PROJECT MANAGEMENT IN CONSTRUCTION
IMPROVING PROJECT PERFORMANCE
INTRODUCTION
• Objective for the presentation is to analyse the various factors in the
project management in construction which lead to success and
failure of the projects.
• Learning from projects by understanding the essential elements of
the project management (e.g. the Leadership Role of the Project
Manager, Project Planning, Risk Management) , Analysis of project
management done in various projects worldwide
what is project management ??
• Project management is the application of knowledge , skills ,
tools and techniques to project activities in order to meet or
exceed stakeholders needs and expectations from a project.
• Need of balancing competing demands among scope , time ,
cost , quality , stakeholders with different needs and
expectations and identified (needs) and unidentified
requirements (expectations).
ATTRIBUTES TO PROJECT MANAGEMENT
• Project Managers.
• Determining Project Objectives.
• Managing Budget and Resources.
• Reporting Progress.
• Evaluating efficiency and effectiveness.
RESPONSIBILITIES OF PROJECT MANAGER
• Planning thoroughly through all the aspects of the project.
• Controlling the manpower of the organization.
• Optimise the technical versus cost trade offs in specific areas
where optimisation is required.
• Monitor performance , costs and efficiency of all elements of the
project.
• Completing the project on schedule and within costs .
COMPETENCIES OF A PROJECT MANAGER
Planning / organizing .
Controlling.
Stress Tolerance.
End customer orientation.
Personal Chemistry.
Analytical skills.
Leadership Quality / Managing people.
Managing performance.
Sensitivity.
WHY DO PROJECTS GO WRONG ??
• Project goals are not clearly defined.
• Constraints on the completion of the project arising from the
different objectives of
Short time scale.
Resource Availability.
Quality factors
Human factors.
CONSTRAINTS OF PROJECT MANAGEMENT
• Cost
• Scope
• Quality
• Customer satisfaction.
• Time.
• Risk
• Resources.
PROJECT MANAGEMENT PROCESS
• Project Initiation.
• Project planning.
• Project scheduling and execution.
• Monitoring and control.
• Close Out of the project.
SUCCESSFUL PROJECTS CASE STUDIES
• AL WAHDA MASTER DEVELOPMENT , ABU DHABI.
 Vibrant bussiness and shopping destination.
 EC Harris International Ltd. Was involved in every element
from master planning of development to the concept
development and upto realization stage.
• Objectives of EC Harris international Limited.
 Project Management gateway approach. (Design verification
checks ,value engineering , Risk Management).
Categorise roles , responsibilities , communication protocols.
RESOURCES
• Truly International Project Team.
• Dynamic Team who were happy to multi task in their daily roles.
• Proper Risk Management team.
• Proper co-ordination among the team.
CHALLENGES
• Due to economic slowdown in 2008 , steel and cement prices
rocketed and whose availability was un predictable. Proper early
planning let the supply lines continue.
AQUEDUCTS AND LARGE DIAMETER TRUNK MAINS
CLEAN & MAINTAIN PROGRAMME, UNITED UTILITIES
• OBJECTIVES :
 Plan , design , develop and implement a major programme of
inspection , maintenance and repairs on two main aqueducts.
Clean and refurbish six large diameter trunk mains reducing
levels of iron and Manganese.
• RESOURCES :
Huge exercise in logistics , resource health and safety planning.
Project centric team members.
Governance board was established to review the project status
and risks.
KEY CHALLENGES
• Water supply interruption to the customers to be avoided.
• Fresh approach for the company to project prioritisation,
resource planning , risk management, integration and
scheduling.
• nature, scale and uncertainty of unforeseen events, such as
extremes of weather, major bursts, and third party damage, and
issues that required reactive maintenance put pressure on the
overall annual budget and caused project priorities to be
frequently re-assessed.
SUCCESS ACHIEVED :
• £8 million efficiency savings.
• Improved customer service standards.
• Better water quality.
• Reduced health and safety risk to employees and third parties by upgraded
access.
• Improved structural integrity of the aqueducts.
• Improved regional network response to incidents such as bursts, with faster
diversions, and altered flow rates to minimise water loss .
• Maintain customer supplies without major discolouration.
• Delivered with no lost time accidents and no significant impact on customer
levels of service.
BUILDING BETTER COMMUNITIES: MANAGING
RECONSTRUCTION AFTER THE INDIAN OCEAN TSUNAMI
• A global business providing management and consultancy services to the
property, transportation and infrastructure, environment and energy and
management and industrial sectors, was called in by the Canadian Red
Cross (CRC) to re-house more than 11,000 people made homeless by the
tsunami in Aceh, Indonesia.
• The company oversaw the reconstruction of 21 villages – 17 of which had to
be relocated – and the design and rebuilding of nearly 4,000 flood and
earthquake-resistant homes.
CHALLENGES:
• According to WSP the pressure to build, in the numbers covered
by the project, in a variety of remote locations with many
unknowns, coupled with a need to complete urgently, was ‘a
challenge of a lifetime’.
• When the company arrived in Aceh in mid- 2006, it found all
contracts behind schedule, confused objectives and programmes .
• No project management unit, poor availability of materials, difficult
access because of flooding, damaged roads and bridges.
• Disaffected communities who refused to take part in planning
because previous promises had been broken.
PROJECT SUCCESSES:
• Relationships were forged with local communities using patience,
listening skills, response to their preferences, and good
communication including a poster that depicted the road to
reconstruction.
• Nearly 4,000 houses were built and handed over to beneficiaries
across 21 villages in 2009 and positive feedback was received.
• The government was appreciative and applauded CRC for
delivering strong, robust durable houses amongst the highest
quality standards in the relief effort.
• WSP continued to maintain a presence for a year to ensure that,
at least for some time after the houses had been handed over,
professional and management capacity was available to iron out
issues.
• Build understanding and capacity about quality and safety from
future hazards.
DAWLISH SEA WALL EMERGENCY WORKS
CHALLENGES
• Nature’s unpredictability.
• Managing the interface between six main contractors on a scheme
with unclear scope and immense pressure to deliver as soon as
possible.
• To establish relationships with local people who had been
evacuated and with Teignbridge District Council as well as
managing the involvement of the Marine Management Organisation
and Crown Estates to ensure necessary licenses were in place.
• The importance of the work to the public and businesses was
never under‐estimated.
• Commit to a date in the first days as the scope was not only
unclear but increasing all the time, yet people needed to know
so they could make plans.
• Issues with those living alongside the line not only being
disturbed by the work but also impacted by the physical damage
to their homes, land and property.
• Need to manage their expectations of what the project team
could deliver.
SUCCESS ACHIEVED
• The rail link to South and West Devon and Cornwall re‐ opened on
time to an extremely ambitious programme, allowing Dawlish and
beyond to be reconnected to their railway and the rest of the UK.
• The team received good feedback from local councils and the public,
including letters and cards of thanks from local residents. For the
project team, the immediate success of achieving the goal has also
led to long term networking and relationships, leading to opportunities
for collaboration on future projects.
• Prime Minister David Cameron, praised the ‘orange army’ of engineers
as they have become known, for their “herculean effort” in completing
the repairs.
DELIVERY OF THE ROTARY WING STRATEGY 2009-2015,
UK MINISTRY OF DEFENCE
• CHALLENGES
• New Wildcat and Chinook Mk6 helicopters were to be
purchased while existing Puma, Apache, Chinook and Merlin
helicopters required upgrading and modernising.
• Investment was needed to ensure training aids such as flight
simulators reflected the upgraded fleet while maximising training
effect and efficiencies.
• Revised support arrangements for each of the core future
helicopters had to be implemented and full ownership of all
Merlins was to be transferred to the Royal Navy.
RESOURCES
• Dedicated project teams were established to deliver defined
elements and ensure that the transition to deliver the
strategy was coherent with ‘business as usual’.
• A strong project management culture was established
within each team through a monthly review drumbeat and
forward-looking metrics aimed at avoiding future pitfalls.
RESULTS
• Through the programme approach, five potent new helicopter
capabilities have been delivered to the UK’s armed forces within
the approved time and cost, while making substantial savings in
supporting military equipment.
• The £1 billion funding gap has been closed and £440 million has
been saved from the forecast cost of supporting the fleet for the
next five years without impacting upon military effectiveness.
GREEN PARK STATION STEP-FREE ACCESS PROJECT,
TRANSPORT FOR LONDON
CHALLENGES
• Despite the complexity, and a number of difficult issues to
manage particularly early in the project, the project managers
used multi-disciplinary design reviews, risk workshops and
programme workshops to maintain the direction of the project
and improve the quality of decision making.
• Because of its duration, and the limited works that could be
progressed until they were complete, the tunnelling works were
on the critical path.
RESULTS
• The changes made by the project allowed Green Park Station to perform
as promised during the London 2012 Olympics and contribute to making
sure the Games were as accessible as possible.
• The project was completed three months ahead of schedule and
substantially under budget, without using any of the risk or contingency
initially allowed.
• All this has been achieved while maintaining the highest standards of
safety through continuous improvement. As of June 2012, the project
had undertaken more than 400,000 man-hours with zero lost-time
injuries.
THE CONSTRUCTION PROGRAMME FOR THE LONDON 2012
OLYMPIC AND PARALYMPIC GAMES, OLYMPIC DELIVERY
AUTHORITY
CHALLENGES
• Huge levels of public interest in London 2012 .
• ODA (Olympic Development Authority ) recognised the project
could only be delivered in partnership and with the support of a
large coalition of organisations, many of whom had differing
interests.
• Ensure complete alignment between internal and external
objectives.
SUCCESS
• The ODA has successfully achieved its objectives, both for the
delivery of the physical infrastructure of the Olympic Park, and
also for significant achievements in its priority themes, such as
health and safety and sustainability.
POWERLINES UNDERGROUNDING PROJECT,
LONDON 2012
KEY OBJECTIVES OF THE PROJECT
• Deliver a quality project. , remove, mitigate and manage risk; ensure
the safety and well being of all personnel and workers engaged on or
affected by the project; demonstrate value for money; keep London
and customer supplies ‘switched on’.
SUCCESS
• Teamwork and trust were absolutely key. All parties worked as one,
focusing on the challenges in hand and buy-in to the common goal
rather than on protecting contractual positions. The fact that individual
success would only happen if everyone was successful was
understood and drove positive behaviours (there were no contractual
incentives to link these parties). Organisation and governance were
recognised as key aspects to the successful delivery of the project.
TRANSFORMING DUBLIN AIRPORT PROGRAMME,
TURNER & TOWNSEND
• CHALLENGES
• There was the sheer scale of the job of transforming Dublin Airport.
• Need to ensure that the airport stayed in full operation while work progressed – and that
key matters such as safety and passenger wellbeing are not compromised.
• Success
• Turner & Townsend successfully met the needs of the client by implementing a
programme management approach.
• Resulted in the transformation of Dublin Airport into a 21st Century Gateway to Ireland on
time and within budget.
• Stakeholder feedback on the finished product has been extremely encouraging .
WORLD’S MAJOR PROJECT FAILURE EXAMPLES
• BRITISH PETROLEUM
• Explosion cause the oil spill which was one of the worst ever oil disaster in the
history of the modern world.
• Reasons for Project Failure
• Extreme geographic location
• Weak risk management
• Lack of timely decisions
• Sluggish response in critical situation
• Undermining the situation
• Lack of planning
CASE STUDY: THE MILLENNIUM DOME
• Millennium Dome is a Dome shaped mega structure, built in the Greenwich
peninsula in south east London which was later closed because it failed to attract
the number of visitors which was expected to visit the place.
Reasons for failure
• Lack of vision.
• Poor execution.
• Lack of sufficient operational expertise.
• Poor marketing strategies.
• Financially mismanaged project.
• Lack of contingency plan.
RECOMMENDATIONS AFTER CASE STUDY:
• Management structure to be properly structured.
• Project costs
• projects should only proceed if they are clear with full life cycle
assessment cost of the project.
• Risk Analysis.
• Risk analysis of the project is necessary so that a project
manager should understand the cost which could arise in the later stages of
the project and prepare a plan for it.
• Project Income.
The project manager should keep in mind the
uncertainties related to this type of income. This can only be done
with the help of careful and practical assumptions.
• Contingency planning should be there.
• Proper financial management should be done prior to moving
with the project further.
CONCLUSISON
• Project failure is preventable with good project planning. When a project
starts to fail there are techniques to recognize and trained Project managers
minimize the extend of project failure or recover the failed projects as early
as possible.
• Project manager needs to be trained in such techniques so that he/she not
only recover the failed projects but also reduce the chances of failure.
COLUMBIA SHUTTLE
• Columbia Shuttle Disintegrates after re-entry into the earths
atmosphere.
Lessons learnt with respect to the columbia shuttle launch
project management
• “recency effect.”
It occurs when decision makers rely on only the most recent
information.
• Conservatism
A situation in which new information is ignored or given too little weight.
• overconfidence.
During the flight, engineers, concerned that the foam strike may have
caused a problem, asked the Mission Management Team (MMT) to request
satellite imagery of the spacecraft. Management, however, was apparently
confident that there was no safety issue.
• selective perception
In which management of the shuttle program had shifted from an
engineering focus to a managerial focus.
HURRICANE KATRINA
• On August 29, 2005 hurricane Katrina raced across the Gulf of Mexico and made
landfall in New Orleans, Louisiana. When it was over, a category 5 storm had
breached the levees, flooded eighty percent of the city, killed 1,500 people, and left
over 80 billion in damages. It was the costliest natural disaster in US history.
• What followed was a project failure of enormous proportions. It failed in
planning, it failed in execution and it failed in meeting even the most basic
needs of those caught in the middle of this tragic disaster.
• Four project management failures stand out.
• Communication
• Selective Perception
• Leadership
• Difficult Relationships
LESSONS LEARNT
• We need to be careful in generalizing the project failure lessons that can be learned
from a once-in-a-hundred-year tragedy, but the magnitude of the failure was so great
that it becomes a caricature of what can go wrong in more conventional projects.
• The more constituents involved, the greater will be the communication challenge.
Unless managed effectively, far too much time can be devoted to resolving
jurisdictional conflicts and not enough time on the real issues. Too many constituents
can sabotage a project.
• Be careful of selective perception. When it goes unchecked it can be effective in
miminizing interruptions, but the consequnces of locking out new data can be
disastrous.
• Either clear leadership lines must be established, or a collaborative environment .
similar to what can emerge in high performance teams must be created and
managed.
• • Difficult relationships must be addressed. Once they surface they are unlikely to go
away.
KEY REASONS OF PROJECT FAILURE
• Lack of senior management.
• Unclear project objectives.
• Scope creep.
• Gaps in communication.
• Lack of visibility of all projects.
CONCLUSION FROM DATA COLLECTION AND DATA
ANALYSIS
• PROJECT DELAYS IN CONSTRUCTION ARE DUE TO
1. Less number of labours against requirement.
2. Skill of labour is very poor or less.
3. Lack of project planning and scheduling by contractor.
4. Delay due to receiving permissions from government authorities.
5. Delay due to transporting material from supplier to site.
6. Complete absence of good site management and supervision by contractor.
7. Lacking of quality and quantity of work.
Project management in construction.

More Related Content

What's hot

Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management pptRajeshPV12
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project managementMC Tubera
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture) Muhammad Aljalali
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering fieldswetha110
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Schedulingakashpadole
 
Construction Project Management Powerpoint Presentation Slides
Construction Project Management Powerpoint Presentation SlidesConstruction Project Management Powerpoint Presentation Slides
Construction Project Management Powerpoint Presentation SlidesSlideTeam
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptTouqeer1
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in ConstructionSamsonFemiAdesope
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
introduction to construction management
 introduction to construction management introduction to construction management
introduction to construction managementHira Atiq
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 

What's hot (20)

Construction project management
Construction project managementConstruction project management
Construction project management
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Construction Project Management ppt
Construction Project Management pptConstruction Project Management ppt
Construction Project Management ppt
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
Types of resources in civil engineering field
Types of resources in civil engineering fieldTypes of resources in civil engineering field
Types of resources in civil engineering field
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Construction management
Construction managementConstruction management
Construction management
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Construction Project Management Powerpoint Presentation Slides
Construction Project Management Powerpoint Presentation SlidesConstruction Project Management Powerpoint Presentation Slides
Construction Project Management Powerpoint Presentation Slides
 
Risk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.pptRisk & Risk Management in Construction.ppt
Risk & Risk Management in Construction.ppt
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Site organization in Construction
Site organization in ConstructionSite organization in Construction
Site organization in Construction
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
introduction to construction management
 introduction to construction management introduction to construction management
introduction to construction management
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 

Viewers also liked

3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies Capterra
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementAditi Shah
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Construction Management: Stages of a Construction Project
Construction Management: Stages of a Construction ProjectConstruction Management: Stages of a Construction Project
Construction Management: Stages of a Construction ProjectLukasz Kisiel
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction managementXubitech
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012Yusuf Yıldız
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.Yousef Abujubba
 
Cost for Construction Project
Cost for Construction ProjectCost for Construction Project
Cost for Construction ProjectNagoorkani Majeed
 
Analyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionAnalyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionMichael Pink
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group
 
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM Lenka Larson
 
Project controls manager, project management, project planner, cost controls ...
Project controls manager, project management, project planner, cost controls ...Project controls manager, project management, project planner, cost controls ...
Project controls manager, project management, project planner, cost controls ...Aswadimanor Safeie
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONDAVIDSON ECHIDIKE
 

Viewers also liked (20)

3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies
 
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Construction Management: Stages of a Construction Project
Construction Management: Stages of a Construction ProjectConstruction Management: Stages of a Construction Project
Construction Management: Stages of a Construction Project
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Project management
Project managementProject management
Project management
 
Construction Management Project
Construction Management ProjectConstruction Management Project
Construction Management Project
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012
 
Overview of project management in engineering environment
Overview of project management in engineering environmentOverview of project management in engineering environment
Overview of project management in engineering environment
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
 
Cost for Construction Project
Cost for Construction ProjectCost for Construction Project
Cost for Construction Project
 
Analyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionAnalyzing data, performance and impacts in construction
Analyzing data, performance and impacts in construction
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
Global EPC Project Management Forum 20-21 APRIL 2017 AMSTERDAM
 
Project controls manager, project management, project planner, cost controls ...
Project controls manager, project management, project planner, cost controls ...Project controls manager, project management, project planner, cost controls ...
Project controls manager, project management, project planner, cost controls ...
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
 

Similar to Project management in construction.

Similar to Project management in construction. (20)

LinkedIn
LinkedInLinkedIn
LinkedIn
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptx
 
01 Monadelphous Marine Capability
01 Monadelphous Marine Capability01 Monadelphous Marine Capability
01 Monadelphous Marine Capability
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Peter Dally Aquenta CV
Peter Dally Aquenta CVPeter Dally Aquenta CV
Peter Dally Aquenta CV
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Emad Hamdy Resume
Emad Hamdy ResumeEmad Hamdy Resume
Emad Hamdy Resume
 
Resume ng ji xian jason
Resume ng ji xian jasonResume ng ji xian jason
Resume ng ji xian jason
 
presentation slide
 presentation slide presentation slide
presentation slide
 
Personal 3 CV 2015
Personal 3  CV 2015Personal 3  CV 2015
Personal 3 CV 2015
 
Psm Cv Presentation Aug 16, 2012
Psm Cv Presentation Aug 16, 2012Psm Cv Presentation Aug 16, 2012
Psm Cv Presentation Aug 16, 2012
 
Psm Cv Presentation Aug 16, 2012
Psm Cv Presentation Aug 16, 2012Psm Cv Presentation Aug 16, 2012
Psm Cv Presentation Aug 16, 2012
 
Jack Oldrin RS2
Jack Oldrin RS2Jack Oldrin RS2
Jack Oldrin RS2
 
CV of Dinesh
CV of DineshCV of Dinesh
CV of Dinesh
 
Resume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / ScheduleResume - Senior Projects Planner / Schedule
Resume - Senior Projects Planner / Schedule
 
Cv master english 30-01-18 v.1
Cv   master english 30-01-18 v.1Cv   master english 30-01-18 v.1
Cv master english 30-01-18 v.1
 
Abd El-Rahman Rostom (PMP) CV
Abd El-Rahman Rostom (PMP) CVAbd El-Rahman Rostom (PMP) CV
Abd El-Rahman Rostom (PMP) CV
 
Petrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj LloydPetrotech Presenttaion- Punj Lloyd
Petrotech Presenttaion- Punj Lloyd
 
How to setup and lead a successfully PMO
How to setup and lead a successfully PMOHow to setup and lead a successfully PMO
How to setup and lead a successfully PMO
 
Resume - Mark Torabinejad-23 June 2016
Resume - Mark Torabinejad-23 June 2016Resume - Mark Torabinejad-23 June 2016
Resume - Mark Torabinejad-23 June 2016
 

Recently uploaded

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

Project management in construction.

  • 1. Prepared By, Navneet Kumar Jha BITS ID : 2014HT74039 PROJECT MANAGEMENT IN CONSTRUCTION IMPROVING PROJECT PERFORMANCE
  • 2. INTRODUCTION • Objective for the presentation is to analyse the various factors in the project management in construction which lead to success and failure of the projects. • Learning from projects by understanding the essential elements of the project management (e.g. the Leadership Role of the Project Manager, Project Planning, Risk Management) , Analysis of project management done in various projects worldwide
  • 3. what is project management ?? • Project management is the application of knowledge , skills , tools and techniques to project activities in order to meet or exceed stakeholders needs and expectations from a project. • Need of balancing competing demands among scope , time , cost , quality , stakeholders with different needs and expectations and identified (needs) and unidentified requirements (expectations).
  • 4. ATTRIBUTES TO PROJECT MANAGEMENT • Project Managers. • Determining Project Objectives. • Managing Budget and Resources. • Reporting Progress. • Evaluating efficiency and effectiveness.
  • 5. RESPONSIBILITIES OF PROJECT MANAGER • Planning thoroughly through all the aspects of the project. • Controlling the manpower of the organization. • Optimise the technical versus cost trade offs in specific areas where optimisation is required. • Monitor performance , costs and efficiency of all elements of the project. • Completing the project on schedule and within costs .
  • 6. COMPETENCIES OF A PROJECT MANAGER Planning / organizing . Controlling. Stress Tolerance. End customer orientation. Personal Chemistry. Analytical skills. Leadership Quality / Managing people. Managing performance. Sensitivity.
  • 7. WHY DO PROJECTS GO WRONG ?? • Project goals are not clearly defined. • Constraints on the completion of the project arising from the different objectives of Short time scale. Resource Availability. Quality factors Human factors.
  • 8. CONSTRAINTS OF PROJECT MANAGEMENT • Cost • Scope • Quality • Customer satisfaction. • Time. • Risk • Resources.
  • 9. PROJECT MANAGEMENT PROCESS • Project Initiation. • Project planning. • Project scheduling and execution. • Monitoring and control. • Close Out of the project.
  • 10. SUCCESSFUL PROJECTS CASE STUDIES • AL WAHDA MASTER DEVELOPMENT , ABU DHABI.  Vibrant bussiness and shopping destination.  EC Harris International Ltd. Was involved in every element from master planning of development to the concept development and upto realization stage. • Objectives of EC Harris international Limited.  Project Management gateway approach. (Design verification checks ,value engineering , Risk Management). Categorise roles , responsibilities , communication protocols.
  • 11. RESOURCES • Truly International Project Team. • Dynamic Team who were happy to multi task in their daily roles. • Proper Risk Management team. • Proper co-ordination among the team. CHALLENGES • Due to economic slowdown in 2008 , steel and cement prices rocketed and whose availability was un predictable. Proper early planning let the supply lines continue.
  • 12. AQUEDUCTS AND LARGE DIAMETER TRUNK MAINS CLEAN & MAINTAIN PROGRAMME, UNITED UTILITIES • OBJECTIVES :  Plan , design , develop and implement a major programme of inspection , maintenance and repairs on two main aqueducts. Clean and refurbish six large diameter trunk mains reducing levels of iron and Manganese. • RESOURCES : Huge exercise in logistics , resource health and safety planning. Project centric team members. Governance board was established to review the project status and risks.
  • 13. KEY CHALLENGES • Water supply interruption to the customers to be avoided. • Fresh approach for the company to project prioritisation, resource planning , risk management, integration and scheduling. • nature, scale and uncertainty of unforeseen events, such as extremes of weather, major bursts, and third party damage, and issues that required reactive maintenance put pressure on the overall annual budget and caused project priorities to be frequently re-assessed.
  • 14. SUCCESS ACHIEVED : • £8 million efficiency savings. • Improved customer service standards. • Better water quality. • Reduced health and safety risk to employees and third parties by upgraded access. • Improved structural integrity of the aqueducts. • Improved regional network response to incidents such as bursts, with faster diversions, and altered flow rates to minimise water loss . • Maintain customer supplies without major discolouration. • Delivered with no lost time accidents and no significant impact on customer levels of service.
  • 15. BUILDING BETTER COMMUNITIES: MANAGING RECONSTRUCTION AFTER THE INDIAN OCEAN TSUNAMI • A global business providing management and consultancy services to the property, transportation and infrastructure, environment and energy and management and industrial sectors, was called in by the Canadian Red Cross (CRC) to re-house more than 11,000 people made homeless by the tsunami in Aceh, Indonesia. • The company oversaw the reconstruction of 21 villages – 17 of which had to be relocated – and the design and rebuilding of nearly 4,000 flood and earthquake-resistant homes.
  • 16. CHALLENGES: • According to WSP the pressure to build, in the numbers covered by the project, in a variety of remote locations with many unknowns, coupled with a need to complete urgently, was ‘a challenge of a lifetime’. • When the company arrived in Aceh in mid- 2006, it found all contracts behind schedule, confused objectives and programmes . • No project management unit, poor availability of materials, difficult access because of flooding, damaged roads and bridges. • Disaffected communities who refused to take part in planning because previous promises had been broken.
  • 17. PROJECT SUCCESSES: • Relationships were forged with local communities using patience, listening skills, response to their preferences, and good communication including a poster that depicted the road to reconstruction. • Nearly 4,000 houses were built and handed over to beneficiaries across 21 villages in 2009 and positive feedback was received. • The government was appreciative and applauded CRC for delivering strong, robust durable houses amongst the highest quality standards in the relief effort.
  • 18. • WSP continued to maintain a presence for a year to ensure that, at least for some time after the houses had been handed over, professional and management capacity was available to iron out issues. • Build understanding and capacity about quality and safety from future hazards.
  • 19. DAWLISH SEA WALL EMERGENCY WORKS CHALLENGES • Nature’s unpredictability. • Managing the interface between six main contractors on a scheme with unclear scope and immense pressure to deliver as soon as possible. • To establish relationships with local people who had been evacuated and with Teignbridge District Council as well as managing the involvement of the Marine Management Organisation and Crown Estates to ensure necessary licenses were in place.
  • 20. • The importance of the work to the public and businesses was never under‐estimated. • Commit to a date in the first days as the scope was not only unclear but increasing all the time, yet people needed to know so they could make plans. • Issues with those living alongside the line not only being disturbed by the work but also impacted by the physical damage to their homes, land and property. • Need to manage their expectations of what the project team could deliver.
  • 21. SUCCESS ACHIEVED • The rail link to South and West Devon and Cornwall re‐ opened on time to an extremely ambitious programme, allowing Dawlish and beyond to be reconnected to their railway and the rest of the UK. • The team received good feedback from local councils and the public, including letters and cards of thanks from local residents. For the project team, the immediate success of achieving the goal has also led to long term networking and relationships, leading to opportunities for collaboration on future projects. • Prime Minister David Cameron, praised the ‘orange army’ of engineers as they have become known, for their “herculean effort” in completing the repairs.
  • 22. DELIVERY OF THE ROTARY WING STRATEGY 2009-2015, UK MINISTRY OF DEFENCE • CHALLENGES • New Wildcat and Chinook Mk6 helicopters were to be purchased while existing Puma, Apache, Chinook and Merlin helicopters required upgrading and modernising. • Investment was needed to ensure training aids such as flight simulators reflected the upgraded fleet while maximising training effect and efficiencies. • Revised support arrangements for each of the core future helicopters had to be implemented and full ownership of all Merlins was to be transferred to the Royal Navy.
  • 23. RESOURCES • Dedicated project teams were established to deliver defined elements and ensure that the transition to deliver the strategy was coherent with ‘business as usual’. • A strong project management culture was established within each team through a monthly review drumbeat and forward-looking metrics aimed at avoiding future pitfalls.
  • 24. RESULTS • Through the programme approach, five potent new helicopter capabilities have been delivered to the UK’s armed forces within the approved time and cost, while making substantial savings in supporting military equipment. • The £1 billion funding gap has been closed and £440 million has been saved from the forecast cost of supporting the fleet for the next five years without impacting upon military effectiveness.
  • 25. GREEN PARK STATION STEP-FREE ACCESS PROJECT, TRANSPORT FOR LONDON CHALLENGES • Despite the complexity, and a number of difficult issues to manage particularly early in the project, the project managers used multi-disciplinary design reviews, risk workshops and programme workshops to maintain the direction of the project and improve the quality of decision making. • Because of its duration, and the limited works that could be progressed until they were complete, the tunnelling works were on the critical path.
  • 26. RESULTS • The changes made by the project allowed Green Park Station to perform as promised during the London 2012 Olympics and contribute to making sure the Games were as accessible as possible. • The project was completed three months ahead of schedule and substantially under budget, without using any of the risk or contingency initially allowed. • All this has been achieved while maintaining the highest standards of safety through continuous improvement. As of June 2012, the project had undertaken more than 400,000 man-hours with zero lost-time injuries.
  • 27. THE CONSTRUCTION PROGRAMME FOR THE LONDON 2012 OLYMPIC AND PARALYMPIC GAMES, OLYMPIC DELIVERY AUTHORITY CHALLENGES • Huge levels of public interest in London 2012 . • ODA (Olympic Development Authority ) recognised the project could only be delivered in partnership and with the support of a large coalition of organisations, many of whom had differing interests. • Ensure complete alignment between internal and external objectives.
  • 28. SUCCESS • The ODA has successfully achieved its objectives, both for the delivery of the physical infrastructure of the Olympic Park, and also for significant achievements in its priority themes, such as health and safety and sustainability.
  • 29. POWERLINES UNDERGROUNDING PROJECT, LONDON 2012 KEY OBJECTIVES OF THE PROJECT • Deliver a quality project. , remove, mitigate and manage risk; ensure the safety and well being of all personnel and workers engaged on or affected by the project; demonstrate value for money; keep London and customer supplies ‘switched on’. SUCCESS • Teamwork and trust were absolutely key. All parties worked as one, focusing on the challenges in hand and buy-in to the common goal rather than on protecting contractual positions. The fact that individual success would only happen if everyone was successful was understood and drove positive behaviours (there were no contractual incentives to link these parties). Organisation and governance were recognised as key aspects to the successful delivery of the project.
  • 30. TRANSFORMING DUBLIN AIRPORT PROGRAMME, TURNER & TOWNSEND • CHALLENGES • There was the sheer scale of the job of transforming Dublin Airport. • Need to ensure that the airport stayed in full operation while work progressed – and that key matters such as safety and passenger wellbeing are not compromised. • Success • Turner & Townsend successfully met the needs of the client by implementing a programme management approach. • Resulted in the transformation of Dublin Airport into a 21st Century Gateway to Ireland on time and within budget. • Stakeholder feedback on the finished product has been extremely encouraging .
  • 31. WORLD’S MAJOR PROJECT FAILURE EXAMPLES • BRITISH PETROLEUM • Explosion cause the oil spill which was one of the worst ever oil disaster in the history of the modern world. • Reasons for Project Failure • Extreme geographic location • Weak risk management • Lack of timely decisions • Sluggish response in critical situation • Undermining the situation • Lack of planning
  • 32. CASE STUDY: THE MILLENNIUM DOME • Millennium Dome is a Dome shaped mega structure, built in the Greenwich peninsula in south east London which was later closed because it failed to attract the number of visitors which was expected to visit the place. Reasons for failure • Lack of vision. • Poor execution. • Lack of sufficient operational expertise. • Poor marketing strategies. • Financially mismanaged project. • Lack of contingency plan.
  • 33. RECOMMENDATIONS AFTER CASE STUDY: • Management structure to be properly structured. • Project costs • projects should only proceed if they are clear with full life cycle assessment cost of the project. • Risk Analysis. • Risk analysis of the project is necessary so that a project manager should understand the cost which could arise in the later stages of the project and prepare a plan for it.
  • 34. • Project Income. The project manager should keep in mind the uncertainties related to this type of income. This can only be done with the help of careful and practical assumptions. • Contingency planning should be there. • Proper financial management should be done prior to moving with the project further.
  • 35. CONCLUSISON • Project failure is preventable with good project planning. When a project starts to fail there are techniques to recognize and trained Project managers minimize the extend of project failure or recover the failed projects as early as possible. • Project manager needs to be trained in such techniques so that he/she not only recover the failed projects but also reduce the chances of failure.
  • 36. COLUMBIA SHUTTLE • Columbia Shuttle Disintegrates after re-entry into the earths atmosphere. Lessons learnt with respect to the columbia shuttle launch project management • “recency effect.” It occurs when decision makers rely on only the most recent information.
  • 37. • Conservatism A situation in which new information is ignored or given too little weight. • overconfidence. During the flight, engineers, concerned that the foam strike may have caused a problem, asked the Mission Management Team (MMT) to request satellite imagery of the spacecraft. Management, however, was apparently confident that there was no safety issue. • selective perception In which management of the shuttle program had shifted from an engineering focus to a managerial focus.
  • 38. HURRICANE KATRINA • On August 29, 2005 hurricane Katrina raced across the Gulf of Mexico and made landfall in New Orleans, Louisiana. When it was over, a category 5 storm had breached the levees, flooded eighty percent of the city, killed 1,500 people, and left over 80 billion in damages. It was the costliest natural disaster in US history. • What followed was a project failure of enormous proportions. It failed in planning, it failed in execution and it failed in meeting even the most basic needs of those caught in the middle of this tragic disaster.
  • 39. • Four project management failures stand out. • Communication • Selective Perception • Leadership • Difficult Relationships
  • 40. LESSONS LEARNT • We need to be careful in generalizing the project failure lessons that can be learned from a once-in-a-hundred-year tragedy, but the magnitude of the failure was so great that it becomes a caricature of what can go wrong in more conventional projects. • The more constituents involved, the greater will be the communication challenge. Unless managed effectively, far too much time can be devoted to resolving jurisdictional conflicts and not enough time on the real issues. Too many constituents can sabotage a project. • Be careful of selective perception. When it goes unchecked it can be effective in miminizing interruptions, but the consequnces of locking out new data can be disastrous. • Either clear leadership lines must be established, or a collaborative environment . similar to what can emerge in high performance teams must be created and managed. • • Difficult relationships must be addressed. Once they surface they are unlikely to go away.
  • 41. KEY REASONS OF PROJECT FAILURE • Lack of senior management. • Unclear project objectives. • Scope creep. • Gaps in communication. • Lack of visibility of all projects.
  • 42. CONCLUSION FROM DATA COLLECTION AND DATA ANALYSIS • PROJECT DELAYS IN CONSTRUCTION ARE DUE TO 1. Less number of labours against requirement. 2. Skill of labour is very poor or less. 3. Lack of project planning and scheduling by contractor. 4. Delay due to receiving permissions from government authorities. 5. Delay due to transporting material from supplier to site. 6. Complete absence of good site management and supervision by contractor. 7. Lacking of quality and quantity of work.