35. E.g.; Today is 20 and assign the priority 12 28 D 2 22 C 2 24 B 8 26 A RWDs Due date Job
36. Critical Ratio 8/12=0.67 12 28-20=8 D 2/2=1 2 22-20=2 C 4/2=2 2 24-20=4 B 6/8=0.75 8 26-20=6 A CR=DD-CD/RWD RWDs Time remaining DD-CD Job
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47. Timings and precedence 5.7 minutes Total H 0.7 I F,G 0.8 H D,E 1.5 G D 0.1 F B,C 0.3 E A 0.5 D - 0.3 C - 0.6 B - 0.9 A Immediate predecessor Required time in minutes Tasks
78. Concepts of material management Raw materials Subassemblies Manufactured parts Packing materials 1.Material specifications 2.Value analysis 3. Supply market research 4. Negotiation 5. Buying 6.Quality assurance 7.Transportation Finished goods inventory Transportation Field inventory Transportation Customer Storage materials handling Production scheduling and control. Goods in process inventory Inventory decisions Procurement activities Physical distribution Materials Management