SlideShare a Scribd company logo
1 of 8
METHOD STATEMENT 
Table of contents 
of 
LEAN CONCRETE 
for 
BUILDING WORKS
1. General. 
2. Sequence of works. 
3. Backfill or excavate to the design level 
4. Formwork design. 
5. Placing of concrete. 
6. Compaction of concrete. 
7. Curing 
8. Dewatering 
9. Electricity 
10.Equipment & Manpower 
Appendix 
A. Plan of three main building 
B. Formwork design & Typical of filling materials 
1. General 
This method statement describe how we construct lean concrete for Building Works
Pleased refer to Appendix A for the plan of three main buildings. 
This method statement covers for the lean concrete of all Building Works. The filling 
material under lean concrete may be varied in difference location. 
Concrete class shall be approved ready-mix concrete B7.5 (Grade 15NM/m2) 
Excavation or Backfilling 
to Design Level 
2. Sequence of works. 
Leveling & Compaction 
Setting Formworks 
Placing lean concrete 
Curing for Concrete 
3. Backfill or Excavate to the design level 
Excavation works will be carried out by manpower or by backhoe depend on soil 
condition. 
Backfilling works will carry out layer by layer. Thickness of each layer is not more than 
300mm.
a) Filling under piles cap of the building have piling foundation 
Material using for backfilling works will be existing soil on site area or other approved 
material if the existing soil is not enough. 
b) Filling under directed foundation 
The ground will be excavated up to soil treatment level, and then backfill up to design 
level following approved design & material. Design of sub layer and proposed material 
shall be submit separately. 
Please refer to Appendix B for typical of filling material. 
4. Formworks Design 
After finish leveling and compaction works, formwork will be set out. 
Please refer to Appendix B for formworks design. 
Timber or steel will be used for formwork. 
5. Placing of Concrete 
Approved ready-mix concrete will transported from batching plant to the site by mixer 
truck. 
From mixer truck concrete will be delivered to casting location by bucket & wheel barrow 
then pour out by showel or directly to the position. 
6. Compaction of Concrete. 
Concrete after pouring to position shall compacted by immersion vibrator. 
7. Curing. 
Curing of concrete will be carried out by spraying water periodically to the surface of the 
newly placed concrete. 
8. Dewatering 
Two nos of water pump (one for spare) shall be arranged on site with enough hose 
9. Electricity 
Electricity will supplied by stand by generator on site.
10. Equipment & Manpower 
a)Equipment 
Equipment Unit Quantity 
Mixer truck Nos 02 
Tamping Ramer No 01 
Vibrator Nos 02 
Wheel barrow Nos 05 
Water Pump 2 HP No 01 
Water Pump 1HP No 01 
Generator 15KVA No 01 
Generator 10KVA Nos 02 
Bucket Nos 10 
Showel Nos 05 
Trowel Nos 05 
b)Equipment 
Description Unit Quantity 
Supervisor No 01 
Surveyor Nos 02 
Foreman No 01 
Electrician No 01 
Worker Nos 08
APPENDIX A
FOUNDATION PLAN OF THREE MAIN BUILDING
APPENDIX B 
FORMWORK DESIGN & TYPICAL OF FILLING 
MATERIAL

More Related Content

What's hot

The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 
Compacting Factor Test
Compacting Factor TestCompacting Factor Test
Compacting Factor TestXinYee Khoo
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORTWan Nee
 
03 e measurement book-ver-1.0
03 e measurement book-ver-1.003 e measurement book-ver-1.0
03 e measurement book-ver-1.0Amulie Jarjusey
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surfaceMinh Bui Si
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010Minh Bui Si
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructureguasiya
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1ArunRavi43
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and ProcessIbrahim Adhnan
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 

What's hot (20)

The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
Compacting Factor Test
Compacting Factor TestCompacting Factor Test
Compacting Factor Test
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
03 e measurement book-ver-1.0
03 e measurement book-ver-1.003 e measurement book-ver-1.0
03 e measurement book-ver-1.0
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
Estimating part 1
Estimating part 1Estimating part 1
Estimating part 1
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and Process
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 

Viewers also liked

Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & windowMinh Bui Si
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003Minh Bui Si
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Minh Bui Si
 

Viewers also liked (6)

Column & beam
Column & beamColumn & beam
Column & beam
 
Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & window
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0
 

Similar to Method stm lean concrete

Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 
Site visit report
Site visit reportSite visit report
Site visit reportWen Crystal
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Krm Chari
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insituLingWei11
 
BFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.pptBFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.pptArdeeArdee
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_aryaAbdul Khader Shahadaf TH
 
Water proofing treatement
Water proofing treatementWater proofing treatement
Water proofing treatementRajiva Gupta
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge codeAjay Kumar
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_aryaimaduddin91
 
Overhead transmission lines_ Foundation.pptx
Overhead transmission lines_ Foundation.pptxOverhead transmission lines_ Foundation.pptx
Overhead transmission lines_ Foundation.pptxEdlirPeci1
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 
Upload a presentation to download Space frame
Upload a presentation to download Space frameUpload a presentation to download Space frame
Upload a presentation to download Space frameBurkaDinka
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWJaspreet singh
 

Similar to Method stm lean concrete (20)

Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
 
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
BFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.pptBFC 31802 Chapter 4a - Copy.ppt
BFC 31802 Chapter 4a - Copy.ppt
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
 
Water proofing treatement
Water proofing treatementWater proofing treatement
Water proofing treatement
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge code
 
accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
Metroppt
MetropptMetroppt
Metroppt
 
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
12 fundamentals for_seismic_design_of_rcc_buildings_by_prof_arya
 
Overhead transmission lines_ Foundation.pptx
Overhead transmission lines_ Foundation.pptxOverhead transmission lines_ Foundation.pptx
Overhead transmission lines_ Foundation.pptx
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
Upload a presentation to download Space frame
Upload a presentation to download Space frameUpload a presentation to download Space frame
Upload a presentation to download Space frame
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Phase2 final.pptx
Phase2  final.pptxPhase2  final.pptx
Phase2 final.pptx
 

Method stm lean concrete

  • 1. METHOD STATEMENT Table of contents of LEAN CONCRETE for BUILDING WORKS
  • 2. 1. General. 2. Sequence of works. 3. Backfill or excavate to the design level 4. Formwork design. 5. Placing of concrete. 6. Compaction of concrete. 7. Curing 8. Dewatering 9. Electricity 10.Equipment & Manpower Appendix A. Plan of three main building B. Formwork design & Typical of filling materials 1. General This method statement describe how we construct lean concrete for Building Works
  • 3. Pleased refer to Appendix A for the plan of three main buildings. This method statement covers for the lean concrete of all Building Works. The filling material under lean concrete may be varied in difference location. Concrete class shall be approved ready-mix concrete B7.5 (Grade 15NM/m2) Excavation or Backfilling to Design Level 2. Sequence of works. Leveling & Compaction Setting Formworks Placing lean concrete Curing for Concrete 3. Backfill or Excavate to the design level Excavation works will be carried out by manpower or by backhoe depend on soil condition. Backfilling works will carry out layer by layer. Thickness of each layer is not more than 300mm.
  • 4. a) Filling under piles cap of the building have piling foundation Material using for backfilling works will be existing soil on site area or other approved material if the existing soil is not enough. b) Filling under directed foundation The ground will be excavated up to soil treatment level, and then backfill up to design level following approved design & material. Design of sub layer and proposed material shall be submit separately. Please refer to Appendix B for typical of filling material. 4. Formworks Design After finish leveling and compaction works, formwork will be set out. Please refer to Appendix B for formworks design. Timber or steel will be used for formwork. 5. Placing of Concrete Approved ready-mix concrete will transported from batching plant to the site by mixer truck. From mixer truck concrete will be delivered to casting location by bucket & wheel barrow then pour out by showel or directly to the position. 6. Compaction of Concrete. Concrete after pouring to position shall compacted by immersion vibrator. 7. Curing. Curing of concrete will be carried out by spraying water periodically to the surface of the newly placed concrete. 8. Dewatering Two nos of water pump (one for spare) shall be arranged on site with enough hose 9. Electricity Electricity will supplied by stand by generator on site.
  • 5. 10. Equipment & Manpower a)Equipment Equipment Unit Quantity Mixer truck Nos 02 Tamping Ramer No 01 Vibrator Nos 02 Wheel barrow Nos 05 Water Pump 2 HP No 01 Water Pump 1HP No 01 Generator 15KVA No 01 Generator 10KVA Nos 02 Bucket Nos 10 Showel Nos 05 Trowel Nos 05 b)Equipment Description Unit Quantity Supervisor No 01 Surveyor Nos 02 Foreman No 01 Electrician No 01 Worker Nos 08
  • 7. FOUNDATION PLAN OF THREE MAIN BUILDING
  • 8. APPENDIX B FORMWORK DESIGN & TYPICAL OF FILLING MATERIAL