SlideShare a Scribd company logo
1 of 43
Download to read offline
WELCOME
KAILAS SREE CHANDRAN
  CLASS: S7 INDUSTRIAL 432

  Guide: V REGIKUMAR

OVERALL EQUIPMENT EFFECTIVENESS
              OEE
MODERN APPROACH TO

OVERALL EQUIPMENT EFFECTIVENESS


               OEE
2
3
4
5
 Loss due to breakdown of equipment.
     Loss is more than 10 minutes.
6    Biggest of SIX BIG LOSSES.
      Tooling Failures
      Unplanned Maintenance
      General Breakdowns
      Equipment Failure
 The time lost due to adjustments
      in the equipment.
7    Loss is less then 10 minutes.
      Setup/ Changeover
      Material Shortages
      Major Adjustments
 Small stops losses occur when equipment
      stops for a short time as a result of a
      temporary problem.
8    These includes stops that are under ten
      minutes.
       Component Jams
       Misfeeds
       Sensor Blocked
       Delivery Blocked
       Cleaning/ Checking
 Reduced speed refers to the
     difference between Design speed
     and Actual Operating speed.
9
      Under Nameplate Capacity
      Under Design Capacity
      Due to Equipment Wear
      Due to Operator Inefficiency
 Some equipments require warm-
      up time and certain adjustments
10
      to obtain optimum output.
      Startup rejection occurs during
      this startup time.
       Scrap
       Rework
 These losses occurs when products
       produced are not conforming to the
       specifications.
11
      These are rejects during steady-state
       production.
        Scrap
        Rework
12
 The amount of time the facility is open and
       available for operation.
13    One year consists of 365 days, one day
       consists of 24 hours, 60 minutes in one
       hour, 60 seconds in one minute.
      PLANT OPERATING TIME = Fully
       Productive Time + Quality Loss + Speed
       Loss + Downtime Loss + Planned
       Shutdown
PLANT OPERATING TIME
14                                                         PLANNED
     PLANNED PRODUCTION TIME                              SHUTDOWN


                                               DOWNTIME
     OPERATING TIME                              LOSS


                                       SPEED
     NET OPERATING TIME                 LOSS

                             QUALITY
     FULLY PRODUCTIVE TIME
                              LOSS
OEE FACTORS

15
 Availability represents the percentage
       of scheduled time that the equipment is
16     available to operate.
      Availability takes into account Down
       Time Losses.

     AVAILABILITY =         Operating Time
                      Planned Production Time
 Performance represents the speed at
       which the equipment runs as a
17
       percentage of its designed speed.
      Performance takes into account Speed
       loss.

       PERFORMANCE = Net Operating Time
                      Operating Time
 Quality represents the Good units
      produced as a percentage of the Total
18    units produced.

        QUALITY = Fully Productive Time
                   Net Operating Time
PERFORMANCE         AVAILABILITY=
      =Actual Run        Operating time/
     Rate/ Ideal Run        Planned
          Rate           Production Time


19                QUALITY=
                 Good Pieces/
                 Total Pieces
20
21
22
OEE= AVAILABILITY X PERFORMANCE X QUALITY

23   Availability = Operating Time / Planned Production
     Time

     Performance = (Total Pieces / Operating Time) / Ideal
     Run Rate

     Quality = Good Pieces / Total Pieces
 This method use computers for
       accessing inputs, calculating OEE
24
       and its analysis.
      E.g.: OEE IMPACT, VISUAL OEE,
       OEE TOOLKIT, PROVIDEAM etc.
       Spreadsheets
       System Software
o Shift Length: 8 Hours
     o Tea Breaks: 10 Minutes x 2
25
     o Meals Break: 1 Hour
     o Downtime: 10% of shift
     o Idle Runrate: 5 pieces/minute (Cycle
          time=0.2min/pieces)
     o Total Pieces Produced: 1600
     o Rejected Pieces: 52
OEE= Availability x Performance x Quality
     Availability = Operating Time/ Planned
26
       Production Time
     Planned Production Time = Plant Operating
       Time – Planned Shutdown
     Plant Operating Time= 8 hours x 60 = 480 min.
     Planned Shut down = Tea break + Lunch
       Break = (10x2) + 60 = 80minutes.
Planned Production Time = 480-80 = 400 min.
     Operating Time = Planned Production Time-
       Downtime Loss = 400-48 = 352 minutes.
     Availability = 352/400 = 0.88
     Performance = (Total Pieces / Operating Time)/
27
       Idle Run Rate = (1600/352) / 5 = 0.9091
     Quality          = Good Pieces / Total Pieces
                      = (1600-52) / 1600 = 0.9675
     OEE = 0.88 x 0.9091 x 0.9675 = 0.774
     OVERALL EQUIPMENT EFFECTIVENESS = 77.4%
OVERALL EQUIPMENT EFFECTIVENESS (EXCEL CALCULATOR)

     Production Data
     Shift Length               8   Hours =        480 Minutes
     Short Breaks               2   Breaks @        10 Minutes Each =           20 Minutes Total
     Meal Break                 1   Breaks @        60 Minutes Each =           60 Minutes Total
     Down Time                 48   Minutes
     Ideal Run Rate             5   PPM (Pieces Per Minute)
     Total Pieces           1,600   Pieces
     Reject Pieces             52   Pieces


     Support Variable   Calculation                                        Result
     Planned
     Production Time    Shift Length - Breaks                                   400 Minutes
     Operating Time     Planned Production Time - Down Time                     352 Minutes
     Good Pieces        Total Pieces - Reject Pieces                          1,548 Pieces
28
     OEE Factor         Calculation                                         OEE%
     Availability       Operating Time / Planned Production Time             88.00%
     Performance        (Total Pieces / Operation Time) / Ideal Run Rate     90.91%
     Quality            Good Pieces / Total Pieces                           96.75%
     Overall OEE        Availability x Performance x Quality               77.40%


                          World
     OEE Factor                       OEE%
                        Class OEE

     Availability         90.00%      88.00%
     Performance          95.00%      90.91%
     Quality              99.90%      96.75%
     Overall OEE        85.00% 77.40%
 World class OEE is a standard which is used to
       compare the OEE of the firm.
29           OEE Factor        WORLD CLASS
              Availability            90%

             Performance              95%

                Quality               99%
           Overall Equipment
                                      85%
             Effectiveness
30
PLANT OPERATING TIME
                                                                 PLANNED
     PLANNED PRODUCTION TIME                                    SHUTDOWN
31
                                                     DOWNTIME
     OPERATING TIME                                    LOSS


                                          STOPTIME
     RUNNING TIME                           LOSS

                                  SPEED
     NET OPERATING TIME            LOSS

     FULLY PRODUCTIVE   QUALITY
            TIME         LOSS
 Usability takes into account Stop Time
      Loss.
32



        USABILITY = Running Time
                  Operating Time
OEE
33


     Availability   Usability   Performance   Quality
34
o Shift Length: 8 Hours             Downtime
                                         Loss of 48
     o Tea Breaks: 10 Minutes x 2       minutes (10%
                                          of Shift)
     o Meals Break: 1 Hour
35
     o Warm-up Time: 20 minutes
     o Equipment Breakdown(Tool Failure): 28 min.
     o Idle Runrate: 5 pieces/minute (Cycle
          time=0.2min/pieces)
     o Total Pieces Produced: 1600
     o Rejected Pieces: 52
Availability = Operating Time/ Planned
       Production Time
     Planned Production Time = 400 minutes
     Operating Time = Planned Production Time-
       Breakdowns        = 400-28 = 372 minutes.
36
     Availability = 372/400 = 0.93
     Usability = Running time / Operating Time
     Running Time = Operating Time – Warm-up
       Time            = 372-20 = 352 minutes.
     Usability = 352 / 372 = 0.9462
Performance =(Total Pieces / Operating Time) /
       Idle Run Rate = (1600 / 352) / 5 = 0.9091
     Quality    = Good Pieces / Total Pieces
                = (1600-52) / 1600 = 0.9675
     OEE = Availability x Usability x Performance x
37
       Quality
     OEE = 0.93 x 0.9462 x 0.9091 x 0.9675 = 0.774

         Modified OVERALL EQUIPMENT
            EFFECTIVENESS = 77.4%
38
39
 Anil S. Badiger, ‘A proposal: evaluation of
       OEE and impact of six big losses’, Int. J.
       Process Management and Benchmarking,
40
       Vol.2, No. 3, 2008, pp 234-248.
      Ravikumar M. M., ‘Improving Equipment
       Effectiveness’, Int. Business Management,
       Vol. 3, No.2, 2008, pp 91-96.
      www.bestmanagementarticles.com
      www.maintenanceworld.com
Overall Equipment Effectiveness

More Related Content

What's hot

6 OEE overview
6 OEE overview6 OEE overview
6 OEE overview
Webseology
 
TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)
Operational Excellence Consulting
 
Poka yoke (mistake proofing)
Poka yoke (mistake proofing)Poka yoke (mistake proofing)
Poka yoke (mistake proofing)
Animesh Khamesra
 

What's hot (20)

Tpm
TpmTpm
Tpm
 
Oee guide
Oee guideOee guide
Oee guide
 
Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Oee (overall equipment effectifness)
Oee (overall equipment effectifness)
 
Total productive maintenance(TPM)
Total productive maintenance(TPM)Total productive maintenance(TPM)
Total productive maintenance(TPM)
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
TPM 8 Pillars
TPM 8 PillarsTPM 8 Pillars
TPM 8 Pillars
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overview
 
TPM Activity
TPM ActivityTPM Activity
TPM Activity
 
TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)TPM: Focused Improvement (Kobetsu Kaizen)
TPM: Focused Improvement (Kobetsu Kaizen)
 
Total Productive Maintenance
Total Productive MaintenanceTotal Productive Maintenance
Total Productive Maintenance
 
TPM - tech talk
TPM - tech talk TPM - tech talk
TPM - tech talk
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
 
Introduction to Takt time - January 2017
Introduction to Takt time - January 2017Introduction to Takt time - January 2017
Introduction to Takt time - January 2017
 
Lean manufacturing ppt
Lean manufacturing pptLean manufacturing ppt
Lean manufacturing ppt
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
 
"Visual management & 5S " in Lean T.P.S (Workshop slides)
"Visual management &  5S " in Lean T.P.S (Workshop slides)"Visual management &  5S " in Lean T.P.S (Workshop slides)
"Visual management & 5S " in Lean T.P.S (Workshop slides)
 
Poka yoke (mistake proofing)
Poka yoke (mistake proofing)Poka yoke (mistake proofing)
Poka yoke (mistake proofing)
 
Downtime 8 Wastes
Downtime 8 WastesDowntime 8 Wastes
Downtime 8 Wastes
 
16 major losses tng
16 major losses tng16 major losses tng
16 major losses tng
 
Visual Management by Operational Excellence Consulting
Visual Management by Operational Excellence ConsultingVisual Management by Operational Excellence Consulting
Visual Management by Operational Excellence Consulting
 

Viewers also liked

NG BB 18 Theory of Constraints
NG BB 18 Theory of ConstraintsNG BB 18 Theory of Constraints
NG BB 18 Theory of Constraints
Leanleaders.org
 

Viewers also liked (13)

The Six Big Losses of OEE
The Six Big Losses of OEEThe Six Big Losses of OEE
The Six Big Losses of OEE
 
NG BB 17 Takt Time
NG BB 17 Takt TimeNG BB 17 Takt Time
NG BB 17 Takt Time
 
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
 
NG BB 18 Theory of Constraints
NG BB 18 Theory of ConstraintsNG BB 18 Theory of Constraints
NG BB 18 Theory of Constraints
 
Tpm Presentation
Tpm PresentationTpm Presentation
Tpm Presentation
 
TPM. DR. K. BARANIDHARAN
TPM. DR. K. BARANIDHARANTPM. DR. K. BARANIDHARAN
TPM. DR. K. BARANIDHARAN
 
Presentation on Total Productive Maintenance
Presentation on Total Productive MaintenancePresentation on Total Productive Maintenance
Presentation on Total Productive Maintenance
 
tpm presentation
tpm presentationtpm presentation
tpm presentation
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case Studies
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping Process
 
Takt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line BalancingTakt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line Balancing
 
Value stream mapping ppt
Value stream mapping pptValue stream mapping ppt
Value stream mapping ppt
 
Value stream mapping training
Value stream mapping trainingValue stream mapping training
Value stream mapping training
 

Similar to Overall Equipment Effectiveness

Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
MohammedLahssaini1
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
videoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
videoaakash15
 
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionD3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
Mannyjg5
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
MukhtarMohamedAbdila
 

Similar to Overall Equipment Effectiveness (20)

OEE CALCULATION PPT
OEE CALCULATION PPTOEE CALCULATION PPT
OEE CALCULATION PPT
 
Overall Equipment Efficiency
Overall Equipment EfficiencyOverall Equipment Efficiency
Overall Equipment Efficiency
 
OEE.pptx
OEE.pptxOEE.pptx
OEE.pptx
 
OEE workshop v5.pptx
OEE workshop v5.pptxOEE workshop v5.pptx
OEE workshop v5.pptx
 
OEE (overall eqipment effectiveness)
OEE (overall eqipment effectiveness)OEE (overall eqipment effectiveness)
OEE (overall eqipment effectiveness)
 
Pamco oleh Bagoes Soehariadji.ppt.pptx
Pamco  oleh Bagoes Soehariadji.ppt.pptxPamco  oleh Bagoes Soehariadji.ppt.pptx
Pamco oleh Bagoes Soehariadji.ppt.pptx
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping Line
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping line
 
Essences of semiconductor manufacturing 2024.pdf
Essences of semiconductor manufacturing 2024.pdfEssences of semiconductor manufacturing 2024.pdf
Essences of semiconductor manufacturing 2024.pdf
 
Oee and its Application
Oee and its ApplicationOee and its Application
Oee and its Application
 
Final Presentation for SMEDA-JICA
Final Presentation for SMEDA-JICAFinal Presentation for SMEDA-JICA
Final Presentation for SMEDA-JICA
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
 
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolutionD3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
D3 ver oee 3bus094475 l en_oee_white_paper_low_resolution
 
OEE IMPLEMENTATION part 1
OEE IMPLEMENTATION part 1OEE IMPLEMENTATION part 1
OEE IMPLEMENTATION part 1
 
OEE vs TEEP.pdf
OEE vs TEEP.pdfOEE vs TEEP.pdf
OEE vs TEEP.pdf
 
Final Presentation
Final PresentationFinal Presentation
Final Presentation
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
 

More from Kailas Sree Chandran

More from Kailas Sree Chandran (20)

Cleaning-Casting-Defects-and-Die-Castings-CleaningFettling-of-Castings
Cleaning-Casting-Defects-and-Die-Castings-CleaningFettling-of-CastingsCleaning-Casting-Defects-and-Die-Castings-CleaningFettling-of-Castings
Cleaning-Casting-Defects-and-Die-Castings-CleaningFettling-of-Castings
 
Computer basics
Computer basicsComputer basics
Computer basics
 
Project
ProjectProject
Project
 
Hybrid Car
Hybrid CarHybrid Car
Hybrid Car
 
Oil Drilling
Oil DrillingOil Drilling
Oil Drilling
 
V22 Osprey
V22 OspreyV22 Osprey
V22 Osprey
 
Apache Helicopter
Apache HelicopterApache Helicopter
Apache Helicopter
 
Go Kart Project
Go Kart ProjectGo Kart Project
Go Kart Project
 
Quasi Turbine Engine
Quasi Turbine EngineQuasi Turbine Engine
Quasi Turbine Engine
 
Pioneers In Industrial Engineering
Pioneers In Industrial EngineeringPioneers In Industrial Engineering
Pioneers In Industrial Engineering
 
Metrology Assignment
Metrology AssignmentMetrology Assignment
Metrology Assignment
 
Pro Model
Pro ModelPro Model
Pro Model
 
Metrology Assignment Ppt
Metrology Assignment PptMetrology Assignment Ppt
Metrology Assignment Ppt
 
Software Lab Mini Project
Software Lab Mini ProjectSoftware Lab Mini Project
Software Lab Mini Project
 
Random Number Generator
Random Number GeneratorRandom Number Generator
Random Number Generator
 
PPT on Statistical - Cent%
PPT on Statistical - Cent%PPT on Statistical - Cent%
PPT on Statistical - Cent%
 
Quality Circles
Quality CirclesQuality Circles
Quality Circles
 
Input Devices
Input DevicesInput Devices
Input Devices
 
Cost & Reliability
Cost & ReliabilityCost & Reliability
Cost & Reliability
 
Concept of ISO
Concept of ISOConcept of ISO
Concept of ISO
 

Recently uploaded

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Recently uploaded (20)

Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 

Overall Equipment Effectiveness

  • 2. KAILAS SREE CHANDRAN CLASS: S7 INDUSTRIAL 432 Guide: V REGIKUMAR OVERALL EQUIPMENT EFFECTIVENESS OEE
  • 3. MODERN APPROACH TO OVERALL EQUIPMENT EFFECTIVENESS OEE
  • 4. 2
  • 5. 3
  • 6. 4
  • 7. 5
  • 8.  Loss due to breakdown of equipment.  Loss is more than 10 minutes. 6  Biggest of SIX BIG LOSSES.  Tooling Failures  Unplanned Maintenance  General Breakdowns  Equipment Failure
  • 9.  The time lost due to adjustments in the equipment. 7  Loss is less then 10 minutes.  Setup/ Changeover  Material Shortages  Major Adjustments
  • 10.  Small stops losses occur when equipment stops for a short time as a result of a temporary problem. 8  These includes stops that are under ten minutes.  Component Jams  Misfeeds  Sensor Blocked  Delivery Blocked  Cleaning/ Checking
  • 11.  Reduced speed refers to the difference between Design speed and Actual Operating speed. 9  Under Nameplate Capacity  Under Design Capacity  Due to Equipment Wear  Due to Operator Inefficiency
  • 12.  Some equipments require warm- up time and certain adjustments 10 to obtain optimum output. Startup rejection occurs during this startup time.  Scrap  Rework
  • 13.  These losses occurs when products produced are not conforming to the specifications. 11  These are rejects during steady-state production.  Scrap  Rework
  • 14. 12
  • 15.  The amount of time the facility is open and available for operation. 13  One year consists of 365 days, one day consists of 24 hours, 60 minutes in one hour, 60 seconds in one minute.  PLANT OPERATING TIME = Fully Productive Time + Quality Loss + Speed Loss + Downtime Loss + Planned Shutdown
  • 16. PLANT OPERATING TIME 14 PLANNED PLANNED PRODUCTION TIME SHUTDOWN DOWNTIME OPERATING TIME LOSS SPEED NET OPERATING TIME LOSS QUALITY FULLY PRODUCTIVE TIME LOSS
  • 18.  Availability represents the percentage of scheduled time that the equipment is 16 available to operate.  Availability takes into account Down Time Losses. AVAILABILITY = Operating Time Planned Production Time
  • 19.  Performance represents the speed at which the equipment runs as a 17 percentage of its designed speed.  Performance takes into account Speed loss. PERFORMANCE = Net Operating Time Operating Time
  • 20.  Quality represents the Good units produced as a percentage of the Total 18 units produced. QUALITY = Fully Productive Time Net Operating Time
  • 21. PERFORMANCE AVAILABILITY= =Actual Run Operating time/ Rate/ Ideal Run Planned Rate Production Time 19 QUALITY= Good Pieces/ Total Pieces
  • 22. 20
  • 23. 21
  • 24. 22
  • 25. OEE= AVAILABILITY X PERFORMANCE X QUALITY 23 Availability = Operating Time / Planned Production Time Performance = (Total Pieces / Operating Time) / Ideal Run Rate Quality = Good Pieces / Total Pieces
  • 26.  This method use computers for accessing inputs, calculating OEE 24 and its analysis.  E.g.: OEE IMPACT, VISUAL OEE, OEE TOOLKIT, PROVIDEAM etc.  Spreadsheets  System Software
  • 27. o Shift Length: 8 Hours o Tea Breaks: 10 Minutes x 2 25 o Meals Break: 1 Hour o Downtime: 10% of shift o Idle Runrate: 5 pieces/minute (Cycle time=0.2min/pieces) o Total Pieces Produced: 1600 o Rejected Pieces: 52
  • 28. OEE= Availability x Performance x Quality Availability = Operating Time/ Planned 26 Production Time Planned Production Time = Plant Operating Time – Planned Shutdown Plant Operating Time= 8 hours x 60 = 480 min. Planned Shut down = Tea break + Lunch Break = (10x2) + 60 = 80minutes.
  • 29. Planned Production Time = 480-80 = 400 min. Operating Time = Planned Production Time- Downtime Loss = 400-48 = 352 minutes. Availability = 352/400 = 0.88 Performance = (Total Pieces / Operating Time)/ 27 Idle Run Rate = (1600/352) / 5 = 0.9091 Quality = Good Pieces / Total Pieces = (1600-52) / 1600 = 0.9675 OEE = 0.88 x 0.9091 x 0.9675 = 0.774 OVERALL EQUIPMENT EFFECTIVENESS = 77.4%
  • 30. OVERALL EQUIPMENT EFFECTIVENESS (EXCEL CALCULATOR) Production Data Shift Length 8 Hours = 480 Minutes Short Breaks 2 Breaks @ 10 Minutes Each = 20 Minutes Total Meal Break 1 Breaks @ 60 Minutes Each = 60 Minutes Total Down Time 48 Minutes Ideal Run Rate 5 PPM (Pieces Per Minute) Total Pieces 1,600 Pieces Reject Pieces 52 Pieces Support Variable Calculation Result Planned Production Time Shift Length - Breaks 400 Minutes Operating Time Planned Production Time - Down Time 352 Minutes Good Pieces Total Pieces - Reject Pieces 1,548 Pieces 28 OEE Factor Calculation OEE% Availability Operating Time / Planned Production Time 88.00% Performance (Total Pieces / Operation Time) / Ideal Run Rate 90.91% Quality Good Pieces / Total Pieces 96.75% Overall OEE Availability x Performance x Quality 77.40% World OEE Factor OEE% Class OEE Availability 90.00% 88.00% Performance 95.00% 90.91% Quality 99.90% 96.75% Overall OEE 85.00% 77.40%
  • 31.  World class OEE is a standard which is used to compare the OEE of the firm. 29 OEE Factor WORLD CLASS Availability 90% Performance 95% Quality 99% Overall Equipment 85% Effectiveness
  • 32. 30
  • 33. PLANT OPERATING TIME PLANNED PLANNED PRODUCTION TIME SHUTDOWN 31 DOWNTIME OPERATING TIME LOSS STOPTIME RUNNING TIME LOSS SPEED NET OPERATING TIME LOSS FULLY PRODUCTIVE QUALITY TIME LOSS
  • 34.  Usability takes into account Stop Time Loss. 32 USABILITY = Running Time Operating Time
  • 35. OEE 33 Availability Usability Performance Quality
  • 36. 34
  • 37. o Shift Length: 8 Hours Downtime Loss of 48 o Tea Breaks: 10 Minutes x 2 minutes (10% of Shift) o Meals Break: 1 Hour 35 o Warm-up Time: 20 minutes o Equipment Breakdown(Tool Failure): 28 min. o Idle Runrate: 5 pieces/minute (Cycle time=0.2min/pieces) o Total Pieces Produced: 1600 o Rejected Pieces: 52
  • 38. Availability = Operating Time/ Planned Production Time Planned Production Time = 400 minutes Operating Time = Planned Production Time- Breakdowns = 400-28 = 372 minutes. 36 Availability = 372/400 = 0.93 Usability = Running time / Operating Time Running Time = Operating Time – Warm-up Time = 372-20 = 352 minutes. Usability = 352 / 372 = 0.9462
  • 39. Performance =(Total Pieces / Operating Time) / Idle Run Rate = (1600 / 352) / 5 = 0.9091 Quality = Good Pieces / Total Pieces = (1600-52) / 1600 = 0.9675 OEE = Availability x Usability x Performance x 37 Quality OEE = 0.93 x 0.9462 x 0.9091 x 0.9675 = 0.774 Modified OVERALL EQUIPMENT EFFECTIVENESS = 77.4%
  • 40. 38
  • 41. 39
  • 42.  Anil S. Badiger, ‘A proposal: evaluation of OEE and impact of six big losses’, Int. J. Process Management and Benchmarking, 40 Vol.2, No. 3, 2008, pp 234-248.  Ravikumar M. M., ‘Improving Equipment Effectiveness’, Int. Business Management, Vol. 3, No.2, 2008, pp 91-96.  www.bestmanagementarticles.com  www.maintenanceworld.com