RAMCO INSTITUTE OF TECHNOLOGY
Mr.M.LAKSHMANAN
Assistant Professor (Senior Grade)
Department of Mechanical Engineering
UNIT II
MAINTENANCE POLICIES –
PREVENTIVE MAINTENANCE
Maintenance categories – Comparative merits of
each category – Preventive maintenance,
maintenance schedules, repair cycle - Principles
and methods of lubrication – TPM.
Maintenance
Approach
Planned
Maintenance
Preventive
Maintenance
Corrective
Maintenance
Predictive
Maintenance
Condition
Based
Maintenance
Reliability
Central
Maintenance
Breakdown
Maintenance
Breakdown / Reactive Maintenance
• The equipment is allowed to operate till no
failure occurs. No maintenance work is
carried out in advance to prevent the failure.
• The people wait till equipment fails and
repair.
• Its ineffective and extremely expensive.
• Poor planning and incomplete repair will be
contributed for high maintenance cost.
Limitations of Reactive Maintenance
• Most repairs are poorly planned due to time
constraint caused by production and plant
management.
• This approach focus only on repair or the
symptoms of failure and not on the root
cause of failure.
Planned Maintenance
• Corrective Maintenance:
Its focused on regular planned tasks that will
maintain all critical machinery and system
in optimum operating conditions.
Main Objectives:
1. Eliminate breakdowns
2. Eliminate deviations from optimum
operating conditions.
3. Eliminate unnecessary repairs
4. Optimize all critical plant systems.
• Corrective maintenance can be defined as
a maintenance task performed to identify,
isolate, and rectify a fault so that the failed
equipment, machine, or asset can be
restored to an operational condition within
the tolerances
• Corrective maintenance is maintenance
which is carried out after failure detection
and is aimed at restoring an asset to a
condition in which it can perform its
intended function.
Preventive Maintenance
• It is the maintenance program which is
committed to the elimination or prevention of
corrective and break down maintenance.
• It involves periodical evaluation of critical
equipment, machinery to detect problem and
schedule maintenance task to avoid
degradation in operating conditions.
• Its designed for day to day maintenance like
cleaning, inspection, lubricating, retightening
etc., to retain the healthy condition of
equipment.
Benefits of Preventive Maintenance
• It maintains the equipment in good
condition to preventing them from bigger
problems.
• Prolongs the effective life of the equipment.
• Detect the problem at earlier stages.
• Minimize / eliminates the rework.
• Reduces unplanned downtime.
Predictive Maintenance
• It is a management technique that uses
regular evaluation of the actual operating
conditions of plant equipment, production
systems and total plant operation.
• Predictive maintenance as regard to
maintenance management, based on need,
will provide necessary data for scheduling
of preventive and corrective maintenance
tasks.
• Predictive maintenance (PdM) techniques are
designed to help determine the condition of in-
service equipment in order to predict when
maintenance should be performed. This approach
promises cost savings over routine or time-based
preventive maintenance, because tasks are
performed only when warranted.
Its helps to improve/increase,
• The production capacity
• Product quality
• Overall effectiveness of production function.
Benefits of predictive Maintenance:
• Reduced breakdown losses
• Reduction of Quality defects
• Increased net operating profit
• Reduced maintenance cost
Condition Based Maintenance
• Condition-based maintenance (CBM),
shortly described, is maintenance when
need arises. This maintenance is performed
after one or more indicators show that
equipment is going to fail or that equipment
performance is deteriorating.
Condition Based Maintenance Techniques
• Vibration Monitoring:
Determines the actual condition of
equipment/machines by studying the noise or
vibration produced during functioning.
• Thermography:
Determines the condition of plant machinery,
system etc. by studying the emission of infra
red energy ( Temperature)
• Tribology:
Determines the dynamic condition of bearing
lubrication, rotor support structure of
machinery etc. by adopting any one of the
techniques like lubricating oil analysis and
wear particle analysis.
• Electrical motor Analysis
Determines the problem within motors and
other equipments.
• Visual inspection:
Determines the conditions of working
elements visually based on the experience.
Reliability Centered Maintenance (RCM)
• RCM is one of the well established
systematic and a step by step instructional
tool for selecting applicable and appropriate
maintenance operation types.
• It helps in how to analyze all failure modes
in a system and define how to prevent or
find those failures early.
The rough process of RCM is as follows:
• Target products or systems of maintenance
should be clearly identified, and necessary
data should be collected.
• All possible failures and their effect on
target products or systems are
systematically analyzed.
Applications of RCM
• When designing, selecting and installing
new systems in a plant
• When setting up preventive maintenance for
complex equipment and systems for which
are not clear on how they work.
Total Productive Maintenance (TPM)
• In industry, total productive maintenance
(TPM) is a system of maintaining and
improving the integrity of production and
quality systems through the machines,
equipment, processes, and employees that
add business value to an organization.
• It’s a maintenance program which involves a
newly defined concept of maintaining plants
and equipments.
• To increase the production, at the same time
increasing employee morale and job
satisfaction.
• To maximize plant and equipment
effectiveness to achieve optimum life cycle
cost of equipment.
Goal of TPM
Evolution of TPM
• Dr.W.Edward Deming – Japanese Industry
• Nippon Denso of Toyoto groups – Quality
circle, Involving employees participation
Implementation of TPM
Stage I
Initialization
(Preparatory)
Stage II
Introduction on TPM
(Take off phase)
Stage III
Implementation
Stage IV
Institutionalization
(Stabilization Phase)
Stage I Initialization
(Preparatory Phase)
• Discussions with workers union
representatives
• Establish basic TPM policies and goals –
Analyze the existing condition
• Preparation and formulation of master plan
Stage II Introduction on TPM
(Take off phase)
• Formal presentation by top executive with
all employees attending.
• To get the full support of all employees.
• Also invite our external customers,
suppliers, contractors and affiliated
companies to get their supports.
Stage III Implementation
• 5’S Principle
• Autonomous Maintenance (JISHU HOZEN)
• KAIZEN
• Planned Maintenance
• Quality Maintenance
• Training
• Office TPM
• Safety, Health and Environment
Stage IV Institutionalization
(Stabilization Phase)
• Once TPM has been implemented, it should
be properly monitored and evaluated and
some reward system can be introduced for
further encouragement.
• The Japanese institute for productive
maintenance runs an annual PM Excellence
Award.
TPM Objectives
Objectives
of TPM
Zero Defect
Zero
breakdown
Involvement
of people
from various
levels
Reliable
maintenance
policy
Benefits of TPM
• Enhanced/ improved productivity and
overall efficiency
• Reduction of manufacturing cost.
• Customer satisfaction by delivering right
quantity at right time with expected quality.
• Minimization of accidents.
• High confidence level among employees.
Category TQM TPM
Objective To have quality
output
To have reliable
equipment
Means of achieving Through
systematized
management
Through active
participation of
employees
Target Minimized defective
through planned
preventive
maintenance
Elimination losses
and wastes
Pillar -1: 5S Principle
Pillar -2: Jishu Hozen(JH)
• Training employees
• Initial cleanup of machines
• Taking counter measures
• Fixing tentative JH standards
• General Inspection
• Autonomous inspection
• Standardization
• Autonomous management
Pillar -3: KAIZEN
Elements of KAIZEN
Motorola’s steps for continuous
improvement
Major losses in an organization
• Equipment efficiency based losses
1. Failure/Breakdown losses
2. Setup/adjustment losses
3. Minor stoppage/ idling loss
4. Speed loss-Operating at low speeds
5. Defect/Rework loss
6. Scheduled downtime loss
• Human work efficiency based losses
1. Management loss
2. Operating motion loss
3. Line organization loss
4. Measurement and Adjustment loss
• Effective use of Production Resources
1. Energy loss
2. Die, Jig and Tool breakage loss
3. Yield loss
Pillar -4: Planned Maintenance(PM)
1. Preventive Maintenance
2. Corrective Maintenance
3. Predictive Maintenance
4. Condition Based Maintenance
5. Reliability Centered Maintenance
Pillar -5: Quality Maintenance(QM)
1. Its aimed towards customer delight by
getting them the highest quality through
defect free manufacturing.
2. Its focused on eliminating non
conformances in a systematic manner.
3. Understanding of what parts of the
equipment affect product quality and begin
to move potential quality
concerns.
Pillar -6: Training
 Its aimed to have multi skilled employees
whose morale is high and who are eager to
work and perform all the required
functions independently and effectively.
 Its not sufficient to know only “Know-How”
but they should also learn “Know-Why”.
Target:
 Achieve and sustain downtime at zero on
critical machines.
 Achieve and sustain zero losses due to lack
of knowledge/skills/techniques.
 Aim for 100% participation in suggestion
scheme.
Pillar -7: Office TPM
• To improve productivity, efficiency in the
administrative functions and identify-
eliminate losses.
• Analyzing processes and procedures
towards increased office automation.
Office TPM Major Losses
• Processing loss.
• Cost loss (Accounts, Marketing, Sales)
• Communication loss
• Idle loss
• Set-up loss
• Accuracy loss
• Office equipment breakdown
• Communication channel breakdown(Telephone,
Fax Lines)
• Non availability of correct on line stock status
• Customer complaints due to logistics
Benefits of Office TPM
• Involvement of all people in support functions for
focusing on better plant performance.
• Better utilized work area
• Reduce repetitive work
• Reduced inventory levels in all parts of the supply
chain.
• Reduced administrative cost
• Reduction in number of files
• Reduced manpower
• Clean and pleasant work environment
Pillar -8: Safety, Health and Environment
• Zero accident
• Zero health damage
• Zero fires
Maintenance Scheduling
• Maintenance scheduling is a joint maintenance
operations activity in which maintenance agrees to
make the resources available at a specific time
when the unit can also be made available by
operations.
Stakeholders
of
maintenance
scheduling
Planner
Scheduler
Maintenance
Supervisors
Craftsman
Store’s In
charge
Operation
Superinten
dent
Operator
1. Planner
He/She should ensure that the work is properly
planned with respect to customer requirements,
Stores material, directly purchased materials, etc.
also work to be carried out with line of safety
requirements should be described.
2. Scheduler
He/She should ensure that,
• Trades are available to conduct the work
during the schedule duration.
• Materials and service availability.
• Communicating the details of the above to
person involved in maintenance and
operation.
3. Maintenance Supervisor
He/She will be responsible for the day to day
activities comprised in weekly schedule and
also determine the business availability.
4. Craftman:
He/She execute the assigned task and keep
informing the maintenance team, the outcome
as well as any practical difficulty in their part,
for any further analysis.
5. Storeroom personnel:
They maintain the records of receipt of goods
and notify if any damage exists.
6. Operation Superintendent:
He must be kept informed in advance about
the equipment condition.
7. Operator:
He is the person responsible for securing the
equipment and report back to maintenance
personnel if any deviation is observed.
Maintenance
Scheduling
Principles
Schedules are
important job
priorities are
important
Schedule from
forecast of
highest skills
available
Schedule for
every
workhour
available
Crew leader
handles current
day’s work
(Daily
schedules)
Measures
performance
by analysis of
schedule
compliance
Plans with
lowest
required
skill level
Repair
• To restore to a good or sound condition
after decay or damage.
• Inspection(I)
• Minor Repair (R1)
• Major Repair(R2)
• Overhauling(O)
Repair Cycle
• The repeated performance of all/some of
the above mentioned activities in sequence
between successive overhauling is termed
as Repair Cycle.
O
I
R1
R2
I
R1
I
R2
Lubrication
• To reduce wear and heat between contacting
surfaces in relative motion.
• Coefficient of friction could be reduced and inturn
heat and wear of the surfaces.
• Lubrication also aids to
1. Reduce oxidation and rust formation
2. Transmit mechanical power in hydro fluid
power systems.
3. Seal against dust, dirt and water.
Lubricants
• Any materials used to reduce friction between
wearing surfaces with high coefficient of
friction, by establishing low viscous film are
called lubricants.
Methods of Lubrication:
• Hydrostatic Lubrication
• Hydrodynamic/ Fluid film Lubrication
• Boundary Lubrication
• Elasto hydrodynamic Lubrication (EHD)
• Extreme pressure Lubrication (EPL)
Method of lubrication is based on:
Mean fluid film thickness
R =
Surface Roughness
Where,
R is less than or equal to 1 for Boundary/Hydrostatic
Lubrication
R is in between 5 and less than or equal to 100 for
mixed lubrication or EHD/EPL
R is between 1 and 5 for fluid film lubrication
1. Hydrostatic Lubrication
A thin film of lubrication is created between
the journal and the bearing by supplying
lubricant under pressure with an external
source like pump.
2. Hydrodynamic/ Fluid film Lubrication
In heavy loaded bearing such a thrust
bearings and horizontal journal bearings
apart from viscosity of fluid, higher fluid
pressure is also required to support the
load.
In hydrodynamic lubrication a fluid wedge is
formed by the relative surface motion of the
journals over their bearing surfaces.
Ex: Cylindrical Journal Bearing & Connecting
rods
3. Boundary Lubrication
When a full fluid film is not developed
between rubbing surfaces, the thickness of
film may be reduced so that dry contact is
formed at high points of mating surfaces.
Ex: Gear Teeth
4. Elasto hydrodynamic Lubrication (EHD)
• The lubrication principle is applicable to
rolling bodies such as ball or roller bearings.
• Elastic deformation of the contacting bodies
under load and hydrodynamic effects
forcing the lubricant to separate the
contacting surfaces while the pressure of
the load is deforming them.
• Ex: Ball bearings
5. Extreme pressure Lubrication (EPL)
In heavy loading applications, oil temperature
raises beyond the anti wear protection.
Under this situation lubricants containing
additives that protect against extreme
pressure (EP) lubricants are used.
EPL can be achieved by chemical compounds
of boron, phosphorus, sulphur, chloride or
combination of these.
MAINTENANCE POLICIES – PREVENTIVE MAINTENANCE
MAINTENANCE POLICIES – PREVENTIVE MAINTENANCE

More Related Content

What's hot

Maintenance management and control
Maintenance management and controlMaintenance management and control
Maintenance management and controlNafis Ahmad
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance ManagementVijay325
 
Maintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceMaintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceDhanesh S
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance ManagementRohit Bisht
 
Introduction to maintenance strategy
Introduction to maintenance strategyIntroduction to maintenance strategy
Introduction to maintenance strategyDr. Munthear Alqaderi
 
Types of maintenance, maintenance in plant ,maintenance type
Types of maintenance, maintenance in plant ,maintenance type  Types of maintenance, maintenance in plant ,maintenance type
Types of maintenance, maintenance in plant ,maintenance type suresh tusia
 
Maintenance module 1 ppt number 1
Maintenance module 1 ppt number 1Maintenance module 1 ppt number 1
Maintenance module 1 ppt number 1Dhanesh S
 
Mechanical Maintenance
Mechanical MaintenanceMechanical Maintenance
Mechanical MaintenanceAshutosh Tomar
 
Unit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
Unit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNINGUnit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
Unit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNINGNatarajanGeetha
 
Maintenance planning and replacement
Maintenance  planning and replacementMaintenance  planning and replacement
Maintenance planning and replacementAmit Singh
 
Maintenance planning systems
Maintenance planning  systemsMaintenance planning  systems
Maintenance planning systemsAnil Mohindru
 
Types of maintenance
Types of maintenanceTypes of maintenance
Types of maintenanceAbhik Rathod
 
Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered MaintenanceNafis Ahmad
 

What's hot (20)

Maintenance management and control
Maintenance management and controlMaintenance management and control
Maintenance management and control
 
Maintenence management
Maintenence managementMaintenence management
Maintenence management
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance Management
 
Maintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceMaintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of Maintenance
 
Maintenance Management
Maintenance ManagementMaintenance Management
Maintenance Management
 
Introduction to maintenance strategy
Introduction to maintenance strategyIntroduction to maintenance strategy
Introduction to maintenance strategy
 
Types of maintenance, maintenance in plant ,maintenance type
Types of maintenance, maintenance in plant ,maintenance type  Types of maintenance, maintenance in plant ,maintenance type
Types of maintenance, maintenance in plant ,maintenance type
 
MAINTENANCE.ppt
MAINTENANCE.pptMAINTENANCE.ppt
MAINTENANCE.ppt
 
Maintenance
MaintenanceMaintenance
Maintenance
 
Maintenance module 1 ppt number 1
Maintenance module 1 ppt number 1Maintenance module 1 ppt number 1
Maintenance module 1 ppt number 1
 
Plant Maintenance
Plant MaintenancePlant Maintenance
Plant Maintenance
 
Maintenance
MaintenanceMaintenance
Maintenance
 
Mechanical Maintenance
Mechanical MaintenanceMechanical Maintenance
Mechanical Maintenance
 
Plant maintenance
Plant maintenancePlant maintenance
Plant maintenance
 
Unit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
Unit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNINGUnit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
Unit 1 - PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
 
Machinery Maintenance
Machinery MaintenanceMachinery Maintenance
Machinery Maintenance
 
Maintenance planning and replacement
Maintenance  planning and replacementMaintenance  planning and replacement
Maintenance planning and replacement
 
Maintenance planning systems
Maintenance planning  systemsMaintenance planning  systems
Maintenance planning systems
 
Types of maintenance
Types of maintenanceTypes of maintenance
Types of maintenance
 
Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered Maintenance
 

Similar to MAINTENANCE POLICIES – PREVENTIVE MAINTENANCE

Production and operation Unit_3.pptx
Production and operation Unit_3.pptxProduction and operation Unit_3.pptx
Production and operation Unit_3.pptxMargi Shah
 
Preventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.pptPreventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.pptMamoonurrasheed9
 
Chp-5-FRSI-2043-Type-of-Maivcsdntenance.ppt
Chp-5-FRSI-2043-Type-of-Maivcsdntenance.pptChp-5-FRSI-2043-Type-of-Maivcsdntenance.ppt
Chp-5-FRSI-2043-Type-of-Maivcsdntenance.pptTausifAhmad53
 
maintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.pptmaintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.pptYunusEmreKarabacak2
 
Total Productivity Maintenance - 60 pg PPT
Total Productivity Maintenance - 60 pg PPTTotal Productivity Maintenance - 60 pg PPT
Total Productivity Maintenance - 60 pg PPTmihirpatel306953
 
Total Productivity Maintenance
Total Productivity MaintenanceTotal Productivity Maintenance
Total Productivity MaintenanceGohelYash1
 
Implementing effective preventive and predictive maintenance programs
Implementing effective preventive and predictive maintenance programsImplementing effective preventive and predictive maintenance programs
Implementing effective preventive and predictive maintenance programshossam hassanein
 
chapter one.pdf 2016.pdf
chapter one.pdf 2016.pdfchapter one.pdf 2016.pdf
chapter one.pdf 2016.pdfgete2
 
Tpm principles and concepts
Tpm principles and conceptsTpm principles and concepts
Tpm principles and conceptsPaul Robere
 
tpmprinciplesandconcepts-190103043928.pdf
tpmprinciplesandconcepts-190103043928.pdftpmprinciplesandconcepts-190103043928.pdf
tpmprinciplesandconcepts-190103043928.pdfmihirpatel306953
 

Similar to MAINTENANCE POLICIES – PREVENTIVE MAINTENANCE (20)

Unit 1 mpa
Unit 1 mpaUnit 1 mpa
Unit 1 mpa
 
MAINTENANCE.ppt
MAINTENANCE.pptMAINTENANCE.ppt
MAINTENANCE.ppt
 
MAINTENANCE.pptx
MAINTENANCE.pptxMAINTENANCE.pptx
MAINTENANCE.pptx
 
Production and operation Unit_3.pptx
Production and operation Unit_3.pptxProduction and operation Unit_3.pptx
Production and operation Unit_3.pptx
 
Maintenace management and TPM
Maintenace management and TPMMaintenace management and TPM
Maintenace management and TPM
 
Preventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.pptPreventive and Predictive maintenance.ppt
Preventive and Predictive maintenance.ppt
 
Tpm
TpmTpm
Tpm
 
Chp-5-FRSI-2043-Type-of-Maivcsdntenance.ppt
Chp-5-FRSI-2043-Type-of-Maivcsdntenance.pptChp-5-FRSI-2043-Type-of-Maivcsdntenance.ppt
Chp-5-FRSI-2043-Type-of-Maivcsdntenance.ppt
 
Tpm basic
Tpm basicTpm basic
Tpm basic
 
maintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.pptmaintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.ppt
 
Total Productivity Maintenance - 60 pg PPT
Total Productivity Maintenance - 60 pg PPTTotal Productivity Maintenance - 60 pg PPT
Total Productivity Maintenance - 60 pg PPT
 
Tpm basic
Tpm basicTpm basic
Tpm basic
 
Asset Managment
Asset ManagmentAsset Managment
Asset Managment
 
TQM-Module 5.pptx
TQM-Module 5.pptxTQM-Module 5.pptx
TQM-Module 5.pptx
 
Total Productivity Maintenance
Total Productivity MaintenanceTotal Productivity Maintenance
Total Productivity Maintenance
 
Implementing effective preventive and predictive maintenance programs
Implementing effective preventive and predictive maintenance programsImplementing effective preventive and predictive maintenance programs
Implementing effective preventive and predictive maintenance programs
 
chapter one.pdf 2016.pdf
chapter one.pdf 2016.pdfchapter one.pdf 2016.pdf
chapter one.pdf 2016.pdf
 
Tpm principles and concepts
Tpm principles and conceptsTpm principles and concepts
Tpm principles and concepts
 
Tpm principles and concepts
Tpm principles and conceptsTpm principles and concepts
Tpm principles and concepts
 
tpmprinciplesandconcepts-190103043928.pdf
tpmprinciplesandconcepts-190103043928.pdftpmprinciplesandconcepts-190103043928.pdf
tpmprinciplesandconcepts-190103043928.pdf
 

More from laxtwinsme

THERMAL ENERGY BASED PROCESSES
THERMAL ENERGY BASED PROCESSESTHERMAL ENERGY BASED PROCESSES
THERMAL ENERGY BASED PROCESSESlaxtwinsme
 
CHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSES
CHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSESCHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSES
CHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSESlaxtwinsme
 
ELECTRICAL ENERGY BASED PROCESSES
ELECTRICAL ENERGY BASED PROCESSESELECTRICAL ENERGY BASED PROCESSES
ELECTRICAL ENERGY BASED PROCESSESlaxtwinsme
 
MECHANICAL ENERGY BASED PROCESSES
MECHANICAL ENERGY BASED PROCESSESMECHANICAL ENERGY BASED PROCESSES
MECHANICAL ENERGY BASED PROCESSESlaxtwinsme
 
Introduction to Unconventional Machining Processes
Introduction to Unconventional Machining ProcessesIntroduction to Unconventional Machining Processes
Introduction to Unconventional Machining Processeslaxtwinsme
 
REPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTSREPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTSlaxtwinsme
 
CONDITION MONITORING
CONDITION MONITORINGCONDITION MONITORING
CONDITION MONITORINGlaxtwinsme
 
PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNINGPRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNINGlaxtwinsme
 
RADIOGRAPHY (RT)
RADIOGRAPHY (RT)RADIOGRAPHY (RT)
RADIOGRAPHY (RT)laxtwinsme
 
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)laxtwinsme
 
THERMOGRAPHY AND EDDY CURRENT TESTING (ET)
THERMOGRAPHY AND EDDY CURRENT TESTING (ET)THERMOGRAPHY AND EDDY CURRENT TESTING (ET)
THERMOGRAPHY AND EDDY CURRENT TESTING (ET)laxtwinsme
 
SURFACE NDE METHODS
SURFACE NDE METHODSSURFACE NDE METHODS
SURFACE NDE METHODSlaxtwinsme
 
OVERVIEW OF NDT
OVERVIEW OF NDTOVERVIEW OF NDT
OVERVIEW OF NDTlaxtwinsme
 
Unit V CNC Machining
Unit V CNC MachiningUnit V CNC Machining
Unit V CNC Machininglaxtwinsme
 
Unit IV Abrasive Process and Broaching
Unit IV   Abrasive Process and BroachingUnit IV   Abrasive Process and Broaching
Unit IV Abrasive Process and Broachinglaxtwinsme
 
shaping, milling and gear cutting machines
shaping, milling and gear cutting machinesshaping, milling and gear cutting machines
shaping, milling and gear cutting machineslaxtwinsme
 
Turning Machines
Turning MachinesTurning Machines
Turning Machineslaxtwinsme
 
Theory of Metal Cutting
 Theory of Metal Cutting Theory of Metal Cutting
Theory of Metal Cuttinglaxtwinsme
 
MANUFACTURE OF PLASTIC COMPONENTS
MANUFACTURE OF PLASTIC COMPONENTSMANUFACTURE OF PLASTIC COMPONENTS
MANUFACTURE OF PLASTIC COMPONENTSlaxtwinsme
 
SHEET METAL PROCESSES
SHEET METAL PROCESSESSHEET METAL PROCESSES
SHEET METAL PROCESSESlaxtwinsme
 

More from laxtwinsme (20)

THERMAL ENERGY BASED PROCESSES
THERMAL ENERGY BASED PROCESSESTHERMAL ENERGY BASED PROCESSES
THERMAL ENERGY BASED PROCESSES
 
CHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSES
CHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSESCHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSES
CHEMICAL AND ELECTROCHEMICAL ENERGY BASED PROCESSES
 
ELECTRICAL ENERGY BASED PROCESSES
ELECTRICAL ENERGY BASED PROCESSESELECTRICAL ENERGY BASED PROCESSES
ELECTRICAL ENERGY BASED PROCESSES
 
MECHANICAL ENERGY BASED PROCESSES
MECHANICAL ENERGY BASED PROCESSESMECHANICAL ENERGY BASED PROCESSES
MECHANICAL ENERGY BASED PROCESSES
 
Introduction to Unconventional Machining Processes
Introduction to Unconventional Machining ProcessesIntroduction to Unconventional Machining Processes
Introduction to Unconventional Machining Processes
 
REPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTSREPAIR METHODS FOR BASIC MACHINE ELEMENTS
REPAIR METHODS FOR BASIC MACHINE ELEMENTS
 
CONDITION MONITORING
CONDITION MONITORINGCONDITION MONITORING
CONDITION MONITORING
 
PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNINGPRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
PRINCIPLES AND PRACTICES OF MAINTENANCE PLANNING
 
RADIOGRAPHY (RT)
RADIOGRAPHY (RT)RADIOGRAPHY (RT)
RADIOGRAPHY (RT)
 
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)ULTRASONIC TESTING (UT)  &  ACOUSTIC EMISSION (AE)
ULTRASONIC TESTING (UT) & ACOUSTIC EMISSION (AE)
 
THERMOGRAPHY AND EDDY CURRENT TESTING (ET)
THERMOGRAPHY AND EDDY CURRENT TESTING (ET)THERMOGRAPHY AND EDDY CURRENT TESTING (ET)
THERMOGRAPHY AND EDDY CURRENT TESTING (ET)
 
SURFACE NDE METHODS
SURFACE NDE METHODSSURFACE NDE METHODS
SURFACE NDE METHODS
 
OVERVIEW OF NDT
OVERVIEW OF NDTOVERVIEW OF NDT
OVERVIEW OF NDT
 
Unit V CNC Machining
Unit V CNC MachiningUnit V CNC Machining
Unit V CNC Machining
 
Unit IV Abrasive Process and Broaching
Unit IV   Abrasive Process and BroachingUnit IV   Abrasive Process and Broaching
Unit IV Abrasive Process and Broaching
 
shaping, milling and gear cutting machines
shaping, milling and gear cutting machinesshaping, milling and gear cutting machines
shaping, milling and gear cutting machines
 
Turning Machines
Turning MachinesTurning Machines
Turning Machines
 
Theory of Metal Cutting
 Theory of Metal Cutting Theory of Metal Cutting
Theory of Metal Cutting
 
MANUFACTURE OF PLASTIC COMPONENTS
MANUFACTURE OF PLASTIC COMPONENTSMANUFACTURE OF PLASTIC COMPONENTS
MANUFACTURE OF PLASTIC COMPONENTS
 
SHEET METAL PROCESSES
SHEET METAL PROCESSESSHEET METAL PROCESSES
SHEET METAL PROCESSES
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 

Recently uploaded (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 

MAINTENANCE POLICIES – PREVENTIVE MAINTENANCE

  • 1. RAMCO INSTITUTE OF TECHNOLOGY Mr.M.LAKSHMANAN Assistant Professor (Senior Grade) Department of Mechanical Engineering
  • 2. UNIT II MAINTENANCE POLICIES – PREVENTIVE MAINTENANCE Maintenance categories – Comparative merits of each category – Preventive maintenance, maintenance schedules, repair cycle - Principles and methods of lubrication – TPM.
  • 4. Breakdown / Reactive Maintenance • The equipment is allowed to operate till no failure occurs. No maintenance work is carried out in advance to prevent the failure. • The people wait till equipment fails and repair. • Its ineffective and extremely expensive. • Poor planning and incomplete repair will be contributed for high maintenance cost.
  • 5. Limitations of Reactive Maintenance • Most repairs are poorly planned due to time constraint caused by production and plant management. • This approach focus only on repair or the symptoms of failure and not on the root cause of failure.
  • 6. Planned Maintenance • Corrective Maintenance: Its focused on regular planned tasks that will maintain all critical machinery and system in optimum operating conditions. Main Objectives: 1. Eliminate breakdowns 2. Eliminate deviations from optimum operating conditions. 3. Eliminate unnecessary repairs 4. Optimize all critical plant systems.
  • 7. • Corrective maintenance can be defined as a maintenance task performed to identify, isolate, and rectify a fault so that the failed equipment, machine, or asset can be restored to an operational condition within the tolerances • Corrective maintenance is maintenance which is carried out after failure detection and is aimed at restoring an asset to a condition in which it can perform its intended function.
  • 8. Preventive Maintenance • It is the maintenance program which is committed to the elimination or prevention of corrective and break down maintenance. • It involves periodical evaluation of critical equipment, machinery to detect problem and schedule maintenance task to avoid degradation in operating conditions. • Its designed for day to day maintenance like cleaning, inspection, lubricating, retightening etc., to retain the healthy condition of equipment.
  • 9. Benefits of Preventive Maintenance • It maintains the equipment in good condition to preventing them from bigger problems. • Prolongs the effective life of the equipment. • Detect the problem at earlier stages. • Minimize / eliminates the rework. • Reduces unplanned downtime.
  • 10. Predictive Maintenance • It is a management technique that uses regular evaluation of the actual operating conditions of plant equipment, production systems and total plant operation. • Predictive maintenance as regard to maintenance management, based on need, will provide necessary data for scheduling of preventive and corrective maintenance tasks.
  • 11. • Predictive maintenance (PdM) techniques are designed to help determine the condition of in- service equipment in order to predict when maintenance should be performed. This approach promises cost savings over routine or time-based preventive maintenance, because tasks are performed only when warranted.
  • 12.
  • 13. Its helps to improve/increase, • The production capacity • Product quality • Overall effectiveness of production function. Benefits of predictive Maintenance: • Reduced breakdown losses • Reduction of Quality defects • Increased net operating profit • Reduced maintenance cost
  • 14. Condition Based Maintenance • Condition-based maintenance (CBM), shortly described, is maintenance when need arises. This maintenance is performed after one or more indicators show that equipment is going to fail or that equipment performance is deteriorating.
  • 15. Condition Based Maintenance Techniques • Vibration Monitoring: Determines the actual condition of equipment/machines by studying the noise or vibration produced during functioning. • Thermography: Determines the condition of plant machinery, system etc. by studying the emission of infra red energy ( Temperature)
  • 16. • Tribology: Determines the dynamic condition of bearing lubrication, rotor support structure of machinery etc. by adopting any one of the techniques like lubricating oil analysis and wear particle analysis. • Electrical motor Analysis Determines the problem within motors and other equipments. • Visual inspection: Determines the conditions of working elements visually based on the experience.
  • 17.
  • 18.
  • 19. Reliability Centered Maintenance (RCM) • RCM is one of the well established systematic and a step by step instructional tool for selecting applicable and appropriate maintenance operation types. • It helps in how to analyze all failure modes in a system and define how to prevent or find those failures early.
  • 20.
  • 21. The rough process of RCM is as follows: • Target products or systems of maintenance should be clearly identified, and necessary data should be collected. • All possible failures and their effect on target products or systems are systematically analyzed.
  • 22. Applications of RCM • When designing, selecting and installing new systems in a plant • When setting up preventive maintenance for complex equipment and systems for which are not clear on how they work.
  • 23. Total Productive Maintenance (TPM) • In industry, total productive maintenance (TPM) is a system of maintaining and improving the integrity of production and quality systems through the machines, equipment, processes, and employees that add business value to an organization. • It’s a maintenance program which involves a newly defined concept of maintaining plants and equipments.
  • 24. • To increase the production, at the same time increasing employee morale and job satisfaction. • To maximize plant and equipment effectiveness to achieve optimum life cycle cost of equipment. Goal of TPM
  • 25. Evolution of TPM • Dr.W.Edward Deming – Japanese Industry • Nippon Denso of Toyoto groups – Quality circle, Involving employees participation
  • 26. Implementation of TPM Stage I Initialization (Preparatory) Stage II Introduction on TPM (Take off phase) Stage III Implementation Stage IV Institutionalization (Stabilization Phase)
  • 27. Stage I Initialization (Preparatory Phase) • Discussions with workers union representatives • Establish basic TPM policies and goals – Analyze the existing condition • Preparation and formulation of master plan
  • 28. Stage II Introduction on TPM (Take off phase) • Formal presentation by top executive with all employees attending. • To get the full support of all employees. • Also invite our external customers, suppliers, contractors and affiliated companies to get their supports.
  • 29. Stage III Implementation • 5’S Principle • Autonomous Maintenance (JISHU HOZEN) • KAIZEN • Planned Maintenance • Quality Maintenance • Training • Office TPM • Safety, Health and Environment
  • 30.
  • 31.
  • 32.
  • 33. Stage IV Institutionalization (Stabilization Phase) • Once TPM has been implemented, it should be properly monitored and evaluated and some reward system can be introduced for further encouragement. • The Japanese institute for productive maintenance runs an annual PM Excellence Award.
  • 34. TPM Objectives Objectives of TPM Zero Defect Zero breakdown Involvement of people from various levels Reliable maintenance policy
  • 35. Benefits of TPM • Enhanced/ improved productivity and overall efficiency • Reduction of manufacturing cost. • Customer satisfaction by delivering right quantity at right time with expected quality. • Minimization of accidents. • High confidence level among employees.
  • 36. Category TQM TPM Objective To have quality output To have reliable equipment Means of achieving Through systematized management Through active participation of employees Target Minimized defective through planned preventive maintenance Elimination losses and wastes
  • 37. Pillar -1: 5S Principle
  • 38. Pillar -2: Jishu Hozen(JH) • Training employees • Initial cleanup of machines • Taking counter measures • Fixing tentative JH standards • General Inspection • Autonomous inspection • Standardization • Autonomous management
  • 41. Motorola’s steps for continuous improvement
  • 42. Major losses in an organization • Equipment efficiency based losses 1. Failure/Breakdown losses 2. Setup/adjustment losses 3. Minor stoppage/ idling loss 4. Speed loss-Operating at low speeds 5. Defect/Rework loss 6. Scheduled downtime loss • Human work efficiency based losses 1. Management loss 2. Operating motion loss 3. Line organization loss 4. Measurement and Adjustment loss
  • 43. • Effective use of Production Resources 1. Energy loss 2. Die, Jig and Tool breakage loss 3. Yield loss
  • 44. Pillar -4: Planned Maintenance(PM) 1. Preventive Maintenance 2. Corrective Maintenance 3. Predictive Maintenance 4. Condition Based Maintenance 5. Reliability Centered Maintenance
  • 45. Pillar -5: Quality Maintenance(QM) 1. Its aimed towards customer delight by getting them the highest quality through defect free manufacturing. 2. Its focused on eliminating non conformances in a systematic manner. 3. Understanding of what parts of the equipment affect product quality and begin to move potential quality concerns.
  • 46. Pillar -6: Training  Its aimed to have multi skilled employees whose morale is high and who are eager to work and perform all the required functions independently and effectively.  Its not sufficient to know only “Know-How” but they should also learn “Know-Why”.
  • 47. Target:  Achieve and sustain downtime at zero on critical machines.  Achieve and sustain zero losses due to lack of knowledge/skills/techniques.  Aim for 100% participation in suggestion scheme.
  • 48. Pillar -7: Office TPM • To improve productivity, efficiency in the administrative functions and identify- eliminate losses. • Analyzing processes and procedures towards increased office automation.
  • 49. Office TPM Major Losses • Processing loss. • Cost loss (Accounts, Marketing, Sales) • Communication loss • Idle loss • Set-up loss • Accuracy loss • Office equipment breakdown • Communication channel breakdown(Telephone, Fax Lines) • Non availability of correct on line stock status • Customer complaints due to logistics
  • 50. Benefits of Office TPM • Involvement of all people in support functions for focusing on better plant performance. • Better utilized work area • Reduce repetitive work • Reduced inventory levels in all parts of the supply chain. • Reduced administrative cost • Reduction in number of files • Reduced manpower • Clean and pleasant work environment
  • 51. Pillar -8: Safety, Health and Environment • Zero accident • Zero health damage • Zero fires
  • 52.
  • 53. Maintenance Scheduling • Maintenance scheduling is a joint maintenance operations activity in which maintenance agrees to make the resources available at a specific time when the unit can also be made available by operations.
  • 55. 1. Planner He/She should ensure that the work is properly planned with respect to customer requirements, Stores material, directly purchased materials, etc. also work to be carried out with line of safety requirements should be described.
  • 56. 2. Scheduler He/She should ensure that, • Trades are available to conduct the work during the schedule duration. • Materials and service availability. • Communicating the details of the above to person involved in maintenance and operation.
  • 57. 3. Maintenance Supervisor He/She will be responsible for the day to day activities comprised in weekly schedule and also determine the business availability. 4. Craftman: He/She execute the assigned task and keep informing the maintenance team, the outcome as well as any practical difficulty in their part, for any further analysis.
  • 58. 5. Storeroom personnel: They maintain the records of receipt of goods and notify if any damage exists. 6. Operation Superintendent: He must be kept informed in advance about the equipment condition. 7. Operator: He is the person responsible for securing the equipment and report back to maintenance personnel if any deviation is observed.
  • 59.
  • 60.
  • 61. Maintenance Scheduling Principles Schedules are important job priorities are important Schedule from forecast of highest skills available Schedule for every workhour available Crew leader handles current day’s work (Daily schedules) Measures performance by analysis of schedule compliance Plans with lowest required skill level
  • 62. Repair • To restore to a good or sound condition after decay or damage. • Inspection(I) • Minor Repair (R1) • Major Repair(R2) • Overhauling(O)
  • 63. Repair Cycle • The repeated performance of all/some of the above mentioned activities in sequence between successive overhauling is termed as Repair Cycle.
  • 65. Lubrication • To reduce wear and heat between contacting surfaces in relative motion. • Coefficient of friction could be reduced and inturn heat and wear of the surfaces. • Lubrication also aids to 1. Reduce oxidation and rust formation 2. Transmit mechanical power in hydro fluid power systems. 3. Seal against dust, dirt and water.
  • 66. Lubricants • Any materials used to reduce friction between wearing surfaces with high coefficient of friction, by establishing low viscous film are called lubricants. Methods of Lubrication: • Hydrostatic Lubrication • Hydrodynamic/ Fluid film Lubrication • Boundary Lubrication • Elasto hydrodynamic Lubrication (EHD) • Extreme pressure Lubrication (EPL)
  • 67. Method of lubrication is based on: Mean fluid film thickness R = Surface Roughness Where, R is less than or equal to 1 for Boundary/Hydrostatic Lubrication R is in between 5 and less than or equal to 100 for mixed lubrication or EHD/EPL R is between 1 and 5 for fluid film lubrication
  • 68. 1. Hydrostatic Lubrication A thin film of lubrication is created between the journal and the bearing by supplying lubricant under pressure with an external source like pump.
  • 69. 2. Hydrodynamic/ Fluid film Lubrication In heavy loaded bearing such a thrust bearings and horizontal journal bearings apart from viscosity of fluid, higher fluid pressure is also required to support the load. In hydrodynamic lubrication a fluid wedge is formed by the relative surface motion of the journals over their bearing surfaces.
  • 70. Ex: Cylindrical Journal Bearing & Connecting rods
  • 71.
  • 72. 3. Boundary Lubrication When a full fluid film is not developed between rubbing surfaces, the thickness of film may be reduced so that dry contact is formed at high points of mating surfaces. Ex: Gear Teeth
  • 73. 4. Elasto hydrodynamic Lubrication (EHD) • The lubrication principle is applicable to rolling bodies such as ball or roller bearings. • Elastic deformation of the contacting bodies under load and hydrodynamic effects forcing the lubricant to separate the contacting surfaces while the pressure of the load is deforming them. • Ex: Ball bearings
  • 74.
  • 75. 5. Extreme pressure Lubrication (EPL) In heavy loading applications, oil temperature raises beyond the anti wear protection. Under this situation lubricants containing additives that protect against extreme pressure (EP) lubricants are used. EPL can be achieved by chemical compounds of boron, phosphorus, sulphur, chloride or combination of these.