75% 4.01% 6.42% 1.34% 4.55% 14.71%
  • 9. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Major Problems 9 Access  Access to work area was not ready for the Mechanical Contractor on many occasions, the most significant are summarized below:  Civil and Structures contractors were late on delivering installation areas or works required by the Mechanical Contractor.  Delays were carried on by the Mechanical Contractor.  Co-activity in work areas was not properly managed by the Engineer. Area Planned Activity Planned Access Date Actual Access Date Access Delay 1 Conveyors July 7, 1990 September 5, 1990 60 3 Feeder June 13, 1990 June 22, 1990 9 4 Mill Shell July 9, 1990 July 12, 1990 3 5 Cone Crusher June 3, 1990 July 6, 1990 33
  • 10. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Delay analysis 10 Chosen method : Impacted As-Planned Steps done in this method :  Importing Primavera files for all areas and filter to Critical path  Find actual start and finish dates of all critical activities from daily log and Equipment delivery  Inserting these dates into software month by month in order to cover all parallel delays and their impacts  Calculating the difference between As-planned finish date of project and Impacted finish date of project by each activity in critical path  Finally, calculating all impacted days of delay
  • 11. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Delay analysis 11
  • 12. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Delay analysis 12
  • 13. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Delay analysis 13
  • 14. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Delay analysis 14
  • 15. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Delay analysis 15
  • 16. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Delay analysis 16 chronology of delays activity delay type duration delays Impact delays(working days) 1 CHUTES DELIVERED FOR FEEDER # 6 EC 0 4 2 PEBBLE CONVEYOR DELIVERED EC 0 29 3 INSTALL PLATEWORK-SAG EC -59 22 4 REMOVE EXISTING CONVEYOR # 1 EC -5 9 5 MODIFY EXISTING MILL 3&4 (PART 2) EC -21 12 6 DEMOBILIZATION . EC 0 3 Owner is responsible for 79 working days of delay -85 79 5% 37% 28% 11% 15% 4% chronology of delays CHUTES DELIVERED FOR FEEDER # 6 PEBBLE CONVEYOR DELIVERED INSTALL PLATEWORK-SAG REMOVE EXISTING CONVEYOR # 1 MODIFY EXISTING MILL 3&4 (PART 2) DEMOBILIZATION .
  • 17. Project overview Scope of work Major problems Delay Analysis Damage Quantification Productivity analysis Claim summary Conclusion Questions Damage Quantification 17 Change Orders  Approved-Unpaid Change Orders, totaling $504,662.00 :  Unapproved-Unpaid Change Orders, totaling $1,528,412.00 : Date Item Description Amount ($) November 21, 1990 Change Order No. 1 This work was carried out during the month of November. 345,271 November 21, 1990 Change Order No. 2 FWI's 1 to 7 inclusive, 9 to 17 inclusive and 19 to 22 inclusive. 4,049 December 6, 1990 Change Order No. 3 FWI's 23, 29, 33, 34, 37, 39, 41, 42, 44 and 51. 155,342 Date Item Description Amount ($) August 22, 1990 re-drawing revisions Additional costs for drawing revisions and additional cost for site overheads and equipment. 345,271 October 17, 1990 re-drawing revisions Verbal instruction to proceed with the work and that CONTRACTOR will receive compensation for this additional work. 4,049 November 26, 1990 drawing revisions Costs associated with extended contract schedule will be addressed at a later date. 155,342 December 11, 1990 Vendor Drawings additional costs from BOLLIDEN- ALLIS vendor drawings 568,407 December 21, 1990 signed Change Order No. 4 Re-drawing revisions and FWI's 58 and 59. This Change Order was never signed by ENGINEER. 455,3423
  • 18. Project overview Scope of work Major problems Delay Analysis Damage Quantification Productivity analysis Claim summary Conclusion Questions Damage Quantification 18 Loss of Profit  Original Contract value, including Contractor profit, is $2,549,130.  Terminated Contract value is $1,814,598.  According to Clause 6.3.3 of contract, the contractor has the right to claim the loss of profit for the difference between the contract price and the earned amount.  For a profit of 5%  Profit loss = 5% x ($2,549,130 – $1,814,598) = 5% x $734,532  Claimable profit loss = $36,727
  • 19. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Productivity analysis 19 1. Total Cost Method 2. Modified Total Cost Method 3. Measured Mile 4. Industry Studies on change orders such as Leonard and Ibbs studies. The total cost method Claim amount = (incurred costs + Mark-up) - Received payment Claim amount = [(64,506 hours x 1.05) – 29,917] x $40/hour ≈ $1,512,600
  • 20. Measured Mile Method Claimable hours = Total Manhours - Total Normal Hours – Hours claimed separately for changes Claimable hours = 34,367 hours Claimable amount = $1,374,680 Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Productivity analysis 20 Area Duration (days) Earned Man-hours Spent Man-hours Productivity Normal Hours 0 216 120 3,324 27.70 121 1 120 1,368 2,687 1.96 1,378 2 212 2,972 7,475 2.51 2,994 3 176 1,405 3,084 2.19 1,415 4 199 2,804 15,936 5.68 2,825 5 174 3,715 6,513 1.75 3,743 6 139 1,004 1,808 1.80 1,011 7 157 16,529 16,652 1.01 16,652 9 226 - 18,672 - 0 Total 29,917 76,149 30,139 Table 1 : Loss of productivity estimation using measured mile method
  • 21. Leonard Study % Change orders = Change order hours Actual labour hours − change order hours = 12%  37% loss of productivity Productivity loss hours = 64,506 hours x 0.37 = 23,868 hours Claimable amount = 23,868 hours x $40/hour = $954,720 Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Productivity analysis 21 Figure 1 : The effect of change orders on productivity for electrical and mechanical work by Charles A. Leonard
  • 22. Leonard Study 12% change  construction productivity = 0.75  loss of productivity = 25% Productivity loss hours = 64,506 hours x 0.25 = 16,127 hours Claimable amount = 16,127 hours x $40/hour = $645,080 Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Productivity analysis 22 Figure 2 : The effect of change orders on productivity by William Ibbs
  • 23. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Productivity analysis 23 Method Total Cost Measured Mile Leonard study Ibbs adapted study Claimable hours 37,815 34,367 23,868 16,127 Claimable amount $1,512,600 1,374,680 $954,720 $645,080 Productivity 1 1.01 37% loss of productivity 25% loss of productivity Table 2 : Comparison of available methods to measure the loss of productivity
  • 24. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Claim summary 24 Summary of the claimed amounts for the contract dispute: Description Amount ($) Unpaid approved changes 504,662 Unpaid unapproved changes 1,528,412 Loss of profit 36,727 Indirect cost 133,065 Loss of productivity 645,080 Total 2,847,946
  • 25. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Conclusion 25  A lump sum contract of $2,549,130 was awarded for the Sag mill mechanical project.  The Engineer terminated the contract with a total payment of $1,814,598.  The total claim amount of $2,847,946 is submitted by the Contractor.
  • 26. Project overview Scope of work Major problems Delay analysis Damage quantification Productivity analysis Claim summary Conclusion Questions Questions 26

Editor's Notes

  1. Content   Background information Summary Personal resources and goals The product or service The market Sale and marketing plan Management & organisation Development of the business Budgets Financial requirements Appendices