PRESENTED BYJayvant choudhary
M.Tech (Ist sem)
Transportation engineering
Railway crossing however adequately designed are accident prone ,but
they are adopted at the places where it is not possible from engineering
and economic consideration to provide road over/under bridge.

Should be located away from railway station and marshalling yards.
if unavoidable then should be located beyond shunting limits.
Special
A class
B class
C class
D class

CLASS I

NH
SH

For Vehicular traffic

For cattle crossing and footpaths

CLASS II

CLASS III

CLASS IV

ODR,MDR
Un imp road
within towns

Imp roads within
towns

Roads within non
municipal towns

Roads in and
around town
where traffic is
heavy

Other surfaced
roads

Earth roads

Cart tracks

Cattle crossing
and footpaths
BETWEEN GATES:
CLASS I

CLASS II

CLASS III

CLASS IV

9 m or equal to
width of
carriageway
immediately
outside gate
plus 2.5 m
7.5 m or equal
to width of
carriageway
immediately
outside gate
plus 2 m
5 m or equal to
width of
carriageway
immediately
outside gate
plus 1.25 m
Minimum of 2m

Whichever
is more
OUTSIDE GATES
CLASS I

CLASS II

CLASS III

CLASS IV

7 m or equal to
width of existing
carriageway

5.5 m or equal
to width of
existing
carriageway
3.75 m or equal
to width of
existing
carriageway

Whichever
is more

Minimum of 2m

Note : the width immediate carriageway tapers down to existing carriageway
within distance of 30 m from gate
Between gates : surface shall not be of lower standard than surface outside the
railway boundary. in case of cement concrete surface black topped surface
may be provided
Outside gates: surface shall not be of lower specification than that of existing
road however in case of class I and class II roads black topped surface should
be provided for distance of at least 30 m from gates

Gates employed are:
1)Swing gates
2) Lifting gates
3)Movables barriers of approved designs
Gates should be at right angle to
centre line of road
Minimum distance of gates from
centre line of nearest railway track
should be 3 m on BG lines and 2.5
m on MG & NG lines.

Angle of crossing between centre line of
railway track and road- it should not be
less than 45 degrees in case of Class
I,II,III roads(lower than 45 degrees can
also be provided only after special
permission by railway board). for class IV
roads angle of crossing should be 90
degrees
It depends upon the design speed, coefficient of friction between tyres and
road surface and max allowable value of superelevation.As per IRC:39-1986
following values should be adopted
BETWEEN GATES :-level for all classes
OUTSIDE GATES:A) Class I roads-same level as between the gates upto 15 m beyond
And not steeper than 1 in 40 beyond
B)Class II roads:-same level as gate upto 8 m beyond gates and not
steeper than 1 in 30 beyond
C)Class III roads-same level as between the gates upto 8 m beyond
gates and not steeper than 1 in 20 beyond
D)Class IV roads:-not steeper than 1 in 15
CLASS
I
CLASS
II

CLASS
III
CLASS
IV

Shall be
provided for
pedestrian
except
where there
are foot
over
bridges

Wicket gates
should be such
manner so that
cattle can not easily
and readily pass
Need not to through them
be provided

Wicket gate
UNGUARDED CROSSING
The distance of
second sign
from crossing

An advance
warning sign
located at 200m 50-100 30from crossing
m for
60m
plain
for hilly
and
terrain
rolling
terrain

GUARDED CROSSING
The distance of
second sign
from crossing

An advance
warning sign
located at 200m 50-100 30from crossing
m for
60m
plain
for hilly
and
terrain
rolling
terrain
Gates should be painted white,with a red disc not less than 60 cm in diameter
in centre.the gate posts also be painted white
LIGHT AS OBSERVED BY ROAD
USERS
CLASS I & II
roads
Red when either
gate is closed to
road
White when gates
are opened

CLASS III roads
Same as that of
class I and II
roads but reflector
may used as
alternate of lamps

LIGHTS AS OBSERVED BY
DRIVERS OF APPROACHING
TRAINS
Class I roads
Red when get
closed across
railway track

Other cases

nil
1. Latest IRC road sign indicating whether the railway crossing is manned
or unmanned shall be installed on either end at prescribed distance as
per IRC:67-1977
2. Speed limit road signs should be installed on either of gates
3. Speed breakers shall not be permitted

4. Flashing signals shall be installed on both sides of crossing after
assessing their requirements

Flashing
signals
A kilometer stone is one of a series
of numbered markers placed along
a road or boundary at intervals of one km or
occasionally, parts of a km. They are typically
located at the side of the road or in a median
Kilometer stones are constructed to
provide reference points along the road. This can
be used to reassure travellers that the proper path
is being followed, and to indicate
either distance travelled or the remaining distance
to a destination
FOR NH,SH,& MDR:- The stones are of two sizes
1. Ordinary kilometer stone(small size)
2. Fifth kilometer stone(bigger size)

ORDINARY KILOMETER STONES

SIDE ELEVATION

FRONT ELEVATION

EXAMPLE
FIFTH KILOMETER STONE

FRONT ELEVATION

SIDE ELEVATION

EXAMPLE
FOR O.D.R &V.R:-

Plate 3
In I
I

LOCALLY AVAILABLE MATERIAL SUCH AS HARD STONE , CEMENT
CONCRETE ETC
Ordinary km stone shall be inscribed in hindi or in local language & indicate
name & distance to the next imp town or terminal station
Fifth km stone can be inscribed only in roman and show the distance of
terminal as well as intermediate station
The place name shall be inscribed in different script in following sequence
On each kilometer stone its number shall be
inscribed on side of stone facing the carriage
way.This numbering is meant for maintenance
staff and will start with zero at starting station

Letters and numerals shall be of following
size
Chart provided in IRC:8-1980 give dimensions of the letters and numerals
Spacing between the standard letters or numerals are also provided in
IRC:8-1980 as follows
Edge clearance should be given as

Background colour should be white with
black letter and numerals
Semicircular portion should be painted
canary yellow (I.S.Shade 309) on NH,brilliant
green on SH and white on MDR
Route numbers written should be of black
colour on canary yellow and white on green
background
Normally kilometer stone are placed on left
hand side of road
On divided roads having central median
they should be provided on both sides of road
Kilometer stone shall be fixed at right angle
to centre line of carriageway
On embankment they shall be located on
edge of roadway beyond shoulder
MATERIAL-locally available materials such as hard stone ,well dressed or of
reinforced cement concrete
LOCATION & SPACING- they should be fixed on either side of road land
opposite every 200 meter stone. In addition they shall be fixed at angular points
of boundary & also in places where land is likely to be encroached upon
INSCRIPTION:- The letters R,B indicating road boundary should be inscribed in
each stone & below it name of authority in which road land vests i.e P.W.D,D.B
etc
Cross section details of boundary stones as per IRC:25-1967
MATERIAL-locally available materials such as hard stone ,well dressed or of
reinforced cement concrete
LOCATION & FIXING:- They are to be located on the same side of road as one
having kilometre stone .they may be fixed in position with rammed spails in
mooram,lime surkhi concrete of lean cement concrete all around.they should be
placed at edge of formation with their side bearing the inscription facing and
parallel to centre line of road
INSCRIPTION:-the inscription carried by the stones shall be the numerals 2,4,6
and 8 marked in an ascending order in direction of increasing kilometerage
away from starting station.the numerals shall be 80 mm high. They should be
properly painted or preferably engraved
COLOUR:- the colour of shall be black on white background
SHAPES OF LETTERS/NUMERALS-All charecters
having an arc at top or bottom are specified as per IRC:301968

SPACING BETWEEN ADJACENT LETTERS/NUMERALS:The space between any combination of letters/numerals
may be obtained by the two step process describe in
footnote of table. this space is distance measured
horizontally between extreme right edge of preceding letter
and extreme left edge of following letter. no part of any
letter/numeral may extend into this space.
The mountainous and steep terrains are collectively
known as hilly terrains

TERRAIN

CROSS SLOPE`

MOUNTAINOUS

25%-60%

STEEP

>60%

Hill roads are classified in five
catagories.

HILL ROADS

NH
SH
MDR
ODR
VR
First step for alignment determination is fixation of obligatory
points and control points which are determine by following factors

•Administrative needs
•Development needs
•Strategic needs
To determine a few alternative alignment the investigation should
start from obligatory summit points and proceed downwards
Optimum alignment is the one which yeilds least overall
transportation cost taking into account cost of construction and
maintenance cost of road and have least adverse affect over
environment
Route should avoid introduction of hair-pin bends as far as
possible
If provision of such bends are unavoidable then
number of hair pin bends should kept at absolute
minimum and inevitability of each bend should
be recorded in reconnaissance report
 the bends should be located on flat and stable
hill slopes and they should be avoided in valleys
Series of hair pin bends on same face of hill
should be avoided
HAIR-PIN BENDS
1)Reconnaissance
2)Preliminary survey
3)Determination of final centre line
4)Final location survey

1)RECONNAISSANCE
It is primary step of fixing the alignment, during this a
general route for alignment is selected. A trace is cut
thereafter corresponding to this an access is provided
to subsequent surveys
It can be conducted in following steps
STUDY OF SURVEY SHEETS & MAPS:-in India
topographical sheets are available to the scale of
1:50000,after study of the maps,a number of
alignments feasible in a general way are selected.

Topographical sheet
AERIAL RECONNAISANCE:- it provide a bird
eye view and help to identify the factors which
call for rejection or modification of any of
alignment.
GROUND RECONNAISANCE:- It consist of
the general examination ground by walking or
riding along the probable routes. it will be
advantageous to start reconnaissance from
highest obligatory point.
FINAL RECONNAISANCE OF INACCISABLE
AND DIFICULT STRETCHES:Above stretches may disclose certain stretches
which call for detail examination. A trace cut is
specially made in such section for inspection, it
is also desirable to have one last round of
aerial reconnaissance to resolve remaining
doubts
2)PRELIMINARY SURVEY:PEGGING AND TRACE CUT:- The line and grade of selected
alternative is pegged and the trace is cut along the pegged route
•The gradient to be followed at this stage should be easier than those
proposed to be achieved for the road by the margin of 10 to 20%
•The indication about the grade should be provided at conspicuous
locations so that they can be easily visible from distance

•Trace cut consist of 1.0 to 1.2 m wide track constructed along the
selected alignment to facilitate access to the area for inspection and
survey
•It is desirable that a senior engineer should walk over the trace cut
before further survey work is undertaken to derive benefit from its
experience for selection of best possible route
SURVEY PROCEDURE
•The survey should cover a strip width of 30m in straight/slightly curved and
60 m at sharp curve and hair pin bends
•Traverse along the trace should be run with a theodolite and all angles
measured by double reversible method, distance should be measure with
metallic tape and chain
•The transit station should be marked by means of stakes and numbered in
sequence
•Leveling work include taking ground along the
trace cut at intervals of 10 m and at abrupt
changes in slope and also establishing bench
marks at intervals of 250 m
•At sharp curves and difficult location detailed
leveling may be done for plotting of contours.
Interval of contours may be taken 2m though
this could be varied as per site conditions
MAP PREPARATION:Plan should be prepared to determine final centre line of road . at
critical section plan should show contour at interval of 1-3 m. scale
of may be adopted as horizontal scale of 1:1000 and vertical scale
of 1:100.scale can be increased at difficult location such as hair pin
bends

DETERMINATION OF FINAL CENTRE LINE:•Best alignment should be selected and study of horizontal
alignment in conjunction with profile is carried out and proper
adjustments should be made
•Horizontal curve including spiral transition should be designed
and final central line should be marked over the map

•Vertical curve should be designed and profile shown in
longitudinal section
3)FINAL LOCATION SURVEY:TRANSIT SURVEY:i.

All angles should be measured with a transit, reference marks
should be fixed for this purpose

ii. These marks should be placed at 20 m at straight reaches and 10 m
at curves
iii. Reference pillars/Burjis should fixed on ground and should not be
disturbed during construction . the maximum spacing between them
should not be greater than 100m
iv. Distance should be measured with help of theodolite

v. Final centre line should be properly staked ,stakes being fixed at 20
m interval
BENCHMARKS:T o establish firm vertical control for location, design and construction
benchmarks established during preliminary survey should be re
checked and where likely to be disturbed during construction reestablished at interval of 250 m and or near all drainage crossing
The design speed of various categories of hill road
are:-

Normally ruling design speed should be the guiding criterion for
correlating various geometric features. Minimum design speed may
however be adopted in sections where site conditions including cost
do not permit that
A hairpin turn (also hairpin bend, hairpin corner,
etc.), named for its resemblance to a hairpin/bobby
pin, is a bend in a road with a very acute inner
angle, making it necessary for an oncoming vehicle
to turn almost 180° to continue on the road.
Hairpin turns are often built when a route climbs up
or down a steep slope, so that it can travel mostly
across the slope with only moderate
steepness, and are often arrayed in a zigzag
pattern. Highways with repeating hairpin turns allow
easier, safer ascents and descents of
mountainous terrain than a direct, steep climb and
descent, at the price of greater distances of travel
and usually lower speed limits, due to the
sharpness of the turn. Highways of this style are
also generally less costly to build and maintain than
highways with tunnels.
Inner and outer edges of roadway should be concentric with respect to
centre line of pavement
Where hair pin bends have to be introduced a minimum intervening
length of 60 m should be provided between successive bends to enable
driver to negotiate the alignment smoothly
At hair pin bends preferably the full
roadway width should be surfaced
Passing places or lay-byes are require to cater following requirements
1)To facilitates crossing of vehicles from the opposite direction
2)To tow aside a disabled vehicle so that it does not obstruct traffic
TYPE OF ROAD
NH,SH having roadway width as per
IRC:52-1981

PROVISIONS FOR LAY-BYES
NO NEED

Single lane sections of NH/SH having
narrow roadway width

May be provided with respect to
actual needs

Other roads

Provided at rate of 2-3per kilometer

Lay-byes should be 3.75m wide,30m long on inner edge(towards the
carriageway)and 20 m long on the farther side
Minimum lateral clearance(distance between the extreme edge
of carriageway and the face of nearest support whether a solid
abutment, pier or column) should equal to normal shoulder width.
On lower category roads in hill areas having comparative
narrow shoulders, it will desirable to increase width at underpass
to a certain extent keeping in mind the principles of IRC:54-1974
Minimum vertical clearance of 5m should be
ensured over the full width of the roadway at all
underpasses and similarly at overhanging cliffs
and any semi-tunnel sections etc
The vertical clearance should be measured
with regard to the highest point of
carriageway(the crown or the super elevated
edge of the carriageway)
Allowance for any future raising/strengthening
of pavement is also be made)
•BRIDGE:-It is a structure having total length of above
6m between inner face of dirt wall for carrying traffic or
other moving loads over the obstruction such as
Channel, roads or railways
It is of two types
1)MINOR BRIDGE:-total length up to 60 m
2)MAJOR BRIDGE:-Total length greater than 60 m
•CULVERT:-It is a cross drainage structure having a
total length of 6 m or less
•HIGH LEVEL BRIDGE:-bridge which carries the
roadway above high flood level
•SUBMERSIBLE BRIDGE /VENTED CAUSEWAY:-bridge designed to be
overtopped during floods
•LINEAR WATERWAY:- it is width of the waterway between the extreme
edges of water surface at highest flood level measured at right angle to the
abutment faces
•EFFECTIVE LINEAR WATERWAY:-it is the total width of waterway of the
bridge at HFL minus the effective width of obstructions
•SAFETY KERB:- it is a roadway kerb for occasional use of pedestrian traffic

SAFETY KERB
•WIDTH OF CARRIAGEWAY:- it is minimum clear width measured at right
angle to longitudinal centre line of the bridge between inside face of roadway
kerb

•WIDTH OF THE SAFETY KERB:-It is minimum clear width any where within
the height of 2.25 metres above the surface of the footway kerb
•In case of road kerbs section shown below should be adopted. for bridges
across deep gorges, major rivers, open sea the design below can be modified
suitably
•They should be so designed that they would be safe for vertical and
horizontal loads
•A safety kerb will have same outline as that of roadway kerb except top width
shall not be less than 750mm
HIGH LEVEL BRIDGE
FOR ROAD TRAFFIC

WIDTH

SINGLE LANE

4.25 M

TWO LANE

7.5 M

For every additional
lane 3.5 m width
should be increased,
bridge should be
provided only single
lane or multiple of 2
lane

•If median is provided than its width shall not be less than 1.2 m
•Minimum width of footpath should be 1.5 m
•Apart from these following conditions must be satisfied by 2 lane bridge
•Super elevation on the deck on horizontal curve should be provided as
per relevant IRC standards

•Due allowance should be made for the effect of superelevation on the
stresses in various members of the bridge
•If there is a change of gradient on the bridge deck suitable vertical shall
be introduced conforming the stipulations in IRC:SP-23
•The approaches on either side of straight bridge shall have minimum
length of 15 m and suitably increased where necessary to provide
minimum sight distance
•If there is a change of gradient, suitable vertical curves shall be
introduce as per IRC:23
•A single vertical curve shall be provided for bridges having a total
length of 30 m
•Approaches to vented causeway likely to be affected by flood shall be
provided with suitable designed safety works
•Suitably designed crash barriers should be provided as safeguard
against errant vehicles
•
•They should be of metal or rcc and their design should consider
following factors
•1)impact of vehicle colliding the vehicle
•2)safety of occupants of vehicle colliding the barrier
•3)safety of other vehicle near the collision site
•4)safety of vehicle and pedestrian underneath the bridge
•5)aesthetics and freedom of view of passing vehicles
•They shall provide smooth and continuous face on traffic side

•Suitable reflective devices shall be provided on the traffic face of
barrier at intervals to ensure visibility
Types of crash barriers are:1)Vehicle crash barriers:-provided for bridges without
footpaths
2)Combination railing/vehicle pedestrian crash
barrier:-provide for bridges with footpaths

3)High containment barriers:-provided mainly on
bridges over busy railway lines complex interchanges
and other similar high risk location.
•High level bridges may preferably built in longitudinal gradient with
suitably designed cross drains
•Suitable vertical recess in the piers may be provided to
accommodate the drainage pipes rather than providing drip courses
underneath deck slab
•All carriageway and footpath surfaces have anti skid characteristics
•All multi lane shall be provided with overhead signs and signals as per
IRC:67
•Non luminous signs shall not be permitted
•Arrangement of supports for overhead structures are shown as below
Minimum horizontal & vertical clearance for single & multiple lane
bridges with vehicular traffic are shown in figure

Unless otherwise specified bridges shall have all their parts constructed
to secure the minimum clearance for traffic given in figure
•For footways and cycle tracks a minimum vertical clearance of 2.25 m
shall be provided
•For a bridge constructed on a horizontal curve with super elevated road
surface, the horizontal clearance shall be increased on side of inner
curve by a amount of 5 m multiplied by super elevation
• Lighting masts may be of the conventional type of suitable heights not
less than 5.5m

•The lamp may be chosen from the following
1.
2.
3.
4.
5.
6.

incandescent lamp
Mercury vapour lamp
High pressure mercury lamp with clear fluorescent bulbs
Tubular fluorescent bulb
Sodium vapour lamp
Mercury halide lamp

• The height & spacing should be such that to achieve minimum level
of illumination of 30 lux
•Illumination level for the vehicular and pedestrian subways may be kept
same as those on approaches at either end of subways.
BRIEF STUDY OF IRC STANDARD CODES

More Related Content

What's hot

Classification of roads PPT
Classification of roads PPTClassification of roads PPT
Classification of roads PPTPandyaKirtan1
 
transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.ayudge
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPTKavin Raval
 
Traffic surveys seminar
Traffic surveys seminar Traffic surveys seminar
Traffic surveys seminar DP NITHIN
 
Spot speed study, transport planning
Spot speed study, transport planningSpot speed study, transport planning
Spot speed study, transport planningPratyush Kumar
 
highway development in india
highway development in indiahighway development in india
highway development in indiaPrathi Baa
 
Origin – Destination survey
Origin – Destination surveyOrigin – Destination survey
Origin – Destination surveykezangkl11
 
role of IRC in transportation development in india
role of IRC in transportation development in indiarole of IRC in transportation development in india
role of IRC in transportation development in indiaRAJPREMANI
 
Width of formation or Roadway , Right of way and land width, Typical cross se...
Width of formation or Roadway , Right of way and land width, Typical cross se...Width of formation or Roadway , Right of way and land width, Typical cross se...
Width of formation or Roadway , Right of way and land width, Typical cross se...RAMPRASAD KUMAWAT
 
Types of intersection of road and design parameters of road intersection
Types of intersection of road and design parameters of road intersectionTypes of intersection of road and design parameters of road intersection
Types of intersection of road and design parameters of road intersectionwaiseee
 
Elements of road x-section
Elements of road x-section Elements of road x-section
Elements of road x-section Rana Ibrahim
 
Geometrical design of highways
Geometrical design of highwaysGeometrical design of highways
Geometrical design of highwaysFresher Thinking
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume surveyRashed Alam
 

What's hot (20)

Classification of roads PPT
Classification of roads PPTClassification of roads PPT
Classification of roads PPT
 
transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.transportation Engineering.Highway planning,alignment and geometry.
transportation Engineering.Highway planning,alignment and geometry.
 
Highway engineering PPT
Highway engineering PPTHighway engineering PPT
Highway engineering PPT
 
Traffic surveys seminar
Traffic surveys seminar Traffic surveys seminar
Traffic surveys seminar
 
Spot speed study, transport planning
Spot speed study, transport planningSpot speed study, transport planning
Spot speed study, transport planning
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Origin – Destination survey
Origin – Destination surveyOrigin – Destination survey
Origin – Destination survey
 
Street furniture
Street furnitureStreet furniture
Street furniture
 
Urban Roads
Urban RoadsUrban Roads
Urban Roads
 
role of IRC in transportation development in india
role of IRC in transportation development in indiarole of IRC in transportation development in india
role of IRC in transportation development in india
 
Width of formation or Roadway , Right of way and land width, Typical cross se...
Width of formation or Roadway , Right of way and land width, Typical cross se...Width of formation or Roadway , Right of way and land width, Typical cross se...
Width of formation or Roadway , Right of way and land width, Typical cross se...
 
Urban roads
Urban roadsUrban roads
Urban roads
 
Types of intersection of road and design parameters of road intersection
Types of intersection of road and design parameters of road intersectionTypes of intersection of road and design parameters of road intersection
Types of intersection of road and design parameters of road intersection
 
Unit 3
Unit 3Unit 3
Unit 3
 
Elements of road x-section
Elements of road x-section Elements of road x-section
Elements of road x-section
 
Highway unit-1-hand-outs
Highway unit-1-hand-outsHighway unit-1-hand-outs
Highway unit-1-hand-outs
 
Geometrical design of highways
Geometrical design of highwaysGeometrical design of highways
Geometrical design of highways
 
Road patten
Road pattenRoad patten
Road patten
 
Traffic volume survey
Traffic volume surveyTraffic volume survey
Traffic volume survey
 
Road network
Road networkRoad network
Road network
 

Viewers also liked

Road Design Manual 1.3
Road Design Manual 1.3Road Design Manual 1.3
Road Design Manual 1.3Praja
 
Simplification of train loading on bridges
Simplification of train loading on bridgesSimplification of train loading on bridges
Simplification of train loading on bridgessanjay002
 
Bridge
Bridge Bridge
Bridge illpa
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge codeAjay Kumar
 
UTTIPEC STREET DESIGN GUIDELINES
UTTIPEC STREET DESIGN GUIDELINESUTTIPEC STREET DESIGN GUIDELINES
UTTIPEC STREET DESIGN GUIDELINESUttipec Dda
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topicsShubham Sadh
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )mohit kumar panchal
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge ConstructionRobin Nirwal
 
Sustainability and Heritage Conservation: Notes from the Malaprabha River Valley
Sustainability and Heritage Conservation: Notes from the Malaprabha River ValleySustainability and Heritage Conservation: Notes from the Malaprabha River Valley
Sustainability and Heritage Conservation: Notes from the Malaprabha River ValleyGitanjali Rao
 
Hidden Speed Bumps on the Road to "Continuous"
Hidden Speed Bumps on the Road to "Continuous"Hidden Speed Bumps on the Road to "Continuous"
Hidden Speed Bumps on the Road to "Continuous"Sonatype
 
Heritage management organisations(unesco)
Heritage management organisations(unesco)Heritage management organisations(unesco)
Heritage management organisations(unesco)suryadav11
 
Doing the right thing external version
Doing the right thing   external versionDoing the right thing   external version
Doing the right thing external versionIRC
 
Track training 03082013
Track training   03082013Track training   03082013
Track training 03082013guernica0131
 

Viewers also liked (20)

Road Design Manual 1.3
Road Design Manual 1.3Road Design Manual 1.3
Road Design Manual 1.3
 
Irccode
IrccodeIrccode
Irccode
 
IRC 21-2000
IRC 21-2000IRC 21-2000
IRC 21-2000
 
Simplification of train loading on bridges
Simplification of train loading on bridgesSimplification of train loading on bridges
Simplification of train loading on bridges
 
Road markings IRC 35
Road markings IRC 35Road markings IRC 35
Road markings IRC 35
 
Bridge
Bridge Bridge
Bridge
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge code
 
UTTIPEC STREET DESIGN GUIDELINES
UTTIPEC STREET DESIGN GUIDELINESUTTIPEC STREET DESIGN GUIDELINES
UTTIPEC STREET DESIGN GUIDELINES
 
Design of staircases
Design of staircasesDesign of staircases
Design of staircases
 
Highway Engineering topics
Highway Engineering topicsHighway Engineering topics
Highway Engineering topics
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
PPT On Bridge Construction
PPT On Bridge ConstructionPPT On Bridge Construction
PPT On Bridge Construction
 
Cool roof
Cool roofCool roof
Cool roof
 
Sustainability and Heritage Conservation: Notes from the Malaprabha River Valley
Sustainability and Heritage Conservation: Notes from the Malaprabha River ValleySustainability and Heritage Conservation: Notes from the Malaprabha River Valley
Sustainability and Heritage Conservation: Notes from the Malaprabha River Valley
 
Hidden Speed Bumps on the Road to "Continuous"
Hidden Speed Bumps on the Road to "Continuous"Hidden Speed Bumps on the Road to "Continuous"
Hidden Speed Bumps on the Road to "Continuous"
 
PROJECT
PROJECTPROJECT
PROJECT
 
Heritage management organisations(unesco)
Heritage management organisations(unesco)Heritage management organisations(unesco)
Heritage management organisations(unesco)
 
Doing the right thing external version
Doing the right thing   external versionDoing the right thing   external version
Doing the right thing external version
 
Track training 03082013
Track training   03082013Track training   03082013
Track training 03082013
 
Geometric design
Geometric designGeometric design
Geometric design
 

Similar to BRIEF STUDY OF IRC STANDARD CODES

1.3_Road Signs & Markings.pdf
1.3_Road Signs & Markings.pdf1.3_Road Signs & Markings.pdf
1.3_Road Signs & Markings.pdfManiNarendraVerma
 
3.TRAFFIC REGULATION (TE) 2170613 GTU
3.TRAFFIC REGULATION (TE)  2170613 GTU3.TRAFFIC REGULATION (TE)  2170613 GTU
3.TRAFFIC REGULATION (TE) 2170613 GTUVATSAL PATEL
 
Road Marking and painting in National Highway
Road Marking and painting in National HighwayRoad Marking and painting in National Highway
Road Marking and painting in National HighwaySunil Jha
 
ch. 5 traffic Island.pptx
ch. 5 traffic Island.pptxch. 5 traffic Island.pptx
ch. 5 traffic Island.pptxMehulChavda10
 
Introduction to transportation engineering
Introduction to transportation engineeringIntroduction to transportation engineering
Introduction to transportation engineeringCivil Zone
 
Road marking and its types
Road marking and its typesRoad marking and its types
Road marking and its typesVIJAYS237
 
Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highwayPratikShinde113
 
Civil engineering pdf
Civil engineering pdfCivil engineering pdf
Civil engineering pdfSaqib Imran
 
HEN Faizan 211121.pdf
HEN Faizan 211121.pdfHEN Faizan 211121.pdf
HEN Faizan 211121.pdfFaizanSolanki
 
Geometric Design 3.ppt
Geometric Design 3.pptGeometric Design 3.ppt
Geometric Design 3.pptRanaImam
 
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...Hossam Shafiq I
 
Cross Sectional Elements PPT.pdf
Cross Sectional Elements PPT.pdfCross Sectional Elements PPT.pdf
Cross Sectional Elements PPT.pdfDhananjayM6
 
Introduction to Highway Cross-Sectional Elements .pptx
Introduction to Highway Cross-Sectional Elements .pptxIntroduction to Highway Cross-Sectional Elements .pptx
Introduction to Highway Cross-Sectional Elements .pptxPinkiDeb4
 
Transportation Engineering System
Transportation Engineering SystemTransportation Engineering System
Transportation Engineering SystemGaurav Maurya
 

Similar to BRIEF STUDY OF IRC STANDARD CODES (20)

Highway engineering
Highway engineeringHighway engineering
Highway engineering
 
1.3_Road Signs & Markings.pdf
1.3_Road Signs & Markings.pdf1.3_Road Signs & Markings.pdf
1.3_Road Signs & Markings.pdf
 
3.TRAFFIC REGULATION (TE) 2170613 GTU
3.TRAFFIC REGULATION (TE)  2170613 GTU3.TRAFFIC REGULATION (TE)  2170613 GTU
3.TRAFFIC REGULATION (TE) 2170613 GTU
 
Hill road
Hill roadHill road
Hill road
 
Training report
Training reportTraining report
Training report
 
Road Marking and painting in National Highway
Road Marking and painting in National HighwayRoad Marking and painting in National Highway
Road Marking and painting in National Highway
 
ch. 5 traffic Island.pptx
ch. 5 traffic Island.pptxch. 5 traffic Island.pptx
ch. 5 traffic Island.pptx
 
Introduction to transportation engineering
Introduction to transportation engineeringIntroduction to transportation engineering
Introduction to transportation engineering
 
Road marking and its types
Road marking and its typesRoad marking and its types
Road marking and its types
 
Geometric design of highway
Geometric design of  highwayGeometric design of  highway
Geometric design of highway
 
Railway pdf
Railway pdfRailway pdf
Railway pdf
 
Civil engineering pdf
Civil engineering pdfCivil engineering pdf
Civil engineering pdf
 
Unit 2
Unit 2Unit 2
Unit 2
 
HEN Faizan 211121.pdf
HEN Faizan 211121.pdfHEN Faizan 211121.pdf
HEN Faizan 211121.pdf
 
Geometric Design 3.ppt
Geometric Design 3.pptGeometric Design 3.ppt
Geometric Design 3.ppt
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
1-Introduction & Concepts-Traffic ( Transportation and Traffic Engineering Dr...
 
Cross Sectional Elements PPT.pdf
Cross Sectional Elements PPT.pdfCross Sectional Elements PPT.pdf
Cross Sectional Elements PPT.pdf
 
Introduction to Highway Cross-Sectional Elements .pptx
Introduction to Highway Cross-Sectional Elements .pptxIntroduction to Highway Cross-Sectional Elements .pptx
Introduction to Highway Cross-Sectional Elements .pptx
 
Transportation Engineering System
Transportation Engineering SystemTransportation Engineering System
Transportation Engineering System
 

Recently uploaded

INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 

Recently uploaded (20)

INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 

BRIEF STUDY OF IRC STANDARD CODES

  • 1. PRESENTED BYJayvant choudhary M.Tech (Ist sem) Transportation engineering
  • 2.
  • 3. Railway crossing however adequately designed are accident prone ,but they are adopted at the places where it is not possible from engineering and economic consideration to provide road over/under bridge. Should be located away from railway station and marshalling yards. if unavoidable then should be located beyond shunting limits.
  • 4. Special A class B class C class D class CLASS I NH SH For Vehicular traffic For cattle crossing and footpaths CLASS II CLASS III CLASS IV ODR,MDR Un imp road within towns Imp roads within towns Roads within non municipal towns Roads in and around town where traffic is heavy Other surfaced roads Earth roads Cart tracks Cattle crossing and footpaths
  • 5. BETWEEN GATES: CLASS I CLASS II CLASS III CLASS IV 9 m or equal to width of carriageway immediately outside gate plus 2.5 m 7.5 m or equal to width of carriageway immediately outside gate plus 2 m 5 m or equal to width of carriageway immediately outside gate plus 1.25 m Minimum of 2m Whichever is more
  • 6. OUTSIDE GATES CLASS I CLASS II CLASS III CLASS IV 7 m or equal to width of existing carriageway 5.5 m or equal to width of existing carriageway 3.75 m or equal to width of existing carriageway Whichever is more Minimum of 2m Note : the width immediate carriageway tapers down to existing carriageway within distance of 30 m from gate
  • 7. Between gates : surface shall not be of lower standard than surface outside the railway boundary. in case of cement concrete surface black topped surface may be provided Outside gates: surface shall not be of lower specification than that of existing road however in case of class I and class II roads black topped surface should be provided for distance of at least 30 m from gates Gates employed are: 1)Swing gates 2) Lifting gates 3)Movables barriers of approved designs Gates should be at right angle to centre line of road
  • 8. Minimum distance of gates from centre line of nearest railway track should be 3 m on BG lines and 2.5 m on MG & NG lines. Angle of crossing between centre line of railway track and road- it should not be less than 45 degrees in case of Class I,II,III roads(lower than 45 degrees can also be provided only after special permission by railway board). for class IV roads angle of crossing should be 90 degrees
  • 9. It depends upon the design speed, coefficient of friction between tyres and road surface and max allowable value of superelevation.As per IRC:39-1986 following values should be adopted
  • 10. BETWEEN GATES :-level for all classes OUTSIDE GATES:A) Class I roads-same level as between the gates upto 15 m beyond And not steeper than 1 in 40 beyond B)Class II roads:-same level as gate upto 8 m beyond gates and not steeper than 1 in 30 beyond C)Class III roads-same level as between the gates upto 8 m beyond gates and not steeper than 1 in 20 beyond D)Class IV roads:-not steeper than 1 in 15
  • 11. CLASS I CLASS II CLASS III CLASS IV Shall be provided for pedestrian except where there are foot over bridges Wicket gates should be such manner so that cattle can not easily and readily pass Need not to through them be provided Wicket gate
  • 12. UNGUARDED CROSSING The distance of second sign from crossing An advance warning sign located at 200m 50-100 30from crossing m for 60m plain for hilly and terrain rolling terrain GUARDED CROSSING The distance of second sign from crossing An advance warning sign located at 200m 50-100 30from crossing m for 60m plain for hilly and terrain rolling terrain
  • 13. Gates should be painted white,with a red disc not less than 60 cm in diameter in centre.the gate posts also be painted white
  • 14. LIGHT AS OBSERVED BY ROAD USERS CLASS I & II roads Red when either gate is closed to road White when gates are opened CLASS III roads Same as that of class I and II roads but reflector may used as alternate of lamps LIGHTS AS OBSERVED BY DRIVERS OF APPROACHING TRAINS Class I roads Red when get closed across railway track Other cases nil
  • 15. 1. Latest IRC road sign indicating whether the railway crossing is manned or unmanned shall be installed on either end at prescribed distance as per IRC:67-1977 2. Speed limit road signs should be installed on either of gates 3. Speed breakers shall not be permitted 4. Flashing signals shall be installed on both sides of crossing after assessing their requirements Flashing signals
  • 16.
  • 17. A kilometer stone is one of a series of numbered markers placed along a road or boundary at intervals of one km or occasionally, parts of a km. They are typically located at the side of the road or in a median Kilometer stones are constructed to provide reference points along the road. This can be used to reassure travellers that the proper path is being followed, and to indicate either distance travelled or the remaining distance to a destination
  • 18. FOR NH,SH,& MDR:- The stones are of two sizes 1. Ordinary kilometer stone(small size) 2. Fifth kilometer stone(bigger size) ORDINARY KILOMETER STONES SIDE ELEVATION FRONT ELEVATION EXAMPLE
  • 19. FIFTH KILOMETER STONE FRONT ELEVATION SIDE ELEVATION EXAMPLE
  • 20. FOR O.D.R &V.R:- Plate 3 In I I LOCALLY AVAILABLE MATERIAL SUCH AS HARD STONE , CEMENT CONCRETE ETC
  • 21. Ordinary km stone shall be inscribed in hindi or in local language & indicate name & distance to the next imp town or terminal station Fifth km stone can be inscribed only in roman and show the distance of terminal as well as intermediate station The place name shall be inscribed in different script in following sequence
  • 22. On each kilometer stone its number shall be inscribed on side of stone facing the carriage way.This numbering is meant for maintenance staff and will start with zero at starting station Letters and numerals shall be of following size
  • 23. Chart provided in IRC:8-1980 give dimensions of the letters and numerals
  • 24. Spacing between the standard letters or numerals are also provided in IRC:8-1980 as follows
  • 25. Edge clearance should be given as Background colour should be white with black letter and numerals Semicircular portion should be painted canary yellow (I.S.Shade 309) on NH,brilliant green on SH and white on MDR Route numbers written should be of black colour on canary yellow and white on green background
  • 26. Normally kilometer stone are placed on left hand side of road On divided roads having central median they should be provided on both sides of road Kilometer stone shall be fixed at right angle to centre line of carriageway On embankment they shall be located on edge of roadway beyond shoulder
  • 27.
  • 28. MATERIAL-locally available materials such as hard stone ,well dressed or of reinforced cement concrete LOCATION & SPACING- they should be fixed on either side of road land opposite every 200 meter stone. In addition they shall be fixed at angular points of boundary & also in places where land is likely to be encroached upon INSCRIPTION:- The letters R,B indicating road boundary should be inscribed in each stone & below it name of authority in which road land vests i.e P.W.D,D.B etc
  • 29. Cross section details of boundary stones as per IRC:25-1967
  • 30.
  • 31. MATERIAL-locally available materials such as hard stone ,well dressed or of reinforced cement concrete LOCATION & FIXING:- They are to be located on the same side of road as one having kilometre stone .they may be fixed in position with rammed spails in mooram,lime surkhi concrete of lean cement concrete all around.they should be placed at edge of formation with their side bearing the inscription facing and parallel to centre line of road INSCRIPTION:-the inscription carried by the stones shall be the numerals 2,4,6 and 8 marked in an ascending order in direction of increasing kilometerage away from starting station.the numerals shall be 80 mm high. They should be properly painted or preferably engraved COLOUR:- the colour of shall be black on white background
  • 32.
  • 33.
  • 34.
  • 35.
  • 36. SHAPES OF LETTERS/NUMERALS-All charecters having an arc at top or bottom are specified as per IRC:301968 SPACING BETWEEN ADJACENT LETTERS/NUMERALS:The space between any combination of letters/numerals may be obtained by the two step process describe in footnote of table. this space is distance measured horizontally between extreme right edge of preceding letter and extreme left edge of following letter. no part of any letter/numeral may extend into this space.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41. The mountainous and steep terrains are collectively known as hilly terrains TERRAIN CROSS SLOPE` MOUNTAINOUS 25%-60% STEEP >60% Hill roads are classified in five catagories. HILL ROADS NH SH MDR ODR VR
  • 42. First step for alignment determination is fixation of obligatory points and control points which are determine by following factors •Administrative needs •Development needs •Strategic needs To determine a few alternative alignment the investigation should start from obligatory summit points and proceed downwards Optimum alignment is the one which yeilds least overall transportation cost taking into account cost of construction and maintenance cost of road and have least adverse affect over environment Route should avoid introduction of hair-pin bends as far as possible
  • 43. If provision of such bends are unavoidable then number of hair pin bends should kept at absolute minimum and inevitability of each bend should be recorded in reconnaissance report  the bends should be located on flat and stable hill slopes and they should be avoided in valleys Series of hair pin bends on same face of hill should be avoided HAIR-PIN BENDS
  • 44. 1)Reconnaissance 2)Preliminary survey 3)Determination of final centre line 4)Final location survey 1)RECONNAISSANCE It is primary step of fixing the alignment, during this a general route for alignment is selected. A trace is cut thereafter corresponding to this an access is provided to subsequent surveys It can be conducted in following steps STUDY OF SURVEY SHEETS & MAPS:-in India topographical sheets are available to the scale of 1:50000,after study of the maps,a number of alignments feasible in a general way are selected. Topographical sheet
  • 45. AERIAL RECONNAISANCE:- it provide a bird eye view and help to identify the factors which call for rejection or modification of any of alignment. GROUND RECONNAISANCE:- It consist of the general examination ground by walking or riding along the probable routes. it will be advantageous to start reconnaissance from highest obligatory point. FINAL RECONNAISANCE OF INACCISABLE AND DIFICULT STRETCHES:Above stretches may disclose certain stretches which call for detail examination. A trace cut is specially made in such section for inspection, it is also desirable to have one last round of aerial reconnaissance to resolve remaining doubts
  • 46. 2)PRELIMINARY SURVEY:PEGGING AND TRACE CUT:- The line and grade of selected alternative is pegged and the trace is cut along the pegged route •The gradient to be followed at this stage should be easier than those proposed to be achieved for the road by the margin of 10 to 20% •The indication about the grade should be provided at conspicuous locations so that they can be easily visible from distance •Trace cut consist of 1.0 to 1.2 m wide track constructed along the selected alignment to facilitate access to the area for inspection and survey •It is desirable that a senior engineer should walk over the trace cut before further survey work is undertaken to derive benefit from its experience for selection of best possible route
  • 47. SURVEY PROCEDURE •The survey should cover a strip width of 30m in straight/slightly curved and 60 m at sharp curve and hair pin bends •Traverse along the trace should be run with a theodolite and all angles measured by double reversible method, distance should be measure with metallic tape and chain •The transit station should be marked by means of stakes and numbered in sequence •Leveling work include taking ground along the trace cut at intervals of 10 m and at abrupt changes in slope and also establishing bench marks at intervals of 250 m •At sharp curves and difficult location detailed leveling may be done for plotting of contours. Interval of contours may be taken 2m though this could be varied as per site conditions
  • 48. MAP PREPARATION:Plan should be prepared to determine final centre line of road . at critical section plan should show contour at interval of 1-3 m. scale of may be adopted as horizontal scale of 1:1000 and vertical scale of 1:100.scale can be increased at difficult location such as hair pin bends DETERMINATION OF FINAL CENTRE LINE:•Best alignment should be selected and study of horizontal alignment in conjunction with profile is carried out and proper adjustments should be made •Horizontal curve including spiral transition should be designed and final central line should be marked over the map •Vertical curve should be designed and profile shown in longitudinal section
  • 49. 3)FINAL LOCATION SURVEY:TRANSIT SURVEY:i. All angles should be measured with a transit, reference marks should be fixed for this purpose ii. These marks should be placed at 20 m at straight reaches and 10 m at curves iii. Reference pillars/Burjis should fixed on ground and should not be disturbed during construction . the maximum spacing between them should not be greater than 100m iv. Distance should be measured with help of theodolite v. Final centre line should be properly staked ,stakes being fixed at 20 m interval
  • 50. BENCHMARKS:T o establish firm vertical control for location, design and construction benchmarks established during preliminary survey should be re checked and where likely to be disturbed during construction reestablished at interval of 250 m and or near all drainage crossing
  • 51. The design speed of various categories of hill road are:- Normally ruling design speed should be the guiding criterion for correlating various geometric features. Minimum design speed may however be adopted in sections where site conditions including cost do not permit that
  • 52. A hairpin turn (also hairpin bend, hairpin corner, etc.), named for its resemblance to a hairpin/bobby pin, is a bend in a road with a very acute inner angle, making it necessary for an oncoming vehicle to turn almost 180° to continue on the road. Hairpin turns are often built when a route climbs up or down a steep slope, so that it can travel mostly across the slope with only moderate steepness, and are often arrayed in a zigzag pattern. Highways with repeating hairpin turns allow easier, safer ascents and descents of mountainous terrain than a direct, steep climb and descent, at the price of greater distances of travel and usually lower speed limits, due to the sharpness of the turn. Highways of this style are also generally less costly to build and maintain than highways with tunnels.
  • 53.
  • 54. Inner and outer edges of roadway should be concentric with respect to centre line of pavement Where hair pin bends have to be introduced a minimum intervening length of 60 m should be provided between successive bends to enable driver to negotiate the alignment smoothly At hair pin bends preferably the full roadway width should be surfaced
  • 55. Passing places or lay-byes are require to cater following requirements 1)To facilitates crossing of vehicles from the opposite direction 2)To tow aside a disabled vehicle so that it does not obstruct traffic TYPE OF ROAD NH,SH having roadway width as per IRC:52-1981 PROVISIONS FOR LAY-BYES NO NEED Single lane sections of NH/SH having narrow roadway width May be provided with respect to actual needs Other roads Provided at rate of 2-3per kilometer Lay-byes should be 3.75m wide,30m long on inner edge(towards the carriageway)and 20 m long on the farther side
  • 56. Minimum lateral clearance(distance between the extreme edge of carriageway and the face of nearest support whether a solid abutment, pier or column) should equal to normal shoulder width. On lower category roads in hill areas having comparative narrow shoulders, it will desirable to increase width at underpass to a certain extent keeping in mind the principles of IRC:54-1974
  • 57. Minimum vertical clearance of 5m should be ensured over the full width of the roadway at all underpasses and similarly at overhanging cliffs and any semi-tunnel sections etc The vertical clearance should be measured with regard to the highest point of carriageway(the crown or the super elevated edge of the carriageway) Allowance for any future raising/strengthening of pavement is also be made)
  • 58.
  • 59. •BRIDGE:-It is a structure having total length of above 6m between inner face of dirt wall for carrying traffic or other moving loads over the obstruction such as Channel, roads or railways It is of two types 1)MINOR BRIDGE:-total length up to 60 m 2)MAJOR BRIDGE:-Total length greater than 60 m •CULVERT:-It is a cross drainage structure having a total length of 6 m or less •HIGH LEVEL BRIDGE:-bridge which carries the roadway above high flood level •SUBMERSIBLE BRIDGE /VENTED CAUSEWAY:-bridge designed to be overtopped during floods
  • 60. •LINEAR WATERWAY:- it is width of the waterway between the extreme edges of water surface at highest flood level measured at right angle to the abutment faces •EFFECTIVE LINEAR WATERWAY:-it is the total width of waterway of the bridge at HFL minus the effective width of obstructions
  • 61. •SAFETY KERB:- it is a roadway kerb for occasional use of pedestrian traffic SAFETY KERB •WIDTH OF CARRIAGEWAY:- it is minimum clear width measured at right angle to longitudinal centre line of the bridge between inside face of roadway kerb •WIDTH OF THE SAFETY KERB:-It is minimum clear width any where within the height of 2.25 metres above the surface of the footway kerb
  • 62.
  • 63. •In case of road kerbs section shown below should be adopted. for bridges across deep gorges, major rivers, open sea the design below can be modified suitably •They should be so designed that they would be safe for vertical and horizontal loads •A safety kerb will have same outline as that of roadway kerb except top width shall not be less than 750mm
  • 64. HIGH LEVEL BRIDGE FOR ROAD TRAFFIC WIDTH SINGLE LANE 4.25 M TWO LANE 7.5 M For every additional lane 3.5 m width should be increased, bridge should be provided only single lane or multiple of 2 lane •If median is provided than its width shall not be less than 1.2 m •Minimum width of footpath should be 1.5 m
  • 65. •Apart from these following conditions must be satisfied by 2 lane bridge
  • 66. •Super elevation on the deck on horizontal curve should be provided as per relevant IRC standards •Due allowance should be made for the effect of superelevation on the stresses in various members of the bridge •If there is a change of gradient on the bridge deck suitable vertical shall be introduced conforming the stipulations in IRC:SP-23
  • 67. •The approaches on either side of straight bridge shall have minimum length of 15 m and suitably increased where necessary to provide minimum sight distance •If there is a change of gradient, suitable vertical curves shall be introduce as per IRC:23 •A single vertical curve shall be provided for bridges having a total length of 30 m •Approaches to vented causeway likely to be affected by flood shall be provided with suitable designed safety works
  • 68. •Suitably designed crash barriers should be provided as safeguard against errant vehicles • •They should be of metal or rcc and their design should consider following factors •1)impact of vehicle colliding the vehicle •2)safety of occupants of vehicle colliding the barrier •3)safety of other vehicle near the collision site •4)safety of vehicle and pedestrian underneath the bridge •5)aesthetics and freedom of view of passing vehicles •They shall provide smooth and continuous face on traffic side •Suitable reflective devices shall be provided on the traffic face of barrier at intervals to ensure visibility
  • 69. Types of crash barriers are:1)Vehicle crash barriers:-provided for bridges without footpaths 2)Combination railing/vehicle pedestrian crash barrier:-provide for bridges with footpaths 3)High containment barriers:-provided mainly on bridges over busy railway lines complex interchanges and other similar high risk location.
  • 70.
  • 71.
  • 72. •High level bridges may preferably built in longitudinal gradient with suitably designed cross drains •Suitable vertical recess in the piers may be provided to accommodate the drainage pipes rather than providing drip courses underneath deck slab •All carriageway and footpath surfaces have anti skid characteristics
  • 73. •All multi lane shall be provided with overhead signs and signals as per IRC:67 •Non luminous signs shall not be permitted •Arrangement of supports for overhead structures are shown as below
  • 74. Minimum horizontal & vertical clearance for single & multiple lane bridges with vehicular traffic are shown in figure Unless otherwise specified bridges shall have all their parts constructed to secure the minimum clearance for traffic given in figure
  • 75. •For footways and cycle tracks a minimum vertical clearance of 2.25 m shall be provided •For a bridge constructed on a horizontal curve with super elevated road surface, the horizontal clearance shall be increased on side of inner curve by a amount of 5 m multiplied by super elevation
  • 76. • Lighting masts may be of the conventional type of suitable heights not less than 5.5m •The lamp may be chosen from the following 1. 2. 3. 4. 5. 6. incandescent lamp Mercury vapour lamp High pressure mercury lamp with clear fluorescent bulbs Tubular fluorescent bulb Sodium vapour lamp Mercury halide lamp • The height & spacing should be such that to achieve minimum level of illumination of 30 lux •Illumination level for the vehicular and pedestrian subways may be kept same as those on approaches at either end of subways.