OPEN CIRCUIT & SHORT CIRCUIT 
TEST ON TRANSFORMER 
PREPAIRED BY: 
MANAVAR MILAN
INTRODUCTION 
• Necessity of testing 
• Open circuit test 
• Short circuit test 
• Advantages 
• Application
NECESSITY OF TESTING 
• In transformer and other equipment have 
input and output. Hence how to we find the 
performance of transformer and other 
equipment…..? 
• We have a solution even we will find the loss 
of transformer so we can easily find the all 
parameters of transformer like, we can find 
iron loss, cu loss, impedance, no load current, 
short circuit current and efficiency.
OPEN CIRCUIT TEST
HOW TO MEASURE O.C. TEST 
1. To connect Wattmeter in primary side. 
2. To connect Ammeter in series of phase. 
3. To connect Voltmeter in parallel of primary 
side. 
4. We will open the Secondary side. 
5. We will give the supply primary side for the 
measurement of iron losses.
• The purpose of this test is to find the no-load loss 
or core loss. 
• A wattmeter, voltmeter and an ammeter are 
connected in low voltage side. 
• Secondary side of transformer we will keep open. 
• We give the normal voltage applied to the 
primary, normal flux will be set up in the core, 
hence normal iron losses will occur which are 
recorded by the wattmeter.
• As the primary no-load current is measured 
by ammeter and its value is small, Cu-loss is 
negligibly small in primary and nil in 
secondary (it being open). 
• Hence, the wattmeter reading represents 
practically the CORE LOSS under no-load 
condition.
• Sometimes a high resistance voltmeter is 
connected across the secondary. The reading 
of the voltmeter gives the induced e.m.f. in 
the secondary winding.
SHORT CIRCUIT TEST
HOW TO MEASURE S.C. TEST 
1. To connect the wattmeter primary side 
2. To connect the Ammeter in series of primary 
side 
3. To connect the Voltmeter in parallel of 
primary side 
4. Short the secondary side using thick 
conductor 
5. Now give the small voltage supply for the 
measurement of Cu-losses.
• A wattmeter, voltmeter and an ammeter are 
connected in high voltage side. 
• The low voltage side of transformer is short 
circuited. 
• The applied voltage is a small percentage of the 
normal voltage. 
• Hence the core losses are very small with the 
result of the wattmeter reading represent the 
full-load CU-LOSS or loss for the whole 
transformer .
ADVANTAGES 
• No require for extra load 
• This test are very economical and convenient, 
because they furnish the required information 
without actually loading the transformer.
APPLICATION 
• By using open circuit test we can measure the 
loss of no-load losses means that iron losses. 
• By using short circuit test we can measure the 
loss of full-load losses means that Cu-losses. 
• We can find the efficiency by using of iron 
losses and cu-losses.
THANK YOU

More Related Content

What's hot

Instrument transformer CT & PT
Instrument transformer CT & PTInstrument transformer CT & PT
Instrument transformer CT & PTChandan Singh
 
Measurement of hvac (High Voltage Engineering )
Measurement  of  hvac (High Voltage Engineering )Measurement  of  hvac (High Voltage Engineering )
Measurement of hvac (High Voltage Engineering )Abhishek Choksi
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEJamil Abdullah
 
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...Abhishek Choksi
 
Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...
Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...
Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...Prasant Kumar
 
Transformer testing
Transformer testingTransformer testing
Transformer testingajayknows
 
Electromagnetic relay
Electromagnetic relayElectromagnetic relay
Electromagnetic relayjawaharramaya
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functionsSourabh sharma
 
Over voltages in power system
Over voltages in power systemOver voltages in power system
Over voltages in power systemSANGEETHA S
 
Testing of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTesting of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTafhim Bin Nasir
 
BREAKDOWN IN LIQUIDS_NDS
BREAKDOWN IN LIQUIDS_NDSBREAKDOWN IN LIQUIDS_NDS
BREAKDOWN IN LIQUIDS_NDSNiraj Solanki
 
Power Electronics - Power Semi – Conductor Devices
Power Electronics - Power Semi – Conductor DevicesPower Electronics - Power Semi – Conductor Devices
Power Electronics - Power Semi – Conductor DevicesBurdwan University
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformerROOPAL PANCHOLI
 
Relay coordination
Relay coordinationRelay coordination
Relay coordinationD Målîk
 

What's hot (20)

Instrument transformer CT & PT
Instrument transformer CT & PTInstrument transformer CT & PT
Instrument transformer CT & PT
 
Measurement of hvac (High Voltage Engineering )
Measurement  of  hvac (High Voltage Engineering )Measurement  of  hvac (High Voltage Engineering )
Measurement of hvac (High Voltage Engineering )
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
 
Transformers
TransformersTransformers
Transformers
 
Tap changer
Tap changerTap changer
Tap changer
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...
Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...
Voltage Regulation of Transformer ,Efficiency of transformer|Day 8| Basic ele...
 
Chapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering IntroductionChapter 01- High Voltage Engineering Introduction
Chapter 01- High Voltage Engineering Introduction
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 
Electromagnetic relay
Electromagnetic relayElectromagnetic relay
Electromagnetic relay
 
Transformer Parts and functions
Transformer Parts and functionsTransformer Parts and functions
Transformer Parts and functions
 
Over voltages in power system
Over voltages in power systemOver voltages in power system
Over voltages in power system
 
Testing of Circuit Breakers.pptx
Testing of Circuit Breakers.pptxTesting of Circuit Breakers.pptx
Testing of Circuit Breakers.pptx
 
BREAKDOWN IN LIQUIDS_NDS
BREAKDOWN IN LIQUIDS_NDSBREAKDOWN IN LIQUIDS_NDS
BREAKDOWN IN LIQUIDS_NDS
 
Power Electronics - Power Semi – Conductor Devices
Power Electronics - Power Semi – Conductor DevicesPower Electronics - Power Semi – Conductor Devices
Power Electronics - Power Semi – Conductor Devices
 
Inverter
InverterInverter
Inverter
 
Ppt of current transformer
Ppt of current transformerPpt of current transformer
Ppt of current transformer
 
Transformer basic
Transformer basicTransformer basic
Transformer basic
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
 

Viewers also liked

EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6ruhiyah
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformervikasgupta1965
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)ruhiyah
 
EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4 ruhiyah
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORSAJAL A J
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)firozamin
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behinBehin anben
 

Viewers also liked (8)

Lecture 8 bjt_1
Lecture 8 bjt_1Lecture 8 bjt_1
Lecture 8 bjt_1
 
EE201 -Chapter 6
EE201 -Chapter 6EE201 -Chapter 6
EE201 -Chapter 6
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)EE201 - Chapter 3 (BJT)
EE201 - Chapter 3 (BJT)
 
EE201 -Chapter 4
EE201 -Chapter 4 EE201 -Chapter 4
EE201 -Chapter 4
 
TRANSISTORS
 TRANSISTORS TRANSISTORS
TRANSISTORS
 
3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)3.bipolar junction transistor (bjt)
3.bipolar junction transistor (bjt)
 
Transistors ppt by behin
Transistors ppt by behinTransistors ppt by behin
Transistors ppt by behin
 

Similar to open circuit and short circuit test on transformer

OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...Prasant Kumar
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of TransformersGirin Chutia
 
4. Test instruments and their connections
4. Test instruments and their connections4. Test instruments and their connections
4. Test instruments and their connectionssanewton
 
Sumpner Test on Transformers
Sumpner Test on TransformersSumpner Test on Transformers
Sumpner Test on TransformersSoham Gajjar
 
Special transformers
Special transformersSpecial transformers
Special transformersPreet_patel
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier pptvikas kumar
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.Geetesh Verma
 
Outcome 2.3 identify appropriate electrical instruments for the measurement...
Outcome 2.3   identify appropriate electrical instruments for the measurement...Outcome 2.3   identify appropriate electrical instruments for the measurement...
Outcome 2.3 identify appropriate electrical instruments for the measurement...sanewton
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjarMukesh gurjar
 
Microsoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfMicrosoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfsrevathiap
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE Lalit Kumar
 
IET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptxIET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptxDavy40
 

Similar to open circuit and short circuit test on transformer (20)

Akshay kumar
Akshay kumarAkshay kumar
Akshay kumar
 
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
OPEN CIRCUIT AND SHORT CIRCUIT TEST OF SINGLE PHASE TRANSFORMER|DAY7| BASIC E...
 
Sumpners Test of Transformers
Sumpners Test of TransformersSumpners Test of Transformers
Sumpners Test of Transformers
 
Notes
NotesNotes
Notes
 
4. Test instruments and their connections
4. Test instruments and their connections4. Test instruments and their connections
4. Test instruments and their connections
 
Usage of meters
 Usage of meters  Usage of meters
Usage of meters
 
Sumpner Test on Transformers
Sumpner Test on TransformersSumpner Test on Transformers
Sumpner Test on Transformers
 
Special transformers
Special transformersSpecial transformers
Special transformers
 
multimeter.pptx
multimeter.pptxmultimeter.pptx
multimeter.pptx
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Transformers
TransformersTransformers
Transformers
 
Outcome 2.3 identify appropriate electrical instruments for the measurement...
Outcome 2.3   identify appropriate electrical instruments for the measurement...Outcome 2.3   identify appropriate electrical instruments for the measurement...
Outcome 2.3 identify appropriate electrical instruments for the measurement...
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Microsoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdfMicrosoft PowerPoint - Unit II.pdf
Microsoft PowerPoint - Unit II.pdf
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
IET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptxIET II EIGHT LESSON EDT (1).pptx
IET II EIGHT LESSON EDT (1).pptx
 
Usage of meters - Notes
Usage of meters - NotesUsage of meters - Notes
Usage of meters - Notes
 
Ratio Burden Admittance Testing
Ratio Burden Admittance TestingRatio Burden Admittance Testing
Ratio Burden Admittance Testing
 

Recently uploaded

THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 

Recently uploaded (20)

THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 

open circuit and short circuit test on transformer

  • 1. OPEN CIRCUIT & SHORT CIRCUIT TEST ON TRANSFORMER PREPAIRED BY: MANAVAR MILAN
  • 2. INTRODUCTION • Necessity of testing • Open circuit test • Short circuit test • Advantages • Application
  • 3. NECESSITY OF TESTING • In transformer and other equipment have input and output. Hence how to we find the performance of transformer and other equipment…..? • We have a solution even we will find the loss of transformer so we can easily find the all parameters of transformer like, we can find iron loss, cu loss, impedance, no load current, short circuit current and efficiency.
  • 5. HOW TO MEASURE O.C. TEST 1. To connect Wattmeter in primary side. 2. To connect Ammeter in series of phase. 3. To connect Voltmeter in parallel of primary side. 4. We will open the Secondary side. 5. We will give the supply primary side for the measurement of iron losses.
  • 6. • The purpose of this test is to find the no-load loss or core loss. • A wattmeter, voltmeter and an ammeter are connected in low voltage side. • Secondary side of transformer we will keep open. • We give the normal voltage applied to the primary, normal flux will be set up in the core, hence normal iron losses will occur which are recorded by the wattmeter.
  • 7. • As the primary no-load current is measured by ammeter and its value is small, Cu-loss is negligibly small in primary and nil in secondary (it being open). • Hence, the wattmeter reading represents practically the CORE LOSS under no-load condition.
  • 8. • Sometimes a high resistance voltmeter is connected across the secondary. The reading of the voltmeter gives the induced e.m.f. in the secondary winding.
  • 10. HOW TO MEASURE S.C. TEST 1. To connect the wattmeter primary side 2. To connect the Ammeter in series of primary side 3. To connect the Voltmeter in parallel of primary side 4. Short the secondary side using thick conductor 5. Now give the small voltage supply for the measurement of Cu-losses.
  • 11. • A wattmeter, voltmeter and an ammeter are connected in high voltage side. • The low voltage side of transformer is short circuited. • The applied voltage is a small percentage of the normal voltage. • Hence the core losses are very small with the result of the wattmeter reading represent the full-load CU-LOSS or loss for the whole transformer .
  • 12. ADVANTAGES • No require for extra load • This test are very economical and convenient, because they furnish the required information without actually loading the transformer.
  • 13. APPLICATION • By using open circuit test we can measure the loss of no-load losses means that iron losses. • By using short circuit test we can measure the loss of full-load losses means that Cu-losses. • We can find the efficiency by using of iron losses and cu-losses.