MAPPING PROJECT MANAGEMENT PRACTICES
IN A MEGA PROJECT RAWALPINDI-ISLAMABAD
METRO BUS SERVICE
Essentials of Project Management
MS(PM)
Arif Khalil (CMS: 15691)
Tahir Muzaffar Malik (CMS: 15592)
Mahmood Ahmed (CMS: 15344)
Muhammad Asif Khan (CMS: 15479)
Wasi ullah (CMS: 15403)
Muhammad Tariq Zafar (CMS: 15306)
A team effort by following members
AN INTRODUCTION TO PAKISTAN’S 1ST
MASS TRANSPORT SYSTEM
Introduction
The Rawalpindi-Islamabad Metrobus (‫بس‬ ‫میٹرو‬ ‫آباد‬ ‫اسالم‬ ‫)راولپنڈی‬ is a
24 km (14.9 mi) bus rapid transit under-construction in the twin cities
of Rawalpindi and Islamabad, Pakistan.
The concept of Metro Bus System (MBS) is a rapid
mode of transportation that can provide the quality of
rail transit with the flexibility of buses. MBS has been
implemented in several cities throughout the world as
a low-cost, rail-like method of moving people quickly
and efficiently.
Introduction
Islamabad is the Capital City of Pakistan and the ninth
largest city in the country. Located within the
Islamabad Capital Territory (ICT), the population of
the city has grown from 100,000 in 1951 to 1.30
million in 2012. The greater Islamabad – Rawalpindi
Metropolitan Area is the third largest conurbation in
Pakistan with a population of over 4.5 million
inhabitants.
Pakistan Economic Survey 2013-14
• Twin cities Islamabad and Rawalpindi are growing at a rate of more than
4 percent per annum
• With present growth trends it is expected that the population would
increase upto 7.0 million in next twenty years
• Currently private transport is the major means of mobility between two
cities comprising of Mazda, Toyota Hiace, and Suzuki vans plying on
various routes within and between the two cities.
• Traffic volumes of over 210,000 vehicles ply on three major corridors
connecting two cities carrying around 525,000 passengers.
The Need for MBS
It is estimated that public transport demand of
around 153,000 passengers is required to cater
daily basis between the two cities. Interestingly
this passenger demand is concentrated around a
corridor which is of high density and
strategically located to provide for a rapid
transit system.
The Need for MBS
The Need for MBS
The government will execute this project through Rawalpindi Development Authority (RDA) It
will work in close coordination with the Capital Development Authority (CDA) for the Islamabad
Part of the project. Punjab Metrobus Authority (PMA) will control the operation & maintenance of
the project after its completion.
The project
will start from
near Flashman
Hotel on Mall
Road
Rawalpindi
and follow the
existing
Murree Road
upto Faizabad.
It will then turn
left into the
federal
territory and
follow I.J.P.
road upto 9th
Avenue.
MBS: Quick Facts
Total Length: 22.5 Kilometers
Total Cost: 44.21 Billion Rupees
Total Buses: 64
Capacity per Bus: 108 People
Project Completion Time: 10 Months
Total Stops: 27
Total Expected MBS users per Day: 153,000
CONSTRUCTION & COST
The works of Rawalpindi Part (03 Packages) have been awarded and the
contractors are mobilized at the site. The works of Islamabad part of five
Packages has also been started. Prime Minister inaugurated the project on
23rd March 2014 and work was started from the same day. Metrobus
project will be completed in next 10 months.
The system was built on the build–operate–transfer basis via the
collaboration between the Punjab and the Turkish government.
Project Overview
 Signal Free: The entire length i.e. 8.6 km of Metro Bus corridor in Rawalpindi area
shall be elevated structure whereas about 14 km in Islamabad shall be at-grade but
made signal-free by constructing grade separations at various intersections.
 Number of Stations: Ten (10) stations in the Rawalpindi Part and fourteen (14) in
the Islamabad Part are provided along the corridor.
 Functional Elements: Functional elements at the stations include ticketing booths,
concourse level passenger transfer, escalators, platform screen doors turnstiles for
automatic fare collection and all other amenities for passenger convenience.
 Central Control Room: A central ITS control room is also included in the project to
control the whole operation of the Metro Bus system.
 Number of Lanes: Initially the provision of a 10 lane Underpass (2 Lanes for Metro
Bus and 8 Lanes for mix traffic) along the 9th Avenue was proposed at Peshawar
Mor intersection. Later on, in view of the traffic issues at Peshawar Mor
intersection, ongoing Widening/Rehabilitation of Kashmir Highway & its link with
new Islamabad Airport, it was decided to dovetail the Metro Bus corridor in the
interchange already designed by CDA which will cost Rs. 6.75 Billion. The same
will be simultaneously executed with Metro Bus Project.
The Buses
All Buses have been produced specifically for
the Islamabad MBS by Volvo.
The ‘Arctic Buses’ hold 108 passengers and are
standard for all major Bus Rapid Transit
Systems including the one in Tehran and
Istanbul
Each bus has special seating for Women &
Children as well as for Handicapped Persons.
All buses are elevated for easier passenger entry
at platforms
Travelling on MBS
The MBS was completely free for the
first month. After that there are standard
charges put in to use.
The Metro Bus Card and MBS Token
can both be used to travel on the MBS.
The MBS Card is like Travel Cards
around the world that can be recharged
for multiple journeys, it costs 133
Rupees.
School Children and Students as well as
senior citizens will be charged a
discounted rate.
Total Expected MBS users per Day
• According to the Islamabad Transport
Company, the daily ridership of the Metro
bus exceeds 130,000 with the peak hourly
ridership being 10,000 passengers per hour
per direction
• Labour, and some tourists have the
same route to commute. Now, they can
easily avail the metro bus service.
• It is not reaching out to colleges,
universities, hospitals and offices
nearby, so that all these students could
also have availed it instead of some
other private transport.
•The MBS is an affordable initiative,
which will go a long way in reducing
emissions and traffic volume. It offers
safe, reliable and comfortable
transport .
Advantages
Rawalpindi Part of Metro Bus
Route Information
Stations along Murree Road Rawalpindi
R A W A L P I N D I
Faizabad
Interchange
Flash Man
Chowk
Saddar
Total Elevated 10 Nos.
Stations
Length of 8.6 Km
Rawalpindi Part
Marrir Chowk
Liaqat Bagh
Committee Chowk
Waris Khan
Hospital
Rehmanabad
6th Road
Faizabad
I-8
I-9
I-10
I-11
Shamsabad
M A L L R O A D
Flash Man
Hotel
Saddar
Station
Marrir Chowk
Station
Turnaround 10
~ 15 Buses
Saddar
Katchery
150 m
Start Point
Church
Open Plot - 4 Kanals for
Control Room & Parking
Saddar Defence
Area
Marrir Chowk
Marrir Chowk
Station
Liaqat Bagh
Station
Committee
Chowk Station
Liaqat Road
Liaqat Bagh Station
Liaqat Bagh
Committee Chowk Station
Iqbal Road
Existing
Underpass
Committee
Chowk Station
Waris Khan Station
Waris Khan
Station
Hospital
Station
Chandni Chowk Flyover
Hospital
Station
Existing
Flyover
Rehmanabad
Station
Benazir
Hospital
Chandni
Chowk
6th Road Flyover
5th Road
Rehmanabad
Station
Khanna Road
6th Road
Station
6th Road Flyover
6th Road
Station
Existing
Flyover
Nawaz Sharif
Park
Shamsabad
Station
I-8 FAIZABAD
INTERCHANGEPir Wadhai
I J P R O A D
Faizabad Station
NAWAZ
SHARIF
PARK
ARID
UNIVERSITY
RAWALPINDI
CRICKET
STADIUM
Shamsabad
Station
Faizabad
Station
Perspective View of Proposed MBS Station
Islamabad Part of Metro Bus
Route Information
F-10
F-9
F-8
F-7
F-6
G-10
G-9
G-8
G-7
G-6
H-8
I-8
I-9
Faizabad
Interchange
Zero Point
IJP Road
Pothar Road
Khayban-E- Johar
Faiz Ahmed Faiz Road
Kashmir Highway
Chaman Road
Ibn-e-Sina Road
Katchery
Station
Centaurus
Saudi Pak
Tower
7th Avenue
Shaheed-e-
Millat Road
Parade Ground
Secretariat
Stations along 9th Avenue & Jinnah Avenue Islamabad
Total At-Grade 14 Nos.
Stations
Length of 13.9 Km
Islamabad Part
H-10
H-9
Flyover MBS
At-Grade
Service Road
Pir Wadhai`
Faizabad
At-Grade
Rotary
At-grade
Rotary
IJP Station
MBS Route at IJP-9th Avenue Intersection
StadiumRoad`
9thAvenue`
IJP Road
Arrangement at IJP Road and 9th Avenue Intersection
I-9
I-8
Future Rotary
Future MBS
Present MBS
Construction
Proposed Interchange at Peshawar Morr With MBS
Corridor
M-2
Zero Point
Sunday
Market
MBS
CORRIDOR
9th Avenue
Alignment Plan From Peshawar Morr To Jinnah Avenue
M-2
IJPRoad
Zero Point
Peshawar Morr
Station
9thAvenue
J i n n a h Av e n u e
Chaman Road
Station
Ibn-e-Sina
Station
Secretariat
G-9
G-8
Sunday
Market
Kashmir Highway
Proposed
Interchange
2- Lane Underpass
for MBS
Alignment Plan From Peshawar Morr To Jinnah Avenue
Peshawar
Morr
Secretariat
Ibn-e-Sina
Station
JinnahAvenue
9 t h A v e n u e
S e r v i c e R o a d
Proposed
Underpass
Ibn-e-SinaRoad
G-9
G-8
NIRM
Junction between 9th Avenue & Jinnah Avenue
Proposed Underpass
for MBS
F-8
10 m widening of
one carriageway
I-8
2- Lane Underpass
for MBS
Covered
Section
Ibn-e-Sina
Road Station
Covered
Section
Open
Trench
Existing Flyover at 8th Avenue
3.3 m widening of
Existing Bridge for
Mixed Traffic
Faisal Masjid
Zero Point
Centaurus
Mall
G-7F-7
FAISAL AVENUE
Centaurus
Station
Saudi Pak Tower
Station
7th Avenue
F-7
9 m widening on
each side
NIC Tower
Zero Point
G-7
7th Avenue
Station
Proposed Interchange at 7th Avenue
Centaurus
Secretariat
Nazim ud Din Road
Fazal ul Haq Road
7th Avenue
Station
ProposedUnderpass
ExistingUnderpass
ProposedUnderpass
Centaurus
Secretariat
Proposed MBS from Parade Ground to Secretariat
Secretariat
Marriott
Hotel
F-6
F-5
Jinnah Avenue
Turn around
L = 1.2 Km
Parliament
House
Secretariat
Station
Parade
Ground
Perspective View of Proposed MBS Station
Disadvantages
• Cost of project
• Effected business a lot
• Transporters are much effected.
Mapping Project Management
Practices
In
Rawalpindi-Islamabad Metro
Bus Service
Project Management is the application of
knowledge, skills, tools, and techniques to
project activities to meet project
requirements.
Project Management Process Groups
vs
Metro Bus Rawalpindi-Islamabad Project
Project Management Process Groups Metro Bus Rawalpindi-Islamabad Project
Initiating Process Foundation Stone on 23rd March 2014
Planning Process • Master Plan – (Rawalpindi Part, Islamabad
Psrt and Peshawar Mor Interchange)
• Project Charter
Executing Process • Rawalpindi Part – (03 Packages)
• Islamabad Part – (05 Packages)
• Peshawar Mor Interchange
Monitoring and Controlling Central Command and Control Office
Closing Process • Expected date of completion: Jan, 2015
• Expected date to be inaugurated: Feb 2015
ProjectManagementBoK—5thEdition
KnowledgeAreas
Process Groups
The
application
of knowledge
requires the
effective
management
of
appropriate
processes.
Project Management Knowledge Areas
vs
Metro Bus Rawalpindi-Islamabad Project
1: Project
Integration
Management
2:ProjectScope
Management
4: Project Cost Management
7:ProjectCommunications
Management
9: Project Procurement
Management
I - Project Integration Management
1. Project Charter
National Logistics Cell,
Lemac-Reliable from Turkey
and ZKB had already
received the contract of nine
kilometers in the Rawalpindi
section of the Metro Bus
Project.
FWO (Frontier Work
Organization), Habib
constructions, Maksons, Zahid
Khan and Brother (ZKB) and
National Logistics Cell (NLC).
The companies that are joint
ventures are China Railway
First Group-HRL-Metracom,
CEW-Sarwar from China,
Lemac-Reliable from Turkey
and Mal-Calsons
I - Project Integration Management
2. Develop Project Management Plan
 The project will start from near Flashman
Hotel on Mall Road Rawalpindi and follow
the existing Murree Road upto Faizabad.
 It will then turn left into the federal territory
and follow I.J.P. road upto 9th Avenue.
 Thereafter, it will turn right and follow the
9th Avenue in Islamabad then turn right on
Jinnah Avenue upto the end of Blue Area.
 From Blue Area a connection to Secretariat
stop will be provided through the open
space behind parade ground.
 It will cross the Constitution Avenue and
another couple of main roads through
underpasses.
 However, the remaining length of this
section is also designed on a lower level in
an open Trench section keeping in view
various security constraints.
I - Project Integration Management
I - Project Integration Management
I - Project Integration Management
3. Direct and manage project work
The Project Management Office is the organizational body or entity
assigned various responsibilities related to the centralized and
coordinated management of projects under its domain, For MBS the
PMO office is near Flashman Hotel Rawalpindi Saddar for Rawalpindi
Part and in the F-11 for Islamabad Part. The offices are involved in
managing the overall operations and resource allocation.
I - Project Integration Management
4. Monitor and Control Project Work
Chairman Metro Bus Project Monitoring and Implementation Committee, Hanif
Abbasi, claimed that the luxury bus project would complete by end of February. The
progress of this project is reviewed at different level of authority as shown below (See
Annexure - ):
I - Project Integration Management
5. Close Project or Phase
The work continues at the project from D-Chowk to Secretariat Blocks, the
Bus service will initially operate up to China Chowk only. Though the track of
the bus service is almost ready, final touches are being given to the project.
Besides, several minor works still pending especially at the Peshawar Mor,
including the access to the underground bus station there.
I - Project Integration Management
II - Project Scope Management
Reference: PMBOK® Guide, 5th Edition
1. Plan Scope Management
2. Collect Requirements
3. Define Scope
4. Create WBS
5. Validate Scope
6. Control Scope
1. Plan Scope Management
II - Project Scope Management
The Metro Bus service Rawalpindi-Islamabad consists of approximately 23 km that
starts from flash man hotel Rawalpindi and end at prime minster secretariat
Islamabad. The project has been divided into two parts i-e
 Rawalpindi
 Islamabad
The Rawalpindi part is further divided into three packages i-e
 Package I (Flash man Hotel to committee chowk)
 Package II (Committee Chowk to sixth road) [we only discuss this package]
 Package III (Sixth road to IJP road Rawalpindi)
The total length of MBS Islamabad will be 13.6 km. The Islamabad part has been
further divided into five packages
 Package I: Faizabad to Peshawar Modr 4.4 km
 Package II: Interchange Peshawar Modr 1.1 km
 Package III: Peshawar Modr to Centaurus 2.9 km
 Package IV: Centaurus to Shaheed-e-Millat 3.1 km
 Package V: Shaheed-e-Millat to Secretariat 2.156 km
2. Collect Requirements
II - Project Scope Management
The process of determining,
documenting, and managing
stakeholder needs and requirements to
meet project objectives. In this regard a
detailed study was conducted by CDA
in December, 2012.
II - Project Scope Management
The Reasons behind Rawalpindi-Islamabad Metro Bus Project
• Population Growth of the Capital
• Population Growth of Rawalpindi
• Traffic Burden on Murree Road
• Future Requirements of Islamabad-Rawalpindi Metropolitan Area
• Requirement of Urban Bus Transport Service
Benefits of Rawalpindi-Islamabad Metro Bus Project
II - Project Scope Management
1. Support local economies
2. Attract business investments
3. Attract tourism
4. Reduce crime
5. Improve pedestrian safety
6. Increase use of public transportation
7. Improve public transport
8. Improve the environment
3. Define Scope
II - Project Scope Management
The detailed description of the project and product.
 Fixed Price Contract
 Procurement of land
 Structural Dimensions
 Architectural Designs and Maps
 Casting Working Piles (Inset with reverse rotary system)
 Piers Shafts ( Steel form work with batching plant concrete)
 Transform (Steel form work with concrete pump & batching plant)
 R.C.C Box Girder precast pre-stressed
 Earth Work ( Approved Rollers
 Marketing Strategy And Mix
 Project mile stones
 Composite Approval from authorities / NOC's
 Architectural Drawings
 Foundation excavation
II - Project Scope Management
4. Create WBS Rawalpindi-
Islamabad MBS
Rawalpindi Phase Islamabad Phase
Package II Package III
Package I Package
II
Package III Package IV
Package V
Package I
III - Project Time Management
1. Plan Schedule Management
2. Define Activities
3. Sequence Activities
4. Estimate Activity Resources
5. Develop Schedule
6. Control Schedule
III - Project Time Management
1. Plan Schedule Management
III - Project Time Management
III - Project Time Management
III - Project Time Management
III - Project Time Management
2. Definition, Sequence and Estimation of Activities
III - Project Time Management
III - Project Time Management
3. Control of Activities
III - Project Time Management
IV - Project Cost Management
1. Plan Cost Management
2. Estimate Costs
3. Determine Budget
4. Control Cost
The 29th meeting of Provincial Development Working Party (PDWP) approved
IV - Project Cost Management
Industries Sector
Acquisition of Land for Establishment of Garment Industrial Zone (GIZ), District Sheikhupura
Cost: PKR 2,538.830 million | Status: Approved
Transport Sector
Rawalpindi-Islamabad Metrobus Project, Land Acquisition & Shifting of Utilities
Cost: PKR 2,957.000 million | Status: Approved
Rawalpindi-Islamabad Metrobus Project, Package-I: Flashman Hotel Committee Chowk
(length-2.9 km)
Cost: PKR 5,670.671 million | Status: Approved
Rawalpindi-Islamabad Metrobus Project, Package-II: Committee Chowk to Sixth Road
(length-3.2 km)
Cost: PKR 4,937.757 million | Status: Approved
Rawalpindi-Islamabad Metrobus Project, Package-III: Sixth Road to IJP Road (length-2.5 km)
Cost: PKR 4460.421 million | Status: Approved
1. Plan Cost Management
IV - Project Cost Management
2. Estimate Costs
In the Budget 2014-2015 the Prime
Minister Nawaz Sharif inaugurated mass
transit project for the twin cities on March
23, 2014. The Rawalpindi-Islamabad Metro
Bus Service project will be completed at a
cost of Rs. 44.21 billion within 10 months.
3. Estimate Costs
IV - Project Cost Management
Summary of Financial Details
4. Control Costs
IV - Project Cost Management
Sr.
#
Name of Package A.A
Cost
Amount
Released
Expenditure Balance
Available
1 Rawalpindi Part 19.62 14.66 10.71 3.95
2 Islamabad Part 23.84 23.66 9.37 14.29
3 Bus Depot 1.48 - - -
Total 44.94 38.32 20.08(45%) 18.24
RAWALPINDI PART
IV - Project Cost Management
Sr. # Name of Package A.A Cost Amount
Released
Expenditure
1 Land Acquisition & Shifting of Utilities 2.81 2.81 2.81 (100%)
2 Package-I 5.67 4.02 3.18 (68%)
3 Package-II 4.93 3.40 2.52 (51%)
4 Package-III 4.46 3.13 2.05 (46%)
5 Package-IV Escalators, Elevators & Platform Screen
Doors (PSD)
1.30 1.30 0.15(12%)
6 PMA Command & Control Centre 0.45 - -
Total 19.62 14.66 10.71 (55%)
IV - Project Cost Management
ISLAMABAD PART
Sr. # Name of Package A.A Cost Amount
Released
Expenditure
1 Package-Isb-I 5.20 23.66 2.30 (44%)
2 Package-Isb-II 6.75 2.01 (30%)
3 Package-Isb-III 3.73 2.24 (60%)
4 Package-Isb-IV 3.95 1.64 (42%)
5 Package- Isb-V 2.47 0.99 (40%)
6 Package- Isb-VI Escalators, Elevators &
Platform Screen Doors (PSD)
1.73 0.19 (11%)
Total 23.83 23.66 9.37 (39%)
V - Project Quality Management
1. Plan Quality Management
2. Perform Quality Assurance
3. Control Quality
1. Plan Quality Management
V - Project Quality Management
The process of identifying quality requirements and/or standards
for the project and its deliverables and documenting how the
project will demonstrate compliance with quality requirements.
2. Perform Quality Assurance
V - Project Quality Management
The process of auditing the
quality requirements and
the results from quality
control measurements to
ensure that appropriate
quality standards and
operational definitions are
used.
The process of monitoring and recording results of executing the
quality activities to assess performance and recommend necessary
changes.
V - Project Quality Management
3. Control Quality
VI - Project Human Resource Management
1. Plan Human Resource Management
2. Acquire Project Team
3. Develop Team
4. Manage Team
1. Plan Human Resource Management
VI - Project Human Resource Management
As per Staff Management Plan for the Package II of the Rawalpindi Phase of Metro Bus
Project it requires approximately 400 employees.
 Project Manager
 Procurement and Logistics Manager
 Construction Manager
 Construction Workers
 Human Resource Manager
 Finance and Accounts Manager
 Budget Control Team Lead
 Risk Manager
 Chief Mechanical Engineer
 Civil Engineers
 Equipment Deployment Engineer
 3rd Engineers
 Lead Architect and Designers
 Electrical Engineers
 Security Guards
2. Manage and Acquire Project Team
VI - Project Human Resource Management
VII - Project Communication Management
1.Planning Communications
2.Managing Communications
3.Control Communications
1.Planning and Managing Communications
The PMO of the Package – II of
Rawalpindi Part manage the
communication on regular basis through
press conferences, media awareness and
visit to communities.
VII - Project Communication Management
VII - Project Communication Management
The process of monitoring and controlling communication throughout the entire project
life cycle to ensure the information needs of the project stakeholders are met.
Following is one of the example that the stakeholders at Senate Session level are kept
informed regarding any issue:
2. Control Communications
VII - Project Communication Management
VII - Project Communication Management
RAWALPINDI - ISLAMABAD METRO BUS PROJECT
RAWALPINDI PACKAGE-II
PROJECT PROGRESS
25-03-2015
FROM COMMITTEE CHOWK TO 6TH ROAD
(RAWALPINDI PACKAGE-II, Length = 3.2 Km)
Sr.
No
Description
of Activity
Unit
Total
(Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
i Super Structure Job 1 0.89 0.95 0.05 95%
ii NJB LM 6400 6300 6300 100 98%
iii Walkway LM 2524 80 2175 349 86%
iv Ducts LM 2500 645 2175 349 86%
v Light Poles Foundation No. 235 235 235 0 100%
vi Light Poles Erection No. 235 165 205 30 87%
vii Asphaltic Wearing Course LM 2524 136 2524 0 100%
At Grade Works
Viii
a
Dismantling/Scarification of
Existing Road R/S
LM 320 170 250 70 78%
b L/S LM 850 50 300 550 35%
ix Side Drain Base Slab LM 3600 880 2125 1475 59%
x Side Drain Walls LM 3600 754 1094 2506 30%
xi Side Drain Top Slab LM 6400 925 1880 4520 29%
xii Walkway LM 2524 0 0 6400 0%
xiii PCC Kerb Stones (B/S) LM 12800 0 0 12800 0%
xiv Asphaltic Base Course LM 3200 675 1000 1524 40%
xv Asphaltic Wearing Course LM 3200 0 0 3200 0%
PROGRESS
From Committee Chowk to Sixth Road (RAWALPINDI-PACKAGE-II)
Sr.
No.
Description of Activity Unit Total (Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
Station Work
1 Tuff Pavers (80mm) SM 3100 425 2015 1085 65%
2 Platform Walls LM 432 232 423.36 8.64 98%
3 Platform Slab LM 216 0 205.2 10.8 95%
4 Floor Tiles SM 500 25 125 375 25%
5
Erection of Steel
Structure
% 100 45 80 20 80%
6 ACP Panel % 100 0 20 80 20%
7 Glass Walls % 100 0 0 100 0%
8 Ticketing Booth No 1 0 0 1 0%
9 Staff Toilet Job 1 0 0.5 0.5 50%
10 PSD Doors Structure No 18 0 18 0 100%
11 PSD Doors 0 18 0%
PROGRESS
Waris Khan Station
Sr.
No.
Description of Activity Unit Total (Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
11
Erection of Steel
Structure(Ped. Bridge)
% 100 60 80 20 80%
12 Concourse Column No 3 3 3 0 100%
13 Concourse Slab No 1 1 1 0 100%
14
Pedestrian Bridge
Footings
No 12 12 12 0 100%
15 Emergency Stair Footing No 4 0 0.8 3.2 20%
16 Escalators Pit No 3 2 3 0 100%
17 Elevators Pit No 3 2 3 0 100%
18 Escalators No 3 3 3 0 100%
19 Elevators No 3 3 0 3 0%
20 Public Toilets Job 1 0 0.2 0.8 20%
PROGRESS
Waris Khan Station
Sr.
No.
Description of Activity Unit Total (Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
Station Work
1 Tuff Pavers (80mm) SM 3600 0 3420 180 95%
2 Platform Walls LM 500 440 500 0 100%
3 Platform Slab LM 250 80 250 0 100%
4 Floor Tiles SM 2200 0 2156 44 98%
5
Erection of Steel
Structure
% 100 22 100 0 100%
6 ACP Panel % 100 0 80 20 80%
7 Glass Walls % 100 0 20 80 20%
8 Ticketing Booth No 1 0 0 1 0%
9 Staff Toilet Job 1 0 0 1 0%
10 PSD Doors Structure No 18 0 14 4 78%
11 PSD Doors No 18 0 0 18 0%
PROGRESS
Chandni Chowk Station
Sr.
No.
Description of Activity Unit Total (Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
11
Erection of Steel
Structure(Ped. Stair)
% 100 25 85 15 85%
12 Pedestrian Stair Footings No 4 3 4 0 100%
13 Escalators Pit No. 1 1 1 0 100%
14 Elevator Pit No. 1 1 1 0 100%
15 Escalators No 1 1 1 0 100%
16 Elevators No 1 1 0 1 0%
17 Public Toilets Job 1 0.5 0.9 0.1 90%
PROGRESS
Chandni Chowk Station (Pedestrian Stair at Grade to Platform)
Sr.
No.
Description of Activity Unit Total (Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
1 Base Slab LM 250 250 250 0 100%
2 Walls LM 500 500 500 0 100%
3 Top slab LM 73 73 73 0 100%
4 Stairs No. 3 2 2 1 67%
5 Tiles SM 4000 160 2550 1450 64%
6 Elevator Pit No 3 1 3 0 100%
7 Escalator Pit No 3 1 3 0 100%
9 Elevator No 3 0 0 3 0%
9 Escalator No 3 0 1 2 33%
PROGRESS
Chandni Chowk Pedestrian Underpass
Sr.
No.
Description of Activity Unit Total (Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
Station Work
1 Tuff Pavers (80mm) SM 3100 0 2480 620 80%
2 Platform Walls LM 430 205 430 0 100%
3 Platform Slab LM 215 45 215 0 100%
4 Floor Tiles SM 700 110 420 280 60%
5
Erection of Steel
Structure
% 100 65 90 10 90%
6 ACP Panel % 100 0 30 70 30%
7 Glass Walls % 100 0 0 100 0%
8 Ticketing Booth No 1 0 0 1 0%
9 Staff Toilet Job 1 0 0.5 0.5 50%
10 PSD Doors Structure No 18 0 9 9 50%
11 PSD Doors No 18 0 0 18 0%
PROGRESS
Rehmanabad Station
Sr.
No.
Description of Activity Unit Total (Qty)
Achievement
(18-03-2015)
Achievement
(25-03-2015)
Over all
Balance
(Qty)
%age
Complete
11
Erection of Steel
Structure(Ped. Bridge)
% 100 45 80 20 80%
12 Concourse Column No 3 3 3 0 100%
13 Concourse Slab No 1 1 1 0 100%
14
Pedestrian Bridge
Footings
No 16 15 16 0 100%
15 Emergency Stair Footing No 4 4 3 1 75%
16 Elevator Pit No 3 2 2 1 67%
17 Escalator Pit No 3 2 2 1 67%
18 Elevator No 3 0 0 3 0%
19 Escalator No 3 0 2 1 67%
PROGRESS
Rehmanabad Station
VIII - Project Risk Management
1. Plan Risk Management
2. Identify Risks
3. Perform Quantitative Analysis
4. Perform Qualitative Analysis
5. Control Risk
In a mega project like Metro Bus Service Islamabad-Rawalpindi there may exists
number of different risk factors that need to be mitigated. Following are some of the
examples of the risks and their plans by PMO.
VIII - Project Risk Management
S.NO RISK PLAN SOURCE
1 The Civil Aviation Authority (CAA) has
expressed concerns that the elevated
road to be constructed for the Rs38
billion Metro Bus service will be a risk for
the flights on the runway of Benazir
Bhutto International Airport.
Neither the provincial
government nor the local
administration contacted CAA
for a No-Objection Certificate
(NoC) in this regard, but the
authority will raise the issue on
the appropriate forum soon
Dawn News (March,
2014)
2 Environment Impact Assessment EIA Report prepared by NESPAK Tribune (March,
2014
3 Hundreds of laborer's working on the
Metro Bus Project in the twin cities are
not only vulnerable to the risks involved
in construction, and health hazards but
also exploitation owing to the apathy of
the government.
Metro Bus Project Office look
after in such hazards and is
taking care of security
measures.
News Today
January 2nd, 201
1. Plan Risk Management
2. Perform Qualitative Analysis
VIII - Project Risk Management
VIII - Project Risk Management
3. Perform Quantitative Analysis
The load pile tests are conducted to determine the underground formations to
prove that the soil is capable of sustaining the designed load of the
infrastructure that could be a bridge or even a high rise building.
During first 30 days’ time of the contract award these tests are being
conducted around Sixth Road and Chandni Chowk flyovers. The results of
the load pile tests will be utilized by the consultant and the contractor of the
project.
VIII - Project Risk Management
4. Plan and Controlling the Risk Responses
VIII - Project Risk Management
VIII - Project Risk Management
IX - Project Procurement Management
1. Plan Procurements
2. Conduct Procurements
3. Control Procurements
4. Close Procurements
In this regard Punjab Province has adopted its own PPRA rules in 2009, after
getting them approved from its assembly while recently it made certain
amendments in the rules, aimed at speeding up development projects.
The PC-1 of the mega project has been approved by the Provincial Development
Working Party (PDWP) on February 4, and under the provisions of Punjab PPRA
rules, Nespak has been appointed as the consultant for the project.
To ensure the timely completion of the project, the Punjab government has
authorised the RDA to execute the work, while the PMA will operate the bus
service. The project director confirmed that in a bid to save time certain provisions
have been initiated by the RDA.
IX - Project Procurement Management
1. Plan Procurements
2. Conduct Procurements
IX - Project Procurement Management
Conduct Procurements
IX - Project Procurement Management
IX - Project Procurement Management
IX - Project Procurement Management
The process of managing
procurement relationships,
monitoring contract
performance, and making
changes and corrections as
appropriate
3. Control and Close Procurements
IX - Project Stakeholders Management
IX - Project Stakeholders Management
1. Identify Stakeholders
Following are different stakeholders
 Fedral Government of Pakistan
 Punjab Government
 Pakistan Environmental Protection Agency (Pak-EPA)
 Environment Impact Assessment (EIA)
 Capital Development Authority (CDA)
 Rawalpindi Development Authority (RDA)
 Punjab Environment Protection Agency (PEPA)
 Trade Community
 General Public
For the proper planning and
management of Metro
Bus project the participants of
shops and property of the
traders of Murree Road are the
part of justifiably assessment
for payment of reasonable
compensation.
2. Planning, Managing and Controlling Stakeholder Management
IX - Project Stakeholders Management
Metro islamabad rawalpindi
Metro islamabad rawalpindi
Metro islamabad rawalpindi

More Related Content

What's hot

What is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - OverviewWhat is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - Overviewuvahidy
 
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination surveyAkash Pandey
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalRajesh Prasad
 
Sky bus an emerging technology
Sky bus an emerging technologySky bus an emerging technology
Sky bus an emerging technologyAmiya Kumar Samal
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India pptNikita James
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.Axay Sharma
 
Urban Transportation Market In India
Urban Transportation Market In IndiaUrban Transportation Market In India
Urban Transportation Market In IndiaJaspal Singh
 
Pakistan railways
Pakistan railwaysPakistan railways
Pakistan railwaysMarwed
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT Deepak Kumar
 
Public transport problems in mumbai
Public transport problems in mumbaiPublic transport problems in mumbai
Public transport problems in mumbaiaziz khan
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase IKaran Shah
 
Urban Transportation system - mass transit system
Urban Transportation system - mass transit systemUrban Transportation system - mass transit system
Urban Transportation system - mass transit systemEddy Ankit Gangani
 

What's hot (20)

Railway pakistan
Railway pakistanRailway pakistan
Railway pakistan
 
03 public transport
03 public transport03 public transport
03 public transport
 
What is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - OverviewWhat is Lahore Metro Train Project - Overview
What is Lahore Metro Train Project - Overview
 
Mobility and City Streets: Bus Karo by Amit Bhatt
Mobility and City Streets: Bus Karo by Amit BhattMobility and City Streets: Bus Karo by Amit Bhatt
Mobility and City Streets: Bus Karo by Amit Bhatt
 
TRAINING ON METRO TRAIN
TRAINING ON METRO TRAINTRAINING ON METRO TRAIN
TRAINING ON METRO TRAIN
 
Origin & destination survey
Origin & destination surveyOrigin & destination survey
Origin & destination survey
 
Cmrl ppt
Cmrl pptCmrl ppt
Cmrl ppt
 
Bus Karo 2.0 Webinar 1: Initiating City Bus Services
Bus Karo 2.0 Webinar 1: Initiating City Bus Services Bus Karo 2.0 Webinar 1: Initiating City Bus Services
Bus Karo 2.0 Webinar 1: Initiating City Bus Services
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West Bengal
 
Sky bus an emerging technology
Sky bus an emerging technologySky bus an emerging technology
Sky bus an emerging technology
 
Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
 
Ksrtc
KsrtcKsrtc
Ksrtc
 
Urban Transportation Market In India
Urban Transportation Market In IndiaUrban Transportation Market In India
Urban Transportation Market In India
 
Pakistan railways
Pakistan railwaysPakistan railways
Pakistan railways
 
Railway communication in bangladesh
Railway communication in bangladeshRailway communication in bangladesh
Railway communication in bangladesh
 
DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT DMRC SUMMER INTERNSHIP REPORT
DMRC SUMMER INTERNSHIP REPORT
 
Public transport problems in mumbai
Public transport problems in mumbaiPublic transport problems in mumbai
Public transport problems in mumbai
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
Urban Transportation system - mass transit system
Urban Transportation system - mass transit systemUrban Transportation system - mass transit system
Urban Transportation system - mass transit system
 

Viewers also liked

Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotelMuhammad Farhan Javed
 
Serena hotel islamabad
Serena hotel islamabadSerena hotel islamabad
Serena hotel islamabadAbdul Basit
 
Metro, A Presentation of Production Management
Metro, A Presentation of Production ManagementMetro, A Presentation of Production Management
Metro, A Presentation of Production ManagementMuti ur Rahman Khan Lodhi
 
Case Study: National Express in the Fast Lane to Sustainability
Case Study: National Express in the Fast Lane to Sustainability Case Study: National Express in the Fast Lane to Sustainability
Case Study: National Express in the Fast Lane to Sustainability bestlinksolutions
 
National Express Company Audit (2014)
National Express Company Audit (2014)National Express Company Audit (2014)
National Express Company Audit (2014)Alexandra MacLeod
 
Project integration management
Project integration management Project integration management
Project integration management KU Leuven
 
OLT-1_SLD_Safe City Project Islamabad
OLT-1_SLD_Safe City Project IslamabadOLT-1_SLD_Safe City Project Islamabad
OLT-1_SLD_Safe City Project IslamabadKhurram Shafique
 
Development of Islamabad through SME
Development of Islamabad through SME Development of Islamabad through SME
Development of Islamabad through SME Hira Shaukat
 
Capital Budgeting Techniques
Capital Budgeting TechniquesCapital Budgeting Techniques
Capital Budgeting TechniquesNatasha Shiri
 
FUN CITY ISB (Itb project)
FUN CITY ISB (Itb project)FUN CITY ISB (Itb project)
FUN CITY ISB (Itb project)saadtipu sultan
 
My Native Town
My Native TownMy Native Town
My Native TownLily Lake
 
Rawalpindi, Potohar town, Union councils list
Rawalpindi, Potohar town, Union councils listRawalpindi, Potohar town, Union councils list
Rawalpindi, Potohar town, Union councils listShaikh Aamer
 

Viewers also liked (20)

metrobus project rwp
metrobus project rwpmetrobus project rwp
metrobus project rwp
 
Project Construction of 5 star hotel
Project Construction of 5 star hotelProject Construction of 5 star hotel
Project Construction of 5 star hotel
 
Metro presentation
Metro presentation Metro presentation
Metro presentation
 
Serena hotel islamabad
Serena hotel islamabadSerena hotel islamabad
Serena hotel islamabad
 
Metro, A Presentation of Production Management
Metro, A Presentation of Production ManagementMetro, A Presentation of Production Management
Metro, A Presentation of Production Management
 
Assignment
AssignmentAssignment
Assignment
 
Case Study: National Express in the Fast Lane to Sustainability
Case Study: National Express in the Fast Lane to Sustainability Case Study: National Express in the Fast Lane to Sustainability
Case Study: National Express in the Fast Lane to Sustainability
 
National Express Company Audit (2014)
National Express Company Audit (2014)National Express Company Audit (2014)
National Express Company Audit (2014)
 
Project integration management
Project integration management Project integration management
Project integration management
 
Architect
ArchitectArchitect
Architect
 
OLT-1_SLD_Safe City Project Islamabad
OLT-1_SLD_Safe City Project IslamabadOLT-1_SLD_Safe City Project Islamabad
OLT-1_SLD_Safe City Project Islamabad
 
Development of Islamabad through SME
Development of Islamabad through SME Development of Islamabad through SME
Development of Islamabad through SME
 
Capital Budgeting Techniques
Capital Budgeting TechniquesCapital Budgeting Techniques
Capital Budgeting Techniques
 
FUN CITY ISB (Itb project)
FUN CITY ISB (Itb project)FUN CITY ISB (Itb project)
FUN CITY ISB (Itb project)
 
anjumAkseer
anjumAkseeranjumAkseer
anjumAkseer
 
Native town
Native townNative town
Native town
 
My Native Town
My Native TownMy Native Town
My Native Town
 
Old rawalpindi
Old rawalpindiOld rawalpindi
Old rawalpindi
 
Rawalpindi, Potohar town, Union councils list
Rawalpindi, Potohar town, Union councils listRawalpindi, Potohar town, Union councils list
Rawalpindi, Potohar town, Union councils list
 
My native city
My native cityMy native city
My native city
 

Similar to Metro islamabad rawalpindi

Mass transit system
Mass transit systemMass transit system
Mass transit systemAsjad Khuram
 
Faisalabad metrobus project
Faisalabad metrobus projectFaisalabad metrobus project
Faisalabad metrobus projectZaheerBabur2
 
mrtscp2018-190316162158 mass rapid transit system.pdf
mrtscp2018-190316162158 mass rapid transit system.pdfmrtscp2018-190316162158 mass rapid transit system.pdf
mrtscp2018-190316162158 mass rapid transit system.pdfchhananpooja8827
 
MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMChandanPadhi3
 
Transportation analysis at anand vihar
Transportation analysis at anand viharTransportation analysis at anand vihar
Transportation analysis at anand viharSneha Lata
 
Mashhad muroc company_presentation_summary20160613
Mashhad muroc company_presentation_summary20160613Mashhad muroc company_presentation_summary20160613
Mashhad muroc company_presentation_summary20160613Abdullah Sarkhosh
 
MUROC, Mashhad Urban Railway Operation Company
MUROC, Mashhad Urban Railway Operation CompanyMUROC, Mashhad Urban Railway Operation Company
MUROC, Mashhad Urban Railway Operation CompanyAbdullah Sarkhosh
 
Market research on the Bandra Skywalk
Market research on the Bandra SkywalkMarket research on the Bandra Skywalk
Market research on the Bandra SkywalkHeemanish Midde
 
Wadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdfWadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdfssuser9aea942
 
Local train v/s best bus in mumbai
Local train v/s best bus in mumbaiLocal train v/s best bus in mumbai
Local train v/s best bus in mumbaiAnil Prajapati
 
DESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUSDESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUSSruthiTummalapalli
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro raillibin paul
 
INDIAN RAILWAYS SERVICE MARKETING
INDIAN RAILWAYS SERVICE MARKETINGINDIAN RAILWAYS SERVICE MARKETING
INDIAN RAILWAYS SERVICE MARKETINGAMAR ID
 
Rail rapid transit system (india)
Rail rapid transit system (india)Rail rapid transit system (india)
Rail rapid transit system (india)Sourabh Jain
 

Similar to Metro islamabad rawalpindi (20)

Mass transit system
Mass transit systemMass transit system
Mass transit system
 
Faisalabad metrobus project
Faisalabad metrobus projectFaisalabad metrobus project
Faisalabad metrobus project
 
mrtscp2018-190316162158 mass rapid transit system.pdf
mrtscp2018-190316162158 mass rapid transit system.pdfmrtscp2018-190316162158 mass rapid transit system.pdf
mrtscp2018-190316162158 mass rapid transit system.pdf
 
MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEM
 
Transportation analysis at anand vihar
Transportation analysis at anand viharTransportation analysis at anand vihar
Transportation analysis at anand vihar
 
Brts
BrtsBrts
Brts
 
Mashhad muroc company_presentation_summary20160613
Mashhad muroc company_presentation_summary20160613Mashhad muroc company_presentation_summary20160613
Mashhad muroc company_presentation_summary20160613
 
BRTS
BRTSBRTS
BRTS
 
MUROC, Mashhad Urban Railway Operation Company
MUROC, Mashhad Urban Railway Operation CompanyMUROC, Mashhad Urban Railway Operation Company
MUROC, Mashhad Urban Railway Operation Company
 
Indian Railways ppt.
Indian Railways ppt.Indian Railways ppt.
Indian Railways ppt.
 
Dubai metro map
Dubai metro mapDubai metro map
Dubai metro map
 
Market research on the Bandra Skywalk
Market research on the Bandra SkywalkMarket research on the Bandra Skywalk
Market research on the Bandra Skywalk
 
Wadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdfWadhwa Wise City Concept-1.pdf
Wadhwa Wise City Concept-1.pdf
 
Local train v/s best bus in mumbai
Local train v/s best bus in mumbaiLocal train v/s best bus in mumbai
Local train v/s best bus in mumbai
 
DESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUSDESIGN STANDARDS FOR PLANNING A BUS TERMINUS
DESIGN STANDARDS FOR PLANNING A BUS TERMINUS
 
ahmedabad BRTS study
ahmedabad BRTS studyahmedabad BRTS study
ahmedabad BRTS study
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
INDIAN RAILWAYS SERVICE MARKETING
INDIAN RAILWAYS SERVICE MARKETINGINDIAN RAILWAYS SERVICE MARKETING
INDIAN RAILWAYS SERVICE MARKETING
 
Rail rapid transit system (india)
Rail rapid transit system (india)Rail rapid transit system (india)
Rail rapid transit system (india)
 
SEM 1 PRESENTATION
SEM 1 PRESENTATIONSEM 1 PRESENTATION
SEM 1 PRESENTATION
 

Recently uploaded

Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
SMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptxSMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptx
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptxShovan Prita Paul .
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlEdouardHusson
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...tanu pandey
 
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...tanu pandey
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentationgememarket11
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...SUHANI PANDEY
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourCall Girls in Nagpur High Profile
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31JSchaus & Associates
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...SUHANI PANDEY
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learningNAP Global Network
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...SUHANI PANDEY
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterChristina Parmionova
 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha ThakurSUHANI PANDEY
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 

Recently uploaded (20)

Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
SMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptxSMART BANGLADESH  I    PPTX   I    SLIDE   IShovan Prita Paul.pptx
SMART BANGLADESH I PPTX I SLIDE IShovan Prita Paul.pptx
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
 
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
 
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hourcelebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
celebrity 💋 Agra Escorts Just Dail 8250092165 service available anytime 24 hour
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
 
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 

Metro islamabad rawalpindi

  • 1. MAPPING PROJECT MANAGEMENT PRACTICES IN A MEGA PROJECT RAWALPINDI-ISLAMABAD METRO BUS SERVICE
  • 2. Essentials of Project Management MS(PM) Arif Khalil (CMS: 15691) Tahir Muzaffar Malik (CMS: 15592) Mahmood Ahmed (CMS: 15344) Muhammad Asif Khan (CMS: 15479) Wasi ullah (CMS: 15403) Muhammad Tariq Zafar (CMS: 15306) A team effort by following members
  • 3. AN INTRODUCTION TO PAKISTAN’S 1ST MASS TRANSPORT SYSTEM Introduction The Rawalpindi-Islamabad Metrobus (‫بس‬ ‫میٹرو‬ ‫آباد‬ ‫اسالم‬ ‫)راولپنڈی‬ is a 24 km (14.9 mi) bus rapid transit under-construction in the twin cities of Rawalpindi and Islamabad, Pakistan.
  • 4. The concept of Metro Bus System (MBS) is a rapid mode of transportation that can provide the quality of rail transit with the flexibility of buses. MBS has been implemented in several cities throughout the world as a low-cost, rail-like method of moving people quickly and efficiently. Introduction Islamabad is the Capital City of Pakistan and the ninth largest city in the country. Located within the Islamabad Capital Territory (ICT), the population of the city has grown from 100,000 in 1951 to 1.30 million in 2012. The greater Islamabad – Rawalpindi Metropolitan Area is the third largest conurbation in Pakistan with a population of over 4.5 million inhabitants.
  • 5. Pakistan Economic Survey 2013-14 • Twin cities Islamabad and Rawalpindi are growing at a rate of more than 4 percent per annum • With present growth trends it is expected that the population would increase upto 7.0 million in next twenty years • Currently private transport is the major means of mobility between two cities comprising of Mazda, Toyota Hiace, and Suzuki vans plying on various routes within and between the two cities. • Traffic volumes of over 210,000 vehicles ply on three major corridors connecting two cities carrying around 525,000 passengers. The Need for MBS
  • 6. It is estimated that public transport demand of around 153,000 passengers is required to cater daily basis between the two cities. Interestingly this passenger demand is concentrated around a corridor which is of high density and strategically located to provide for a rapid transit system. The Need for MBS
  • 7.
  • 8. The Need for MBS The government will execute this project through Rawalpindi Development Authority (RDA) It will work in close coordination with the Capital Development Authority (CDA) for the Islamabad Part of the project. Punjab Metrobus Authority (PMA) will control the operation & maintenance of the project after its completion.
  • 9. The project will start from near Flashman Hotel on Mall Road Rawalpindi and follow the existing Murree Road upto Faizabad. It will then turn left into the federal territory and follow I.J.P. road upto 9th Avenue.
  • 10. MBS: Quick Facts Total Length: 22.5 Kilometers Total Cost: 44.21 Billion Rupees Total Buses: 64 Capacity per Bus: 108 People Project Completion Time: 10 Months Total Stops: 27 Total Expected MBS users per Day: 153,000
  • 11. CONSTRUCTION & COST The works of Rawalpindi Part (03 Packages) have been awarded and the contractors are mobilized at the site. The works of Islamabad part of five Packages has also been started. Prime Minister inaugurated the project on 23rd March 2014 and work was started from the same day. Metrobus project will be completed in next 10 months. The system was built on the build–operate–transfer basis via the collaboration between the Punjab and the Turkish government.
  • 12. Project Overview  Signal Free: The entire length i.e. 8.6 km of Metro Bus corridor in Rawalpindi area shall be elevated structure whereas about 14 km in Islamabad shall be at-grade but made signal-free by constructing grade separations at various intersections.  Number of Stations: Ten (10) stations in the Rawalpindi Part and fourteen (14) in the Islamabad Part are provided along the corridor.  Functional Elements: Functional elements at the stations include ticketing booths, concourse level passenger transfer, escalators, platform screen doors turnstiles for automatic fare collection and all other amenities for passenger convenience.  Central Control Room: A central ITS control room is also included in the project to control the whole operation of the Metro Bus system.  Number of Lanes: Initially the provision of a 10 lane Underpass (2 Lanes for Metro Bus and 8 Lanes for mix traffic) along the 9th Avenue was proposed at Peshawar Mor intersection. Later on, in view of the traffic issues at Peshawar Mor intersection, ongoing Widening/Rehabilitation of Kashmir Highway & its link with new Islamabad Airport, it was decided to dovetail the Metro Bus corridor in the interchange already designed by CDA which will cost Rs. 6.75 Billion. The same will be simultaneously executed with Metro Bus Project.
  • 13. The Buses All Buses have been produced specifically for the Islamabad MBS by Volvo. The ‘Arctic Buses’ hold 108 passengers and are standard for all major Bus Rapid Transit Systems including the one in Tehran and Istanbul Each bus has special seating for Women & Children as well as for Handicapped Persons. All buses are elevated for easier passenger entry at platforms
  • 14. Travelling on MBS The MBS was completely free for the first month. After that there are standard charges put in to use. The Metro Bus Card and MBS Token can both be used to travel on the MBS. The MBS Card is like Travel Cards around the world that can be recharged for multiple journeys, it costs 133 Rupees. School Children and Students as well as senior citizens will be charged a discounted rate.
  • 15. Total Expected MBS users per Day • According to the Islamabad Transport Company, the daily ridership of the Metro bus exceeds 130,000 with the peak hourly ridership being 10,000 passengers per hour per direction
  • 16. • Labour, and some tourists have the same route to commute. Now, they can easily avail the metro bus service. • It is not reaching out to colleges, universities, hospitals and offices nearby, so that all these students could also have availed it instead of some other private transport. •The MBS is an affordable initiative, which will go a long way in reducing emissions and traffic volume. It offers safe, reliable and comfortable transport . Advantages
  • 17. Rawalpindi Part of Metro Bus Route Information
  • 18. Stations along Murree Road Rawalpindi R A W A L P I N D I Faizabad Interchange Flash Man Chowk Saddar Total Elevated 10 Nos. Stations Length of 8.6 Km Rawalpindi Part Marrir Chowk Liaqat Bagh Committee Chowk Waris Khan Hospital Rehmanabad 6th Road Faizabad I-8 I-9 I-10 I-11 Shamsabad
  • 19. M A L L R O A D Flash Man Hotel Saddar Station Marrir Chowk Station Turnaround 10 ~ 15 Buses Saddar Katchery 150 m Start Point Church Open Plot - 4 Kanals for Control Room & Parking Saddar Defence Area
  • 21. Liaqat Bagh Station Committee Chowk Station Liaqat Road Liaqat Bagh Station Liaqat Bagh
  • 22. Committee Chowk Station Iqbal Road Existing Underpass Committee Chowk Station
  • 23. Waris Khan Station Waris Khan Station Hospital Station
  • 25. 6th Road Flyover 5th Road Rehmanabad Station Khanna Road 6th Road Station
  • 26. 6th Road Flyover 6th Road Station Existing Flyover Nawaz Sharif Park Shamsabad Station
  • 27. I-8 FAIZABAD INTERCHANGEPir Wadhai I J P R O A D Faizabad Station NAWAZ SHARIF PARK ARID UNIVERSITY RAWALPINDI CRICKET STADIUM Shamsabad Station Faizabad Station
  • 28. Perspective View of Proposed MBS Station
  • 29. Islamabad Part of Metro Bus Route Information
  • 30. F-10 F-9 F-8 F-7 F-6 G-10 G-9 G-8 G-7 G-6 H-8 I-8 I-9 Faizabad Interchange Zero Point IJP Road Pothar Road Khayban-E- Johar Faiz Ahmed Faiz Road Kashmir Highway Chaman Road Ibn-e-Sina Road Katchery Station Centaurus Saudi Pak Tower 7th Avenue Shaheed-e- Millat Road Parade Ground Secretariat Stations along 9th Avenue & Jinnah Avenue Islamabad Total At-Grade 14 Nos. Stations Length of 13.9 Km Islamabad Part H-10 H-9
  • 31. Flyover MBS At-Grade Service Road Pir Wadhai` Faizabad At-Grade Rotary At-grade Rotary IJP Station MBS Route at IJP-9th Avenue Intersection StadiumRoad` 9thAvenue` IJP Road
  • 32. Arrangement at IJP Road and 9th Avenue Intersection I-9 I-8 Future Rotary Future MBS Present MBS Construction
  • 33. Proposed Interchange at Peshawar Morr With MBS Corridor M-2 Zero Point Sunday Market MBS CORRIDOR 9th Avenue
  • 34. Alignment Plan From Peshawar Morr To Jinnah Avenue M-2 IJPRoad Zero Point Peshawar Morr Station 9thAvenue J i n n a h Av e n u e Chaman Road Station Ibn-e-Sina Station Secretariat G-9 G-8 Sunday Market Kashmir Highway Proposed Interchange 2- Lane Underpass for MBS
  • 35. Alignment Plan From Peshawar Morr To Jinnah Avenue Peshawar Morr Secretariat Ibn-e-Sina Station JinnahAvenue 9 t h A v e n u e S e r v i c e R o a d Proposed Underpass Ibn-e-SinaRoad G-9 G-8 NIRM
  • 36. Junction between 9th Avenue & Jinnah Avenue Proposed Underpass for MBS F-8 10 m widening of one carriageway I-8 2- Lane Underpass for MBS Covered Section Ibn-e-Sina Road Station Covered Section Open Trench
  • 37. Existing Flyover at 8th Avenue 3.3 m widening of Existing Bridge for Mixed Traffic Faisal Masjid Zero Point Centaurus Mall G-7F-7 FAISAL AVENUE Centaurus Station Saudi Pak Tower Station
  • 38. 7th Avenue F-7 9 m widening on each side NIC Tower Zero Point G-7 7th Avenue Station
  • 39. Proposed Interchange at 7th Avenue Centaurus Secretariat Nazim ud Din Road Fazal ul Haq Road 7th Avenue Station ProposedUnderpass ExistingUnderpass ProposedUnderpass Centaurus Secretariat
  • 40. Proposed MBS from Parade Ground to Secretariat Secretariat Marriott Hotel F-6 F-5 Jinnah Avenue Turn around L = 1.2 Km Parliament House Secretariat Station Parade Ground
  • 41. Perspective View of Proposed MBS Station
  • 42. Disadvantages • Cost of project • Effected business a lot • Transporters are much effected. Mapping Project Management Practices In Rawalpindi-Islamabad Metro Bus Service Project Management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements.
  • 43. Project Management Process Groups vs Metro Bus Rawalpindi-Islamabad Project Project Management Process Groups Metro Bus Rawalpindi-Islamabad Project Initiating Process Foundation Stone on 23rd March 2014 Planning Process • Master Plan – (Rawalpindi Part, Islamabad Psrt and Peshawar Mor Interchange) • Project Charter Executing Process • Rawalpindi Part – (03 Packages) • Islamabad Part – (05 Packages) • Peshawar Mor Interchange Monitoring and Controlling Central Command and Control Office Closing Process • Expected date of completion: Jan, 2015 • Expected date to be inaugurated: Feb 2015
  • 44.
  • 46. Project Management Knowledge Areas vs Metro Bus Rawalpindi-Islamabad Project 1: Project Integration Management 2:ProjectScope Management 4: Project Cost Management 7:ProjectCommunications Management 9: Project Procurement Management
  • 47. I - Project Integration Management 1. Project Charter National Logistics Cell, Lemac-Reliable from Turkey and ZKB had already received the contract of nine kilometers in the Rawalpindi section of the Metro Bus Project. FWO (Frontier Work Organization), Habib constructions, Maksons, Zahid Khan and Brother (ZKB) and National Logistics Cell (NLC). The companies that are joint ventures are China Railway First Group-HRL-Metracom, CEW-Sarwar from China, Lemac-Reliable from Turkey and Mal-Calsons
  • 48. I - Project Integration Management 2. Develop Project Management Plan  The project will start from near Flashman Hotel on Mall Road Rawalpindi and follow the existing Murree Road upto Faizabad.  It will then turn left into the federal territory and follow I.J.P. road upto 9th Avenue.  Thereafter, it will turn right and follow the 9th Avenue in Islamabad then turn right on Jinnah Avenue upto the end of Blue Area.  From Blue Area a connection to Secretariat stop will be provided through the open space behind parade ground.  It will cross the Constitution Avenue and another couple of main roads through underpasses.  However, the remaining length of this section is also designed on a lower level in an open Trench section keeping in view various security constraints.
  • 49. I - Project Integration Management
  • 50. I - Project Integration Management
  • 51. I - Project Integration Management
  • 52. 3. Direct and manage project work The Project Management Office is the organizational body or entity assigned various responsibilities related to the centralized and coordinated management of projects under its domain, For MBS the PMO office is near Flashman Hotel Rawalpindi Saddar for Rawalpindi Part and in the F-11 for Islamabad Part. The offices are involved in managing the overall operations and resource allocation. I - Project Integration Management
  • 53. 4. Monitor and Control Project Work Chairman Metro Bus Project Monitoring and Implementation Committee, Hanif Abbasi, claimed that the luxury bus project would complete by end of February. The progress of this project is reviewed at different level of authority as shown below (See Annexure - ): I - Project Integration Management
  • 54. 5. Close Project or Phase The work continues at the project from D-Chowk to Secretariat Blocks, the Bus service will initially operate up to China Chowk only. Though the track of the bus service is almost ready, final touches are being given to the project. Besides, several minor works still pending especially at the Peshawar Mor, including the access to the underground bus station there. I - Project Integration Management
  • 55. II - Project Scope Management Reference: PMBOK® Guide, 5th Edition 1. Plan Scope Management 2. Collect Requirements 3. Define Scope 4. Create WBS 5. Validate Scope 6. Control Scope
  • 56. 1. Plan Scope Management II - Project Scope Management The Metro Bus service Rawalpindi-Islamabad consists of approximately 23 km that starts from flash man hotel Rawalpindi and end at prime minster secretariat Islamabad. The project has been divided into two parts i-e  Rawalpindi  Islamabad The Rawalpindi part is further divided into three packages i-e  Package I (Flash man Hotel to committee chowk)  Package II (Committee Chowk to sixth road) [we only discuss this package]  Package III (Sixth road to IJP road Rawalpindi) The total length of MBS Islamabad will be 13.6 km. The Islamabad part has been further divided into five packages  Package I: Faizabad to Peshawar Modr 4.4 km  Package II: Interchange Peshawar Modr 1.1 km  Package III: Peshawar Modr to Centaurus 2.9 km  Package IV: Centaurus to Shaheed-e-Millat 3.1 km  Package V: Shaheed-e-Millat to Secretariat 2.156 km
  • 57. 2. Collect Requirements II - Project Scope Management The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. In this regard a detailed study was conducted by CDA in December, 2012.
  • 58. II - Project Scope Management The Reasons behind Rawalpindi-Islamabad Metro Bus Project • Population Growth of the Capital • Population Growth of Rawalpindi • Traffic Burden on Murree Road • Future Requirements of Islamabad-Rawalpindi Metropolitan Area • Requirement of Urban Bus Transport Service
  • 59. Benefits of Rawalpindi-Islamabad Metro Bus Project II - Project Scope Management 1. Support local economies 2. Attract business investments 3. Attract tourism 4. Reduce crime 5. Improve pedestrian safety 6. Increase use of public transportation 7. Improve public transport 8. Improve the environment
  • 60. 3. Define Scope II - Project Scope Management The detailed description of the project and product.  Fixed Price Contract  Procurement of land  Structural Dimensions  Architectural Designs and Maps  Casting Working Piles (Inset with reverse rotary system)  Piers Shafts ( Steel form work with batching plant concrete)  Transform (Steel form work with concrete pump & batching plant)  R.C.C Box Girder precast pre-stressed  Earth Work ( Approved Rollers  Marketing Strategy And Mix  Project mile stones  Composite Approval from authorities / NOC's  Architectural Drawings  Foundation excavation
  • 61. II - Project Scope Management 4. Create WBS Rawalpindi- Islamabad MBS Rawalpindi Phase Islamabad Phase Package II Package III Package I Package II Package III Package IV Package V Package I
  • 62. III - Project Time Management 1. Plan Schedule Management 2. Define Activities 3. Sequence Activities 4. Estimate Activity Resources 5. Develop Schedule 6. Control Schedule
  • 63. III - Project Time Management 1. Plan Schedule Management
  • 64. III - Project Time Management
  • 65. III - Project Time Management
  • 66. III - Project Time Management
  • 67. III - Project Time Management 2. Definition, Sequence and Estimation of Activities
  • 68. III - Project Time Management
  • 69. III - Project Time Management 3. Control of Activities
  • 70. III - Project Time Management
  • 71. IV - Project Cost Management 1. Plan Cost Management 2. Estimate Costs 3. Determine Budget 4. Control Cost
  • 72. The 29th meeting of Provincial Development Working Party (PDWP) approved IV - Project Cost Management Industries Sector Acquisition of Land for Establishment of Garment Industrial Zone (GIZ), District Sheikhupura Cost: PKR 2,538.830 million | Status: Approved Transport Sector Rawalpindi-Islamabad Metrobus Project, Land Acquisition & Shifting of Utilities Cost: PKR 2,957.000 million | Status: Approved Rawalpindi-Islamabad Metrobus Project, Package-I: Flashman Hotel Committee Chowk (length-2.9 km) Cost: PKR 5,670.671 million | Status: Approved Rawalpindi-Islamabad Metrobus Project, Package-II: Committee Chowk to Sixth Road (length-3.2 km) Cost: PKR 4,937.757 million | Status: Approved Rawalpindi-Islamabad Metrobus Project, Package-III: Sixth Road to IJP Road (length-2.5 km) Cost: PKR 4460.421 million | Status: Approved 1. Plan Cost Management
  • 73. IV - Project Cost Management 2. Estimate Costs
  • 74. In the Budget 2014-2015 the Prime Minister Nawaz Sharif inaugurated mass transit project for the twin cities on March 23, 2014. The Rawalpindi-Islamabad Metro Bus Service project will be completed at a cost of Rs. 44.21 billion within 10 months. 3. Estimate Costs IV - Project Cost Management
  • 75. Summary of Financial Details 4. Control Costs IV - Project Cost Management Sr. # Name of Package A.A Cost Amount Released Expenditure Balance Available 1 Rawalpindi Part 19.62 14.66 10.71 3.95 2 Islamabad Part 23.84 23.66 9.37 14.29 3 Bus Depot 1.48 - - - Total 44.94 38.32 20.08(45%) 18.24
  • 76. RAWALPINDI PART IV - Project Cost Management Sr. # Name of Package A.A Cost Amount Released Expenditure 1 Land Acquisition & Shifting of Utilities 2.81 2.81 2.81 (100%) 2 Package-I 5.67 4.02 3.18 (68%) 3 Package-II 4.93 3.40 2.52 (51%) 4 Package-III 4.46 3.13 2.05 (46%) 5 Package-IV Escalators, Elevators & Platform Screen Doors (PSD) 1.30 1.30 0.15(12%) 6 PMA Command & Control Centre 0.45 - - Total 19.62 14.66 10.71 (55%)
  • 77. IV - Project Cost Management ISLAMABAD PART Sr. # Name of Package A.A Cost Amount Released Expenditure 1 Package-Isb-I 5.20 23.66 2.30 (44%) 2 Package-Isb-II 6.75 2.01 (30%) 3 Package-Isb-III 3.73 2.24 (60%) 4 Package-Isb-IV 3.95 1.64 (42%) 5 Package- Isb-V 2.47 0.99 (40%) 6 Package- Isb-VI Escalators, Elevators & Platform Screen Doors (PSD) 1.73 0.19 (11%) Total 23.83 23.66 9.37 (39%)
  • 78. V - Project Quality Management 1. Plan Quality Management 2. Perform Quality Assurance 3. Control Quality
  • 79. 1. Plan Quality Management V - Project Quality Management The process of identifying quality requirements and/or standards for the project and its deliverables and documenting how the project will demonstrate compliance with quality requirements.
  • 80. 2. Perform Quality Assurance V - Project Quality Management The process of auditing the quality requirements and the results from quality control measurements to ensure that appropriate quality standards and operational definitions are used.
  • 81. The process of monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes. V - Project Quality Management 3. Control Quality
  • 82. VI - Project Human Resource Management 1. Plan Human Resource Management 2. Acquire Project Team 3. Develop Team 4. Manage Team
  • 83. 1. Plan Human Resource Management VI - Project Human Resource Management As per Staff Management Plan for the Package II of the Rawalpindi Phase of Metro Bus Project it requires approximately 400 employees.  Project Manager  Procurement and Logistics Manager  Construction Manager  Construction Workers  Human Resource Manager  Finance and Accounts Manager  Budget Control Team Lead  Risk Manager  Chief Mechanical Engineer  Civil Engineers  Equipment Deployment Engineer  3rd Engineers  Lead Architect and Designers  Electrical Engineers  Security Guards
  • 84. 2. Manage and Acquire Project Team VI - Project Human Resource Management
  • 85. VII - Project Communication Management 1.Planning Communications 2.Managing Communications 3.Control Communications
  • 86. 1.Planning and Managing Communications The PMO of the Package – II of Rawalpindi Part manage the communication on regular basis through press conferences, media awareness and visit to communities. VII - Project Communication Management
  • 87. VII - Project Communication Management The process of monitoring and controlling communication throughout the entire project life cycle to ensure the information needs of the project stakeholders are met. Following is one of the example that the stakeholders at Senate Session level are kept informed regarding any issue: 2. Control Communications
  • 88. VII - Project Communication Management
  • 89. VII - Project Communication Management
  • 90. RAWALPINDI - ISLAMABAD METRO BUS PROJECT RAWALPINDI PACKAGE-II PROJECT PROGRESS 25-03-2015 FROM COMMITTEE CHOWK TO 6TH ROAD (RAWALPINDI PACKAGE-II, Length = 3.2 Km)
  • 91. Sr. No Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete i Super Structure Job 1 0.89 0.95 0.05 95% ii NJB LM 6400 6300 6300 100 98% iii Walkway LM 2524 80 2175 349 86% iv Ducts LM 2500 645 2175 349 86% v Light Poles Foundation No. 235 235 235 0 100% vi Light Poles Erection No. 235 165 205 30 87% vii Asphaltic Wearing Course LM 2524 136 2524 0 100% At Grade Works Viii a Dismantling/Scarification of Existing Road R/S LM 320 170 250 70 78% b L/S LM 850 50 300 550 35% ix Side Drain Base Slab LM 3600 880 2125 1475 59% x Side Drain Walls LM 3600 754 1094 2506 30% xi Side Drain Top Slab LM 6400 925 1880 4520 29% xii Walkway LM 2524 0 0 6400 0% xiii PCC Kerb Stones (B/S) LM 12800 0 0 12800 0% xiv Asphaltic Base Course LM 3200 675 1000 1524 40% xv Asphaltic Wearing Course LM 3200 0 0 3200 0% PROGRESS From Committee Chowk to Sixth Road (RAWALPINDI-PACKAGE-II)
  • 92. Sr. No. Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete Station Work 1 Tuff Pavers (80mm) SM 3100 425 2015 1085 65% 2 Platform Walls LM 432 232 423.36 8.64 98% 3 Platform Slab LM 216 0 205.2 10.8 95% 4 Floor Tiles SM 500 25 125 375 25% 5 Erection of Steel Structure % 100 45 80 20 80% 6 ACP Panel % 100 0 20 80 20% 7 Glass Walls % 100 0 0 100 0% 8 Ticketing Booth No 1 0 0 1 0% 9 Staff Toilet Job 1 0 0.5 0.5 50% 10 PSD Doors Structure No 18 0 18 0 100% 11 PSD Doors 0 18 0% PROGRESS Waris Khan Station
  • 93. Sr. No. Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete 11 Erection of Steel Structure(Ped. Bridge) % 100 60 80 20 80% 12 Concourse Column No 3 3 3 0 100% 13 Concourse Slab No 1 1 1 0 100% 14 Pedestrian Bridge Footings No 12 12 12 0 100% 15 Emergency Stair Footing No 4 0 0.8 3.2 20% 16 Escalators Pit No 3 2 3 0 100% 17 Elevators Pit No 3 2 3 0 100% 18 Escalators No 3 3 3 0 100% 19 Elevators No 3 3 0 3 0% 20 Public Toilets Job 1 0 0.2 0.8 20% PROGRESS Waris Khan Station
  • 94. Sr. No. Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete Station Work 1 Tuff Pavers (80mm) SM 3600 0 3420 180 95% 2 Platform Walls LM 500 440 500 0 100% 3 Platform Slab LM 250 80 250 0 100% 4 Floor Tiles SM 2200 0 2156 44 98% 5 Erection of Steel Structure % 100 22 100 0 100% 6 ACP Panel % 100 0 80 20 80% 7 Glass Walls % 100 0 20 80 20% 8 Ticketing Booth No 1 0 0 1 0% 9 Staff Toilet Job 1 0 0 1 0% 10 PSD Doors Structure No 18 0 14 4 78% 11 PSD Doors No 18 0 0 18 0% PROGRESS Chandni Chowk Station
  • 95. Sr. No. Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete 11 Erection of Steel Structure(Ped. Stair) % 100 25 85 15 85% 12 Pedestrian Stair Footings No 4 3 4 0 100% 13 Escalators Pit No. 1 1 1 0 100% 14 Elevator Pit No. 1 1 1 0 100% 15 Escalators No 1 1 1 0 100% 16 Elevators No 1 1 0 1 0% 17 Public Toilets Job 1 0.5 0.9 0.1 90% PROGRESS Chandni Chowk Station (Pedestrian Stair at Grade to Platform)
  • 96. Sr. No. Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete 1 Base Slab LM 250 250 250 0 100% 2 Walls LM 500 500 500 0 100% 3 Top slab LM 73 73 73 0 100% 4 Stairs No. 3 2 2 1 67% 5 Tiles SM 4000 160 2550 1450 64% 6 Elevator Pit No 3 1 3 0 100% 7 Escalator Pit No 3 1 3 0 100% 9 Elevator No 3 0 0 3 0% 9 Escalator No 3 0 1 2 33% PROGRESS Chandni Chowk Pedestrian Underpass
  • 97. Sr. No. Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete Station Work 1 Tuff Pavers (80mm) SM 3100 0 2480 620 80% 2 Platform Walls LM 430 205 430 0 100% 3 Platform Slab LM 215 45 215 0 100% 4 Floor Tiles SM 700 110 420 280 60% 5 Erection of Steel Structure % 100 65 90 10 90% 6 ACP Panel % 100 0 30 70 30% 7 Glass Walls % 100 0 0 100 0% 8 Ticketing Booth No 1 0 0 1 0% 9 Staff Toilet Job 1 0 0.5 0.5 50% 10 PSD Doors Structure No 18 0 9 9 50% 11 PSD Doors No 18 0 0 18 0% PROGRESS Rehmanabad Station
  • 98. Sr. No. Description of Activity Unit Total (Qty) Achievement (18-03-2015) Achievement (25-03-2015) Over all Balance (Qty) %age Complete 11 Erection of Steel Structure(Ped. Bridge) % 100 45 80 20 80% 12 Concourse Column No 3 3 3 0 100% 13 Concourse Slab No 1 1 1 0 100% 14 Pedestrian Bridge Footings No 16 15 16 0 100% 15 Emergency Stair Footing No 4 4 3 1 75% 16 Elevator Pit No 3 2 2 1 67% 17 Escalator Pit No 3 2 2 1 67% 18 Elevator No 3 0 0 3 0% 19 Escalator No 3 0 2 1 67% PROGRESS Rehmanabad Station
  • 99. VIII - Project Risk Management 1. Plan Risk Management 2. Identify Risks 3. Perform Quantitative Analysis 4. Perform Qualitative Analysis 5. Control Risk
  • 100. In a mega project like Metro Bus Service Islamabad-Rawalpindi there may exists number of different risk factors that need to be mitigated. Following are some of the examples of the risks and their plans by PMO. VIII - Project Risk Management S.NO RISK PLAN SOURCE 1 The Civil Aviation Authority (CAA) has expressed concerns that the elevated road to be constructed for the Rs38 billion Metro Bus service will be a risk for the flights on the runway of Benazir Bhutto International Airport. Neither the provincial government nor the local administration contacted CAA for a No-Objection Certificate (NoC) in this regard, but the authority will raise the issue on the appropriate forum soon Dawn News (March, 2014) 2 Environment Impact Assessment EIA Report prepared by NESPAK Tribune (March, 2014 3 Hundreds of laborer's working on the Metro Bus Project in the twin cities are not only vulnerable to the risks involved in construction, and health hazards but also exploitation owing to the apathy of the government. Metro Bus Project Office look after in such hazards and is taking care of security measures. News Today January 2nd, 201 1. Plan Risk Management
  • 101. 2. Perform Qualitative Analysis VIII - Project Risk Management
  • 102. VIII - Project Risk Management 3. Perform Quantitative Analysis The load pile tests are conducted to determine the underground formations to prove that the soil is capable of sustaining the designed load of the infrastructure that could be a bridge or even a high rise building. During first 30 days’ time of the contract award these tests are being conducted around Sixth Road and Chandni Chowk flyovers. The results of the load pile tests will be utilized by the consultant and the contractor of the project.
  • 103. VIII - Project Risk Management 4. Plan and Controlling the Risk Responses
  • 104. VIII - Project Risk Management
  • 105. VIII - Project Risk Management
  • 106. IX - Project Procurement Management 1. Plan Procurements 2. Conduct Procurements 3. Control Procurements 4. Close Procurements
  • 107. In this regard Punjab Province has adopted its own PPRA rules in 2009, after getting them approved from its assembly while recently it made certain amendments in the rules, aimed at speeding up development projects. The PC-1 of the mega project has been approved by the Provincial Development Working Party (PDWP) on February 4, and under the provisions of Punjab PPRA rules, Nespak has been appointed as the consultant for the project. To ensure the timely completion of the project, the Punjab government has authorised the RDA to execute the work, while the PMA will operate the bus service. The project director confirmed that in a bid to save time certain provisions have been initiated by the RDA. IX - Project Procurement Management 1. Plan Procurements
  • 108. 2. Conduct Procurements IX - Project Procurement Management
  • 109. Conduct Procurements IX - Project Procurement Management
  • 110. IX - Project Procurement Management
  • 111. IX - Project Procurement Management The process of managing procurement relationships, monitoring contract performance, and making changes and corrections as appropriate 3. Control and Close Procurements
  • 112. IX - Project Stakeholders Management
  • 113. IX - Project Stakeholders Management 1. Identify Stakeholders Following are different stakeholders  Fedral Government of Pakistan  Punjab Government  Pakistan Environmental Protection Agency (Pak-EPA)  Environment Impact Assessment (EIA)  Capital Development Authority (CDA)  Rawalpindi Development Authority (RDA)  Punjab Environment Protection Agency (PEPA)  Trade Community  General Public
  • 114. For the proper planning and management of Metro Bus project the participants of shops and property of the traders of Murree Road are the part of justifiably assessment for payment of reasonable compensation. 2. Planning, Managing and Controlling Stakeholder Management IX - Project Stakeholders Management