SlideShare a Scribd company logo
1 of 48
CVL 776
CONSTRUCTION PRACTICES AND EQUIPMENT
SUBMITTED TO:-
PROF. A.K. JAIN
(DEPT. OF CIVIL
ENGINEERING, IIT
DELHI)
SUBMITTED BY :-
SHASHANK NAMDEO
2015CET2152
COFFERDAM
COFFER DAM
A cofferdam is a temporary structure designed to
keep water and/or soil out of the excavation in which a
bridge pier or other structure is built.
When construction must take place below the water
level, a cofferdam is built to give workers a dry work
environment. Sheet piling is driven around the work
site, seal concrete is placed into the bottom to prevent
water from seeping in from underneath the sheet piling,
and the water is pumped out
The word "cofferdam" comes from "coffer" meaning
box, in other words a dam in the shape of a box.
DEFINITION
• Braced
• Earth-Type
• Timber Crib
• Double-Walled Sheet Pile
• Cellular
TYPES
• Formed from a single wall of sheet piling
• Driven into the ground to form a box
• around the excavation site
• The "box" is then braced on the inside
• Interior is dewatered
• Primarily used for bridge piers in
• shallow water (30 - 35 ft depth)
1.BRACED COFFERDAMS
• It is the simplest type of cofferdam.
• It consists of an earth bank with a clay core or
vertical sheet piling enclosing the excavation.
• It is used for low-level waters with low velocity
and easily scoured by water rising over the top.
2. EARTH-TYPE
• Constructed on land and floated into place.
• Lower portion of each cell is matched with
contour of river bed.
• It uses rock ballast and soil to decrease seepage
and sink into place, also known as “Gravity
Dam”.
• It usually consists of 12’x12’ cells and is used in
rapid currents or on rocky river beds.
• It must be properly designed to resist lateral
forces such as tipping / overturning and sliding
3. TIMBER CRIB
TIMBER CRIB COFFER
DAM
• They are double wall cofferdams
comprising two parallel rows of sheet
piles driven into the ground and
connected together by a system of tie rods
at one or more levels.
• The space between the walls is generally
filled with granular material such as
sand, gravel or broken rock.
4. DOUBLE-WALLED SHEET PILE
• Cellular cofferdams are used only in
those circumstances where the excavation
size precludes the use of cross-excavation
bracing.
• In this case, the cofferdam must be stable
by virtue of its own resistance to lateral
forces.
5. CELLULAR
CELLULAR COFFER DAM
• Scouring or undermining by rapidly
• flowing water
• Stability against overturning or tilting
• Upward forces on outside edge due to
tilting
• Stability against vertical shear
• Effects of forces resulting from:
• Ice, Wave, Water, Active Earth and
• Passive Earth Pressures
DESIGN CONSIDERATIONS
• Allow excavation and construction of structures
in otherwise poor environment .
• Provides safe environment to work
• Contractors typically have design responsibility
• Steel sheet piles are easily installed and
removed
• Materials can typically be reused on
• other projects
ADVANTAGES
Items needed for installation:
•Pile driving hammer
•Vibratory or Impact
•Crane of sufficient size
•Steel sheet piles are typically used
•H-piles and/or wide-flange beams for wales and
stringers
•Barges may be required
INSTALLATION
•Sheet piling
•Bracing frame
•Concrete seal
•Bearing piles
COMPONENTS
BRACING FRAME
BEARING
PILES
The typical cofferdam, such as a bridge pier,
consists of sheet piles set around a bracing frame
and driven into the soil sufficiently far to develop
vertical and lateral support and to cut off the flow
of soil and, in some cases the flow of water.
DESCRIPTION
The structure inside may be founded directly on
rock or firm soil or may require pile foundations.
In the latter case, these generally extend well
below the cofferdam.
In order to dewater the cofferdam, the bottom
must be stable and able to resist hydrostatic uplift.
Placement of an underwater concrete seal course is
the fastest and most common method.
DESCRIPTION
An underwater concrete seal course may be placed
prior to dewatering in order to seal off the water, resist its
pressure, and also to act as a slab to brace against the
inward movement of the sheet piles in order to mobilize
their resistance to uplift under the hydrostatic pressure.
CONSTRUCTION
For a typical cofferdam, such as for a bridge
pier, the construction procedure follow the listed
pattern.
1. Pre-dredge to remove soil or soft sediments
and level the area of the cofferdam.
CONSTRUCTION SEQUENCE
2. Drive temporary support piles
3. Temporarily erect bracing frame on the support piles.
CONSTRUCTION SEQUENCE
4. Set steel sheet piles, starting at all four corners and
meeting at the center of each side
5. Drive sheet piles to grade.
6. Block between bracing frame and sheets, and provide
ties for sheet piles at the top as necessary.
CONSTRUCTION SEQUENCE
7. Excavate inside the grade or slightly below
grade, while leaving the cofferdam full of water.
CONSTRUCTION SEQUENCE
8. Drive bearing piles.
9. Place rock fill as a leveling and support
course.
CONSTRUCTION SEQUENCE
10. Place tremie concrete seal.
CONSTRUCTION SEQUENCE
Tremie concrete seal.
CONSTRUCTION SEQUENCE
CONSTRUCTION SEQUENCE
Tremie concrete seal.
11. Check blocking between bracing and sheets.
12. Dewater.
13. Construct new structure.
CONSTRUCTION SEQUENCE
AFTER DEWATERING AND
CONSTRUCTION OF STRUCTURE
14. Flood cofferdam.
CONSTRUCTION SEQUENCE
15. Remove sheet piles.
16. Remove bracing.
17. Backfill.
CONSTRUCTION SEQUENCE
Installation of Wale and Strut System for Framework
WALE AND STRUT SYSTEM
Installation of Wale and Strut System for Template
WALE AND STRUT SYSTEM
In cofferdam construction, safety is a paramount
concern, since workers will be exposed to the hazard of
flooding and collapse. Safety requirements are:
• Good design
• Proper construction
• Verification that structure is constructed as per plan
• Monitoring the behavior of cofferdam and its
surrounding
• Provision of adequate access
• Light and ventilation
• Attention to safe practices on the part of all workers and
supervisors
SAFETY REQUIREMENTS
Principal hazards and risks
1. Falls from height from dam walls into
excavation or into water
2. Health hazards from contaminated water,
hazardous gases in confined spaces, noise and
vibration from piling operations
3. Hazards from services such as cables in river
bed, temporary power cables in water etc.
4. Contact with moving equipment such as
collisions between boats, pontoons, crane barges
and cofferdam. moving plant and slewed
equipment in confined space
5. Flooding caused by failure of cofferdam walls
Some design options to reduce
hazards
1.Consider a temporary causeway instead of
floating rigs
2. Prefabricated caissons towed into place be used
instead of driven piled cofferdams to lessen the
work in the water and reduce the noise.
3. Consider the level of the working platform or
causeway with respect to high tide and flood
levels.
5. Plan the shape of the cofferdam to suit working
space and construction plant as well as final
structure.
6. Consider the use of different construction or of
remotely controlled techniques to design out the
need for underwater working.
7. Incorporate lugs and holes in design to aid
fixing of equipment
TRADITIONAL SHEET PILE SHAPES
LARSON U TYPE SHEET PILES
Z SHAPED SHEET PILES
JOINTS IN SHEET PILING
TYPES OF INTERLOCKS
1. BALL AND SOCKET
2. SINGLE JAW SOCKET
3. DOUBLE JAW SOCKET
4. HOOKE AND GRIP
5. THUMB AND FINGURE ONE PIONT
6. THUMB AND FINGURE THREE POINT
7. DOUBLE HOOKE
THANK YOU

More Related Content

What's hot

Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
Tarique048
 
footing
footingfooting
footing
illpa
 

What's hot (20)

Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Caisson
CaissonCaisson
Caisson
 
Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concrete
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Workability of Concrete.ppt
Workability of Concrete.pptWorkability of Concrete.ppt
Workability of Concrete.ppt
 
Sheet pile presentation
Sheet pile presentationSheet pile presentation
Sheet pile presentation
 
Grouting
GroutingGrouting
Grouting
 
Well foundation
Well foundationWell foundation
Well foundation
 
Bridge components
Bridge componentsBridge components
Bridge components
 
1. Pile foundations (SL 1-143).pdf
1. Pile foundations (SL 1-143).pdf1. Pile foundations (SL 1-143).pdf
1. Pile foundations (SL 1-143).pdf
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Shotcrete
ShotcreteShotcrete
Shotcrete
 
REPORT ON PLASTERING
REPORT ON PLASTERINGREPORT ON PLASTERING
REPORT ON PLASTERING
 
Earth pressure
Earth pressureEarth pressure
Earth pressure
 
Caisson foundation.ppt
Caisson foundation.pptCaisson foundation.ppt
Caisson foundation.ppt
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
 
SINKING , TILTING AND DISEASE OF CAISSON
SINKING , TILTING AND DISEASE OF CAISSONSINKING , TILTING AND DISEASE OF CAISSON
SINKING , TILTING AND DISEASE OF CAISSON
 
Unit 1 sheet pile-converted
Unit 1   sheet pile-convertedUnit 1   sheet pile-converted
Unit 1 sheet pile-converted
 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls
 
footing
footingfooting
footing
 

Similar to Cofferdam

Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
Rizwan Samor
 
cofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptxcofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptx
ssuser23e4af
 

Similar to Cofferdam (20)

Lesson4
Lesson4Lesson4
Lesson4
 
Chapter 4.2 coffer dam, well foundation-final1
Chapter 4.2   coffer dam, well foundation-final1Chapter 4.2   coffer dam, well foundation-final1
Chapter 4.2 coffer dam, well foundation-final1
 
Aravind B RGUKT Basar
Aravind B RGUKT BasarAravind B RGUKT Basar
Aravind B RGUKT Basar
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
Underwater construction
Underwater construction Underwater construction
Underwater construction
 
caissons and cofferdam in substructure construction
caissons and cofferdam in substructure constructioncaissons and cofferdam in substructure construction
caissons and cofferdam in substructure construction
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
coffer Dam.pptx
coffer Dam.pptxcoffer Dam.pptx
coffer Dam.pptx
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
Coffer Dams and Caissons
Coffer Dams and CaissonsCoffer Dams and Caissons
Coffer Dams and Caissons
 
Breakwaters
BreakwatersBreakwaters
Breakwaters
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
Notes on introduction and design of caissons
Notes on introduction and design of caissonsNotes on introduction and design of caissons
Notes on introduction and design of caissons
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
underwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptxunderwater-construction-5651f4bb8b92f.pptx
underwater-construction-5651f4bb8b92f.pptx
 
Underwater construction
Underwater constructionUnderwater construction
Underwater construction
 
underwater construction
underwater constructionunderwater construction
underwater construction
 
cofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptxcofferdam-150424121052-conversion-gate01.pptx
cofferdam-150424121052-conversion-gate01.pptx
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Breakwaters ports and harbors report
Breakwaters ports and harbors reportBreakwaters ports and harbors report
Breakwaters ports and harbors report
 

Recently uploaded

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 

Recently uploaded (20)

Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 

Cofferdam

  • 1. CVL 776 CONSTRUCTION PRACTICES AND EQUIPMENT SUBMITTED TO:- PROF. A.K. JAIN (DEPT. OF CIVIL ENGINEERING, IIT DELHI) SUBMITTED BY :- SHASHANK NAMDEO 2015CET2152
  • 3. A cofferdam is a temporary structure designed to keep water and/or soil out of the excavation in which a bridge pier or other structure is built. When construction must take place below the water level, a cofferdam is built to give workers a dry work environment. Sheet piling is driven around the work site, seal concrete is placed into the bottom to prevent water from seeping in from underneath the sheet piling, and the water is pumped out The word "cofferdam" comes from "coffer" meaning box, in other words a dam in the shape of a box. DEFINITION
  • 4. • Braced • Earth-Type • Timber Crib • Double-Walled Sheet Pile • Cellular TYPES
  • 5. • Formed from a single wall of sheet piling • Driven into the ground to form a box • around the excavation site • The "box" is then braced on the inside • Interior is dewatered • Primarily used for bridge piers in • shallow water (30 - 35 ft depth) 1.BRACED COFFERDAMS
  • 6.
  • 7. • It is the simplest type of cofferdam. • It consists of an earth bank with a clay core or vertical sheet piling enclosing the excavation. • It is used for low-level waters with low velocity and easily scoured by water rising over the top. 2. EARTH-TYPE
  • 8.
  • 9. • Constructed on land and floated into place. • Lower portion of each cell is matched with contour of river bed. • It uses rock ballast and soil to decrease seepage and sink into place, also known as “Gravity Dam”. • It usually consists of 12’x12’ cells and is used in rapid currents or on rocky river beds. • It must be properly designed to resist lateral forces such as tipping / overturning and sliding 3. TIMBER CRIB
  • 11. • They are double wall cofferdams comprising two parallel rows of sheet piles driven into the ground and connected together by a system of tie rods at one or more levels. • The space between the walls is generally filled with granular material such as sand, gravel or broken rock. 4. DOUBLE-WALLED SHEET PILE
  • 12.
  • 13. • Cellular cofferdams are used only in those circumstances where the excavation size precludes the use of cross-excavation bracing. • In this case, the cofferdam must be stable by virtue of its own resistance to lateral forces. 5. CELLULAR
  • 15. • Scouring or undermining by rapidly • flowing water • Stability against overturning or tilting • Upward forces on outside edge due to tilting • Stability against vertical shear • Effects of forces resulting from: • Ice, Wave, Water, Active Earth and • Passive Earth Pressures DESIGN CONSIDERATIONS
  • 16. • Allow excavation and construction of structures in otherwise poor environment . • Provides safe environment to work • Contractors typically have design responsibility • Steel sheet piles are easily installed and removed • Materials can typically be reused on • other projects ADVANTAGES
  • 17. Items needed for installation: •Pile driving hammer •Vibratory or Impact •Crane of sufficient size •Steel sheet piles are typically used •H-piles and/or wide-flange beams for wales and stringers •Barges may be required INSTALLATION
  • 18. •Sheet piling •Bracing frame •Concrete seal •Bearing piles COMPONENTS
  • 20. The typical cofferdam, such as a bridge pier, consists of sheet piles set around a bracing frame and driven into the soil sufficiently far to develop vertical and lateral support and to cut off the flow of soil and, in some cases the flow of water. DESCRIPTION
  • 21. The structure inside may be founded directly on rock or firm soil or may require pile foundations. In the latter case, these generally extend well below the cofferdam. In order to dewater the cofferdam, the bottom must be stable and able to resist hydrostatic uplift. Placement of an underwater concrete seal course is the fastest and most common method. DESCRIPTION
  • 22. An underwater concrete seal course may be placed prior to dewatering in order to seal off the water, resist its pressure, and also to act as a slab to brace against the inward movement of the sheet piles in order to mobilize their resistance to uplift under the hydrostatic pressure. CONSTRUCTION
  • 23. For a typical cofferdam, such as for a bridge pier, the construction procedure follow the listed pattern. 1. Pre-dredge to remove soil or soft sediments and level the area of the cofferdam. CONSTRUCTION SEQUENCE
  • 24. 2. Drive temporary support piles 3. Temporarily erect bracing frame on the support piles. CONSTRUCTION SEQUENCE
  • 25. 4. Set steel sheet piles, starting at all four corners and meeting at the center of each side 5. Drive sheet piles to grade. 6. Block between bracing frame and sheets, and provide ties for sheet piles at the top as necessary. CONSTRUCTION SEQUENCE
  • 26. 7. Excavate inside the grade or slightly below grade, while leaving the cofferdam full of water. CONSTRUCTION SEQUENCE
  • 27. 8. Drive bearing piles. 9. Place rock fill as a leveling and support course. CONSTRUCTION SEQUENCE
  • 28. 10. Place tremie concrete seal. CONSTRUCTION SEQUENCE
  • 31. 11. Check blocking between bracing and sheets. 12. Dewater. 13. Construct new structure. CONSTRUCTION SEQUENCE
  • 34. 15. Remove sheet piles. 16. Remove bracing. 17. Backfill. CONSTRUCTION SEQUENCE
  • 35. Installation of Wale and Strut System for Framework WALE AND STRUT SYSTEM
  • 36. Installation of Wale and Strut System for Template WALE AND STRUT SYSTEM
  • 37. In cofferdam construction, safety is a paramount concern, since workers will be exposed to the hazard of flooding and collapse. Safety requirements are: • Good design • Proper construction • Verification that structure is constructed as per plan • Monitoring the behavior of cofferdam and its surrounding • Provision of adequate access • Light and ventilation • Attention to safe practices on the part of all workers and supervisors SAFETY REQUIREMENTS
  • 38. Principal hazards and risks 1. Falls from height from dam walls into excavation or into water 2. Health hazards from contaminated water, hazardous gases in confined spaces, noise and vibration from piling operations 3. Hazards from services such as cables in river bed, temporary power cables in water etc.
  • 39. 4. Contact with moving equipment such as collisions between boats, pontoons, crane barges and cofferdam. moving plant and slewed equipment in confined space 5. Flooding caused by failure of cofferdam walls
  • 40. Some design options to reduce hazards 1.Consider a temporary causeway instead of floating rigs 2. Prefabricated caissons towed into place be used instead of driven piled cofferdams to lessen the work in the water and reduce the noise. 3. Consider the level of the working platform or causeway with respect to high tide and flood levels.
  • 41. 5. Plan the shape of the cofferdam to suit working space and construction plant as well as final structure. 6. Consider the use of different construction or of remotely controlled techniques to design out the need for underwater working. 7. Incorporate lugs and holes in design to aid fixing of equipment
  • 43. LARSON U TYPE SHEET PILES
  • 44. Z SHAPED SHEET PILES
  • 45. JOINTS IN SHEET PILING
  • 46. TYPES OF INTERLOCKS 1. BALL AND SOCKET 2. SINGLE JAW SOCKET 3. DOUBLE JAW SOCKET 4. HOOKE AND GRIP 5. THUMB AND FINGURE ONE PIONT 6. THUMB AND FINGURE THREE POINT 7. DOUBLE HOOKE
  • 47.