SlideShare a Scribd company logo
1 of 101
Download to read offline
EPC Project Interdependency
and
Work Flow
Our Belief
Now Everyone Can Be Trained
Table Of Contents
Topic Page
Introduction to EPC Project Management 5
EPC Project Management work flow 13
Engineering Document Issuance Purpose 19
Engineering Work Flow 21
Procurement work flow 43
On Shore Project Schedule and Schedule dependency 46
Work Front Concept 48
Advance Work Packaging 52
Sample WBS 65
Piping Engineering as case study 73
Vessel Fabrication Work flow as case study 83
3
4
Don’t be like this…
5
EPC Project Management
- Introduction
6
EPC Project Management
EPC stands for Engineering, Procurement, Construction and
is a prominent form of contracting agreement in the
construction industry.
The engineering and construction contractor will carry out
the detailed engineering design of the project, procure all
the equipment and materials necessary, and then construct
to deliver a functioning facility or asset to their clients.
Companies that deliver EPC Projects are commonly referred
to as EPC Contractors.
The EPC phase of the project is also known as the Execution
phase which normally follows what is know as a FEED or
Front End Engineering Design phase. The FEED is a basic
engineering design used as the basis for the EPC phase.
The FEED can be divided into separate packages covering
different portions of the project. The FEED packages are
used as the basis for bidding on when the client offers the
EPC work to the market.
Under an EPC contract, the contractor designs the
installation, procures the necessary materials and builds the
project, either directly or by of the work.
In some cases, the contractor carries the project risk for
schedule as well as budget in return for a fixed price,
called lump sum LSTK depending on the agreed scope of
work.
EPCM stands for Engineering, Procurement, Construction
Management. This type of contract is different to an EPC
Contract in that the Contractor is not directly involved in
the construction but is responsible for administering the
Construction Contracts.
EPCI stands for Engineering Procurement Construction
and Installation which is a common form of contracting
arrangement in the Offshore Construction Industry. As
opposed to an EPC contract, the offshore facility or vessel
that is constructed has to be transported and installed at
the project location.
EPIC stands for Engineering Procurement Installation
Commissioning is typically a Lump Sum Turn Key (LSTK)
type Contract integrating the responsibility going from the
conception to the final acceptance of one or more
elements of a production system. It can be awarded for
all, or part, of a field development.
7
EPC Project Organization
8
EPC Project Organization
9
Design Procurement
Manufacturing/
Fabrication
Shipment
Installation
Construction &
Erection
Inspection & FAT Hand-Over
10
Engineering in the Project
11
Engineering Discipline
12
EPC Project Management
- Work Flow
13
Engineering work flow concept is required to be fully understand
for someone who involved in the EPC Planning and Activity
Sequencing.
This concept is applied when the EPC level 4 schedule is
developed.
The process of engineering work to produce the required
deliverables depends on not only within the functional
discipline itself but also among the process, mechanical and
piping engineering functions.
Engineering in EPC project is the task of translating a set of
functional requirement into a full set of drawings and
specifications depicting every detail of a facility,
Engineering involves varieties of specialties, which include :
• Process
•Civil and Structure
•Mechanical
•Piping
•Electrical
•Instrumentation
•General Engineering
•Safety
Engineering Work Flow
There are many interdependencies between engineering
documents.
For instance piping routing drawings are issued after the process
diagram Is defined.
Most of the documents will usually issued several times, at
different stages to for review as well as to incorporate the
comments.
Typically a document is first issued for Internal Review (IFR) of the
other disciplines, then to client for comment (IFC), it will be
returned to be incorporated with the client comments and issue
for Approval (IFA), then for construction (IFC) and last once
everything is confirmed and will Approve for Construction (AFC)
14
The entire strategy is dependent on Engineering and
Procurement providing their deliverables to meet
Path of Construction.
Contractor mobilizes based on Engineering forecast
of IFC EWPs (Engineering Work Packages).
15
Engineering Work Flow
Engineering Disciplines
Activity Process
Civil and
Structure
Mechanical Piping Electrical Instrumentation
Diagrams
Geographical
Drawing
Architecture
Drawing
Calculations
Equipment or
material spec,
data sheet &
requisition
Site work spec
Engineering phase is very much concerned with documentation.
16
From Sequential To Concurrent Execution
Engineering Procurement Construction
Engineering
Procurement
Construction
17
Project Execution
The Past: sequential execution
The Present: concurrent execution
18
EPC Project Management
- Engineering Document Issue Purposes
19
Issuing Purpose
FYI For Your Information
IAB Issued For As-Built
ICR Issued For Construction Record
IFA Issued For Approval
IFB Issued For Bid
IFC Issued For Construction
IFD Issued For Design
IFE Issued For Estimate
IFH Issued For Hazop
IFP Issued For Purchase
IFR Issued For Review
IFS Issued For Squad Check
IFU Issued For Use
IFV Issued For Void
RLM Red Line Mark-up
RTS Return To Supplier
SFR Supplier Issued For Review
SFS Supplier Issued For Squad Check
AFC Approved for Construction
20
EPC Project Management
- Engineering Work Flow
21
Engineering Workflow
22Source : Herve Baron Oil & Gas Engineering Guide
slideshare
Engineering Workflow
23Source : Herve Baron Oil & Gas Engineering Guide
slideshare
Engineering Document Review Cycle
Step Review cycle
Rule of credit
Increment% Cumulative%
1 Study and design preparation 5% 5%
2 Issue for review (IFR) 10% 15%
3 Issue for approval (IFA) 20% 35%
4 Issue for construction (IFC) 30% 65%
5 Approved for construction 35% 100%
24
Engineering Document Review Cycle
IFR IFA IFC
P&ID
REVIEW
HAZOP
PIPING MTO
& PO
25
Document Control
Engineering
Client
Vendor
Documents
submitted
to client
Approval/
Comments
Documents
submission Comments
•Client Review cycle. (IFR,IFA,IFC,AFC)
•Client Review duration
•Engineering submission cut-off
•Maintain internal and external baseline
•Vendor information criticality for client
doc approval
•Vendor duration to incorporate the
comments
•Vendor delivery estimation
26
Vendor Data
Engineering is the integrator of the Plant equipment, and is highly dependent on vendor data
27
Engineering Work Flow – Process Design
Process Design
PFDs
H&M balance
P&IDs
Process data sheet
Equipmentspecification
Vendor drawings
Rotating
Pressure vessels
Heat exchangers
Fired equipment
Packages etc.
Layout
Civil
Electrical
Piping
Instrumentation
28
Piping Engineering Flow
PFD
Process
equipment
list
Piping
isometric
drawing IFC
Stress
ok ?
29
3D
Modeling
(General)
1st Model
review
2nd model
review
3rd model
review
3DModel
30
3D
Modeling
(Skid
Project)
1st Model
review (30%)
2nd model
review(60%)
3rd model
review(90%)
3DModel
IFA pipe support dwg
IFA pipe GA dwg
IFA piping plan dwg
IFA structural GA
IFA tubing routing
layout
IFI pipe ISO
IFA Instrumentcable
routing layout
IFA instrument cable
trench &tray layout
IFA Instrument
location
IFA Skid Tie-in report
IFA General
structuraldeflection
& stress analysis
report
IFA Structural GA
dwg
IFC Instrument
locationdwg
IFC pipe GA dwg
Piping Materials
P&IDs1st issue
Plot plan
IFD P&IDs
E&Imain cable
routing
First equipment
vendor dwg
IFC piping ISO
Final piping MTO
31
Skid 3D Modelling – Interdependency
30% PDMS
30% model review
Update PDMS model 30%
Issue close out report
Report review by EPCC
contractor
60% PDMS
60% model review
Update PDMS model 60%
Issue close out report
90% PDMS
90% model review
Update PDMS model 90%
Issue close out 90% report
Report review by EPC
contractor
Receivefinal comment from
EPC contractor
Successor for 60% PDMS (issue close out report)
IFI for piping ISO
IFI [Piping Isometric]
IFA cable routing layout
IFA instrumentationlocation
IFA pipe support drawing
IFA piping GA drawing
IFA piping plan drawing
IFA structural GA drawing
Successor for 90% PDMS (issue close out report)
EPC contractorreview piping GA
EPC contractorreview piping plan
EPCcontractorreview pipe support
EPC contractorreview structural GA
32
Skid 3D Modelling – Piping GA as example
30% PDMS
30% model review
Update PDMS model 30%
Issue close out report
Report review by EPCC
contractor
60% PDMS
60% model review
Update PDMS model 60%
Issue close out report
90% PDMS
90% model review
Update PDMS model 90%
Issue close out 90% report
Report review by EPC
contractor
Receivefinal comment from
EPC contractor
Prepareand Submit IFA Rev.A [Piping GA Drawings]
EPC Contractor Review [Piping GA Drawings]
IncorporateComments & Submit IFC Rev.0 [Piping GA
Drawings]
33
Engineering Work Flow-Process, Mech and Piping
34
Engineering Work Flow –C&S, Mech and Piping
35
Engineering Work Flow – E&I
36
Engineering Work Flow – Instrumentation
•Instrument Index
•Instrument Data sheet
•Instrument Hookup Diagram
•Instrument Loop Diagram
•Instrument I/O List
•Instrument Layout Diagram
•Cause & Effect Diagram
•Cable Schedule Diagram
•Project Interconnection Diagram
37
Engineering Work Flow – Instrumentation
I/O List is a contains list of instrumentation which serve as an input or output of control system. Hence the tag number thatphysically
has a cable which connects to the control system appears on I/O list.
Instrument index is a document containing list of instrument devices within a plant. Instrument index shall include tag number of all
physical instruments
Reference Drawing
P&ID, HMB
Instrument Index
Reference Document
Cause & Effect
I/O Count will determines the required capacity of a system
38
Engineering Work Flow – Instrumentation
Instrument Data Sheet is a document containing specification and information of an instrument device. It specifies general information
of instrument such as tag number identification, service description, location (line number/equipment number), P&ID number or
drawing number reference, process data (if applicable), calibrated range (if applicable), material, performance details (such as accuracy,
linearity – if applicable), hazardous certification (for electrical device), accessories required, etc. The details of information in data sheet
may differ among each types of instrument such as transmitter, switch, gauge, control valve
Instrument Data
Sheet
Reference Drawing
P&ID, HMB,
Reference Document
Instrument specification,
piping specification,
calculation, vendor
catalogue
Once the data sheet completed, it is attached to requisition which to be sent to vendors. Vendors will offer their quotation with various model and
manufacturer among the offers.
Having been considered its technical and commercial aspects, the instrument is purchased. Following the purchase order, vendor will submit
supporting document and drawing. Based on vendor data, instrument data sheet may be updated to accommodate details to make the data sheet
“as-built”.
39
Engineering Work Flow – Instrumentation
Hook-up drawing is a detailed drawing showing mounting and connection of instrument to process lines and corresponding list of
required material.
Hook-up drawing also gives information the requirement of bulk material for each installation. It also details its specification (size, type
and material) and the quantity.
There are two types of hook-up drawing:
1. Process Hook-Up
This hook-up drawing contains typical installations for instrument which connects to the process
1. Pneumatic Hook-Up
Hookup Drawing
Reference Drawing
P&ID, Installation Detail
Specification, Piping
Specification
40
Engineering Work Flow – Instrumentation
Instrument Layout is also known as instrument location plan. This drawing shows the exact position of each instruments with reference
to plant layout.
The point indication of instrument position and its mounting stand where instrument to be mounted and process tap
location.
Often the tap location and the instrument is separated quite distant. In some project, it is not mandatory to show the
process tap location
Instrument Layout
Reference Drawing
P&ID, Piping
Plan,piping GA and
ISO
41
Engineering Work Flow – Instrumentation
Cable Schedule is a document containing list of instrument cables to install, cable type, length, origin, destination and route.
Reference Drawing
Instrument Cable Layout,
Interconnection block
diagram
Cable Schedule
Reference Document
Instrument Index / I/O
List
42
EPC Project Management
- Procurement Work Flow
43
Procurement Work Flow
Inquiry
issued to
bidders
Tender
Evaluation
and client
approval
Purchasing
request
created
Purchasing
order
placed
Received
Key vendor
drawings
Approved
key vendor
drawings
Fabrication
FAT or Final
inspection
finished
Ex-work
Deliveryat
site
General procurement work flow and how rule of credit being assigned to each step.
44
Procurement Work Flow
Procurement progress calculation excel sheets are available for download in ignite.com
Progress tracking sheet for procurement work flow
45
Typical On-Shore Project Schedule and
Dependencies
46
TypicalLevel1–On-ShoreProjectSchedule
47
Work front Concept
48
Work Front
Engineering progress is commonly measured by assigning a weight, usually the required number of required manhours, to each
task/deliverable. Once the task is performed/ the deliverable is issued, the corresponding manhours are earned.
The earned progress divided by the total number of manhours gives the % progress.
As each engineering task/deliverable is scheduled at certain dates, it is possible to anticipate the progress that should beearned at a
given date. It is the planned progress.
At regular period, usually on a monthly basis, the actual progress of each activity/deliverable is measured against the planned progress.
An actual progress less than the planned progress might show a lack of resources and a need for increased mobilization to getback on
plan, following a (re-)forecast progress curve.
Although such progress measure is commonly used, it could be deceiving. It indeed reflects rather well the progress of engineering on
its own but not how well is engineering supporting the Project schedule.
Let’s consider that engineering must issue 2 material requisitions, an urgent one for a Long Lead Item and another one which is
required later on. Engineering will earn progress whatever requisition it issues, even if putting the Project in delay by issuing the non
urgent requisition first.
One sees that the above measure of progress alone is insufficient. It must be complemented by monitoring that important Milestones
are met.
These Milestones are first of all, the ones associated with the issue of the Requisition for the equipment. Long lead items have
naturally to be purchased early. All equipment and packages also need to be purchased as early as their technical definition allows.
Indeed, engineering development is highly dependent on information from vendors. The sooner the purchase orders are placed the
sooner the vendor information will be available.
Next come the Milestones associated with Bulk Material Procurement to support construction, such as the Piping MTO and the
Structural Steel MTO (for an off-shore Project).
49
Work Front
Then come the Milestones associated with Construction. These are the IFC Plot Plan, a pre-requisite to start any site work, and the IFC
P&IDs, a pre-requisite to the issue of Piping isometrics. The 50% IFC Piping isometric milestone comes next, which typically falls half way
through the Project, as ensuing works, such as pre-fab and erection have a rather incompressible duration, due to site constraints
(capacity of pre-fab shop, space constraints for erection limiting the progress).
Even if engineering deliveries are in sequence, the above engineering progress measure might still be deceiving, as it will only reflect
the amount of engineering work completed and not the workfront made available to construction.
Let’s consider for instance that two foundations are to be cast. The first one is a very large foundation and the second one a small one.
Issuing the drawing of either the large or small foundation will earn engineering the same progress, although it will open quite a
different workfront to Construction.
One sees the necessity to measure the issued Workfront.
In the case of foundations, for instance, this will be done by monitoring the cumulative quantity of concrete (m3) of all issued IFC
foundation drawings.
Producing an S curve, such as the one shown in next slide, showing both planned and actually issued quantities will give a true picture of
how well engineering is supporting civil works.
One will similarly monitor, for an On-Shore project, the cumulative quantity of steel (tons) of issued IFC Structural drawings.
The cumulative tons (or dia inch) of IFC issued Piping isometrics will show the available piping workfront.
Such progress curves, showing the actual versus planned available workfronts are instrumental to monitor engineering progress, identify
shortage and take corrective actions (increase mobilisation).
It is not perfect however and can still be deceiving, in case of out-of-sequence issues: engineering may have issued drawings
representing significant quantities, but that does not generate construction workfront as such works can not be performed at this time
(due to lack of access or pre-requisite for another work to be completed before, for instance).
50
Work Front
Construction work-front planning and forecasting processes allow Materials to gather construction work package requirements and
material situation throughout the supply chain with appropriate feedback into the EP process 51
Advanced Work Packaging
52
Work Face Planning
Path of
Construction
EWP CWP
FIWPs
500 – 1000mhrs
Construction drives Engineering & Procurement
EWPs(Engineering Work Packages) are Engineering deliverables
CWPs (Construction Work Packages)& FIWPs (Field Installation Work Packages) are Construction deliverables
System turn-over drives Construction
53
Work Face Planning
EWPs (Engineering
Work Packages) set
the precedence for
Construction work.
Using the P&IDs (for item count) and Piping Layout Drawings (for lengths) a preliminary list for piping material requirement generated
which known as piping MTO (piping material takeoffs)
The GA drawing used for pipe erection while the piping ISO are used for pipe prefabrication.
54
Planned Path in Construction Work
Engineering Work Package (EWP)
Procurement Package (PP)
Supplier Equipment / material
Construction Work Package (CWP)
9 weeks lag
Work commences
Equipment / Material arrives prior
to work commencingPurchase Order to supplier
Engineering’s Bill of Material
55
Planned Path in Construction Work
Engineering Work Package (EWP)
Procurement Package (PP)
Supplier Equipment / material
Construction Work Package (CWP)
9 weeks lag
Work commences
Equipment / Material arrives prior
to work commencingPurchase Order to supplier
Engineering’s Bill of Material
Forecasting to meet scheduled IFC
Contractor resource mobilized
1 2
56
Constrained Path of Construction
Engineering Work Package (EWP)
Procurement Package (PP)
Supplier Equipment / material
Construction Work Package (CWP)
9 weeks lag
Work commences
Equipment / Material arrives prior
to work commencingPurchase Order to supplier
Contractor resource mobilized2
Vendor Data needed to complete
EW deliveredlate or incomplete
Lag gets squeezed CWP starts late
57
Constrained Path of Construction
Engineering Work Package (EWP)
Procurement Package (PP)
Supplier Equipment / material
Construction Work Package (CWP)
Work commences
Purchase Order to supplier
Contractor resource mobilized2
How do we improve this interface?
58
Constrained Path of Construction
Engineering Work Package (EWP) Construction Work Package (CWP)
Work commences
Delay in Engineering will cause lag gets squeezed CWP
starts late
Model Review causes late changes
MTO can’t be created
No IFC or AFC status for P&IDs
Specification is not complete
Client or EPC take longer time for document review and caused delay
How are these mitigated /
eliminated?
It is important to knows
the work sequence in order
to plan for Construction
Work Package.
59
Engineering Work Package Progress
Ex : Piping Work Package.
2 P&IDs
3 Requisitions
4 Specifications.
1 3D modelling development
5 Pipe Stress analysis
6 Calculations
60
Forecasting Scenario
Ex : Piping Work Package.
Next Weekly Forecast - EWP slips one week
EWP is forecast to meet scheduled IFC
Next Weekly Forecast - EWP slips another week
Contractor plans resource mobilization
Contractor tries to mitigate
Delay in Construction work and recovery needed
Delay in Engineering Work
Package approval in return cause
delay in construction work.
61
Potential Work Flow and Rule of Credit for Piping
Step Work Flow Increment % Cumulative %
1 EWP ID’d and mapped to CWP 5% 5%
2 Initial scope identified (line numbers) 15% 20%
3 Preliminary equipment data received 5% 25%
4 Initial routing of lines established 20% 45%
5 Initial bulk material (BOM) to supply chain 10% 55%
6 Piping studies rec’d for critical lines: 5% 60%
7 Final vendor data received 10% 70%
8 Final routings completed 5% 75%
9 P&IDs and LDT issued IFC 5% 80%
10 Stress analysis for large bore completed 5% 85%
11 BOM completed 5% 90%
12 EWP c/w all drawings/specs issued IFC 5% 95%
13 EWP accepted by Construction AFC 5% 100%
62
What Makes Forecasting is a Challenge
Challenges
EWP process has many steps to get to IFC
The rules of credit (if they exist) are either not known or not utilized.
EWP development held back by outside influence
(e.g., Systems, Vendor Data or Owner Decisions)
Construction mobilizes resources based on forecast completions of EWP IFC
Engineering forced to release partial EWPs or releases EWPs out of sequence or
EWPs with HOLDS
EWP releases continue to slip but construction is now mobilized
63
Engineering Work Package and Construction Work Package
CWP
Scope of Work
IFC drwgs Eng.Specs&Stds
Equipment/Materials
Vendor info
Quality Instructions
Regulatory
approvals/permits
Turnover Documents
Schedule (Level 5)
Engineering
Long Leads RAS dates
Material Mgmt Expediting
Transportation Special
Requirements
Procurement
HSE/Safety
Manpower req.
Level 4 Schedule
QA/QC
Construction Tools/Equip
Heavy Lift Plans
Scaffold
Waste Mgmt
Interfaces/Coordination
Construction
64
Sample WBS
65
WBS Structure
66
WBS Structure
67
Sample WBS for Electrical Construction
68
Sample Pipeline Construction Project WBS for Refinery/Chemical Plant
69
Sample Pipeline Construction Project WBS for Refinery/Chemical Plant
Sample WBS for piping construction project for a refinery or chemical plant may be organized as the following.
It is worth to be organized by location wise (i.e. platform and pipe rack, platform and equipment around piping) prior to “Phase” WBS.
Timely completion of piping construction is not only depending on timely receiving of engineering drawings and materials from Owner/EPC
contractor but timely availability of the infrastructure should also be addressed. Sometime it refers to work front availability.
Developing WBS is mainly depending on the project scope. It should be defined according to the project specific as every project is different,
for instance, “Demolishing” WBS may also be added under “Phase” level priority to “Installation” WBS if your project scope involved a
considerable amount of piping demolishing scope. “Above Ground” and “Under Ground” WBS can be left in case no underground piping work
is
included in the project.
(1) Level 1: Plant Unit, e.g. Utility Unit, Ethylene Theatre Unit, etc.
(2) Level 2: Area within a Unit, for instance, Area ABC, Area XYZ. Area demarcation is marked for a group of process piping on above
ground and underground.
(3) Level 3: Height. This is to segregate pipe work on the above ground and underground.
(4) Level 4: Location where pipeline is run, for instance, piping on and around pipe rack, equipment and equipment platform.
(5) Level 5: Phase, e.g. Fabrication, Installation (field erection, NDT) and pre-commissioning (hydro testing, air flushing, chemical cleaning
etc.)
Note :
“Common” WBS name refers to common location where interconnecting piping is running between the pipe rack and equipment
or equipment platform. Having a clear definition of what is and what is not meant by “Common” is important
70
Sample Fuel Tank WBS
ExternalFloating Roof Tank
0
Foundation work
1.0
Field erection works
2.0
Tank Bottom
2.1
Shell side
2.2
Roof works
2.3
Tank accessories
installation
2.4
Fire fighting
works
2.5
Bottom plates
installation
2.1.1
Final coating
2.1.2
Shell plates
installation
2.2.1
Nozzles and man
ways installation
2.2.2
Final Coating
2.2.3
Center deck plate
installation
2.3.1
Drainagepiping
2.3.2
Final Coating
2.3.3
Internal
Appurtenances
2.4.1
External
accessories
2.4.2
Foam piping
installation
2.5.1
Final coating
2.5.2
71
Sample Fuel Tank WBS
72
Piping Discipline
( Piping Fabrication, Tie-in and Commissioning )
73
Piping Tie-in Process
Normally, piping tie-in installation scope is involved in revamp project only. The progress tracking system for tie-in work includes Tie-in
Tracker Sheet and Progress tracking sheet.
Tie-in numbers against the Isometric drawings and work packages are listed in the tracker sheet. The tie-in type (Bolt-up, cut and
weld, hot tap, cold tap and threaded are typical tie-in types in process industry), project area or system name and installed dates are
also included in the tracker sheet.
To develop Progress Tracking Sheet for overall Isometric drawings, the following work steps and weight factor percentages areutilized.
1. Preparation ( Scaffold erection if required/remove insulation if required) -20%
2. Tie-in work (Bolt up/cut & weld/hot tap/cold tap/threaded) -70%
3. Inspection (Sign QC document, example : flange make up check list) -10%
The Progress Tracking System for Pipeline Erection Work
Developing procedure of progress tracking system for pipeline erection work is the same as piping fabrication work except work steps
and weight factor percentages. To do that, replace the following work steps and weight factor percentages with the existing ones and
rearrange the formulae.
1. Material at Erection area - 5%
2. Piping Laying -20%
3. Preparation(align/tack weld) -20%
4. Full Welding Execution - 40%
5. Non Destructive Examination - 5%
6. Pipe Support Erection -15%
7. Final Inspection - 5%
74
Commissioning Test package and Tie-In
System
Commisionning
Piping Fabrication
Piping Tie-In
Piping Test Package
75
Piping Tie-in Work Sequence
General piping tie-in work flow and how rule of credit being assigned to each step.
Weld map
drawing
preparation
Withdrew
material
Welding
preparation
Spool
assemble and
tack weld
Welding NDT
Surface
preparation
and coating
Final
inspection
Deliveryat
site
76
Piping Hydrotest Work Sequence
Preparation Done Testing Reinstated Clear Punch list
General hydrotest work flow and how rule of credit being assigned to each step.
77
Commissioning Test package and Tie-In
Test Package for Pre- CommissioningTie-In List
78
Piping Tie-In
79
Special Pipe Support Drawing
80
Piping Pre-Fab Drawing
81
Piping ISO Drawing
82
Vessel Fabrication
83
Vessel Fabrication Work Flow
Exchanger Vessel
Fit Up (Pre-
Fabrication)
Exchanger Vessel
Weld Out
(Assembly)
Tubesheet Fit Up
/ Weld Out
Testing (NDE,
Hydro
Painting Ex-work
84
Vessel Fabrication Work Flow
Shell Side Fabrication
· Plate marking/cutting/ beveling and inspection
· Shell plate rolling work
· Longitudinalsteel (LS) fit-up and inspection
· LS welding and inspection (NDE)
· Circumferencesteel (CS) fit-up and inspection
· CS welding and inspection (NDE)
Inlet and outlet nozzles fabrication
· Pipe marking/cutting / beveling and inspection
· Fit-up and welding of flanges and pipes
· Inspection for nozzles to flange joints (NDE)
Nozzle Attachmentsto Dished Head
· Marking of nozzle location on dished head
· Cutting/opening/ beveling and inspection
· Fit-up and tack weld nozzle to dished head
· Inspection for tack welding (if required)
· Full weld - nozzle assembly with dished head
· Inspection for nozzle to dished head welds (NDE)
Nozzles and other accessoriesto Shell
· Marking of nozzles location
· Cutting/opening/ beveling and Inspection
· Fit-up and tack weld nozzle assembly to shell/inspection
· Full weld - nozzle assembly with shell
· Inspection for nozzle to shell side welds (NDE)
· Fit up and welding for instrument attachments
· Fit up and welding for lifting lugs
Dished head Installation
· Fit up and tack weld/Inspection – Dished head to shell
· Full circumference welding
· Inspection for full welds (NDE)
Inspection(Hydro-testing)
· Hydrostatic testing
· Draining/dryingand final inspection
Blastingand Painting
· Blasting/Inspection
· Primer/Finalcoating/Inspection
85
Vessel Fabrication Case Study
86
Vessel Fabrication Process
87
Plate Cutting
88
Plate Rolling
89
Longitudinal Seam Welding
90
Longitudinal Seam Welding
91
Can to Can Fit-up
92
Can to Can Fit-up
93
Can to Can Fit-up
94
Tack Weld
95
Weld Inside Circumference of Can
96
Weld Outside Circumference of Can
97
Weld Outside Circumference of Can
98
NDT
99
The End
101

More Related Content

What's hot

Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionJaswin Sood
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparisonhelensuni
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsNam N.N Tran M.Eng, PMP
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draftignitetribes
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Modelavnishnarula86
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & ControlsProcept Associates
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...John Buchovecky
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Philippe Porta
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
 
Why EPC
Why EPCWhy EPC
Why EPCvivektmax
 

What's hot (20)

Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Epc overview
Epc  overviewEpc  overview
Epc overview
 
EPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A ComparisonEPC v EPCM Contracting- A Comparison
EPC v EPCM Contracting- A Comparison
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Engineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projectsEngineering, procurement and construction (EPC) projects
Engineering, procurement and construction (EPC) projects
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Epc contractor
Epc contractorEpc contractor
Epc contractor
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
Why EPC
Why EPCWhy EPC
Why EPC
 

Similar to Epc project interdepency and Work Flow- promo

Session 25 - Documentation
Session 25 - DocumentationSession 25 - Documentation
Session 25 - DocumentationVidyaIA
 
Project Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfProject Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfMOHDFIRRDHAUSBINMOHD
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr Bhavana Deshpande
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction TeamsMOHDFIRRDHAUSBINMOHD
 
Project Engineer
Project EngineerProject Engineer
Project EngineerVikram Singh
 
CURRICULUM VITAE-1 (2)
CURRICULUM VITAE-1 (2)CURRICULUM VITAE-1 (2)
CURRICULUM VITAE-1 (2)Puneet Dogra
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr. Pramod Deshpande
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Dr. Mohamed A. El-Reedy
 
Engineering Quality Process
Engineering Quality ProcessEngineering Quality Process
Engineering Quality ProcessEarl Schneider
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanJames Zhang (Chi, Zhang)
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...CCT International
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedEnergy Construction Forum
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringCCT International
 
CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05Paula Intra Lohit
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2Jerry Bauers
 

Similar to Epc project interdepency and Work Flow- promo (20)

Mepl presentation
Mepl presentationMepl presentation
Mepl presentation
 
Documentation
DocumentationDocumentation
Documentation
 
Session 25 - Documentation
Session 25 - DocumentationSession 25 - Documentation
Session 25 - Documentation
 
Project Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfProject Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdf
 
COE
COECOE
COE
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction Teams
 
Piping Design Engineering
Piping Design EngineeringPiping Design Engineering
Piping Design Engineering
 
Project Engineer
Project EngineerProject Engineer
Project Engineer
 
CURRICULUM VITAE-1 (2)
CURRICULUM VITAE-1 (2)CURRICULUM VITAE-1 (2)
CURRICULUM VITAE-1 (2)
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template Egyps 2017 technical conference power point template
Egyps 2017 technical conference power point template
 
Engineering Quality Process
Engineering Quality ProcessEngineering Quality Process
Engineering Quality Process
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
 
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons LearnedMajor CAPEX Project Success Assurance-Best Practices and Lessons Learned
Major CAPEX Project Success Assurance-Best Practices and Lessons Learned
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
 
CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 

More from ignitetribes

Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Codingignitetribes
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectignitetribes
 
Headed Towards Burnout
Headed Towards BurnoutHeaded Towards Burnout
Headed Towards Burnoutignitetribes
 
The Leadership Qualities of Elon Musk
The Leadership Qualities of Elon MuskThe Leadership Qualities of Elon Musk
The Leadership Qualities of Elon Muskignitetribes
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganignitetribes
 
101 toughest interviews_questions
101 toughest interviews_questions101 toughest interviews_questions
101 toughest interviews_questionsignitetribes
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technipignitetribes
 
Technip case study
Technip case studyTechnip case study
Technip case studyignitetribes
 
Project planning and control training with lego
Project planning and control training with legoProject planning and control training with lego
Project planning and control training with legoignitetribes
 

More from ignitetribes (9)

Primavera Activity ID Coding
Primavera Activity ID CodingPrimavera Activity ID Coding
Primavera Activity ID Coding
 
Sample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_projectSample wbs for_upstream_epcic_project
Sample wbs for_upstream_epcic_project
 
Headed Towards Burnout
Headed Towards BurnoutHeaded Towards Burnout
Headed Towards Burnout
 
The Leadership Qualities of Elon Musk
The Leadership Qualities of Elon MuskThe Leadership Qualities of Elon Musk
The Leadership Qualities of Elon Musk
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
 
101 toughest interviews_questions
101 toughest interviews_questions101 toughest interviews_questions
101 toughest interviews_questions
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
Technip case study
Technip case studyTechnip case study
Technip case study
 
Project planning and control training with lego
Project planning and control training with legoProject planning and control training with lego
Project planning and control training with lego
 

Recently uploaded

Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 

Recently uploaded (20)

Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 

Epc project interdepency and Work Flow- promo

  • 2. Our Belief Now Everyone Can Be Trained
  • 3. Table Of Contents Topic Page Introduction to EPC Project Management 5 EPC Project Management work flow 13 Engineering Document Issuance Purpose 19 Engineering Work Flow 21 Procurement work flow 43 On Shore Project Schedule and Schedule dependency 46 Work Front Concept 48 Advance Work Packaging 52 Sample WBS 65 Piping Engineering as case study 73 Vessel Fabrication Work flow as case study 83 3
  • 4. 4
  • 5. Don’t be like this… 5
  • 6. EPC Project Management - Introduction 6
  • 7. EPC Project Management EPC stands for Engineering, Procurement, Construction and is a prominent form of contracting agreement in the construction industry. The engineering and construction contractor will carry out the detailed engineering design of the project, procure all the equipment and materials necessary, and then construct to deliver a functioning facility or asset to their clients. Companies that deliver EPC Projects are commonly referred to as EPC Contractors. The EPC phase of the project is also known as the Execution phase which normally follows what is know as a FEED or Front End Engineering Design phase. The FEED is a basic engineering design used as the basis for the EPC phase. The FEED can be divided into separate packages covering different portions of the project. The FEED packages are used as the basis for bidding on when the client offers the EPC work to the market. Under an EPC contract, the contractor designs the installation, procures the necessary materials and builds the project, either directly or by of the work. In some cases, the contractor carries the project risk for schedule as well as budget in return for a fixed price, called lump sum LSTK depending on the agreed scope of work. EPCM stands for Engineering, Procurement, Construction Management. This type of contract is different to an EPC Contract in that the Contractor is not directly involved in the construction but is responsible for administering the Construction Contracts. EPCI stands for Engineering Procurement Construction and Installation which is a common form of contracting arrangement in the Offshore Construction Industry. As opposed to an EPC contract, the offshore facility or vessel that is constructed has to be transported and installed at the project location. EPIC stands for Engineering Procurement Installation Commissioning is typically a Lump Sum Turn Key (LSTK) type Contract integrating the responsibility going from the conception to the final acceptance of one or more elements of a production system. It can be awarded for all, or part, of a field development. 7
  • 11. Engineering in the Project 11
  • 13. EPC Project Management - Work Flow 13
  • 14. Engineering work flow concept is required to be fully understand for someone who involved in the EPC Planning and Activity Sequencing. This concept is applied when the EPC level 4 schedule is developed. The process of engineering work to produce the required deliverables depends on not only within the functional discipline itself but also among the process, mechanical and piping engineering functions. Engineering in EPC project is the task of translating a set of functional requirement into a full set of drawings and specifications depicting every detail of a facility, Engineering involves varieties of specialties, which include : • Process •Civil and Structure •Mechanical •Piping •Electrical •Instrumentation •General Engineering •Safety Engineering Work Flow There are many interdependencies between engineering documents. For instance piping routing drawings are issued after the process diagram Is defined. Most of the documents will usually issued several times, at different stages to for review as well as to incorporate the comments. Typically a document is first issued for Internal Review (IFR) of the other disciplines, then to client for comment (IFC), it will be returned to be incorporated with the client comments and issue for Approval (IFA), then for construction (IFC) and last once everything is confirmed and will Approve for Construction (AFC) 14
  • 15. The entire strategy is dependent on Engineering and Procurement providing their deliverables to meet Path of Construction. Contractor mobilizes based on Engineering forecast of IFC EWPs (Engineering Work Packages). 15
  • 16. Engineering Work Flow Engineering Disciplines Activity Process Civil and Structure Mechanical Piping Electrical Instrumentation Diagrams Geographical Drawing Architecture Drawing Calculations Equipment or material spec, data sheet & requisition Site work spec Engineering phase is very much concerned with documentation. 16
  • 17. From Sequential To Concurrent Execution Engineering Procurement Construction Engineering Procurement Construction 17
  • 18. Project Execution The Past: sequential execution The Present: concurrent execution 18
  • 19. EPC Project Management - Engineering Document Issue Purposes 19
  • 20. Issuing Purpose FYI For Your Information IAB Issued For As-Built ICR Issued For Construction Record IFA Issued For Approval IFB Issued For Bid IFC Issued For Construction IFD Issued For Design IFE Issued For Estimate IFH Issued For Hazop IFP Issued For Purchase IFR Issued For Review IFS Issued For Squad Check IFU Issued For Use IFV Issued For Void RLM Red Line Mark-up RTS Return To Supplier SFR Supplier Issued For Review SFS Supplier Issued For Squad Check AFC Approved for Construction 20
  • 21. EPC Project Management - Engineering Work Flow 21
  • 22. Engineering Workflow 22Source : Herve Baron Oil & Gas Engineering Guide slideshare
  • 23. Engineering Workflow 23Source : Herve Baron Oil & Gas Engineering Guide slideshare
  • 24. Engineering Document Review Cycle Step Review cycle Rule of credit Increment% Cumulative% 1 Study and design preparation 5% 5% 2 Issue for review (IFR) 10% 15% 3 Issue for approval (IFA) 20% 35% 4 Issue for construction (IFC) 30% 65% 5 Approved for construction 35% 100% 24
  • 25. Engineering Document Review Cycle IFR IFA IFC P&ID REVIEW HAZOP PIPING MTO & PO 25
  • 26. Document Control Engineering Client Vendor Documents submitted to client Approval/ Comments Documents submission Comments •Client Review cycle. (IFR,IFA,IFC,AFC) •Client Review duration •Engineering submission cut-off •Maintain internal and external baseline •Vendor information criticality for client doc approval •Vendor duration to incorporate the comments •Vendor delivery estimation 26
  • 27. Vendor Data Engineering is the integrator of the Plant equipment, and is highly dependent on vendor data 27
  • 28. Engineering Work Flow – Process Design Process Design PFDs H&M balance P&IDs Process data sheet Equipmentspecification Vendor drawings Rotating Pressure vessels Heat exchangers Fired equipment Packages etc. Layout Civil Electrical Piping Instrumentation 28
  • 31. 3D Modeling (Skid Project) 1st Model review (30%) 2nd model review(60%) 3rd model review(90%) 3DModel IFA pipe support dwg IFA pipe GA dwg IFA piping plan dwg IFA structural GA IFA tubing routing layout IFI pipe ISO IFA Instrumentcable routing layout IFA instrument cable trench &tray layout IFA Instrument location IFA Skid Tie-in report IFA General structuraldeflection & stress analysis report IFA Structural GA dwg IFC Instrument locationdwg IFC pipe GA dwg Piping Materials P&IDs1st issue Plot plan IFD P&IDs E&Imain cable routing First equipment vendor dwg IFC piping ISO Final piping MTO 31
  • 32. Skid 3D Modelling – Interdependency 30% PDMS 30% model review Update PDMS model 30% Issue close out report Report review by EPCC contractor 60% PDMS 60% model review Update PDMS model 60% Issue close out report 90% PDMS 90% model review Update PDMS model 90% Issue close out 90% report Report review by EPC contractor Receivefinal comment from EPC contractor Successor for 60% PDMS (issue close out report) IFI for piping ISO IFI [Piping Isometric] IFA cable routing layout IFA instrumentationlocation IFA pipe support drawing IFA piping GA drawing IFA piping plan drawing IFA structural GA drawing Successor for 90% PDMS (issue close out report) EPC contractorreview piping GA EPC contractorreview piping plan EPCcontractorreview pipe support EPC contractorreview structural GA 32
  • 33. Skid 3D Modelling – Piping GA as example 30% PDMS 30% model review Update PDMS model 30% Issue close out report Report review by EPCC contractor 60% PDMS 60% model review Update PDMS model 60% Issue close out report 90% PDMS 90% model review Update PDMS model 90% Issue close out 90% report Report review by EPC contractor Receivefinal comment from EPC contractor Prepareand Submit IFA Rev.A [Piping GA Drawings] EPC Contractor Review [Piping GA Drawings] IncorporateComments & Submit IFC Rev.0 [Piping GA Drawings] 33
  • 34. Engineering Work Flow-Process, Mech and Piping 34
  • 35. Engineering Work Flow –C&S, Mech and Piping 35
  • 36. Engineering Work Flow – E&I 36
  • 37. Engineering Work Flow – Instrumentation •Instrument Index •Instrument Data sheet •Instrument Hookup Diagram •Instrument Loop Diagram •Instrument I/O List •Instrument Layout Diagram •Cause & Effect Diagram •Cable Schedule Diagram •Project Interconnection Diagram 37
  • 38. Engineering Work Flow – Instrumentation I/O List is a contains list of instrumentation which serve as an input or output of control system. Hence the tag number thatphysically has a cable which connects to the control system appears on I/O list. Instrument index is a document containing list of instrument devices within a plant. Instrument index shall include tag number of all physical instruments Reference Drawing P&ID, HMB Instrument Index Reference Document Cause & Effect I/O Count will determines the required capacity of a system 38
  • 39. Engineering Work Flow – Instrumentation Instrument Data Sheet is a document containing specification and information of an instrument device. It specifies general information of instrument such as tag number identification, service description, location (line number/equipment number), P&ID number or drawing number reference, process data (if applicable), calibrated range (if applicable), material, performance details (such as accuracy, linearity – if applicable), hazardous certification (for electrical device), accessories required, etc. The details of information in data sheet may differ among each types of instrument such as transmitter, switch, gauge, control valve Instrument Data Sheet Reference Drawing P&ID, HMB, Reference Document Instrument specification, piping specification, calculation, vendor catalogue Once the data sheet completed, it is attached to requisition which to be sent to vendors. Vendors will offer their quotation with various model and manufacturer among the offers. Having been considered its technical and commercial aspects, the instrument is purchased. Following the purchase order, vendor will submit supporting document and drawing. Based on vendor data, instrument data sheet may be updated to accommodate details to make the data sheet “as-built”. 39
  • 40. Engineering Work Flow – Instrumentation Hook-up drawing is a detailed drawing showing mounting and connection of instrument to process lines and corresponding list of required material. Hook-up drawing also gives information the requirement of bulk material for each installation. It also details its specification (size, type and material) and the quantity. There are two types of hook-up drawing: 1. Process Hook-Up This hook-up drawing contains typical installations for instrument which connects to the process 1. Pneumatic Hook-Up Hookup Drawing Reference Drawing P&ID, Installation Detail Specification, Piping Specification 40
  • 41. Engineering Work Flow – Instrumentation Instrument Layout is also known as instrument location plan. This drawing shows the exact position of each instruments with reference to plant layout. The point indication of instrument position and its mounting stand where instrument to be mounted and process tap location. Often the tap location and the instrument is separated quite distant. In some project, it is not mandatory to show the process tap location Instrument Layout Reference Drawing P&ID, Piping Plan,piping GA and ISO 41
  • 42. Engineering Work Flow – Instrumentation Cable Schedule is a document containing list of instrument cables to install, cable type, length, origin, destination and route. Reference Drawing Instrument Cable Layout, Interconnection block diagram Cable Schedule Reference Document Instrument Index / I/O List 42
  • 43. EPC Project Management - Procurement Work Flow 43
  • 44. Procurement Work Flow Inquiry issued to bidders Tender Evaluation and client approval Purchasing request created Purchasing order placed Received Key vendor drawings Approved key vendor drawings Fabrication FAT or Final inspection finished Ex-work Deliveryat site General procurement work flow and how rule of credit being assigned to each step. 44
  • 45. Procurement Work Flow Procurement progress calculation excel sheets are available for download in ignite.com Progress tracking sheet for procurement work flow 45
  • 46. Typical On-Shore Project Schedule and Dependencies 46
  • 49. Work Front Engineering progress is commonly measured by assigning a weight, usually the required number of required manhours, to each task/deliverable. Once the task is performed/ the deliverable is issued, the corresponding manhours are earned. The earned progress divided by the total number of manhours gives the % progress. As each engineering task/deliverable is scheduled at certain dates, it is possible to anticipate the progress that should beearned at a given date. It is the planned progress. At regular period, usually on a monthly basis, the actual progress of each activity/deliverable is measured against the planned progress. An actual progress less than the planned progress might show a lack of resources and a need for increased mobilization to getback on plan, following a (re-)forecast progress curve. Although such progress measure is commonly used, it could be deceiving. It indeed reflects rather well the progress of engineering on its own but not how well is engineering supporting the Project schedule. Let’s consider that engineering must issue 2 material requisitions, an urgent one for a Long Lead Item and another one which is required later on. Engineering will earn progress whatever requisition it issues, even if putting the Project in delay by issuing the non urgent requisition first. One sees that the above measure of progress alone is insufficient. It must be complemented by monitoring that important Milestones are met. These Milestones are first of all, the ones associated with the issue of the Requisition for the equipment. Long lead items have naturally to be purchased early. All equipment and packages also need to be purchased as early as their technical definition allows. Indeed, engineering development is highly dependent on information from vendors. The sooner the purchase orders are placed the sooner the vendor information will be available. Next come the Milestones associated with Bulk Material Procurement to support construction, such as the Piping MTO and the Structural Steel MTO (for an off-shore Project). 49
  • 50. Work Front Then come the Milestones associated with Construction. These are the IFC Plot Plan, a pre-requisite to start any site work, and the IFC P&IDs, a pre-requisite to the issue of Piping isometrics. The 50% IFC Piping isometric milestone comes next, which typically falls half way through the Project, as ensuing works, such as pre-fab and erection have a rather incompressible duration, due to site constraints (capacity of pre-fab shop, space constraints for erection limiting the progress). Even if engineering deliveries are in sequence, the above engineering progress measure might still be deceiving, as it will only reflect the amount of engineering work completed and not the workfront made available to construction. Let’s consider for instance that two foundations are to be cast. The first one is a very large foundation and the second one a small one. Issuing the drawing of either the large or small foundation will earn engineering the same progress, although it will open quite a different workfront to Construction. One sees the necessity to measure the issued Workfront. In the case of foundations, for instance, this will be done by monitoring the cumulative quantity of concrete (m3) of all issued IFC foundation drawings. Producing an S curve, such as the one shown in next slide, showing both planned and actually issued quantities will give a true picture of how well engineering is supporting civil works. One will similarly monitor, for an On-Shore project, the cumulative quantity of steel (tons) of issued IFC Structural drawings. The cumulative tons (or dia inch) of IFC issued Piping isometrics will show the available piping workfront. Such progress curves, showing the actual versus planned available workfronts are instrumental to monitor engineering progress, identify shortage and take corrective actions (increase mobilisation). It is not perfect however and can still be deceiving, in case of out-of-sequence issues: engineering may have issued drawings representing significant quantities, but that does not generate construction workfront as such works can not be performed at this time (due to lack of access or pre-requisite for another work to be completed before, for instance). 50
  • 51. Work Front Construction work-front planning and forecasting processes allow Materials to gather construction work package requirements and material situation throughout the supply chain with appropriate feedback into the EP process 51
  • 53. Work Face Planning Path of Construction EWP CWP FIWPs 500 – 1000mhrs Construction drives Engineering & Procurement EWPs(Engineering Work Packages) are Engineering deliverables CWPs (Construction Work Packages)& FIWPs (Field Installation Work Packages) are Construction deliverables System turn-over drives Construction 53
  • 54. Work Face Planning EWPs (Engineering Work Packages) set the precedence for Construction work. Using the P&IDs (for item count) and Piping Layout Drawings (for lengths) a preliminary list for piping material requirement generated which known as piping MTO (piping material takeoffs) The GA drawing used for pipe erection while the piping ISO are used for pipe prefabrication. 54
  • 55. Planned Path in Construction Work Engineering Work Package (EWP) Procurement Package (PP) Supplier Equipment / material Construction Work Package (CWP) 9 weeks lag Work commences Equipment / Material arrives prior to work commencingPurchase Order to supplier Engineering’s Bill of Material 55
  • 56. Planned Path in Construction Work Engineering Work Package (EWP) Procurement Package (PP) Supplier Equipment / material Construction Work Package (CWP) 9 weeks lag Work commences Equipment / Material arrives prior to work commencingPurchase Order to supplier Engineering’s Bill of Material Forecasting to meet scheduled IFC Contractor resource mobilized 1 2 56
  • 57. Constrained Path of Construction Engineering Work Package (EWP) Procurement Package (PP) Supplier Equipment / material Construction Work Package (CWP) 9 weeks lag Work commences Equipment / Material arrives prior to work commencingPurchase Order to supplier Contractor resource mobilized2 Vendor Data needed to complete EW deliveredlate or incomplete Lag gets squeezed CWP starts late 57
  • 58. Constrained Path of Construction Engineering Work Package (EWP) Procurement Package (PP) Supplier Equipment / material Construction Work Package (CWP) Work commences Purchase Order to supplier Contractor resource mobilized2 How do we improve this interface? 58
  • 59. Constrained Path of Construction Engineering Work Package (EWP) Construction Work Package (CWP) Work commences Delay in Engineering will cause lag gets squeezed CWP starts late Model Review causes late changes MTO can’t be created No IFC or AFC status for P&IDs Specification is not complete Client or EPC take longer time for document review and caused delay How are these mitigated / eliminated? It is important to knows the work sequence in order to plan for Construction Work Package. 59
  • 60. Engineering Work Package Progress Ex : Piping Work Package. 2 P&IDs 3 Requisitions 4 Specifications. 1 3D modelling development 5 Pipe Stress analysis 6 Calculations 60
  • 61. Forecasting Scenario Ex : Piping Work Package. Next Weekly Forecast - EWP slips one week EWP is forecast to meet scheduled IFC Next Weekly Forecast - EWP slips another week Contractor plans resource mobilization Contractor tries to mitigate Delay in Construction work and recovery needed Delay in Engineering Work Package approval in return cause delay in construction work. 61
  • 62. Potential Work Flow and Rule of Credit for Piping Step Work Flow Increment % Cumulative % 1 EWP ID’d and mapped to CWP 5% 5% 2 Initial scope identified (line numbers) 15% 20% 3 Preliminary equipment data received 5% 25% 4 Initial routing of lines established 20% 45% 5 Initial bulk material (BOM) to supply chain 10% 55% 6 Piping studies rec’d for critical lines: 5% 60% 7 Final vendor data received 10% 70% 8 Final routings completed 5% 75% 9 P&IDs and LDT issued IFC 5% 80% 10 Stress analysis for large bore completed 5% 85% 11 BOM completed 5% 90% 12 EWP c/w all drawings/specs issued IFC 5% 95% 13 EWP accepted by Construction AFC 5% 100% 62
  • 63. What Makes Forecasting is a Challenge Challenges EWP process has many steps to get to IFC The rules of credit (if they exist) are either not known or not utilized. EWP development held back by outside influence (e.g., Systems, Vendor Data or Owner Decisions) Construction mobilizes resources based on forecast completions of EWP IFC Engineering forced to release partial EWPs or releases EWPs out of sequence or EWPs with HOLDS EWP releases continue to slip but construction is now mobilized 63
  • 64. Engineering Work Package and Construction Work Package CWP Scope of Work IFC drwgs Eng.Specs&Stds Equipment/Materials Vendor info Quality Instructions Regulatory approvals/permits Turnover Documents Schedule (Level 5) Engineering Long Leads RAS dates Material Mgmt Expediting Transportation Special Requirements Procurement HSE/Safety Manpower req. Level 4 Schedule QA/QC Construction Tools/Equip Heavy Lift Plans Scaffold Waste Mgmt Interfaces/Coordination Construction 64
  • 68. Sample WBS for Electrical Construction 68
  • 69. Sample Pipeline Construction Project WBS for Refinery/Chemical Plant 69
  • 70. Sample Pipeline Construction Project WBS for Refinery/Chemical Plant Sample WBS for piping construction project for a refinery or chemical plant may be organized as the following. It is worth to be organized by location wise (i.e. platform and pipe rack, platform and equipment around piping) prior to “Phase” WBS. Timely completion of piping construction is not only depending on timely receiving of engineering drawings and materials from Owner/EPC contractor but timely availability of the infrastructure should also be addressed. Sometime it refers to work front availability. Developing WBS is mainly depending on the project scope. It should be defined according to the project specific as every project is different, for instance, “Demolishing” WBS may also be added under “Phase” level priority to “Installation” WBS if your project scope involved a considerable amount of piping demolishing scope. “Above Ground” and “Under Ground” WBS can be left in case no underground piping work is included in the project. (1) Level 1: Plant Unit, e.g. Utility Unit, Ethylene Theatre Unit, etc. (2) Level 2: Area within a Unit, for instance, Area ABC, Area XYZ. Area demarcation is marked for a group of process piping on above ground and underground. (3) Level 3: Height. This is to segregate pipe work on the above ground and underground. (4) Level 4: Location where pipeline is run, for instance, piping on and around pipe rack, equipment and equipment platform. (5) Level 5: Phase, e.g. Fabrication, Installation (field erection, NDT) and pre-commissioning (hydro testing, air flushing, chemical cleaning etc.) Note : “Common” WBS name refers to common location where interconnecting piping is running between the pipe rack and equipment or equipment platform. Having a clear definition of what is and what is not meant by “Common” is important 70
  • 71. Sample Fuel Tank WBS ExternalFloating Roof Tank 0 Foundation work 1.0 Field erection works 2.0 Tank Bottom 2.1 Shell side 2.2 Roof works 2.3 Tank accessories installation 2.4 Fire fighting works 2.5 Bottom plates installation 2.1.1 Final coating 2.1.2 Shell plates installation 2.2.1 Nozzles and man ways installation 2.2.2 Final Coating 2.2.3 Center deck plate installation 2.3.1 Drainagepiping 2.3.2 Final Coating 2.3.3 Internal Appurtenances 2.4.1 External accessories 2.4.2 Foam piping installation 2.5.1 Final coating 2.5.2 71
  • 73. Piping Discipline ( Piping Fabrication, Tie-in and Commissioning ) 73
  • 74. Piping Tie-in Process Normally, piping tie-in installation scope is involved in revamp project only. The progress tracking system for tie-in work includes Tie-in Tracker Sheet and Progress tracking sheet. Tie-in numbers against the Isometric drawings and work packages are listed in the tracker sheet. The tie-in type (Bolt-up, cut and weld, hot tap, cold tap and threaded are typical tie-in types in process industry), project area or system name and installed dates are also included in the tracker sheet. To develop Progress Tracking Sheet for overall Isometric drawings, the following work steps and weight factor percentages areutilized. 1. Preparation ( Scaffold erection if required/remove insulation if required) -20% 2. Tie-in work (Bolt up/cut & weld/hot tap/cold tap/threaded) -70% 3. Inspection (Sign QC document, example : flange make up check list) -10% The Progress Tracking System for Pipeline Erection Work Developing procedure of progress tracking system for pipeline erection work is the same as piping fabrication work except work steps and weight factor percentages. To do that, replace the following work steps and weight factor percentages with the existing ones and rearrange the formulae. 1. Material at Erection area - 5% 2. Piping Laying -20% 3. Preparation(align/tack weld) -20% 4. Full Welding Execution - 40% 5. Non Destructive Examination - 5% 6. Pipe Support Erection -15% 7. Final Inspection - 5% 74
  • 75. Commissioning Test package and Tie-In System Commisionning Piping Fabrication Piping Tie-In Piping Test Package 75
  • 76. Piping Tie-in Work Sequence General piping tie-in work flow and how rule of credit being assigned to each step. Weld map drawing preparation Withdrew material Welding preparation Spool assemble and tack weld Welding NDT Surface preparation and coating Final inspection Deliveryat site 76
  • 77. Piping Hydrotest Work Sequence Preparation Done Testing Reinstated Clear Punch list General hydrotest work flow and how rule of credit being assigned to each step. 77
  • 78. Commissioning Test package and Tie-In Test Package for Pre- CommissioningTie-In List 78
  • 80. Special Pipe Support Drawing 80
  • 84. Vessel Fabrication Work Flow Exchanger Vessel Fit Up (Pre- Fabrication) Exchanger Vessel Weld Out (Assembly) Tubesheet Fit Up / Weld Out Testing (NDE, Hydro Painting Ex-work 84
  • 85. Vessel Fabrication Work Flow Shell Side Fabrication · Plate marking/cutting/ beveling and inspection · Shell plate rolling work · Longitudinalsteel (LS) fit-up and inspection · LS welding and inspection (NDE) · Circumferencesteel (CS) fit-up and inspection · CS welding and inspection (NDE) Inlet and outlet nozzles fabrication · Pipe marking/cutting / beveling and inspection · Fit-up and welding of flanges and pipes · Inspection for nozzles to flange joints (NDE) Nozzle Attachmentsto Dished Head · Marking of nozzle location on dished head · Cutting/opening/ beveling and inspection · Fit-up and tack weld nozzle to dished head · Inspection for tack welding (if required) · Full weld - nozzle assembly with dished head · Inspection for nozzle to dished head welds (NDE) Nozzles and other accessoriesto Shell · Marking of nozzles location · Cutting/opening/ beveling and Inspection · Fit-up and tack weld nozzle assembly to shell/inspection · Full weld - nozzle assembly with shell · Inspection for nozzle to shell side welds (NDE) · Fit up and welding for instrument attachments · Fit up and welding for lifting lugs Dished head Installation · Fit up and tack weld/Inspection – Dished head to shell · Full circumference welding · Inspection for full welds (NDE) Inspection(Hydro-testing) · Hydrostatic testing · Draining/dryingand final inspection Blastingand Painting · Blasting/Inspection · Primer/Finalcoating/Inspection 85
  • 92. Can to Can Fit-up 92
  • 93. Can to Can Fit-up 93
  • 94. Can to Can Fit-up 94
  • 100.