SlideShare a Scribd company logo
1 of 72
1
Process Design
and
Facility Layout
2
Introduction
• Make or Buy?
– Available capacity, excess capacity
– Expertise, knowledge, know-how exists?
– Quality Consideration, specialized firms, control
over quality if in-house
– The nature of demand, aggregation
– Cost
Make some components buy remaining
3
Introduction
 Process selection
 Deciding on the way
production of goods or
services will be
organized
 Major implications
 Capacity planning
 Layout of facilities
 Equipment, Capital-
equipment or labor
intensive
 Design of work
4
Forecasting
Product and
Service Design
Technological
Change
Capacity
Planning
Process
Selection
Facilities and
Equipment
Layout
Work
Design
Figure 6.1
Process Selection and System
Design
5
Process Types
• Job Shops: Small lots, low volume, general equipment,
skilled workers, high-variety. Ex: tool and die shop,
veterinarian’s office
• Batch Processing: Moderate volume and variety. Variety
among batches but not inside. Ex:paint production ,
BA3352 sections
• Repetitive/Assembly: Semicontinuous, high volume of
standardized items, limited variety. Ex: auto plants,
cafeteria
• Continuous Processing: Very high volume an no variety.
Ex: steel mill, chemical plants
• Projects: Nonroutine jobs. Ex: preparing BA3352
midterm
6
 Variety of products
and services
 How much
 Flexibility of the process; volume, mix, technology and
design
 What type and degree
 Volume
 Expected output
Job Shop
Batch
Repetitive
Continuous
Questions Before Selecting A
Process
7
Dimension Job Shop Batch Repetitive Continuous
Job variety Very High Moderate Low Very low
Process
flexibility
Very High Moderate Low Very low
Unit cost Very High Moderate Low Very low
Volume of
output
Very low Low High Very high
Product – Process Matrix
8
Product
Variety
High Moderate Low Very Low
Equipment
flexibility
High Moderate Low Very Low
Low
Volume
Moderate
Volume
High
Volume
Very high
Volume
Job
Shop
Batch
Repetitive
assembly
Continuous
Flow
Variety, Flexibility, & Volume
9
Process Type High variety Low variety
Job Shop Appliance
repair
Emergency
room
Batch Commercial
bakery
Classroom
Lecture
Repetitive Automotive
assembly
Automatic
carwash
Continuous
(flow)
Oil refinery
Water purification
Product – Process Matrix
10
Product-Process Matrix
Flexibility-Quality Dependability-Cost
Continuous
Flow
Assembly
Line
Batch
Job
Shop
Low
Volume
One of a
Kind
Multiple
Products,
Low
Volume
Few
Major
Products,
Higher
Volume
High
Volume,
High
Standard-
ization
Book
Writing
Movie
Theaters
Automobile
Assembly
Sugar
Refinery
Flexibility-
Quality
Dependability-
Cost
11
Fixed automation: Low production cost and high volume but with
minimal variety and high changes cost
 Assembly line
Programmable automation: Economically producing a wide
variety of low volume products in small batches
 Computer-aided design and manufacturing systems (CAD/CAM)
 Numerically controlled (NC) machines / CNC
 Industrial robots (arms)
Flexible automation: Require less changeover time and allow
continuous operation of equipment and product variety
 Manufacturing cell
 Flexible manufacturing systems: Use of high automation to achieve
repetitive process efficiency with job shop process
• Automated retrieval and storage
• Automated guided vehicles
 Computer-integrated manufacturing (CIM)
Automation: Machinery that has sensing and control
devices that enables it to operate
12
Robot
Show wafer_handler_web
13
Flexible Manufacturing System
 Group of machines that include supervisory computer
control, automatic material handling, robots and other
processing equipment
 Advantage:
reduce labor costs and more consistent quality
lower capital investment and higher flexibility than
hard automation
relative quick changeover time
 Disadvantage
used for a family of products and require longer planning
and development times
14
Computer-integrated
manufacturing
 Use integrating computer system to link a broad
range of manufacturing activities, including
engineering design, purchasing, order processing and
production planning and control
 Advantage:
rapid response to customer order and product change,
reduce direct labor cost, high quality
15
 Service blueprint: A method used in service
design to describe and analyze a proposed
service. Flowchart:
Service Blueprint
Begin Turn on laptop Connect to LCD A
A View on
Yes
Lecture
No
Begin
16
 Establish boundaries
 Identify steps involved
 Prepare a flowchart
 Identify potential failure points
 Establish a time frame for operations
 Analyze profitability
Service Process Design
17
 Layout: the configuration of departments, work
centers, and equipment,
 Whose design involves particular emphasis on movement
of work (customers or materials) through the system
 Importance of layout
 Requires substantial investments of money and effort
 Involves long-term commitments
 Has significant impact on cost and efficiency of short-
term operations
Layout
18
Inefficient operations
For Example:
High Cost
Bottlenecks
Changes in the design
of products or services
The introduction of new
products or services
Accidents
Safety hazards
The Need for Layout Decisions
19
Changes in
environmental
or other legal
requirements
Changes in volume of
output or mix of
products
Changes in methods
and equipment
Morale problems
The Need for Layout Design
(Cont’d)
20
Basic Layout Types
 Product Layout
– Layout that uses standardized processing operations to
achieve smooth, rapid, high-volume flow
• Auto plants, cafeterias
 Process Layout
– Layout that can handle varied processing requirements
• Tool and die shops, university departments
 Fixed Position Layout
– Layout in which the product or project remains stationary,
and workers, materials, and equipment are moved as
needed
• Building projects, disabled patients at hospitals
• Combination Layouts
21
A Flow Line for Production or
Service
Flow Shop or Assembly Line Work Flow
Raw
materials
or customer
Finished
item
Station
2
Station
3
Station
4
Material
and/or
labor
Station
1
Material
and/or
labor
Material
and/or
labor
Material
and/or
labor
22
A U-Shaped Production Line
Advantage: more compact, increased communication
facilitating team work, minimize the material handling
23
Dept. A
Dept. B Dept. D
Dept. C
Dept. F
Dept. E
Used for Intermittent processing
Process Layout
(functional)
Process Layout
24
Process Layout
Process Layout - work travels
to dedicated process centers
Milling
Assembly
& Test
Grinding
Drilling Plating
25
Layout types: Product or Process
Make your pick
A
B
A
B
26
Process vs Layout types
 Job Shop
 Project
 Repetitive
 Product
 Process
 Fixed-point
Match?
27
Product layout
Advantages
 High volume
 Low unit cost
 Low labor skill needed
 Low material handling
 High efficiency and
utilization
 Simple routing and
scheduling
 Simple to track and
control
Disadvantages
 Lacks flexibility
 Volume, design, mix
 Boring for labor
 Low motivation
 Low worker enrichment
 Can not accommodate
partial shut
downs/breakdowns
 Individual incentive
plans are not possible
28
Cellular Layouts
 Cellular Manufacturing
– Layout in which machines are grouped into a cell that can
process items that have similar processing requirements.
A product layout is visible inside each cell.
 Group Technology
– The grouping into part families of items with similar
design or manufacturing characteristics. Each cell is
assigned a family for production. This limits the
production variability inside cells, hence allowing for a
product layout.
29
A Group of Parts
Similar manufacturing characters
30
Dimension Process Cellular
Number of moves
between departments
many few
Travel distances longer shorter
Travel paths variable fixed
Job waiting times greater shorter
Amount of work in
process
higher lower
Supervision difficulty higher lower
Scheduling complexity higher lower
Equipment utilization Lower? Higher?
Process vs. Cellular Layouts
31
Process Layout
Gear
cutting
Mill Drill
Lathes
Grind
Heat
treat
Assembly
111
333
222
444
222
111
444
111 333
1111 2222
222
3333
111
444
111
333333333
44444
333333
22222
32
Cellular Manufacturing Layout
-1111 -1111
222222222 - 2222
Assembly
3333333333 - 3333
44444444444444 - 4444
Lathe
Lathe
Mill
Mill
Mill
Mill
Drill
Drill
Drill
Heat
treat
Heat
treat
Heat
treat
Gear
cut
Gear
cut
Grind
Grind
33
Basic Layout Formats
 Group Technology Layout
Similar to cellular layout
 Fixed Position Layout
– e.g. Shipbuilding
Part Family W Part Family X
Part Family Y
Part Family Z
Assemble Y,W Assemble X,Z
Final Product
34
Fixed-Position and combination
Layout
 Fixed-Position Layout:
item being worked on remains stationary, and
workers, materials and equipment are moved
as needed.
Example: buildings, dams, power plants
 Combination Layouts:
combination of three pure types.
Example: hospital: process and fixed position.
35
 Warehouse and storage layouts
Issue: Frequency of orders
 Retail layouts
Issue: Traffic patterns and traffic flows
 Office layouts
Issue: Information transfer, openness
Service Layouts
36
Design Product Layouts: Line
Balancing
Line balancing is the process of assigning tasks to workstations
in such a way that the workstations have approximately the same
processing time requirements. This results in the minimized idle ti
along the line and high utilization of labor and equipment.
Cycle time is the maximum time allowed at each workstation
to complete its set of tasks on a single unit
What is the cycle time for the system above?
Worker 1 Worker 2
4 tasks 2 tasks
Each task takes 1 minutes, how to balance?
37
Parallel Workstations
1 min.2 min.1 min.1 min.
30/hr. 30/hr. 30/hr. 30/hr.
1 min.
2 min.
1 min.1 min.
60/hr.
30/hr. 30/hr.
60/hr.
2 min.
30/hr.
30/hr.
Bottleneck
Parallel Workstations
38
The obstacle
 The difficulty to forming task bundles that have the
same duration.
 The difference among the elemental task lengths can
not be overcome by grouping task.
 Ex: Can you split the tasks with task times {1,2,3,4} into
two groups such that total task time in each group is the
same?
 Ex: Try the above question with {1,2,2,4}
 A required technological sequence prohibit the
desirable task combinations
 Ex: Let the task times be {1,2,3,4} but suppose that the
task with time 1 can only done after the task with time 4 is
completed. Moreover task with time 3 can only done after
the task with time 2 is completed. How to group?
39
Cycle time is the maximum time allowed at each
workstation to complete its tasks on a unit.
Cycle Time
The major determinant: cycle time
Minimum cycle time: longest task time by
assigning each task to a workstation
Maximum cycle time: sum of the task time by
assigning all tasks to a workstation
40
Determine Maximum Output
Cycle Time: Time to process 1 unit
Example: If a student can answer a multiple choice question in 2 minutes but gets a
test with 30 questions and is given only 30 minutes then
OT=30 minutes; D=30
Desired cycle time=1 minute < 2 minutes = Cycle time from the process capability
OT
D
OT
D
CT
OT
D
CT
OT
D
CT
:
:
OperatingTimePerDay
DesiredOutputRate
DesiredCycleTime
CycleTime FromProcessDesign
Can produce at the desired level, design is feasible
Cannot produce at the desired level, design is infeasible
=
= ←
≥
<
41
of Workstations Required:
Efficiency
stask timeofsum=t
CT
t
productafortimeAvailabale
productafortask timeTotal
OT/D
t
N
OT
t)(D)(
dayaintimeAvailabale
dayainproducedproductsallfortask timeTotal
=N
min
min
∑
∑∑
∑
===
=
Example: Students can answer a multiple choice question in 2 minutes but given a
test with 30 questions and is given only 30 minutes. What is the minimum number of
students to collaborate to answer all the questions in the exam?
Total operation (task) time = 60 minutes = 30 x 2 minutes
Operating time=30 minutes
60/3=2 students must collaborate. This Nmin below.
42
Percent idle time =
Idle time per cycle
(N)(CT)
Efficiency = 1 – Percent idle time
Percent Idle Time
43
Example 1: Precedence Diagram
Precedence diagram: Tool used in line
balancing to display elemental tasks and
sequence requirements
a b
c d e
0.1 min.
0.7 min.
1.0 min.
0.5 min. 0.2 min.
44
Example 1: Assembly Line
Balancing
 Arrange tasks shown in the previous slide into
workstations.
– Use a cycle time of 1.0 minute
• Every 1 minute, 1 unit must be completed
– Rule: Assign tasks in order of the most number of
followers
• If you are to choose between a and c, choose a
• If you are to choose between b and d, choose b
• Number of followers: a:3, b:2, c:2, d:1, e:0
– Eligible task fits into the remaining time and all of
its predecessors are assigned.
45
Assigning operations by the
number of followers
Work-
Station
Time
Remaining Eligible
Assign
Task
Station
Idle Time
1 1.0
.9
.2
a,c
c
none
a
c
- .2
2 1.0
0
b
none
b
- 0
3 1.0
.5
.3
d
e
-
d
e
- .3
.5
- Eligible operation fits into the remaining time and its predecessors are already assigned.
- What is the minimum cycle time possible for this example?
46
Calculate Percent Idle Time
mestation tiTotal(N)(CT)
cycleaduringstationsattimesidleofSum
=timeidlePercent
=
%7.16167.0
(3)(1)
0.300.2
=timeidlePercent ==
++
Efficiency=1-percent idle time=1-0.167=0.833=83.3%
47
Line Balancing Heuristic Rules
 Assign tasks in order of most following
tasks.
 Assign task in the order of the greatest task
time.
 Assign tasks in order of greatest positional
weight.
– Positional weight is the sum of each task’s
time and the times of all following tasks.
48
Solution to Example 1. Assigning
operations using their task times.
Work-
Station
Time
Remaining Eligible
Assign
Task
Station
Idle Time
1 1.0
.9
.2
a,c
a
none
c
a
- .2
2 1.0
0
b
none
b
- 0
3 1.0
.5
.3
d
e
-
d
e
- .3
.5
Eligible operation fits into the remaining time and its predecessors are already assigned.
49
Positional Weights
Assign tasks in order of greatest positional weight.
– Positional weight is the sum of each task’s time
and the times of all following tasks.
– a:1.8 mins; b: 1.7 mins; c:1.4 mins; d: 0.7 mins;
e:0.2 mins.
50
Solution to Example 1. Assigning
operations using their task times.
Work-
Station
Time
Remaining Eligible
Assign
Task
Station
Idle Time
1 1.0
.9
.2
a,c
c
none
a
c
- .2
2 1.0
0
b
none
b
- 0
3 1.0
.5
.3
d
e
-
d
e
- .3
.5
Eligible operation fits into the remaining time and its predecessors are already assigned.
51
c d
a b e
f g h
0.2 0.2 0.3
0.8 0.6
1.0 0.4 0.3
Example 2
52
Station 1 Station 2 Station 3 Station 4
a b e
f
d
g h
c
Solution to Example 2
53
 Requirements:
 List of departments
 Shape requirements
 Projection of work flows
 One way vs. two way: Packaging and final assembly.
 Distance between locations
 One way vs. two way: Conveyors, Elevators.
 Amount of money to be invested
 List of special considerations
 Technical, Environmental requirements
Designing Process Layouts
54
Example 3:
Locate 3 departments to 3 sites
 Distances:
in meters
 Work Flow:
in kilos
FromTo A B C
A - 20 40
B 20 - 30
C 40 30 -
FromTo 1 2 3
1 - 10 80
2 20 - 30
3 90 70 -
55
Example 3
 Mutual flow:
 Closeness graph:
FromTo 1 2 3
1 - - -
2 30 - -
3 170 100 -
3
1 2
56
 Create Layout Alternatives
 Find the one which minimizes transportation
costs and distance traveled
Designing Process Layouts
57
Example 3: Layout Alternative 1
1 3 2
30
170 100
A B C
Total Distance Traveled by Material=7600 m
58
Example 3: Layout Alternative 2
1 2 3
170
30 100
A B C
Total Distance Traveled by Material=10400 m
59
Closeness Rating: multiple criteria
60
Muther Grid
 Allow multiple objectives and subjective
input from analysis or manager to indicate the
relative importance of each combination of
department pairs.
 Subjective inputs are imprecise and unreliable
61
Example 4
 Heuristic: assign
critical departments
first. The critical
departments are those
with X and A ratings.
 Solution:
As Xs
1-2 1-4
1-3 3-6
2-6 3-4
3-5
4-6
5-6
62
Example 4
 Begin with most
frequently in the A list
(6)
 Add remaining As to
the main cluster
 Graphically portray Xs
 Fit the cluster into the
arrangement
6
2 4
5
1
3
1 2 6
3 5 4
63
Summary
 Process Selection
Objective, Implication, types
 Product Layout
Line balancing: procedures and measures
 Process layout
Information requirements, measures
From to chart and Muther grid
64
Tasks times and predecessors for
an operation
Task label Time Predecessors
A 2 None
B 7 A
C 5 None
D 2 None
E 15 C,D
F 7 A,E
G 6 None
H 4 B,G
I 9 A
J 10 None
K 4 None
L 8 J,K
M 6 A,L
N 15 F,H,I,M
C
D
A
G
J
K
E
L
F
B
I
M
H N
65
Recitation example
 Find a workstation assignment by taking
cycle time=17 minutes by assigning in the
order of the greatest task time.
 Can you find an assignment that uses only six
stations and meets 17 minute cycle time
requirement.
 See the solution in the next recitation.
66
Station
Time
remaining Eligible Assign
Idle
Time
1 17 C,D,A,G,J,K J
7 C,D,A,G,K G 1
2 17 C,D,A,K C
12 D,A,K K
8 D,A,L L 0
3 17 D,A A
15 D,B,I,M I
6 D,B,M M 0
4 17 D,B B
10 D,H H
6 D D 4
5 17 E E 2
6 17 F F 10
7 17 N N 2
Solution 1: Greatest task time first
A 2 None
B 7 A
C 5 None
D 2 None
E 15 C,D
F 7 A,E
G 6 None
H 4 B,G
I 9 A
J 10 None
K 4 None
L 8 J,K
M 6 A,L
N 15 F,H,I,M
67
Solution 2: A heuristic
 Workstation Assignment
that uses only six stations
and meets 17 minute
cycle time requirement
STATION NO OPERATIONS STATION TIME
1 C,D,G,K 17
2 E,A 17
3 J,B 17
4 L,I 17
5 F,H,M 17
6 N 15
68
OPERATION
SUCCESSORS'
TASK TIME TASK TIME
C 42 5
D 39 2
J 39 10
E 37 15
K 33 4
L 29 8
A 28 2
B 26 7
G 25 6
I 24 9
F 22 7
M 21 6
H 19 4
N 15 15
Solution 3: Greatest positional
weight first
STATION NO OPERATIONS
STATION
TIME
1 C,D,J 17
2 E,A 17
3 K,L 12
4 B,G,H 17
5 I,F 16
6 M 6
7 N 15
69
Practice Questions
 True/False
 General, Job-Shop systems have a lower unit cost
than continuous systems do because continuous
systems use costly specialized equipment.
 In cellular manufacturing, machines and equipment
are grouped by type (e.g., all grinders are grouped
into a cell).
Answer: False Page: 218
Answer: False Page: 233
70
Practice Questions
1. Layout planning is required because of:
 Efficient operations
 Accidents or safety hazards
 New products or services
 Morale problems
 A) I and II
 B) II and IV
 C) I and III
 D) II, III, and IV
 E) I, II, III, and IV
Answer: D Page: 227
71
Practice Questions
2. Which type of processing system tends to
produce the most product variety?
 A)Assembly
 B)Job-Shop
 C)Batch
 D)Continuous
 E) Project
•Answer: B Page: 220
72
Practice Questions
3. A production line is to be designed for a job
with three tasks. The task times are 0.3
minutes, 1.4 minutes, and 0.7 minutes. The
minimum cycle time in minutes, is:
 A)0.3
 B)0.7
 C)1.4
 D)2.4
 E) 0.8 •Answer: C

More Related Content

What's hot

What's hot (20)

Facility location and layout planning
Facility location and layout planningFacility location and layout planning
Facility location and layout planning
 
Cellular LayOut
Cellular LayOutCellular LayOut
Cellular LayOut
 
S ch6
S ch6S ch6
S ch6
 
Facility location & steps on location selection
Facility location & steps on location selectionFacility location & steps on location selection
Facility location & steps on location selection
 
Facility Capacity & Layout Planning
Facility Capacity & Layout PlanningFacility Capacity & Layout Planning
Facility Capacity & Layout Planning
 
Manufacturing systems
Manufacturing systems Manufacturing systems
Manufacturing systems
 
Facility Layout
Facility LayoutFacility Layout
Facility Layout
 
Production and operation management
Production and operation management Production and operation management
Production and operation management
 
PRODUCTION SYSTEMS
PRODUCTION SYSTEMSPRODUCTION SYSTEMS
PRODUCTION SYSTEMS
 
Design of process layout
Design of process layoutDesign of process layout
Design of process layout
 
Job shop production system final
Job shop production system finalJob shop production system final
Job shop production system final
 
What is strategic fit
What is strategic fitWhat is strategic fit
What is strategic fit
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
 
Production management
Production managementProduction management
Production management
 
types of production system
types of production systemtypes of production system
types of production system
 
Plant layout
Plant layoutPlant layout
Plant layout
 
Design of supply chain networks
Design of supply chain networksDesign of supply chain networks
Design of supply chain networks
 
Production and operations management
Production and operations management Production and operations management
Production and operations management
 
Production and operations management
Production and operations managementProduction and operations management
Production and operations management
 
PPT ON Just in time technique (JIT)
PPT ON Just in time technique (JIT)PPT ON Just in time technique (JIT)
PPT ON Just in time technique (JIT)
 

Viewers also liked

Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout StrategiesJoanmaines
 
Manufacturing systems powerpoint
Manufacturing systems powerpointManufacturing systems powerpoint
Manufacturing systems powerpointkertisha
 
Layout types
Layout typesLayout types
Layout typesSartaj
 
Plant layout and its types
Plant layout and its typesPlant layout and its types
Plant layout and its typesHammaduddin
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Pathdmdk12
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network DiagramsNicola2903
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by meAnkit Walia
 

Viewers also liked (17)

Process And Layout Strategies
Process And Layout StrategiesProcess And Layout Strategies
Process And Layout Strategies
 
Location model smm
Location model smmLocation model smm
Location model smm
 
Manufacturing systems powerpoint
Manufacturing systems powerpointManufacturing systems powerpoint
Manufacturing systems powerpoint
 
Plant location & layout
Plant location & layoutPlant location & layout
Plant location & layout
 
Plant location & layout design
Plant location & layout designPlant location & layout design
Plant location & layout design
 
Network Techniques
Network TechniquesNetwork Techniques
Network Techniques
 
Layout types
Layout typesLayout types
Layout types
 
Plant layout and its types
Plant layout and its typesPlant layout and its types
Plant layout and its types
 
Types of layouts
Types of layoutsTypes of layouts
Types of layouts
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
Plant layout
Plant layoutPlant layout
Plant layout
 
Pert
PertPert
Pert
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Plant location
Plant locationPlant location
Plant location
 
Plant layout ppt by me
Plant layout ppt by mePlant layout ppt by me
Plant layout ppt by me
 
Layout strategies
Layout strategiesLayout strategies
Layout strategies
 

Similar to Process design layout

Process design layout ppt bec doms
Process design layout ppt bec domsProcess design layout ppt bec doms
Process design layout ppt bec domsBabasab Patil
 
Process Selection & Facility Layout.ppt
Process Selection & Facility Layout.pptProcess Selection & Facility Layout.ppt
Process Selection & Facility Layout.pptRenu Lamba
 
om ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptxom ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptxYosefSisay3
 
Product service -profiling
Product service -profilingProduct service -profiling
Product service -profilingMeenakshi Singh
 
Lecture on Production management- Plant layout
Lecture on Production management- Plant layoutLecture on Production management- Plant layout
Lecture on Production management- Plant layoutSujeet TAMBE
 
Process Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular ManufacturingProcess Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular ManufacturingDrGopiKrishnanPonnus
 
Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.Pramod Patil
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aRai University
 
Mba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aMba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aRai University
 
Operation management
Operation managementOperation management
Operation managementMamta Karanji
 
Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Ishan Parekh
 

Similar to Process design layout (20)

Layout
LayoutLayout
Layout
 
layout.ppt
layout.pptlayout.ppt
layout.ppt
 
Process design layout ppt bec doms
Process design layout ppt bec domsProcess design layout ppt bec doms
Process design layout ppt bec doms
 
Facility Layout,PPT.pptx
Facility Layout,PPT.pptxFacility Layout,PPT.pptx
Facility Layout,PPT.pptx
 
Process Selection & Facility Layout.ppt
Process Selection & Facility Layout.pptProcess Selection & Facility Layout.ppt
Process Selection & Facility Layout.ppt
 
Plant layouts(presentation)
Plant layouts(presentation)Plant layouts(presentation)
Plant layouts(presentation)
 
om ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptxom ch 2.5 Layouting.pptx
om ch 2.5 Layouting.pptx
 
Product service -profiling
Product service -profilingProduct service -profiling
Product service -profiling
 
Lecture on Production management- Plant layout
Lecture on Production management- Plant layoutLecture on Production management- Plant layout
Lecture on Production management- Plant layout
 
Om plant_layout
Om   plant_layoutOm   plant_layout
Om plant_layout
 
Process Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular ManufacturingProcess Planning & Cost Estimation - Cellular Manufacturing
Process Planning & Cost Estimation - Cellular Manufacturing
 
Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.Implementation of Business Process Reengineering in Thermax Ltd.
Implementation of Business Process Reengineering in Thermax Ltd.
 
Facility+layout
Facility+layoutFacility+layout
Facility+layout
 
Process Strategy
Process StrategyProcess Strategy
Process Strategy
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection a
 
POM .ppt
POM .pptPOM .ppt
POM .ppt
 
Mba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aMba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout a
 
plant layout
plant layoutplant layout
plant layout
 
Operation management
Operation managementOperation management
Operation management
 
Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)Group Layout (Manufacturing Management)
Group Layout (Manufacturing Management)
 

Recently uploaded

Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in designnooreen17
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Yantram Animation Studio Corporation
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfShivakumar Viswanathan
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxmapanig881
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改yuu sss
 
Create Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdfCreate Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdfworkingdev2003
 
General Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptxGeneral Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptxmarckustrevion
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptMaryamAfzal41
 
韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作7tz4rjpd
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一F dds
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degreeyuu sss
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCRdollysharma2066
 
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...ttt fff
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfAayushChavan5
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...katerynaivanenko1
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubaikojalkojal131
 

Recently uploaded (20)

Design principles on typography in design
Design principles on typography in designDesign principles on typography in design
Design principles on typography in design
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
Unveiling the Future: Columbus, Ohio Condominiums Through the Lens of 3D Arch...
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdf
 
Untitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptxUntitled presedddddddddddddddddntation (1).pptx
Untitled presedddddddddddddddddntation (1).pptx
 
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
1比1办理美国北卡罗莱纳州立大学毕业证成绩单pdf电子版制作修改
 
Call Girls in Pratap Nagar, 9953056974 Escort Service
Call Girls in Pratap Nagar,  9953056974 Escort ServiceCall Girls in Pratap Nagar,  9953056974 Escort Service
Call Girls in Pratap Nagar, 9953056974 Escort Service
 
Create Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdfCreate Web Pages by programming of your chice.pdf
Create Web Pages by programming of your chice.pdf
 
General Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptxGeneral Knowledge Quiz Game C++ CODE.pptx
General Knowledge Quiz Game C++ CODE.pptx
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis ppt
 
韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作韩国SKKU学位证,成均馆大学毕业证书1:1制作
韩国SKKU学位证,成均馆大学毕业证书1:1制作
 
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
办理学位证(SFU证书)西蒙菲莎大学毕业证成绩单原版一比一
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
昆士兰大学毕业证(UQ毕业证)#文凭成绩单#真实留信学历认证永久存档
 
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
原版美国亚利桑那州立大学毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#degree
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
 
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
毕业文凭制作#回国入职#diploma#degree美国威斯康星大学欧克莱尔分校毕业证成绩单pdf电子版制作修改#毕业文凭制作#回国入职#diploma#...
 
Pharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdfPharmaceutical Packaging for the elderly.pdf
Pharmaceutical Packaging for the elderly.pdf
 
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
 

Process design layout

  • 2. 2 Introduction • Make or Buy? – Available capacity, excess capacity – Expertise, knowledge, know-how exists? – Quality Consideration, specialized firms, control over quality if in-house – The nature of demand, aggregation – Cost Make some components buy remaining
  • 3. 3 Introduction  Process selection  Deciding on the way production of goods or services will be organized  Major implications  Capacity planning  Layout of facilities  Equipment, Capital- equipment or labor intensive  Design of work
  • 4. 4 Forecasting Product and Service Design Technological Change Capacity Planning Process Selection Facilities and Equipment Layout Work Design Figure 6.1 Process Selection and System Design
  • 5. 5 Process Types • Job Shops: Small lots, low volume, general equipment, skilled workers, high-variety. Ex: tool and die shop, veterinarian’s office • Batch Processing: Moderate volume and variety. Variety among batches but not inside. Ex:paint production , BA3352 sections • Repetitive/Assembly: Semicontinuous, high volume of standardized items, limited variety. Ex: auto plants, cafeteria • Continuous Processing: Very high volume an no variety. Ex: steel mill, chemical plants • Projects: Nonroutine jobs. Ex: preparing BA3352 midterm
  • 6. 6  Variety of products and services  How much  Flexibility of the process; volume, mix, technology and design  What type and degree  Volume  Expected output Job Shop Batch Repetitive Continuous Questions Before Selecting A Process
  • 7. 7 Dimension Job Shop Batch Repetitive Continuous Job variety Very High Moderate Low Very low Process flexibility Very High Moderate Low Very low Unit cost Very High Moderate Low Very low Volume of output Very low Low High Very high Product – Process Matrix
  • 8. 8 Product Variety High Moderate Low Very Low Equipment flexibility High Moderate Low Very Low Low Volume Moderate Volume High Volume Very high Volume Job Shop Batch Repetitive assembly Continuous Flow Variety, Flexibility, & Volume
  • 9. 9 Process Type High variety Low variety Job Shop Appliance repair Emergency room Batch Commercial bakery Classroom Lecture Repetitive Automotive assembly Automatic carwash Continuous (flow) Oil refinery Water purification Product – Process Matrix
  • 10. 10 Product-Process Matrix Flexibility-Quality Dependability-Cost Continuous Flow Assembly Line Batch Job Shop Low Volume One of a Kind Multiple Products, Low Volume Few Major Products, Higher Volume High Volume, High Standard- ization Book Writing Movie Theaters Automobile Assembly Sugar Refinery Flexibility- Quality Dependability- Cost
  • 11. 11 Fixed automation: Low production cost and high volume but with minimal variety and high changes cost  Assembly line Programmable automation: Economically producing a wide variety of low volume products in small batches  Computer-aided design and manufacturing systems (CAD/CAM)  Numerically controlled (NC) machines / CNC  Industrial robots (arms) Flexible automation: Require less changeover time and allow continuous operation of equipment and product variety  Manufacturing cell  Flexible manufacturing systems: Use of high automation to achieve repetitive process efficiency with job shop process • Automated retrieval and storage • Automated guided vehicles  Computer-integrated manufacturing (CIM) Automation: Machinery that has sensing and control devices that enables it to operate
  • 13. 13 Flexible Manufacturing System  Group of machines that include supervisory computer control, automatic material handling, robots and other processing equipment  Advantage: reduce labor costs and more consistent quality lower capital investment and higher flexibility than hard automation relative quick changeover time  Disadvantage used for a family of products and require longer planning and development times
  • 14. 14 Computer-integrated manufacturing  Use integrating computer system to link a broad range of manufacturing activities, including engineering design, purchasing, order processing and production planning and control  Advantage: rapid response to customer order and product change, reduce direct labor cost, high quality
  • 15. 15  Service blueprint: A method used in service design to describe and analyze a proposed service. Flowchart: Service Blueprint Begin Turn on laptop Connect to LCD A A View on Yes Lecture No Begin
  • 16. 16  Establish boundaries  Identify steps involved  Prepare a flowchart  Identify potential failure points  Establish a time frame for operations  Analyze profitability Service Process Design
  • 17. 17  Layout: the configuration of departments, work centers, and equipment,  Whose design involves particular emphasis on movement of work (customers or materials) through the system  Importance of layout  Requires substantial investments of money and effort  Involves long-term commitments  Has significant impact on cost and efficiency of short- term operations Layout
  • 18. 18 Inefficient operations For Example: High Cost Bottlenecks Changes in the design of products or services The introduction of new products or services Accidents Safety hazards The Need for Layout Decisions
  • 19. 19 Changes in environmental or other legal requirements Changes in volume of output or mix of products Changes in methods and equipment Morale problems The Need for Layout Design (Cont’d)
  • 20. 20 Basic Layout Types  Product Layout – Layout that uses standardized processing operations to achieve smooth, rapid, high-volume flow • Auto plants, cafeterias  Process Layout – Layout that can handle varied processing requirements • Tool and die shops, university departments  Fixed Position Layout – Layout in which the product or project remains stationary, and workers, materials, and equipment are moved as needed • Building projects, disabled patients at hospitals • Combination Layouts
  • 21. 21 A Flow Line for Production or Service Flow Shop or Assembly Line Work Flow Raw materials or customer Finished item Station 2 Station 3 Station 4 Material and/or labor Station 1 Material and/or labor Material and/or labor Material and/or labor
  • 22. 22 A U-Shaped Production Line Advantage: more compact, increased communication facilitating team work, minimize the material handling
  • 23. 23 Dept. A Dept. B Dept. D Dept. C Dept. F Dept. E Used for Intermittent processing Process Layout (functional) Process Layout
  • 24. 24 Process Layout Process Layout - work travels to dedicated process centers Milling Assembly & Test Grinding Drilling Plating
  • 25. 25 Layout types: Product or Process Make your pick A B A B
  • 26. 26 Process vs Layout types  Job Shop  Project  Repetitive  Product  Process  Fixed-point Match?
  • 27. 27 Product layout Advantages  High volume  Low unit cost  Low labor skill needed  Low material handling  High efficiency and utilization  Simple routing and scheduling  Simple to track and control Disadvantages  Lacks flexibility  Volume, design, mix  Boring for labor  Low motivation  Low worker enrichment  Can not accommodate partial shut downs/breakdowns  Individual incentive plans are not possible
  • 28. 28 Cellular Layouts  Cellular Manufacturing – Layout in which machines are grouped into a cell that can process items that have similar processing requirements. A product layout is visible inside each cell.  Group Technology – The grouping into part families of items with similar design or manufacturing characteristics. Each cell is assigned a family for production. This limits the production variability inside cells, hence allowing for a product layout.
  • 29. 29 A Group of Parts Similar manufacturing characters
  • 30. 30 Dimension Process Cellular Number of moves between departments many few Travel distances longer shorter Travel paths variable fixed Job waiting times greater shorter Amount of work in process higher lower Supervision difficulty higher lower Scheduling complexity higher lower Equipment utilization Lower? Higher? Process vs. Cellular Layouts
  • 32. 32 Cellular Manufacturing Layout -1111 -1111 222222222 - 2222 Assembly 3333333333 - 3333 44444444444444 - 4444 Lathe Lathe Mill Mill Mill Mill Drill Drill Drill Heat treat Heat treat Heat treat Gear cut Gear cut Grind Grind
  • 33. 33 Basic Layout Formats  Group Technology Layout Similar to cellular layout  Fixed Position Layout – e.g. Shipbuilding Part Family W Part Family X Part Family Y Part Family Z Assemble Y,W Assemble X,Z Final Product
  • 34. 34 Fixed-Position and combination Layout  Fixed-Position Layout: item being worked on remains stationary, and workers, materials and equipment are moved as needed. Example: buildings, dams, power plants  Combination Layouts: combination of three pure types. Example: hospital: process and fixed position.
  • 35. 35  Warehouse and storage layouts Issue: Frequency of orders  Retail layouts Issue: Traffic patterns and traffic flows  Office layouts Issue: Information transfer, openness Service Layouts
  • 36. 36 Design Product Layouts: Line Balancing Line balancing is the process of assigning tasks to workstations in such a way that the workstations have approximately the same processing time requirements. This results in the minimized idle ti along the line and high utilization of labor and equipment. Cycle time is the maximum time allowed at each workstation to complete its set of tasks on a single unit What is the cycle time for the system above? Worker 1 Worker 2 4 tasks 2 tasks Each task takes 1 minutes, how to balance?
  • 37. 37 Parallel Workstations 1 min.2 min.1 min.1 min. 30/hr. 30/hr. 30/hr. 30/hr. 1 min. 2 min. 1 min.1 min. 60/hr. 30/hr. 30/hr. 60/hr. 2 min. 30/hr. 30/hr. Bottleneck Parallel Workstations
  • 38. 38 The obstacle  The difficulty to forming task bundles that have the same duration.  The difference among the elemental task lengths can not be overcome by grouping task.  Ex: Can you split the tasks with task times {1,2,3,4} into two groups such that total task time in each group is the same?  Ex: Try the above question with {1,2,2,4}  A required technological sequence prohibit the desirable task combinations  Ex: Let the task times be {1,2,3,4} but suppose that the task with time 1 can only done after the task with time 4 is completed. Moreover task with time 3 can only done after the task with time 2 is completed. How to group?
  • 39. 39 Cycle time is the maximum time allowed at each workstation to complete its tasks on a unit. Cycle Time The major determinant: cycle time Minimum cycle time: longest task time by assigning each task to a workstation Maximum cycle time: sum of the task time by assigning all tasks to a workstation
  • 40. 40 Determine Maximum Output Cycle Time: Time to process 1 unit Example: If a student can answer a multiple choice question in 2 minutes but gets a test with 30 questions and is given only 30 minutes then OT=30 minutes; D=30 Desired cycle time=1 minute < 2 minutes = Cycle time from the process capability OT D OT D CT OT D CT OT D CT : : OperatingTimePerDay DesiredOutputRate DesiredCycleTime CycleTime FromProcessDesign Can produce at the desired level, design is feasible Cannot produce at the desired level, design is infeasible = = ← ≥ <
  • 41. 41 of Workstations Required: Efficiency stask timeofsum=t CT t productafortimeAvailabale productafortask timeTotal OT/D t N OT t)(D)( dayaintimeAvailabale dayainproducedproductsallfortask timeTotal =N min min ∑ ∑∑ ∑ === = Example: Students can answer a multiple choice question in 2 minutes but given a test with 30 questions and is given only 30 minutes. What is the minimum number of students to collaborate to answer all the questions in the exam? Total operation (task) time = 60 minutes = 30 x 2 minutes Operating time=30 minutes 60/3=2 students must collaborate. This Nmin below.
  • 42. 42 Percent idle time = Idle time per cycle (N)(CT) Efficiency = 1 – Percent idle time Percent Idle Time
  • 43. 43 Example 1: Precedence Diagram Precedence diagram: Tool used in line balancing to display elemental tasks and sequence requirements a b c d e 0.1 min. 0.7 min. 1.0 min. 0.5 min. 0.2 min.
  • 44. 44 Example 1: Assembly Line Balancing  Arrange tasks shown in the previous slide into workstations. – Use a cycle time of 1.0 minute • Every 1 minute, 1 unit must be completed – Rule: Assign tasks in order of the most number of followers • If you are to choose between a and c, choose a • If you are to choose between b and d, choose b • Number of followers: a:3, b:2, c:2, d:1, e:0 – Eligible task fits into the remaining time and all of its predecessors are assigned.
  • 45. 45 Assigning operations by the number of followers Work- Station Time Remaining Eligible Assign Task Station Idle Time 1 1.0 .9 .2 a,c c none a c - .2 2 1.0 0 b none b - 0 3 1.0 .5 .3 d e - d e - .3 .5 - Eligible operation fits into the remaining time and its predecessors are already assigned. - What is the minimum cycle time possible for this example?
  • 46. 46 Calculate Percent Idle Time mestation tiTotal(N)(CT) cycleaduringstationsattimesidleofSum =timeidlePercent = %7.16167.0 (3)(1) 0.300.2 =timeidlePercent == ++ Efficiency=1-percent idle time=1-0.167=0.833=83.3%
  • 47. 47 Line Balancing Heuristic Rules  Assign tasks in order of most following tasks.  Assign task in the order of the greatest task time.  Assign tasks in order of greatest positional weight. – Positional weight is the sum of each task’s time and the times of all following tasks.
  • 48. 48 Solution to Example 1. Assigning operations using their task times. Work- Station Time Remaining Eligible Assign Task Station Idle Time 1 1.0 .9 .2 a,c a none c a - .2 2 1.0 0 b none b - 0 3 1.0 .5 .3 d e - d e - .3 .5 Eligible operation fits into the remaining time and its predecessors are already assigned.
  • 49. 49 Positional Weights Assign tasks in order of greatest positional weight. – Positional weight is the sum of each task’s time and the times of all following tasks. – a:1.8 mins; b: 1.7 mins; c:1.4 mins; d: 0.7 mins; e:0.2 mins.
  • 50. 50 Solution to Example 1. Assigning operations using their task times. Work- Station Time Remaining Eligible Assign Task Station Idle Time 1 1.0 .9 .2 a,c c none a c - .2 2 1.0 0 b none b - 0 3 1.0 .5 .3 d e - d e - .3 .5 Eligible operation fits into the remaining time and its predecessors are already assigned.
  • 51. 51 c d a b e f g h 0.2 0.2 0.3 0.8 0.6 1.0 0.4 0.3 Example 2
  • 52. 52 Station 1 Station 2 Station 3 Station 4 a b e f d g h c Solution to Example 2
  • 53. 53  Requirements:  List of departments  Shape requirements  Projection of work flows  One way vs. two way: Packaging and final assembly.  Distance between locations  One way vs. two way: Conveyors, Elevators.  Amount of money to be invested  List of special considerations  Technical, Environmental requirements Designing Process Layouts
  • 54. 54 Example 3: Locate 3 departments to 3 sites  Distances: in meters  Work Flow: in kilos FromTo A B C A - 20 40 B 20 - 30 C 40 30 - FromTo 1 2 3 1 - 10 80 2 20 - 30 3 90 70 -
  • 55. 55 Example 3  Mutual flow:  Closeness graph: FromTo 1 2 3 1 - - - 2 30 - - 3 170 100 - 3 1 2
  • 56. 56  Create Layout Alternatives  Find the one which minimizes transportation costs and distance traveled Designing Process Layouts
  • 57. 57 Example 3: Layout Alternative 1 1 3 2 30 170 100 A B C Total Distance Traveled by Material=7600 m
  • 58. 58 Example 3: Layout Alternative 2 1 2 3 170 30 100 A B C Total Distance Traveled by Material=10400 m
  • 60. 60 Muther Grid  Allow multiple objectives and subjective input from analysis or manager to indicate the relative importance of each combination of department pairs.  Subjective inputs are imprecise and unreliable
  • 61. 61 Example 4  Heuristic: assign critical departments first. The critical departments are those with X and A ratings.  Solution: As Xs 1-2 1-4 1-3 3-6 2-6 3-4 3-5 4-6 5-6
  • 62. 62 Example 4  Begin with most frequently in the A list (6)  Add remaining As to the main cluster  Graphically portray Xs  Fit the cluster into the arrangement 6 2 4 5 1 3 1 2 6 3 5 4
  • 63. 63 Summary  Process Selection Objective, Implication, types  Product Layout Line balancing: procedures and measures  Process layout Information requirements, measures From to chart and Muther grid
  • 64. 64 Tasks times and predecessors for an operation Task label Time Predecessors A 2 None B 7 A C 5 None D 2 None E 15 C,D F 7 A,E G 6 None H 4 B,G I 9 A J 10 None K 4 None L 8 J,K M 6 A,L N 15 F,H,I,M C D A G J K E L F B I M H N
  • 65. 65 Recitation example  Find a workstation assignment by taking cycle time=17 minutes by assigning in the order of the greatest task time.  Can you find an assignment that uses only six stations and meets 17 minute cycle time requirement.  See the solution in the next recitation.
  • 66. 66 Station Time remaining Eligible Assign Idle Time 1 17 C,D,A,G,J,K J 7 C,D,A,G,K G 1 2 17 C,D,A,K C 12 D,A,K K 8 D,A,L L 0 3 17 D,A A 15 D,B,I,M I 6 D,B,M M 0 4 17 D,B B 10 D,H H 6 D D 4 5 17 E E 2 6 17 F F 10 7 17 N N 2 Solution 1: Greatest task time first A 2 None B 7 A C 5 None D 2 None E 15 C,D F 7 A,E G 6 None H 4 B,G I 9 A J 10 None K 4 None L 8 J,K M 6 A,L N 15 F,H,I,M
  • 67. 67 Solution 2: A heuristic  Workstation Assignment that uses only six stations and meets 17 minute cycle time requirement STATION NO OPERATIONS STATION TIME 1 C,D,G,K 17 2 E,A 17 3 J,B 17 4 L,I 17 5 F,H,M 17 6 N 15
  • 68. 68 OPERATION SUCCESSORS' TASK TIME TASK TIME C 42 5 D 39 2 J 39 10 E 37 15 K 33 4 L 29 8 A 28 2 B 26 7 G 25 6 I 24 9 F 22 7 M 21 6 H 19 4 N 15 15 Solution 3: Greatest positional weight first STATION NO OPERATIONS STATION TIME 1 C,D,J 17 2 E,A 17 3 K,L 12 4 B,G,H 17 5 I,F 16 6 M 6 7 N 15
  • 69. 69 Practice Questions  True/False  General, Job-Shop systems have a lower unit cost than continuous systems do because continuous systems use costly specialized equipment.  In cellular manufacturing, machines and equipment are grouped by type (e.g., all grinders are grouped into a cell). Answer: False Page: 218 Answer: False Page: 233
  • 70. 70 Practice Questions 1. Layout planning is required because of:  Efficient operations  Accidents or safety hazards  New products or services  Morale problems  A) I and II  B) II and IV  C) I and III  D) II, III, and IV  E) I, II, III, and IV Answer: D Page: 227
  • 71. 71 Practice Questions 2. Which type of processing system tends to produce the most product variety?  A)Assembly  B)Job-Shop  C)Batch  D)Continuous  E) Project •Answer: B Page: 220
  • 72. 72 Practice Questions 3. A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4 minutes, and 0.7 minutes. The minimum cycle time in minutes, is:  A)0.3  B)0.7  C)1.4  D)2.4  E) 0.8 •Answer: C