EMERGENT POWER DEVELOPMENT CO. LTD.
INSTALLATION OF 35MW GAS-POWERED ELECTRICITY PLANT
PROJECT INFORMATION
INCEPTION: July 2015
DESCRIPTION: Installation and operation of 15 Nos. 35MW electric plants in Lagos State
LOCATION: Various (Depending on allocation from Lagos State Government)
COST: $50m each (Total cost=$750m)
DURATION: 45 months from project inception.
OWNERSHIP: Public-Private Partnership (LASG 15%: Private Investors: 85%)
FINANCING: Equity & Debt
OFF-TAKERS: Eko DISCO and Ikeja DISCO
PROMOTERS: Emergent Power Development Co. Limited
PARTNERS: PowerCap Limited (Nigeria), Aldwych Capital Partners (USA), General Electric (USA),
Prometheus Renewable Energy Development Solutions Ltd. (Hungary),
KEY ACTIVITY FOCAL POINTS:
DEVELOPMENT MANAGEMENT
 Review any existing project documents, collection of project data, analyzing the different power generation options
 Establishment and utilization of new legal entity for the preparation of the program (if any)
 Preparation and maintenance of new website for existing or new project company
 Study the legislations related to the actual projects
 Establishment of government relations, networking
 Establishment of local private sector relations, networking
 Review, modification or preparation of conceptual studies for the different technology options
 Optimizing the technology on the basis of the available information, raw materials and the market demand of the
different potential end products.
 Setting the proper capacity of the plant.
 Selecting the optimal site
 Securing the necessary volume of fuels, energy sources on long term with contracts, concessions.
 Securing the guaranteed operation and maintenance structure during the lifetime of the project.
 Securing and negotiations of the Power Purchase Agreements
 Preparation of Preliminary and Detailed Business Plan
 Preparation of Pre-feasibility and Detailed Feasibility Studies for the different project options
PROJECT MANAGEMENT
 Setting the project implementation structure and methodology
 Setting the method for selecting the suppliers, procurement strategy
 Possibilities for Worldwide/EU/Local suppliers
 Setting up the Project organization
 Licensing, Permitting and Quality Assurance
 Preparation EPC bid packages, invitation, specifications
 Evaluating the received bids, especially
 Checking the bid for completeness of the information requested
 Checking the scope and limits of supply of services and interfaces
 Evaluating the technical features of the equipment and structures and the adequacy of the services
 Evaluating the prices, the completeness of the proposed services
 Preparing questionnaires, evaluation reports (including the identification of problem areas) and technical
documents.
 Proposing for the award of the contract, negotiations and advise during the contract signing process
 Preparing the project schedule and controlling deviations from it
 Ensuring project definition in the form of project requirements and specifications and controlling changes
 Expediting engineering and subcontractor deliveries
 Controlling project interfaces inside and outside the organization in charge of the project
 Controlling EPC contract compliance, progress
 Ensuring timely and proper preparation of licensing documentation and applications as well as adherence to compliance
procedures
 Providing problem solving leadership and assistance where needed, and establishing a project risk analysis and risk
reduction program
 Monitoring and controlling costs
 Ensuring progress payments and preparing claims for justified price changes
 Ensuring quality assurance and control
 Providing assistance, proper interfacing and transfer of information within the different actor at the site
 Reporting progress, reports to the lenders, owners
FUNDING
 Setting the most optimal ownership and financing structure
 Preparation and submission of licensing or concession documents, bids for individual projects
 Preparation of Preliminary or Detailed Investor’s Information Memorandum for individual projects
 Distribution of the Information Memorandums, invitation of potential investors, advisory services during the
negotiations
 Preparation of Grant applications, submission and follow up, supporting during award and utilization
 Financial advise during the loan agreements preparation, negotiations

More Related Content

Viewers also liked

7 Questions About Employee Motivation
7 Questions About Employee Motivation7 Questions About Employee Motivation
7 Questions About Employee Motivationjtaylorireland
 
Setting And Reaching Goals
Setting And Reaching GoalsSetting And Reaching Goals
Setting And Reaching Goalsssimacek
 
Goal Setting and Goal Achieving Is A Lawful Process
Goal Setting and Goal Achieving Is A Lawful ProcessGoal Setting and Goal Achieving Is A Lawful Process
Goal Setting and Goal Achieving Is A Lawful ProcessRobert C. Hinds
 
7 Keys To Goal Setting Success
7 Keys To Goal Setting Success7 Keys To Goal Setting Success
7 Keys To Goal Setting SuccessMohammed Algarni
 
5 star time mgt and goal setting workshop
5 star time mgt and goal setting workshop5 star time mgt and goal setting workshop
5 star time mgt and goal setting workshopPro356 Consulting
 
Good Habits are Easy to Make!
Good Habits are Easy to Make!Good Habits are Easy to Make!
Good Habits are Easy to Make!Jim Jubelirer
 
3600planning
3600planning3600planning
3600planningknksmart
 
Get your Business Organised seminar
Get your Business Organised seminarGet your Business Organised seminar
Get your Business Organised seminarBusinessVictoria
 
Say Goodbye to Fear Forever!
Say Goodbye to Fear Forever!Say Goodbye to Fear Forever!
Say Goodbye to Fear Forever!Jim Jubelirer
 
7 Questions You Must Ask When Setting Goals
7 Questions You Must Ask When Setting Goals7 Questions You Must Ask When Setting Goals
7 Questions You Must Ask When Setting GoalsWeekdone.com
 
Greatest Coach Ever!
Greatest Coach Ever!Greatest Coach Ever!
Greatest Coach Ever!Jim Jubelirer
 
Winning Personality
Winning PersonalityWinning Personality
Winning PersonalityMMMTS
 
12 Time Management Techniques
12 Time Management Techniques12 Time Management Techniques
12 Time Management TechniquesWeekdone.com
 
Discover the Power of WHY
Discover the Power of WHYDiscover the Power of WHY
Discover the Power of WHYJim Jubelirer
 

Viewers also liked (20)

7 Questions About Employee Motivation
7 Questions About Employee Motivation7 Questions About Employee Motivation
7 Questions About Employee Motivation
 
Setting And Reaching Goals
Setting And Reaching GoalsSetting And Reaching Goals
Setting And Reaching Goals
 
Goal Setting and Goal Achieving Is A Lawful Process
Goal Setting and Goal Achieving Is A Lawful ProcessGoal Setting and Goal Achieving Is A Lawful Process
Goal Setting and Goal Achieving Is A Lawful Process
 
Who moved-my-cheese131
Who moved-my-cheese131Who moved-my-cheese131
Who moved-my-cheese131
 
7 Keys To Goal Setting Success
7 Keys To Goal Setting Success7 Keys To Goal Setting Success
7 Keys To Goal Setting Success
 
Time management
Time managementTime management
Time management
 
5 star time mgt and goal setting workshop
5 star time mgt and goal setting workshop5 star time mgt and goal setting workshop
5 star time mgt and goal setting workshop
 
Good Habits are Easy to Make!
Good Habits are Easy to Make!Good Habits are Easy to Make!
Good Habits are Easy to Make!
 
Analyze Your Business
Analyze Your BusinessAnalyze Your Business
Analyze Your Business
 
Improving the Time Management Skills
Improving the Time Management  SkillsImproving the Time Management  Skills
Improving the Time Management Skills
 
3600planning
3600planning3600planning
3600planning
 
Get your Business Organised seminar
Get your Business Organised seminarGet your Business Organised seminar
Get your Business Organised seminar
 
Say Goodbye to Fear Forever!
Say Goodbye to Fear Forever!Say Goodbye to Fear Forever!
Say Goodbye to Fear Forever!
 
7 Questions You Must Ask When Setting Goals
7 Questions You Must Ask When Setting Goals7 Questions You Must Ask When Setting Goals
7 Questions You Must Ask When Setting Goals
 
Greatest Coach Ever!
Greatest Coach Ever!Greatest Coach Ever!
Greatest Coach Ever!
 
Time Management
Time ManagementTime Management
Time Management
 
Winning Personality
Winning PersonalityWinning Personality
Winning Personality
 
12 Time Management Techniques
12 Time Management Techniques12 Time Management Techniques
12 Time Management Techniques
 
Discover the Power of WHY
Discover the Power of WHYDiscover the Power of WHY
Discover the Power of WHY
 
Goal Setting
Goal SettingGoal Setting
Goal Setting
 

Similar to EMERGENT POWER DEVELOPMENT CO

Similar to EMERGENT POWER DEVELOPMENT CO (20)

Kartik CV
Kartik CVKartik CV
Kartik CV
 
151213CS2426993.2 (1)
151213CS2426993.2 (1)151213CS2426993.2 (1)
151213CS2426993.2 (1)
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Detailed project report
Detailed project reportDetailed project report
Detailed project report
 
CV
CVCV
CV
 
Preparation of project reports and appraisal of projects
Preparation of project reports and appraisal of projectsPreparation of project reports and appraisal of projects
Preparation of project reports and appraisal of projects
 
Frances L. Vessell Resume 01.26.2017
Frances L. Vessell Resume 01.26.2017Frances L. Vessell Resume 01.26.2017
Frances L. Vessell Resume 01.26.2017
 
Saptak_CV
Saptak_CVSaptak_CV
Saptak_CV
 
CV
CVCV
CV
 
Senior Subcontracts officer-Mehadi
Senior Subcontracts officer-MehadiSenior Subcontracts officer-Mehadi
Senior Subcontracts officer-Mehadi
 
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEERRESUME FOR PROCUREMENT & CONTRACTS ENGINEER
RESUME FOR PROCUREMENT & CONTRACTS ENGINEER
 
PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
CV_ S Arunkumar -Procurement And Sub Contract
CV_ S  Arunkumar -Procurement And Sub ContractCV_ S  Arunkumar -Procurement And Sub Contract
CV_ S Arunkumar -Procurement And Sub Contract
 
CV_Gaurav Mohite
CV_Gaurav MohiteCV_Gaurav Mohite
CV_Gaurav Mohite
 
Harish Resume.pdf
Harish Resume.pdfHarish Resume.pdf
Harish Resume.pdf
 
JMC Resume V13
JMC Resume V13JMC Resume V13
JMC Resume V13
 
Project Planning & Control Engineer
Project Planning & Control EngineerProject Planning & Control Engineer
Project Planning & Control Engineer
 
Vikram Prabhakar Updated Resume
Vikram Prabhakar Updated ResumeVikram Prabhakar Updated Resume
Vikram Prabhakar Updated Resume
 
Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016
 
Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016Resume Short Version with Project List 07252016
Resume Short Version with Project List 07252016
 

EMERGENT POWER DEVELOPMENT CO

  • 1. EMERGENT POWER DEVELOPMENT CO. LTD. INSTALLATION OF 35MW GAS-POWERED ELECTRICITY PLANT PROJECT INFORMATION INCEPTION: July 2015 DESCRIPTION: Installation and operation of 15 Nos. 35MW electric plants in Lagos State LOCATION: Various (Depending on allocation from Lagos State Government) COST: $50m each (Total cost=$750m) DURATION: 45 months from project inception. OWNERSHIP: Public-Private Partnership (LASG 15%: Private Investors: 85%) FINANCING: Equity & Debt OFF-TAKERS: Eko DISCO and Ikeja DISCO PROMOTERS: Emergent Power Development Co. Limited PARTNERS: PowerCap Limited (Nigeria), Aldwych Capital Partners (USA), General Electric (USA), Prometheus Renewable Energy Development Solutions Ltd. (Hungary),
  • 2. KEY ACTIVITY FOCAL POINTS: DEVELOPMENT MANAGEMENT  Review any existing project documents, collection of project data, analyzing the different power generation options  Establishment and utilization of new legal entity for the preparation of the program (if any)  Preparation and maintenance of new website for existing or new project company  Study the legislations related to the actual projects  Establishment of government relations, networking  Establishment of local private sector relations, networking  Review, modification or preparation of conceptual studies for the different technology options  Optimizing the technology on the basis of the available information, raw materials and the market demand of the different potential end products.  Setting the proper capacity of the plant.  Selecting the optimal site  Securing the necessary volume of fuels, energy sources on long term with contracts, concessions.  Securing the guaranteed operation and maintenance structure during the lifetime of the project.  Securing and negotiations of the Power Purchase Agreements  Preparation of Preliminary and Detailed Business Plan  Preparation of Pre-feasibility and Detailed Feasibility Studies for the different project options
  • 3. PROJECT MANAGEMENT  Setting the project implementation structure and methodology  Setting the method for selecting the suppliers, procurement strategy  Possibilities for Worldwide/EU/Local suppliers  Setting up the Project organization  Licensing, Permitting and Quality Assurance  Preparation EPC bid packages, invitation, specifications  Evaluating the received bids, especially  Checking the bid for completeness of the information requested  Checking the scope and limits of supply of services and interfaces  Evaluating the technical features of the equipment and structures and the adequacy of the services  Evaluating the prices, the completeness of the proposed services  Preparing questionnaires, evaluation reports (including the identification of problem areas) and technical documents.  Proposing for the award of the contract, negotiations and advise during the contract signing process  Preparing the project schedule and controlling deviations from it  Ensuring project definition in the form of project requirements and specifications and controlling changes  Expediting engineering and subcontractor deliveries  Controlling project interfaces inside and outside the organization in charge of the project  Controlling EPC contract compliance, progress  Ensuring timely and proper preparation of licensing documentation and applications as well as adherence to compliance procedures  Providing problem solving leadership and assistance where needed, and establishing a project risk analysis and risk reduction program  Monitoring and controlling costs  Ensuring progress payments and preparing claims for justified price changes  Ensuring quality assurance and control  Providing assistance, proper interfacing and transfer of information within the different actor at the site  Reporting progress, reports to the lenders, owners FUNDING  Setting the most optimal ownership and financing structure  Preparation and submission of licensing or concession documents, bids for individual projects  Preparation of Preliminary or Detailed Investor’s Information Memorandum for individual projects  Distribution of the Information Memorandums, invitation of potential investors, advisory services during the negotiations  Preparation of Grant applications, submission and follow up, supporting during award and utilization  Financial advise during the loan agreements preparation, negotiations