SlideShare a Scribd company logo
1 of 21
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
CAI MEP INTERNATIONAL CONTAINER TERMINAL 
METHOD STATEMENT OF PILING WORKS FOR BUILDINGS 
Page 1
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
TABLE OF CONTENTS 
1. General…………………………………………………………… 2 
2. Scope of Works…………………………………………………... 2 
3. Reference Technical Specification ………………………………. 2 
4. Reference Drawings……………………………………………..... 2 
5. Specification of Piling Machine…………………………………... 2 
6. Piling Schedule……………………………………………………. 2 
7. Equipment and manpower list…………………………………… 2 
7.1. Equipment………………………………………………………… 3 
7.2. Labors…………………………………………………………….. 5 
8. General Flow Chart Of Piling Work……………………………… 6 
9. Piling Procedure…………………………………………………... 7 
10. Piling by Diesel Hammer…………………………………………. 8 
10.1 Driving Lower Segment PHC Pile………………………………... 8 
10.2 Splicing Work……………………………………………………... 9 
10.3 Driving Upper Segment PHC Pile……………………………….... 9 
11. Pile Driving Record………………………………………………. 10 
12. Pile Dynamic Analyzer…………………………………………... 11 
13. Quality Control………………………………………………….... 11 
13.1. Inspection of Fabrication ……………………………………….... 11 
13.2. Inspection of Welding Work……………………………………... 11 
14. Safety Control…………………………………………………...... 12 
15. Appendixes……………………………………………………….. 13 
Page 2
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
1. General : 
This Method Statement for PHC and the solid pile, piling work procedure of 
buildings for CAI MEP INTERNATIONAL CONTAINER TERMINAL 
PROJECT is to demonstrate the process of driving these piles in compliance with 
all the required specifications, standards, and proper construction procedures 
governing the pile driving works for the building foundation of the project. 
2. Scope Of Works : 
Execution and supply of PHC and square solid piles, setting piles location before 
driving, driving and all necessary engineering works could be categorized as 
follows: 
Type of piles are PHC pile type A, (Ø 600 mm, Ø500mm), and 400mmx400mm 
solid square piles. 
3. Reference Technical Specifications : 
Technical Specification: Part 4B, Division 2 – Piling Works for Buildings. 
4. Reference Drawing List : 
Attached in Appendix B 
5. Specification and Certificate of Piling Machine 
Specification of piling machine and crane operation certificate: 
Attached in Appendix C 
6. Piling Schedule : 
Attached in Appendix E 
Page 3
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
7. Equipment & Manpower List: 
7.1. Equipment to Be Used: 
The Equipment to be used for pile driving works is summarized in Table 7.1 
Table 7.1 List of Equipment 
No Equipment Specification Quantity Capacity 
1 Diesel Pile Hammer KOBELCO K35/K25 1 5T 
KOBELCO 
2 Diesel Pile Hammer 
K35/DELMAG D 25 
1 5T 
3 Diesel Pile Hammer HERA3500/D25C 1 5T 
4 Diesel Pile Hammer 
KOBELKO K45/KB60 
MITSUBISHI MB 70 
1 4.5T,6T,7T 
5 Crane Truck Model: LS78 1 35T 
6 Crane Truck Model: DH 350 1 35T 
7 Theodolite Japan Made 04 100% precise 
8 Survey Equipment US Made 1 100% precise 
9 Automatic Level Japan Made 2 100% precise 
TOTAL→ 13 
7.2. Labors To Be Deployed: 
Labors and/or trades to be deployed for PHC piling work is summarized in 
Table 7.2 
Page 4
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Table 7.2- List of labors 
Description Quantity Remark 
Engineer 3 
Foreman 3 
Piling operator 3 
Workers 12 
Welders 6 
Surveyor 4 
Crane operator 2 
TOTAL→ 33 
8. General Flow Chart Of Piling Work: 
General Flow Chart: 
Page 5
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Mobilization of Piling Machine 
Lifting the upper segment PHC pile 
and Splicing 
Driving the upper PHC pile 
(Middle/Top) 
9. Piling Procedure 
 PHC Piles D600mm, D500mm and Solid 400mmx400mm will be plant 
fabricated and transported to the site by a Trailer truck and by barge. They will be 
Page 6 
Delivery of PHC Pile by Barge & 
Trailer Truck for Building 
Lifting the lower segment PHC pile by 
Crane then mount Diesel Hammer 
Driving the lower segment PHC pile 
Confirm the bearing capacity by 
evaluating penetration during driving 
Finish
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
supported by bedding timbers placed directly under the positions of lifting hooks 
(Shown in Figure 1). 
 Piles will be stored carefully on flat ground within the temporary yard and a 
maximum of three (3) layers per stock pile is required. 
 Pile markings should be carried out to every pile segments to check the rough 
penetration per hammer blow. Bottom segment piles will be marked at every 1.0m 
pitch, middle segments, and top segments will be marked every 20cm pitch. 
 Material delivery dockets, receipts and physical inspection report shall be 
submitted to the Engineer. 
TRUCK CRANE 
TRAILER 
PHC PILE 
0. 2L 0. 6L 0. 2L 
Figure 1: Transportation of PHC Pile 
Sand Bag Sand Bag 
TIMBER PHC PILE 
0. 2L E 
R 
0. 2L 0. 2L 
Figure 2: Storage of PHC Pile 
10.Piling By Diesel Hammer : 
Page 7
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
The piles will be driven by diesel hammer. The driving will be stopped after 
confirming the bearing capacity. (Shown in Figure 2) 
PILE UNDER DRIVING 
CENTER LINE OF PILE 
PILE DRIVER 
TRANSIT/PLUMB BOB 
SURVEYER 
SURVEYER 
DIESEL 
HAMMER 
VI NG DR I 
I ON RE C T DI 
TRANSIT/PLUMB BOB 
Figure 2: Pile Driving 
10.1. Driving Lower Segment PHC Pile: 
 Crane will lift up the lower segment PHC Pile near the piling machine. The PHC 
pile will be held along leader of diesel hammer. Lifting position shall be 0.2L of pile 
length. ( lower than cracking moment) 
 The pile position will be adjusted by moving the leader until its top coincides with 
the hammer then mount the cap on the pile top. Before start driving, vertical position 
of the pile will be checked carefully by total station or theodolite to confirm its 
verticality. 
10.2. Splicing Work: 
Page 8
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
 Prior to splicing, welding surfaces will be cleaned and free from rust, oil, water 
and other foreign elements that would affect welded joints. 
 After driving lower segment, the upper segment will be lifted by piling machine, 
set above the lower segment coincide their centers directly and aligned vertically 
then fixed the clamp to maintain its alignment. Inclination tolerance shall be 
checked by split level, and it should be less than 1.0cm/1.0m) 
 . Splices will be made by butt welding, using arc welding performed 2G position 
and in accordance to WPS (Welding Position Standard) for welding. 
 Visual and NDT inspection check will be conducted to every welding joint done. 
Figure 3 
UPPER PILE 
10.3Driving Upper Segment PHC Pile: 
Top segment shall be driven after obtaining the PDA test results for correction 
factor from Hailey’s formula 
 Driving will be complete after confirming the sufficient bearing capacity, from 
Hailey’ s formula shown below with reference to PDA Test results. 
Page 9 
PILE DRIVER 
DIESEL HAMMER 
HELMET 
LOWER PILE 
1) DRIVING OF LOWER PILE 2) CLEANING OF PILE HEAD 3) SPLICING 4) RESUMING OF DRIVING
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
 If it is found that the bearing capacity is still insufficient obtained from 
rebound record against design, the pile should be extended and re-driven until the 
bearing capacity is reached. 
Ru = 9.81 (Ef.MR.H) x MR + e 2 .MP 
S+0.5(C1+C2+C3) MR + MP 
= A 
In which: 
Ru : Ultimate Resistance, KN 
MR: Weight of ram, Kg 
H : Drop height of hammer, mm 
Ef : Efficiency of fall of hammer 
MP: Weight of pile + helmet, Kg 
e : Coefficient of restitution [ e = (S+{C₁+C₂+C₃}÷2 x PDA)/(Ef x MR x H) ] 
C1: Elastic deformation of pile, mm 
C2: Elastic deformation of ground, mm 
C3: Elastic deformation of pile head cushion, mm (here C3 = 2 mm). 
S : average penetration, in mm per blow for at least the last 10 blows 
RP: Correction Factor (RP = S.L.T. / A) 
(Use rebound record- Attached Appendix F) 
 The result of Pile driving and bearing capacity shall be confirmed by the 
Engineer and the records of pile installation shall be submitted to the Engineer. 
 In case the pile tip can not reach the design level due to unforeseen hard layer, 
this matter will be reported to the Engineer. 
 If piles cannot be driven to the design level but has already attained the required 
bearing capacity, the driving shall be stopped in accordance to specification and 
Engineer’s instruction to avoid buckling or cracking of the pile. 
 Pile head treatment shall be done after getting Engineer’s approval. 
11. Pile Record: 
 Before final setting of the piles, the rebound shall be recorded. 
Page 10 
x RP
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
 The pile driving is deemed completed after confirmation of the sufficient bearing 
capacity against design. Bearing capacity for all piles will be calculated with 
formula. 
12. Pile Dynamic Analyzer (PDA) 
 Pile Dynamic Analysis will be conducted to confirm the pile capacities and to 
decide the correction factor of Hiley’s formula. PDA test provides more 
information, about Skin resistance distribution, Toe resistance, simulated static 
load-settlement relationship, pile integrity, stresses in the pile during the blow. 
PDA test shall be conducted by Engineer 
13. Quality Control 
13.1. Inspection of Fabrication 
 Before fabrication PHC and square Pile materials such as, cement, sand, gravel, 
reinforcing bars, tendon wires and etc, will be inspected on Factory before 
fabrication, and finished product will again be inspected before delivery to the site. 
 The inspection report shall be submitted before piles will be delivered on site. 
When PHC and square piles arrives on site/stockyard, these will be inspected 
again for its, physical conditions, quantity and quality in accordance with 
specification or standards listed below: 
- Length tolerance: ±3% 
- Outside diameter tolerance: +7mm/-4mm 
- Wall thickness tolerance: +unspecified/-0mm 
- Cracking: no crack 
 The quality control and inspection report will be submitted to the Engineer. 
13.2. Inspection of Welding Work. 
 Prior to the welding, the grooved face and its adjacent areas shall be completely 
free from oil, paint, oxide, water and all other foreign materials. 
 Welding rod will be stored in a dry and humid place to keep its required 
temperature. Only welding rod approved by the Engineer will be used on the 
splicing of pile. 
Page 11
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
 Piles are jointed with their end plates evenly around its diameter, welding must 
be carried out in accordance with manufacture’s instruction and must be checked 
before driving resumes. Piles welding splice will be tested by NDT test. Basically 
all weld joints shall be tested by NDT but reducing option will be proposed 
depending on the quality of test obtained on the previous welded joints. (Refer to 
attached form in Appendix F) 
(1) Crack Inspection of Welding 
There shall be no cracks in or near the weld beads. The inspection shall be carried 
out by visual and Non Destructive test (NDT). 
(2) Inspection of Bead Surface and Shape 
Visual inspection of bead surface and shape shall be done by the process listed 
below. 
a. Pits on bead surface 
Butt joints shall be free of weld pits on the bead surface. 
b. Flatness of bead 
There shall be no height difference exceeding 3mm within 25mm length of a bead. 
c. Undercut 
The depth of undercut shall not exceed 0.3mm. 
d. Overlap 
There shall be no overlap. 
 During driving, the pile head will be protected by helmet of cast steel or mild 
steel fitted closely around the pile. Packing (cushion) timber, covering the head of 
pile, will be placed on the pile and will be replaced as often as necessary to prevent 
damage to the piles. 
14. Safety Control: 
 Prior to commencement of any activities, the contractor will ensure all safety 
work practices and requirements for the different operations and are made 
informed and strictly complied at all times. 
Page 12
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
The following steps are strictly checked before and during working. 
1. Equipment and machine efficiency checking prior to operation. 
2. Grand condition 
3. Tool box meeting 
15. Appendices: 
Appendix A: Organizational Chart 
Appendix B: Ref. Drawings List 
Appendix C: Specification and Certificate of Piling Machine 
Appendix D: Fabrication Schedule 
Appendix E: Pile Driving Schedule 
Appendix F: Pile Driving & Welding splicing Form 
Appendix G: Checklist for PHC Pile Manufacturing 
Appendix H: Inspection and Test PLan 
Page 13
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix A: Organizational Chart 
TOA-TOYO JV 
Site Manager 
Engineer & Safety 
Pile Transportation 
Team 
Item No Title Numbers Remarks 
1 Site Manager 2 
2 Engineer/Safety 3 
3 Foreman 3 
4 Operator 3 
5 Welder 6 
6 Worker 12 
7 Surveyor 4 
Total→ 33 
Page 14 
Piling Rig-2 
Team-2 
Piling Rig-1 
Team-1
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix B: 
Ref. Drawing List: 
Page 15
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix C: 
Specification and Certificate of Piling Machine 
Page 16
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix D: 
Pile Fabrication Schedule 
Page 17
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix E: 
Pile Driving Schedule 
Page 18
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix F: 
Pile Driving & Welding splicing Form 
Page 19
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix G: 
Checklist for PHC Pile Manufacturing 
Page 20
Doc. Title Method Statement of Piling Works 
for Buildings TOA-TOYO JOINT VENTURE 
Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 
Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 
Appendix H: 
Inspection and Test Plan 
Page 21

More Related Content

What's hot

TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil worksMuhammad Shahid
 
Post tensioning company method statement | shivforce.in
Post tensioning company   method statement | shivforce.in Post tensioning company   method statement | shivforce.in
Post tensioning company method statement | shivforce.in Sathish Kumar
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Design calculations of raft foundation
Design calculations of raft foundationDesign calculations of raft foundation
Design calculations of raft foundationShahzad Ali
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantityhlksd
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipmentTareq Shreehah
 
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILL
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILLPile driving problems and solutions by Dr. Malek Smadi of GEOTILL
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILLDr. Malek Smadi
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concreteMinh Bui Si
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored PilesAhmed Zanaty
 
Design And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining WallsDesign And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining WallsKumar Aman
 

What's hot (20)

TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
 
Project report
Project reportProject report
Project report
 
Post tensioning company method statement | shivforce.in
Post tensioning company   method statement | shivforce.in Post tensioning company   method statement | shivforce.in
Post tensioning company method statement | shivforce.in
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Design calculations of raft foundation
Design calculations of raft foundationDesign calculations of raft foundation
Design calculations of raft foundation
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILL
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILLPile driving problems and solutions by Dr. Malek Smadi of GEOTILL
Pile driving problems and solutions by Dr. Malek Smadi of GEOTILL
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concrete
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
 
Design And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining WallsDesign And Construction Of Cantilevered Retaining Walls
Design And Construction Of Cantilevered Retaining Walls
 
Site possession
Site possessionSite possession
Site possession
 

Similar to Piling work method statement cm- ms- bw - 002

Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Krm Chari
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...fijsekkdmdm2w
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...yqen95561858
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...ze3xiandiao
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...ufs89eodkdmdm
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...jdkskmmdmd1
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...jdkksmemmd
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...fskekkdmdmdm3e
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...fjisejkdmd8id
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...ifkkdkmdmd
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...f8sejdkdmdijd
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...f7usuejkdkddm3
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...jjfksekdmejik
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...zatao0179249295
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...yinranhe0814
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...wfu089267
 
Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...
Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...
Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...didkkskdmmd
 
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...f89siekkmdmm2w
 
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...fujkse9didkke3
 
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...km7seyrduhdw
 

Similar to Piling work method statement cm- ms- bw - 002 (20)

Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
Buildingworkmethodstatement cm-ms-bw-001-141120013134-conversion-gate01(1)
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual Instant D...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
Caterpillar cat 345 d l excavator (prefix kfh) service repair manual (kfh0000...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
Caterpillar Cat 345D L Excavator (Prefix KFH) Service Repair Manual (KFH00001...
 
Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...
Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...
Caterpillar cat 349 d l excavator (prefix fla) service repair manual (fla0000...
 
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual Instant D...
 
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
 
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
Caterpillar Cat 349D L Excavator (Prefix FLA) Service Repair Manual (FLA00001...
 

More from Minh Bui Si

Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003Minh Bui Si
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Minh Bui Si
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surfaceMinh Bui Si
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & windowMinh Bui Si
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
03 jun 08 pile head
03 jun 08 pile head03 jun 08 pile head
03 jun 08 pile headMinh Bui Si
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 

More from Minh Bui Si (9)

Static load test method statement cm - ms- bw - 003
Static load test method statement  cm - ms- bw - 003Static load test method statement  cm - ms- bw - 003
Static load test method statement cm - ms- bw - 003
 
Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0Method statement for structural concrete repair rev.0
Method statement for structural concrete repair rev.0
 
Method statement for repair of concrete surface
Method statement for repair of concrete surfaceMethod statement for repair of concrete surface
Method statement for repair of concrete surface
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & window
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Column & beam
Column & beamColumn & beam
Column & beam
 
03 jun 08 pile head
03 jun 08 pile head03 jun 08 pile head
03 jun 08 pile head
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 

Piling work method statement cm- ms- bw - 002

  • 1. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal CAI MEP INTERNATIONAL CONTAINER TERMINAL METHOD STATEMENT OF PILING WORKS FOR BUILDINGS Page 1
  • 2. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal TABLE OF CONTENTS 1. General…………………………………………………………… 2 2. Scope of Works…………………………………………………... 2 3. Reference Technical Specification ………………………………. 2 4. Reference Drawings……………………………………………..... 2 5. Specification of Piling Machine…………………………………... 2 6. Piling Schedule……………………………………………………. 2 7. Equipment and manpower list…………………………………… 2 7.1. Equipment………………………………………………………… 3 7.2. Labors…………………………………………………………….. 5 8. General Flow Chart Of Piling Work……………………………… 6 9. Piling Procedure…………………………………………………... 7 10. Piling by Diesel Hammer…………………………………………. 8 10.1 Driving Lower Segment PHC Pile………………………………... 8 10.2 Splicing Work……………………………………………………... 9 10.3 Driving Upper Segment PHC Pile……………………………….... 9 11. Pile Driving Record………………………………………………. 10 12. Pile Dynamic Analyzer…………………………………………... 11 13. Quality Control………………………………………………….... 11 13.1. Inspection of Fabrication ……………………………………….... 11 13.2. Inspection of Welding Work……………………………………... 11 14. Safety Control…………………………………………………...... 12 15. Appendixes……………………………………………………….. 13 Page 2
  • 3. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 1. General : This Method Statement for PHC and the solid pile, piling work procedure of buildings for CAI MEP INTERNATIONAL CONTAINER TERMINAL PROJECT is to demonstrate the process of driving these piles in compliance with all the required specifications, standards, and proper construction procedures governing the pile driving works for the building foundation of the project. 2. Scope Of Works : Execution and supply of PHC and square solid piles, setting piles location before driving, driving and all necessary engineering works could be categorized as follows: Type of piles are PHC pile type A, (Ø 600 mm, Ø500mm), and 400mmx400mm solid square piles. 3. Reference Technical Specifications : Technical Specification: Part 4B, Division 2 – Piling Works for Buildings. 4. Reference Drawing List : Attached in Appendix B 5. Specification and Certificate of Piling Machine Specification of piling machine and crane operation certificate: Attached in Appendix C 6. Piling Schedule : Attached in Appendix E Page 3
  • 4. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal 7. Equipment & Manpower List: 7.1. Equipment to Be Used: The Equipment to be used for pile driving works is summarized in Table 7.1 Table 7.1 List of Equipment No Equipment Specification Quantity Capacity 1 Diesel Pile Hammer KOBELCO K35/K25 1 5T KOBELCO 2 Diesel Pile Hammer K35/DELMAG D 25 1 5T 3 Diesel Pile Hammer HERA3500/D25C 1 5T 4 Diesel Pile Hammer KOBELKO K45/KB60 MITSUBISHI MB 70 1 4.5T,6T,7T 5 Crane Truck Model: LS78 1 35T 6 Crane Truck Model: DH 350 1 35T 7 Theodolite Japan Made 04 100% precise 8 Survey Equipment US Made 1 100% precise 9 Automatic Level Japan Made 2 100% precise TOTAL→ 13 7.2. Labors To Be Deployed: Labors and/or trades to be deployed for PHC piling work is summarized in Table 7.2 Page 4
  • 5. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Table 7.2- List of labors Description Quantity Remark Engineer 3 Foreman 3 Piling operator 3 Workers 12 Welders 6 Surveyor 4 Crane operator 2 TOTAL→ 33 8. General Flow Chart Of Piling Work: General Flow Chart: Page 5
  • 6. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Mobilization of Piling Machine Lifting the upper segment PHC pile and Splicing Driving the upper PHC pile (Middle/Top) 9. Piling Procedure  PHC Piles D600mm, D500mm and Solid 400mmx400mm will be plant fabricated and transported to the site by a Trailer truck and by barge. They will be Page 6 Delivery of PHC Pile by Barge & Trailer Truck for Building Lifting the lower segment PHC pile by Crane then mount Diesel Hammer Driving the lower segment PHC pile Confirm the bearing capacity by evaluating penetration during driving Finish
  • 7. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal supported by bedding timbers placed directly under the positions of lifting hooks (Shown in Figure 1).  Piles will be stored carefully on flat ground within the temporary yard and a maximum of three (3) layers per stock pile is required.  Pile markings should be carried out to every pile segments to check the rough penetration per hammer blow. Bottom segment piles will be marked at every 1.0m pitch, middle segments, and top segments will be marked every 20cm pitch.  Material delivery dockets, receipts and physical inspection report shall be submitted to the Engineer. TRUCK CRANE TRAILER PHC PILE 0. 2L 0. 6L 0. 2L Figure 1: Transportation of PHC Pile Sand Bag Sand Bag TIMBER PHC PILE 0. 2L E R 0. 2L 0. 2L Figure 2: Storage of PHC Pile 10.Piling By Diesel Hammer : Page 7
  • 8. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal The piles will be driven by diesel hammer. The driving will be stopped after confirming the bearing capacity. (Shown in Figure 2) PILE UNDER DRIVING CENTER LINE OF PILE PILE DRIVER TRANSIT/PLUMB BOB SURVEYER SURVEYER DIESEL HAMMER VI NG DR I I ON RE C T DI TRANSIT/PLUMB BOB Figure 2: Pile Driving 10.1. Driving Lower Segment PHC Pile:  Crane will lift up the lower segment PHC Pile near the piling machine. The PHC pile will be held along leader of diesel hammer. Lifting position shall be 0.2L of pile length. ( lower than cracking moment)  The pile position will be adjusted by moving the leader until its top coincides with the hammer then mount the cap on the pile top. Before start driving, vertical position of the pile will be checked carefully by total station or theodolite to confirm its verticality. 10.2. Splicing Work: Page 8
  • 9. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal  Prior to splicing, welding surfaces will be cleaned and free from rust, oil, water and other foreign elements that would affect welded joints.  After driving lower segment, the upper segment will be lifted by piling machine, set above the lower segment coincide their centers directly and aligned vertically then fixed the clamp to maintain its alignment. Inclination tolerance shall be checked by split level, and it should be less than 1.0cm/1.0m)  . Splices will be made by butt welding, using arc welding performed 2G position and in accordance to WPS (Welding Position Standard) for welding.  Visual and NDT inspection check will be conducted to every welding joint done. Figure 3 UPPER PILE 10.3Driving Upper Segment PHC Pile: Top segment shall be driven after obtaining the PDA test results for correction factor from Hailey’s formula  Driving will be complete after confirming the sufficient bearing capacity, from Hailey’ s formula shown below with reference to PDA Test results. Page 9 PILE DRIVER DIESEL HAMMER HELMET LOWER PILE 1) DRIVING OF LOWER PILE 2) CLEANING OF PILE HEAD 3) SPLICING 4) RESUMING OF DRIVING
  • 10. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal  If it is found that the bearing capacity is still insufficient obtained from rebound record against design, the pile should be extended and re-driven until the bearing capacity is reached. Ru = 9.81 (Ef.MR.H) x MR + e 2 .MP S+0.5(C1+C2+C3) MR + MP = A In which: Ru : Ultimate Resistance, KN MR: Weight of ram, Kg H : Drop height of hammer, mm Ef : Efficiency of fall of hammer MP: Weight of pile + helmet, Kg e : Coefficient of restitution [ e = (S+{C₁+C₂+C₃}÷2 x PDA)/(Ef x MR x H) ] C1: Elastic deformation of pile, mm C2: Elastic deformation of ground, mm C3: Elastic deformation of pile head cushion, mm (here C3 = 2 mm). S : average penetration, in mm per blow for at least the last 10 blows RP: Correction Factor (RP = S.L.T. / A) (Use rebound record- Attached Appendix F)  The result of Pile driving and bearing capacity shall be confirmed by the Engineer and the records of pile installation shall be submitted to the Engineer.  In case the pile tip can not reach the design level due to unforeseen hard layer, this matter will be reported to the Engineer.  If piles cannot be driven to the design level but has already attained the required bearing capacity, the driving shall be stopped in accordance to specification and Engineer’s instruction to avoid buckling or cracking of the pile.  Pile head treatment shall be done after getting Engineer’s approval. 11. Pile Record:  Before final setting of the piles, the rebound shall be recorded. Page 10 x RP
  • 11. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal  The pile driving is deemed completed after confirmation of the sufficient bearing capacity against design. Bearing capacity for all piles will be calculated with formula. 12. Pile Dynamic Analyzer (PDA)  Pile Dynamic Analysis will be conducted to confirm the pile capacities and to decide the correction factor of Hiley’s formula. PDA test provides more information, about Skin resistance distribution, Toe resistance, simulated static load-settlement relationship, pile integrity, stresses in the pile during the blow. PDA test shall be conducted by Engineer 13. Quality Control 13.1. Inspection of Fabrication  Before fabrication PHC and square Pile materials such as, cement, sand, gravel, reinforcing bars, tendon wires and etc, will be inspected on Factory before fabrication, and finished product will again be inspected before delivery to the site.  The inspection report shall be submitted before piles will be delivered on site. When PHC and square piles arrives on site/stockyard, these will be inspected again for its, physical conditions, quantity and quality in accordance with specification or standards listed below: - Length tolerance: ±3% - Outside diameter tolerance: +7mm/-4mm - Wall thickness tolerance: +unspecified/-0mm - Cracking: no crack  The quality control and inspection report will be submitted to the Engineer. 13.2. Inspection of Welding Work.  Prior to the welding, the grooved face and its adjacent areas shall be completely free from oil, paint, oxide, water and all other foreign materials.  Welding rod will be stored in a dry and humid place to keep its required temperature. Only welding rod approved by the Engineer will be used on the splicing of pile. Page 11
  • 12. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal  Piles are jointed with their end plates evenly around its diameter, welding must be carried out in accordance with manufacture’s instruction and must be checked before driving resumes. Piles welding splice will be tested by NDT test. Basically all weld joints shall be tested by NDT but reducing option will be proposed depending on the quality of test obtained on the previous welded joints. (Refer to attached form in Appendix F) (1) Crack Inspection of Welding There shall be no cracks in or near the weld beads. The inspection shall be carried out by visual and Non Destructive test (NDT). (2) Inspection of Bead Surface and Shape Visual inspection of bead surface and shape shall be done by the process listed below. a. Pits on bead surface Butt joints shall be free of weld pits on the bead surface. b. Flatness of bead There shall be no height difference exceeding 3mm within 25mm length of a bead. c. Undercut The depth of undercut shall not exceed 0.3mm. d. Overlap There shall be no overlap.  During driving, the pile head will be protected by helmet of cast steel or mild steel fitted closely around the pile. Packing (cushion) timber, covering the head of pile, will be placed on the pile and will be replaced as often as necessary to prevent damage to the piles. 14. Safety Control:  Prior to commencement of any activities, the contractor will ensure all safety work practices and requirements for the different operations and are made informed and strictly complied at all times. Page 12
  • 13. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal The following steps are strictly checked before and during working. 1. Equipment and machine efficiency checking prior to operation. 2. Grand condition 3. Tool box meeting 15. Appendices: Appendix A: Organizational Chart Appendix B: Ref. Drawings List Appendix C: Specification and Certificate of Piling Machine Appendix D: Fabrication Schedule Appendix E: Pile Driving Schedule Appendix F: Pile Driving & Welding splicing Form Appendix G: Checklist for PHC Pile Manufacturing Appendix H: Inspection and Test PLan Page 13
  • 14. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix A: Organizational Chart TOA-TOYO JV Site Manager Engineer & Safety Pile Transportation Team Item No Title Numbers Remarks 1 Site Manager 2 2 Engineer/Safety 3 3 Foreman 3 4 Operator 3 5 Welder 6 6 Worker 12 7 Surveyor 4 Total→ 33 Page 14 Piling Rig-2 Team-2 Piling Rig-1 Team-1
  • 15. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix B: Ref. Drawing List: Page 15
  • 16. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix C: Specification and Certificate of Piling Machine Page 16
  • 17. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix D: Pile Fabrication Schedule Page 17
  • 18. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix E: Pile Driving Schedule Page 18
  • 19. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix F: Pile Driving & Welding splicing Form Page 19
  • 20. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix G: Checklist for PHC Pile Manufacturing Page 20
  • 21. Doc. Title Method Statement of Piling Works for Buildings TOA-TOYO JOINT VENTURE Doc. No CM - MS – BW - 002 Rev. No. 0 Date July,2010 Construction of Port Facilities and Buildings for Cai Mep International Container Terminal Appendix H: Inspection and Test Plan Page 21