Task relationships and lags
1. Task Relationships
A
4
B
8
Finish to Start
Task B cannot start until A is finished
Example: โPainting wallsโ (Task B) canโt start until
โInstall Drywallโ is complete (Task A)
2. Task Relationships
A
4 B
8Start to Start
Task B cannot start until Task A is started
Example: "Level concrete" (Task B) can't begin until
"Pour foundation" (Task A) begins.
3. Task Relationships
A
4 B
8Finish to Finish
Task B cannot finish until Task A is finished
Example: "Inspect electrical" (Task B) can't finish
until "Install electrical" finishes (Task A).
4. Task Relationships
A
4
B
8
Start to Finish
Task B cannot finish until Task A is started
Example: Your garden plants must be wet
when the fertilizer is applied. We need to
start โwater the gardenโ (Task B) first to
get the plants wet. Task B must continue
and can only finish when the โFertilizingโ
starts (Task A).
Rare
5. Task Relationships +
Lags
A
4
B
8
Finish to Start
Task B cannot start until Task A is finished
Example: โPainting wallsโ (Task B) canโt start until 4
days after โInstall Drywallโ is complete (Task A)
+4d
0 4 8 16
1680 4
6. A
4 B
8Start to Start
Task B can start 2 days after Task A is started
Example: "Install Furniture" (Task B) can begin 2
days after "Install Carpet" (Task A) begins.
Task Relationships +
Lags
+2d
0 4
2 10
102
0