SlideShare a Scribd company logo
1 of 50
Download to read offline
Connoisseur Solutions
Project Cost Management
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Project Cost Management
Project Cost Management includes the processes involved in estimating,
budgeting, and controlling costs so that the project can be completed
within the approved budget.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Cost Management Processes
Process Process Group
Plan Cost Management Planning
Estimate Costs Planning
Determine Budget Planning
Control Costs Monitoring and Controlling
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs
Estimate Costs is the process of developing an approximation of the
monetary resources needed to complete project activities. The table below
shows five different types of estimates that can be used based on the need.
Estimate Type Range
Order of Magnitude Estimates -25% to +75%
Conceptual Estimate -30% to +50%
Preliminary Estimate -20% to +30%
Definitive Estimate -15% to +20%
Control Estimate -10% to +15%
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
 Direct Cost- Any cost that is identified specifically with a particular final
cost objective.
 Indirect Cost- Any cost not directly identified with a single, final cost
objective (more than one project)
 Fixed Cost - Periodic charge that does not vary with business volume
 Variable Cost - Cost that fluctuates based on the business volume
 Opportunity Cost: When there is a decision to be made between two
opportunities, the opportunity cost is the value / money forgone for the not
doing the project.
Types of Cost
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
• Lifecycle Costing: Takes into account cost of development of a project
and also the cost of supporting during the lifecycle.
• Sunk Cost - Cost already incurred which cannot be recovered regardless
of future events
Types of Cost
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Cost Management
The process that establishes the policies, procedures , and
documentation for planning , managing , expending , and
controlling project costs.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Cost Management
Inputs Tools and Techniques Outputs
 Project Management
Plan
 Project Charter
Enterprise
Environmental Factors
 Organizational Process
Assets
 Expert Judgment
 Analytical Techniques
 Meetings
 Cost Management
Plan
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Cost Management- Inputs
Project Management Plan component that is important for this process are
primarily the scope and cost baselines.
Project Charter provides the summary budget from which the detailed project costs
are developed . It also defines the project approval requirements that will influence
the management of the project costs.
Enterprise Environmental Factors include factors such as Organization
structure/culture, Market conditions, currency exchange rates (for project sourced
from more than one country) that influence the project cost.
Organizational Process Assets include financial control procedures , historical
information . Existing formal and informal cost estimating and budgeting related
policies, procedures and guidelines.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Cost Management- Tools and Techniques
Expert Judgment – Guided by historical information, provides valuable insight about
the environment and information from prior similar projects. Judgment based upon
expertise in an application area, knowledge area , discipline, industry can be useful in
this process.
Analytical Techniques – Some of the techniques payback period, return on
investment, internal rate of return, discounted cash flow and net present value can be
useful in this process
Meetings - Project teams may hold meetings planning meetings to develop the cost
management plan. These meetings may include, project sponsor, project manager,
selected team members , selected stakeholders, anyone with responsibility for project
costs.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Cost Management- Outputs
Cost Management Plan – is a component of the project management plan and
describes how the project costs will be planned, structured , and controlled. The cost
management plan can establish the following.
 Units of measure - Each unit of measure for each resource.
 Level of precision – The degree to which activity cost estimates will be rounded up
or down.
 Level of accuracy - The acceptable range (e.g. +_ 100%) used in determining
realistic activity cost estimates is specified , may include an amount for contingencies.
 Control threshold – Variance threshold for monitoring cost performance may be
specified to indicate an agreed – upon amount of variation to be allowed before some
action need to be taken.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Plan Cost Management- Outputs
The cost management plan also contains.
 Rules of performance measurement – Earned value management (EVM) rules of
performance measurement are set. For example
 Define the points in the WBS at which measurement of control accounts will be
performed
 Establish the earned value measurement techniques (e.g. weighted
milestones, fixed formula, percent complete, etc) to be used and
 Specify tracking methodologies and the earned value management
computation equations for calculating projected estimate at completion (EAC)
forecasts to provide a validity check on the bottom-up EAC
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Cost
pankaj sharma, 9810996356
Estimate cost is the process of developing an approximation of the
monetary resources needed to complete project activities. The key
benefit of this process is that it determines the amount of cost
required to complete project work.
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs
Inputs Tools and Techniques Outputs
 Cost Management Plan
 Human Resource
Management Plan
 Scope baseline
 Project Schedule
 Risk Register
 Enterprise
Environmental Factors
 Organizational Process
Assets
 Expert Judgment
 Analogous Estimating
 Parametric estimating
 Bottom-up estimating
 Three-point estimates
 Reserve Analysis
 Cost of Quality
 Project management
estimating software
 Vendor bid analysis
 Group decision – making
techniques
 Activity Cost
estimates
 Basis of estimates
 Project document
updates
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs - Inputs
Cost management plan – The cost management plan defines how project costs will
be managed and controlled . It includes the method used and the level of accuracy
required to estimate activity cost.
Human Resource Plan provides detail on Project staffing attributes, personnel rates,
and related rewards/recognition, these are necessary components for developing the
project cost estimates.
Scope baseline include inputs from scope statement, Work Breakdown Structure and
WBS dictionary.
Project Schedule provides detail on the type and quantity of resources and the
amount of time which those resources are applied to complete the work of the project,
all these factors directly impact the cost
Risk Register provides input related to costs associated with risk response
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs - Inputs
Enterprise Environmental Factors include availability of resources, published
commercial information
Organizational Process Assets – include cost estimating policies, historical
information, cost estimating templates and lesson learned
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs -Tools and Techniques
Expert Judgment guided by historical information, provides valuable
insight about the environment and information from prior similar projects. Expert
judgment can also be used to determine whether to combine methods of estimating and
how to reconcile differences between them.
Analogous Estimating relies on historical information (Previous projects executed by
the organization) to predict the cost of current project. This is a top-down approach is
good for fast estimates to get a general idea of what the project may cost. The accuracy
depends upon how similar the two projects actually are.
Parametric estimating uses a mathematical model based on known parameters to
predict the cost of a Project. A parameter can be cost per unit, cost per cubic yard etc.
Two Parametric estimating techniques are Regression Analysis and Leaning curve.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs -Tools and Techniques
Bottom-up estimating produces a separate estimate for each scheduled activity. The
detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting
and tracking purposes. The cost and accuracy of bottom-up cost estimating is typically
influenced by the size and complexity of the individual activity or work package.
Three-point estimates concept originated with the program evaluation and review
technique (PERT). PERT uses three estimates to define an approximate range for an
activity’s cost:
Triangular Distribution
Estimated Cost = Optimistic + Most Likely + Pessimistic)/ 3
Beta Distribution
ESTIMATED COST = (Optimistic + 4*(Most Likely) + Pessimistic) / 6
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs -Tools and Techniques
Reserve Analysis adds reserve amount (Contingency) to the cost. This is done to take
care of uncertainties in the project.
Cost of Quality includes assumptions related to Cost of Quality
Project management software is helpful in performing calculations, Organizing and
storing large amount of information needed for preparing cost estimates and for
reporting purpose
Vendor bid analysis may include analysis of what the project should cost, based on the
responsive bids from qualified vendors.
Group Decision Making Techniques Team – based approaches , such as
brainstorming, the Delphi or nominal group techniques, are used for engaging team
members to improve estimate accuracy and commitment to the emerging estimates.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Estimate Costs - Outputs
Activity Cost estimates details how much it would cost to complete each schedule
activity on the project
Basis of estimates include supporting documentation of the cost estimates and it
may include documentation of the basis of estimates , documentation of all
assumptions made , documentation of any known constraint , indication of the range
of possible estimates and indication of the confidence level of the final estimates
Project document updates include project risk register and cost management plan
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Revise Tools to Estimate Cost
Exercise : Estimate Cost
1. You figure out a best case scenario and , a likely scenario and a worst
case scenario. Then you use a formula to come up with an expected cost
for the project. The tool used by you is ________
2. John creates a document with all the historical information from similar
project he had done in past and also takes input from a contractor who
provides his input. The tool used by John is_________
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Revise Tools to Estimate Cost
Answers to Exercise : Estimate Cost
1. You figure figures out a best case scenario and , a likely scenario and a
worst case scenario. Then you use a formula to come up with an
expected cost for the project. The tool used by you is Three-point
estimate
2. John creates a document with all the historical information from similar
project he had done in past and also takes input from a contractor who
provides his input. The tool used by John is Expert Judgment
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Determine Budget
Determine Budget is the process of aggregating the estimated costs of individual
activities or work packages to establish an authorized cost baseline. This baseline
includes all authorized budgets, but excludes management reserves.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Determine Budget
Inputs Tools and Techniques Outputs
 Cost management
plan
Activity cost estimates
 Basis of estimate
 Scope baseline
 Project Schedule
 Resource Calendars
 Risk register
 Agreements
 Organizational Process
Assets
 Cost Aggregation
 Reserve Analysis
 Expert Judgment
 Historical relationship
 Funding limit reconciliation
 Cost baseline
 Project funding
requirements
 Project document
updates
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Cost Management Plan - describes how the project costs will be managed and
controlled
Scope baseline refers to collection of approved project scope statement and its
associated WBS and WBS dictionary.
Activity cost estimates of a work package is a summation of the activity cost
estimates of activities under the work package
Basis of estimate includes supporting detail for cost estimates contained in the basis
for estimates should specify any basic assumptions
Project Schedule helps in mapping the cost back to time for planning purpose
Determine Budget - Inputs
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Resource Calendars along with Project schedule will help plan for when the costs will
be incurred
Agreements Applicable agreement information and costs relating to products,
services or results that have been or will be purchased are included when determining
the budget.
Organizational Process Assets include cost budgeting policies procedures ,
guidelines and reporting method
Determine Budget - Inputs
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Determine Budget – Tools and Techniques
Cost Aggregation involves aggregating the costs of individual activities to work
packages that are further aggregated to higher levels of WBS and finally into the
project cost
Reserve Analysis include contingency reserve and management reserves for the
project. Contingency reserves are allowances for response plan strategized for the
identified risks. These are also known as “known unknowns” . Management reserves
are allowance for unplanned changes to thee project scope and cost. The are also
known as “unknown unknowns”. Reserves are not the part of the project cost baseline.
Expert Judgment can be taken from experienced consultant in the project application
area. This can be from an internal organizational resource or external sources
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Determine Budget – Tools and Techniques
Historical relationship result in parametric estimates or analogous estimates that
involve parameter to develop mathematical models to predict total project costs.
Funding limit reconciliation refers to reconciliation of planned spending with the
funding limit
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Determine Budget – Outputs
Cost performance baseline is an authorized time-phased budget at completion
(BAC) used to measure, monitor, and control overall cost performance on the project.
It is developed as a summation of the approved budgets by time period and is
typically displayed in the form of an S-curve, as is illustrated in Figure below
(Reference PMBOK 4th edition). In the earned value management technique the cost
performance baseline is referred to as the performance measurement baseline (PMB).
Reference PMBOK 5th Edition
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Determine Budget – Outputs
Project funding requirements are derived from cost baselines. Total funding
requirement is sum of cost baseline and management reserve.
Project document updates include updates to risk register, cost estimates and
project schedule
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Project Budget Components
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Revise Tools to Determine Budget
Exercise 2: Determine Budget
Monika reads a newspaper article that says there has been sharp increase in steel
cost recently. She knows this was not in her contractor’s original plan and decides to
put a few hundred dollars aside to deal with the price hike if it should happen. The
tool used by Monika is
• Parametric estimating
• Reserve analysis
• Cost aggregation
• Fund Limit Reconciliation
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Revise Tools to Determine Budget
Answers to Exercise 2: Determine Budget
Monika reads a newspaper article that says there has been sharp increase in steel
cost recently. She knows this was not in her contractor’s original plan and decides to
put a few hundred dollars aside to deal with the price hike if it should happen. The
tool used by Monika is
• Parametric estimating
• Reserve analysis
• Cost aggregation
• Fund Limit Reconciliation
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs
Control Costs is the process of monitoring the status of the project
to update the project budget and managing changes to the cost
baseline.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs
Inputs Tools and Techniques Outputs
 Project management
plan
 Project Funding
Requirements
 Work Performance
data
 Organizational Process
Assets
□ Earned value management
□ Forecasting
□ To-complete performance
index TCPI
□ Performance reviews
□ Project management software
□ Reserve analysis
 Work performance
Information
 Cost forecasts
 Change Requests
 Project
management plan
updates
 Project document
updates
 Organizational
Process assets
updates
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Project Management Plan contains Cost management plan and Cost performance
Baseline, these are helpful in controlling the cost.
Project Funding Requirements As explained earlier include projected expenditures
plus anticipated liabilities
Work Performance Data provides information on the status and cost of project
activities and ensures that the project goals and objectives are met as per the project
management plan
Organizational Process Assets that can influence this process include cost
budgeting policies, procedures, guidelines , cost budgeting tools and reporting
methods
Control Costs - Inputs
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs – Tools and Techniques
Earned value management is used to measure the performance of the project, It
integrates project scope, cost, and schedule measures to help the project management
team assess and measure project performance and progress. The EVM technique
involves evaluating the planned value , Earned Value and the Actual cost for each
schedule activity , work package or control account.
1. Planned Value (PV) is the authorized budget assigned to the scheduled work to be
accomplished for a schedule activity or work breakdown structure component. It is
also known as Budgeted Cost of Work Scheduled (BCWS)
2. Earned Value (EV) is the value of work performed expressed in terms of the
approved budget assigned to that work for a schedule activity or a WBS
component. It is also known as Budgeted cost of Work Performed (BCWP)
3. Actual Cost (AC) is the total cost actually incurred and recorded in accomplishing
work performed for an activity or work breakdown structure component.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs – Tools and Techniques
Variance Analysis helps in analyzing the performance of the project vis-à-vis cost
and schedule baselines
Schedule Variance (SV) is a measure of schedule performance on a project.
It is equal to the earned value (EV) minus the planned value (PV). SV= EV-PV.
Cost variance (CV) is a measure of cost performance on a project. It is equal
to the earned value (EV) minus the actual costs (AC). CV = EV-AC
Schedule performance Index (SPI) in addition to project status is used to predict
the completion date. SPI = EV/PV
Cost Performance Index (CPI) measures the cost efficiency for the work completed,
it is the ration of EV to AC. CPI = EV/AC.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs – Tools and Techniques
Forecasting Techniques are used to calculate Estimate at completion (EAC) and
Estimate to complete (ETC).
EAC = AC + ETC
EAC forecast for ETC work performed at the budgeted rate
EAC = AC + BAC – EV
EAC forecast for ETC work performed at the present CPI
EAC = BAC / cumulative CPI
EAC forecast for ETC work considering both SPI and CPI factors.
AC + [(BAC – EV) / (cumulative CPI x cumulative SPI)].
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs – Tools and Techniques
To-complete performance index (TCPI) is the calculated projection of cost
performance that must be achieved on the remaining work to meet a specified
management goal, such as the BAC or the EAC.
TCPI based on the BAC: Work Remaining (BAC – EV) / Fund Remaining (BAC – AC).
TCPI based on EAC : (BAC-EV)/(EAC-AC)
Performance reviews involves following three types of analysis
1. Variance Analysis compares actual project performance to planned or expected
performance. Cost and schedule variances are the most frequently analyzed.
2. Trend Analysis examines project performance over time to determine if
performance is improving or deteriorating.
3. Earned value management compares the baseline plan to actual schedule and
cost performance.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs – Tools and Techniques
Project management software is often used to monitor the three EVM dimensions
(PV, EV, and AC), to display graphical trends, and to forecast a range of possible final
project results.
Reserve Analysis – During cost control, reserve analysis is used to monitor the status
of contingency and management reserves for the project to determine if these reserves
are still needed or if additional reserves need to be requested.
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs – Outputs
Work Performance Information includes the calculated CV, SV, CPI, and SPI
values for WBS components, in particular the work packages.
Cost Forecasts includes a calculated EAC value or a bottom-up EAC value.
Organizational Process Assets Updates include Causes of variances, Corrective
action chosen and the reasons, and Other types of lessons learned from project cost
control.
Change Requests include change request to the cost performance baseline
or other components of the project management plan. Change requests can include
preventive or corrective actions and are processed for review and disposition through
the Perform Integrated Change Control process
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Control Costs – Outputs
Project Management Plan Updates Elements of the project management plan that
may be updated include Cost performance baseline, Cost management plan.
Project Documents Updates include updates to cost estimates, basis of
Estimates
Organizational Process Assets Updates
Organizational Process Assets that may be updated include, but are not limited to :
 Cause of variances
 Corrective action choosen and the reasons
 Financial databases
 Other types of lesson learned from project cost control
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Practice Earned Value Formulae
Exercise 1 : EVM
Your current project is an $800,000 software development effort, with
two teams of programmers that will work for six months, at a total of
10,000 hours. According to the project schedule your team should be
done with 38% of the work. You find that the project is currently 40%
complete. You have spent 50% of the budget so far. Calculate the
following
1. BAC
2. EV, PV
3. SV, CV
4. SPI, CPI
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Practice Earned Value Formulae
Answer to Exercise - 1 : EVM
1. BAC = $ 800,000, AC = $ 400,000
2. PV = $ 80,000 * 38 / 100 = $ 304,000
EV = $ 80,000 * 40 / 100 = $ 320,000
3. SV = EV – PV = $ 16,000
CV = EV – AC = - $ 80,000
4. SPI = EV / PV = 1.05
CPI = EV / AC = 0.8
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Practice Earned Value Formulae
Exercise – 2 : EVM
You’re managing a highway construction project. Your total budget is
$650,000, and there are a total of 7,500 hours of work scheduled on
the project. You check with your accounting department, and they tell
you that you’ve spent a total of $400,000. According to the schedule,
your crew should have worked 4,500 hours, but your foreman says
that the crew was allowed to work some overtime, and they’ve
actually put in 5,100 hours of work. Based on this Calculate the
following Earned Value numbers:
PV =
EV =
CV =
BAC =
AC =
SV =
SPI = , CPI =
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Practice Earned Value Formulae
Answer to Exercise - 2 : EVM
BAC = $ 650,000
AC = $ 400,000
PV = 650,000 x 60% = $390,000
EV = 650,000 x 68% = $ 442,000
CV =442,000 – 400,000 = $42,000
SV = $ 52,000
SPI = 1.13 , CPI = 1.11
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Practice Earned Value Formulae
Exercise - 3 : EVM
It’s nine months into your project. The total budget for your project is
$4,200,000. You’ve spent $1,650,000 so far, and you’ve got a CPI of
.875. Use the Earned Value Management formulas from forecasting to
figure out where things stand.
Find the following
EAC =
ETC =
VAC =
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
Practice Earned Value Formulae
Answer to Exercise - 3 : EVM
EAC = $ 4,200,000 / 0.875 = $ 4,800,000
ETC = $ 4,800,000 – $ 1,650,000 = $ 3, 150,000
VAC = $ 4,200,000 – $ 4,800,000 = $ 600,000
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356
Connoisseur Solutions
QUIZ !
pankaj sharma, 9810996356
Pankaj Sharma - Mobile No -919810996356

More Related Content

What's hot

Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOKArief Rahmana
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Scheduleshofiulalom
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaJoshua Render
 
Project Charter
Project CharterProject Charter
Project CharterReema
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementWaleed Elnaggar
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Agus Suhanto
 
Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5pankajsh10
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control ProcurementsDavidMcLachlan1
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and controlDr.R. SELVAM
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesAnand Bobade
 

What's hot (20)

Project Quality Management - PMBOK
Project Quality Management - PMBOKProject Quality Management - PMBOK
Project Quality Management - PMBOK
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
Project cost management
Project cost managementProject cost management
Project cost management
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
Project Charter
Project CharterProject Charter
Project Charter
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Project Quality Management - PMBOK6
Project Quality Management - PMBOK6Project Quality Management - PMBOK6
Project Quality Management - PMBOK6
 
Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5Project Procurement Management PMBOK 5
Project Procurement Management PMBOK 5
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
12.3 Control Procurements
12.3 Control Procurements12.3 Control Procurements
12.3 Control Procurements
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
project management (10).pptx
project management (10).pptxproject management (10).pptx
project management (10).pptx
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and control
 
PMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management ProcessesPMP Chap 3 - Project Management Processes
PMP Chap 3 - Project Management Processes
 

Viewers also liked

Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5pankajsh10
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Managementpankajsh10
 
Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)pankajsh10
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Editionpankajsh10
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Editionpankajsh10
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 
ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!尚 鈴木
 
ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!Ayako Togaeri
 
PMBOKで学ぶプロジェクトマネジメントの基礎
PMBOKで学ぶプロジェクトマネジメントの基礎PMBOKで学ぶプロジェクトマネジメントの基礎
PMBOKで学ぶプロジェクトマネジメントの基礎Hiroyuki Tanaka
 
初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門尚 鈴木
 
すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方Eisuke Sugitani
 
Jenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテストJenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテストHiroyuki Tanaka
 
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジTrainocate Japan, Ltd.
 
よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02minamo
 
プロジェクト見える化計画 Web
プロジェクト見える化計画 Webプロジェクト見える化計画 Web
プロジェクト見える化計画 Webminamo
 
Scrum始めました
Scrum始めましたScrum始めました
Scrum始めましたminamo
 
統計的品質管理の功罪
統計的品質管理の功罪統計的品質管理の功罪
統計的品質管理の功罪工 久納
 
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAAJenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAAkyon mm
 

Viewers also liked (20)

Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)Project communications management (PMBOK 5th Edition)
Project communications management (PMBOK 5th Edition)
 
Project Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th EditionProject Quality Management - PMBOK 5th Edition
Project Quality Management - PMBOK 5th Edition
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 
9. project procurement management
9. project procurement management9. project procurement management
9. project procurement management
 
PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP
PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACPPMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP
PMP PPTs PMBOK 5th Edition - Author Pankaj Sharma, PMP,PMI-ACP
 
ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!ウォーターフォールでカンバンやってみた!
ウォーターフォールでカンバンやってみた!
 
ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!ようこそ!“プロジェクトマネジメント保健室”へ!
ようこそ!“プロジェクトマネジメント保健室”へ!
 
PMBOKで学ぶプロジェクトマネジメントの基礎
PMBOKで学ぶプロジェクトマネジメントの基礎PMBOKで学ぶプロジェクトマネジメントの基礎
PMBOKで学ぶプロジェクトマネジメントの基礎
 
初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門初めての人の為のプロジェクトマネジメント入門
初めての人の為のプロジェクトマネジメント入門
 
すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方すぐに分かる!プロジェクト計画の作り方
すぐに分かる!プロジェクト計画の作り方
 
Jenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテストJenkinsを使ったコンシューマゲームでのデプロイとテスト
Jenkinsを使ったコンシューマゲームでのデプロイとテスト
 
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
[G-Tech2014講演資料] プロジェクト・コスト・マネジメントの核心 - グローバルナレッジ
 
よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02よりぬきPmbok~ゲーム開発風味~ Web02
よりぬきPmbok~ゲーム開発風味~ Web02
 
プロジェクト見える化計画 Web
プロジェクト見える化計画 Webプロジェクト見える化計画 Web
プロジェクト見える化計画 Web
 
Scrum始めました
Scrum始めましたScrum始めました
Scrum始めました
 
統計的品質管理の功罪
統計的品質管理の功罪統計的品質管理の功罪
統計的品質管理の功罪
 
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAAJenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
JenkinsとGitで実装するGatewayCheckIn Pattern #AsianAA
 

Similar to Project cost management PMBOK 5th Edition

Cost management
Cost managementCost management
Cost managementshkadry
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptxInayatSheikh1
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.commkhilauria
 
Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part threeHossam Maghrabi
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationVandalRay
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1Skillogic Solutions
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPMI_IREP_TP
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaGlobalSkillup
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?MirzaNuman1
 
PMP GLOSSARY
PMP GLOSSARYPMP GLOSSARY
PMP GLOSSARYSoumya De
 
Executing the project - Final PPT.pptx
Executing the project - Final PPT.pptxExecuting the project - Final PPT.pptx
Executing the project - Final PPT.pptxAkshithKota
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostYudi Setiawan
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017Peter Cholakis
 

Similar to Project cost management PMBOK 5th Edition (20)

Cost management
Cost managementCost management
Cost management
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptx
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Brochure PlanningPackage.com
Brochure PlanningPackage.comBrochure PlanningPackage.com
Brochure PlanningPackage.com
 
Project cost management
Project cost management Project cost management
Project cost management
 
Term paper spm
Term paper spmTerm paper spm
Term paper spm
 
Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part three
 
Unit 2.pptx
Unit 2.pptxUnit 2.pptx
Unit 2.pptx
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
 
Uttara Pal.pdf
Uttara Pal.pdfUttara Pal.pdf
Uttara Pal.pdf
 
PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1PMP Training Project Cost Management Part 1
PMP Training Project Cost Management Part 1
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Presentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajanPresentation by sathish nataraj sundararajan
Presentation by sathish nataraj sundararajan
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES? WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
WHAT IS COST ESTIMATION IN PROJECT MANAGEMENT AND THEIR TYPES?
 
PMP GLOSSARY
PMP GLOSSARYPMP GLOSSARY
PMP GLOSSARY
 
Executing the project - Final PPT.pptx
Executing the project - Final PPT.pptxExecuting the project - Final PPT.pptx
Executing the project - Final PPT.pptx
 
Cost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total CostCost Estimators Cost Engineeringand Total Cost
Cost Estimators Cost Engineeringand Total Cost
 
Constructiion cost estimating 2017
Constructiion cost estimating 2017Constructiion cost estimating 2017
Constructiion cost estimating 2017
 
Quantim - Best Project Management Software
Quantim - Best Project Management SoftwareQuantim - Best Project Management Software
Quantim - Best Project Management Software
 

Recently uploaded

ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6Vanessa Camilleri
 
Employablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptxEmployablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptxryandux83rd
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvRicaMaeCastro1
 
Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...
Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...
Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...Osopher
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...Nguyen Thanh Tu Collection
 
6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroomSamsung Business USA
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWQuiz Club NITW
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxSayali Powar
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdfMr Bounab Samir
 
Comparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptxComparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptxAvaniJani1
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...DhatriParmar
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...Nguyen Thanh Tu Collection
 
Objectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptxObjectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptxMadhavi Dharankar
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...HetalPathak10
 

Recently uploaded (20)

ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6ICS 2208 Lecture Slide Notes for Topic 6
ICS 2208 Lecture Slide Notes for Topic 6
 
Employablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptxEmployablity presentation and Future Career Plan.pptx
Employablity presentation and Future Career Plan.pptx
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
 
Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...
Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...
Healthy Minds, Flourishing Lives: A Philosophical Approach to Mental Health a...
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptxINCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
BÀI TẬP BỔ TRỢ TIẾNG ANH 11 THEO ĐƠN VỊ BÀI HỌC - CẢ NĂM - CÓ FILE NGHE (GLOB...
 
Spearman's correlation,Formula,Advantages,
Spearman's correlation,Formula,Advantages,Spearman's correlation,Formula,Advantages,
Spearman's correlation,Formula,Advantages,
 
6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom6 ways Samsung’s Interactive Display powered by Android changes the classroom
6 ways Samsung’s Interactive Display powered by Android changes the classroom
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITW
 
Mattingly "AI & Prompt Design" - Introduction to Machine Learning"
Mattingly "AI & Prompt Design" - Introduction to Machine Learning"Mattingly "AI & Prompt Design" - Introduction to Machine Learning"
Mattingly "AI & Prompt Design" - Introduction to Machine Learning"
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
 
MS4 level being good citizen -imperative- (1) (1).pdf
MS4 level   being good citizen -imperative- (1) (1).pdfMS4 level   being good citizen -imperative- (1) (1).pdf
MS4 level being good citizen -imperative- (1) (1).pdf
 
Comparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptxComparative Literature in India by Amiya dev.pptx
Comparative Literature in India by Amiya dev.pptx
 
Mattingly "AI & Prompt Design: Large Language Models"
Mattingly "AI & Prompt Design: Large Language Models"Mattingly "AI & Prompt Design: Large Language Models"
Mattingly "AI & Prompt Design: Large Language Models"
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
 
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
BÀI TẬP BỔ TRỢ TIẾNG ANH 8 - I-LEARN SMART WORLD - CẢ NĂM - CÓ FILE NGHE (BẢN...
 
Objectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptxObjectives n learning outcoms - MD 20240404.pptx
Objectives n learning outcoms - MD 20240404.pptx
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
Satirical Depths - A Study of Gabriel Okara's Poem - 'You Laughed and Laughed...
 

Project cost management PMBOK 5th Edition

  • 1. Connoisseur Solutions Project Cost Management pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 2. Connoisseur Solutions Project Cost Management Project Cost Management includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 3. Connoisseur Solutions Cost Management Processes Process Process Group Plan Cost Management Planning Estimate Costs Planning Determine Budget Planning Control Costs Monitoring and Controlling pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 4. Connoisseur Solutions Estimate Costs Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project activities. The table below shows five different types of estimates that can be used based on the need. Estimate Type Range Order of Magnitude Estimates -25% to +75% Conceptual Estimate -30% to +50% Preliminary Estimate -20% to +30% Definitive Estimate -15% to +20% Control Estimate -10% to +15% pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 5. Connoisseur Solutions  Direct Cost- Any cost that is identified specifically with a particular final cost objective.  Indirect Cost- Any cost not directly identified with a single, final cost objective (more than one project)  Fixed Cost - Periodic charge that does not vary with business volume  Variable Cost - Cost that fluctuates based on the business volume  Opportunity Cost: When there is a decision to be made between two opportunities, the opportunity cost is the value / money forgone for the not doing the project. Types of Cost pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 6. Connoisseur Solutions • Lifecycle Costing: Takes into account cost of development of a project and also the cost of supporting during the lifecycle. • Sunk Cost - Cost already incurred which cannot be recovered regardless of future events Types of Cost pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 7. Connoisseur Solutions Plan Cost Management The process that establishes the policies, procedures , and documentation for planning , managing , expending , and controlling project costs. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 8. Connoisseur Solutions Plan Cost Management Inputs Tools and Techniques Outputs  Project Management Plan  Project Charter Enterprise Environmental Factors  Organizational Process Assets  Expert Judgment  Analytical Techniques  Meetings  Cost Management Plan pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 9. Connoisseur Solutions Plan Cost Management- Inputs Project Management Plan component that is important for this process are primarily the scope and cost baselines. Project Charter provides the summary budget from which the detailed project costs are developed . It also defines the project approval requirements that will influence the management of the project costs. Enterprise Environmental Factors include factors such as Organization structure/culture, Market conditions, currency exchange rates (for project sourced from more than one country) that influence the project cost. Organizational Process Assets include financial control procedures , historical information . Existing formal and informal cost estimating and budgeting related policies, procedures and guidelines. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 10. Connoisseur Solutions Plan Cost Management- Tools and Techniques Expert Judgment – Guided by historical information, provides valuable insight about the environment and information from prior similar projects. Judgment based upon expertise in an application area, knowledge area , discipline, industry can be useful in this process. Analytical Techniques – Some of the techniques payback period, return on investment, internal rate of return, discounted cash flow and net present value can be useful in this process Meetings - Project teams may hold meetings planning meetings to develop the cost management plan. These meetings may include, project sponsor, project manager, selected team members , selected stakeholders, anyone with responsibility for project costs. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 11. Connoisseur Solutions Plan Cost Management- Outputs Cost Management Plan – is a component of the project management plan and describes how the project costs will be planned, structured , and controlled. The cost management plan can establish the following.  Units of measure - Each unit of measure for each resource.  Level of precision – The degree to which activity cost estimates will be rounded up or down.  Level of accuracy - The acceptable range (e.g. +_ 100%) used in determining realistic activity cost estimates is specified , may include an amount for contingencies.  Control threshold – Variance threshold for monitoring cost performance may be specified to indicate an agreed – upon amount of variation to be allowed before some action need to be taken. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 12. Connoisseur Solutions Plan Cost Management- Outputs The cost management plan also contains.  Rules of performance measurement – Earned value management (EVM) rules of performance measurement are set. For example  Define the points in the WBS at which measurement of control accounts will be performed  Establish the earned value measurement techniques (e.g. weighted milestones, fixed formula, percent complete, etc) to be used and  Specify tracking methodologies and the earned value management computation equations for calculating projected estimate at completion (EAC) forecasts to provide a validity check on the bottom-up EAC pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 13. Connoisseur Solutions Estimate Cost pankaj sharma, 9810996356 Estimate cost is the process of developing an approximation of the monetary resources needed to complete project activities. The key benefit of this process is that it determines the amount of cost required to complete project work. Pankaj Sharma - Mobile No -919810996356
  • 14. Connoisseur Solutions Estimate Costs Inputs Tools and Techniques Outputs  Cost Management Plan  Human Resource Management Plan  Scope baseline  Project Schedule  Risk Register  Enterprise Environmental Factors  Organizational Process Assets  Expert Judgment  Analogous Estimating  Parametric estimating  Bottom-up estimating  Three-point estimates  Reserve Analysis  Cost of Quality  Project management estimating software  Vendor bid analysis  Group decision – making techniques  Activity Cost estimates  Basis of estimates  Project document updates pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 15. Connoisseur Solutions Estimate Costs - Inputs Cost management plan – The cost management plan defines how project costs will be managed and controlled . It includes the method used and the level of accuracy required to estimate activity cost. Human Resource Plan provides detail on Project staffing attributes, personnel rates, and related rewards/recognition, these are necessary components for developing the project cost estimates. Scope baseline include inputs from scope statement, Work Breakdown Structure and WBS dictionary. Project Schedule provides detail on the type and quantity of resources and the amount of time which those resources are applied to complete the work of the project, all these factors directly impact the cost Risk Register provides input related to costs associated with risk response pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 16. Connoisseur Solutions Estimate Costs - Inputs Enterprise Environmental Factors include availability of resources, published commercial information Organizational Process Assets – include cost estimating policies, historical information, cost estimating templates and lesson learned pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 17. Connoisseur Solutions Estimate Costs -Tools and Techniques Expert Judgment guided by historical information, provides valuable insight about the environment and information from prior similar projects. Expert judgment can also be used to determine whether to combine methods of estimating and how to reconcile differences between them. Analogous Estimating relies on historical information (Previous projects executed by the organization) to predict the cost of current project. This is a top-down approach is good for fast estimates to get a general idea of what the project may cost. The accuracy depends upon how similar the two projects actually are. Parametric estimating uses a mathematical model based on known parameters to predict the cost of a Project. A parameter can be cost per unit, cost per cubic yard etc. Two Parametric estimating techniques are Regression Analysis and Leaning curve. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 18. Connoisseur Solutions Estimate Costs -Tools and Techniques Bottom-up estimating produces a separate estimate for each scheduled activity. The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purposes. The cost and accuracy of bottom-up cost estimating is typically influenced by the size and complexity of the individual activity or work package. Three-point estimates concept originated with the program evaluation and review technique (PERT). PERT uses three estimates to define an approximate range for an activity’s cost: Triangular Distribution Estimated Cost = Optimistic + Most Likely + Pessimistic)/ 3 Beta Distribution ESTIMATED COST = (Optimistic + 4*(Most Likely) + Pessimistic) / 6 pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 19. Connoisseur Solutions Estimate Costs -Tools and Techniques Reserve Analysis adds reserve amount (Contingency) to the cost. This is done to take care of uncertainties in the project. Cost of Quality includes assumptions related to Cost of Quality Project management software is helpful in performing calculations, Organizing and storing large amount of information needed for preparing cost estimates and for reporting purpose Vendor bid analysis may include analysis of what the project should cost, based on the responsive bids from qualified vendors. Group Decision Making Techniques Team – based approaches , such as brainstorming, the Delphi or nominal group techniques, are used for engaging team members to improve estimate accuracy and commitment to the emerging estimates. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 20. Connoisseur Solutions Estimate Costs - Outputs Activity Cost estimates details how much it would cost to complete each schedule activity on the project Basis of estimates include supporting documentation of the cost estimates and it may include documentation of the basis of estimates , documentation of all assumptions made , documentation of any known constraint , indication of the range of possible estimates and indication of the confidence level of the final estimates Project document updates include project risk register and cost management plan pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 21. Connoisseur Solutions Revise Tools to Estimate Cost Exercise : Estimate Cost 1. You figure out a best case scenario and , a likely scenario and a worst case scenario. Then you use a formula to come up with an expected cost for the project. The tool used by you is ________ 2. John creates a document with all the historical information from similar project he had done in past and also takes input from a contractor who provides his input. The tool used by John is_________ pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 22. Connoisseur Solutions Revise Tools to Estimate Cost Answers to Exercise : Estimate Cost 1. You figure figures out a best case scenario and , a likely scenario and a worst case scenario. Then you use a formula to come up with an expected cost for the project. The tool used by you is Three-point estimate 2. John creates a document with all the historical information from similar project he had done in past and also takes input from a contractor who provides his input. The tool used by John is Expert Judgment pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 23. Connoisseur Solutions Determine Budget Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. This baseline includes all authorized budgets, but excludes management reserves. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 24. Connoisseur Solutions Determine Budget Inputs Tools and Techniques Outputs  Cost management plan Activity cost estimates  Basis of estimate  Scope baseline  Project Schedule  Resource Calendars  Risk register  Agreements  Organizational Process Assets  Cost Aggregation  Reserve Analysis  Expert Judgment  Historical relationship  Funding limit reconciliation  Cost baseline  Project funding requirements  Project document updates pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 25. Connoisseur Solutions Cost Management Plan - describes how the project costs will be managed and controlled Scope baseline refers to collection of approved project scope statement and its associated WBS and WBS dictionary. Activity cost estimates of a work package is a summation of the activity cost estimates of activities under the work package Basis of estimate includes supporting detail for cost estimates contained in the basis for estimates should specify any basic assumptions Project Schedule helps in mapping the cost back to time for planning purpose Determine Budget - Inputs pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 26. Connoisseur Solutions Resource Calendars along with Project schedule will help plan for when the costs will be incurred Agreements Applicable agreement information and costs relating to products, services or results that have been or will be purchased are included when determining the budget. Organizational Process Assets include cost budgeting policies procedures , guidelines and reporting method Determine Budget - Inputs pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 27. Connoisseur Solutions Determine Budget – Tools and Techniques Cost Aggregation involves aggregating the costs of individual activities to work packages that are further aggregated to higher levels of WBS and finally into the project cost Reserve Analysis include contingency reserve and management reserves for the project. Contingency reserves are allowances for response plan strategized for the identified risks. These are also known as “known unknowns” . Management reserves are allowance for unplanned changes to thee project scope and cost. The are also known as “unknown unknowns”. Reserves are not the part of the project cost baseline. Expert Judgment can be taken from experienced consultant in the project application area. This can be from an internal organizational resource or external sources pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 28. Connoisseur Solutions Determine Budget – Tools and Techniques Historical relationship result in parametric estimates or analogous estimates that involve parameter to develop mathematical models to predict total project costs. Funding limit reconciliation refers to reconciliation of planned spending with the funding limit pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 29. Connoisseur Solutions Determine Budget – Outputs Cost performance baseline is an authorized time-phased budget at completion (BAC) used to measure, monitor, and control overall cost performance on the project. It is developed as a summation of the approved budgets by time period and is typically displayed in the form of an S-curve, as is illustrated in Figure below (Reference PMBOK 4th edition). In the earned value management technique the cost performance baseline is referred to as the performance measurement baseline (PMB). Reference PMBOK 5th Edition pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 30. Connoisseur Solutions Determine Budget – Outputs Project funding requirements are derived from cost baselines. Total funding requirement is sum of cost baseline and management reserve. Project document updates include updates to risk register, cost estimates and project schedule pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 31. Connoisseur Solutions Project Budget Components pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 32. Connoisseur Solutions Revise Tools to Determine Budget Exercise 2: Determine Budget Monika reads a newspaper article that says there has been sharp increase in steel cost recently. She knows this was not in her contractor’s original plan and decides to put a few hundred dollars aside to deal with the price hike if it should happen. The tool used by Monika is • Parametric estimating • Reserve analysis • Cost aggregation • Fund Limit Reconciliation pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 33. Connoisseur Solutions Revise Tools to Determine Budget Answers to Exercise 2: Determine Budget Monika reads a newspaper article that says there has been sharp increase in steel cost recently. She knows this was not in her contractor’s original plan and decides to put a few hundred dollars aside to deal with the price hike if it should happen. The tool used by Monika is • Parametric estimating • Reserve analysis • Cost aggregation • Fund Limit Reconciliation pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 34. Connoisseur Solutions Control Costs Control Costs is the process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 35. Connoisseur Solutions Control Costs Inputs Tools and Techniques Outputs  Project management plan  Project Funding Requirements  Work Performance data  Organizational Process Assets □ Earned value management □ Forecasting □ To-complete performance index TCPI □ Performance reviews □ Project management software □ Reserve analysis  Work performance Information  Cost forecasts  Change Requests  Project management plan updates  Project document updates  Organizational Process assets updates pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 36. Connoisseur Solutions Project Management Plan contains Cost management plan and Cost performance Baseline, these are helpful in controlling the cost. Project Funding Requirements As explained earlier include projected expenditures plus anticipated liabilities Work Performance Data provides information on the status and cost of project activities and ensures that the project goals and objectives are met as per the project management plan Organizational Process Assets that can influence this process include cost budgeting policies, procedures, guidelines , cost budgeting tools and reporting methods Control Costs - Inputs pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 37. Connoisseur Solutions Control Costs – Tools and Techniques Earned value management is used to measure the performance of the project, It integrates project scope, cost, and schedule measures to help the project management team assess and measure project performance and progress. The EVM technique involves evaluating the planned value , Earned Value and the Actual cost for each schedule activity , work package or control account. 1. Planned Value (PV) is the authorized budget assigned to the scheduled work to be accomplished for a schedule activity or work breakdown structure component. It is also known as Budgeted Cost of Work Scheduled (BCWS) 2. Earned Value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or a WBS component. It is also known as Budgeted cost of Work Performed (BCWP) 3. Actual Cost (AC) is the total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 38. Connoisseur Solutions Control Costs – Tools and Techniques Variance Analysis helps in analyzing the performance of the project vis-à-vis cost and schedule baselines Schedule Variance (SV) is a measure of schedule performance on a project. It is equal to the earned value (EV) minus the planned value (PV). SV= EV-PV. Cost variance (CV) is a measure of cost performance on a project. It is equal to the earned value (EV) minus the actual costs (AC). CV = EV-AC Schedule performance Index (SPI) in addition to project status is used to predict the completion date. SPI = EV/PV Cost Performance Index (CPI) measures the cost efficiency for the work completed, it is the ration of EV to AC. CPI = EV/AC. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 39. Connoisseur Solutions Control Costs – Tools and Techniques Forecasting Techniques are used to calculate Estimate at completion (EAC) and Estimate to complete (ETC). EAC = AC + ETC EAC forecast for ETC work performed at the budgeted rate EAC = AC + BAC – EV EAC forecast for ETC work performed at the present CPI EAC = BAC / cumulative CPI EAC forecast for ETC work considering both SPI and CPI factors. AC + [(BAC – EV) / (cumulative CPI x cumulative SPI)]. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 40. Connoisseur Solutions Control Costs – Tools and Techniques To-complete performance index (TCPI) is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC. TCPI based on the BAC: Work Remaining (BAC – EV) / Fund Remaining (BAC – AC). TCPI based on EAC : (BAC-EV)/(EAC-AC) Performance reviews involves following three types of analysis 1. Variance Analysis compares actual project performance to planned or expected performance. Cost and schedule variances are the most frequently analyzed. 2. Trend Analysis examines project performance over time to determine if performance is improving or deteriorating. 3. Earned value management compares the baseline plan to actual schedule and cost performance. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 41. Connoisseur Solutions Control Costs – Tools and Techniques Project management software is often used to monitor the three EVM dimensions (PV, EV, and AC), to display graphical trends, and to forecast a range of possible final project results. Reserve Analysis – During cost control, reserve analysis is used to monitor the status of contingency and management reserves for the project to determine if these reserves are still needed or if additional reserves need to be requested. pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 42. Connoisseur Solutions Control Costs – Outputs Work Performance Information includes the calculated CV, SV, CPI, and SPI values for WBS components, in particular the work packages. Cost Forecasts includes a calculated EAC value or a bottom-up EAC value. Organizational Process Assets Updates include Causes of variances, Corrective action chosen and the reasons, and Other types of lessons learned from project cost control. Change Requests include change request to the cost performance baseline or other components of the project management plan. Change requests can include preventive or corrective actions and are processed for review and disposition through the Perform Integrated Change Control process pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 43. Connoisseur Solutions Control Costs – Outputs Project Management Plan Updates Elements of the project management plan that may be updated include Cost performance baseline, Cost management plan. Project Documents Updates include updates to cost estimates, basis of Estimates Organizational Process Assets Updates Organizational Process Assets that may be updated include, but are not limited to :  Cause of variances  Corrective action choosen and the reasons  Financial databases  Other types of lesson learned from project cost control pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 44. Connoisseur Solutions Practice Earned Value Formulae Exercise 1 : EVM Your current project is an $800,000 software development effort, with two teams of programmers that will work for six months, at a total of 10,000 hours. According to the project schedule your team should be done with 38% of the work. You find that the project is currently 40% complete. You have spent 50% of the budget so far. Calculate the following 1. BAC 2. EV, PV 3. SV, CV 4. SPI, CPI pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 45. Connoisseur Solutions Practice Earned Value Formulae Answer to Exercise - 1 : EVM 1. BAC = $ 800,000, AC = $ 400,000 2. PV = $ 80,000 * 38 / 100 = $ 304,000 EV = $ 80,000 * 40 / 100 = $ 320,000 3. SV = EV – PV = $ 16,000 CV = EV – AC = - $ 80,000 4. SPI = EV / PV = 1.05 CPI = EV / AC = 0.8 pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 46. Connoisseur Solutions Practice Earned Value Formulae Exercise – 2 : EVM You’re managing a highway construction project. Your total budget is $650,000, and there are a total of 7,500 hours of work scheduled on the project. You check with your accounting department, and they tell you that you’ve spent a total of $400,000. According to the schedule, your crew should have worked 4,500 hours, but your foreman says that the crew was allowed to work some overtime, and they’ve actually put in 5,100 hours of work. Based on this Calculate the following Earned Value numbers: PV = EV = CV = BAC = AC = SV = SPI = , CPI = pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 47. Connoisseur Solutions Practice Earned Value Formulae Answer to Exercise - 2 : EVM BAC = $ 650,000 AC = $ 400,000 PV = 650,000 x 60% = $390,000 EV = 650,000 x 68% = $ 442,000 CV =442,000 – 400,000 = $42,000 SV = $ 52,000 SPI = 1.13 , CPI = 1.11 pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 48. Connoisseur Solutions Practice Earned Value Formulae Exercise - 3 : EVM It’s nine months into your project. The total budget for your project is $4,200,000. You’ve spent $1,650,000 so far, and you’ve got a CPI of .875. Use the Earned Value Management formulas from forecasting to figure out where things stand. Find the following EAC = ETC = VAC = pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 49. Connoisseur Solutions Practice Earned Value Formulae Answer to Exercise - 3 : EVM EAC = $ 4,200,000 / 0.875 = $ 4,800,000 ETC = $ 4,800,000 – $ 1,650,000 = $ 3, 150,000 VAC = $ 4,200,000 – $ 4,800,000 = $ 600,000 pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356
  • 50. Connoisseur Solutions QUIZ ! pankaj sharma, 9810996356 Pankaj Sharma - Mobile No -919810996356