Sabarmati River Front Development Project
Sabarmati Riverfront Development Corporation Ltd, Ahmedabad
Ahmedabad Municipal Corporation
Sabarmati has been an integral part in the life of
Ahmedabad…
•It is an important source of water for the
city
•A space for cultural and recreational
activities
Project Objectives
1.Reconnect the city to the river
2.Create a conducive urban
environment
3.Create an identity for the city
Key aspects of the Project
1. Overall environmental improvement
2. Creating high quality public open spaces
3. Providing adequate public access to the river
4. Rehabilitating the slums
5. Creating vibrant urban neighborhoods
6. Providing city level infrastructure
SPV to Execute
Sabarmati River Front Development
• Ahmedabad Municipal Corporation (AMC)
constituted a SPV in 1997
Sabarmati River Front
Development Corporation Ltd
(SRFDCL)
a Company under the Companies Act.
• Chairman: Municipal Commissioner
• Board of Directors :
– Mayor, Chairman Standing Committee, Leader
Opposition (AMC), Technical Experts, Collector-
Ahmedabad, ED HUDCO, Deputy Commissioner-AMC
Financing of the PROJECT
• Estimated Cost (2005 price)
Phase-1= Rs. 824.24 cr. (under construction)
Phase-2 = Rs. 462.93 cr.
• Equity of AMC = Rs. 75 cr.
• Loan from HUDCO = Rs. 550 cr.
• Loan tenure 3 yr moratorium + 8 years
• Loan servicing being done by AMC
• Source of Revenue: 20% of the reclaimed
land to be allotted for commercial
development
Project area
10.5 kms stretch
Railway
Bridge
Vasna Barrage
The area is delineated based on
• Current extents of the city
• Future potentials of the area
Study of Sabarmati River Basin
☺
☺ ☺
☺
DATUM DATUM
RLINMETERS
E2-41.621
E3-42.390
E4-41.439
E1-43.28
E9-39.783
E8-40.338
E5-40.715
E11-39.525
E10-40.963
E6-42.900 E7-42.735
Analysis
•Hydrology review
of the Sabarmati
river catchments
Study of river hydraulics by
NIH Roorkie, IIT Roorkie, M/s. CC Patel Associates
☺
0
0
123456789101112131416 15
1
2
3
4
5
6
7
8
9
10
☺
100 - 120m 100 - 120m275m
30m 30m275m
•Water retention
study
•Optimal width of
water is 275 mts
Analysis
Construction Work
• Diaphragm wall, Anchor slab & Ghaats
• Earthfilling
• Retaining wall
• Diversion of Sewer
Sardar Bridge to Vasna Barrage (West)7
U/s Of Subhash Bridge to AEC in West & Cantonment in East9 & 10
Gandhi Bridge to Ellis Bridge- East4
Ellis Bridge to Sardar Bridge- East & West5 & 6
Sardar Bridge to Vasna Barrage (East)8
Dudheshwar to Gandhi Bridge- East3
Subhash Bridge to Gandhi Bridge -West2
Gandhi Bridge to Ellis Bridge – West1
LocationStretch
Aerial view after proposed construction of Level-1
Infrastructure
Main trunk
sewer
Provision of an integrated storm water and sewage drainage system
• Diversion of sewers connecting all sewage outfalls
•A main trunk sewer connecting all such outfalls to the STP
•Pumping stations at regular intervals
Pumping
station
To Sewage
treatment
plant
West bank
East Bank
Based on Hydrological Study by NIH Roorkie and IIT Roorkie
the clearance height of bridges will be increased by 1 mtr.
•Bring back focus
to the centre city
•Reconnect the city
to the river
The riverfront holds great potential…
Public access to the riverfront
Establishing and strengthening accessibility to and along the riverfront
•Improved pedestrian and bicycle circulation
•New transportation systems along the river
•Opening up visual vistas
West bank
East Bank
East River
street
Slum rehabilitation and informal activities
Rehabilitation of
Sunday Market
New
rehabilitation
housing
New
rehabilitation
housing
Informal
market
New
rehabilitation
housing
Informal
market
Accommodating the project affected section in the overall plan
•Reorganizing the existing informal markets and creating new
opportunities along the river
•Provide new housing as a part of slum rehabilitation
West bank
East Bank
New urban neighborhoods
Creating opportunities for new developments by integrating with the
existing
•Creating a business district
•Commercial / Retail
•Residential
West bank
East Bank
Commercial
Business
district
Residential
Residential
Commercial
River Promenade
11 meter wide pedestrian lower promenade
6 meter wide pedestrian lower promenade
15 meter wide upper promenade
River Promenade
View of Lower promenade
View of public park
Sabarmati River FrontSabarmati River Front
DevelopmentDevelopment
•• Progress of ExecutionProgress of Execution
DIAPHRAGM WALL & ANCHOR SLAB
U/s of Subhash Bridge (East & West)
Sardar Bridge to Vasna Barrage (East)
Sardar Bridge to Vasna Barrage (West)
Ellis Bridge to Sardar Bridge (E & W)
Gandhi Bridge to Ellis Bridge (East)
Dudheshwar to Gandhi Bridge (East)
Subhash Bridge to Gandhi Bridge (West)
Gandhi Bridge to Ellis Bridge (West)
Location
in progress
Started
Started
@ completion
@ completion
@ completion
@ completion
@ completion
Status
8
9 & 10
7
5 & 6
4
3
2
1
Stretch
DIAPHRAGM WALL & ANCHOR SLAB
Stretch 1 - Gandhi Bridge to Ellis Bridge (West)
• Agency : ITD Cementation India Limited
• Project Cost: Rs. 22.95 crores
• Start Date: 07/02/2005
100.001797RMTAnchor Slab
100.002065RMTDiaphragm wall
88.88665000CMTEarth filling
% work doneQuantityUnitDescription
DIAPHRAGM WALL & ANCHOR SLAB
Stretch 2 – Subhash Bridge to Gandhi Bridge (West)
• Agency : ITD Cementation India Limited
• Project Cost: Rs. 25 crores
• Start Date: 07/02/2005
100.002648RMTAnchor Slab
100.003029RMTDiaphragm wall
97.12280000CMTEarth filling
% work doneQuantityUnitDescription
DIAPHRAGM WALL & ANCHOR SLAB
Stretch 3 – Dudheshwar to Gandhi Bridge (East)
• Agency : Gammon India Limited
• Project Cost: Rs. 20.16 crores
• Start Date: 07/04/2005
100.001968RMTAnchor Slab
100.002176RMTDiaphragm wall
89.92200000CMTEarth filling
% work doneQuantityUnitDescription
DIAPHRAGM WALL & ANCHOR SLAB
Stretch 4 –Gandhi Bridge to Ellis Bridge (East)
• Agency : Gammon India Limited
• Project Cost: Rs. 20.60 crores
• Start Date: 07/04/2005
100.001724RMTAnchor Slab
100.001974RMTDiaphragm wall
80.20200000CMTEarth filling
% work doneQuantityUnitDescription
DIAPHRAGM WALL & ANCHOR SLAB
Stretch 5 & 6 –Ellis Bridge to Sardar Bridge (East & West)
• Agency : ITD Cementation India Limited
• Project Cost: Rs. 33.18 crores
• Start Date: 07/02/2006
97.602248RMTAnchor Slab
100.002525RMTDiaphragm wall
86.45947000CMTEarth filling
% work doneQuantityUnitDescription
DIAPHRAGM WALL & ANCHOR SLAB
Stretch 7 - Sardar Bridge to Vasna Barrage (West)
• Agency : ITD Cementation India Limited
• Project Cost: Rs. 45.06 crores
• Start Date: 28/05/2007
0.003000RMTAnchor Slab
23.203000RMTDiaphragm wall
57.63495362CMTEarth filling
% work doneQuantityUnitDescription
DIAPHRAGM WALL & ANCHOR SLAB
Stretch 8 Sardar Bridge to Vasna Barrage (East)
• Agency : ITD Cementation India Limited
• Project Cost: Rs. 42.27 crores
• Start Date: 28/05/2007
0.003000RMTAnchor Slab
3.203000RMTDiaphragm wall
28.85424352CMTEarth filling
% work doneQuantityUnitDescription
DIVERSION OF SEWER
RAILWAY BRIDGE TO ELLIS BRIDGE (WEST)
• Agency : Alcock Cement Pipes & Concrete Works
• Project Cost: Rs. 5.65 crores
• Start Date: 15/01/2006
67.456375RMTLaying of
Pipeline
% work doneQuantityUnitDescription
DIVERSION OF SEWER
RAILWAY BRIDGE TO ELLIS BRIDGE (EAST)
• Agency : Ramky Infrastructure Limited
• Project Cost: Rs. 8.22 crores
• Start Date: 15/04/2006
40.986100RMTLaying of
Pipeline
% work doneQuantityUnitDescription
DIVERSION OF SEWER
ELLIS BRIDGE TO SARDAR BRIDGE (EAST & WEST)
• Agency : Alcock Cement Pipes & Concrete Works
• Project Cost: Rs. 6.08 crores
• Start Date: 01/03/2007
37.152530RMTLaying of
Pipeline
% work doneQuantityUnitDescription
Thank you
Sabarmati Riverfront Development Corporation Ltd. Ahmedabad

More Related Content

What's hot

Settlement pattern of town (Varanasi)
Settlement pattern of town (Varanasi)Settlement pattern of town (Varanasi)
Settlement pattern of town (Varanasi)Jagjeet Kumar
 
Jaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian CityJaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian CityLakshya Pandit
 
Riverfront development Case study Hoshangabad Thesis
Riverfront development  Case study Hoshangabad Thesis Riverfront development  Case study Hoshangabad Thesis
Riverfront development Case study Hoshangabad Thesis Praveen Mukati
 
Sabarmati riverfront development
Sabarmati riverfront developmentSabarmati riverfront development
Sabarmati riverfront developmentShailja km
 
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UK
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UKCITY INFRASTRUCTURE Nashik Maharastra, Leeds UK
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UKsonika patel
 
CARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENTCARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENTOmkar Nandavadekar
 
Riverfront Development & Haat Case Study
Riverfront Development & Haat Case StudyRiverfront Development & Haat Case Study
Riverfront Development & Haat Case StudyAMIT ANAND
 
Varanasi Riverfront Development
Varanasi Riverfront DevelopmentVaranasi Riverfront Development
Varanasi Riverfront DevelopmentBeda Choudhury
 
Gandhinagar town planning and master plan study
Gandhinagar town planning and master plan studyGandhinagar town planning and master plan study
Gandhinagar town planning and master plan studyAnoushka Tyagi
 
Evolution of Chennai & Bangalore over time
Evolution of Chennai & Bangalore over timeEvolution of Chennai & Bangalore over time
Evolution of Chennai & Bangalore over timeAbby Varghese
 
RIVER FRONT DEVELOPMENT
RIVER FRONT DEVELOPMENT RIVER FRONT DEVELOPMENT
RIVER FRONT DEVELOPMENT Praveen Mukati
 
Kancheepuram - Urban Heritage and Conservation
Kancheepuram - Urban Heritage and ConservationKancheepuram - Urban Heritage and Conservation
Kancheepuram - Urban Heritage and ConservationLahari Yaddanapudi
 
Dilli haat janakpuri
Dilli haat janakpuriDilli haat janakpuri
Dilli haat janakpuriBISHAL KHANAL
 
Masters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdf
Masters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdfMasters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdf
Masters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdfDeep Gupta
 

What's hot (20)

Settlement pattern of town (Varanasi)
Settlement pattern of town (Varanasi)Settlement pattern of town (Varanasi)
Settlement pattern of town (Varanasi)
 
Sanskriti Kendra
Sanskriti KendraSanskriti Kendra
Sanskriti Kendra
 
Jaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian CityJaipur: Evolution Of an Indian City
Jaipur: Evolution Of an Indian City
 
Riverfront development Case study Hoshangabad Thesis
Riverfront development  Case study Hoshangabad Thesis Riverfront development  Case study Hoshangabad Thesis
Riverfront development Case study Hoshangabad Thesis
 
Sabarmati riverfront development
Sabarmati riverfront developmentSabarmati riverfront development
Sabarmati riverfront development
 
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UK
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UKCITY INFRASTRUCTURE Nashik Maharastra, Leeds UK
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UK
 
CARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENTCARTER ROAD WATERFRONT DEVELOPMENT
CARTER ROAD WATERFRONT DEVELOPMENT
 
Riverfront Development & Haat Case Study
Riverfront Development & Haat Case StudyRiverfront Development & Haat Case Study
Riverfront Development & Haat Case Study
 
Varanasi Riverfront Development
Varanasi Riverfront DevelopmentVaranasi Riverfront Development
Varanasi Riverfront Development
 
Tactical Urbanism - examples from India
Tactical Urbanism - examples from IndiaTactical Urbanism - examples from India
Tactical Urbanism - examples from India
 
Gandhinagar town planning and master plan study
Gandhinagar town planning and master plan studyGandhinagar town planning and master plan study
Gandhinagar town planning and master plan study
 
CITY PROFILE OF VARANASI -CASE STUDY by Savitri kumari
CITY PROFILE OF VARANASI -CASE STUDY by Savitri kumariCITY PROFILE OF VARANASI -CASE STUDY by Savitri kumari
CITY PROFILE OF VARANASI -CASE STUDY by Savitri kumari
 
Evolution of Chennai & Bangalore over time
Evolution of Chennai & Bangalore over timeEvolution of Chennai & Bangalore over time
Evolution of Chennai & Bangalore over time
 
Navi mumbai
Navi mumbaiNavi mumbai
Navi mumbai
 
Gopi Talav
Gopi Talav Gopi Talav
Gopi Talav
 
RIVER FRONT DEVELOPMENT
RIVER FRONT DEVELOPMENT RIVER FRONT DEVELOPMENT
RIVER FRONT DEVELOPMENT
 
Kancheepuram - Urban Heritage and Conservation
Kancheepuram - Urban Heritage and ConservationKancheepuram - Urban Heritage and Conservation
Kancheepuram - Urban Heritage and Conservation
 
Dilli haat janakpuri
Dilli haat janakpuriDilli haat janakpuri
Dilli haat janakpuri
 
Masters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdf
Masters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdfMasters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdf
Masters thesis - Urban renewal of Historic core- Case of Varanasi (Ongoing).pdf
 
City center kolkata
City center kolkataCity center kolkata
City center kolkata
 

Viewers also liked

20100629 public engagement strategy and action plan
20100629 public engagement strategy and action plan20100629 public engagement strategy and action plan
20100629 public engagement strategy and action planRiddhi Dash
 
Sabarmati Riverfront development project
Sabarmati Riverfront development projectSabarmati Riverfront development project
Sabarmati Riverfront development projectNoopur Raval
 
Urban design
Urban designUrban design
Urban designBarsha
 
The High Line — Exploring New York’s raised linear park
The High Line — Exploring New York’s raised linear parkThe High Line — Exploring New York’s raised linear park
The High Line — Exploring New York’s raised linear parkInleaf
 
Urban design analysis, Circulation, Architecture, London, Redevelopment studies
Urban design analysis, Circulation, Architecture, London, Redevelopment  studiesUrban design analysis, Circulation, Architecture, London, Redevelopment  studies
Urban design analysis, Circulation, Architecture, London, Redevelopment studiesSujeet Thakare
 

Viewers also liked (8)

20100629 public engagement strategy and action plan
20100629 public engagement strategy and action plan20100629 public engagement strategy and action plan
20100629 public engagement strategy and action plan
 
Alainid
AlainidAlainid
Alainid
 
Srfdc
SrfdcSrfdc
Srfdc
 
Sabarmati Riverfront development project
Sabarmati Riverfront development projectSabarmati Riverfront development project
Sabarmati Riverfront development project
 
Urban design
Urban designUrban design
Urban design
 
The High Line — Exploring New York’s raised linear park
The High Line — Exploring New York’s raised linear parkThe High Line — Exploring New York’s raised linear park
The High Line — Exploring New York’s raised linear park
 
case study highline
case study highlinecase study highline
case study highline
 
Urban design analysis, Circulation, Architecture, London, Redevelopment studies
Urban design analysis, Circulation, Architecture, London, Redevelopment  studiesUrban design analysis, Circulation, Architecture, London, Redevelopment  studies
Urban design analysis, Circulation, Architecture, London, Redevelopment studies
 

Similar to Ahmedabad srfdcl

cv asif shah
cv asif shahcv asif shah
cv asif shahasif shah
 
Amjad Bacha CV Apr 2014 (1)
Amjad Bacha CV Apr 2014 (1)Amjad Bacha CV Apr 2014 (1)
Amjad Bacha CV Apr 2014 (1)Syed Shah
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentationBhismo Dev
 
Polavaram project
Polavaram projectPolavaram project
Polavaram projectHari Harish
 
polavaram and pattiseema project's
 polavaram and pattiseema project's polavaram and pattiseema project's
polavaram and pattiseema project'sAravindVankadaru
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Fairfax County
 
Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad Ar Vandana Talikoti
 
CES Capability Statement V1
CES Capability Statement V1CES Capability Statement V1
CES Capability Statement V1Steve Coleman
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Soumalya Bag
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Crosstown TO
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Crosstown TO
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration ProjectFairfax County
 

Similar to Ahmedabad srfdcl (20)

Karcham wangtoo
Karcham wangtooKarcham wangtoo
Karcham wangtoo
 
cv asif shah
cv asif shahcv asif shah
cv asif shah
 
Amjad Bacha CV Apr 2014 (1)
Amjad Bacha CV Apr 2014 (1)Amjad Bacha CV Apr 2014 (1)
Amjad Bacha CV Apr 2014 (1)
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentation
 
Training Report on "ELEVATED ROAD"
Training Report on "ELEVATED ROAD"Training Report on "ELEVATED ROAD"
Training Report on "ELEVATED ROAD"
 
Polavaram project
Polavaram projectPolavaram project
Polavaram project
 
polavaram and pattiseema project's
 polavaram and pattiseema project's polavaram and pattiseema project's
polavaram and pattiseema project's
 
State of the City 2012
State of the City 2012State of the City 2012
State of the City 2012
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
Little Hunting Creek Sewer Replacement Community Meeting: 12-11-2017
 
Bsp
BspBsp
Bsp
 
Adeel Ahemd Chishty
Adeel Ahemd ChishtyAdeel Ahemd Chishty
Adeel Ahemd Chishty
 
Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015Fairhill/MLK pre-construction public meeting 3-25-2015
Fairhill/MLK pre-construction public meeting 3-25-2015
 
Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad
 
CES Capability Statement V1
CES Capability Statement V1CES Capability Statement V1
CES Capability Statement V1
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
 
Revised Resume
Revised ResumeRevised Resume
Revised Resume
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration Project
 

Recently uploaded

Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Kaya Weers
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observabilityitnewsafrica
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Mark Goldstein
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
JET Technology Labs White Paper for Virtualized Security and Encryption Techn...
JET Technology Labs White Paper for Virtualized Security and Encryption Techn...JET Technology Labs White Paper for Virtualized Security and Encryption Techn...
JET Technology Labs White Paper for Virtualized Security and Encryption Techn...amber724300
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesThousandEyes
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Nikki Chapple
 
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...BookNet Canada
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
A Glance At The Java Performance Toolbox
A Glance At The Java Performance ToolboxA Glance At The Java Performance Toolbox
A Glance At The Java Performance ToolboxAna-Maria Mihalceanu
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
Infrared simulation and processing on Nvidia platforms
Infrared simulation and processing on Nvidia platformsInfrared simulation and processing on Nvidia platforms
Infrared simulation and processing on Nvidia platformsYoss Cohen
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesBernd Ruecker
 
QMMS Lesson 2 - Using MS Excel Formula.pdf
QMMS Lesson 2 - Using MS Excel Formula.pdfQMMS Lesson 2 - Using MS Excel Formula.pdf
QMMS Lesson 2 - Using MS Excel Formula.pdfROWELL MARQUINA
 
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS:  6 Ways to Automate Your Data IntegrationBridging Between CAD & GIS:  6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integrationmarketing932765
 
Français Patch Tuesday - Avril
Français Patch Tuesday - AvrilFrançais Patch Tuesday - Avril
Français Patch Tuesday - AvrilIvanti
 
WomenInAutomation2024: AI and Automation for eveyone
WomenInAutomation2024: AI and Automation for eveyoneWomenInAutomation2024: AI and Automation for eveyone
WomenInAutomation2024: AI and Automation for eveyoneUiPathCommunity
 

Recently uploaded (20)

Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
JET Technology Labs White Paper for Virtualized Security and Encryption Techn...
JET Technology Labs White Paper for Virtualized Security and Encryption Techn...JET Technology Labs White Paper for Virtualized Security and Encryption Techn...
JET Technology Labs White Paper for Virtualized Security and Encryption Techn...
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
 
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
Transcript: New from BookNet Canada for 2024: BNC SalesData and LibraryData -...
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
A Glance At The Java Performance Toolbox
A Glance At The Java Performance ToolboxA Glance At The Java Performance Toolbox
A Glance At The Java Performance Toolbox
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
Infrared simulation and processing on Nvidia platforms
Infrared simulation and processing on Nvidia platformsInfrared simulation and processing on Nvidia platforms
Infrared simulation and processing on Nvidia platforms
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architectures
 
QMMS Lesson 2 - Using MS Excel Formula.pdf
QMMS Lesson 2 - Using MS Excel Formula.pdfQMMS Lesson 2 - Using MS Excel Formula.pdf
QMMS Lesson 2 - Using MS Excel Formula.pdf
 
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS:  6 Ways to Automate Your Data IntegrationBridging Between CAD & GIS:  6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
 
Français Patch Tuesday - Avril
Français Patch Tuesday - AvrilFrançais Patch Tuesday - Avril
Français Patch Tuesday - Avril
 
WomenInAutomation2024: AI and Automation for eveyone
WomenInAutomation2024: AI and Automation for eveyoneWomenInAutomation2024: AI and Automation for eveyone
WomenInAutomation2024: AI and Automation for eveyone
 

Ahmedabad srfdcl

  • 1. Sabarmati River Front Development Project Sabarmati Riverfront Development Corporation Ltd, Ahmedabad Ahmedabad Municipal Corporation
  • 2. Sabarmati has been an integral part in the life of Ahmedabad… •It is an important source of water for the city •A space for cultural and recreational activities
  • 3.
  • 4.
  • 5. Project Objectives 1.Reconnect the city to the river 2.Create a conducive urban environment 3.Create an identity for the city
  • 6. Key aspects of the Project 1. Overall environmental improvement 2. Creating high quality public open spaces 3. Providing adequate public access to the river 4. Rehabilitating the slums 5. Creating vibrant urban neighborhoods 6. Providing city level infrastructure
  • 7. SPV to Execute Sabarmati River Front Development • Ahmedabad Municipal Corporation (AMC) constituted a SPV in 1997 Sabarmati River Front Development Corporation Ltd (SRFDCL) a Company under the Companies Act. • Chairman: Municipal Commissioner • Board of Directors : – Mayor, Chairman Standing Committee, Leader Opposition (AMC), Technical Experts, Collector- Ahmedabad, ED HUDCO, Deputy Commissioner-AMC
  • 8. Financing of the PROJECT • Estimated Cost (2005 price) Phase-1= Rs. 824.24 cr. (under construction) Phase-2 = Rs. 462.93 cr. • Equity of AMC = Rs. 75 cr. • Loan from HUDCO = Rs. 550 cr. • Loan tenure 3 yr moratorium + 8 years • Loan servicing being done by AMC • Source of Revenue: 20% of the reclaimed land to be allotted for commercial development
  • 9. Project area 10.5 kms stretch Railway Bridge Vasna Barrage The area is delineated based on • Current extents of the city • Future potentials of the area
  • 10. Study of Sabarmati River Basin ☺ ☺ ☺ ☺ DATUM DATUM RLINMETERS E2-41.621 E3-42.390 E4-41.439 E1-43.28 E9-39.783 E8-40.338 E5-40.715 E11-39.525 E10-40.963 E6-42.900 E7-42.735 Analysis •Hydrology review of the Sabarmati river catchments Study of river hydraulics by NIH Roorkie, IIT Roorkie, M/s. CC Patel Associates
  • 11. ☺ 0 0 123456789101112131416 15 1 2 3 4 5 6 7 8 9 10 ☺ 100 - 120m 100 - 120m275m 30m 30m275m •Water retention study •Optimal width of water is 275 mts Analysis
  • 12. Construction Work • Diaphragm wall, Anchor slab & Ghaats • Earthfilling • Retaining wall • Diversion of Sewer
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18. Sardar Bridge to Vasna Barrage (West)7 U/s Of Subhash Bridge to AEC in West & Cantonment in East9 & 10 Gandhi Bridge to Ellis Bridge- East4 Ellis Bridge to Sardar Bridge- East & West5 & 6 Sardar Bridge to Vasna Barrage (East)8 Dudheshwar to Gandhi Bridge- East3 Subhash Bridge to Gandhi Bridge -West2 Gandhi Bridge to Ellis Bridge – West1 LocationStretch
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26. Aerial view after proposed construction of Level-1
  • 27. Infrastructure Main trunk sewer Provision of an integrated storm water and sewage drainage system • Diversion of sewers connecting all sewage outfalls •A main trunk sewer connecting all such outfalls to the STP •Pumping stations at regular intervals Pumping station To Sewage treatment plant West bank East Bank
  • 28. Based on Hydrological Study by NIH Roorkie and IIT Roorkie the clearance height of bridges will be increased by 1 mtr.
  • 29. •Bring back focus to the centre city •Reconnect the city to the river The riverfront holds great potential…
  • 30. Public access to the riverfront Establishing and strengthening accessibility to and along the riverfront •Improved pedestrian and bicycle circulation •New transportation systems along the river •Opening up visual vistas West bank East Bank East River street
  • 31. Slum rehabilitation and informal activities Rehabilitation of Sunday Market New rehabilitation housing New rehabilitation housing Informal market New rehabilitation housing Informal market Accommodating the project affected section in the overall plan •Reorganizing the existing informal markets and creating new opportunities along the river •Provide new housing as a part of slum rehabilitation West bank East Bank
  • 32. New urban neighborhoods Creating opportunities for new developments by integrating with the existing •Creating a business district •Commercial / Retail •Residential West bank East Bank Commercial Business district Residential Residential Commercial
  • 33. River Promenade 11 meter wide pedestrian lower promenade
  • 34. 6 meter wide pedestrian lower promenade 15 meter wide upper promenade River Promenade
  • 35. View of Lower promenade
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.
  • 44.
  • 45. Sabarmati River FrontSabarmati River Front DevelopmentDevelopment •• Progress of ExecutionProgress of Execution
  • 46. DIAPHRAGM WALL & ANCHOR SLAB U/s of Subhash Bridge (East & West) Sardar Bridge to Vasna Barrage (East) Sardar Bridge to Vasna Barrage (West) Ellis Bridge to Sardar Bridge (E & W) Gandhi Bridge to Ellis Bridge (East) Dudheshwar to Gandhi Bridge (East) Subhash Bridge to Gandhi Bridge (West) Gandhi Bridge to Ellis Bridge (West) Location in progress Started Started @ completion @ completion @ completion @ completion @ completion Status 8 9 & 10 7 5 & 6 4 3 2 1 Stretch
  • 47. DIAPHRAGM WALL & ANCHOR SLAB Stretch 1 - Gandhi Bridge to Ellis Bridge (West) • Agency : ITD Cementation India Limited • Project Cost: Rs. 22.95 crores • Start Date: 07/02/2005 100.001797RMTAnchor Slab 100.002065RMTDiaphragm wall 88.88665000CMTEarth filling % work doneQuantityUnitDescription
  • 48. DIAPHRAGM WALL & ANCHOR SLAB Stretch 2 – Subhash Bridge to Gandhi Bridge (West) • Agency : ITD Cementation India Limited • Project Cost: Rs. 25 crores • Start Date: 07/02/2005 100.002648RMTAnchor Slab 100.003029RMTDiaphragm wall 97.12280000CMTEarth filling % work doneQuantityUnitDescription
  • 49. DIAPHRAGM WALL & ANCHOR SLAB Stretch 3 – Dudheshwar to Gandhi Bridge (East) • Agency : Gammon India Limited • Project Cost: Rs. 20.16 crores • Start Date: 07/04/2005 100.001968RMTAnchor Slab 100.002176RMTDiaphragm wall 89.92200000CMTEarth filling % work doneQuantityUnitDescription
  • 50. DIAPHRAGM WALL & ANCHOR SLAB Stretch 4 –Gandhi Bridge to Ellis Bridge (East) • Agency : Gammon India Limited • Project Cost: Rs. 20.60 crores • Start Date: 07/04/2005 100.001724RMTAnchor Slab 100.001974RMTDiaphragm wall 80.20200000CMTEarth filling % work doneQuantityUnitDescription
  • 51. DIAPHRAGM WALL & ANCHOR SLAB Stretch 5 & 6 –Ellis Bridge to Sardar Bridge (East & West) • Agency : ITD Cementation India Limited • Project Cost: Rs. 33.18 crores • Start Date: 07/02/2006 97.602248RMTAnchor Slab 100.002525RMTDiaphragm wall 86.45947000CMTEarth filling % work doneQuantityUnitDescription
  • 52. DIAPHRAGM WALL & ANCHOR SLAB Stretch 7 - Sardar Bridge to Vasna Barrage (West) • Agency : ITD Cementation India Limited • Project Cost: Rs. 45.06 crores • Start Date: 28/05/2007 0.003000RMTAnchor Slab 23.203000RMTDiaphragm wall 57.63495362CMTEarth filling % work doneQuantityUnitDescription
  • 53. DIAPHRAGM WALL & ANCHOR SLAB Stretch 8 Sardar Bridge to Vasna Barrage (East) • Agency : ITD Cementation India Limited • Project Cost: Rs. 42.27 crores • Start Date: 28/05/2007 0.003000RMTAnchor Slab 3.203000RMTDiaphragm wall 28.85424352CMTEarth filling % work doneQuantityUnitDescription
  • 54. DIVERSION OF SEWER RAILWAY BRIDGE TO ELLIS BRIDGE (WEST) • Agency : Alcock Cement Pipes & Concrete Works • Project Cost: Rs. 5.65 crores • Start Date: 15/01/2006 67.456375RMTLaying of Pipeline % work doneQuantityUnitDescription
  • 55. DIVERSION OF SEWER RAILWAY BRIDGE TO ELLIS BRIDGE (EAST) • Agency : Ramky Infrastructure Limited • Project Cost: Rs. 8.22 crores • Start Date: 15/04/2006 40.986100RMTLaying of Pipeline % work doneQuantityUnitDescription
  • 56. DIVERSION OF SEWER ELLIS BRIDGE TO SARDAR BRIDGE (EAST & WEST) • Agency : Alcock Cement Pipes & Concrete Works • Project Cost: Rs. 6.08 crores • Start Date: 01/03/2007 37.152530RMTLaying of Pipeline % work doneQuantityUnitDescription
  • 57. Thank you Sabarmati Riverfront Development Corporation Ltd. Ahmedabad